A method and system for analyzing engineering data for engineering management

By obtaining and analyzing monitoring information, meteorological data and building layout in engineering project management, identifying dangerous areas and key actions, a refined warning of high-altitude fall risks has been achieved, solving the problem of prevention of high-altitude fall accidents in the existing technology, and improving the Safety management level and personnel safety guarantee at the construction site.

CN118711256BActive Publication Date: 2024-12-06ZHONGMEI ENGINEERING GROUP LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411186584.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-28
Publication Date
2024-12-06
Estimated Expiration
2044-08-28

AI Technical Summary

Technical Problem

In engineering project management, it is difficult for the existing technology to effectively prevent and early warning of high-altitude fall accidents, resulting in threats to personnel safety.

Method used

By obtaining engineering monitoring information, extracting personnel behavior images and project building edge information, dividing dangerous areas, analyzing key action information, determining whether there is a risk of falling from high altitudes, and providing early warnings. Combining meteorological data and building layout, accurately calculate the light transmittance, identify edge information, and enhance the accuracy and reliability of the early warning system.

Benefits of technology

It significantly improves the safety management level of the construction site, effectively prevents the occurrence of high-altitude fall accidents, provides strong guarantees for the safety of people's lives, and improves the accuracy and reliability of the early warning system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118711256B_ABST
    Figure CN118711256B_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of engineering data analysis, and in particular to an engineering data analysis method and system for engineering management. The method includes: obtaining engineering monitoring information, extracting personnel behavior images based on the monitoring information; obtaining engineering building edge information based on the monitoring information, dividing dangerous areas based on the engineering building edge information, and obtaining the range of dangerous areas; analyzing the personnel behavior images based on the dangerous area range to obtain key action information; judging whether there is dangerous behavior based on the key action information, and if so, issuing a high-altitude fall warning. By dividing the edges of engineering buildings into regions, the accurate determination of dangerous areas is achieved, and the personnel behavior is analyzed and determined, and corresponding high-altitude fall warning measures can be effectively taken according to the specific behavior of the personnel, effectively ensuring personnel safety and improving the level of engineering safety management.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of engineering data analysis, and in particular to an engineering data analysis method and system for engineering management. Background Art

[0002] With the country's continuous investment in infrastructure construction, the accelerated urbanization process has led to an increasing demand for urban construction. Engineering management has also become an important part of engineering project construction. Scientific and orderly management of engineering project construction helps to ensure the quality and reliability of engineering construction.

[0003] However, in the process of managing construction projects, the prevention of people falling from heights is simply achieved by setting up protective nets and reminding construction personnel to take safety precautions. However, when danger may occur, no effective measures are taken to provide warnings for high-altitude falls, which can cause harm to personnel. Summary of the invention

[0004] The present application provides an engineering data analysis method and system for engineering management to solve the above problems.

[0005] In a first aspect, the present application provides an engineering data analysis method for engineering management, the method comprising:

[0006] Acquire engineering monitoring information, and extract personnel behavior images based on the monitoring information;

[0007] According to the monitoring information, edge information of the engineering building is obtained, and according to the edge information of the engineering building, the dangerous area is divided to obtain the range of the dangerous area;

[0008] Analyze the personnel behavior image according to the range of the dangerous area to obtain key action information;

[0009] Based on the key action information, determine whether there is any dangerous behavior. If so, issue a high-altitude fall warning.

[0010] Through the above technical solution, the transmittance of each area of ​​the engineering building is accurately calculated by comprehensively analyzing the monitoring information, meteorological data and engineering building layout, and the edge information of the engineering building is accurately identified based on this. Combined with the personnel behavior image, several dangerous areas can be scientifically divided and their scope can be determined, so as to achieve refined early warning and management of the risk of falling from height. This not only improves the safety management level of the construction site, but also effectively prevents the occurrence of high-altitude falling accidents, providing a strong guarantee for the life safety of personnel. At the same time, the influence of lighting conditions on transmittance and edge recognition is taken into account, which enhances the accuracy and reliability of the early warning system.

[0011] Optionally, obtaining engineering building edge information according to the monitoring information, dividing the dangerous area according to the engineering building edge information, and obtaining the range of the dangerous area includes:

[0012] Determine the layout of the engineering building according to the monitoring information;

[0013] Obtain meteorological data to obtain light intensity and angle;

[0014] Analyze the layout of the engineering building according to the light intensity and the light angle to obtain the light transmittance of each area of ​​the engineering building;

[0015] Determine whether the light transmittance of each area reaches a preset light transmittance, and if so, determine each area of ​​the engineering building that reaches the preset light transmittance as the edge information of the engineering building;

[0016] The edge of the engineering building is divided according to the engineering building edge information and the personnel behavior image to obtain a number of dangerous areas, and the range of the dangerous area is obtained according to the several dangerous areas.

[0017] Through the above technical solution, the transmittance of each area of ​​the engineering building is accurately calculated by comprehensively analyzing the monitoring information, meteorological data and engineering building layout, and the edge information of the engineering building is accurately identified based on this. Combined with the personnel behavior image, several dangerous areas can be scientifically divided and their scope can be determined, so as to achieve refined early warning and management of the risk of falling from height. This not only improves the safety management level of the construction site, but also effectively prevents the occurrence of high-altitude falling accidents, providing a strong guarantee for the life safety of personnel. At the same time, the influence of lighting conditions on transmittance and edge recognition is taken into account, which enhances the accuracy and reliability of the early warning system.

[0018] Optionally, analyzing the personnel behavior image according to the range of the dangerous area to obtain key action information includes:

[0019] According to the range of the dangerous area, the personnel behavior image is cropped to obtain the dangerous area range.

[0020] surrounding behavioral images;

[0021] Analyze the behavior image of the dangerous area, classify the behavior of people in the dangerous area, and determine the type of people's behavior;

[0022] The key action information is obtained according to the personnel behavior type.

[0023] Through the above technical solution, by cropping the personnel behavior images in the dangerous area, the analysis scope is effectively narrowed and the processing efficiency is improved; using the computer behavior recognition algorithm, the cropped dangerous area behavior images are deeply analyzed to accurately classify personnel behaviors and determine the types of personnel behaviors; based on the classification results, key action information is further extracted to achieve refined early warning and management of high-altitude fall risks. It not only improves the safety monitoring level of the construction site, but also effectively prevents the occurrence of high-altitude fall accidents, providing a strong guarantee for the life safety of construction workers.

[0024] Optionally, judging whether there is a dangerous behavior according to the key action information includes:

[0025] According to the meteorological data, wind strength is obtained;

[0026] Analyze the key action information to determine the speed and direction of movement of the personnel;

[0027] Determine the movement trend of the personnel according to the movement speed and the movement direction of the personnel;

[0028] Predicting the actual location of the personnel based on the movement trend of the personnel and the wind strength;

[0029] Matching the actual stay position of the person with the preset person position to determine whether the actual stay position of the person is consistent with the preset person position;

[0030] If the actual stay position of the person is consistent with the preset person position, it is determined whether there is any dangerous behavior based on the actual stay position of the person.

[0031] Through the above technical solution, by comprehensively analyzing meteorological data and key action information of personnel, it is possible to accurately predict the actual location of personnel, and then determine whether the personnel have dangerous behavior. It improves the accuracy and real-time monitoring of personnel behavior, helps to timely discover and prevent potential safety hazards, and ensure personnel safety. At the same time, matching the predicted location with the preset location further enhances the accuracy and reliability of monitoring, providing strong support for safety management.

[0032] Optionally, if the actual stay position of the person is consistent with the preset person position, judging whether there is a dangerous behavior according to the actual stay position of the person includes:

[0033] Analyze the behavior image of the dangerous area to obtain building material information and personnel information;

[0034] According to the building material information, the material volume, material type, material density and material size of the building material are obtained;

[0035] According to the personnel information, obtaining the personnel volume;

[0036] Determining the weight of the building material based on the density of the material and the volume of the material;

[0037] Obtaining wind direction data according to the meteorological data;

[0038] According to the behavior image of the dangerous area, the relative positions of the personnel and the building materials are obtained;

[0039] Determining the influence of the wind intensity on the relative position according to the material size, the material weight and the volume of the personnel;

[0040] Matching the impact degree with a preset impact degree to determine whether the impact degree is consistent with the preset impact degree;

[0041] If the impact degree matches the preset impact degree, it is determined whether there is an interaction between the actual staying position of the person and the wind strength according to the wind direction. If there is such an interaction, it is determined that a dangerous behavior exists.

