A method, system, device and medium for evaluating the bonding performance between thin-layer overlay layers
Through high-temperature oblique shear test and dynamic curve analysis of interlayer shear strength, the inaccuracy problem of interlayer bonding performance evaluation of thin layer asphalt mixture is solved, and a more accurate evaluation method is provided, suitable for thin layers of different thickness combinations are provided. plan to guide engineering practice.
Patent Information
- Application Number
- CN202411025944.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-07-30
AI Technical Summary
The existing method of evaluation of bonding performance between thin layer asphalt pavement has problems such as uneven bonding, difficult to control the interface of composite specimens, magnitude of normal force depends on experience setting, and insufficient evaluation of thin layer schemes of different thickness combinations , especially in the construction of thin layer asphalt mixtures, there is a lack of effective simulation reduction methods.
Using the high-temperature inclined shear test method, the double-layer asphalt mixture composite rut plate test piece is prepared by insulating heat and spreading adhesive layer materials on the rut plate, recording vertical pressure and displacement, and calculating the dynamic curve of shear strength between layers, using the first appearance. The peak shear strength of the thin layer is evaluated for the bonding performance between the thin layer.
More accurately simulates the actual construction status of thin layer asphalt mixture, considers the stress characteristics of the road surface under vehicle load, fills the shortcomings of the existing technology evaluation methods, and provides a more comprehensive and convenient thin layer asphalt mixture with existing ones. Evaluation of the performance of bonding between pavement surfaces.
Smart Images

Figure CN118566119B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of road engineering technology, and in particular to a method, system, equipment and medium for evaluating the high-temperature interlayer bonding performance of a thin-layer overlay. Background Art
[0002] The interlayer bonding condition of asphalt pavement has a significant impact on the performance of the pavement, especially in thin-layer paving and other construction occasions. Good interlayer bonding can improve the integrity of the pavement structure, thereby effectively resisting diseases such as granulation and peeling caused by traffic loads, which is of great significance to improving the service life of the pavement. When designing the combination of asphalt pavement structures or optimizing the construction plan, it is necessary to accurately evaluate the interlayer bonding performance of the thin-layer asphalt mixture and the existing pavement to ensure that the designed and adopted interlayer treatment method can effectively play a bonding role and ensure the service quality of the pavement.
[0003] The commonly used test methods for evaluating the interlayer bonding effect of asphalt pavement mainly include pull-out test, direct shear test and oblique shear test. Among them, the pull-out test requires the specimen to be bonded to the fixture during the test. For thin asphalt mixtures, it is easy for the bonding surface between the specimen and the fixture to be pulled apart due to uneven bonding, and the damage interface is difficult to control. In addition, the interlayer stress condition of the bonding interface of the composite specimen in this test is quite different from the actual service condition. The direct shear test can apply normal force and tangential force to the bonding interface respectively, which is closer to the actual pavement stress state than the pull-out test. However, the magnitude of the normal force applied to the interface is usually determined by the experimenter based on experience and is generally set to zero. Compared with the actual situation, the evaluation of the interlayer bonding performance is not accurate and objective enough. The oblique shear test decomposes the controllable vertical force at a certain angle, which can achieve the simultaneous application of normal force and tangential force. Since the adhesion coefficient between the vehicle load and the road surface determines that the normal force and tangential force generated on the road surface change synchronously in a certain proportion, the oblique shear test is used to evaluate the interlayer bonding performance, which is closest to the actual road stress conditions.
[0004] The existing interlayer bonding performance evaluation method based on the oblique shear test has certain limitations on the thickness of the test specimens. Conventional oblique shear test molds are not suitable for thin-layer asphalt mixtures and need to be customized according to actual conditions, which increases the test cost. In addition, with the continuous advancement of technology, new treatment methods to improve interlayer bonding properties are constantly emerging, such as the use of pavement instant heating technology to preheat existing pavements to replace or reduce the spreading of tack oil, thereby improving the interlayer bonding effect between thin-layer asphalt mixture overlays and existing pavements. At present, there is a lack of relevant indoor operation methods to evaluate the performance of various interlayer treatment methods and thin-layer solutions with different thickness combinations, which will also lead to incomplete evaluation of the interlayer bonding characteristics of different materials, limiting the potential for technology expansion.
