A data collaborative interaction method based on DHTMLX Gantt chart

By dividing project collaboration steps and adjusting color annotations in the DHTMLX Gantt chart, the problem of timely correction of project collaboration steps in the existing technology is solved, the efficiency and accuracy of project task management is improved, and the correctness of DHTMLX components is ensured.

CN118691237BActive Publication Date: 2025-01-03BINHUI DIGITAL TECH (NANJING) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410894051.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-04
Publication Date
2025-01-03
Estimated Expiration
2044-07-04

AI Technical Summary

Technical Problem

The prior art cannot promptly correct the errors in project collaboration steps during the DHTMLX component process, resulting in inefficient project task management.

Method used

Using the data collaborative interaction method based on DHTMLX Gantt chart, the project collaboration steps are divided into different categories in preset time periods, the Gantt chart display processing is carried out, error nodes and core nodes are clustered, color labeling status is adjusted, and management dependencies are removed. Ensure the accuracy and efficiency of task indicators.

Benefits of technology

Improve the inspection efficiency and accuracy of project collaboration steps, avoid the impact of DHTMLX component management dependencies on other tasks, and ensure the correctness and effectiveness of project task management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118691237B_ABST
    Figure CN118691237B_ABST
Patent Text Reader

Abstract

The present invention discloses a data collaborative interaction method based on a DHTMLX Gantt chart, the method comprising: performing different forms of operation Gantt chart display processing on each different category of project collaborative steps, clustering whether the different category of project collaborative steps are in the project collaborative step error node and whether they belong to the core different category of project collaborative steps, and marking the different category of project collaborative steps and the core different category of project collaborative steps in the project collaborative step error node with DHTMLX component colors, and also using management personnel to check each terminal in the core different category of project collaborative steps to determine the DHTMLX component management dependency relationship therein. The present invention quickly and accurately locates the corresponding project task management indicators by dividing the project collaborative steps into different categories of project collaborative steps and performing partition operation Gantt chart display and checking, thereby improving the inspection efficiency and accuracy of the project collaborative steps.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of project task management, and in particular relates to a data collaborative interaction method based on a DHTMLX Gantt chart. Background Art

[0002] Collaborative project management is an important development in today's project management field. It emphasizes collaboration and communication among team members, and improves the efficiency and quality of project execution through effective resource allocation and task allocation. In this context, Gantt charts have become a common tool for visualizing project progress, task dependencies, and resource utilization.

[0003] DHTMLX Gantt Chart is a Gantt chart solution developed based on DHTMLX library. DHTMLX library is a powerful JavaScript component library that provides rich user interface components and data processing functions. DHTMLX Gantt Chart takes advantage of these functions to provide users with an intuitive and flexible project management tool.

[0004] The features of DHTMLX Gantt chart include but are not limited to:

[0005] Customizability: Users can customize the appearance and behavior of the Gantt chart according to their needs, including task color, style, working time settings, etc.

[0006] Interactivity: Users can quickly adjust the display of tasks and timelines by dragging, zooming, and other operations, and view changes in project progress in real time.

[0007] Data import and export: Supports importing project data from various data sources and can export to common file formats such as JSON, XML, Excel, etc.

[0008] Cross-platform compatibility: DHTMLX Gantt chart can run on a variety of modern browsers and devices, including desktop and mobile.

[0009] Extensibility: Developers can conduct secondary development based on the DHTMLX Gantt chart to achieve more complex project management functions, such as resource scheduling, cost control, etc.

[0010] At present, the main display methods of project management DHTMLX Gantt chart are:

[0011] 1. Project plan and progress display: DHTMLX Gantt chart uses bar charts to display the progress and plan of the project. The horizontal axis represents time, the vertical axis represents projects or tasks, and the lines represent the period plan and actual completion. This allows project managers to clearly see the overall progress of the project, as well as the start and end time of each task or activity.

[0012] 2. Task dependency display: DHTMLX Gantt chart allows you to display the dependencies between activities. This helps project managers understand which tasks must be started after other tasks are completed, thus ensuring the smooth progress of the project.

[0013] 3. Task status display: DHTMLX Gantt chart can display the current task status with completion percentage shadow. This enables project managers to understand the completion status of tasks in real time and make decisions and adjustments accordingly.

[0014] 4. Task organization display: DHTMLX Gantt chart allows tasks to be organized into a tree structure. This helps project managers to manage projects in a hierarchical manner, so as to better understand and control all aspects of the project.

[0015] 5. Multi-view display: DHTMLX Gantt chart supports multiple views, including monthly view, daily view and hourly view. This allows project managers to select the appropriate view to view the project progress and plan as needed.

[0016] 6. Zoom function: The zoom function of DHTMLX Gantt chart allows project managers to focus on specific parts of the project. This helps project managers better understand and control the key parts of the project.

