A resource scheduling method and system for highway maintenance information management

By monitoring the operating status of the crack detector and road surface crack data in real time, calculate abnormal scores and risk scores, identify high and low risk areas, solve the problems of inaccurate data and insufficient prediction in the existing system, and achieve efficient, safe and efficient highway maintenance Economical.

CN118657347BActive Publication Date: 2024-11-05山东路科公路信息咨询有限公司
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411131622.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-05
Estimated Expiration
2044-08-19

AI Technical Summary

Technical Problem

The existing highway maintenance system has equipment failures that lead to inaccurate data and lack of effective predictions on the development trend of road cracks, which limits the foresight and efficiency of maintenance work.

Method used

The operating data of the crack detector is collected in real time through temperature sensors and pressure sensors, and the temperature and pressure values ​​are analyzed to determine the status of the equipment, calculate the abnormal score, and calculate the risk score based on the road surface crack data, identify high-risk areas and start the emergency maintenance plan, and predict low-risk risks. The maintenance plan will be adjusted for the future trends of the region.

Benefits of technology

Ensure the accuracy of crack detection data, improve the response speed and maintenance efficiency of highway management, reduce the frequency of manual inspection and material costs, and improve road safety and user satisfaction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118657347B_ABST
    Figure CN118657347B_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of highway maintenance information management, and specifically discloses a resource scheduling method and system for highway maintenance information management, which obtains operation data of a crack detector and analyzes to obtain an operation status signal; after ensuring that the crack detector collects data accurately, obtains pavement crack status data in real time; analyzes the crack status data to obtain a risk score Rs, and identifies high-risk areas accordingly; immediately initiates an emergency maintenance plan for high-risk areas, and predicts future risk scores for low-risk areas based on historical data to adjust the maintenance plan; marks potential high-risk areas, increases inspection frequency, and arranges repair work in advance; the invention realizes effective scheduling of maintenance resources by real-time monitoring of the status of a crack detector and the development trend of pavement cracks, improves the efficiency and accuracy of highway maintenance, helps to reduce maintenance costs, and extends the service life of highways.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of highway maintenance information management, and in particular to a resource scheduling method and system for highway maintenance information management. Background Art

[0002] With the acceleration of urbanization and the continuous increase in traffic volume, the importance of highway maintenance and upkeep is becoming increasingly prominent as an important infrastructure. Pavement cracks not only affect driving comfort, but may also cause more serious road damage, thus threatening driving safety. Therefore, timely and effective detection and evaluation of pavement crack conditions are crucial for the rational planning of highway maintenance plans.

[0003] Traditional highway maintenance methods mainly rely on manual inspections and empirical judgments. This method is inefficient and highly subjective, and it is difficult to meet the needs of modern highway management. In recent years, with the development of information technologies such as the Internet of Things and big data analysis, the application of intelligent detection equipment has gradually become popular. As a key detection tool, crack detectors can automatically collect pavement crack data and conduct preliminary analysis, greatly improving the efficiency and accuracy of highway maintenance work.

[0004] However, the existing crack detection technology and maintenance management system still have some shortcomings, such as inaccurate data caused by equipment failure and lack of effective prediction methods for the development trend of pavement cracks. These problems limit the foresight and efficiency of maintenance work. Therefore, it is particularly necessary to develop an information management system that can comprehensively monitor the operating status of crack detectors, accurately assess the risk of pavement cracks, and dynamically adjust maintenance strategies. Summary of the invention

[0005] The purpose of the present invention is to provide a resource scheduling method for highway maintenance information management, which collects the operating data of the crack detector in real time through temperature sensors and pressure sensors, including operating temperature and operating pressure, and analyzes these data to determine the operating status of the equipment, that is, whether there is an abnormality. This process involves statistical analysis of temperature values ​​and pressure values, such as calculating the average temperature value, standard deviation, and range of pressure values, and then deriving temperature anomaly factors and pressure anomaly factors, and calculating the abnormal score of the crack detector in combination with a preset proportional factor. If the abnormal score exceeds the preset threshold, it indicates that the equipment is abnormal and an abnormal operation signal needs to be generated; otherwise, a normal operation signal is generated.