[0005] Therefore, when evaluating the interlayer bonding characteristics between a thin layer of overlay and an existing pavement, it is necessary to simultaneously consider the actual stress state of the material and the simulated restoration of the interlayer treatment method, so as to more comprehensively, conveniently and accurately evaluate the bonding performance between the thin layer of asphalt mixture overlay and the existing pavement, thereby better guiding engineering practice. Summary of the invention
[0006] Based on this, it is necessary to provide a method, system, equipment and medium for evaluating the bonding performance between thin-layer covering layers in response to the above-mentioned technical problems.
[0007] The present invention adopts the following technical solutions:
[0008] The present invention provides a method for evaluating the bonding performance between thin-layer overlay layers, comprising:
[0009] The rutting plate representing the existing road surface is insulated, and the tack layer material is spread on the rutting plate at the same time during the insulation process; the mixed thin layer of asphalt mixture is spread on the insulated rutting plate to prepare a double-layer asphalt mixture composite rutting plate specimen, and the composite pavement structure after the thin layer overlay construction is simulated based on the double-layer asphalt mixture composite rutting plate specimen;
[0010] The composite rutting plate specimen is cut to obtain a test sample, and a high-temperature oblique shear test is performed on the test sample. During the test, the vertical pressure and the vertical displacement of the loading pressure head are simultaneously recorded;
[0011] According to the vertical pressure, the vertical displacement of the loading head, the angle between the inclined shear plane and the horizontal plane, and the size of the test sample, the interlaminar shear strength of the composite rutting plate specimen is obtained;
[0012] The dynamic curve of the interlayer shear strength of the composite rutting plate specimens changing with the interlayer vertical displacement is obtained by obtaining the interlayer shear strength of the composite rutting plate specimens;
[0013] The shear strength peak value that first appears in the dynamic curve is taken as an index, and the bonding performance between thin-layer overlays is evaluated based on the index.
[0014] Preferably, the rutting plate representing the existing road surface is insulated for a period of not less than 3 hours.
[0015] Preferably, the preparation of a double-layer asphalt mixture composite rutting plate specimen comprises:
[0016] After the thin layer of asphalt mixture is mixed indoors, take out the insulated rutting plate from the temperature control equipment and then immediately spread and shape it.
[0017] Preferably, the performing of a high temperature oblique shear test on the test specimen specifically comprises: performing the high temperature oblique shear test at least three times.
[0018] Preferably, the vertical pressure and the vertical displacement of the loading head are recorded synchronously during the test. Specifically, during the oblique shear test, when the vertical pressure is greater than 0.1 kN, start to synchronously record the vertical pressure and the vertical displacement of the loading head; when the vertical pressure reaches a peak and drops to 80% of the peak, stop recording data.
[0019] Preferably, during the test, the vertical pressure and the vertical displacement of the loading head are recorded synchronously, and the frequency of data recording is 100 Hz, that is, the time interval between adjacent data points is 0.01 s.
[0020] The embodiment of the present invention further provides a thin layer overlay interlayer bonding performance evaluation system, comprising:
[0021] The specimen preparation module is used to prepare a double-layer asphalt mixture composite rutting plate specimen, and simulate the composite pavement structure after the thin layer overlay construction based on the double-layer asphalt mixture composite rutting plate specimen;
[0022] The data acquisition module is used to perform high-temperature oblique shear tests on the test specimens, and synchronously record the vertical pressure, vertical displacement of the loading head, and time during the test;
[0023] A data processing module is used to obtain the interlaminar shear strength of the composite rutting plate specimen according to the vertical pressure, the vertical displacement of the loading head, the angle between the inclined shear plane and the horizontal plane, and the size of the test sample;
[0024] A curve calculation module is used to obtain a dynamic curve of the interlayer shear strength of the composite rutting plate specimen changing with displacement by using the obtained interlayer shear strength of the composite rutting plate specimen;
[0025] The evaluation module is used to use the peak value of the dynamic curve that appears for the first time as an indicator, and evaluate the bonding performance between thin-layer covering layers based on the indicator.
[0026] An embodiment of the present invention further provides a computer-readable storage medium, wherein the storage medium stores a computer program, and when the computer program is executed by a processor, the above-mentioned method for evaluating the bonding performance between thin-layer covering layers is implemented.
