Method and system for detecting output connection line of off-grid output port of inverter parallel system

By synchronizing the adjustment of the inverter master and slave before the parallel system output of the energy storage inverter, sampling and integration, identifying the connection line error of the off-grid output port, the detection hysteresis in the prior art is solved and the problem of confusing functions have achieved efficient wiring error recognition and improved system stability.

CN118642008BActive Publication Date: 2024-11-15SHENZHEN POWEROAK NEWENER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411124188.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-15
Estimated Expiration
2044-08-16

AI Technical Summary

Technical Problem

The existing energy storage inverter parallel system performs off-grid output port connection line detection after outputting power, which may lead to missed detection, resulting in system function operation or device damage.

Method used

Before the inverter parallel system outputs power, the inverter master and slave adjustment are synchronized, and the RST three-phase preset voltage adjustment period and target waveform are successively performed on single-phase voltage adjustment, sampling and integration, according to the integral value and target The range determines the connection line detection result and identifies the wiring error type.

Benefits of technology

It realizes fully automated pre-detection of the off-grid output port connection line of the inverter parallel system, accurately identify abnormal working conditions, avoids system functions and device damage, and improves installation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118642008B_ABST
    Figure CN118642008B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and system for detecting an output connection line of an off-grid output port of an inverter parallel system, wherein the method comprises: an inverter host and an inverter slave perform adjustment synchronization; after completing the adjustment synchronization, the inverter host sequentially performs single-phase voltage adjustment on one or more phases of the RST three-phase according to a preset voltage adjustment cycle and a preset target waveform; the inverter slave samples and integrates the three-phase load voltage on the inverter slave side during each single-phase voltage adjustment, and obtains the three-phase load voltage integral value corresponding to each single-phase voltage adjustment; the inverter slave or the inverter host determines the detection result according to the three-phase load voltage integral value corresponding to each single-phase voltage adjustment and the preset three-phase load voltage target range corresponding to each single-phase voltage adjustment. The method of the present invention not only effectively avoids the problem of confusion in the function operation of the system and even damage to the device, but also improves the work efficiency of the installer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of energy storage technology, and in particular to a method and system for detecting an output connection line of an off-grid output port of an inverter parallel system. Background Art

[0002] In order to meet the market demand for flexible expansion of energy storage inverters, inverter parallel technology came into being. In the inverter parallel system, it is very important to accurately connect the output connection lines between multiple inverter parallel modules, especially the output connection lines of the off-grid output port, which is the basis for the normal operation of the inverter parallel system. For off-grid and off-grid integrated inverter parallel systems, there are mainly the following three types of wiring errors and adverse consequences:

[0003] (1) In-phase disconnection: The common wiring of the same-phase output between different modules is disconnected. This situation will cause serious uneven output of each module within the system. If it cannot be quickly identified, it will have an adverse effect on the machine itself and the load.

[0004] (2) Short circuit between different phases: There is a short circuit between the phases of a single module. This may cause serious overcurrent when the machine starts, and if protection is not timely, the inverter components may be damaged.

[0005] (3) Phase sequence confusion: The output lines of different phase sequences between different modules are connected incorrectly. In this case, the system output will cause the output voltages of different phases to be short-circuited together, causing serious consequences.

[0006] The existing energy storage inverter parallel system mainly relies on the standardized operation of on-site installers, combined with inherent accessories such as distribution boxes, to avoid the problem of wiring errors at the off-grid output port. The detection of the output connection line of the off-grid output port is mostly carried out after the system outputs power. Since there is already a large voltage at the output end of the system after the parallel inverter system outputs power. For wiring errors of short circuits between the same phases, it may not be detected when the system phase is not loaded or only loaded with a small load, resulting in missed detection. For the other two wiring errors, it may cause confusion in the function operation of the system or even damage to the device.

[0007] Therefore, it is very important to effectively and proactively identify wiring errors in the output connection lines of the off-grid output port before the parallel inverter system outputs power. Summary of the invention

[0008] The embodiments of the present invention aim to provide a method and system for detecting the output connection line of the off-grid output port of an inverter parallel system, so as to solve the problem in the prior art that the output connection line detection of the off-grid output port of the inverter parallel system is performed after the parallel inverter system outputs power, which may cause missed detection, confusion in system function operation, and even damage to components.