[0017] 7. Baseline display: The baseline function of DHTMLX Gantt chart helps ensure that the project is completed on time. By comparing the actual progress with the baseline progress, project managers can identify potential problems and make adjustments in time.

[0018] The above collaborative project management DHTMLX Gantt chart display method combines the concept of collaborative project management and the functional characteristics of the DHTMLX Gantt chart, providing a highly efficient and intuitive project management tool for the project team.

[0019] However, the above-mentioned prior art cannot perform Gantt chart display clustering according to the collaborative steps of project task management based on the Gantt chart, which results in that if errors occur in the project collaborative steps during the DHTMLX component process, there is no way to correct them in time, resulting in low efficiency of project task management. Summary of the invention

[0020] In view of the defects of the prior art, the purpose of the present invention is to provide a data collaborative interaction method based on the DHTMLX Gantt chart to solve the technical problem in the prior art that if there is an error in the project collaboration step in the DHTMLX component process, there is no way to correct it in time, resulting in low efficiency of project task management.

[0021] In order to achieve the above purpose, the present invention adopts the following technical solutions:

[0022] A first aspect of the present invention provides a data collaborative interaction method based on a DHTMLX Gantt chart, comprising the following steps:

[0023] S100, dividing the project collaboration steps into different categories of project collaboration steps in a preset time period, and performing a first operation Gantt chart display process on all project task management indicators connected to each different category of project collaboration step, to obtain a data interaction mode for each project task management indicator; clustering whether the different categories of project collaboration steps are at a project collaboration step error node according to the data interaction mode;

[0024] S200, performing DHTMLX component color marking processing on all different types of project collaboration steps at the project collaboration step error node in the project collaboration step, and performing a second operation Gantt chart display processing on each different type of project collaboration step at the project collaboration step error node, to obtain participant detail processing information inside the different types of project collaboration steps at the project collaboration step error node; clustering the different types of project collaboration steps at the project collaboration step error node to determine whether they belong to core different types of project collaboration steps according to the participant detail processing information;

[0025] S300, according to the clustering result of whether the core different categories of project collaboration steps belong to the core different categories of project collaboration steps, adjusting the color marking state of the DHTMLX component of the corresponding different categories of project collaboration steps at the error node of the project collaboration step; the management personnel perform the third operation Gantt chart display processing on the core different categories of project collaboration steps to obtain the Gantt chart display result of each project task management indicator included in the core different categories of project collaboration steps;

[0026] S400, analyzing and processing the Gantt chart display result to determine the DHTMLX component management dependency relationship between the core different types of project collaboration steps;

[0027] After the DHTMLX component management dependency is processed with DHTMLX component color marking, the DHTMLX component color marking status of all project task management indicators that do not belong to the DHTMLX component management dependency in the core different categories of project collaboration steps is released.

[0028] In the S100, the project collaboration steps are divided into different types of project collaboration steps in a preset time period, and a first operation Gantt chart display process is performed on all project task management indicators connected to each different type of project collaboration step to obtain a data interaction mode for each project task management indicator, including:

[0029] Obtaining the specific time of all collaborative step nodes in the project collaborative step, dividing the project collaborative step into different categories of project collaborative steps in preset time periods according to the specific time, and identifying and classifying the common collaborative step nodes between the different categories of project collaborative steps, and determining the DHTMLX component task features of all the common collaborative step nodes in the project collaborative steps;

[0030] A first operation Gantt chart display processing is performed on all project task management indicators connected to each different category of project collaboration steps to obtain all project task production report data and all project task financial report data of each project task management indicator within the preset processing collaboration step, which is used as the data interaction method.

[0031] In the S100, clustering the different types of project collaboration steps to see whether they are at project collaboration step error nodes according to the data interaction mode includes:

[0032] Analyze and process all project task production report data and all project task financial report data to determine the detail processing efficiency of ordinary employees and management personnel in the first preset processing collaboration step corresponding to different types of project collaboration steps;

[0033] If the detail processing efficiency of ordinary employees or the detail processing efficiency of managers is greater than the preset maximum value of the detail processing efficiency of participants, the clustering of the different categories of project collaboration steps is at a project collaboration step error node; otherwise, the clustering of the different categories of project collaboration steps does not belong to a project collaboration step error node.

[0034] In the S200, DHTMLX component color marking processing is performed on all different types of project collaboration steps at the project collaboration step error node in the project collaboration step, and a second operation Gantt chart display processing is performed on each different type of project collaboration step at the project collaboration step error node, to obtain detailed processing information of participants inside the different types of project collaboration steps at the project collaboration step error node, including:

[0035] According to the respective flow step information of all common coordination step nodes of different types of project coordination steps at the project coordination step error node, all the common coordination step nodes are switched to the normal operation state, so as to mark the different types of project coordination steps at the project coordination step error node and the different types of project coordination steps not at the project coordination step error node in the project coordination steps with the DHTMLX component color;

[0036] A second operation Gantt chart display processing is performed on each different category of project collaboration step that is at an error node of the project collaboration step, and the participating DHTMLX component number information and the participating DHTMLX component specific task information transmitted between the internal different project task management indicators of the different categories of project collaboration steps that are at an error node of the project collaboration step are obtained, which is used as the participant detail processing information.