[0027] An embodiment of the present invention also provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the above-mentioned method for evaluating the bonding performance between thin-layer covering layers when executing the program.
[0028] The present invention provides a method for evaluating the interlayer bonding performance of a thin layer of overlay, which has the following beneficial effects compared with the prior art:
[0029] The present invention provides a method for evaluating the interlayer bonding performance of a thin layer of overlay, which simulates and restores the actual interlayer construction conditions of a thin layer of asphalt mixture, and simultaneously considers the actual stress characteristics of the pavement under the action of vehicle loads, thereby filling the gap in the method for evaluating the interlayer bonding performance of a thin layer of overlay and an existing pavement by preheating the pavement, spreading tack oil, etc., and can more accurately and extensively evaluate the bonding effect between a thin layer of overlay and an existing pavement. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0031] Figure 1 A schematic flow chart of a method for evaluating the bonding performance between asphalt and pavement provided by the present invention;
[0032] Figure 2 A schematic diagram of loading for a high temperature oblique shear test provided by the present invention;
[0033] Figure 3 This is a diagram of a double-layer asphalt mixture composite rutting plate specimen used in a high-temperature oblique shear test in an embodiment of the present invention;
[0034] Figure 4 It is a schematic diagram of the change of vertical pressure and vertical displacement of the pressure head with loading time in the oblique shear test of an embodiment of the present invention;
[0035] Figure 5 This is a schematic diagram of the change of interlayer shear strength with interlayer displacement in the oblique shear test of an embodiment of the present invention;
[0036] Figure 6 It is a comparison diagram of interlaminar shear strength curves of three types of specimens in the embodiments of the present invention.
[0037] Figure 2 middle,
[0038] 1-pressure rod, 2-upper module of oblique shear fixture, 3-first cushion block, 4-thin layer of asphalt mixture, 5-lower layer of mixture, 6-second cushion block, 7-lower module of oblique shear fixture, 8-support. DETAILED DESCRIPTION
[0039] In order to make the purpose, technical solutions and advantages of this specification more clear, the technical solutions of this application will be clearly and completely described below in combination with the specific embodiments of this specification and the corresponding drawings. Obviously, the described embodiments are only part of the embodiments of this application, not all of them. Based on the embodiments in the specification, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0040] The technical solutions provided by various embodiments of the present application are described in detail below in conjunction with the accompanying drawings.
[0041] Figure 1 The following is a flow chart of a method for evaluating the bonding performance between thin-layer overlay layers in this specification, which specifically includes the following steps:
[0042] S101, insulating a wheel rutting plate representing an existing road surface to a set construction preheating temperature;
[0043] The rutting plate representing the existing road surface is insulated in the temperature control equipment to simulate the interlayer treatment method of preheating the road surface before the thin layer cover is implemented in actual construction. The insulation time is not less than 3h.
[0044] S102, while keeping warm, spreading a tack layer material on the rutting plate, and then promptly forming a thin layer of asphalt mixture to prepare a double-layer asphalt mixture composite rutting plate specimen to simulate the composite pavement structure after the thin layer overlay construction is restored;
[0045] When preparing double-layer composite rutting plate specimens, after the thin layer of asphalt mixture is mixed indoors, the rutting plate that has been insulated in the temperature control equipment is taken out and then immediately paved and formed. For specimens using spreading tack coat oil, after the spreading operation is completed, the rutting plate can be put back into the temperature control equipment and kept for a period of time. After its temperature stabilizes to the target temperature, the upper thin layer of the overlay can be formed according to the above method.
[0046] S103, cutting the composite rutting plate to obtain a test sample, performing a high temperature oblique shear test on the test sample, and synchronously recording the vertical pressure and the vertical displacement of the loading pressure head during the test;
[0047] The molded composite rutting plate specimens were placed in a conventional indoor environment for 48 hours, then removed from the mold. After being placed for another 24 hours, they were cut into 10cm×10cm×5cm rectangular test specimens for high-temperature oblique shear tests. When cutting, the asphalt mixture within a width of 5cm around the composite rutting plate was removed and discarded, and the remaining plate was cut into 4 equal parts.