[0042] Through the above technical solution, firstly, through image analysis technology, detailed information of building materials and personnel is accurately extracted, including the volume, type, density and size of building materials, as well as the volume of personnel. Secondly, the weight of building materials is calculated using this information, and the relative position relationship between personnel and building materials is further analyzed in combination with the wind direction information in the meteorological data. By comprehensively considering the material size, weight and volume of personnel, the degree of influence of wind intensity on relative position is accurately evaluated, and matched with the preset degree of influence, so as to determine whether there is potential dangerous behavior. Through multi-dimensional data analysis and refined evaluation methods, the ability to identify and warn of dangerous behaviors is significantly improved, which helps to take timely measures to ensure the safety of personnel and property.

[0043] Optionally, determining the degree of influence of the wind intensity on the relative position according to the material size, the material weight and the volume of the person includes:

[0044] According to the personnel behavior image, the body contour of the personnel, the initial distance between the personnel and the dangerous area, and the walking time of the personnel are obtained;

[0045] Determine the overall center of gravity of the person and the cargo based on the person's body contour, the material size, the person's behavior, the person's volume, and the material weight;

[0046] Determine whether the overall center of gravity position exists within the dangerous area, and if so, determine the moving direction of the overall center of gravity position according to the walking direction of the personnel;

[0047] Determine the walking distance of the personnel according to the walking time and walking speed of the personnel;

[0048] Determine whether the distance the person has walked is greater than the initial distance between the person and the dangerous area. If greater, determine the degree of influence of the wind intensity on the relative position based on the overall center of gravity position, the moving direction of the overall center of gravity position and the distance the person has walked.

[0049] Through the above technical solution, firstly, through the analysis of personnel behavior images, detailed personnel and environmental information, including body contours, initial distances, and walking time, is obtained, providing an accurate data basis for subsequent calculations. Secondly, by comprehensively considering the physical characteristics of personnel, cargo attributes, and personnel behavior, the overall center of gravity position of personnel and cargo is accurately determined. Furthermore, the relationship between the overall center of gravity position and the dangerous area is determined, and the changes in the center of gravity position and the possible entry into the dangerous area are predicted based on the direction and speed of the personnel's movement. Finally, the degree of influence of wind intensity on relative position is evaluated, providing a scientific basis for formulating targeted safety measures in the actual working environment. A comprehensive and dynamic assessment of personnel work safety is achieved, which helps to improve the safety and efficiency of the working environment.

[0050] Optionally, determining the degree of influence of the wind intensity on the relative position according to the material size, the material weight and the volume of the person includes:

[0051] According to the meteorological data, real-time wind speed is obtained;

[0052] According to the volume of the personnel, the weight of the personnel and the area exposed to wind of the personnel are obtained;

[0053] According to the material size, the surface area of ​​the material is obtained;

[0054] According to the real-time wind speed, the surface area of ​​the material, the windward area of ​​the personnel, the weight of the material and the weight of the personnel, the influence degree of the relative position is obtained, referring to the following formula:

[0055] ;

[0056] in, is the influence strength of the relative position, is the air density, is the real-time wind speed, is the surface area of ​​the material, is the area exposed to wind by the personnel, is the weight of the material, is the weight of the person.

[0057] Through the above technical solution, the real-time wind speed is obtained through meteorological data, ensuring the accuracy and timeliness of wind speed information. Secondly, the physical characteristics of personnel and materials are taken into account, including personnel volume, personnel weight, personnel windward area, material size and material surface area. By combining these factors with the real-time wind speed and applying physical formulas for calculation, the degree of influence of relative position, that is, the potential influence of wind force on the relative position of personnel and materials, is accurately obtained. Not only does it improve the accuracy of the assessment, but it can also provide a scientific and quantitative basis for actual operations, which helps to formulate more accurate and effective safety measures, thereby ensuring the safety of the working environment.

[0058] Optionally, judging whether there is a dangerous behavior according to the key action information includes:

[0059] According to the material size, the material height and the material wind-exposed area are obtained;

[0060] According to the material height, the material weight, the material position, the ground roughness, the material windward area and the wind strength, the relative displacement of the material is obtained, referring to the following formula:

[0061] ;

[0062] in, is the relative displacement of the material, is the air density, is the real-time wind speed, is the wind-exposed area of ​​the material, is the material height, is the ground roughness, The weight of the material, is the acceleration due to gravity;

[0063] It is determined whether the relative displacement of the material is greater than the preset relative displacement of the material. If the relative displacement of the material is greater than the preset relative displacement of the material, it is determined that a dangerous behavior exists.

[0064] Through the above technical solution, a variety of key factors affecting material stability are comprehensively considered and quantitatively analyzed through specific mathematical models. Not only the direct force factor of wind strength is added, but also the physical properties of the material (such as size, weight), location information and ground conditions (such as roughness) are added. By comprehensively calculating these factors, the stability of materials in specific environments can be more accurately predicted and judged, thereby more effectively identifying potential dangerous behaviors and providing a scientific basis for timely preventive measures. Comprehensive consideration of multiple factors and quantitative evaluation improves the accuracy and reliability of dangerous behavior identification, which helps to improve the overall safety management level.

[0065] Optionally, determining whether there is an interaction between the direction of movement of the person and the wind strength according to the wind direction, and determining that there is a dangerous behavior if there is such an interaction, includes:

[0066] According to the material size, the wind-exposed area of ​​the material is obtained;

[0067] According to the volume of the personnel, the wind-exposed area of ​​the personnel is obtained;

[0068] According to the relative position of the personnel and the material, the wind-exposed area of ​​the material, and the wind-exposed area of ​​the personnel, the wind-exposed area of ​​the material and the personnel are obtained;

[0069] According to the wind direction and the personnel walking direction, a wind direction vector and a personnel walking direction vector are obtained;

[0070] Determine the angle between the wind direction vector and the personnel walking direction vector according to the wind direction vector and the personnel walking direction vector;

[0071] According to the wind strength, the material weight, the personnel weight and the vector angle, the stability of the personnel is calculated, referring to the following formula:

[0072] ;

[0073] in, For the stability of the personnel, is the air density, is the real-time wind speed, The area exposed to wind for the materials and personnel mentioned above, is the vector angle, is the weight of the person, is the weight of the material;

[0074] The personnel stability is matched with the preset personnel stability to determine whether the personnel stability is consistent with the preset personnel stability. If they are consistent, it is determined that there is an interaction between the personnel's walking direction and the wind intensity. Based on the interaction, it is determined that there is a dangerous behavior.

[0075] Through the above technical solution, a variety of key factors affecting personnel stability are comprehensively calculated, including the wind-exposed area of ​​materials, the wind-exposed area of ​​personnel, the relative relationship between wind direction and personnel movement direction, wind strength, material weight, and personnel weight, and the stability of personnel is calculated. Not only does it improve the accuracy of personnel stability assessment, but it also monitors and judges in real time whether there are potential dangers in the behavior of personnel in a specific environment, thereby effectively preventing accidents. In addition, by matching the calculated personnel stability with the preset stability threshold, unstable or dangerous behavior patterns can be quickly identified, providing a scientific basis for timely safety measures, greatly enhancing the safety of the working environment.

[0076] In a second aspect, the present application provides an engineering data analysis system for engineering management, the system comprising:

[0077] Image extraction module, used to obtain engineering monitoring information and extract personnel behavior images based on the monitoring information;

[0078] The area range determination module is used to obtain the edge information of the engineering building according to the monitoring information, divide the dangerous area according to the edge information of the engineering building, and obtain the range of the dangerous area;

[0079] The action information determination module is used to analyze the personnel behavior image according to the scope of the dangerous area and obtain key action information;

[0080] The high-altitude warning module is used to determine whether there is any dangerous behavior based on key action information. If so, a high-altitude fall warning will be issued.

