Method for dividing dike plugging stages based on flow and head difference
By establishing a grading model of the blocking stage and a coupling determination model of flow and head difference, the problem of low division efficiency in the emergency construction stage of embankment breach in the existing technology is solved, and the rapid division and quantitative classification of the embankment breach sealing construction stage is achieved, which is short The rapid rescue of dikes during the window period provides scientific basis.
Patent Information
- Application Number
- CN202411107198.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-13
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-13
AI Technical Summary
In the prior art, the dike breach emergency construction stage is inefficient, which affects the breach emergency speed, and it is difficult to quickly deal with the difficulty of blocking the hole and the flood loss caused by different breach flow and head differences.
The method of dike blocking stage division based on flow and head difference is adopted. By establishing a hike stage classification model, a coupling determination model of flow and head difference and a partition model of the blocking seal implementation stage, the rapid division and quantification of the embankment breach emergency construction stage is achieved. Grading.
The rapid division of embankment breach sealing construction stage and quantitative classification of difficulty levels are achieved, and the scientific basis for rapid rescue of embankments during the short window period is provided, and it is suitable for the division of all river embankment blocking stages.
Smart Images

Figure CN118627180B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of river embankment emergency rescue, in particular to a method for dividing embankment plugging stages based on flow and water head difference. Background Art
[0002] The difficulty of plugging a dike breach and the losses caused by the burst flood vary depending on the breach flow and the difference in water head inside and outside the dike. How to quickly divide the plugging and rescue construction stages is directly related to the success or failure of the plugging.
[0003] In the prior art, the emergency rescue construction phases are usually divided by drawing on existing experience and comparing with the cases of dike breaches that have occurred. This method is inefficient and seriously affects the speed of breach rescue.
[0004] Therefore, the applicant considered proposing a method for dividing the dike plugging stages based on flow and head difference, so as to achieve rapid division of the construction stages of dike breach rescue and provide a scientific basis for rapid dike rescue in a short window period. Summary of the invention
[0005] The purpose of the present invention is to address the deficiencies of the above-mentioned prior art and provide a method for dividing the dike breach plugging stages based on flow and head difference. By establishing a plugging stage classification model, a flow and head difference coupling judgment model, and a plugging implementation stage division model, the rapid division of the dike breach plugging construction stages can be achieved, providing a scientific basis for rapid dike rescue in a short window period.
[0006] To achieve the above purpose, the technical solution adopted by the present invention is as follows:
[0007] A method for dividing dike plugging stages based on flow and head difference comprises the following steps:
[0008] Establish a plugging stage classification model, and divide the plugging stage into single plugging stage, double plugging stage, and multiple plugging stages;
[0009] A flow rate and head difference coupling judgment model is established, and the difficulty of plugging and sealing is graded based on the flow rate and head difference; the flow rate is the dike breach flow rate, and the head difference is the head difference inside and outside the dike;
[0010] Based on the plugging stage classification model and the flow and head difference coupling judgment model, a plugging implementation stage division model is constructed to realize the embankment plugging stage division, and corresponding plugging measures are selected based on the divided plugging stages;
[0011] The blocking stage is the emergency rescue construction stage for the embankment breach.
[0012] Preferably, the plugging stage classification model is:
[0013] ;
[0014] in, M It is the model set of the plugging stage; M 1 is the single-stage plugging model; M 2 is the double-stage plugging model; M 3 is the multi-stage plugging model; m 1 = blocking measures; m 2 = dike filling measures; m 3 = Shipwreck measures, m 4 = Backfill measures, m 5=Measures to block the mouth and seal the air.
[0015] Preferably, the flow rate and head difference coupling determination model includes a classification operator and a quantization operator.
[0016] Preferably, the model of the classification operator is:
[0017]
[0018] in, is a classification operator; is the water head difference between the inside and outside of the dike, in m; Q is the dike breach flow, unit: m 3 / s; among them, Grade I corresponds to low difficulty in plugging breaches, Grade II corresponds to medium difficulty in plugging breaches, and Grade III corresponds to high difficulty in plugging breaches; the classification is based on the difference in water head inside and outside the levee. and dike breach flow Q Conducted , In general, the head difference between the inside and outside of the levee at each level is and dike breach flow Q The conditions will be met at the same time. If they are not met at the same time, the water head difference inside and outside the levee will be used. Classification as a priority condition.