[0037] In S200, clustering the different types of project collaboration steps at the project collaboration step error node to determine whether they belong to the core different types of project collaboration steps according to the participant detail processing information includes:

[0038] Parsing the participating DHTMLX component number information to determine whether the DHTMLX components transmitted between different project task management indicators include a preset list of participants;

[0039] The specific task information of the participating DHTMLX components is analyzed and processed to determine whether all DHTMLX components with a preset list of participants have the same DHTMLX component task in the second preset processing collaboration step; if so, the different categories of project collaboration steps that are clustered at the error nodes of the project collaboration steps belong to the core different categories of project collaboration steps; otherwise, the different categories of project collaboration steps that are clustered at the error nodes of the project collaboration steps do not belong to the core different categories of project collaboration steps.

[0040] In the S300, according to the clustering result of whether the core different categories of project collaboration steps belong to the core different categories of project collaboration steps, the color marking state of the DHTMLX component of the corresponding different categories of project collaboration steps at the error node of the project collaboration step is adjusted, specifically including:

[0041] When the different-category project collaboration step at the project collaboration step error node does not belong to the core different-category project collaboration step, all the common collaboration step nodes of the different-category project collaboration steps at the project collaboration step error node are switched to a marked state according to their respective flow step information;

[0042] When the different categories of project collaboration steps at the project collaboration step error node belong to the core different categories of project collaboration steps, then according to the respective flow step information of all the common collaboration step nodes of the different categories of project collaboration steps at the project collaboration step error node, the current normal operating status of all the common collaboration step nodes is kept unchanged.

[0043] In S300, the manager performs the third operation Gantt chart display processing on the core different types of project collaboration steps to obtain the Gantt chart display results of each project task management indicator included in the core different types of project collaboration steps, specifically including:

[0044] According to the respective DHTMLX component task characteristics of all project task management indicators included in the core different categories of project collaboration steps, the management personnel are instructed to send preset request messages for each project task management indicator respectively, and the Gantt chart display is operated to intercept the preset request message for each project task management indicator, and the Gantt chart display results to be fed back are marked to the management personnel.

[0045] In the S400, the Gantt chart display result is analyzed and processed to determine the DHTMLX component management dependency relationship existing in the core different categories of project collaboration steps, specifically including:

[0046] Performing artificial intelligence screening processing on the Gantt chart display results to be fed back, and obtaining management dependency points of the Gantt chart display results to be fed back of each project task management indicator;

[0047] The management dependency point is analyzed and processed to determine whether there is a human error in the management dependency point; if so, the corresponding project task management indicator is determined as belonging to the DHTMLX component management dependency; and the DHTMLX component task characteristics of all DHTMLX component management dependencies in the core different categories of project collaboration steps and the DHTMLX component task characteristics of all project task management indicators that do not belong to the DHTMLX component management dependency are determined.

[0048] In the S400, after the DHTMLX component management dependency is processed with DHTMLX component color marking, the DHTMLX component color marking status of all project task management indicators that do not belong to the DHTMLX component management dependency in the core different categories of project collaboration steps is released, specifically including:

[0049] According to the DHTMLX component task characteristics of all project task management indicators that do not belong to the DHTMLX component management dependency relationship in the core different categories of project collaboration steps, DHTMLX component correction processing is performed on all project task management indicators that do not belong to the DHTMLX component management dependency relationship;

[0050] According to the DHTMLX component task characteristics of all DHTMLX component management dependencies in the core different categories of project collaboration steps, the DHTMLX component task characteristics of all collaboration step nodes connected to all DHTMLX component management dependencies are determined, so that all collaboration step nodes connected to all DHTMLX component management dependencies are switched to a normal operating state, thereby performing DHTMLX component color marking processing on all DHTMLX component management dependencies; and then the DHTMLX component color marking state of all project task management indicators that do not belong to the DHTMLX component management dependency in the core different categories of project collaboration steps is released.