[0006] Once the crack detector is ensured to be in normal working condition, the device can be used to obtain real-time pavement crack status data of each area, including key information such as the number, length, width and depth of cracks. Next, the present invention calculates the risk score of each sub-area by analyzing these data, which reflects the severity of pavement cracks. By comparing the risk score with the preset threshold, high-risk areas and low-risk areas can be identified. For high-risk areas, an emergency maintenance plan is immediately initiated, including repairs and enhanced treatments, and the monitoring frequency of the area is increased to ensure that new problems can be discovered in time. For low-risk areas, possible future trends can be predicted by analyzing historical data, and the maintenance plan can be adjusted accordingly, such as predicting the growth rate of cracks. If the predicted risk score exceeds the preset threshold in the future, the area should be marked as a potential high-risk area, and preventive measures should be taken, including increasing the inspection frequency and arranging repair work in advance; to solve the problems in the above background.

[0007] The purpose of the present invention can be achieved through the following technical solutions:

[0008] A resource scheduling method for highway maintenance information management, characterized in that it includes the following steps:

[0009] S1: Acquire the operation data of the crack detector, analyze the operation data of the crack detector, and obtain the operation status signal of the crack detector;

[0010] The operation data includes the operation temperature and the operation pressure, and the operation status signal includes the operation abnormality signal and the operation normal signal;

[0011] S2: After ensuring that the crack detector collects accurate data, the crack detector is used to obtain the pavement crack status data of each area in real time;

[0012] Among them, the crack status data includes the number of cracks, crack length, crack width and crack depth;

[0013] S3: Analyze the pavement crack status data to obtain a risk score Rs, compare the risk score Rs with the risk score threshold, and identify high-risk areas;

[0014] S4: For high-risk areas, immediately initiate emergency maintenance plans; for low-risk areas, predict the future risk score of each sub-area based on historical data;

[0015] S5: Mark potential high-risk areas, increase inspection frequency and arrange repair work in advance.

[0016] As a further solution of the present invention: the operating temperature and operating pressure are processed to obtain the temperature anomaly factor and pressure abnormality factors ;

[0017] The temperature anomaly factor The weight of the pressure anomaly factor is w1. The weight distribution is w2;

[0018] By formula Calculate the abnormal score of the crack detector ;

[0019] Score the crack detector abnormality The crack detector is compared with the preset abnormal score threshold to generate abnormal operation signal and normal operation signal.

[0020] As a further solution of the present invention: temperature anomaly factor The acquisition process is:

[0021] Get the real-time temperature value of each collection point, recorded as Ti;

[0022] Wherein, i represents the number of acquisition points, i=1, 2, ..., n;

[0023] Integrate all temperature values ​​within the monitoring period to obtain a temperature value group;

[0024] By formula Calculate the temperature anomaly factor ;

[0025] Wherein, Ty is the average temperature value of the temperature value group, α is the standard deviation value of the temperature value group, b1 and b2 are preset proportional factors, and b1 and b2 are both greater than 0.

[0026] As a further solution of the present invention: Abnormal pressure factor The acquisition process is:

[0027] Get the real-time pressure value of each collection point, recorded as Fi;

[0028] Integrate all pressure values ​​within the monitoring period to obtain a pressure value group;

[0029] By formula Calculate the pressure abnormality factor ;

[0030] Among them, Fy is the average pressure value of the pressure value group, Fc is the pressure deviation ratio of the pressure value group, b3 and b4 are preset proportional factors, and b3 and b4 are both greater than 0.

[0031] As a further solution of the present invention: the crack state data standardization process is:

[0032] The maximum crack length Lsmax and the minimum crack length Lsmin are calculated by difference to obtain the crack length extreme value, and the crack length extreme value is calculated by ratio to the crack length average value Lsy to obtain the crack length standardized score. ;

[0033] Among them, the crack width standardized score and crack depth normalized score Acquisition method and crack length standardized score The acquisition method is the same.

[0034] As a further solution of the present invention: the process of obtaining the risk score Rs is:

[0035] Normalize the crack length score The weight of the crack width is assigned as Wa, and the crack width is standardized as The weight of the crack depth is assigned as Wb, and the crack depth is standardized to score The weight of is Wc, and the weight of the number of cracks Js is Wd;

[0036] By formula The risk score Rs of each sub-area is calculated.