[0009] To solve the above technical problems, the embodiments of the present invention provide the following technical solutions:

[0010] According to one aspect of the present invention, a method for detecting an output connection line of an off-grid output port of an inverter parallel system is provided. The method is performed before the inverter parallel system outputs power, and the method comprises:

[0011] Step A, the inverter master and the inverter slave are adjusted and synchronized;

[0012] Step B, after completing the regulation synchronization, the inverter host sequentially performs single-phase voltage regulation on one or more phases of the three phases RST according to a preset voltage regulation cycle and a preset target waveform;

[0013] Step C, the inverter slave samples and integrates the three-phase load voltage on the inverter slave side during each single-phase voltage regulation to obtain the three-phase load voltage integral value corresponding to each single-phase voltage regulation;

[0014] Step D, the inverter slave or inverter master determines the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each single-phase voltage regulation and the preset three-phase load voltage target range corresponding to each single-phase voltage regulation.

[0015] Optionally, step D comprises:

[0016] The inverter slave or inverter master compares the three-phase load voltage integral value corresponding to each single-phase voltage regulation with the three-phase load voltage target range corresponding to the single-phase voltage regulation based on the same phase. If the number of times that the single-phase load voltage integral value is not within the single-phase load voltage target range exceeds the preset alarm threshold, it is determined that there is an abnormality in the output connection line of the off-grid output port of the inverter parallel system.

[0017] Optionally, when the single-phase load voltage integral value is not within the single-phase load voltage target range, the method further includes:

[0018] The inverter slave or the inverter master records the regulated single phase as an abnormal single phase when the load voltage integral value of the single phase is not within the load voltage target range of the single phase;

[0019] After the inverter slave determines that an output connection line of the off-grid output port of the inverter parallel system is abnormal, the method further includes:

[0020] The inverter slave or inverter master compares the three-phase load voltage integral value corresponding to the single-phase voltage regulation based on the abnormal single phase with the load voltage target range corresponding to the abnormal single phase based on the single-phase voltage regulation based on the abnormal single phase to determine the type of wiring error.

[0021] Optionally, determining the type of wiring error includes:

[0022] During the single-phase voltage regulation based on the abnormal single-phase, if there is no single-phase load voltage integral value among the three-phase load voltage integral values ​​that meets the load voltage target range corresponding to the abnormal list, the type of the wiring error is judged to be a short circuit; if there are multiple single-phase load voltage integral values ​​among the three-phase load voltage integral values ​​that meet the load voltage target range corresponding to the abnormal list, the type of the wiring error is judged to be a short circuit; if there is a single-phase load voltage integral value among the three-phase load voltage integral values ​​that meets the load voltage target range corresponding to the abnormal list, and the compliant single phase is different from the abnormal single phase, the type of the wiring error is judged to be a phase sequence disorder.

[0023] Optionally, step A comprises:

[0024] The inverter master sends a readiness adjustment synchronization signal to the inverter slave through the CAN bus to perform adjustment synchronization.

[0025] Optionally, the target waveform is a preset band on a standard sinusoidal voltage periodic waveform.

[0026] Optionally, the preset band includes a first band corresponding to a preset time length before the positive zero crossing point on the standard sinusoidal voltage periodic waveform and a second band corresponding to the preset time length after the positive zero crossing point, and the preset time length is much shorter than the period of the standard sinusoidal voltage.

[0027] Optionally, the target waveform includes multiple bands, and step C further includes:

[0028] During each single-phase voltage regulation period, the inverter slave machine samples and integrates the three-phase load voltage on the inverter slave machine side based on each band of the target waveform, and obtains the three-phase load voltage integral value corresponding to each band of the target waveform for each single-phase voltage regulation;

[0029] The step D also includes:

[0030] The inverter slave or inverter master determines the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each band of the target waveform for each single-phase voltage adjustment and the preset three-phase load voltage target range corresponding to each band of the target waveform for each single-phase voltage adjustment.

[0031] According to another aspect of the present invention, there is provided an inverter parallel system, the system comprising an inverter master and a plurality of inverter slaves, wherein the inverter master and the plurality of inverter slaves are both provided with an off-grid output port;

[0032] The inverter master is used to perform regulation synchronization with the inverter slave before the system outputs power, and after completing the regulation synchronization, sequentially perform single-phase voltage regulation on one or more phases of the three phases RST according to a preset voltage regulation cycle and a preset target waveform;

[0033] The inverter slave is used to sample and integrate the three-phase load voltage on the inverter slave side during each single-phase voltage regulation to obtain the three-phase load voltage integral value corresponding to each single-phase voltage regulation;

[0034] The inverter slave or the inverter master is also used to determine the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each single-phase voltage regulation and the preset three-phase load voltage target range corresponding to each single-phase voltage regulation.

[0035] According to another aspect of the present invention, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program. When the computer program is executed by a processor, the processor executes the steps of the above-mentioned method for detecting an output connection line of an off-grid output port of an inverter parallel system.

