Pier column segmental prefabrication and aerial splicing construction method

Through segmented prefabrication of piers and columns and aerial splicing construction methods, the problems of long construction period and high energy consumption in the existing technology have been solved, efficient and environmentally friendly bridge construction has been achieved, construction quality and safety have been improved, and the impact on traffic and traffic has been reduced. environmental impact.

CN118727581APending Publication Date: 2024-10-01XINJIANG JIAOJIAN MUNICIPAL ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410745335.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-11
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

In the existing technology, the construction of highways and urban bridges has problems such as long construction period, large impact on traffic, high overall energy consumption, large number of on-site construction personnel, and high labor intensity for workers.

Method used

The piers are prefabricated in sections and spliced ​​in the air, including prefabricating the piers in sections, installing and fixing the lower piers, installing the centering guide brackets, fine-tuning the attitude of the upper piers, and connecting UHPC ring joints, using UHPC materials and steel formwork. Pouring and operation are performed on the frame operating platform to reduce on-site construction.

Benefits of technology

It improves construction efficiency, shortens the construction period, reduces the impact on traffic, saves energy and protects the environment, improves construction quality and safety, reduces on-site pollution and noise, and improves worker proficiency and product consistency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727581A_ABST
    Figure CN118727581A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of road construction, and particularly discloses a pier column segmental prefabrication and aerial splicing construction method which comprises the following steps: pier column segmental prefabrication; mounting and fixing the lower-section pier column, and pouring UHPC (Ultra High Performance Concrete); centralizing the guide bracket, and mounting and fixing the guide bracket; mounting and fixing the upper-section pier column, and finely adjusting the posture of the upper-section pier column; uHPC circular seam connection is carried out, UHPC materials are used as pouring materials, the length of a wet joint is 60 cm, a steel formwork is used for pouring, personnel operation is carried out on a frame body operation platform, and maintenance is carried out after pouring is completed. The construction efficiency is improved, the construction period can be shortened, the quality is improved, the field operation of bridge construction is greatly reduced, the influence on urban traffic flow can also be reduced, energy conservation and environmental protection are achieved, the pollution of the field construction to the environment is avoided, meanwhile, the construction noise is reduced, the safety coefficient is improved, the proficiency is greatly improved, and the accident rate is effectively reduced. And the product quality excellence degree and the component consistency are high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of road construction, and in particular to a construction method for prefabricating pier columns in sections and splicing them in the air. Background Art

[0002] At present, roads and urban bridges are constructed using cast-in-place concrete. This construction method has the characteristics of stable structure and strong durability, and can meet the needs of large-scale infrastructure construction. In urban construction, cast-in-place concrete construction accounts for a large proportion.

[0003] However, the existing technology has problems such as long construction period, great impact on traffic, high overall energy consumption, large number of on-site construction personnel, and high labor intensity of workers. Summary of the invention

[0004] The purpose of the present invention is to provide a method for prefabricating and splicing pier sections in the air, aiming to solve the technical problems in the prior art such as long construction period, great impact on traffic, high overall energy consumption, large number of on-site construction personnel and high labor intensity of workers.

[0005] To achieve the above-mentioned purpose, the present invention adopts a pier column segment prefabrication and aerial splicing construction method, which comprises the following steps: Piers are prefabricated in sections; Install and fix the lower pier column, and pour UHPC; Straighten the guide bracket and install and fix it; Install and fix the upper pier column, and make fine adjustments to the posture of the upper pier column; UHPC annular joint connection, the casting material is UHPC material, the wet joint length is 60cm, steel formwork is used for casting, and personnel operate on the frame operating platform. After the casting is completed, curing is carried out.

[0006] Among them, in the step of prefabricating the pier columns in sections: when prefabricating the pier columns in sections, the pier column formwork is supported and installed on the trolley, and then the pier column steel cage is installed, and the formwork is sealed, the formwork and steel cage are turned over to a vertical state, and the pouring and demolding maintenance are carried out.