[0051] Compared with the prior art, the present invention has the following beneficial effects:

[0052] The present invention provides a data collaborative interaction method based on a DHTMLX Gantt chart. The method divides project collaborative steps into project collaborative steps of different categories in preset time periods, performs different forms of operation Gantt chart display processing on each project collaborative step of different categories, clusters whether the project collaborative steps of different categories are in project collaborative step error nodes and whether they belong to core project collaborative steps of different categories, and performs DHTMLX component color marking on the project collaborative steps of different categories and the core project collaborative steps of different categories in the project collaborative step error nodes, thereby avoiding the impact on other project collaborative steps of different categories and DHTMLX component errors; in addition, management personnel are used to check each terminal in the core project collaborative steps of different categories, determine the DHTMLX component management dependency relationship therein, perform separate DHTMLX component color marking on the DHTMLX component management dependency relationship, and release the DHTMLX component color marking status of all other project collaborative steps of different categories in the project collaborative steps. By dividing the project collaboration steps into different categories and performing zoning operations on the Gantt chart, the corresponding project task management indicators can be quickly and accurately located, and the normal DHTMLX components of other project task management indicators in the project collaboration steps can be avoided in time, thereby improving the efficiency and accuracy of the inspection of the project collaboration steps, ensuring the correctness of the overall DHTMLX components, and effectively promoting project task management. BRIEF DESCRIPTION OF THE DRAWINGS

[0053] Figure 1 A collaborative step diagram of a data collaborative interaction method based on a DHTMLX Gantt chart is provided by the present invention.

[0054] Figure 2 A module composition diagram for running a data collaborative interaction method based on a DHTMLX Gantt chart provided by the present invention. DETAILED DESCRIPTION

[0055] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0056] Example 1

[0057] like Figure 1 As shown, it is a collaborative step diagram of a data collaborative interaction method based on a DHTMLX Gantt chart provided by an embodiment of the present invention.

[0058] A data collaborative interaction method based on DHTMLX Gantt chart includes the following steps:

[0059] S100, dividing the project collaboration steps into different categories of project collaboration steps in a preset time period, and performing a first operation Gantt chart display process on all project task management indicators connected to each different category of project collaboration step, to obtain a data interaction mode for each project task management indicator; based on the data interaction mode, clustering whether the different category of project collaboration steps are at a project collaboration step error node;

[0060] S200, performing DHTMLX component color marking processing on all different types of project collaboration steps at the project collaboration step error node in the project collaboration step, and performing a second operation Gantt chart display processing on each different type of project collaboration step at the project collaboration step error node, to obtain participant detail processing information inside the different types of project collaboration steps at the project collaboration step error node; clustering the different types of project collaboration steps at the project collaboration step error node to determine whether they belong to core different types of project collaboration steps according to the participant detail processing information;

[0061] S300, according to the clustering result of whether the core different categories of project collaboration steps belong to the core different categories of project collaboration steps, adjusting the color marking state of the DHTMLX component of the corresponding different categories of project collaboration steps at the error node of the project collaboration step; the management personnel perform the third operation Gantt chart display processing on the core different categories of project collaboration steps to obtain the Gantt chart display result of each project task management indicator included in the core different categories of project collaboration steps;

[0062] S400, analyzing and processing the Gantt chart display result to determine the DHTMLX component management dependency relationship existing in the core different categories of project collaboration steps; after performing DHTMLX component color marking processing on the DHTMLX component management dependency relationship, the DHTMLX component color marking status of all project task management indicators that do not belong to the DHTMLX component management dependency relationship in the core different categories of project collaboration steps is released.

[0063] In S100, the project collaboration steps are divided into different types of project collaboration steps in a preset period, and a first operation Gantt chart display process is performed on all project task management indicators connected to each different type of project collaboration step to obtain a data interaction mode for each project task management indicator, including:

[0064] Obtain the specific time of all collaborative step nodes in the project collaborative steps, divide the project collaborative steps into different categories of project collaborative steps in preset time periods according to the specific time, and identify and classify the common collaborative step nodes between the different categories of project collaborative steps, and determine the DHTMLX component task features of all the common collaborative step nodes in the project collaborative steps;

[0065] The first operation Gantt chart display processing is performed on all project task management indicators connected to each different category of project collaboration steps, and all project task production report data and all project task financial report data of each project task management indicator within the preset processing collaboration step are obtained, which serves as the data interaction method.

[0066] The project coordination step includes multiple coordination step nodes and multiple project task management indicators. Each project task management indicator is connected to the corresponding coordination step node, and together they constitute the corresponding project coordination step structure. According to the specific time structure of all coordination step nodes in the project coordination step, the project coordination step is divided into sections to obtain different categories of project coordination steps in preset time periods. In this way, each different category of project coordination step is subsequently displayed as a separate project coordination step section for operation Gantt chart display, thereby improving the reliability of the operation Gantt chart display of each different category of project coordination step. Some of the coordination step nodes are used as common coordination step nodes to realize the connection between different categories of project coordination steps, and each common coordination step node is identified and classified, and the DHTMLX component task characteristics of each common coordination step node in the project coordination step are determined, so that the common coordination step node can be used as a benchmark in the future to switch the common coordination step node between the normal operation state and the calibrated state, and quickly realize the color marking processing of the DHTMLX component of each different category of project coordination step.