[0037] As a further solution of the present invention: for low-risk areas, historical monitoring data are obtained, and based on the historical monitoring data, the crack length growth rate m1, the crack width growth rate m2, the crack depth growth rate m3 and the crack number growth rate m4 are obtained.

[0038] As a further solution of the present invention: by formula Predict the growth rate of crack length;

[0039] Where b1 is the intercept corresponding to the crack length, Indicates the prediction time;

[0040] By formula Predict the growth rate of crack width;

[0041] Where b2 is the intercept corresponding to the crack width;

[0042] By formula Predict the growth rate of crack depth;

[0043] Among them, b3 is the intercept corresponding to the crack depth;

[0044] By formula Predict the growth rate of the number of cracks;

[0045] Among them, b4 is the intercept corresponding to the number of cracks.

[0046] As a further solution of the present invention: the marking process is:

[0047] The risk score of each low-risk area is updated using the predicted value, and if the predicted risk score exceeds the preset risk score threshold, the area is marked as a potential high-risk area.

[0048] A resource scheduling system for highway maintenance information management, including a data acquisition module, a data analysis module, an anomaly detection and repair module, a maintenance plan adjustment module and a dynamic monitoring and adjustment module;

[0049] A data acquisition module, the data acquisition module is used to obtain the operating data of the crack detector, including operating temperature data and operating pressure data; real-time acquisition of pavement crack status data, including crack number, crack length, crack width and crack depth;

[0050] A data analysis module, which is used to analyze the operating status data of the crack detector, generate an operating status signal, calculate the risk score Rs of the crack status data, and identify high-risk areas;

[0051] Anomaly detection and repair module, which is used to detect the abnormal score of the crack detector, determine whether the equipment is normal, and repair or replace the equipment to ensure data accuracy;

[0052] A maintenance plan adjustment module, which is used to initiate an emergency maintenance plan for high-risk areas, predict future risks for low-risk areas, and adjust maintenance plans;

[0053] A dynamic monitoring and adjustment module is used to monitor the status of the sub-areas in real time and dynamically adjust the maintenance plan according to the crack growth trend.

[0054] Beneficial effects of the present invention:

[0055] (1) First, by real-time monitoring of the operating status of the crack detector, the stable operation of the crack detector is ensured, thereby ensuring the accuracy of the crack detection data. This real-time monitoring mechanism can detect equipment failures in a timely manner and reduce data errors caused by equipment abnormalities, thereby ensuring the accuracy of highway crack detection. Secondly, through in-depth analysis of pavement crack status data, the present invention can accurately evaluate the pavement conditions of each area, especially by identifying high-risk areas through quantitative risk scores Rs, so that highway management departments can respond quickly and take emergency maintenance measures for high-risk areas to prevent further deterioration of pavement conditions. In addition, through regular equipment maintenance and calibration, the long-term stable operation of the crack detector is ensured, maintenance delays caused by equipment aging or failure are reduced, and overall maintenance efficiency is improved.

[0056] (2) Traditional highway maintenance methods often rely on regular manual inspections, which is not only time-consuming and labor-intensive, but also prone to missing some highly concealed cracks. The use of the automated monitoring system in the present invention can effectively reduce the frequency of manual inspections while ensuring that cracks are discovered and properly handled in a timely manner. Through preventive maintenance and decision-making based on data analysis, large-scale repair projects caused by crack expansion can be reduced, thereby saving a lot of material and labor costs. In the long run, this method can significantly reduce the overall expenditure of highway maintenance and improve economic benefits;

[0057] (3) By timely discovering and dealing with safety hazards such as road cracks, traffic accidents can be effectively prevented and road safety can be improved. For high-risk areas, the present invention can quickly initiate emergency maintenance plans to ensure the safety of these areas. At the same time, for low-risk areas, by continuously monitoring and predicting future risk trends, preventive measures can be taken in advance to avoid potential safety hazards. In addition, the present invention can also reduce traffic interference caused by maintenance work by improving the efficiency and quality of highway maintenance work, such as by optimizing maintenance plans to reduce road closure time and reduce the impact on highway users. Through these measures, the present invention not only improves the overall safety level of the highway, but also provides highway users with a smoother and more comfortable travel environment, thereby greatly enhancing the public's satisfaction and support for highway maintenance work. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] The present invention will be further described below in conjunction with the accompanying drawings.