[0007] Among them, in the steps of installing and fixing the lower section of the pier column: the pier column is transported horizontally into the site, the crane unloads the pier column horizontally, and then the crane moves backward with load to the pier column lifting radius. When walking with load, the lifting weight of a single machine is calculated as 70% of the rated lifting weight. After the pier column is unloaded, the sling and sling are installed, the steel shoulder pole is connected to the lifting wire rope up and down, and the shackle is used to connect the lifting beam shoulder pole and the pier column lifting point to avoid bending of the embedded steel bars. After the installation is completed, the pier column is turned over and unloaded horizontally, and one end of the column bottom is placed on the rubber shock-absorbing pad. On the top, one end of the column top is placed on the ground with sleepers, and then the column top is lifted by a crane. The pier is slowly turned over and erected, and the pier is rotated back to the pedestal, inserted into the exposed steel bars of the pedestal, and hoisted into place. When installing the pier, the crane station must maintain a safe distance from the edge of the foundation pit. The splicing surface between the pier and the pedestal is a mortar cushion layer. Under the control of splicing, mortar seating, and verticality, the dense mortar seating effect must be ensured. After the mortar seating process is completed, the verticality must be controlled and calibrated within 30 minutes, and the verticality must be controlled and adjusted before the pier is moved away.

[0008] Among them, in the steps of straightening the guide bracket and installing and fixing it: after the installation of the lower pier column and the UHPC grouting are completed, the frame installation operation is carried out after the strength test is up to standard. This tooling frame provides a construction platform for the circumferential wet joint, which serves as an operating platform for the construction personnel to assist in straightening the upper pier column. The frame is designed to be quick-installed and quick-disassembled, and the whole can be split into two parts.

[0009] Among them, in the steps of installing and fixing the upper pier column: transport, unload and turn over the upper pier column. After the upper pier column is turned over and hoisted in a vertical state, use a total station to measure the verticality of the upper pier column to ensure that the upper and lower verticality deviations of the upper pier column are no more than 1°. Lift the lower end face of the upper pier column to be 1m higher than the guide frame, adjust the position of the crane to make the upper pier column and the lower pier column accurately aligned. After the upper pier column and the lower pier column are accurately aligned, slowly lower the upper pier column until the upper pier column contacts the lower pier column. At this time, keep the crane bearing 90% of the weight of the pier column. Observe the alignment and verticality of the upper and lower pier columns by measuring to ensure that the four surfaces are accurately connected. The construction personnel are operating Observe the gap of the contact surface on the platform. Use adjusting gaskets with appropriate thickness to adjust the gap. Adjust the screw on the guide frame. Set a rubber gasket between the screw and the pier body. Twist the screw to make the rubber gasket and the pier body tightly contact. Unload slowly with the crane. Do not unload at one time. Repeat the screw tightening operation each time unloading. Fine-tune the posture of the upper pier column by gaskets and screws. After the upper pier column and the lower pier column are stably connected, at least two steel bars are reliably welded on each surface of the upper pier column. Observation should be carried out continuously at the same time. The guide righting bracket must not be subjected to the lateral pressure of the pier column tilt. The righting bracket is designed to withstand the lateral force generated by the pier column tilting 3°, so that the load of the upper pier column is transmitted vertically downward.

[0010] The beneficial effects of the pier column segment prefabrication and aerial splicing construction method of the present invention are: improving construction efficiency, adopting modular design and prefabrication assembly, and having a high degree of streamlined operation, which can shorten the construction period, improve quality, greatly reduce on-site operations in bridge construction, and reduce the impact on urban traffic flow. It is energy-saving and environmentally friendly. The prefabricated components are all manufactured in the factory, saving template materials and construction sites, avoiding environmental pollution caused by on-site construction, and reducing construction noise, reducing on-site material stacking, and improving the safety factor. The prefabricated components are constructed using an assembly line, and the workers are more professional in their division of labor, and their proficiency is greatly improved, which effectively reduces the accident rate, and the product quality is excellent and the component consistency is high. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0012] Figure 1 The invention discloses a flow chart of steps of a construction method for prefabricating pier sections and splicing them in the air. DETAILED DESCRIPTION

[0013] See also Figure 1 The present invention provides a method for prefabricating pier sections and splicing them in the air, comprising the following steps: S1: Pier column segmented prefabrication; S2: Install and fix the lower pier column and pour UHPC; S3: straighten the guide bracket and install and fix it; S4: Install and fix the upper pier column, and make fine adjustments to the posture of the upper pier column; S5: UHPC annular joint connection, the casting material is UHPC material, the wet joint length is 60cm, and steel formwork is used for casting. The personnel operate on the frame operating platform, and curing is carried out after the casting is completed.