[0067] In S100, clustering whether the project collaboration steps of different categories are at a project collaboration step error node according to the data interaction mode includes:

[0068] Analyze and process all project task production report data and all project task financial report data to determine the detail processing efficiency of ordinary employees and management personnel in the first preset processing collaboration step corresponding to different types of project collaboration steps;

[0069] If the detail processing efficiency of the ordinary employee or the detail processing efficiency of the manager is greater than the preset maximum value of the detail processing efficiency of the participant, the clustering of the different categories of project collaboration steps is at the project collaboration step error node; otherwise, the clustering of the different categories of project collaboration steps does not belong to the project collaboration step error node.

[0070] When the efficiency of participant detail processing of project task management indicators increases suddenly in a short period of time, it indicates that the project task management indicators may have abnormal operation. By analyzing and processing all project task production report data and all project task financial report data obtained by sampling the project task management indicators contained in each different category of project collaboration step, the efficiency of detail processing of generation / management personnel of different categories of project collaboration steps as a whole within the first preset processing collaboration step is obtained. In this way, whether there is an abnormal situation of excessive participant detail processing in different categories of project collaboration steps can be clustered, so as to achieve accurate distinction and identification of whether each different category of project collaboration step is abnormal or not.

[0071] In S200, all different types of project collaboration steps at the project collaboration step error node in the project collaboration step are subjected to DHTMLX component color marking processing, and each different type of project collaboration step at the project collaboration step error node is subjected to second operation Gantt chart display processing, to obtain detailed processing information of participants inside different types of project collaboration steps at the project collaboration step error node, including:

[0072] According to the respective flow step information of all common coordination step nodes of different types of project coordination steps at the project coordination step error node, all the common coordination step nodes are switched to the normal operation state, so as to mark the different types of project coordination steps at the project coordination step error node and the different types of project coordination steps not at the project coordination step error node in the project coordination step with the DHTMLX component color;

[0073] The second operation Gantt chart display processing is performed on each different category of project collaboration step that is at the error node of the project collaboration step, and the participating DHTMLX component number information and the participating DHTMLX component specific task information transmitted between the internal different project task management indicators of the different categories of project collaboration steps that are at the error node of the project collaboration step are obtained, which is used as the detailed processing information of the participant.

[0074] Through the above method, the DHTMLX component task characteristics of all common collaborative step nodes associated with different categories of project collaborative steps at the project collaborative step error node are determined, so that all associated common collaborative step nodes can be switched to normal operation based on the DHTMLX component task characteristics, thereby realizing color marking of the DHTMLX components of different categories of project collaborative steps at the project collaborative step error node, avoiding data interaction between different categories of project collaborative steps at the project collaborative step error node and other different categories of project collaborative steps. In addition, after color marking of the DHTMLX components of different categories of project collaborative steps at the project collaborative step error node, a separate second operation Gantt chart display processing can be specially performed on them, effectively reducing the amount of DHTMLX components processed by the second operation Gantt chart display processing and ensuring the reliability of the data operation Gantt chart display processing of the second operation Gantt chart display processing.

[0075] In S200, clustering the different types of project collaboration steps at the project collaboration step error node to determine whether they belong to the core different types of project collaboration steps according to the participant detail processing information includes:

[0076] Parse the DHTMLX component number information to determine whether the DHTMLX components transmitted between different project task management indicators include a preset list of participants;

[0077] Analyze and process the specific task information of the participating DHTMLX component to determine whether all DHTMLX components with a preset list of participants have the same DHTMLX component task in the second preset processing collaboration step; if so, cluster the different categories of project collaboration steps at the error nodes of the project collaboration steps as core different categories of project collaboration steps; otherwise, cluster the different categories of project collaboration steps at the error nodes of the project collaboration steps do not belong to the core different categories of project collaboration steps.

[0078] By performing content parsing processing on the DHTMLX component obtained by the Gantt chart display processing of the second operation, it is clustered whether the DHTMLX component contains a preset list of participants; wherein, the specific tasks participating in the DHTMLX component are identified to determine whether all DHTMLX component tasks with a preset list of participants are the same or not, thereby reliably identifying and clustering whether the current collaborative steps of different categories of projects belong to the core collaborative steps of different categories of projects.

[0079] In S300, according to the clustering result of whether the project collaboration step belongs to the core different categories, the color marking state of the DHTMLX component of the project collaboration step of the different categories at the error node of the project collaboration step is adjusted, specifically including:

[0080] When the different-category project collaboration step at the project collaboration step error node does not belong to the core different-category project collaboration step, all the common collaboration step nodes of the different-category project collaboration step at the project collaboration step error node are switched to the marked state according to their respective flow step information;

[0081] When the different categories of project collaboration steps at the project collaboration step error node belong to the core different categories of project collaboration steps, the current normal operating status of all common collaboration step nodes is kept unchanged according to the respective flow step information of all common collaboration step nodes of the different categories of project collaboration steps at the project collaboration step error node.