[0059] Figure 1 It is a flow chart of a resource scheduling method for highway maintenance information management of the present invention;

[0060] Figure 2 It is a flow chart of a resource scheduling system for highway maintenance information management of the present invention;

[0061] Figure 3 It is a flowchart of the road surface risk division process in the present invention. DETAILED DESCRIPTION

[0062] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0063] See also Figure 1 As shown, the present invention is a resource scheduling method for highway maintenance information management, comprising the following steps:

[0064] S1: Acquire the operation data of the crack detector, analyze the operation data of the crack detector, and obtain the operation status signal of the crack detector;

[0065] The operation data includes the operation temperature and the operation pressure, and the operation status signal includes the operation abnormality signal and the operation normal signal;

[0066] S2: After ensuring that the crack detector collects accurate data, the crack detector is used to obtain the pavement crack status data of each area in real time;

[0067] Among them, the crack status data includes the number of cracks, crack length, crack width and crack depth;

[0068] S3: Analyze the pavement crack status data to obtain a risk score Rs, compare the risk score Rs with the risk score threshold, and identify high-risk areas;

[0069] S4: For high-risk areas, immediately initiate emergency maintenance plans; for low-risk areas, predict the future risk score of each sub-area based on historical data;

[0070] S5: Mark potential high-risk areas, increase inspection frequency and arrange repair work in advance.

[0071] Embodiment 2, based on embodiment 1, during the monitoring period of the crack detector, the operating temperature data of the crack detector is collected in real time according to a time series (such as every minute) by a temperature sensor;

[0072] Get the real-time temperature value of each collection point, recorded as Ti;

[0073] Wherein, i represents the number of acquisition points, i=1, 2, ..., n;

[0074] Integrate all temperature values ​​within the monitoring period to obtain a temperature value group;

[0075] Calculate the mean of all temperature values ​​in the temperature value group to obtain the average temperature value, which is recorded as Ty;

[0076] Calculate the standard deviation of all temperature values ​​in the temperature value group to obtain the standard deviation, which is recorded as α;

[0077] By formula Calculate the temperature anomaly factor ;

[0078] Wherein, b1 and b2 are preset proportional factors, and b1 and b2 are both greater than 0.

[0079] The operating pressure data of the crack detector is collected in real time according to a time series (such as every minute) through a pressure sensor;

[0080] Get the real-time pressure value of each collection point, recorded as Fi;

[0081] Integrate all pressure values ​​within the monitoring period to obtain a pressure value group;

[0082] Calculate the mean of all pressure values ​​in the pressure value group to obtain the average pressure value, which is recorded as Fy;

[0083] The maximum pressure value in the pressure value group is subtracted from the minimum pressure value to obtain the pressure extreme difference value in the pressure value group. The pressure extreme difference value is calculated by ratio with the average pressure value to obtain the pressure value deviation ratio, which is recorded as Fc.

[0084] By formula Calculate the pressure abnormality factor ;

[0085] Among them, b3 and b4 are preset proportional factors, and b3 and b4 are both greater than 0.

[0086] Temperature anomaly factor and pressure abnormality factors to process;

[0087] The temperature anomaly factor The weight of the pressure anomaly factor is w1. The weight distribution is w2;

[0088] By formula Calculate the abnormal score of the crack detector ;

[0089] Score the crack detector abnormality comparing with a preset crack detector abnormality score threshold;

[0090] If the crack detector scores abnormally If the value is greater than or equal to the preset crack detector abnormality score threshold, it indicates that the crack detector equipment is abnormal and generates an operation abnormality signal;

[0091] If the crack detector scores abnormally If the value is less than the preset abnormal score threshold of the crack detector, it means that the crack detector equipment is normal and generates a normal operation signal;

[0092] It should be noted that: Crack detector abnormal score It is obtained by analyzing the internal operating data of the crack detector equipment and weighting the temperature anomaly factor and pressure anomaly factor. The status of the equipment determines the accuracy of highway crack detection during highway maintenance.

[0093] Example 3, please refer to Figure 3As shown, on the basis of Example 2, any abnormal crack detector is promptly repaired or replaced to ensure the accuracy of detecting highway cracks that are affected by abnormal equipment status. After adjusting the crack detector, the abnormal score of the crack detector is recalculated and compared with the abnormal score threshold of the crack detector to ensure that the crack detector is in normal working condition.

