Material transportation control method, device, system and storage medium

By using the process matrix table and the system to share equipment information in the material transportation control system, the equipment status is judged in real time, and the problem of strong subjectivity of manual judgment is solved, and efficient, stable and reliable control of material transportation is achieved.

CN118567288BActive Publication Date: 2024-11-29CERI DIGITAL TECHNOLOGY (BEIJING) CO LTD +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411046588.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-11-29
Estimated Expiration
2044-08-01

AI Technical Summary

Technical Problem

In the existing material transportation control technology, equipment status judgment relies on manual labor, is highly subjective, and it is difficult to meet the needs of centralized intelligent production, resulting in poor transportation control accuracy.

Method used

By using the process matrix table and the system to share the identification information of the device in the programmable logic controller, the device occupation status is judged in real time, and the target transportation process is determined to avoid repeated selection and waste of equipment.

Benefits of technology

Improve the sustainability, stability and reliability of material transportation, and avoid mixing accidents and energy waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118567288B_ABST
    Figure CN118567288B_ABST
Patent Text Reader

Abstract

The present application discloses a method, device, system and storage medium for material transportation control, and relates to the field of computer technology. The method includes: in response to the selection operation of the first transportation process, based on the first process matrix table and the first transportation process, determining the association between the first transportation process and the selected second transportation process; in response to the association between the first transportation process and the selected second transportation process meeting the preset association condition, obtaining the identification information of the system shared device of the first transportation process; based on the identification information of the system shared device, obtaining the occupancy status information of the system shared device in the second system; in response to the occupancy status information being unoccupied, determining the first transportation process and the second transportation process as target transportation processes; based on the target transportation process, controlling the transportation equipment in the target transportation process to transport materials. The solution of the present application solves the problem of poor accuracy in material transportation control.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of computer technology, specifically to technical fields such as material transportation control technology, and particularly to a material transportation control method, device, system and storage medium. Background Art

[0002] The raw material yard is mainly composed of a large process conveying group of belt conveyors, which are combined with reversing equipment such as reversible belt conveyors, mobile telescopic head belt conveyors, shuttle belt conveyors, three-way distributors, and fixed unloading vehicles. There are many intersections of equipment in the material yard. When selecting a process, it is necessary to determine whether the equipment is used. If it is used, it cannot be selected. When a device is used in one process, the other process cannot select this device, and an alarm prompt will be issued when the process is selected.

[0003] At present, the commonly used small and medium-sized material yards are all manually judging the use status of the equipment, which is highly subjective. However, with the development of material transportation automation control technology, equipment control is also gradually developing towards centralized control and intelligent production, which has higher requirements for control procedures. Manual subjective judgment of equipment status is no longer suitable for centralized control and intelligent production. Summary of the invention

[0004] The present application provides a method, device, system and storage medium for material transportation control, which can solve the problem of poor accuracy of material transportation control. The technical solution is as follows:

[0005] In a first aspect, a method for controlling material transportation is provided, the method being applied to a programmable logic controller of a first system, the method comprising:

[0006] In response to a selection operation of a first transport process, determining, based on a first process matrix table and the first transport process, an association between the first transport process and a selected second transport process; wherein the first process matrix table is constructed based on the transport equipment of the first system and the preset transport process of the first system;

[0007] In response to the association between the first transport process and the selected second transport process satisfying a preset association condition, obtaining identification information of a system shared device of the first transport process;

[0008] Based on the identification information of the system shared device, the occupation status information of the system shared device in the second system is obtained, wherein the occupation status information of the system shared device in the second system is the first status information sent by the second system to the first system in real time, and the first status information is determined based on the second process matrix table and the identification information of the system shared device; the second process matrix table is constructed based on the transportation equipment of the second system and the preset transportation process of the second system;

[0009] In response to the occupancy status information being unoccupied, determining the first transport process and the second transport process as target transport processes;

[0010] Based on the target transportation process, the transportation equipment in the target transportation process is controlled to transport the material according to the target transportation process.

[0011] In a possible implementation, in response to the selection operation of the first transport process, determining the association between the first transport process and the selected second transport process based on the first process matrix table and the first transport process includes:

[0012] Determine the number of operations of the first transportation process based on the first process matrix table and the first transportation process;

[0013] Determine the number of operations of the second transportation process based on the first process matrix table and the selected second transportation process;

[0014] Based on the number of operations of the first transport process and the number of operations of the second transport process, the association between the first transport process and the selected second transport process is determined.

[0015] In a possible implementation, the determining, based on the operand of the first transport process and the operand of the second transport process, the association between the first transport process and the selected second transport process includes:

[0016] determining an association status value based on the number of operations of the first transport process and the number of operations of the second transport process;

[0017] Based on the association status value, an association status between the first transport process and the selected second transport process is determined.

[0018] In a possible implementation, the method further includes:

[0019] In response to the association between the first transport process and the selected second transport process not satisfying a preset association condition, acquiring an operation number of the first transport process and an operation number of the second transport process based on the first process matrix table;

[0020] Calculating a reference value based on the number of operations of the first transport process and the number of operations of the second transport process;

[0021] Based on the equipment position number and reference value of the first process matrix table, the process sharing equipment of the first transportation process and the second transportation process is determined using a preset process sharing equipment identification algorithm.

[0022] In a possible implementation, based on the target transportation process, controlling the transportation equipment in the target transportation process to transport the material according to the target transportation process includes:

[0023] Based on the first process matrix table and the target transportation process, obtaining an operation number of the target transportation process;

[0024] Based on the operand, controlling the transport equipment in the target transport process to transport the material according to the target transport process;

[0025] Output the operation status information of the first transportation process.

[0026] In a second aspect, a method for material transportation control is provided, the method being applied to a programmable logic controller of a second system, the method comprising:

[0027] In response to the selection operation of the third transport process, based on the second process matrix table and the third transport process, determining the association between the third transport process and the selected fourth transport process; wherein the second process matrix table is constructed based on the transport equipment of the second system and the preset transport process of the second system;

[0028] In response to the association between the third transport process and the selected fourth transport process satisfying a preset association condition, obtaining identification information of a system shared device of the third transport process;

[0029] Based on the identification information of the system shared device, the occupation status information of the system shared device in the second system is obtained, wherein the occupation status information of the system shared device in the second system is the first status information sent by the second system to the first system in real time, and the first status information is determined based on the second process matrix table and the identification information of the system shared device; the second process matrix table is constructed based on the transportation equipment of the second system and the preset transportation process of the second system;

[0030] In response to the occupancy status information being unoccupied, determining the third transport process and the fourth transport process as target transport processes;

[0031] Based on the target transportation process, the transportation equipment in the target transportation process is controlled to transport the material according to the target transportation process.

[0032] In a third aspect, a material transport control device is provided, which is applied to a programmable logic controller of a first system, and the device comprises:

[0033] A first selection unit, configured to determine, in response to a selection operation of a first transport process, an association between the first transport process and a selected second transport process based on a first process matrix table and the first transport process; wherein the first process matrix table is constructed based on the transport equipment of the first system and a preset transport process of the first system;

[0034] A first acquisition unit, configured to acquire identification information of a system shared device of the first transport process in response to an association between the first transport process and the selected second transport process satisfying a preset association condition;

[0035] A first obtaining unit is configured to obtain occupation status information of the system shared device in the second system based on the identification information of the system shared device, wherein the occupation status information of the system shared device in the second system is first status information sent by the second system to the first system in real time, and the first status information is determined based on a second process matrix table and the identification information of the system shared device; and the second process matrix table is constructed based on the transportation equipment of the second system and a preset transportation process of the second system;

[0036] a first determining unit, configured to determine, in response to the occupancy status information being unoccupied, the first transport process and the second transport process as target transport processes;

[0037] The first control unit is used to control the transportation equipment in the target transportation process to transport the material according to the target transportation process based on the target transportation process.

[0038] In a fourth aspect, a material transport control device is provided, which is applied to a programmable logic controller of a second system, and the device comprises:

[0039] A second selection unit is used to determine, in response to a selection operation of a third transport process, an association between the third transport process and a selected fourth transport process based on a second process matrix table and the third transport process; wherein the second process matrix table is constructed based on the transport equipment of the second system and a preset transport process of the second system;

[0040] A second acquisition unit, configured to acquire identification information of a system shared device of the third transport process in response to the association between the third transport process and the selected fourth transport process satisfying a preset association condition;

[0041] A second obtaining unit is configured to obtain occupation status information of the system shared device in the first system based on the identification information of the system shared device, wherein the occupation status information of the system shared device in the first system is second status information sent by the first system to the second system in real time, and the second status information is determined based on a first process matrix table and the identification information of the system shared device; the first process matrix table is constructed based on the transportation equipment of the first system and a preset transportation process of the first system;

[0042] a second determining unit, configured to determine, in response to the occupancy status information being unoccupied, the third transport process and the fourth transport process as target transport processes;

[0043] The second control unit is used to control the transportation equipment in the target transportation process to transport the material according to the target transportation process based on the target transportation process.