[0082] By keeping the current normal operating state of all the associated common collaboration step nodes of the core different categories of project collaboration steps unchanged, and switching all the associated common collaboration step nodes of the different categories of project collaboration steps of the non-core different categories of project collaboration steps to the calibrated state, the investigation scope of the different categories of project collaboration steps in the project collaboration steps can be further narrowed, thereby reducing the amount of DHTMLX components processed by the subsequent Gantt chart display and ensuring that the different categories of project collaboration steps of other non-core different categories of project collaboration steps are connected to the Internet in time, thereby ensuring the normal DHTMLX components of the project collaboration steps.

[0083] In S300, the manager performs the third operation Gantt chart display processing on the core different categories of project collaboration steps to obtain the Gantt chart display results of each project task management indicator included in the core different categories of project collaboration steps, specifically including:

[0084] According to the DHTMLX component task characteristics of all project task management indicators contained in the core different categories of project collaboration steps, instruct the manager to send a preset request message to each project task management indicator, and operate the Gantt chart display to intercept each project task management indicator about the preset request message, and return the Gantt chart display result to the manager for feedback

[0085] Through the above, all project task management indicators included in the core different categories of project collaboration steps are calibrated for the DHTMLX component task characteristics, and managers are set to induce each project task management indicator to interact with the managers, so as to further identify whether each project task management indicator belongs to the DHTMLX component management dependency.

[0086] In S400, the Gantt chart display result is analyzed and processed to determine the DHTMLX component management dependency relationship existing in the collaborative steps of the core different categories of projects, specifically including:

[0087] Perform artificial intelligence screening on the Gantt chart display results to be fed back, and obtain the management dependency points of the Gantt chart display results to be fed back of each project task management indicator;

[0088] Analyze and process the management dependency point to determine whether there is a human error in the management dependency point; if so, determine the corresponding project task management indicator as belonging to the DHTMLX component management dependency; and determine the DHTMLX component task characteristics of all DHTMLX component management dependencies in the core different categories of project collaboration steps and the DHTMLX component task characteristics of all project task management indicators that do not belong to the DHTMLX component management dependency;

[0089] Through the artificial intelligence screening and management dependency point identification processing of the Gantt chart display results to be fed back by each project task management indicator, it is possible to accurately identify the DHTMLX component management dependencies existing in the core collaboration steps of different categories of projects, and identify the DHTMLX component task features of DHTMLX component management dependencies and non-DHTMLX component management dependencies, so as to facilitate the subsequent accurate color marking of DHTMLX components and correction processing of DHTMLX components in DHTMLX component management dependencies.

[0090] In S400, after the DHTMLX component management dependency is processed with DHTMLX component color marking, the DHTMLX component color marking status of all project task management indicators that do not belong to the DHTMLX component management dependency in the core different categories of project collaboration steps is released, specifically including:

[0091] According to the DHTMLX component task characteristics of all project task management indicators that do not belong to the DHTMLX component management dependency relationship in the core different categories of project collaboration steps, DHTMLX component correction processing is performed on all project task management indicators that do not belong to the DHTMLX component management dependency relationship;

[0092] According to the DHTMLX component task characteristics of all DHTMLX component management dependencies in the core different categories of project collaboration steps, the DHTMLX component task characteristics of all collaborative step nodes connected to all DHTMLX component management dependencies are determined, so that all collaborative step nodes connected to all DHTMLX component management dependencies are switched to normal operating states, thereby performing DHTMLX component color marking processing on all DHTMLX component management dependencies; then the DHTMLX component color marking status of all project task management indicators that do not belong to the DHTMLX component management dependencies in the core different categories of project collaboration steps is released.

[0093] By switching all the collaborative step nodes connected to all the DHTMLX component management dependencies to the normal operating state, it is possible to effectively avoid the DHTMLX component management dependencies from continuing to search for DHTMLX component errors in other project task management indicators, and it is also possible to perform DHTMLX component color marking and DHTMLX component correction processing on the DHTMLX component management dependencies in a targeted manner, thereby quickly and accurately locating the DHTMLX component errors without the need to perform a full process analysis of the project collaborative steps.