[0036] The beneficial effects of the embodiments of the present invention are as follows: Different from the prior art, in the embodiments of the present invention, a method for detecting the output connection line of the off-grid output port of the inverter parallel system is provided, which is executed before the inverter parallel system outputs power, and can avoid the problem of confusion in the function operation of the system or even damage to the device. When performing the detection, the inverter host and the inverter slave first perform adjustment synchronization. After completing the adjustment synchronization, the inverter host sequentially performs single-phase voltage regulation on one or more phases of the three-phase RST according to a preset voltage regulation cycle and a preset target waveform; the inverter slave samples and integrates the three-phase load voltage on the inverter slave side during each single-phase voltage regulation, and obtains the three-phase load voltage integral value corresponding to each single-phase voltage regulation; finally, the inverter slave or the inverter host determines the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each single-phase voltage regulation and the preset three-phase load voltage target range corresponding to each single-phase voltage regulation. The detection method of the present invention is a fully automated pre-detection method performed before the inverter parallel system outputs. It is highly targeted and can accurately identify various abnormal working conditions. It not only effectively avoids the problem of system functional operation confusion or even device damage, but also improves the work efficiency of installers. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] One or more embodiments are exemplarily described by pictures in the corresponding drawings, and these exemplified descriptions do not constitute limitations on the embodiments. Elements with the same reference numerals in the drawings represent similar elements, and unless otherwise stated, the figures in the drawings do not constitute proportional limitations.

[0038] Figure 1 This is a wiring diagram when the off-grid output port wiring error is a disconnection between the same phases provided by an embodiment of the present invention;

[0039] Figure 2 This is a wiring diagram when the wiring error of the off-grid output port provided by the embodiment of the present invention is a short circuit between different phases;

[0040] Figure 3 This is a wiring diagram when the off-grid output port wiring error is a phase sequence disorder provided by an embodiment of the present invention;

[0041] Figure 4 is a schematic diagram of a communication architecture of an inverter parallel system provided in an embodiment of the present invention;

[0042] Figure 5 1 is a schematic diagram of an equivalent circuit of an R-phase load voltage sampling position and an output position in an inverter parallel system provided by an embodiment of the present invention;

[0043] Figure 6 is a flow chart of a method for detecting an output connection line of an off-grid output port of an inverter parallel system provided by an embodiment of the present invention;

[0044] Figure 7 It is a schematic diagram of the execution timing of the output connection line detection method of the off-grid output port of the inverter parallel system provided by an embodiment of the present invention;

[0045] Figure 8 It is a schematic diagram of a target waveform for voltage regulation provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0046] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0047] In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0048] It should be noted that the steps shown in the flowcharts of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and that, although a logical order is shown in the flowcharts, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0049] The present invention aims at the situation that the output connection line of the off-grid output port of the off-grid or off-grid integrated inverter parallel system may have wiring errors in actual application scenarios, and proposes an output connection line detection method for the off-grid output port of the inverter parallel system. The detection method is based on a fast communication path in the inverter parallel system, and on the basis of the original hardware, a pure software detection method is used to realize the detection of various wiring errors of the output connection line of the off-grid output port.

[0050] See also Figures 1 to 3 , which are three specific error conditions that need to be identified in practical applications.

[0051] 1) Interphase disconnection

[0052] like Figure 1 As shown, point A is the connection point between the master-slave common connection line and the load output line. The R-phase common connection line of the master-slave is broken, resulting in the load power being provided by only one module, causing the actual capacity of the system to be halved. When the expected load with the same capacity as the parallel system is actually put into use, the module that solely undertakes the output task will be overloaded.

[0053] In addition to the halving of capacity, this situation will also cause the problem of unstable output voltage. When the circuit breaker is on the left side of point A, the system will be solely borne by the slave for all outputs. At this time, since the system adopts the droop control method of the slave following the host for active power averaging, the slave will automatically reduce its own output voltage in the hope of achieving power sharing with the host. Since the output line from the host to the load is broken, the power is always impossible to be averaged. If the load input is large, the slave voltage will be adjusted to an unreasonable low value, and even trigger a fault. When the circuit breaker is on the right side of point A, the system will be solely borne by the host for all outputs. At this time, the slave has never output power. In order to make the master and slave power evenly shared, the slave will actively increase the output voltage. If the load input is large, the slave voltage will be adjusted to an unreasonable high value until a fault is triggered.

[0054] 2) Short circuit between different phases

[0055] like Figure 2As shown in the figure, the R and S phases of the system common connection line are short-circuited, which makes the R and S phase outputs of the master and slave form a common loop with the R and S phases of the load, that is, the dotted part in the figure. Since the fault location is outside the single module (inverter master or inverter slave), the single module cannot be detected. When the master and slave close the load relay at the same time for output, the voltages of different phases will be short-circuited together, and the output common port will generate severe distorted voltage and peak current, which will have adverse effects on the inverter and the connected load.