[0081] Optional, area range determination module, specifically used for:

[0082] Determine the layout of engineering buildings based on monitoring information;

[0083] Obtain meteorological data to obtain light intensity and angle;

[0084] Analyze the layout of the project building according to the light intensity and light angle, and obtain the light transmittance of each area of ​​the project building;

[0085] Determine whether the light transmittance of each area reaches a preset light transmittance, and if so, determine each area of ​​the engineering building that reaches the preset light transmittance as the engineering building edge information;

[0086] The edge of the engineering building is divided according to the edge information of the engineering building and the personnel behavior image to obtain a number of dangerous areas, and the range of the dangerous area is obtained according to the several dangerous areas.

[0087] Optionally, the action information determination module is specifically used to:

[0088] According to the scope of the dangerous area, the personnel behavior image is cropped to obtain the behavior image within the dangerous area;

[0089] Analyze the behavior images within the dangerous area, classify the behaviors of people within the dangerous area, and determine the types of people's behaviors;

[0090] According to the type of personnel behavior, key action information is obtained.

[0091] Optional, area range determination module, specifically used for:

[0092] According to the meteorological data, the wind strength is obtained;

[0093] Analyze key action information to determine the speed and direction of movement of personnel;

[0094] Determine the movement trend of personnel based on their movement speed and direction;

[0095] Predict the actual location of people based on their movement trends and wind strength;

[0096] Match the actual location of the person with the preset location of the person to determine whether the actual location of the person is consistent with the preset location of the person;

[0097] If the actual location of the person is consistent with the preset location of the person, it is determined whether there is any dangerous behavior based on the actual location of the person.

[0098] Optional, area range determination module, specifically used for:

[0099] Analyze the behavior images of the dangerous area to obtain the information of building materials and personnel;

[0100] According to the building material information, the material volume, material type, material density and material size of the building material are obtained;

[0101] According to the personnel information, the personnel volume is obtained;

[0102] Determine the weight of building materials based on material density and material volume;

[0103] According to the meteorological data, wind direction data is obtained;

[0104] According to the behavior image of the dangerous area, the relative position of personnel and building materials is obtained;

[0105] Determine the degree to which wind intensity affects relative positions based on material size, material weight, and personnel volume;

[0106] Match the impact degree with the preset impact degree to determine whether the impact degree is consistent with the preset impact degree;

[0107] If the impact degree matches the preset impact degree, it is determined whether there is an interaction between the actual stay position of the person and the wind strength based on the wind direction. If there is an interaction, it is determined that a dangerous behavior exists.

[0108] Optional, area range determination module, specifically used for:

[0109] According to the personnel behavior image, the personnel body outline, the initial distance between the personnel and the dangerous area, and the personnel movement time are obtained;

[0110] Determine the overall center of gravity of personnel and cargo based on the personnel's body contours, material dimensions, personnel behavior, personnel volume, and material weight;

[0111] Determine whether the overall center of gravity is within the dangerous area. If so, determine the direction of movement of the overall center of gravity based on the direction of personnel movement.

[0112] Determine the distance people walk based on their walking time and walking speed;

[0113] Determine whether the distance the personnel have walked is greater than the initial distance between the personnel and the dangerous area. If so, determine the degree of influence of wind intensity on the relative position based on the overall center of gravity position, the direction of movement of the overall center of gravity position and the distance the personnel have walked.

[0114] Optional, area range determination module, specifically used for:

[0115] Get real-time wind speed based on meteorological data;

[0116] According to the volume of personnel, obtain the weight of personnel and the area exposed to wind;

[0117] According to the material size, the surface area of ​​the material is obtained;

[0118] According to the real-time wind speed, material surface area, personnel windward area, material weight and personnel weight, the influence of relative position is obtained, referring to the following formula:

[0119] ;

[0120] in, is the influence strength of relative position, is the air density, is the real-time wind speed, is the surface area of ​​the material, The area of ​​personnel exposed to wind, is the material weight, The weight of the person.

[0121] Optional, area range determination module, specifically used for:

[0122] According to the behavior image of the dangerous area, the material position within the dangerous area and the ground roughness within the dangerous area are obtained;

[0123] According to the material size, the material height and the wind-exposed area of ​​the material are obtained;

[0124] According to the material height, material weight, material location, ground roughness, material windward area and wind strength, the relative displacement of the material is obtained, referring to the following formula:

[0125] ;

[0126] in, is the relative displacement of the material, is the air density, is the real-time wind speed, is the wind-exposed area of ​​the material, is the material height, The roughness of the ground. Material weight, is the acceleration due to gravity;

[0127] Determine whether the relative displacement of the material is greater than the preset relative displacement of the material. If the relative displacement of the material is greater than the preset relative displacement of the material, it is determined that there is a dangerous behavior.

[0128] Optional, area range determination module, specifically used for:

[0129] According to the material size, the wind-exposed area of ​​the material is obtained;

[0130] According to the volume of personnel, the wind-exposed area of ​​personnel is obtained;

[0131] According to the relative position of personnel and materials, the wind-exposed area of ​​materials and the wind-exposed area of ​​personnel, the wind-exposed area of ​​materials and personnel is obtained;

[0132] According to the wind direction and the direction of personnel movement, the wind direction vector and the personnel movement direction vector are obtained;

[0133] According to the wind direction vector and the personnel walking direction vector, determine the angle between the wind direction vector and the personnel walking direction vector;

[0134] According to the wind strength, material weight, personnel weight and vector angle, calculate the stability of personnel, refer to the following formula:

[0135] ;

[0136] in, For the stability of personnel, is the air density, is the real-time wind speed, The area exposed to wind for materials and personnel. is the vector angle, is the weight of the person, is the material weight;

[0137] Match the personnel stability with the preset personnel stability to determine whether the personnel stability is consistent with the preset personnel stability. If they are consistent, it is determined that there is an interaction between the personnel's walking direction and the wind intensity. Based on the interaction, it is determined that there is a dangerous behavior. BRIEF DESCRIPTION OF THE DRAWINGS

[0138] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, a brief introduction will be given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0139] Figure 1 A schematic diagram of an application scenario provided for an embodiment of the present application;

[0140] Figure 2 A flowchart of a method for analyzing engineering data for engineering management provided in one embodiment of the present application;

[0141] Figure 3 A schematic diagram of the structure of an engineering data analysis system for engineering management provided in one embodiment of the present application. DETAILED DESCRIPTION

[0142] In order to make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0143] In addition, the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article, unless otherwise specified, generally means that the associated objects before and after are in an "or" relationship.

[0144] The embodiments of the present application are further described in detail below in conjunction with the drawings in the specification.

[0145] In the process of managing construction projects, the prevention of people falling from heights is simply achieved by setting up protective nets and reminding construction workers to take safety precautions. However, when danger may occur, no effective measures are taken to provide warnings for high-altitude falls, which can cause harm to people.

[0146] Based on this, the present application provides an engineering data analysis method and system for engineering management, which integrates engineering monitoring information and image processing technology to achieve comprehensive monitoring and intelligent analysis of the construction site. By extracting personnel behavior images, identifying the edges of engineering buildings and dividing dangerous areas, and further analyzing personnel behavior, key action information can be captured in real time, so as to accurately judge whether there are dangerous behaviors such as falling from heights, and timely issue early warnings, which significantly improves the safety management level and emergency response capabilities of the construction site. Combined with personnel behavior images, several dangerous areas are scientifically divided and their scopes are determined, so as to achieve refined early warning and management of the risk of falling from heights. This not only improves the safety management level of the construction site, but also effectively prevents the occurrence of high-altitude falling accidents, providing strong protection for the life safety of personnel. At the same time, the influence of lighting conditions on light transmittance and edge recognition is taken into account, which enhances the accuracy and reliability of the early warning system.

[0147] Figure 1 A schematic diagram of an application scenario provided for this application. When conducting safety management of a project, the method provided by this application is applied to analyze the project monitoring information, divide the dangerous areas and analyze the behavior of personnel, and then determine whether there is any dangerous behavior to achieve high-altitude fall warning.

[0148] Specifically, the method provided by the present application is applied to any server, and the server interacts with the monitoring device. By acquiring the engineering monitoring information of the monitoring device, the behavior images of personnel and the edge information of the engineering building are extracted, and the dangerous area is divided according to the edge information of the engineering building. The behavior images of personnel in the dangerous area are analyzed to obtain key action information. According to the key action information, it is determined whether there is a dangerous behavior. If so, a high-altitude fall warning is issued. By judging whether there is a high-altitude fall risk based on the behavior of personnel in the dangerous area and issuing a high-altitude fall warning, the risk of high-altitude fall of personnel is effectively reduced, the level of engineering safety management is improved, and the safety of personnel is effectively guaranteed.