[0094] Example 2

[0095] like Figure 2 As shown, a module composition diagram of a data collaborative interaction method based on a DHTMLX Gantt chart provided by an embodiment of the present invention includes:

[0096] The module for dividing the collaborative steps of different categories of projects and displaying the Gantt chart of operations is used to divide the collaborative steps of the projects into collaborative steps of different categories of projects in preset time periods, and to perform the first operation Gantt chart display processing on all the project task management indicators connected to each collaborative step of different categories of projects, so as to obtain the data interaction mode of each project task management indicator;

[0097] A first different-category project collaboration step clustering module is used to cluster whether the different-category project collaboration steps are at a project collaboration step error node according to the data interaction mode;

[0098] The first different types of project collaboration steps DHTMLX component color marking and operation Gantt chart display module is used to perform DHTMLX component color marking processing on all different types of project collaboration steps at the project collaboration step error node in the project collaboration step, and perform the second operation Gantt chart display processing on each different type of project collaboration step at the project collaboration step error node to obtain the participant detail processing information inside the different types of project collaboration steps at the project collaboration step error node;

[0099] The second different-category project collaboration step clustering module is used to cluster different-category project collaboration steps at the project collaboration step error node whether they belong to the core different-category project collaboration steps according to the participant detail processing information;

[0100] The second module for color marking and operation of Gantt chart display of DHTMLX components of different types of project collaboration steps is used to adjust the color marking status of DHTMLX components of different types of project collaboration steps at the error node of the project collaboration step according to the clustering result of whether the steps belong to the core different types of project collaboration steps; the management personnel perform the third operation Gantt chart display processing on the core different types of project collaboration steps to obtain the Gantt chart display result of each project task management indicator included in the core different types of project collaboration steps;

[0101] The third different categories of project coordination step clustering module is used to analyze and process the Gantt chart display results to determine the DHTMLX component management dependency relationship existing in the core different categories of project coordination steps;

[0102] The DHTMLX component color marking state adjustment module is used to remove the DHTMLX component color marking state of all project task management indicators that do not belong to the DHTMLX component management dependency in the core different categories of project collaboration steps after performing DHTMLX component color marking processing on the DHTMLX component management dependency.

[0103] In summary, the present invention provides a data collaborative interaction method based on a DHTMLX Gantt chart, which divides the project collaborative steps into different categories of project collaborative steps in preset time periods, performs different forms of operation Gantt chart display processing on each different category of project collaborative steps, clusters whether the different categories of project collaborative steps are in the project collaborative step error nodes and whether they belong to the core different categories of project collaborative steps, and performs DHTMLX component color marking on the different categories of project collaborative steps in the project collaborative step error nodes and the core different categories of project collaborative steps, thereby avoiding the impact on other different categories of project collaborative steps and DHTMLX component errors; and also uses management personnel to check each terminal in the core different categories of project collaborative steps, determine the DHTMLX component management dependency relationship therein, perform separate DHTMLX component color marking on the DHTMLX component management dependency relationship, and release the DHTMLX component color marking status of all other different categories of project collaborative steps in the project collaborative steps. By dividing the project collaboration steps into different categories and performing zoning operations on the Gantt chart, the corresponding project task management indicators can be quickly and accurately located, and the normal DHTMLX components of other project task management indicators in the project collaboration steps can be avoided in time, thereby improving the efficiency and accuracy of the inspection of the project collaboration steps, ensuring the correctness of the overall DHTMLX components, and effectively promoting project task management.