[0094] Calibrate the crack detector and obtain the pavement crack status data in real time through the crack detector. Monitor the pavement status of different areas of the highway in real time, analyze the distribution of cracks, and identify high-risk areas.

[0095] Among them, the pavement crack status data includes the number of cracks, crack length, crack width and crack depth;

[0096] Specific:

[0097] Divide the monitoring area of ​​the crack detector into several identical sub-areas, and collect crack status data of each sub-area respectively;

[0098] Among them, the crack length is measured by a crack detector, the crack width is measured by a crack width meter, and the crack depth is measured non-destructively by an ultrasonic detector. Each instrument needs to be calibrated before measurement to ensure the accuracy of the measurement data.

[0099] Get the number of cracks Js in each sub-area;

[0100] Where s represents the number of sub-regions, s=1, 2, ..., n;

[0101] Obtain the crack length Lsj, crack width Esj and crack depth Hsj of each sub-area respectively;

[0102] Where Lsj, Esj and Hsj represent the length, width and depth of the jth crack in the sth sub-region, respectively;

[0103] The crack length Lsj, crack width Esj and crack depth Hsj of each sub-region are integrated to obtain the length group, width group and depth group;

[0104] The maximum and minimum values ​​in each group are obtained respectively, including the maximum crack length Lsmax, the minimum crack length Lsmin, the maximum crack width Esmax, the minimum crack width Esmin, the maximum crack depth Hsmax and the minimum crack depth Hsmin;

[0105] The mean values ​​of each group were calculated to obtain the average value of crack length Lsy, the average value of crack width Esy and the average value of crack depth Hsy;

[0106] The crack length, crack width and crack depth were standardized and calculated respectively;

[0107] The maximum crack length Lsmax and the minimum crack length Lsmin are calculated by difference to obtain the crack length extreme value, and the crack length extreme value is calculated by ratio to the crack length average value Lsy to obtain the crack length standardized score. ;

[0108] The maximum crack width Esmax and the minimum crack width Esmin are calculated to obtain the crack width extreme value, and the crack width extreme value is calculated to obtain the crack width standardization score by comparing the crack width extreme value to the crack width average value Esy. ;

[0109] The maximum crack depth Hsmax and the minimum crack depth Hsmin are calculated to obtain the crack depth extreme value, and the crack depth extreme value is calculated to obtain the crack depth standardization score by comparing the crack depth extreme value with the crack depth average value Hsy. ;

[0110] Normalize the crack length score The weight of the crack width is assigned as Wa, and the crack width is standardized as The weight of the crack depth is assigned as Wb, and the crack depth is standardized to score The weight of is Wc, and the weight of the number of cracks Js is Wd;

[0111] By formula Calculate the risk score Rs of each sub-area;

[0112] Compare the risk score Rs of each sub-area with the preset risk score threshold;

[0113] If the risk score Rs is greater than or equal to the preset risk score threshold, it means that the road condition of the corresponding sub-area is poor and is recorded as a high-risk area;

[0114] If the risk score Rs is less than the preset risk score threshold, it means that the road surface condition of the corresponding sub-area is good and is recorded as a low-risk area;

[0115] It should be noted that the risk score Rs reflects the crack situation in each sub-area. The larger the risk score Rs, the higher the abnormality of the corresponding sub-area and the more likely it is to have safety problems. Timely risk assessment of each area will help to promptly discover abnormalities in the road surface condition and facilitate road maintenance.

[0116] Example 4, based on Example 3, real-time monitoring is performed on each sub-area, and the maintenance plan is dynamically adjusted according to the crack status data to ensure timely intervention in high-risk areas. For low-risk areas, possible future situations are predicted based on the development trend of the cracks, and the maintenance plan is set and adjusted to avoid further deterioration of the cracks.

[0117] Specifically: For high-risk areas, immediately initiate emergency maintenance plans, carry out repairs or enhancements, and increase the frequency of monitoring in the area to ensure that new problems are discovered in a timely manner.