[0149] For specific implementation methods, please refer to the following embodiments.

[0150] Figure 2 This is a flowchart of a method for analyzing engineering data for engineering management provided in one embodiment of the present application. The method of this embodiment can be applied to the server in the above scenario. Figure 2 As shown, the method includes:

[0151] S201. Acquire engineering monitoring information, and extract personnel behavior images based on the monitoring information.

[0152] The project monitoring information may be all the monitoring information when the project is under construction.

[0153] The personnel behavior image may be a behavior image of all personnel during the construction of the project.

[0154] Specifically, first, all monitoring information of the engineering construction can be obtained through monitoring equipment, and then the obtained monitoring information can be identified using a behavior recognition algorithm to obtain images of relevant personnel behaviors, and the personnel behavior images can be extracted.

[0155] S202: Obtain edge information of the engineering building according to the monitoring information, divide the dangerous area according to the edge information of the engineering building, and obtain the scope of the dangerous area.

[0156] The engineering building edge information may be information close to the edge of each floor of the engineering building.

[0157] Dangerous areas can be all areas on each floor that may cause danger.

[0158] The danger zone range may be the range of all danger zones.

[0159] Specifically, according to the monitoring information obtained in the above steps, firstly, the edge detection algorithm can be used to detect the image of the acquired monitoring information to obtain the image detection result, and the image detection result can be screened to determine the image with the edge as the edge information of the engineering building. Secondly, the contour detection algorithm can be used to extract the edge of the engineering building, and the main contour of the edge of the engineering building can be determined according to a certain distance range. For example, the range of two meters within the edge of the engineering building is determined as a certain distance range. According to the main contour of the edge of the engineering building, the edge of the engineering building is determined as a dangerous area according to the human body position, and the obtained dangerous area is determined as the range of the dangerous area.

[0160] S203: Analyze the personnel behavior image according to the range of the dangerous area to obtain key action information.

[0161] The critical action information may be information about a person in a dangerous area that may produce dangerous actions.

[0162] Specifically, a behavior recognition algorithm can be used to extract key points of human behavior within the dangerous area to obtain key point extraction results. Based on the key point extraction results, human actions, such as bending, reaching, and carrying, can be identified to obtain key action information.

[0163] S204. Determine whether there is any dangerous behavior based on the key action information. If so, issue a high-altitude fall warning.

[0164] Dangerous behaviors can be all behaviors that may threaten safety when personnel are working. In order to ensure accurate judgment, all behaviors that may threaten safety can be preset in the database in advance to form preset dangerous behaviors.

[0165] Specifically, based on the monitoring information, it is determined whether the person is in the danger zone. If the person is in the danger zone, the behavior recognition algorithm can be used to identify the key action information, obtain the key action information recognition result, match the key action information recognition result with the preset dangerous behavior, and determine whether the behavior displayed by the current person matches the preset dangerous behavior. If the match is consistent, it is determined that there is a dangerous behavior and a high-altitude fall warning is issued.

[0166] Through the method provided in this embodiment, by analyzing the engineering monitoring information, it is possible to extract personnel behavior images in real time and accurately identify the edges of engineering buildings, effectively divide dangerous areas, and then accurately analyze personnel behavior, timely capture key action information, and achieve rapid early warning of height-falling risks, significantly improve the safety management level of engineering construction sites, effectively prevent the occurrence of height-falling accidents, and ensure the safety of personnel lives.

[0167] In some embodiments, the layout of the engineering building is determined based on monitoring information; meteorological data is acquired to obtain light intensity and light angle; based on the light intensity and light angle, the layout of the engineering building is analyzed to obtain the light transmittance of each area of ​​the engineering building; it is determined whether the light transmittance of each area reaches a preset light transmittance, and if so, each area of ​​the engineering building that reaches the preset light transmittance is determined as the edge information of the engineering building; the edge of the engineering building is divided according to the edge information of the engineering building and the image of personnel behavior to obtain a number of dangerous areas, and based on the several dangerous areas, the range of the dangerous area is obtained.

[0168] The engineering building layout may be the layout of the location of each engineering building.

[0169] Light transmittance can be the degree to which light can penetrate each floor of a building.

[0170] The preset light transmittance can be a preset degree of light that can penetrate the edge of each floor of the engineering building.

[0171] Specifically, first, the layout of the engineering building can be extracted from the engineering design drawings, and secondly, the training algorithm can be used to obtain the light transmittance under different environments based on the light intensity and light angle.

[0172] Then, the weather API can be used to obtain the light intensity and light angle in different environments. Assuming that the transmittance is proportional to the light intensity and is affected by the light angle, the light intensity and light angle in the current environment are input into the algorithm training model in combination with the light intensity and light angle of the engineering building in the current environment to obtain the transmittance of each area in the current environment. Transmittance can be estimated by simulating the propagation of light in the building. Determine whether the transmittance of each area currently reaches the preset transmittance standard. If so, the area that reaches the preset transmittance is regarded as the edge of the engineering building. According to the personnel behavior image, the position of the personnel is obtained. Determine whether the position of the personnel is at the edge of the engineering building. If so, determine the possibility of danger at the edge of the position of the personnel at different degrees according to the personnel behavior image. According to the edge information of the engineering building and the possibility of danger, determine several dangerous areas, and determine the range of the dangerous area based on several dangerous areas.

[0173] Through the method provided in this embodiment, by comprehensively analyzing monitoring information, meteorological data and engineering construction layout, the transmittance of each area of ​​the engineering construction is accurately calculated, and the edge information of the engineering construction is accurately identified based on this. Combined with the personnel behavior image, several dangerous areas can be scientifically divided and their scope can be determined, so as to achieve refined early warning and management of the risk of falling from heights. This not only improves the safety management level of the construction site, but also effectively prevents the occurrence of high-altitude falling accidents, providing a strong guarantee for the life safety of personnel. At the same time, the influence of lighting conditions on transmittance and edge recognition is taken into account, which enhances the accuracy and reliability of the early warning system.

[0174] In some embodiments, the personnel behavior image is cropped according to the danger zone range to obtain the danger zone range behavior image; the danger zone range behavior image is analyzed to classify the personnel behavior within the danger zone range to determine the personnel behavior type; and key action information is obtained according to the personnel behavior type.

[0175] The personnel behavior type may be the types of different behaviors of personnel when performing operations.

[0176] Specifically, firstly, according to the range of the dangerous area, the personnel behavior image in the monitoring information is cropped, and the cropped personnel behavior image is subjected to denoising and contrast enhancement processing to obtain the processed dangerous area range behavior image. Then, the dangerous area range behavior image can be analyzed using a computer behavior recognition algorithm to obtain the current personnel's ongoing behavior. The current personnel's ongoing behavior is classified to determine which behavior type the current personnel's ongoing behavior belongs to, and the personnel behavior type is obtained.

[0177] According to the personnel behavior type, the key features of the current personnel behavior are determined. Finally, the action classification algorithm can be used to analyze the extracted key features, and the obtained analysis results are determined as key action information.

[0178] Through the method provided by this embodiment, by cutting the personnel behavior image according to the dangerous area range, the analysis scope is effectively narrowed and the processing efficiency is improved; by using the computer behavior recognition algorithm, the cropped dangerous area range behavior image is deeply analyzed, and the personnel behavior can be accurately classified and the personnel behavior type can be determined; based on the classification results, key action information is further extracted to achieve refined early warning and management of high-altitude falling risks. It not only improves the safety monitoring level of the construction site, but also effectively prevents the occurrence of high-altitude falling accidents, providing a strong guarantee for the life safety of construction workers.

[0179] In some embodiments, wind strength is obtained based on meteorological data; key action information is analyzed to determine the speed and direction of personnel movement; personnel movement trend is determined based on the speed and direction of personnel movement; the actual stay position of personnel is predicted based on the personnel movement trend and wind strength; the actual stay position of personnel is matched with the preset personnel position to determine whether the actual stay position of personnel is consistent with the preset personnel position; if the actual stay position of personnel is consistent with the preset personnel position, whether there is any dangerous behavior is determined based on the actual stay position of personnel.