[0044] In a fifth aspect, a material transportation control system is provided, the material transportation control system comprising a first system and a second system, the first system comprising a programmable logic controller and a transportation device, the second system comprising a programmable logic controller and a transportation device;

[0045] The programmable logic controller of the first system is used to control the transportation equipment in the first system to transport the material according to the method of the first aspect and any possible implementation manner;

[0046] The programmable logic controller of the second system is used to control the transportation equipment in the second system to transport the material according to the method described in the first aspect.

[0047] In a sixth aspect, a computer-readable storage medium is provided, wherein the storage medium stores at least one instruction, and the at least one instruction is loaded and executed by a processor to implement the method of the above-mentioned aspect and any possible implementation method.

[0048] In a seventh aspect, a programmable logic controller is provided, comprising:

[0049] at least one processor; and

[0050] a memory communicatively connected to the at least one processor; wherein,

[0051] The memory stores instructions that can be executed by the at least one processor, and the instructions are executed by the at least one processor to enable the at least one processor to perform the method of any possible implementation manner and the aspects described above.

[0052] The beneficial effects of the technical solution provided by this application include at least:

[0053] It can be known from the above technical scheme that the embodiment of the present application can determine the association between the first transport process and the selected second transport process based on the first process matrix table and the first transport process in response to the selection operation of the first transport process through the programmable logic controller of the first system, and then in response to the association between the first transport process and the selected second transport process meeting the preset association condition, obtain the identification information of the system shared device of the first transport process, obtain the occupancy status information of the system shared device in the second system based on the identification information of the system shared device, and in response to the occupancy status information being unoccupied, determine that the first transport process and the second transport process are target transport processes, so that the target transport process can be controlled based on the target transport process. The transportation equipment in the process transports the materials according to the target transportation process, wherein the second process matrix is ​​constructed based on the transportation equipment of the second system and the preset transportation process of the second system, and the first process matrix is ​​constructed based on the transportation equipment of the first system and the preset transportation process of the first system. Since the equipment occupancy situation of the selected process within the system, that is, the equipment interference situation, can be judged based on the predetermined first process matrix and second process matrix, and then the equipment interference situation between systems can be judged to determine whether the selected process can be used to control the transportation of materials, it can effectively avoid mixing accidents caused by repeated equipment selection and avoid wasting energy, thereby ensuring the continuity, stability and reliability of multi-cross bulk material transportation.

[0054] It should be understood that the content described in this section is not intended to identify the key or important features of the embodiments of the present application, nor is it intended to limit the scope of the present application. Other features of the present application will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0055] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0056] Figure 1It is a flow chart of a method for material transportation control provided by an embodiment of the present application;

[0057] Figure 2 is a flow chart of a material transportation control method provided by another embodiment of the present application;

[0058] Figure 3 is a flow chart of a material transportation control method provided by another embodiment of the present application;

[0059] Figure 4 is a schematic diagram of a transportation process model of a material transportation control system provided by another embodiment of the present application;

[0060] Figure 5 is a schematic diagram of a transportation process selection screen in a material transportation control method provided by another embodiment of the present application;

[0061] Figure 6 is a schematic diagram of another transportation process selection screen in a material transportation control method provided by another embodiment of the present application;

[0062] Figure 7 is a structural block diagram of a material transportation control device provided in yet another embodiment of the present application;

[0063] Figure 8 This is a structural block diagram of a material transportation control device provided in yet another embodiment of the present application. DETAILED DESCRIPTION

[0064] The following is a description of exemplary embodiments of the present application in conjunction with the accompanying drawings, including various details of the embodiments of the present application to facilitate understanding, which should be considered as merely exemplary. Therefore, it should be recognized by those of ordinary skill in the art that various changes and modifications can be made to the embodiments described herein without departing from the scope and spirit of the present application. Similarly, for the sake of clarity and conciseness, the description of well-known functions and structures is omitted in the following description.

[0065] Obviously, the described embodiments are only part of the embodiments of the present application, but not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.

[0066] It should be noted that the terminal devices involved in the embodiments of the present application may include but are not limited to mobile phones, personal digital assistants (PDAs), wireless handheld devices, tablet computers and other smart devices; display devices may include but are not limited to personal computers, televisions and other devices with display functions.

[0067] In addition, the term "and / or" in this article is only a description of the association of related objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the related objects before and after are in an "or" relationship.

[0068] Please refer to Figure 1 , which shows a flow chart of a material transportation control method provided by an embodiment of the present application. The material transportation control method can be applied to a programmable logic controller of the first system, and specifically may include:

[0069] Step 101, in response to the selection operation of the first transport process, based on the first process matrix table and the first transport process, determine the association between the first transport process and the selected second transport process; wherein the first process matrix table is constructed based on the transportation equipment of the first system and the preset transport process of the first system.

[0070] Step 102: In response to the association between the first transport process and the selected second transport process satisfying a preset association condition, obtaining identification information of a system shared device of the first transport process.

[0071] Step 103: Based on the identification information of the system shared device, obtain the occupancy status information of the system shared device in the second system, wherein the occupancy status information of the system shared device in the second system is the first status information sent by the second system to the first system in real time, and the first status information is determined based on the second process matrix table and the identification information of the system shared device; the second process matrix table is constructed based on the transportation equipment of the second system and the preset transportation process of the second system.

[0072] Step 104: In response to the occupancy status information being unoccupied, determining the first transport process and the second transport process as target transport processes.

[0073] Step 105: Based on the target transportation process, control the transportation equipment in the target transportation process to transport the material according to the target transportation process.

[0074] It should be noted that the material transportation control system may include a first system and a second system. The first system and the second system may be divided according to actual transportation equipment and transportation process. For material transportation of a system for multi-cross bulk material transportation control, the number of transportation equipment in the material transportation control system may be multiple. The number of transportation equipment in the first system may be multiple; the number of transportation equipment in the second system may be multiple.

[0075] It should be noted that the transportation process may refer to the equipment of the transportation nodes and the information of these equipments that the materials pass through in sequence during the transportation process in the multi-cross bulk material flow transportation system. A transportation process may include multiple transportation equipments.

[0076] It is understandable that the first system and the second system may be subsystems of the system for material transport control. In addition, the system for material transport control may include a plurality of subsystems. In practical applications, the number of subsystems of the system for material transport control may be determined according to the transport process model.

[0077] It should be noted that the first transportation process and the second transportation process can be the transportation processes of the first system.

[0078] It should be noted that the system shared equipment may be transportation equipment that exists in both the transportation process of the first system and the transportation process of the second system, that is, equipment that may be shared by the transportation process of the first system and the transportation process of the second system.

[0079] It can be understood that the number of the system shared device may be at least one. There is a corresponding relationship between the identification information of the system shared device and the occupation state information of the system shared device in the second system.

[0080] It should be noted that the first process matrix table may be pre-compiled based on the transportation process model of the first system. The second process matrix table may be pre-compiled based on the transportation process model of the second system. The transportation process model may be constructed based on the conditions of various types of transportation equipment in actual transportation scenarios.

[0081] It can be understood that the selected second transport process may be a transport process that is determined to be executable after being selected.

[0082] In this way, based on the predetermined first process matrix table and the second process matrix table, the equipment interference situation of the selected process can be judged within the system first, and then the equipment interference situation between systems can be judged to determine whether the selected process can be used to control the transportation of materials. This can effectively avoid mixing accidents caused by repeated equipment selection and avoid wasting energy, thereby ensuring the continuity, stability and reliability of multi-cross bulk material transportation.

[0083] Optionally, in a possible implementation of this embodiment, in step 101, in response to the selection operation of the first transport process, first, based on the first process matrix table and the first transport process, the number of operations of the first transport process is determined. Secondly, based on the first process matrix table and the selected second transport process, the number of operations of the second transport process is determined. Thirdly, based on the number of operations of the first transport process and the number of operations of the second transport process, the association between the first transport process and the selected second transport process is determined.

[0084] In this implementation, the association between the first transport process and the selected second transport process may include no conflict between transport equipment and conflict between transport equipment.