[0056] 3) The phase sequence is confusing

[0057] like Figure 3 As shown, the common connection line between the host and the slave is partially wired in a disordered manner, and the corresponding phases are not connected in sequence. If the voltage output of each inverter in the inverter parallel system has been phase synchronized, the same-phase inverter voltage adjusted by the master and slave is consistent before the load relay is released. Therefore, at this stage, the inverter parallel system cannot determine the wiring condition of the inverter output connection line by comparing the same-phase voltage of the master and slave. If the load relay is closed without being identified, a cross-phase short circuit will result. If the host in the system has already output off-grid voltage, and the slave follows the output in the phase mode of following the sampled common contact voltage when joining, the system will cause functional confusion or even device damage due to mismatch of control loop input parameters.

[0058] See also Figure 4 , which is a schematic diagram of the communication architecture of an inverter parallel system provided in an embodiment of the present invention. The inverter parallel system includes an inverter host and a plurality of inverter slaves. Among them, the control architecture of the inverter host and the inverter slaves are composed of DSP (Digital Signal Processor) + ARM (Advanced RISC Machines). Fast communication is achieved between the single-module DSP and ARM through CAN (Controller Area Network). The second CAN of the DSP constitutes a bus, which connects the sub-modules in the inverter parallel system and realizes data interaction.

[0059] The inverter master is used to perform regulation synchronization with the inverter slave before the system outputs power. After the regulation synchronization is completed, single-phase voltage regulation is performed on one or more phases of the RST three-phase according to a preset voltage regulation cycle and a preset target waveform.

[0060] The inverter slave is used to sample and integrate the three-phase load voltage on the inverter slave side during each single-phase voltage regulation to obtain the three-phase load voltage integral value corresponding to each single-phase voltage regulation.

[0061] The inverter master or inverter slave is also used to determine the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each single-phase voltage regulation and the preset three-phase load voltage target range corresponding to each single-phase voltage regulation.

[0062] See also Figure 5 , is a schematic diagram of the equivalent circuit of the R-phase load voltage sampling position and output position in the inverter parallel system provided by the embodiment of the present invention. An LC filter is used at the output end of each inverter, and the voltage of the DSP sampling capacitor C1 or C2 is used as feedback for inverter voltage regulation, and the load voltage is sampled by ARM. Among them, the load voltage sampling point is located at the outer end of the load relay, and the load relay is located outside the filter.

[0063] From the structure of the output terminal and the sampling position, it can be seen that when there is a problem with the load relay, it may affect the judgment of the output connection line. In addition, if the slave load relay is also energized at the same time, the filter circuits of the master and slave will be connected together. When the host outputs alone, the change in the filter structure will have a certain impact. Based on the above considerations, the load voltage can be used as the basis for judgment, and only the load relay of the host is energized.

[0064] See also Figure 6 , is a flow chart of a method for detecting an output connection line of an off-grid output port of an inverter parallel system provided in an embodiment of the present invention. The method is executed before the inverter parallel system outputs power, and specifically comprises the following steps:

[0065] Step S601: the inverter master and the inverter slave are regulated and synchronized.

[0066] After the inverter host is turned on, the chip and CAN communication are initialized first, and then it is determined whether the detection completion flag is set. If not, the output connection line detection is ready. At this time, the inverter parallel system has not started normally, that is, the inverter parallel system has not output power. Before the detection, the inverter host closes the load relay on the host side and waits for the load relay to be fully energized. The inverter slave may not close the load relay on the slave side (that is, when the detection is performed, the load relay on the inverter host side is in a closed state and the load relay on the inverter slave side is in a non-closed state).

[0067] like Figure 7As shown, after completing the above operations, the inverter host and the inverter slave perform adjustment synchronization and determine the voltage adjustment start time point respectively. In one embodiment, the inverter host sends a ready adjustment synchronization signal to the inverter slave through the CAN bus to perform adjustment synchronization, and the inverter host and the inverter slave respectively determine the voltage adjustment start time point based on the sending time and receiving time of the ready adjustment synchronization signal and the communication delay between the inverter host and the inverter slave. Specifically, the inverter host sets t S +T wait The time point is determined as the starting time point of voltage regulation, and the inverter slave sets t R + (T wait -T delay ) is determined as the starting time point of voltage regulation. S In order to prepare to adjust the sending time of the synchronization signal, t R To prepare for adjusting the reception time of the synchronization signal, T wait is the preset synchronization waiting time, T delay It is the communication delay between the inverter master and inverter slave.