[0180] The preset personnel position may be a preset position of a personnel within the danger zone.

[0181] Specifically, first, the meteorological API can be used to obtain meteorological data, and the wind intensity can be extracted from the meteorological data. Then, the computer behavior recognition algorithm can be used to identify the key action information obtained in the above steps to obtain the specific actions of the personnel. Through monitoring information, continuous video frames and the initial positions of personnel in the dangerous area are obtained. According to the changes in key actions in the video frames, the time intervals between key actions are obtained. Then, the speed of the person's movement can be obtained by dividing the moving distance of the key points between adjacent frames by the time interval. Based on the initial position of the person, the angle change of the key points between adjacent frames is calculated to determine the direction of the person's movement. If the person's walking speed is greater than zero, it means that the person is moving. If the person's walking speed is zero, it means that the person has stopped moving. According to the walking speed and direction of the person, the movement trend of the person is determined.

[0182] According to the movement trend of personnel and wind strength, the influence degree between the movement trend of personnel and wind strength is calculated, and the actual stay position of personnel is obtained according to the influence degree. It is judged whether the actual stay position of personnel is consistent with the preset personnel position. If the actual stay position of personnel is consistent with the preset personnel position, it is determined that the personnel is in the dangerous area, and the personnel behavior is matched with the preset dangerous behavior obtained in the above steps. If the personnel behavior matches the preset dangerous behavior, it is judged that the personnel has dangerous behavior.

[0183] Through the method provided by this embodiment, by comprehensively analyzing meteorological data and key action information of personnel, the actual stay location of personnel can be accurately predicted, and then it can be determined whether the personnel have dangerous behavior. The accuracy and real-time monitoring of personnel behavior are improved, which helps to timely discover and prevent potential safety hazards and ensure personnel safety. At the same time, matching the predicted location with the preset location further enhances the accuracy and reliability of monitoring, providing strong support for safety management.

[0184] In some embodiments, the behavior image of the dangerous area is analyzed to obtain building material information and personnel information; based on the building material information, the material volume, material type, material density and material size of the building materials are obtained; based on the personnel information, the personnel volume is obtained; based on the material density and material volume, the weight of the building materials is determined; based on the meteorological data, wind direction data is obtained; based on the behavior image of the dangerous area, the relative position of the personnel and the building materials is obtained; based on the material size, material weight and personnel volume, the degree of influence of the wind intensity on the relative position is determined; the degree of influence is matched with the preset degree of influence to determine whether the degree of influence is consistent with the preset degree of influence; if the degree of influence is consistent with the preset degree of influence, then it is determined based on the wind direction whether there is an interaction between the actual stay position of the personnel and the wind intensity, and if there is an interaction, it is determined that a dangerous behavior exists.

[0185] The interaction can be the mutual influence between personnel and wind force, personnel and wind direction, which brings personnel closer to the danger zone.

[0186] The relative position can be the position of a person relative to an object in a certain space.

[0187] The preset influence degree may be the influence degree of the preset wind strength on the relative position.

[0188] Specifically, first, image analysis technology can be used to obtain monitoring images, and building material information and personnel information can be extracted from the monitoring images. Based on the building material information, the material type, material volume, material density and material size of the building materials can be obtained. After that, image analysis technology can be used to analyze the personnel behavior image to obtain the personnel volume and the initial position of the personnel. According to the personnel volume and personnel density, the weight of the personnel is determined. According to the material volume and material density, the weight of the material is obtained. According to the meteorological data obtained in the above steps, the wind strength, wind direction and wind speed are obtained. According to the monitoring information, the relative position between the personnel and the material is obtained. According to the size and weight of the material and the volume of the personnel, the fluid mechanics formula can be used to calculate the influence of the wind on the relative position.

[0189] The influence degree of wind strength on relative position is matched with the preset influence degree to determine whether the actual influence degree reaches the preset influence degree. If it reaches, the personnel's windward area and personnel's walking time are determined according to the personnel behavior image and wind direction. And according to the wind speed, wind direction, personnel's windward area, personnel's weight and personnel's walking time, the final staying position after the wind direction affects the actual staying position of the personnel is calculated. Refer to the following steps:

[0190] According to the air density and wind speed, the wind pressure is obtained, referring to formula (1),

[0191] (1)

[0192] in, is the wind pressure, is the air density, is the wind speed.

[0193] Calculate the wind force based on wind pressure and personnel exposure area, refer to formula (2),

[0194] (2)

[0195] in, For wind power, is the wind pressure, The area where personnel are exposed to wind.

[0196] According to the influence of wind on people's movement, the wind resistance coefficient is obtained .

[0197] Calculate the acceleration of a person based on their weight, the area exposed to wind, and the wind speed. Refer to formula (3):

[0198] (3)

[0199] in, is the personnel acceleration, is the wind resistance coefficient, is the air density, The area of ​​personnel exposed to wind, is the wind speed, The weight of the person.

[0200] According to the personnel acceleration and the personnel walking time, the personnel displacement is calculated, referring to formula (4):

[0201] (4)

[0202] in, Q For personnel displacement, is the personnel acceleration, Time for people to move around.

[0203] Take the engineering building layout in the monitoring information as the plane and establish the coordinates, with the horizontal axis as Axis, vertical axis is axis, depending on wind direction and wind strength, Axis and The displacement is decomposed on the axis, referring to formulas (5) and (6):

[0204] (5)

[0205] (6)

[0206] in, For personnel The displacement component on the axis, For personnel displacement, For personnel The displacement component on the axis, For personnel displacement and The angle of the axis.

[0207] According to the personnel The displacement components on the axis and the personnel The displacement component on the axis and the initial position of the personnel are used to calculate the final position of the personnel after the wind direction affects their actual position.

[0208] The distance between the actual stay position of the person and the dangerous area is compared with the distance between the final stay position and the dangerous area. If the distance between the actual stay position of the person and the dangerous area is greater than the distance between the final stay position and the dangerous area, it is determined that there is an interaction, and the existence of dangerous behavior is determined based on the interaction.

[0209] Through the method provided in this embodiment, firstly, through image analysis technology, detailed information of building materials and personnel is accurately extracted, including the volume, type, density and size of building materials, as well as the volume of personnel. Secondly, the weight of building materials is calculated using this information, and the relative position relationship between personnel and building materials is further analyzed in combination with the wind direction information in the meteorological data. Through comprehensive consideration of material size, weight and personnel volume, the degree of influence of wind intensity on relative position is accurately evaluated, and matched with the preset degree of influence, so as to determine whether there is potential dangerous behavior. Through multi-dimensional data analysis and refined evaluation methods, the ability to identify and warn of dangerous behaviors is significantly improved, which helps to take timely measures to ensure the safety of personnel and property.

[0210] In some embodiments, based on the personnel behavior image, the person's body contour, the initial distance between the person and the danger zone, and the person's walking time are obtained; the overall center of gravity position of the person and the cargo is determined based on the person's body contour, material size, person behavior, person volume and material weight; it is judged whether the overall center of gravity position exists within the danger zone, and if so, the moving direction of the overall center of gravity position is determined based on the person's walking direction; the person's walking distance is determined based on the person's walking time and the person's walking speed; it is judged whether the person's walking distance is greater than the initial distance between the person and the danger zone, and if greater, the degree of influence of wind intensity on relative position is determined based on the overall center of gravity position, the moving direction of the overall center of gravity position and the person's walking distance.

[0211] The initial distance between the person and the dangerous area may be the distance between the person and the dangerous area when the person is in a non-dangerous area.

[0212] The personnel walking time may be the time when the personnel walks on the edge.

[0213] The walking distance of a person may be a distance generated when a person walks on the edge compared to an initial position.

[0214] Specifically, when a person enters the boundary, it may be to carry materials within the boundary. Therefore, during the transportation process, there is a situation where the person walks at the boundary between the dangerous area and the non-dangerous area. At this time, it is necessary to determine the movement of the person at the boundary, and then determine the mutual influence of wind intensity on the person and the material. First, image analysis technology can be used to analyze the person's behavior image to extract the person's body contour, the initial distance between the person and the dangerous area, the material size and the person's walking time. Secondly, the person's volume can be determined based on the person's behavior image using three-dimensional reconstruction technology. According to the person's body contour and the person's volume, the person's center of gravity position is calculated, and the specific coordinates of the person's center of gravity position are determined according to the coordinate system obtained in the above steps. Then, the segmentation method can be used to segment the material into several small objects, and the center of gravity position of each object is calculated respectively, and then the center of gravity position of each object is weighted to obtain the center of gravity position of the material.