[0048] Before conducting the oblique shear test, the oblique shear test fixture, test sample and pads need to be installed and placed; the oblique shear test fixture consists of two parts, the upper and lower parts, each of which can be sheared to a depth of 5cm. During the test, pads of a certain thickness need to be placed on the upper and lower parts to ensure that the shear surface is aligned with the bonding interface. The vertical pressure is applied to the test sample through the fixture. The loading diagram is shown in the figure. Figure 2 shown.
[0049] During the oblique shear test, when the vertical pressure is greater than 0.1 kN, F and x are recorded synchronously; when the vertical pressure reaches a peak and drops to 80% of the peak, data recording is stopped; the frequency of data recording is 100 Hz, that is, the time interval between adjacent data points is 0.01 s.
[0050] In addition, the oblique shear test is carried out at least three times at high temperature.
[0051] S104. Calculate the interlayer shear strength according to the vertical pressure, the vertical displacement of the loading head, the angle between the inclined shear plane and the horizontal plane, and the size of the test sample;
[0052] The interlaminar shear strength expression is:
[0053]
[0054] Among them, τ is the interlayer shear strength; F is the vertical pressure; x is the vertical displacement of the loading head; α is the angle between the inclined shear plane and the horizontal plane; L is the side length of the cube specimen.
[0055] S105, obtaining a dynamic curve of the interlayer shear strength of the composite rutting plate specimen as a function of vertical displacement according to the interlayer shear strength of the composite rutting plate specimen;
[0056] S106. The peak value that appears for the first time on the dynamic curve is used as an index, and the bonding performance between thin-layer covering layers is evaluated based on the index.
[0057] Based on formula (1), the variation curve of the shear strength τ of the bonding interface during the oblique shear test can be calculated, and the first peak τ of the shear strength variation curve is taken as max It is used as an indicator to evaluate the interlayer bonding performance of the material; the larger the peak value, the better the interlayer bonding performance.
[0058] Example:
[0059] In this embodiment, the high-temperature interlayer bonding performance of thin-layer overlays under three different interlayer treatment methods was compared and evaluated. One type is the existing surface layer preheating temperature of 80°C, defined as specimen A; one type is the existing surface layer preheating temperature of 100°C, defined as specimen B; the third type is the existing surface layer preheating temperature of 120°C, defined as specimen C; except for the different interlayer preheating temperatures, the other relevant conditions in the molding process of the three types of asphalt mixture composite specimens A, B, and C remain the same.
[0060] When specimens A, B, and C are formed, the preheating temperature of the lower rutting plate is increased successively. Under the same material and rolling conditions, the higher the temperature of the lower layer, the slower the temperature of the thin layer mixture drops during the rolling process, and the stronger the thermal bond formed between the two layers of material. Therefore, the peak value of the interlayer shear strength should gradually increase. In this embodiment, the method proposed in the present invention is used to compare the differences in the interlayer bonding properties formed by the three types of treatment methods, and further verify the reliability of the method proposed in the present invention.
[0061] First, three groups of rutting plate specimens with a thickness of 4 cm were prepared and placed in a standard rutting plate mold (thickness of 5 cm). They were then placed in environmental boxes with temperatures of 80°C, 100°C, and 120°C, respectively, and kept warm for more than 3 hours. This step simulated the preheating process of restoring the existing pavement.
[0062] The interlayer treatment method studied in this example does not involve spreading of tack coat oil. Therefore, after the mixing of the thin layer of asphalt mixture is completed indoors, the preheated lower rutting plate is taken out from the environmental chamber and a thin layer of overlay is immediately formed on it. After rolling and forming, the rutting plate mold is removed after being placed in a normal indoor environment for 48 hours, and then placed in a normal indoor environment for another 24 hours.
[0063] The asphalt mixture within the 5 cm width of the edge of the composite rutting plate was cut off and discarded, and the remaining plate was divided into 4 pieces, and 4 10 cm × 10 cm × 5 cm rectangular specimens were obtained. One rutting plate can support four parallel tests. The specimens formed under different working conditions were prepared according to the above method for the oblique shear test. Figure 3 shown.