[0085] In a specific implementation process of this implementation, first, based on the operands of the first transport process and the operands of the second transport process, an association state value is determined. Secondly, based on the association state value, an association between the first transport process and the selected second transport process is determined.

[0086] In one case of the specific implementation process, further, first, the association status value of each preset transport process of the first system determined based on the operand of the second transport process is obtained. Secondly, the identifier of the first transport process is determined based on the operand of the first transport process. Thirdly, the association status value corresponding to the first transport process is queried from the association status value of each preset transport process of the first system based on the identifier of the first transport process, so as to determine the association between the first transport process and the selected second transport process based on the association status value corresponding to the first transport process.

[0087] Here, the operation number of the first transport process can correspond to a transport process. Therefore, the association status value corresponding to the first transport process can be directly queried from the association status value of each preset transport process of the first system based on the operation number of the first transport process, so as to determine the association between the first transport process and the selected second transport process based on the association status value corresponding to the first transport process.

[0088] Exemplarily, the association status value may be 1 or 0. When the association status value corresponding to the first transport process may be 1, it indicates that the association between the first transport process and the selected second transport process is a conflict between transport equipment, that is, there is interference equipment between the two processes. When the association status value corresponding to the first transport process may be 0, it indicates that the association between the first transport process and the selected second transport process is a non-conflict between transport equipment, that is, there is no interference equipment between the two processes.

[0089] In a specific implementation, the first transport process and the second transport process belong to different selection operations. For example, the second transport process corresponds to the first selection operation, and the first transport process corresponds to the second selection operation.

[0090] Another situation of the specific implementation process is that in step 101, in response to the operator's selection operation of the second transport process of the first system, the operands of the second transport process and the operands of other transport processes other than the second transport process can be determined based on the first process matrix table and the second transport process. Secondly, it is determined whether the initial association state value of each preset transport process of the first system meets the preset selection condition. Thirdly, in response to the initial association state value of each preset transport process meeting the preset selection condition, the operands of the second transport process are respectively subjected to logical AND operation processing with the operands of other transport processes to obtain the relationship value of the second transport process and each other transport process. Thirdly, each relationship value and each initial relationship value corresponding to the second selection operation are subjected to logical OR operation processing, so as to update the initial association state value of each preset transport process of the first system based on the result of the logical OR operation processing, and obtain the association state value of each preset transport process after the update processing.

[0091] Here, the preset selection condition may include that the state of the transportation equipment corresponding to the initial associated state value is a state in which the transportation equipment can be selected.

[0092] Exemplarily, the initial association state value may include 1 or 0. If the initial association state value is 1, it indicates that the transport equipment in the preset transport process is not in a state of being unselectable, that is, the transport equipment has been selected and cannot be selected again. If the initial association state value is 0, it indicates that the transport equipment in the preset transport process is in a state of being selectable, that is, the transport equipment has not been selected and can be selected again.

[0093] Optionally, in a possible implementation of this embodiment, in step 102, the preset association condition includes that there is no conflict between transport equipment in different transport processes. Specifically, in response to the association between the first transport process and the selected second transport process being a conflict between transport equipment, that is, not satisfying the preset association condition, an alarm message may be output based on the first transport process. The alarm message may include that the transport equipment in the first transport process is occupied.

[0094] Optionally, in a possible implementation of this embodiment, after step 102, firstly, in response to the association between the first transport process and the selected second transport process not satisfying the preset association condition, the operands of the first transport process and the operands of the second transport process may be obtained based on the first process matrix table. Secondly, a reference value may be calculated based on the operands of the first transport process and the operands of the second transport process. Thirdly, based on the equipment position number and the reference value of the first process matrix table, the process sharing equipment of the first transport process and the second transport process may be determined using a preset process sharing equipment identification algorithm.

[0095] In a specific implementation process of this implementation method, first, the operands of the first transport process and the operands of the second transport process are processed by AND operation to calculate the reference value. Secondly, based on the equipment position number and the reference value of the first process matrix table, the equipment position number of the process shared equipment of the first transport process and the second transport process is calculated using the preset process shared equipment identification algorithm. Thirdly, based on the equipment position number of the process shared equipment, the process shared equipment of the first transport process and the second transport process is determined.

[0096] Here, the equipment bit number may be the bit number corresponding to the transport equipment in the first process matrix table. The bit number may be used to represent text information such as the name and number of the transport equipment.

[0097] Optionally, in a possible implementation of this embodiment, in step 105, first, based on the first process matrix table and the target transportation process, an operand of the target transportation process is obtained. Secondly, based on the operand, the transportation equipment in the target transportation process is controlled to transport the material according to the target transportation process. Thirdly, the operation status information of the first transportation process is output.

[0098] In this implementation, the running status information of the first transport process may be display status information used to indicate that the first transport process is executable or selectable. For example, the running status information may include the display background color of the first transport process.

[0099] It should be noted that the specific implementation process provided in this implementation can be combined with the various specific implementation processes provided in the aforementioned implementation to implement the material transportation control method of this embodiment. For detailed description, please refer to the relevant content in the aforementioned implementation, which will not be repeated here.

[0100] Figure 2 is a flow chart of a material transportation control method provided by another embodiment of the present application. Figure 2 The material transportation control method can be applied to the programmable logic controller of the second system, and specifically may include:

[0101] Step 201, in response to the selection operation of the third transport process, based on the second process matrix table and the third transport process, determine the association between the third transport process and the selected fourth transport process; wherein the second process matrix table is constructed based on the transportation equipment of the second system and the preset transport process of the second system.

[0102] Step 202: In response to the association between the third transport process and the selected fourth transport process satisfying a preset association condition, obtaining identification information of a system shared device of the third transport process.

[0103] Step 203: Based on the identification information of the system shared device, obtain the occupancy status information of the system shared device in the first system, wherein the occupancy status information of the system shared device in the first system is second status information sent by the first system to the second system in real time, and the second status information is determined based on the first process matrix table and the identification information of the system shared device; the first process matrix table is constructed based on the transportation equipment of the first system and the preset transportation process of the first system.

[0104] Step 204: In response to the occupancy status information being unoccupied, determining the third transport process and the fourth transport process as target transport processes.

[0105] Step 205: Based on the target transportation process, control the transportation equipment in the target transportation process to transport the material according to the target transportation process.

[0106] It should be noted that the third transportation process and the fourth transportation process can be the transportation processes of the second system.

[0107] It should be noted that the system shared equipment may be transportation equipment that exists in both the transportation process of the first system and the transportation process of the second system, that is, equipment that may be shared by the transportation process of the first system and the transportation process of the second system.

[0108] It is understandable that the number of the system shared devices may be at least one. There is a corresponding relationship between the identification information of the system shared devices and the occupation state information of the system shared devices in the first system.

[0109] It should be noted that the first process matrix table may be pre-compiled based on the transportation process model of the first system. The second process matrix table may be pre-compiled based on the transportation process model of the second system. The transportation process model may be constructed based on the conditions of various types of transportation equipment in actual transportation scenarios.

[0110] In this way, the programmable logic controller of the second system can first judge the equipment interference situation of the selected process within the system based on the predetermined first process matrix table and the second process matrix table, and then judge the equipment interference situation between systems to determine whether the selected process can be used to control the transportation of materials. This can effectively avoid mixing accidents caused by repeated equipment selection and avoid wasting energy, thereby ensuring the continuity, stability and reliability of multi-cross bulk material transportation.

[0111] It can be understood that here, the specific implementation method of the material transportation control method based on the second system is similar to the specific implementation method of the material transportation control method based on the first system. The specific implementation method of the material transportation control method based on the second system can refer to the specific implementation method in the aforementioned embodiment, which will not be repeated here.

[0112] In order to better understand the method of the embodiment of the present application, the method of the embodiment of the present application is described below in conjunction with the accompanying drawings and specific application scenarios.

[0113] Figure 3 is a flow chart of a material transportation control method provided by another embodiment of the present application. Figure 3 shown.

[0114] In this embodiment, the transportation process model corresponding to the material transportation control system can be predetermined. In the application scenario of the material transportation control system, Figure 4 is a schematic diagram of a transportation process model of a material transportation control system provided by another embodiment of the present application, such as Figure 4 As shown. The material transportation control system can be an unloading system, i.e. the first system, and a feeding system, i.e. the second system. The left virtual box is the unloading process, which ends when the material is delivered to the stacker. The right virtual box is the feeding process, which ends when the material is delivered to the user's silo. The transportation process of the unloading system and the transportation process of the feeding system are independent of each other, and should not be affected as much as possible during maintenance, and they are not in the same programmable logic controller (PLC). Figure 4As shown, the loading and unloading system includes four transportation processes: A101→A102R→G101→G1ST, A101→A102R→G201→G2ST, A201→A202R→G101→G1ST, and A201→A202R→G201→G2ST. The feeding system includes 6 transportation processes: G1RC→G101→G102SHR→B101→J101, G1RC→G101→G102SHR→B201→Q101, G1RC→G101→G102SHR→B301→K101, G2RC→G201→G202SHR→B101→J101, G2RC→G201→G202SHR→B201→Q101, G2RC→G201→G202SHR→B301→K101.