[0215] Based on the above coordinate system, the center of gravity position of the personnel and the center of gravity position of the material are marked in the coordinate system, and the weighted average method is used to calculate the overall center of gravity position. According to the overall center of gravity position, the coordinates of the overall center of gravity position are marked, and the direction of the personnel's movement is determined as the moving direction of the overall center of gravity position. The personnel's walking time and the personnel's walking speed are multiplied to obtain the personnel's walking distance. According to the personnel behavior image, the initial distance between the personnel and the dangerous area is obtained, and the personnel's walking distance is compared with the initial distance. If the personnel's walking distance is greater than the initial distance, it is determined that the personnel is in the dangerous area. According to the overall center of gravity position, the moving direction of the overall center of gravity position and the personnel's walking distance, the degree of influence of wind intensity on the relative position is determined.

[0216] Through the method provided in this embodiment, firstly, through personnel behavior image analysis, detailed personnel and environmental information, including body contours, initial distances, and walking time, etc., is obtained, providing an accurate data basis for subsequent calculations. Secondly, by comprehensively considering the physical characteristics of personnel, cargo attributes, and personnel behavior, the overall center of gravity position of personnel and cargo is accurately determined. Furthermore, the relationship between the overall center of gravity position and the danger zone is determined, and the changes in the center of gravity position and the possible entry into the danger zone are predicted based on the walking direction and speed of the personnel. Finally, the degree of influence of wind intensity on relative position is evaluated, providing a scientific basis for formulating targeted safety measures in the actual working environment. A comprehensive and dynamic assessment of personnel work safety is achieved, which helps to improve the safety and efficiency of the working environment.

[0217] In some embodiments, the real-time wind speed is obtained based on meteorological data; the weight of the person and the windward area of ​​the person are obtained based on the volume of the person; the surface area of ​​the material is obtained based on the size of the material; and the influence degree of the relative position is obtained based on the real-time wind speed, the surface area of ​​the material, the windward area of ​​the person, the weight of the material and the weight of the person, referring to formula (7):

[0218] (7)

[0219] in, is the influence strength of relative position, is the air density, is the real-time wind speed, is the surface area of ​​the material, The area of ​​personnel exposed to wind, is the material weight, The weight of the person.

[0220] Specifically, first, the meteorological data obtained through the above steps can be used to extract the real-time wind speed from the meteorological data, and the personnel volume and personnel density can be multiplied to obtain the personnel weight. According to the personnel volume, the length, width and height data of the personnel are determined, and the windward area of ​​the personnel is calculated based on the length, width and height data. According to the material size, the length, width and height data of the material are obtained from the material size, and the surface area of ​​the material is calculated. According to the real-time wind speed, material surface area, personnel windward area, material weight and personnel weight, refer to formula (7) to obtain the influence of the relative position.

[0221] By the method provided in this embodiment, real-time wind speed is obtained through meteorological data, thereby ensuring the accuracy and timeliness of wind speed information. Secondly, the physical properties of personnel and materials are taken into account, including personnel volume, personnel weight, personnel windward area, material size, and material surface area. By combining these factors with the real-time wind speed and applying physical formulas for calculation, the degree of influence of relative position, that is, the potential influence of wind force on the relative position of personnel and materials, is accurately obtained. Not only does it improve the accuracy of the assessment, but it can also provide a scientific and quantitative basis for actual operations, which helps to formulate more accurate and effective safety measures, thereby ensuring the safety of the working environment.

[0222] In some embodiments, the material position within the dangerous area and the ground roughness within the dangerous area are obtained based on the dangerous area range behavior image; the material height and the material windward area are obtained based on the material size; the material relative displacement is obtained based on the material height, material weight, material position, ground roughness, material windward area and wind intensity, and it is determined whether the material relative displacement is greater than the preset material relative displacement. If the material relative displacement is greater than the preset material relative displacement, it is determined that dangerous behavior exists.

[0223] According to the material size, the material height and the material windward area are obtained; according to the material height, material weight, material position, ground roughness, material windward area and wind strength, the material relative displacement is obtained, referring to formula (8):

[0224] (8)

[0225] in, is the relative displacement of the material, is the air density, is the real-time wind speed, is the wind-exposed area of ​​the material, is the material height, The roughness of the ground. Material weight, is the acceleration due to gravity.

[0226] The preset material relative displacement may be a preset material movement distance relative to the initial position of the material. The ground roughness may be the ground roughness of each floor of the engineering building.

[0227] The relative displacement of the material may be the distance the material moves relative to the initial position of the material.

[0228] The relative position of the material may be the relative displacement between the initial position of the material and the actual position of the material.

[0229] The initial position of the material may be the position of the material when it is not moved.

[0230] The actual position of the material may be the position at which the material stops after being moved.

[0231] Specifically, first, the image analysis technology can be used to analyze the behavior image of the dangerous area to obtain the material position within the dangerous area. From the behavior image of the dangerous area, the ground image is extracted, and the ground image is scanned to obtain a clear ground image. The protrusions and recesses in the clear ground image are marked, and the protrusions and recesses are calculated. The protrusions and recesses are weighted averaged to obtain the ground roughness. The specific data of the length, width and height of the material are extracted from the material size, and the material height and the material windward area are calculated based on the specific data. According to the material height, material weight, material position, ground roughness, material windward area and wind strength, the relative displacement of the material is obtained by referring to formula (8).

[0232] The calculated material relative displacement is compared with the preset material relative displacement. If the material relative displacement is greater than the preset material displacement, it is determined that a dangerous behavior exists.

[0233] Through the method provided in this embodiment, a variety of key factors affecting the stability of materials are comprehensively considered, and quantitative analysis is performed through a specific mathematical model. Not only the direct force factor of wind intensity is added, but also the physical properties of the material (such as size, weight), location information, and ground conditions (such as roughness) are added. By comprehensively calculating these factors, it is possible to more accurately predict and judge the stability of materials in specific environments, thereby more effectively identifying potential dangerous behaviors and providing a scientific basis for taking preventive measures in a timely manner. Comprehensive consideration of multiple factors and quantitative evaluation improves the accuracy and reliability of dangerous behavior identification, which helps to improve the overall level of safety management.

[0234] In some embodiments, the wind-exposed area of ​​the material is obtained according to the material size; the wind-exposed area of ​​the personnel is obtained according to the personnel volume; the wind-exposed areas of the material and the personnel are obtained according to the relative position of the personnel and the material, the wind-exposed area of ​​the material, and the wind-exposed area of ​​the personnel; the wind direction vector and the personnel walking direction vector are obtained according to the wind direction and the personnel walking direction; the angle between the wind direction vector and the personnel walking direction vector is determined according to the wind direction vector and the personnel walking direction vector; the stability of the personnel is calculated according to the wind strength, the material weight, the personnel weight and the vector angle, referring to formula (9).

[0235] (9)

[0236] in, For the stability of personnel, is the air density, is the real-time wind speed, The area exposed to wind for materials and personnel. is the vector angle, is the weight of the person, is the material weight;

[0237] Match the personnel stability with the preset personnel stability to determine whether the personnel stability is consistent with the preset personnel stability. If they are consistent, determine that there is an interaction between the personnel's walking direction and the real-time wind speed. Based on the interaction, determine that there is a dangerous behavior.

[0238] The stability of personnel may be the stability of personnel while performing operations.

[0239] The preset personnel stability may be a preset level of stability at which the personnel may remain stable.

[0240] The interaction can be between wind strength and the direction in which people are walking.