[0068] In other embodiments, the adjustment synchronization may be performed in other ways. For example, other devices simultaneously send a readiness adjustment synchronization signal to the inverter master and the inverter slave, and after the inverter master and the inverter slave receive the readiness adjustment synchronization signal, the same waiting time is added to the reception time of the readiness adjustment synchronization signal as the voltage adjustment start time point.

[0069] Step S602, after completing the regulation synchronization, the inverter host sequentially performs single-phase voltage regulation on one phase or multiple phases of the RST three phases according to a preset voltage regulation cycle and a preset target waveform.

[0070] In some embodiments, starting from the voltage regulation start time point, the inverter host sequentially performs single-phase voltage regulation for the R phase, S phase and T phase several times according to a preset voltage regulation cycle and a preset target waveform. Preferably, the voltage regulation cycle is the same as the power frequency voltage cycle. Figure 7 As shown, the inverter host sequentially performs single-phase voltage regulation five times on the R phase, S phase and T phase according to a 20ms interval period (corresponding to a 50Hz power frequency voltage period), and the total voltage regulation time for each single phase is 100ms. In other embodiments, the inverter host performs single-phase voltage regulation several times on one or two single phases of the R phase, S phase and T phase according to a preset voltage regulation period and a preset target waveform.

[0071] In order to avoid the influence of the regulated pulse voltage on the load at the output end, the target waveform preferably has a waveform with a smaller pulse regulation voltage and a pulse regulation time much shorter than the voltage regulation period. In one embodiment, the target waveform is a preset band on a standard sinusoidal voltage cycle waveform. The preset band includes a first band corresponding to a preset time before the positive zero crossing point on the standard sinusoidal voltage cycle waveform and a second band corresponding to the preset time after the positive zero crossing point, and the preset time length is much shorter than the period of the standard sinusoidal voltage. Preferably, the preset time length is selected within 0.0005s~0.001s. For example, the preset band is a band of 0.001s before and after the positive zero crossing point on the standard sinusoidal voltage cycle waveform. Figure 8 As shown, a band corresponding to the horizontal axis time from -0.001 seconds to 0.001 seconds is selected on the standard sinusoidal voltage cycle waveform as the target waveform for each single-phase voltage regulation of the inverter host.

[0072] When the inverter host performs single-phase voltage regulation according to the target waveform, it is also used to detect the load voltage and inverter voltage on the inverter host side to ensure that the load relays of each phase on the inverter host side will not cause additional interference to the detection results. For example, when the host load voltage and the host inverter voltage are close, it indicates that the load relay on the host side has been normally energized, and when the host load voltage and the host inverter voltage differ greatly, it indicates that the load relay on the host side has not been energized or has failed. When the latter situation occurs, the inverter host notifies the inverter slave to exit the current detection process, ensure that the load relay is normally energized and can work normally, and then restart the detection.

[0073] Step S603: the inverter slave samples and integrates the three-phase load voltage on the inverter slave side during each single-phase voltage regulation to obtain the three-phase load voltage integral value corresponding to each single-phase voltage regulation.

[0074] Specifically, the inverter slave determines the sampling integration period corresponding to each single-phase voltage regulation according to the voltage regulation starting time point and the regulation duration of the target waveform, and samples and integrates the three-phase load voltage on the inverter slave side based on the sampling integration period to obtain the three-phase load voltage integral value corresponding to each single-phase voltage regulation.

[0075] To avoid the influence of short-term single sampling on the result judgment, the sampling integration period can be longer than the period of single-phase voltage regulation. For example, the start time point of single-phase voltage regulation is t0, and the adjustment time of the target waveform is T c , then for the first single-phase voltage regulation, the inverter slave can start sampling and integrating the three-phase load voltage on the inverter slave side from (t0-T1) until (t0+T c+T2). Among them, T1 and T2 are respectively the surplus time before the start of single-phase voltage regulation and the surplus time after the end of single-phase voltage regulation, and the two can be the same or different.

[0076] When part of the band of the target waveform is located above the time axis and part of the band is located below the time axis, in order to avoid the detection being affected by the integral offset, the target waveform can be divided into multiple bands and then integrated separately, wherein adjacent bands are located on different sides of the time axis. During each single-phase voltage regulation period, the inverter slave samples and integrates the three-phase load voltage on the inverter slave side based on each band of the target waveform, and obtains the three-phase load voltage integral value corresponding to each single-phase voltage regulation in each band of the target waveform. In one embodiment, the inverter slave determines the sampling and integration period of each single-phase voltage regulation in each band according to the voltage regulation starting time point and the adjustment period of each band of the target waveform, and samples and integrates the three-phase load voltage on the inverter slave side based on the sampling and integration period, and obtains the three-phase load voltage integral value corresponding to each single-phase voltage regulation in each band of the target waveform.