[0064] The three types of mixed material specimens A, B, and C were subjected to high-temperature oblique shear tests at a test temperature of 60°C and a vertical load rate of 2mm / min. The specimens were kept in a 60°C constant temperature environment box for more than 5 hours in advance. After the fixtures, specimens, and pads were installed and placed, the test could begin. Four parallel tests were conducted on each type of specimen. During the test, the vertical pressure F (kN) and the vertical displacement x (mm) of the loading pressure head were recorded synchronously over time t (s); the vertical pressure F detection accuracy was 1×10 -5 kN; the detection accuracy of the vertical displacement x of the loading head is 1×10 -4 mm.
[0065] During the test, when the vertical pressure is greater than 0.1kN, F and x are recorded synchronously; when the vertical pressure reaches a peak and drops to 80% of the peak, data recording stops; the frequency of data recording is 100Hz, that is, the time interval between adjacent data points is 0.01s. During an oblique shear test, the typical curves of vertical pressure F (kN) and main shaft displacement x (mm) with loading time t are as follows Figure 4 shown.
[0066] Substituting the F and x data collected in the oblique shear test into formula (1), the dynamic variation curve of the interlaminar shear strength of the specimen with displacement can be calculated. The typical interlaminar shear strength variation curve is as follows: Figure 5 As shown. Record the peak value of the interlaminar shear strength curve as the index τ max (like Figure 5 (as shown) for the interlayer bonding properties of two asphalt mixture interlayer treatment methods.
[0067] Finally, according to the test results, the τ of the three types of mixture specimens A, B, and C is max The values are determined as shown in Table 1.
[0068] Table 1 τ of three types of mixture specimens A, B and C max value
[0069]
[0070] As shown in Table 1, the τ corresponding to specimen A max The average value is 0.459MPa, and the τ corresponding to specimen B is max The average value is 0.611MPa, and the τ corresponding to specimen C is max The average value is 0.755MPa. max The larger the value, the better the interlayer bonding performance. The bonding performance evaluation results of the three types of interlayer treatment methods are A<B<C. Figure 6 The above evaluation results are consistent with the working principles of the three types of interlayer disposal methods, further proving the rationality and reliability of the method proposed in the present invention.
[0071] The method proposed in the patent of this invention takes into account the actual stress characteristics of the road surface under the action of vehicle loads, can simulate and restore the actual interlayer construction conditions of thin-layer asphalt mixtures, and at the same time fills the deficiencies in the evaluation method of the interlayer bonding performance between thin-layer asphalt mixtures and existing pavements by preheating the pavement, spreading tack oil, etc., and can more accurately and extensively evaluate the bonding effect between thin-layer asphalt mixtures and existing pavements.
[0072] The embodiment of the present invention further provides a thin layer overlay interlayer bonding performance evaluation system, comprising:
[0073] The specimen preparation module is used to prepare a double-layer asphalt mixture composite rutting plate specimen, and simulate the composite pavement structure after thin-layer overlay construction based on the double-layer asphalt mixture composite rutting plate specimen.
[0074] The data acquisition module is used to perform high-temperature oblique shear tests on the test specimens, and synchronously record the vertical pressure, vertical displacement of the loading head, and time during the test.
[0075] The data processing module is used to obtain the interlayer shear strength of the composite rutting plate specimen according to the vertical pressure, the vertical displacement of the loading head, the angle between the inclined shear plane and the horizontal plane, and the size of the test sample.
[0076] The curve calculation module is used to obtain the dynamic curve of the interlayer shear strength of the composite rutting plate specimen changing with displacement through the obtained interlayer shear strength of the composite rutting plate specimen.
[0077] The evaluation module is used to use the peak value of the dynamic curve that appears for the first time as an indicator, and evaluate the bonding performance between thin-layer covering layers based on the indicator.
[0078] An embodiment of the present invention further provides a computer-readable storage medium, wherein the storage medium stores a computer program, and when the computer program is executed by a processor, the above-mentioned method for evaluating the bonding performance between thin-layer covering layers is implemented.
[0079] An embodiment of the present invention also provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, the above-mentioned method for evaluating the bonding performance between thin-layer covering layers is implemented.