[0241] Specifically, the length, width and height data of the material are extracted from the material size, and the windward area of ​​the material is calculated based on the length, width and height data of the material. The length, width and height data of the person are extracted from the person's volume, and the windward area of ​​the person is calculated based on the length, width and height data of the person. The relative position of the person and the material, the windward area of ​​the material, and the windward area of ​​the person are integrated to calculate the windward area of ​​the person and the material. According to the walking direction of the person and the wind direction, the direction of the walking direction of the person and the direction of the wind are determined. According to the weight of the person and the weight of the material, the stabilizing force of the person is obtained. The walking direction of the person and the direction of the wind direction are connected to obtain the walking direction vector of the person and the wind direction vector. The angle between the walking direction vector of the person and the wind direction vector is determined as the vector angle. According to the real-time wind speed, the weight of the material, the weight of the person and the vector angle, the stability of the person is calculated.

[0242] The calculated personnel stability is compared with the preset personnel stability. If the personnel stability is greater than the preset personnel stability, it is determined that there is an interaction between the wind speed and the direction of personnel movement. If the interaction force is greater than the personnel stability force, it is determined that dangerous behavior exists.

[0243] According to the real-time wind speed, material weight, personnel weight and vector angle, refer to formula (9) to calculate the stability of personnel.

[0244] Through the method provided in this embodiment, a variety of key factors affecting personnel stability are comprehensively calculated, including the windward area of ​​materials, the windward area of ​​personnel, the relative relationship between wind direction and personnel walking direction, wind strength, material weight and personnel weight, and the stability of personnel is calculated. Not only is the accuracy of personnel stability assessment improved, but also real-time monitoring and judgment of whether there are potential dangers in the behavior of personnel in a specific environment, thereby effectively preventing accidents. In addition, by matching the calculated personnel stability with the preset stability threshold, unstable or dangerous behavior patterns can be quickly identified, providing a scientific basis for timely taking safety measures, and greatly enhancing the safety of the working environment.

[0245] Figure 3 A schematic diagram of a structure of a system for engineering management and engineering data analysis provided in an embodiment of the present application is shown in FIG. Figure 3 As shown, the engineering data analysis system 300 for engineering management of this embodiment includes: an image extraction module 301, an area range determination module 302, an action information determination module 303 and a high-altitude warning module 304.

[0246] The image extraction module 301 is used to obtain engineering monitoring information and extract personnel behavior images based on the monitoring information;

[0247] The area range determination module 302 is used to obtain the edge information of the engineering building according to the monitoring information, divide the dangerous area according to the edge information of the engineering building, and obtain the range of the dangerous area;

[0248] The action information determination module 303 is used to analyze the personnel behavior image according to the range of the dangerous area to obtain key action information;

[0249] The high altitude warning module 304 is used to determine whether there is any dangerous behavior based on the key action information, and if so, issue a high altitude fall warning.

[0250] Optionally, the dangerous area range determination module 302 is specifically configured to:

[0251] Determine the layout of engineering buildings based on monitoring information;

[0252] Obtain meteorological data to obtain light intensity and angle;

[0253] Analyze the layout of the project building according to the light intensity and light angle, and obtain the light transmittance of each area of ​​the project building;

[0254] Determine whether the light transmittance of each area reaches a preset light transmittance, and if so, determine each area of ​​the engineering building that reaches the preset light transmittance as the engineering building edge information;

[0255] The edge of the engineering building is divided according to the edge information of the engineering building and the personnel behavior image to obtain a number of dangerous areas, and the range of the dangerous area is obtained according to the several dangerous areas.

[0256] Optionally, the action information determination module 303 is specifically configured to:

[0257] According to the scope of the dangerous area, the personnel behavior image is cropped to obtain the behavior image within the dangerous area;

[0258] Analyze the behavior images within the dangerous area, classify the behaviors of people within the dangerous area, and determine the types of people's behaviors;

[0259] According to the type of personnel behavior, key action information is obtained.

[0260] Optionally, the area range determination module 302 is specifically configured to:

[0261] According to the meteorological data, the wind strength is obtained;

[0262] Analyze key action information to determine the speed and direction of movement of personnel;

[0263] Determine the movement trend of personnel based on their movement speed and direction;

[0264] Predict the actual location of people based on their movement trends and wind strength;

[0265] Match the actual location of the person with the preset location of the person to determine whether the actual location of the person is consistent with the preset location of the person;

[0266] If the actual location of the person is consistent with the preset location of the person, it is determined whether there is any dangerous behavior based on the actual location of the person.

[0267] Optionally, the area range determination module 302 is specifically configured to:

[0268] Analyze the behavior images of the dangerous area to obtain the information of building materials and personnel;

[0269] According to the building material information, the material volume, material type, material density and material size of the building material are obtained;

[0270] According to the personnel information, the personnel volume is obtained;

[0271] Determine the weight of building materials based on material density and material volume;

[0272] According to the meteorological data, wind direction data is obtained;

[0273] According to the behavior image of the dangerous area, the relative position of personnel and building materials is obtained;

[0274] Determine the degree to which wind intensity affects relative positions based on material size, material weight, and personnel volume;

[0275] Match the impact degree with the preset impact degree to determine whether the impact degree is consistent with the preset impact degree;

[0276] If the impact degree matches the preset impact degree, it is determined whether there is an interaction between the actual stay position of the person and the wind strength based on the wind direction. If there is an interaction, it is determined that a dangerous behavior exists.

[0277] Optionally, the area range determination module 302 is specifically configured to:

[0278] According to the personnel behavior image, the personnel body outline, the initial distance between the personnel and the dangerous area, and the personnel movement time are obtained;

[0279] Determine the overall center of gravity of personnel and cargo based on the personnel's body contours, material dimensions, personnel behavior, personnel volume, and material weight;

[0280] Determine whether the overall center of gravity is within the dangerous area. If so, determine the direction of movement of the overall center of gravity based on the direction of personnel movement.

[0281] Determine the distance people walk based on their walking time and walking speed;

[0282] Determine whether the distance the personnel have walked is greater than the initial distance between the personnel and the dangerous area. If so, determine the degree of influence of wind intensity on the relative position based on the overall center of gravity position, the direction of movement of the overall center of gravity position and the distance the personnel have walked.

[0283] Optionally, the area range determination module 302 is specifically configured to:

[0284] Get real-time wind speed based on meteorological data;

[0285] According to the volume of personnel, obtain the weight of personnel and the area exposed to wind;

[0286] According to the material size, the surface area of ​​the material is obtained;

[0287] According to the real-time wind speed, material surface area, personnel windward area, material weight and personnel weight, the influence of relative position is obtained, referring to the following formula:

[0288] ;

[0289] in, is the influence strength of relative position, is the air density, is the real-time wind speed, is the surface area of ​​the material, The area of ​​personnel exposed to wind, is the material weight, The weight of the person.

[0290] Optionally, the area range determination module 302 is specifically configured to:

[0291] According to the behavior image of the dangerous area, the material position within the dangerous area and the ground roughness within the dangerous area are obtained;

[0292] According to the material size, the material height and the wind-exposed area of ​​the material are obtained;

[0293] According to the material height, material weight, material location, ground roughness, material windward area and wind strength, the relative displacement of the material is obtained, referring to the following formula:

[0294] ;

[0295] in, is the relative displacement of the material, is the air density, is the real-time wind speed, is the wind-exposed area of ​​the material, is the material height, The roughness of the ground. Material weight, is the acceleration due to gravity;

[0296] Determine whether the relative displacement of the material is greater than the preset relative displacement of the material. If the relative displacement of the material is greater than the preset relative displacement of the material, it is determined that there is a dangerous behavior.

[0297] Optionally, the area range determination module 302 is specifically configured to:

[0298] According to the material size, the wind-exposed area of ​​the material is obtained;

[0299] According to the volume of personnel, the wind-exposed area of ​​personnel is obtained;

[0300] According to the relative position of personnel and materials, the wind-exposed area of ​​materials and the wind-exposed area of ​​personnel, the wind-exposed area of ​​materials and personnel is obtained;

[0301] According to the wind direction and the direction of personnel movement, the wind direction vector and the personnel movement direction vector are obtained;

[0302] According to the wind direction vector and the personnel walking direction vector, determine the angle between the wind direction vector and the personnel walking direction vector;

[0303] According to the wind strength, material weight, personnel weight and vector angle, calculate the stability of personnel, refer to the following formula:

[0304] ;

[0305] in, For the stability of personnel, is the air density, is the real-time wind speed, The area exposed to wind for materials and personnel. is the vector angle, is the weight of the person, is the material weight;

[0306] Match the personnel stability with the preset personnel stability to determine whether the personnel stability is consistent with the preset personnel stability. If they are consistent, it is determined that there is an interaction between the personnel's walking direction and the wind intensity. Based on the interaction, it is determined that there is a dangerous behavior.