[0077] like Figure 8 As shown, the target waveform includes two bands, the adjustment period of the first band is from -0.001 seconds to 0 seconds, and the adjustment period of the second band is from 0 seconds to 0.001 seconds. The inverter slave samples and integrates the three-phase load voltage corresponding to the first band and the second band respectively, and obtains the three-phase load voltage integral value corresponding to the first band and the second band for each single-phase voltage adjustment.

[0078] Step S604, the inverter slave or the inverter master determines the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each single-phase voltage regulation and the preset three-phase load voltage target range corresponding to each single-phase voltage regulation.

[0079] When step S604 is executed by the inverter master, before step S604, the method further includes: the inverter slave sends the three-phase load voltage integral value corresponding to each single-phase voltage regulation to the inverter master. Preferably, step S604 is executed by the inverter slave.

[0080] In one embodiment, the inverter slave or the inverter master compares the three-phase load voltage integral value corresponding to each single-phase voltage regulation with the three-phase load voltage target range corresponding to the single-phase voltage regulation based on the same phase. If the number of times that the single-phase load voltage integral value is not within the single-phase load voltage target range exceeds the preset alarm threshold, it is determined that there is an abnormality in the output connection line of the off-grid output port of the inverter parallel system. For example, if the inverter master performs voltage regulation based on the R phase for 5 times, the inverter slave can obtain 5 groups of three-phase load voltage integral values ​​through sampling and integration, which are (V R1, V S1 , V T1 )、(V R2 , V S2 , V T2 )、(V R3 , V S3 , V T3 )、(V R4 , V S4 , V T4 )、(V R5 , V S5 , V T5 The three-phase load voltage target range (V R0 ~ V R0’ , V S0 ~ V S0’ , V T0 ~ V T0’ ) are compared in phase (taking the first group as an example, comparing V R1 Is it in V R0 ~ V R0’ Range, V S1 Is it in V S0 ~ V S0’ Range and V T1 Is it in V T0 ~ V T0’ range), counting the number of times that the single-phase load voltage integral value is not within the single-phase load voltage target range, and when the number exceeds a preset alarm threshold, determining that an output connection line of the off-grid output port of the inverter parallel system is abnormal.

[0081] In some embodiments, the inverter slave or inverter host also records the regulated single-phase when the load voltage integral value of the single-phase is not within the load voltage target range of the single-phase as an abnormal single-phase. After the inverter slave determines that there is an abnormality in the output connection line of the off-grid output port of the inverter parallel system, the inverter slave or inverter host compares the three-phase load voltage integral value corresponding to the single-phase voltage regulation based on the abnormal single-phase with the single-phase voltage regulation based on the abnormal single-phase within the load voltage target range corresponding to the abnormal single-phase to determine the type of wiring error.

[0082] When the output connection line of the off-grid output port of the inverter parallel system is correctly connected, the voltage regulation based on a single phase will generate a corresponding integral value on the load voltage of the same single phase on the inverter slave side, while the load voltage integral values ​​of the other two single phases should be zero. Based on this theory, the type of wiring error can be determined. In one embodiment, during the single-phase voltage regulation based on the abnormal single phase, if there is no single-phase load voltage integral value in the three-phase load voltage integral value that meets the load voltage target range corresponding to the abnormal single, the type of the wiring error is judged to be open circuit; if there are multiple single-phase load voltage integral values ​​in the three-phase load voltage integral value that meet the load voltage target range corresponding to the abnormal single, the type of the wiring error is judged to be short circuit; if there is a single-phase load voltage integral value in the three-phase load voltage integral value that meets the load voltage target range corresponding to the abnormal single, and the single phase that meets the abnormal single phase is different, then the type of the wiring error is judged to be phase sequence confusion.

[0083] For example, if the abnormal single phase is the R phase, the three-phase load voltage integral value corresponding to the single-phase voltage adjustment based on the R phase is compared with the R phase load voltage target range corresponding to the R phase voltage adjustment. If there is no single-phase load voltage integral value that meets the R phase load voltage target range among the three-phase load voltage integral values ​​(that is, when adjusting the R phase voltage, no phase on the inverter slave side detects a voltage of the corresponding magnitude), it is determined that the output connection line has a circuit breaker. If there are multiple single-phase load voltage integral values ​​that meet the R phase load voltage target range among the three-phase load voltage integral values ​​(that is, when adjusting the R phase voltage, the inverter slave side detects voltages of the corresponding magnitude in multiple phases), the type of the wiring error is determined to be a short circuit. If there is a single-phase load voltage integral value that meets the R phase load voltage target range among the three-phase load voltage integral values, and the single-phase that meets the R phase is different from the R phase (that is, when adjusting the R phase voltage, the inverter slave side detects a voltage of the corresponding magnitude in the S phase or T phase), the type of the wiring error is determined to be a phase sequence disorder.