[0019] Preferably, the model of the quantization operator is:
[0020] ;
[0021] in, is the quantization operator, H 1 is the elevation of the water surface inside the dike, in m; H 2 is the elevation of the water surface outside the dike, in meters; b is the average width of the breach, in m; g is the acceleration of gravity, in m 2 / s; α is the shape factor.
[0022] Preferably, the shape factor α The values of are as follows:
[0023] .
[0024] Preferably, the plugging and sealing implementation stage division model is:
[0025] .
[0026] Compared with the prior art, the present invention has the following beneficial effects:
[0027] The present invention realizes the quantification of the plugging construction stages and the quantitative grading of the difficulty of breach plugging based on the established plugging stage classification model and the flow rate and water head difference coupling judgment model.
[0028] The present invention is based on the established model for dividing the implementation stages of the plugging and sealing, and can quickly divide the construction stages of any dike breach rescue. When it is judged that the breach plugging belongs to a single-stage plugging model according to the model, the plugging and sealing measures can be immediately adopted to achieve the breach plugging. When it is judged to belong to a two-stage plugging model, the dike filling is implemented first, and then the plugging and sealing are implemented; when it is judged to belong to a multi-stage plugging model, the five steps of shipwreck, dike filling, plugging and sealing, back dike filling, and plugging and sealing are implemented in sequence to achieve the breach plugging. The present invention will provide a scientific basis for the rapid rescue of dikes in a short window period.
[0029] The method developed has good applicability and is suitable for the division of all river embankment blocking stages. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a design flow chart of the dike plugging stage division method based on flow and head difference of the present invention. DETAILED DESCRIPTION
[0031] The following is a detailed description of the implementation of the present invention in conjunction with the accompanying drawings, but they do not constitute a limitation of the present invention and are only given as examples. At the same time, the advantages of the present invention will become clearer and easier to understand through the description.
[0032] See also Figure 1 It can be seen that the dike plugging stage division method based on flow and head difference of the present invention includes the following steps:
[0033] 1) Establish a classification model for the plugging stage
[0034] The plugging stage classification model is used to quantify the plugging construction stage. The plugging stage classification model is as follows:
[0035] ;
[0036] Where: M is the plugging stage model set, including 3 subsets, namely M 1 is the single-stage plugging model.M 2 is the double-stage plugging model. M 3 is a multi-stage plugging model. M 1 includes a single element m 1, that is m 1=Block and seal. M 2Sets include double elements m 1 and m 2, m 1 Ibid. m 2=Dike filling. M 3 consists of 5 elements m 1. m 2. m 3. m 4 and m 5. m 1 and m 2 Ibid. m 3 = Shipwreck, m 4 = Back platform filling, m 5 = blocking the breach. This model can be used to quantify the construction phase of any dike breach.
[0037] 2) Establish a flow and head difference coupling judgment model
[0038] The coupled determination model of flow and head difference includes the classification operator and quantization operator According to this model, the breach flow can be Q and head difference The calculation can realize the quantitative classification of the difficulty of breach plugging. The coupling judgment model of flow and head difference is as follows:
[0039] ;
[0040] Where: It is a hierarchical operator, which is divided into three levels. is the water head difference between the inside and outside of the dike, in m; Q is the dike breach flow, unit: m 3 / s; among them, level I corresponds to low difficulty in plugging the breach, level II corresponds to medium difficulty in plugging the breach, and level III corresponds to high difficulty in plugging the breach. is the quantization operator, H 1 is the elevation of the water surface inside the dike, in m; H 2 is the elevation of the water surface outside the dike, in meters; b is the average width of the breach, in m; g is the acceleration of gravity, in m 2 / s; α is the shape factor, and its value is as follows:
[0041] .