[0115] The transport equipment of the unloading system includes A101, A102R, A201, A202R, G101, G201, G1ST, among which G1ST and G2ST can be stackers. A101, A102R, A201, A202R, G101, G201, G1ST can be the equipment number of the transport equipment, that is, the equipment number. The transport equipment of the feeding system includes G1RC, G2RC, G101, G201, G102SHR, G202SHR, B101, J101, Q101, K101, among which G1RC and G2RC are reclaimers. The system-shared equipment of the two systems is G101 and G201.

[0116] It can be understood that A101, A102R, A201, A202R, G101, G201, G1ST, G1RC, G2RC, G101, G201, G102SHR, G202SHR, B101, J101, Q101, and K101 can be the equipment numbers of the transportation equipment, that is, the equipment numbers.

[0117] Step 301: In response to an operator selecting a second transport process of a receiving and unloading system, an operation number of the second transport process is determined based on a first process matrix table and the second transport process.

[0118] In this embodiment, the second transport process can be an executable transport process, that is, a selectable transport process. It is understandable that the transport equipment in the second transport process is not occupied in the system and is not occupied in other systems related thereto.

[0119] In this embodiment, first, in response to the operator's selection operation of the second transport process of the receiving and unloading system, the operands of the second transport process can be determined based on the first process matrix table and the second transport process. Based on the operands of the second transport process, it is determined whether the second transport process is executable in the receiving and unloading system. Thirdly, in response to determining that the second transport process is executable in the receiving and unloading system, the identification information of the system shared device of the second transport process is obtained. Thirdly, based on the identification information of the system shared device of the second transport process, the occupation status information of the system shared device in the second system is obtained. Thirdly, in response to the occupation status information being unoccupied, it is determined that the second transport process is an executable transport process.

[0120] Step 302: In response to the operator's selection operation of the first transport process of the unloading system, the operation number of the first transport process is determined based on the first process matrix table and the first transport process.

[0121] In this embodiment, the first process matrix table is constructed based on the transportation equipment of the first system and the preset transportation process of the first system.

[0122] Based on A101 and A201 of the starting transport equipment in the transport process of the receiving and unloading system in the process model, a first process matrix table, namely, the receiving and unloading process matrix table, can be pre-compiled, as shown in Table 1 below:

[0123] Table 1 First process matrix

[0124] flow1 flow2 operand Equipment tag [0] [1] [2] [3] [4] [5] [6] [7] … LOW Process ID A101 A102R A201 A202R G101 G1ST G201 G2ST 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 1 1 0 0 51 2 1 1 0 0 0 0 1 1 195 3 0 0 1 1 1 1 0 0 60 4 0 0 1 1 0 0 1 1 204

[0125] Here, the equipment number can be used to represent the name of each transport equipment. For example, the equipment number [0] can represent the transport equipment with the equipment number A101. The receiving and unloading system can select two flows to run simultaneously, that is, two transport flow selection operations can be performed. Flow1 and flow2 can be used to identify the two transport flow selection operations of the receiving and unloading system.

[0126] In this embodiment, flow1 and flow2 can be pre-configured based on the number of devices that can be run simultaneously corresponding to the narrowest transport channel of the entire material transport control system. In this embodiment, the devices that can be run simultaneously corresponding to the narrowest transport channel of the material transport control system are G101 and G201, and the number of devices is 2, so flow1 and flow2 can be pre-configured. Flow1 and flow2 can be executed using different program blocks of the same PLC.

[0127] Step 303: Determine the association between the first transport process and the second transport process based on the operands of the first transport process and the operands of the second transport process.

[0128] Step 304: In response to the association between the first transport process and the second transport process satisfying a preset association condition, obtain identification information of the system shared device of the first transport process.

[0129] In this embodiment, the preset association condition includes that there is no conflict between the transport equipment of different transport processes. The association between the first transport process and the selected second transport process may include that there is no conflict between the transport equipment of the first transport process and the transport equipment of the second transport process, and there is a conflict between the transport equipment of the first transport process and the transport equipment of the second transport process.

[0130] In this embodiment, first, the association status value may be determined based on the operands of the first transport process and the operands of the second transport process, and the association between the first transport process and the selected second transport process may be determined based on the association status value.

[0131] Specifically, if the association status value is not equal to the preset first threshold, it can be determined that the association between the first transport process and the selected second transport process is a conflict between the transport equipment of the first transport process and the transport equipment of the second transport process, that is, there is a conflicting transport equipment between the first transport process and the second transport process.

[0132] If the association status value is equal to the preset first threshold, it can be determined that the association between the first transport process and the second transport process is that there is no conflict between the transport equipment of the first transport process and the transport equipment of the second transport process, that is, there is no conflicting transport equipment between the first transport process and the second transport process.

[0133] Here, the preset first threshold may be 0. The conflicting transport equipment may be an interfering transport equipment.

[0134] In this embodiment, in response to the operator's selection operation of the second transport process of the unloading system, the operands of the second transport process and the operands of other transport processes other than the second transport process can be determined based on the first process matrix table and the second transport process. Secondly, it is determined whether the initial association state value of each preset transport process of the unloading system meets the preset selection condition. Thirdly, in response to the initial association state value of each preset transport process meeting the preset selection condition, the operands of the second transport process are respectively subjected to logical AND operation processing with the operands of other transport processes to obtain the relationship value of the second transport process and each other transport process. Thirdly, each relationship value and each initial relationship value corresponding to the second selection operation are subjected to logical OR operation processing, so as to update the initial transport process association state value based on the result of the logical OR operation processing, and obtain the association state value of each preset transport process after the update processing. Thirdly, the association state value of each preset transport process of the unloading system determined based on the operand of the second transport process is obtained. Thirdly, based on the operand of the first transport process, the identifier of the first transport process is determined. Again, based on the identification of the first transport process, the association status value corresponding to the first transport process is queried from the association status value of each preset transport process of the unloading system, so as to determine the association between the first transport process and the selected second transport process based on the association status value corresponding to the first transport process.

[0135] For example, the transport process with process ID 1 shown in Table 1 is selected, and the unloading order of the transport equipment is A101→A102R→G101→G1ST. The relevant variables of the transport process, that is, the changes in the state values ​​are shown in Table 2 below:

[0136] Table 2 Table of relevant variables of transportation process

[0137] Serial number Variable Name Variable Symbols Data Types Before selection After selection Other related equipment 1 flow1 is selected flow1_selected bool 0 1 Selected flag 2 flow2 is selected flow2_selected bool 0 0 3 flow1 The flow number of the selected transport flow select_flow1_no int 0 1 4 flow2 The flow number of the selected transport flow select_flow2_no int 0 0 5 flow1 interferes with the status of flow ID=1 flow1_disturb[1] bool 0 1 A101, A102R, G101, G1ST 6 flow1 interferes with flow ID=2 flow1_disturb[2] bool 0 1 A101,A102R 7 flow1 interferes with the status of flow ID=3 flow1_disturb[3] bool 0 1 G101,G1ST 8 flow1 interferes with flow ID=4 flow1_disturb[4] bool 0 0 9 flow2 interferes with the status of flow ID=1 flow2_disturb[1] bool 0 0 10 flow2 interferes with the status of flow ID=2 flow2_disturb[2] bool 0 0 11 flow2 interferes with the status of flow ID=3 flow2_disturb[3] bool 0 0 12 flow2 interferes with the status of flow ID=4 flow2_disturb[4] bool 0 0 13 All table ID = 1 process interference status flow_disturb[1] bool 0 1 A101,A102R,G101,G1ST 14 Full table ID = 2 process interference status flow_disturb[2] bool 0 1 A101,A102R 15 Full table ID=3 process interference status flow_disturb[3] bool 0 1 G101,G1ST 16 Full table ID = 4 process interference status flow_disturb[4] bool 0 0 No interference with ID=1 device

[0138] Here, in Table 2, flow_disturb[a] = (flow1_disturb[a]) logical or (flow2_disturb[a]), where a can represent the process number, a = 1 to 4, and the state value of this flow_disturb[a] variable can be used as the condition for selecting the process. If it is 1, it indicates that there is an interfering device and the corresponding transportation process cannot be selected. If it is 0, the corresponding transportation process can be selected.