[0118] For low-risk areas, historical monitoring data are obtained, and based on the historical monitoring data, the crack length growth rate m1, crack width growth rate m2, crack depth growth rate m3 and crack number growth rate m4 are obtained;

[0119] By formula Predict the growth rate of crack length;

[0120] Where b1 is the intercept corresponding to the crack length, Indicates the prediction time;

[0121] By formula Predict the growth rate of crack width;

[0122] Where b2 is the intercept corresponding to the crack width;

[0123] By formula Predict the growth rate of crack depth;

[0124] Among them, b3 is the intercept corresponding to the crack depth;

[0125] By formula Predict the growth rate of the number of cracks;

[0126] Among them, b4 is the intercept corresponding to the number of cracks.

[0127] The predicted value is used to update the risk score of each low-risk area. If the predicted risk score exceeds the preset risk score threshold, the area is marked as a potential high-risk area, and corresponding preventive measures are taken to adjust the maintenance plan, including increasing the inspection frequency and arranging repair work in advance to prevent further deterioration of cracks.

[0128] It should be noted that: priority should be given according to the severity of cracks, and a reasonable maintenance plan should be formulated to ensure the safety and service life of the highway. Dynamic maintenance plans can reduce maintenance costs and save maintenance material costs and labor costs.

[0129] Example 5, please refer to Figure 2As shown, a resource scheduling system for highway maintenance information management includes a data acquisition module, a data analysis module, an anomaly detection and repair module, a maintenance plan adjustment module and a dynamic monitoring and adjustment module;

[0130] A data acquisition module, the data acquisition module is used to obtain the operating data of the crack detector, including operating temperature data and operating pressure data; real-time acquisition of pavement crack status data, including crack number, crack length, crack width and crack depth;

[0131] A data analysis module, which is used to analyze the operating status data of the crack detector, generate an operating status signal, calculate the risk score Rs of the crack status data, and identify high-risk areas;

[0132] Anomaly detection and repair module, which is used to detect the abnormal score of the crack detector, determine whether the equipment is normal, and repair or replace the equipment to ensure data accuracy;

[0133] A maintenance plan adjustment module, which is used to initiate an emergency maintenance plan for high-risk areas, predict future risks for low-risk areas, and adjust maintenance plans;

[0134] A dynamic monitoring and adjustment module is used to monitor the status of the sub-areas in real time and dynamically adjust the maintenance plan according to the crack growth trend.

[0135] Working principle of the present invention: The present invention first collects the operating data of the crack detector in real time through the temperature sensor and the pressure sensor, including the operating temperature and the operating pressure, and analyzes these data to determine the operating status of the equipment, that is, whether there is an abnormality. This process involves statistical analysis of temperature values ​​and pressure values, such as calculating the average temperature value, standard deviation, and the range of pressure values, and then deriving the temperature anomaly factor and the pressure anomaly factor, and calculating the anomaly score of the crack detector in combination with the preset proportional factor. If the anomaly score exceeds the preset threshold, it indicates that the equipment is abnormal and an abnormal operation signal needs to be generated; otherwise, a normal operation signal is generated.

[0136] Once the crack detector is ensured to be in normal working condition, the device can be used to obtain real-time pavement crack status data of each area, including key information such as the number, length, width and depth of cracks. Next, the present invention calculates the risk score of each sub-area by analyzing these data, which reflects the severity of pavement cracks. By comparing the risk score with the preset threshold, high-risk areas and low-risk areas can be identified. For high-risk areas, the present invention recommends immediately launching an emergency maintenance plan, including repair and enhanced treatment, and increasing the monitoring frequency of the area to ensure that new problems can be discovered in time. For low-risk areas, the possible future change trends can be predicted by analyzing historical data, and the maintenance plan can be adjusted accordingly, such as predicting the growth rate of cracks. If the predicted risk score exceeds the preset threshold in the future, the area should be marked as a potential high-risk area, and preventive measures should be taken, including increasing the inspection frequency and arranging repair work in advance to prevent the cracks from further deteriorating.

[0137] In summary, the present invention realizes effective management of highway cracks through real-time monitoring and data analysis technology, which can not only timely discover and solve problems in high-risk areas, but also effectively control the development trends of low-risk areas through predictive maintenance strategies, thereby greatly improving the efficiency and effectiveness of highway maintenance work, reducing maintenance costs, and ensuring the safety and service life of the highway.