[0084] In an embodiment of the present invention, the target range of the three-phase load voltage corresponding to each single-phase voltage regulation can be determined by the theoretical integral value of the target waveform. Specifically, the target range of the load voltage of the same phase as the regulated single phase can be about (±10%~±30%) of the theoretical integral value, preferably about ±20%. The theoretical value of the load voltage of a phase different from the regulated single phase is 0, and its load voltage target range can be set to ±10V*ms. For example, if the regulated single phase of the inverter host is the R phase, the R phase load voltage target range on the inverter slave side is about ±20% of the theoretical integral value, while the S phase and T phase load voltage target ranges are ±10V*ms. Among them, the absolute value of the theoretical integral value of the target waveform is the area of ​​the area enclosed by the target waveform and the time axis.

[0085] In one embodiment, the inverter slave or the inverter master determines the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each band of the target waveform and the preset three-phase load voltage target range corresponding to each single-phase voltage adjustment in each band of the target waveform. Figure 8 The target waveform of is taken as an example to illustrate the method for determining the target range of the three-phase load voltage when the target waveform is divided into multiple bands.

[0086] for Figure 8 The theoretical integral value of the first band in is:

[0087]

[0088] for Figure 8 The theoretical integral value of the second band in is:

[0089]

[0090] in, , is the voltage frequency (50Hz here).

[0091] According to the above calculation, the theoretical integral value of the first band is about -50 , the theoretical integral value of the second band is about 50 , assuming that the load voltage target range of the same phase as the single-phase regulation is ±20% of the theoretical integral value, and the load voltage target range of the different phases than the single-phase regulation is ±10V*ms, then the three-phase load voltage target ranges corresponding to the first and second bands of the target waveform for each single-phase voltage regulation are shown in the following table:

[0092]

[0093] In this embodiment, the inverter slave determines the sampling integration period in the first band and the sampling integration period in the second band of each voltage adjustment according to the voltage regulation starting time point, the adjustment period of the first band of the target waveform and the adjustment period of the second band of the target waveform, and samples and integrates the three-phase load voltage on the inverter slave side based on the sampling integration period to obtain the three-phase load voltage integral value corresponding to each single-phase voltage adjustment.

[0094] Furthermore, the inverter slave or the inverter master determines the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to the first band and the second band of each single-phase voltage regulation and the three-phase load voltage target range corresponding to the first band and the second band of each single-phase voltage regulation.

[0095] When step S604 is executed by the inverter slave, after the inverter slave determines the detection result of the output connection line of the off-grid output port of the inverter parallel system, the detection result is fed back to the inverter master. The inverter master determines whether re-inspection is required based on the detection result, and if necessary, re-executes steps S601 to S604.

[0096] The output connection line detection method of the off-grid output port of the inverter parallel system provided by the embodiment of the present invention is a fully automated pre-detection method, which can be carried out after the wiring required for normal operation is completed, and effectively avoids the hysteresis of detection after the inverter parallel system outputs power, as well as the problem of confusion in the functional operation of the system and even damage to the device. When performing the voltage adjustment required for detection, the inverter host preferably uses a target waveform with a smaller pulse and a shorter duration for voltage adjustment, so that the detection process has almost no effect on the load connected to the common output terminal; when performing detection judgment, the form of integral calculation is adopted, which reduces the impact of random errors and increases the accuracy of recognition. In addition, the detection method of the present invention is highly targeted, can identify a variety of abnormal working conditions and give corresponding prompts, and does not require the introduction of any other additional equipment, which can improve the work efficiency of the installer.

[0097] According to an embodiment of the present invention, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program. When the computer program is executed by a processor, the processor executes the steps of the above-mentioned method for detecting an output connection line of an off-grid output port of an inverter parallel system.

[0098] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them. Under the concept of the present invention, the technical features in the above embodiments or different embodiments can be combined, the steps can also be implemented in other reasonable orders, and there are many other changes in different aspects of the present invention as described above, which are not provided in detail for the sake of simplicity. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present application.

Claims

1. A method for detecting an output connection line of an off-grid output port of an inverter parallel system, characterized in that: The method is performed before the inverter parallel system outputs power, and the method includes: Step A, the inverter master and the inverter slave are adjusted and synchronized; Step B, after completing the regulation synchronization, the inverter host sequentially performs single-phase voltage regulation on one or more phases of the three phases RST according to a preset voltage regulation cycle and a preset target waveform; Step C, the inverter slave samples and integrates the three-phase load voltage on the inverter slave side during each single-phase voltage regulation to obtain the three-phase load voltage integral value corresponding to each single-phase voltage regulation; Step D, the inverter slave or the inverter master determines the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each single-phase voltage regulation and the preset three-phase load voltage target range corresponding to each single-phase voltage regulation; The step D comprises: The inverter slave or inverter master records the regulated single-phase when the load voltage integral value of the single-phase is not within the load voltage target range of the single-phase as an abnormal single-phase, and after determining that there is an abnormality in the output connection line of the off-grid output port of the inverter parallel system, compares the three-phase load voltage integral value corresponding to the single-phase voltage regulation based on the abnormal single-phase with the single-phase voltage regulation based on the abnormal single-phase within the load voltage target range corresponding to the abnormal single-phase, to determine the type of wiring error.