[0139] For example, when selecting flow1, if the transport process with process ID=1 is selected, because no other transport process is selected, the state value of the initial associated state value flow_disturb[a] variable is 0, indicating that the transport process with ID=1 can be selected.

[0140] When the transport process with ID=1 is selected, all processes with ID=1 to 4 can be traversed, and the operand 51 of the transport process with ID=1, which is 110011 in binary, is used for logical AND operation with the operands of other transport processes to obtain the operation result. If the operation result is greater than 0, it is determined that there is interference equipment between the two transport processes, and flow1_disturb[a] of the other transport process is set to 1. The transport process with ID=1 belongs to flow1, and each relationship value can be obtained: flow1_disturb[1]=1, flow1_disturb[2]=1, flow1_disturb[3]=1, while the transport process with ID=4 is A201-A202R-G201-G2ST, flow1_disturb[4]=0, that is, there is no interference equipment. Based on the first process matrix table, the unloading system can run two processes at the same time. The process corresponding to flow2 is not selected. Flow2_disturb[1], flow2_disturb[2], flow2_disturb[3], and flow2_disturb[4] are all 0. Flow_disturb[a] = (flow1_disturb[a]) logical OR (flow2_disturb[a]). The new associated state values ​​flow_disturb[1], flow_disturb[2], and flow_disturb[3] are 1, and flow_disturb[4] is 0.

[0141] When the transport flow with ID=1 is selected, if the transport flow with ID=3 is selected, select_flow2_n becomes 3. By querying the state value when the transport flow with ID=1 is selected, flow_disturb[3]=1 can be obtained. The association between the two transport flows is that there is conflicting equipment. Then the interactive selection interface will pop up: This flow equipment is already occupied. Figure 5 As shown, Figure 5 It is a schematic diagram of a transportation process selection screen in a material transportation control method provided in an embodiment of the present application.

[0142] When the transport process with ID=1 is selected, the transport process with ID=4 is selected. At this time, based on the operand of the transport process with ID=4, the queried flow_disturb[4]=0, that is, the transport process with ID=4 can be selected. After the transport process is selected in the interactive selection interface, the background color changes. Figure 6 As shown, Figure 6 It is a schematic diagram of another transportation process selection screen in the material transportation control method provided in an embodiment of the present application.

[0143] In addition, when the transport process with ID=1 based on flow1 is selected, after the transport process with ID=4 is selected based on flow2, all processes with ID=1 to 4 can be traversed, and the operands of the transport process with ID=4 are used to perform logical AND operations with the operands of other transport processes to obtain the associated state value. If the associated state value is greater than 0, it is determined that there is equipment interfering between the two transport processes, and the flow2_disturb of the other transport process is set to 1. Here, the transport process with ID=4 belongs to flow2, and flow2_disturb[1]=0, flow2_disturb[2]=1, flow2_disturb[3]=1 can be obtained, while the transport process with ID=4 flow2_disturb[4]=1. Based on the first process matrix table, it can be seen that the unloading system can run two flow processes at the same time. Based on flow_disturb[a]=(flow1_disturb[a]) logical OR (flow2_disturb[a]), the calculated state values ​​flow_disturb[1], flow_disturb[2], flow_disturb[3], and flow_disturb[4] are 1, respectively, which means that the transportation process cannot be selected later. Furthermore, based on the results of the above calculation process, the variables in the relevant variable table of the transportation process can be updated.

[0144] In addition, in this embodiment, after the selected transport process prompts "this process equipment is occupied", the number of occupied transport equipment in the transport process can be calculated, that is, the number of 1s after the logical AND of the first transport process and the second transport process.

[0145] Specifically, the result value of the logical AND operation of the first transport flow and the second transport flow can be n, and n and (n-1) can be logically ANDed. If the result is greater than 0, the counter is incremented by 1; then the n=n&(n-1) assignment and logical AND operation are performed cyclically. If it is greater than 0, the counter is incremented by 1 again, until the result of the logical AND operation is 0, the counter is incremented by 1 again and the operation is terminated. The counter value can represent the number of occupied transport equipment, that is, the number of interfering transport equipment, which can be expressed in code as follows:

[0146] public static int DeviceCount(int n)

[0147] { int res = 0;

[0148] while (n != 0)

[0149] { n &= n - 1;

[0150] res++;

[0151] }

[0152] return res;

[0153] }

[0154] For example, when the transport process with ID=1 is selected, the transport process with ID=3 is selected: the operand of ID=1 is 51, the operand of ID=3 is 60, and the value after the AND operation of the two operands is 48, which is 110000 in binary. Perform a logical AND operation on 48 (2#110000) and 48-1=47 (2#101111), and the result is 2#100000, which is 32, and the counter is 1. Then perform an AND operation on 32 (2#100000) and 31 (2#11111), and the result is 0, and the counter is 2. Because the operation result is 0, the loop terminates, and it is determined that 2 transport devices are occupied.

[0155] In this embodiment, the preset process sharing device identification algorithm can also be used to determine the device number of the occupied transport device based on the judgment of the device bit number. Furthermore, the device number can also be displayed on the human-computer interaction interface of the PLC controller.

[0156] Exemplarily, based on the first process matrix table, the number 1 is moved from the right side of the binary to the left to the position to be judged to obtain a numerical value. The numerical value is ANDed with the result of the AND operation of the two selected transport process operands. If the result is not 0, it means that the bit is 1, indicating that the device corresponding to the bit number of the bit is an occupied device; if the result is 0, it means that the bit is not 1, indicating that the device corresponding to the bit number of the bit is an unoccupied device. The code of the preset process sharing device identification algorithm is expressed as follows:

[0157] public static void JudgeOnePos(int n) / / Method for judging the specific position of process ID=1

[0158] { for (int i =1; i < 15; i++) / / The size of i depends on the length of the process matrix word

[0159] { int k = 1 << (i - 1); / / Number generated by left shift 1

[0160] int w = n & k; / / AND operation with the original value n

[0161] if (w > 0)

[0162] { Console.WriteLine("The {0}th position is 1", i - 1);} / / Output (i-1) is the position of 1

[0163] }

[0164] }

[0165] Using the preset process sharing equipment identification algorithm, based on the first process matrix table, it is determined that after the transport process with ID=1 is selected, the transport process with ID=3 is selected, and the occupied interfering equipment position number. At this time, the result of the AND of the two transport process operands is w =48, which is 110000 in binary.

[0166] When i=1, k=1; w=48(2#110000)&1(2#000001)=0; when w=0, i-1=0 is not 1;

[0167] When i=2, k=2; w=48(2#110000)&2(2#000010)=0; when w=0, i-1=1 is not 1;

[0168] When i=3, k=4; w=48(2#110000)&4(2#000100)=0; when w=0, i-1=2 bits are not 1;

[0169] When i=4, k=8; w=48(2#110000)&8(2#001000)=0; when w=0, i-1=3 bits are not 1;

[0170] When i=5, k=16; w=48(2#110000)&16(2#010000)=16; if w>0, i-1=4 bits are 1;

[0171] When i=6, k=32; w=48(2#110000)&32(2#100000)=32; if w>0, i-1=4 bits are 1;

[0172] Based on this, it can be determined that the transport equipment corresponding to the 4th and 5th equipment position numbers in the first process matrix table is occupied equipment, and the corresponding equipment numbers are G101 and G1ST.

[0173] In this way, the determined number and name of occupied transport equipment can be stored for subsequent viewing and use by maintenance personnel.

[0174] Step 305: Based on the identification information of the system shared device, obtain the occupation status information of the system shared device in the second system.

[0175] In this embodiment, the identification information of the system shared device may include identification information preset based on the first process matrix table, or identification information preset based on the second process matrix table.

[0176] It can be understood that the system sharing device is two system sharing devices, and therefore, the identification information preset based on the first process matrix table and the identification information preset based on the second process matrix table may correspond to each other, or may be the same.

[0177] In this embodiment, the occupation status information of the system shared device in the second system is the first status information sent by the second system to the first system in real time, and the first status information is determined based on the second process matrix table and the identification information of the system shared device. The second process matrix table is constructed based on the transportation equipment of the second system and the preset transportation process of the second system.