[0307] The system of this embodiment can be used to execute the method of any of the above embodiments. The implementation principles and technical effects are similar and will not be described in detail here.

Claims

1. A method for analyzing engineering data for engineering management, characterized in that: include: Acquire engineering monitoring information, and extract personnel behavior images based on the monitoring information; According to the monitoring information, edge information of the engineering building is obtained, and according to the edge information of the engineering building, the dangerous area is divided to obtain the range of the dangerous area; Analyze the personnel behavior image according to the range of the dangerous area to obtain key action information; Based on the key action information, determine whether there is any dangerous behavior, and if so, issue a high-altitude fall warning; The step of obtaining the edge information of the engineering building according to the monitoring information, dividing the dangerous area according to the edge information of the engineering building, and obtaining the range of the dangerous area includes: Determine the layout of the engineering building according to the monitoring information; Obtain meteorological data to obtain light intensity and angle; Analyze the layout of the engineering building according to the light intensity and the light angle to obtain the light transmittance of each area of ​​the engineering building; Determine whether the light transmittance of each area reaches a preset light transmittance, and if so, determine each area of ​​the engineering building that reaches the preset light transmittance as the edge information of the engineering building; The edge of the engineering building is divided according to the engineering building edge information and the personnel behavior image to obtain a number of dangerous areas, and the range of the dangerous area is obtained according to the several dangerous areas.

2. The method according to claim 1, characterized in that According to the scope of the dangerous area, Analyze the personnel behavior image to obtain key action information, including: According to the range of the dangerous area, the personnel behavior image is cropped to obtain the dangerous area range. surrounding behavioral images; Analyze the behavior image of the dangerous area, classify the behavior of people in the dangerous area, and determine the type of people's behavior; The key action information is obtained according to the personnel behavior type.

3. The method according to claim 1, characterized in that The key action information Determine whether there is risky behavior, including: According to the meteorological data, wind strength is obtained; Analyze the key action information to determine the speed and direction of movement of the personnel; Determine the movement trend of the personnel according to the movement speed and the movement direction of the personnel; Predicting the actual location of the personnel based on the movement trend of the personnel and the wind strength; Matching the actual stay position of the person with the preset person position to determine whether the actual stay position of the person is consistent with the preset person position; If the actual stay position of the person is consistent with the preset person position, it is determined whether there is any dangerous behavior based on the actual stay position of the person.

4. The method according to claim 3, characterized in that If the actual position of the person is consistent with the preset position of the person, judging whether there is any dangerous behavior according to the actual position of the person, including: Analyze the behavior image of the dangerous area to obtain building material information and personnel information; According to the building material information, the material volume, material type, material density and material size of the building material are obtained; According to the personnel information, obtaining the personnel volume; Determining the weight of the building material based on the density of the material and the volume of the material; Obtaining wind direction data according to the meteorological data; According to the behavior image of the dangerous area, the relative positions of the personnel and the building materials are obtained; Determining the influence of the wind intensity on the relative position according to the material size, the material weight and the volume of the personnel; Matching the impact degree with a preset impact degree to determine whether the impact degree is consistent with the preset impact degree; If the impact degree matches the preset impact degree, it is determined whether there is an interaction between the actual staying position of the person and the wind strength according to the wind direction. If there is such an interaction, it is determined that a dangerous behavior exists.

5. The method according to claim 4, characterized in that According to the material size, The weight of the material and the volume of the person are used to determine the degree of influence of the wind intensity on the relative position, including: According to the personnel behavior image, the body contour of the personnel, the initial distance between the personnel and the dangerous area, and the walking time of the personnel are obtained; Determine the overall center of gravity of the person and the cargo based on the person's body contour, the material size, the person's behavior, the person's volume, and the material weight; Determine whether the overall center of gravity position exists within the dangerous area, and if so, determine the moving direction of the overall center of gravity position according to the walking direction of the personnel; Determine the walking distance of the personnel according to the walking time and walking speed of the personnel; Determine whether the distance the person has walked is greater than the initial distance between the person and the dangerous area. If greater, determine the degree of influence of the wind intensity on the relative position based on the overall center of gravity position, the moving direction of the overall center of gravity position and the distance the person has walked.

6. The method according to claim 5, characterized in that According to the material size, The weight of the material and the volume of the person are used to determine the degree of influence of the wind intensity on the relative position, including: According to the meteorological data, real-time wind speed is obtained; According to the volume of the personnel, the weight of the personnel and the area exposed to wind of the personnel are obtained; According to the material size, the surface area of ​​the material is obtained; According to the real-time wind speed, the surface area of ​​the material, the windward area of ​​the personnel, the weight of the material and the weight of the personnel, the influence degree of the relative position is obtained, referring to the following formula: ; in, is the influence strength of the relative position, is the air density, is the real-time wind speed, is the surface area of ​​the material, is the area exposed to wind by the personnel, is the weight of the material, is the weight of the person.

7. The method according to claim 6, characterized in that The determining whether there is a dangerous behavior according to the key action information includes: According to the dangerous area range behavior image, the material position within the dangerous area range and the ground roughness within the dangerous area range are obtained; According to the material size, the material height and the material wind-exposed area are obtained; According to the material height, the material weight, the material position, the ground roughness, the material windward area and the wind strength, the relative displacement of the material is obtained, referring to the following formula: ; in, is the relative displacement of the material, is the air density, is the real-time wind speed, is the wind-exposed area of ​​the material, is the material height, is the ground roughness, The weight of the material, is the acceleration due to gravity; It is determined whether the relative displacement of the material is greater than the preset relative displacement of the material. If the relative displacement of the material is greater than the preset relative displacement of the material, it is determined that a dangerous behavior exists.

8. The method according to claim 7, characterized in that The determining, according to the wind direction, whether there is an interaction between the direction of movement of the person and the wind strength, and if there is such an interaction, determining that there is a dangerous behavior, includes: According to the material size, the wind-exposed area of ​​the material is obtained; According to the volume of the personnel, the wind-exposed area of ​​the personnel is obtained; According to the relative position of the personnel and the material, the wind-exposed area of ​​the material, and the wind-exposed area of ​​the personnel, the wind-exposed area of ​​the material and the personnel are obtained; According to the wind direction and the personnel walking direction, a wind direction vector and a personnel walking direction vector are obtained; Determine the angle between the wind direction vector and the personnel walking direction vector according to the wind direction vector and the personnel walking direction vector; According to the wind strength, the material weight, the personnel weight and the vector angle, the stability of the personnel is calculated, referring to the following formula: ; in, For the stability of the personnel, is the air density, is the real-time wind speed, The area exposed to wind for the materials and personnel mentioned above, is the vector angle, is the weight of the person, is the weight of the material; The personnel stability is matched with the preset personnel stability to determine whether the personnel stability is consistent with the preset personnel stability. If they are consistent, it is determined that there is an interaction between the personnel's walking direction and the wind intensity. Based on the interaction, it is determined that there is a dangerous behavior.

9. An engineering data analysis system for engineering management, characterized in that: The method as applied to any one of claims 1 to 8 above comprises: An image extraction module is used to obtain engineering monitoring information and extract personnel behavior images based on the monitoring information; An area range determination module is used to obtain the edge information of the engineering building according to the monitoring information, divide the dangerous area according to the edge information of the engineering building, and obtain the range of the dangerous area; An action information determination module is used to analyze the personnel behavior image according to the range of the dangerous area to obtain key action information; The high-altitude warning module is used to determine whether there is any dangerous behavior based on the key action information, and if so, issue a high-altitude fall warning.

Citation Information

Patent Citations

  • Early warning method, device and terminal

    CN105575049A

  • Engineering safety remote online monitoring system based on machine vision and artificial intelligence

    CN112903026A

  • Intelligent monitoring method applied to hydro-junction project

    CN113919627A

  • Infrastructure project engineering construction site safety intelligent supervision, monitoring, analysis and early warning system

    CN114821373A

  • Personnel falling risk detection method and system and storage medium

    CN115115988A