2. The method according to claim 1, characterized in that The step D also includes: The inverter slave or inverter master compares the three-phase load voltage integral value corresponding to each single-phase voltage regulation with the three-phase load voltage target range corresponding to the single-phase voltage regulation based on the same phase. If the number of times that the single-phase load voltage integral value is not within the single-phase load voltage target range exceeds the preset alarm threshold, it is determined that there is an abnormality in the output connection line of the off-grid output port of the inverter parallel system.

3. The method according to claim 1, characterized in that Determining the type of wiring error includes: During the single-phase voltage regulation based on the abnormal single phase, If there is no single-phase load voltage integral value among the three-phase load voltage integral values ​​that meets the load voltage target range corresponding to the abnormality list, then the type of the wiring error is determined to be a circuit breaker; If there are multiple single-phase load voltage integral values ​​in the three-phase load voltage integral values ​​that meet the load voltage target range corresponding to the abnormal order, then the type of the wiring error is determined to be a short circuit; If there is a single-phase load voltage integral value among the three-phase load voltage integral values ​​that meets the load voltage target range corresponding to the abnormal single phase, and the compliant single phase is different from the abnormal single phase, then the type of the wiring error is determined to be phase sequence disorder.

4. The method according to claim 1, characterized in that: The step A comprises: The inverter master sends a ready-to-adjust synchronization signal to the inverter slave via the CAN bus for adjustment synchronization.

5. The method according to any one of claims 1 to 4, characterized in that: The target waveform is a preset band on a standard sinusoidal voltage periodic waveform.

6. The method according to claim 5, characterized in that The preset band includes a first band corresponding to a preset time length before the positive zero crossing point on the standard sinusoidal voltage periodic waveform and a second band corresponding to the preset time length after the positive zero crossing point, and the preset time length is much shorter than the period of the standard sinusoidal voltage.

7. The method according to any one of claims 1 to 4, characterized in that: The target waveform includes multiple bands, and the step C further includes: During each single-phase voltage regulation period, the inverter slave machine samples and integrates the three-phase load voltage on the inverter slave machine side based on each band of the target waveform, and obtains the three-phase load voltage integral value corresponding to each band of the target waveform for each single-phase voltage regulation; The step D also includes: The inverter slave or inverter master determines the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each band of the target waveform for each single-phase voltage adjustment and the preset three-phase load voltage target range corresponding to each band of the target waveform for each single-phase voltage adjustment.

8. An inverter parallel system, characterized in that: The system comprises an inverter host and a plurality of inverter slaves, wherein the inverter host and the plurality of inverter slaves are both provided with an off-grid output port; The inverter master is used to perform regulation synchronization with the inverter slave before the system outputs power, and after completing the regulation synchronization, sequentially perform single-phase voltage regulation on one or more phases of the three phases RST according to a preset voltage regulation cycle and a preset target waveform; The inverter slave is used to sample and integrate the three-phase load voltage on the inverter slave side during each single-phase voltage regulation to obtain the three-phase load voltage integral value corresponding to each single-phase voltage regulation; The inverter slave or the inverter master is further used to determine the detection result of the output connection line of the off-grid output port of the inverter parallel system according to the three-phase load voltage integral value corresponding to each single-phase voltage regulation and the preset three-phase load voltage target range corresponding to each single-phase voltage regulation. The detection result of the output connection line of the off-grid output port of the inverter parallel system is determined, and the detection result of the output connection line of the off-grid output port of the inverter parallel system is determined. The output connection line is recorded as an abnormal single phase when the load voltage integral value of the single phase is not within the load voltage target range of the single phase, and after judging that the output connection line of the off-grid output port of the inverter parallel system is abnormal, the three-phase load voltage integral value corresponding to the single-phase voltage regulation based on the abnormal single phase is compared with the load voltage target range corresponding to the single-phase voltage regulation based on the abnormal single phase, so as to determine the type of wiring error.

9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program. When the computer program is executed by a processor, the processor executes the steps of the method for detecting the output connection line of the off-grid output port of the inverter parallel system according to any one of claims 1 to 7.