[0178] Here, the occupancy status information may include unoccupied and occupied. When the value of the occupancy status information is 1, it may indicate that the occupancy status information is occupied, and when the value of the occupancy status information is 0, it may indicate that the occupancy status information is unoccupied.

[0179] In this embodiment, the second process matrix table is constructed based on the transportation equipment of the feeding system and the preset transportation process of the feeding system.

[0180] Specifically, based on G101 and G201 of the transport equipment shared by the transport process of the feeding system and the transport process of the unloading system in the process model, a second process matrix table, namely the feeding process matrix table, can be pre-compiled, as shown in Table 3 below:

[0181] Table 3 Second process matrix

[0182] flow3 flow4 Equipment tag [0] [1] [2] [3] [4] [5] [6] [7] [8] [9]

[10]

[11] … operand Process ID G1RC G101 G102SHR G2RC G201 G202SHR B101 B201 B301 J101 Q101 K101 low 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 0 1 0 0 1 0 0 583 2 1 1 1 0 0 0 0 1 0 0 1 0 1159 3 1 1 1 0 0 0 0 0 1 0 0 1 2311 4 0 0 0 1 1 1 1 0 0 1 0 0 632 5 0 0 0 1 1 1 0 1 0 0 1 0 1208 6 0 0 0 1 1 1 0 0 1 0 0 1 2360

[0183] Here, after constructing the first process matrix table and the second process matrix table, in general, the process matrix tables are distributed in PLCs of different systems, and a shared equipment table spanning multiple process tables can be established, indicating the bit number under each table, so as to obtain the occupancy status information of the system shared transportation equipment. In the above-mentioned first process matrix table and the second process matrix table, two devices G101 and G201 are shared.

[0184] Exemplarily, a relationship between equipment occupancy and interference arrays may be established for the process matrix table of each system.

[0185] For example, for the unloading process table, that is, the first process matrix table, a shared interference array is established as flow_comdisturb, and variables G101_IN_USE_G and G201_IN_USE_G are established. Based on these variables, the status of whether G101 and G201 in the second process matrix table are selected, that is, the occupation status information, can be obtained through communication. According to the first process matrix table, there are the following assignment relationships:

[0186] flow_comdisturb[1]=G101_IN_USE_G; flow_comdisturb[3]=G101_IN_USE_G;

[0187] flow_comdisturb[2]=G201_IN_USE_G; flow_comdisturb[4]=G201_IN_USE_G;

[0188] The data flow is shown in Table 4 below:

[0189] Table 4 Data flow table based on the unloading process table

[0190]

[0191] Here, G101_IN_USE_G and G201_IN_USE_G can be used as identification information of system shared equipment based on the receiving and unloading system. There is a corresponding relationship between the identification information of the system shared equipment based on the receiving and unloading system and the identification information of the system shared equipment in the feeding system. The system shared equipment in the feeding system can also be identified as G101_IN_USE_G and G201_IN_USE_G. The occupancy status information of the system shared equipment in the feeding system, that is, the first status information, can be queried based on the identification information of the system shared equipment in the feeding system and the second process matrix table. The value of the occupancy status information, that is, the value of the first status information, can be used to characterize the occupancy status information, that is, the first status information.

[0192] The value of the occupancy status information of the system shared equipment in the feeding system received by the receiving system, that is, the value of the first status information, can correspond to the process sharing interference variable value in the receiving system. The process sharing interference variable value can be used to characterize the occupancy status information of the system shared equipment in the feeding system. The process sharing interference variable value and the identification information of the system shared equipment of the receiving system can also have a corresponding relationship, and then the occupancy status information of the system shared equipment in the feeding system can be obtained based on the identification information of the system shared equipment of the receiving system and the process sharing interference variable value. The process sharing interference variable value may include flow_comdisturb[1], flow_comdisturb[2], flow_comdisturb[3], flow_comdisturb[4]. Among them, 1, 2, 3, 4 can represent the process number of the system shared equipment selected for transportation in the receiving system, which can be represented by the variable select_flow1_no or select_flow2_no. When the value of the first status information is 1, the system shared device is in an occupied state in the feeding system, that is, there are interfering transportation devices between systems. When the value of the first status information is 0, the system shared device is in an unoccupied state in the feeding system, that is, there are no interfering transportation devices between systems.

[0193] For example, the transport process with process ID 1 in the receiving and unloading system is selected, and the value of flow_comdisturb[1] obtained based on the first status information sent in real time by the feeding system can be obtained based on G101_IN_USE_G. If flow_comdisturb[1] is 1, it can be determined that the occupancy status information of the system shared equipment in the feeding system is occupied. The transport process with process ID 4 in the receiving and unloading system is selected, and the value of flow_comdisturb[4] can be obtained based on G201_IN_USE_G. If flow_comdisturb[4] is 0, it can be determined that the occupancy status information of the system shared equipment in the feeding system is not occupied.

[0194] For example, when the transport process including the G101 transport equipment is selected in the feeding system, the value of G101_IN_USE_G in the feeding controller is 1. Through real-time communication, the feeding system sends the information that the value of G101_IN_USE_G is 1 to the receiving system. The values ​​of flow_comdisturb[1] and flow_comdisturb[3] in the receiving system become 1, and then G101_IN_USE_G in the receiving system is assigned a value of 1.

[0195] For another example, for the feed flow table, i.e., the second flow matrix table, a shared interference array is established as flow_comdisturb[]; variables G101_IN_USE_S and G201_IN_USE_S are established. This variable obtains the status of whether G101 and G201 are selected in the first flow matrix table through communication, and has the following assignment relationship according to the second flow matrix table:

[0196] flow_comdisturb[1]=G101_IN_USE_S;

[0197] flow_comdisturb[2]=G101_IN_USE_S;

[0198] flow_comdisturb[3]=G101_IN_USE_S;

[0199] flow_comdisturb[4]=G201_IN_USE_S;

[0200] flow_comdisturb[5]=G201_IN_USE_S;

[0201] flow_comdisturb[6]=G201_IN_USE_S;

[0202] The data flow is shown in Table 5 below:

[0203] Table 5 Data flow table based on the feed flow table

[0204]

[0205] Here, G101_IN_USE_S and G201_IN_USE_S are identification information of the system shared device based on the feeding system in Table 5, that is, identification information of the system shared device when the second system performs material transportation control.

[0206] It can be understood that the process of determining whether there is an equipment operation conflict between systems in the transportation process selected by the feeding system is similar to the relevant process of the receiving and unloading system. The detailed implementation method can refer to the relevant content of the receiving and unloading system, and will not be repeated here.

[0207] It can be understood that, on the one hand, no matter which transport process of the unloading system based on the unloading process table is selected, the addressing method of flow_comdisturb [select_flow1_no] or flow_comdisturb [select_flow2_no] can be used to determine whether there is an external interference device, and when it is 1, there is an interference device, and when it is 0, there is no interference device. On the other hand, no matter which transport process of the feeding system based on the feeding process table is selected, the addressing method of flow_comdisturb [select_flow3_no] or flow_comdisturb [select_flow4_no] can be used to determine whether there is external interference, and when it is 1, there is interference, and when it is 0, there is no interference.

[0208] In addition, it is understandable that the value assigned to each flow_comdisturb array is not necessarily unique. There may be several devices that affect a process at the same time. This can be achieved by establishing multiple bool type flow_comdisturb arrays, such as flow_comdisturb1[m], flow_comdisturb2[m], where m is determined by the number of process IDs.

[0209] Step 306: In response to the occupancy status information being unoccupied, determining the first transport process and the second transport process as target transport processes.

[0210] In this embodiment, for the external addressing situation, that is, when determining the usage of other associated system devices, the transport flow can be selected only when the values ​​corresponding to flow_comdisturb[select_flow1_no] and flow_disturb[select_flow1_no] are both 0. Similarly, the same is true in the processing of the process numbers select_flow2_no, select_flow3_no, and select_flow4_no of the selected transport flows corresponding to different selection operations.

[0211] It can be understood that when selecting a transport process, when flow_disturb[the process number of the selected transport process] and flow_comdisturb[the process number of the selected transport process] are both in the 0 state, it means that the two selected transport processes have no interfering equipment within this system and between them and other systems, and the two selected transport processes can be selected as the target transport processes.

[0212] Step 307: Based on the target transportation process, control the transportation equipment in the target transportation process to transport materials according to the target transportation process.