[0042] The quantitative classification of the difficulty of breach sealing is based on the head difference between the inside and outside of the levee. and dike breach flow Q To be graded , In general, the head difference between the inside and outside of the levee at each level is and dike breach flow Q The conditions will be met at the same time; if in extreme cases, the conditions are not met at the same time, then the water head difference inside and outside the levee As a priority condition. For example, when < 1m, but 20m 3 / s≤ Q< 100m 3 / s, the water head difference between the inside and outside of the dike As a classification condition, this case is classified as Class I.
[0043] 3) Establish a model for dividing the implementation stages of plugging and sealing
[0044] Based on the established plugging stage classification model and the flow and head difference coupling judgment model, a plugging implementation stage division model is constructed to achieve rapid division of any embankment breach rescue construction stages, providing a scientific basis for rapid embankment rescue in a short window period.
[0045] ;
[0046] Where: M x : A model for dividing the stages of any dike breach plugging. Less than 1m, and the breach flow Q Less than 20m 3 / s, that is = Level I, at this time, the dike breach blocking belongs to the single-stage blocking model, that is, M x = M 1. Since the head difference and flow rate are small, direct implementation m 1 = plugging, the breach can be plugged. Greater than or equal to 1m and less than 2m, and breach flow Q Greater than or equal to 20m 3 / s and less than 100m 3 / s, that is = Level II, at this time, the dike breach blocking belongs to the two-stage blocking model, that is, M x = M 2. First, implement it at the location with low flow velocity on the upstream surface. m 2 = Fill the dike to reduce the head difference and flow at the breach, and then implementm 1 = plugging; when the head difference is calculated Greater than or equal to 2m, and the breach flow Q Greater than or equal to 100m 3 / s, that is = Level III, at this time, the embankment breach blocking belongs to the multi-stage blocking model, that is, M x = M 3. Due to the large flow rate and head difference of the breach, the breach plugging needs to be carried out in sequence m 3 = Shipwreck, m 2 = dike filling, m 1 = Block the mouth, m 4 = Back platform filling, m 5=It takes 5 steps to seal the ulcer.
[0047] Other parts not described belong to the prior art.
Claims
1. A method for dividing dike plugging stages based on flow and head difference, characterized in that: The following steps are involved: A plugging stage classification model is established to divide the plugging stage into single plugging stage, double plugging stage and multiple plugging stages; the plugging stage classification model is: ; in, M It is the model set of the plugging stage; M 1 is the single-stage plugging model; M 2 is the double-stage plugging model; M 3 is the multi-stage plugging model; m 1 = blocking measures; m 2 = dike filling measures; m 3 = Shipwreck measures, m 4 = Backfill measures, m 5= blocking and airtight measures; A flow rate and head difference coupling judgment model is established, and the difficulty of plugging is graded based on the flow rate and head difference; the flow rate is the dike breach flow rate, and the head difference is the head difference inside and outside the dike; the flow rate and head difference coupling judgment model includes a classification operator and a quantization operator, and the model of the classification operator is: in, is a classification operator; is the water head difference between the inside and outside of the dike, in m; Q is the dike breach flow, unit: m 3 / s; among them, level I corresponds to low difficulty in plugging the breach, level II corresponds to medium difficulty in plugging the breach, and level III corresponds to high difficulty in plugging the breach; The model of the quantization operator is: ; in, is the quantization operator, H 1 is the elevation of the water surface inside the dike, in m; H 2 is the elevation of the water surface outside the dike, in meters; b is the average width of the breach, in m; g is the acceleration of gravity, in m 2 / s; α is the shape factor; Based on the plugging stage classification model and the flow and head difference coupling judgment model, a plugging implementation stage division model is constructed to realize the embankment plugging stage division, and the corresponding plugging measures are selected based on the divided plugging stages; the plugging implementation stage division model is: 。 2. The method for dividing dike plugging stages based on flow and head difference according to claim 1 is characterized by: In the classification operator, the classification is based on the head difference between the inside and outside of the dike. and dike breach flow Q Conducted , In general, the head difference between the inside and outside of the levee at each classification is and dike breach flow Q The conditions will be met at the same time. If they are not met at the same time, the water head difference inside and outside the levee will be used. Classification as a priority condition.
3. The method for dividing dike plugging stages based on flow and head difference according to claim 1 is characterized by: The shape factor α The values of are as follows: 。