[0138] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A resource scheduling method for highway maintenance information management, characterized in that: The following steps are involved: S1: Acquire the operation data of the crack detector, analyze the operation data of the crack detector, and obtain the operation status signal of the crack detector; The operation data includes the operation temperature and the operation pressure, and the operation status signal includes the operation abnormality signal and the operation normal signal; S2: After ensuring that the crack detector collects accurate data, the crack detector is used to obtain the pavement crack status data of each area in real time; Among them, the crack status data includes the number of cracks, crack length, crack width and crack depth; S3: Analyze the pavement crack status data to obtain a risk score Rs, compare the risk score Rs with the risk score threshold, and identify high-risk areas; S4: For high-risk areas, immediately initiate emergency maintenance plans; for low-risk areas, predict the future risk score of each sub-area based on historical data; S5: Mark potential high-risk areas, increase inspection frequency and arrange repair work in advance; Process the operating temperature and operating pressure to obtain the temperature anomaly factor and pressure abnormality factors ; The temperature anomaly factor The weight of the pressure anomaly factor is w1. The weight distribution is w2; By formula Calculate the abnormal score of the crack detector ; Score the crack detector abnormality Compare with the preset abnormal score threshold of the crack detector to generate an abnormal operation signal and a normal operation signal; Temperature anomaly factor The acquisition process is: Get the real-time temperature value of each collection point, recorded as Ti; Wherein, i represents the number of acquisition points, i=1, 2, ..., n; Integrate all temperature values ​​within the monitoring period to obtain a temperature value group; By formula Calculate the temperature anomaly factor ; Wherein, Ty is the average temperature value of the temperature value group, α is the standard deviation value of the temperature value group, b1 and b2 are preset proportional factors, and b1 and b2 are both greater than 0; Abnormal pressure factor The acquisition process is: Get the real-time pressure value of each collection point, recorded as Fi; Integrate all pressure values ​​within the monitoring period to obtain a pressure value group; By formula Calculate the pressure abnormality factor ; Wherein, Fy is the average pressure value of the pressure value group, Fc is the pressure deviation ratio of the pressure value group, b3 and b4 are preset proportional factors, and b3 and b4 are both greater than 0; The process of standardization of crack status data is as follows: The maximum crack length Lsmax and the minimum crack length Lsmin are calculated to obtain the crack length extreme value, and the crack length extreme value is calculated to obtain the crack length standardization score by comparing the crack length extreme value with the crack length average value Lsy. ; The maximum crack width Esmax and the minimum crack width Esmin are calculated to obtain the crack width extreme value, and the crack width extreme value is calculated to obtain the crack width standardization score by comparing the crack width extreme value to the crack width average value Esy. ; The maximum crack depth Hsmax and the minimum crack depth Hsmin are calculated to obtain the crack depth extreme value, and the crack depth extreme value is calculated to obtain the crack depth standardization score by comparing the crack depth extreme value with the crack depth average value Hsy. ; Normalize the crack length score The weight of the crack width is assigned as Wa, and the crack width is standardized as The weight of the crack depth is assigned as Wb, and the crack depth is standardized to score The weight of is Wc, and the weight of the number of cracks Js is Wd; By formula Calculate the risk score Rs of each sub-area; Compare the risk score Rs of each sub-area with the preset risk score threshold; If the risk score Rs is greater than or equal to the preset risk score threshold, it means that the road condition of the corresponding sub-area is poor and is recorded as a high-risk area; If the risk score Rs is less than the preset risk score threshold, it means that the road condition of the corresponding sub-area is good and it is recorded as a low-risk area.

2. A resource scheduling method for highway maintenance information management according to claim 1, characterized in that: For low-risk areas, historical monitoring data are obtained, and based on the historical monitoring data, the crack length growth rate m1, crack width growth rate m2, crack depth growth rate m3 and crack number growth rate m4 are obtained.

3. A resource scheduling method for highway maintenance information management according to claim 2, characterized in that: By formula Predict the growth rate of crack length; Where b1 is the intercept corresponding to the crack length, Indicates the prediction time; By formula Predict the growth rate of crack width; Where b2 is the intercept corresponding to the crack width; By formula Predict the growth rate of crack depth; Among them, b3 is the intercept corresponding to the crack depth; By formula Predict the growth rate of the number of cracks; Among them, b4 is the intercept corresponding to the number of cracks.