[0213] In this embodiment, firstly, when no transport process is selected in the first system, i.e., the receiving and unloading system, the operator can select the second transport process of the receiving and unloading system. In response to the operator's selection of the second transport process of the receiving and unloading system, the identification information of the system shared device of the second transport process can be obtained. Secondly, based on the identification information of the system shared device, the occupancy status information of the system shared device in the second system can be obtained. In response to the occupancy status information being unoccupied, the second transport process is determined to be an executable transport process. Thirdly, based on the second transport process, the transport equipment can be controlled to transport materials according to the second transport process, or steps 302 to 307 can be continued.

[0214] It is understandable that, when no transport process is selected in the first system, i.e., the receiving and unloading system, the operator can directly judge the inter-system interference equipment to determine whether the second transport process is operational when selecting the second transport process of the receiving and unloading system. If it is operational, the transport equipment can be controlled to transport logistics based on the second transport process. When the operator selects the first transport process of the receiving and unloading system, steps 302 to 307 are executed.

[0215] In addition, it can be understood that here, the specific implementation method of the material transportation control method based on the feeding system is similar to the specific implementation method of the material transportation control method based on the unloading system in this embodiment. The specific implementation method of the material transportation control method based on the feeding system can refer to the specific implementation method in this embodiment, which will not be repeated here.

[0216] In this way, by adopting the scheme in this embodiment, the internal process matrix table of each subsystem can be constructed through the process model pre-established based on the actual transportation application scenario. Based on the internal process matrix table of each subsystem, the corresponding internal loop judgment method and external addressing judgment method are used to make transportation equipment interference judgment when selecting the process, and the number of interfering equipment and which specific equipment interferes can be calculated and displayed on the PLC human-machine interface, thereby avoiding mixing accidents caused by repeated equipment selection, avoiding energy waste and reducing production efficiency, thereby ensuring the accuracy of interfering equipment judgment in the transportation process, and ensuring the continuity, stability and reliability of transportation production.

[0217] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present application.

[0218] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0219] Figure 7 FIG. 1 shows a structural block diagram of a material transport control device provided by an embodiment of the present application. Figure 7 As shown. The material transportation control device 700 of this embodiment is applied to the first system programmable logic controller, and may include a first selection unit 701, a first acquisition unit 702, a first acquisition unit 703, a first determination unit 704 and a first control unit 705. Among them, the first selection unit 701 is used to respond to the selection operation of the first transportation process, based on the first process matrix table and the first transportation process, determine the association between the first transportation process and the selected second transportation process; wherein, the first process matrix table is constructed based on the transportation equipment of the first system and the preset transportation process of the first system; the first acquisition unit 702 is used to respond to the association between the first transportation process and the selected second transportation process meets the preset association condition, and obtain the identification information of the system shared device of the first transportation process; the first acquisition unit 703 is used to obtain the occupancy status of the system shared device in the second system based on the identification information of the system shared device. Status information, wherein the occupancy status information of the system shared device in the second system is the first status information sent by the second system to the first system in real time, and the first status information is determined based on the second process matrix table and the identification information of the system shared device; the second process matrix table is constructed based on the transportation equipment of the second system and the preset transportation process of the second system; the first determination unit 704 is used to determine that the first transportation process and the second transportation process are target transportation processes in response to the occupancy status information being unoccupied; the first control unit 705 is used to control the transportation equipment in the target transportation process to transport the material according to the target transportation process based on the target transportation process.

[0220] Optionally, in a possible implementation of the present embodiment, the first selection unit 701 is used to determine the number of operations of the first transport process based on the first process matrix table and the first transport process; determine the number of operations of the second transport process based on the first process matrix table and the selected second transport process; and determine the association between the first transport process and the selected second transport process based on the number of operations of the first transport process and the number of operations of the second transport process.

[0221] Optionally, in a possible implementation of this embodiment, the first selection unit 701 is used to determine an association status value based on the operation number of the first transport process and the operation number of the second transport process; and based on the association status value, determine the association between the first transport process and the selected second transport process.

[0222] Optionally, in a possible implementation of the present embodiment, the first acquisition unit 702 is used to obtain the operation number of the first transport process and the operation number of the second transport process based on the first process matrix table in response to the association between the first transport process and the selected second transport process not satisfying the preset association condition; calculate a reference value based on the operation number of the first transport process and the operation number of the second transport process; determine the process sharing equipment of the first transport process and the second transport process based on the equipment position number and the reference value of the first process matrix table and using a preset process sharing equipment identification algorithm.

[0223] Optionally, in a possible implementation of this embodiment, the first control unit 705 is used to obtain the operands of the target transport process based on the first process matrix table and the target transport process; based on the operands, control the transportation equipment in the target transport process to transport the materials according to the target transport process; and output the operating status information of the first transport process.

[0224] In this embodiment, the selection unit can respond to the selection operation of the first transport process and determine the association between the first transport process and the selected second transport process based on the first process matrix table and the first transport process; wherein the first process matrix table is constructed based on the transport equipment of the first system and the preset transport process of the first system, and the acquisition unit obtains the identification information of the system shared device of the first transport process in response to the association between the first transport process and the selected second transport process meeting the preset association condition, and the acquisition unit obtains the occupancy status information of the system shared device in the second system based on the identification information of the system shared device, wherein the occupancy status information of the system shared device in the second system is the first status information sent by the second system to the first system in real time, and the first status information is based on the second process matrix table and the system shared The second process matrix is ​​constructed based on the transportation equipment of the second system and the preset transportation process of the second system. The determination unit determines that the first transportation process and the second transportation process are target transportation processes in response to the occupancy status information that the system is not occupied, so that the control unit controls the transportation equipment in the target transportation process to transport the materials according to the target transportation process based on the target transportation process. Since the occupancy status of the selected process in the system, that is, the equipment interference status, can be judged based on the predetermined first process matrix and second process matrix, and then the equipment interference status between systems can be judged to determine whether the selected process can be used to control the transportation of materials, it can effectively avoid mixing accidents caused by repeated equipment selection and waste of energy, thereby ensuring the continuity, stability and reliability of multi-cross bulk material transportation.

[0225] Figure 8 FIG. 1 shows a structural block diagram of a material transport control device provided by an embodiment of the present application. Figure 8As shown. The material transportation control device 800 of this embodiment is applied to the second system programmable logic controller, and may include a second selection unit 801, a second acquisition unit 802, a second acquisition unit 803, a second determination unit 804 and a second control unit 805. Among them, the second selection unit 801 is used to respond to the selection operation of the third transportation process, based on the second process matrix table and the third transportation process, determine the association between the third transportation process and the selected fourth transportation process; wherein the second process matrix table is constructed based on the transportation equipment of the second system and the preset transportation process of the second system; the second acquisition unit 802 is used to respond to the association between the third transportation process and the selected fourth transportation process meets the preset association condition, and obtain the identification information of the system shared device of the third transportation process; the second acquisition unit 803 is used to obtain the occupancy status of the system shared device in the first system based on the identification information of the system shared device. state information, wherein the occupancy state information of the system shared device in the first system is the second state information sent by the first system to the second system in real time, and the second state information is determined based on the first process matrix table and the identification information of the system shared device; the first process matrix table is constructed based on the transportation equipment of the first system and the preset transportation process of the first system; the second determination unit 804 is used to determine that the third transportation process and the fourth transportation process are target transportation processes in response to the occupancy state information being unoccupied; the second control unit 805 is used to control the transportation equipment in the target transportation process to transport the material according to the target transportation process based on the target transportation process.

[0226] In this embodiment, the selection unit can respond to the selection operation of the third transport process and determine the association between the third transport process and the selected fourth transport process based on the second process matrix table and the third transport process; wherein the second process matrix table is constructed based on the transport equipment of the second system and the preset transport process of the second system, and the acquisition unit responds to the association between the third transport process and the selected fourth transport process satisfying the preset association condition, and obtains the identification information of the system shared device of the third transport process; the acquisition unit obtains the occupancy status information of the system shared device in the first system based on the identification information of the system shared device, wherein the occupancy status information of the system shared device in the first system is the second status information sent by the first system to the second system in real time, and the second status information is based on the first process matrix table and the system shared The first process matrix is ​​constructed based on the transportation equipment of the first system and the preset transportation process of the first system. The determination unit determines the third transportation process and the fourth transportation process as the target transportation process in response to the occupancy status information being unoccupied, so that the control unit controls the transportation equipment in the target transportation process to transport the material according to the target transportation process based on the target transportation process. Since the occupancy status of the selected process in the system, i.e., the equipment interference status, can be judged based on the predetermined first process matrix and second process matrix, and then the equipment interference status between systems can be judged to determine whether the selected process can be used to control the transportation of materials, it can effectively avoid mixing accidents caused by repeated equipment selection and waste of energy, thereby ensuring the continuity, stability and reliability of multi-cross bulk material transportation.