[0080] The technical features of the above embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
Claims
1. A method for evaluating the bonding performance between thin-layer overlay layers, characterized in that: include: The rutting plate representing the existing road surface is insulated, and the tack layer material is spread on the rutting plate at the same time during the insulation process; the mixed thin layer of asphalt mixture is spread on the insulated rutting plate to prepare a double-layer asphalt mixture composite rutting plate specimen, and the composite pavement structure after the thin layer overlay construction is simulated based on the double-layer asphalt mixture composite rutting plate specimen; The composite rutting plate specimen is cut to obtain a test sample, and a high-temperature oblique shear test is performed on the test sample. During the test, the vertical pressure and the vertical displacement of the loading pressure head are simultaneously recorded; According to the vertical pressure, the vertical displacement of the loading head, the angle between the inclined shear plane and the horizontal plane, and the size of the test sample, the interlaminar shear strength of the composite rutting plate specimen is obtained; The dynamic curve of the interlayer shear strength of the composite rutting plate specimens changing with the interlayer vertical displacement is obtained by obtaining the interlayer shear strength of the composite rutting plate specimens; The shear strength peak value that first appears in the dynamic curve is taken as an index, and the bonding performance between thin-layer overlays is evaluated based on the index.
2. A method for evaluating the bonding performance between thin-layer overlay layers as claimed in claim 1, characterized in that: The rutting plate representing the existing road surface is insulated for a period of not less than 3 hours.
3. A method for evaluating the bonding performance between thin-layer overlay layers as claimed in claim 1, characterized in that: The method for preparing a double-layer asphalt mixture composite rutting plate specimen comprises: After the thin layer of asphalt mixture is mixed indoors, take out the insulated rutting plate from the temperature control equipment and then immediately spread and form it.
4. A method for evaluating the bonding performance between thin-layer overlay layers as claimed in claim 1, characterized in that: The high temperature oblique shear test on the test sample specifically includes: performing the high temperature oblique shear test at least three times.
5. A method for evaluating the bonding performance between thin-layer overlay layers as claimed in claim 1, characterized in that: During the test, the vertical pressure and the vertical displacement of the loading head are recorded synchronously. Specifically, during the oblique shear test, when the vertical pressure is greater than 0.1 kN, the vertical pressure and the vertical displacement of the loading head are recorded synchronously; when the vertical pressure reaches a peak and drops to 80% of the peak, the data recording is stopped.
6. A method for evaluating the bonding performance between thin-layer overlay layers as claimed in claim 1, characterized in that: During the test, the vertical pressure and the vertical displacement of the loading head were recorded synchronously, and the frequency of data recording was 100 Hz, that is, the time interval between adjacent data points was 0.01 s.
7. A thin layer overlay interlayer bonding performance evaluation system, characterized in that: include: The specimen preparation module is used to prepare a double-layer asphalt mixture composite rutting plate specimen, and simulate the composite pavement structure after the thin layer overlay construction based on the double-layer asphalt mixture composite rutting plate specimen; The data acquisition module is used to perform high-temperature oblique shear tests on the test specimens, and synchronously record the vertical pressure, vertical displacement of the loading head, and time during the test; A data processing module is used to obtain the interlaminar shear strength of the composite rutting plate specimen according to the vertical pressure, the vertical displacement of the loading head, the angle between the inclined shear plane and the horizontal plane, and the size of the test sample; A curve calculation module is used to obtain a dynamic curve of the interlayer shear strength of the composite rutting plate specimen changing with displacement by using the obtained interlayer shear strength of the composite rutting plate specimen; The evaluation module is used to use the peak value of the dynamic curve that appears for the first time as an indicator, and evaluate the bonding performance between thin-layer covering layers based on the indicator.
8. A computer-readable storage medium, characterized in that: The storage medium stores a computer program, and when the computer program is executed by a processor, the method for evaluating the bonding performance between thin-layer covering layers described in any one of claims 1 to 6 is implemented.
9. A computer device, characterized in that: The method comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, a method for evaluating the bonding performance between thin-layer covering layers as described in any one of claims 1 to 6 is implemented.
Citation Information
Patent Citations
Method for testing shearing strength of road structure
CN102095682A
Testing apparatus and testing method for testing interlayer connection strength of pavement layers
CN103604743A
Asphalt pavement compression shearing device and interlaminar shear modulus test method
CN114509355A
Method and system for evaluating interlayer bonding durability of pavement in complex load environment
CN115931603A
Method and device for testing interlayer shearing performance of waterproof bonding layer of bridge floor in consideration of construction and actual road conditions
CN117232994A