4. A resource scheduling method for highway maintenance information management according to claim 1, characterized in that: The marking process is: The risk score of each low-risk area is updated using the predicted value, and if the predicted risk score exceeds the preset risk score threshold, the area is marked as a potential high-risk area.

5. A resource scheduling system for highway maintenance information management, characterized in that: It includes data acquisition module, data analysis module, anomaly detection and repair module, maintenance plan adjustment module and dynamic monitoring and adjustment module; A data acquisition module, the data acquisition module is used to obtain the operating data of the crack detector, including operating temperature data and operating pressure data; real-time acquisition of pavement crack status data, including crack number, crack length, crack width and crack depth; A data analysis module, which is used to analyze the operating status data of the crack detector, generate an operating status signal, calculate the risk score Rs of the crack status data, and identify high-risk areas; Anomaly detection and repair module, which is used to detect the abnormal score of the crack detector, determine whether the equipment is normal, and repair or replace the equipment to ensure data accuracy; A maintenance plan adjustment module, which is used to initiate an emergency maintenance plan for high-risk areas, predict future risks for low-risk areas, and adjust maintenance plans; A dynamic monitoring and adjustment module, which is used to monitor the status of the sub-areas in real time and dynamically adjust the maintenance plan according to the crack growth trend; Process the operating temperature and operating pressure to obtain the temperature anomaly factor and pressure abnormality factors ; The temperature anomaly factor The weight of the pressure anomaly factor is w1. The weight distribution is w2; By formula Calculate the abnormal score of the crack detector ; Score the crack detector abnormality Compare with the preset abnormal score threshold of the crack detector to generate an abnormal operation signal and a normal operation signal; Temperature anomaly factor The acquisition process is: Get the real-time temperature value of each collection point, recorded as Ti; Wherein, i represents the number of acquisition points, i=1, 2, ..., n; Integrate all temperature values ​​within the monitoring period to obtain a temperature value group; By formula Calculate the temperature anomaly factor ; Wherein, Ty is the average temperature value of the temperature value group, α is the standard deviation value of the temperature value group, b1 and b2 are preset proportional factors, and b1 and b2 are both greater than 0; Abnormal pressure factor The acquisition process is: Get the real-time pressure value of each collection point, recorded as Fi; Integrate all pressure values ​​within the monitoring period to obtain a pressure value group; By formula Calculate the pressure abnormality factor ; Wherein, Fy is the average pressure value of the pressure value group, Fc is the pressure deviation ratio of the pressure value group, b3 and b4 are preset proportional factors, and b3 and b4 are both greater than 0; The process of standardization of crack status data is as follows: The maximum crack length Lsmax and the minimum crack length Lsmin are calculated to obtain the crack length extreme value, and the crack length extreme value is calculated to obtain the crack length standardization score by comparing the crack length extreme value with the crack length average value Lsy. ; The maximum crack width Esmax and the minimum crack width Esmin are calculated to obtain the crack width extreme value, and the crack width extreme value is calculated to obtain the crack width standardization score by comparing the crack width extreme value to the crack width average value Esy. ; The maximum crack depth Hsmax and the minimum crack depth Hsmin are calculated to obtain the crack depth extreme value, and the crack depth extreme value is calculated to obtain the crack depth standardization score by comparing the crack depth extreme value with the crack depth average value Hsy. ; Normalize the crack length score The weight of the crack width is assigned as Wa, and the crack width is standardized as The weight of the crack depth is assigned as Wb, and the crack depth is standardized to score The weight of is Wc, and the weight of the number of cracks Js is Wd; By formula Calculate the risk score Rs of each sub-area; Compare the risk score Rs of each sub-area with the preset risk score threshold; If the risk score Rs is greater than or equal to the preset risk score threshold, it means that the road condition of the corresponding sub-area is poor and is recorded as a high-risk area; If the risk score Rs is less than the preset risk score threshold, it means that the road condition of the corresponding sub-area is good and it is recorded as a low-risk area.

Citation Information

Patent Citations

  • Road and bridge crack detection system with automatic detection function

    CN117449172A

  • Bridge crack detection method and system

    CN117743830A

  • Municipal road crack repairing and monitoring method

    CN117845684A

  • Deep learning-based hydraulic engineering monitoring big data analysis method

    CN118134246A

  • Highway maintenance data management system

    CN118152900A