[0227] In an embodiment of the present application, a material transportation control system is also provided, wherein the material transportation control system includes a first system and a second system, wherein the first system includes a programmable logic controller and transportation equipment, and the second system includes a programmable logic controller and transportation equipment; the programmable logic controller of the first system is used to control the transportation equipment to transport the material according to the method in the aforementioned embodiment; and the programmable logic controller of the second system is used to control the transportation equipment in the second system to transport the material according to the method in the aforementioned embodiment.

[0228] In this embodiment, the material transportation control system may be a multi-cross bulk material flow transportation system, and the number of transportation equipment in the system may be multiple.

[0229] In this embodiment, the programmable logic controller can control a plurality of transport equipment corresponding to the target transport process to transport the material based on the target transport process determined by the method described in the above embodiment.

[0230] In the technical solution of this application, the user personal information involved, such as the collection, storage, use, processing, transmission, provision and disclosure of user images and attribute data, etc., complies with the provisions of relevant laws and regulations and does not violate public order and good morals.

[0231] According to an embodiment of the present application, the present application also provides an electronic device, a readable storage medium and a computer program product.

[0232] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps recorded in this disclosure can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution disclosed in this application can be achieved, and this document is not limited here.

[0233] The above specific implementations do not constitute a limitation on the protection scope of this application. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modifications, equivalent substitutions and improvements made within the spirit and principles of this application should be included in the protection scope of this application.

Claims

1. A method for material transportation control, characterized in that: The method is applied to a programmable logic controller of a first system, and the method comprises: In response to a selection operation of a first transport process, determining, based on a first process matrix table and the first transport process, an association between the first transport process and a selected second transport process; wherein the first process matrix table is constructed based on the transport equipment of the first system and the preset transport process of the first system; In response to the association between the first transport process and the selected second transport process satisfying a preset association condition, obtaining identification information of a system shared device of the first transport process; the preset association condition includes that transport devices of different transport processes do not conflict with each other; Based on the identification information of the system shared device, the occupation status information of the system shared device in the second system is obtained, wherein the occupation status information of the system shared device in the second system is the first status information sent by the second system to the first system in real time, and the first status information is determined based on the second process matrix table and the identification information of the system shared device; the second process matrix table is constructed based on the transportation equipment of the second system and the preset transportation process of the second system; In response to the occupancy status information being unoccupied, determining the first transport process and the second transport process as target transport processes; Based on the target transportation process, the transportation equipment in the target transportation process is controlled to transport the material according to the target transportation process.

2. The method according to claim 1, characterized in that In response to the selection operation of the first transport process, determining the association between the first transport process and the selected second transport process based on the first process matrix table and the first transport process, includes: Determine the number of operations of the first transportation process based on the first process matrix table and the first transportation process; Determine the number of operations of the second transportation process based on the first process matrix table and the selected second transportation process; Based on the number of operations of the first transport process and the number of operations of the second transport process, the association between the first transport process and the selected second transport process is determined.

3. The method according to claim 2, characterized in that The determining, based on the operand of the first transport process and the operand of the second transport process, the association between the first transport process and the selected second transport process includes: determining an association status value based on the number of operations of the first transport process and the number of operations of the second transport process; Based on the association status value, an association status between the first transport process and the selected second transport process is determined.

4. The method according to claim 1, characterized in that: The method further comprises: In response to the association between the first transport process and the selected second transport process not satisfying a preset association condition, acquiring an operation number of the first transport process and an operation number of the second transport process based on the first process matrix table; Calculating a reference value based on the number of operations of the first transport process and the number of operations of the second transport process; Based on the equipment position number and reference value of the first process matrix table, the process sharing equipment of the first transportation process and the second transportation process is determined using a preset process sharing equipment identification algorithm.

5. The method according to claim 1, characterized in that The controlling, based on the target transportation process, of the transportation equipment in the target transportation process to transport the material according to the target transportation process comprises: Based on the first process matrix table and the target transportation process, obtaining an operation number of the target transportation process; Based on the operand, controlling the transport equipment in the target transport process to transport the material according to the target transport process; Output the operation status information of the first transportation process.

6. A method for material transportation control, characterized in that: The method is applied to a programmable logic controller of a second system, and the method comprises: In response to the selection operation of the third transport process, based on the second process matrix table and the third transport process, determining the association between the third transport process and the selected fourth transport process; wherein the second process matrix table is constructed based on the transport equipment of the second system and the preset transport process of the second system; In response to the association between the third transport process and the selected fourth transport process satisfying a preset association condition, obtaining identification information of a system shared device of the third transport process; the preset association condition includes that transport devices of different transport processes do not conflict with each other; Based on the identification information of the system shared device, the occupation status information of the system shared device in the first system is obtained, wherein the occupation status information of the system shared device in the first system is second status information sent by the first system to the second system in real time, and the second status information is determined based on the first process matrix table and the identification information of the system shared device; the first process matrix table is constructed based on the transportation equipment of the first system and the preset transportation process of the first system; In response to the occupancy status information being unoccupied, determining the third transport process and the fourth transport process as target transport processes; Based on the target transportation process, the transportation equipment in the target transportation process is controlled to transport the material according to the target transportation process.

7. A device for controlling material transportation, characterized in that: Applied to a first system programmable logic controller, the device comprises: A first selection unit, configured to determine, in response to a selection operation on a first transport process, an association between the first transport process and a selected second transport process based on a first process matrix table and the first transport process; wherein the first process matrix table is constructed based on the transport equipment of the first system and a preset transport process of the first system; A first acquisition unit is used to acquire identification information of a system shared device of the first transport process in response to the association between the first transport process and the selected second transport process satisfying a preset association condition; the preset association condition includes that transport devices of different transport processes do not conflict with each other; A first obtaining unit is configured to obtain occupation status information of the system shared device in the second system based on the identification information of the system shared device, wherein the occupation status information of the system shared device in the second system is first status information sent by the second system to the first system in real time, and the first status information is determined based on a second process matrix table and the identification information of the system shared device; and the second process matrix table is constructed based on the transportation equipment of the second system and a preset transportation process of the second system; a first determining unit, configured to determine, in response to the occupancy status information being unoccupied, the first transport process and the second transport process as target transport processes; The first control unit is used to control the transportation equipment in the target transportation process to transport the material according to the target transportation process based on the target transportation process.

8. A material transport control device, characterized in that: Applied to a second system programmable logic controller, the device comprises: A second selection unit is used to determine, in response to a selection operation of a third transport process, an association between the third transport process and a selected fourth transport process based on a second process matrix table and the third transport process; wherein the second process matrix table is constructed based on the transport equipment of the second system and a preset transport process of the second system; a second acquisition unit, configured to acquire identification information of a system shared device of the third transport process in response to the association between the third transport process and the selected fourth transport process satisfying a preset association condition; the preset association condition includes that transport devices of different transport processes do not conflict with each other; A second obtaining unit is configured to obtain occupation status information of the system shared device in the first system based on the identification information of the system shared device, wherein the occupation status information of the system shared device in the first system is second status information sent by the first system to the second system in real time, and the second status information is determined based on a first process matrix table and the identification information of the system shared device; the first process matrix table is constructed based on the transportation equipment of the first system and a preset transportation process of the first system; a second determining unit, configured to determine, in response to the occupancy status information being unoccupied, the third transport process and the fourth transport process as target transport processes; The second control unit is used to control the transportation equipment in the target transportation process to transport the material according to the target transportation process based on the target transportation process.

9. A material transportation control system, characterized in that: The material transportation control system includes a first system and a second system, wherein the first system includes a programmable logic controller and a transportation device, and the second system includes a programmable logic controller and a transportation device; The programmable logic controller of the first system is used to control the transportation equipment in the first system to transport the material according to the method according to any one of claims 1 to 5; The programmable logic controller of the second system is used to control the transportation equipment in the second system to transport the material according to the method according to claim 6.

10. A non-transitory computer-readable storage medium storing computer instructions, wherein: The computer instructions are used to cause the computer to execute the method according to any one of claims 1-6.

Citation Information

Patent Citations

  • Method for controlling and judging process conflict by using INUSE matrix

    CN110597195A

  • Optimal dynamic selection method for raw material yard conveying belt process

    CN111522316A

  • Intelligent scheduling method for multi-bin-group combined feeding

    CN112269363A

  • Scheduling system and method based on metallurgical intelligent raw material field production process plan

    CN115545391A

  • Belt unmanned transportation control method and device, electronic equipment and storage medium

    CN116050981A