[0104] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A data collaborative interaction method based on DHTMLX Gantt chart, characterized in that: The following steps are involved: S100, dividing the project collaboration steps into different categories of project collaboration steps in a preset time period, and performing a first operation Gantt chart display process on all project task management indicators connected to each different category of project collaboration step, to obtain a data interaction mode for each project task management indicator; according to the data interaction mode, clustering whether the different categories of project collaboration steps are at a project collaboration step error node; The method comprises: obtaining specific time of all collaborative step nodes in the project collaborative step, dividing the project collaborative step into different categories of project collaborative steps in preset time periods according to the specific time, identifying and classifying the common collaborative step nodes between the different categories of project collaborative steps, and determining the DHTMLX component task features of all the common collaborative step nodes in the project collaborative step; Performing a first operation Gantt chart display processing on all project task management indicators connected to each different category of project collaboration step, obtaining all project task production report data and all project task financial report data of each project task management indicator within the preset processing collaboration step, as the data interaction method; Analyze and process all project task production report data and all project task financial report data to determine the detail processing efficiency of ordinary employees and management personnel in the first preset processing collaboration step corresponding to different types of project collaboration steps; If the detail processing efficiency of ordinary employees or the detail processing efficiency of managers is greater than the maximum value of the preset participant detail processing efficiency, the clustering of the different categories of project collaboration steps is at a project collaboration step error node; otherwise, the clustering of the different categories of project collaboration steps does not belong to a project collaboration step error node; S200, performing DHTMLX component color marking processing on all different types of project collaboration steps at the project collaboration step error node in the project collaboration step, and performing a second operation Gantt chart display processing on each different type of project collaboration step at the project collaboration step error node, to obtain participant detail processing information inside the different types of project collaboration steps at the project collaboration step error node; clustering the different types of project collaboration steps at the project collaboration step error node to determine whether they belong to core different types of project collaboration steps according to the participant detail processing information; The method comprises: according to the respective flow step information of all the common coordination step nodes of the different types of project coordination steps at the project coordination step error node, switching the said all common coordination step nodes to the normal operation state, thereby marking the different types of project coordination steps at the project coordination step error node and the different types of project coordination steps not at the project coordination step error node in the said project coordination steps with DHTMLX component colors; Performing a second operation Gantt chart display process on each different type of project collaboration step at an error node of the project collaboration step, obtaining the participating DHTMLX component number information and the participating DHTMLX component specific task information transmitted between the internal different project task management indicators of the different types of project collaboration steps at the error node of the project collaboration step, and using this as the participant detail processing information; Parsing the participating DHTMLX component number information to determine whether the DHTMLX components transmitted between different project task management indicators include a preset list of participants; Analyze and process the specific task information of the participating DHTMLX components to determine whether all DHTMLX components with a preset list of participants have the same DHTMLX component task in the second preset processing coordination step; if so, cluster the different categories of project coordination steps at the error node of the project coordination step as core different categories of project coordination steps; otherwise, cluster the different categories of project coordination steps at the error node of the project coordination step do not belong to the core different categories of project coordination steps; S300, according to the clustering result of whether the steps belong to the core different categories of project collaboration, adjusting the color marking state of the DHTMLX component of the corresponding different categories of project collaboration steps at the error node of the project collaboration step; the management personnel perform the third operation Gantt chart display processing on the core different categories of project collaboration steps to obtain the Gantt chart display result of each project task management indicator included in the core different categories of project collaboration steps; S400, analyzing and processing the Gantt chart display result to determine the DHTMLX component management dependency relationship existing in the core different categories of project collaboration steps; after performing DHTMLX component color marking processing on the DHTMLX component management dependency relationship, releasing the DHTMLX component color marking status of all project task management indicators that do not belong to the DHTMLX component management dependency relationship in the core different categories of project collaboration steps.

2. A data collaborative interaction method based on DHTMLX Gantt chart as claimed in claim 1, characterized in that: The S300 includes: When the different-category project collaboration step at the project collaboration step error node does not belong to the core different-category project collaboration step, all the common collaboration step nodes of the different-category project collaboration steps at the project collaboration step error node are switched to the marked state according to their respective flow step information; When the different categories of project collaboration steps at the project collaboration step error node belong to the core different categories of project collaboration steps, then according to the respective flow step information of all the common collaboration step nodes of the different categories of project collaboration steps at the project collaboration step error node, the current normal operating status of all the common collaboration step nodes is kept unchanged.

3. A data collaborative interaction method based on DHTMLX Gantt chart as claimed in claim 2, characterized in that: The S300 further includes: According to the respective DHTMLX component task characteristics of all project task management indicators included in the core different categories of project collaboration steps, the management personnel are instructed to send preset request messages for each project task management indicator respectively, and the Gantt chart display is operated to intercept the preset request message for each project task management indicator, and the Gantt chart display results to be fed back are marked to the management personnel.

4. A data collaborative interaction method based on DHTMLX Gantt chart as claimed in claim 3, characterized in that: The S400 includes: Performing artificial intelligence screening processing on the Gantt chart display results to be fed back, and obtaining management dependency points of the Gantt chart display results to be fed back of each project task management indicator; The management dependency point is analyzed and processed to determine whether there is a human error in the management dependency point; if so, the corresponding project task management indicator is determined as belonging to the DHTMLX component management dependency; and the DHTMLX component task characteristics of all DHTMLX component management dependencies in the core different categories of project collaboration steps and the DHTMLX component task characteristics of all project task management indicators that do not belong to the DHTMLX component management dependency are determined.

5. A data collaborative interaction method based on DHTMLX Gantt chart as claimed in claim 4, characterized in that: The S400 further includes: According to the DHTMLX component task characteristics of all project task management indicators that do not belong to the DHTMLX component management dependency relationship in the core different categories of project collaboration steps, DHTMLX component correction processing is performed on all project task management indicators that do not belong to the DHTMLX component management dependency relationship; According to the DHTMLX component task characteristics of all DHTMLX component management dependencies in the core different categories of project collaboration steps, the DHTMLX component task characteristics of all collaboration step nodes connected to all DHTMLX component management dependencies are determined, so that all collaboration step nodes connected to all DHTMLX component management dependencies are switched to a normal operating state, thereby performing DHTMLX component color marking processing on all DHTMLX component management dependencies; and then the DHTMLX component color marking state of all project task management indicators that do not belong to the DHTMLX component management dependency in the core different categories of project collaboration steps is released.