[0014] Furthermore, in the step of prefabricating the pier columns in sections: when prefabricating the pier columns in sections, the pier column formwork is supported and installed on the trolley, and then the pier column reinforcement cage is installed, and the formwork is sealed, the formwork and reinforcement cage are turned over to a vertical state, and the pouring and demolding maintenance are carried out.

[0015] Furthermore, in the step of installing and fixing the lower section of the pier column: the pier column is transported horizontally into the yard, the crane unloads the pier column horizontally, and then the crane moves backward with load to the pier column lifting radius. When moving with load, the lifting weight of a single machine is calculated as 70% of the rated lifting weight. After the pier column is unloaded, the sling and sling are installed, the steel shoulder pole is connected to the lifting wire rope up and down, and the shackle is used to connect the lifting beam shoulder pole and the pier column lifting point to avoid bending of the embedded steel bars. After the installation is completed, the pier column is turned over and unloaded horizontally, and one end of the column bottom is placed on the rubber shock absorber. On the pad, one end of the column top is placed on the ground with sleepers, and then the column top is lifted by a crane. The pier is slowly turned over and erected, and the pier is rotated back to the pedestal, inserted into the exposed steel bars of the pedestal, and hoisted into place. When installing the pier, the crane station must maintain a safe distance from the edge of the foundation pit. The splicing surface between the pier and the pedestal is a slurry cushion layer. Under the control of splicing, slurry seating, and verticality, the dense slurry seating must be ensured. After the slurry seating process is completed, the verticality must be controlled and calibrated within 30 minutes, and the verticality must be controlled and adjusted before the pier is moved away.

[0016] Furthermore, in the step of straightening the guide bracket and installing and fixing it: after the installation of the lower pier column and the UHPC grouting are completed, the frame installation operation is carried out after the strength test is up to standard. This tooling frame provides a construction platform for the circumferential wet joint, which serves as an operating platform for the construction personnel to assist in straightening the upper pier column. The frame is designed to be quick-install and quick-disassemble, and the whole can be split into two parts.

[0017] Furthermore, in the steps of installing and fixing the upper pier column: the upper pier column is transported, unloaded and turned over. After the upper pier column is turned over and hoisted in a vertical state, the verticality of the upper pier column is measured using a total station to ensure that the upper and lower verticality deviations of the upper pier column are no more than 1°. The lower end face of the upper pier column is hoisted to be 1m higher than the guide frame. The position of the crane is adjusted to make the upper pier column and the lower pier column accurately aligned. After the upper pier column and the lower pier column are accurately aligned, the upper pier column is slowly lowered until the upper pier column contacts the lower pier column. At this time, the crane is kept to bear 90% of the weight of the pier column. By measuring and observing the alignment and verticality of the upper and lower pier columns, it is ensured that the four surfaces are accurately connected. The construction personnel are operating Observe the gap of the contact surface on the working platform. Use adjusting gaskets with appropriate thickness to adjust the gap. Adjust the screw on the guide frame. Set a rubber gasket between the screw and the pier body. Twist the screw to make the rubber gasket and the pier body tightly contact. Unload slowly with the crane. Do not unload at one time. Repeat the screw tightening operation each time unloading. Fine-tune the posture of the upper pier column by gaskets and screws. After the upper pier column and the lower pier column are stably connected, at least two steel bars are reliably welded on each surface of the upper pier column. Observation should be carried out continuously at the same time. The guide righting bracket must not be subjected to the lateral pressure of the pier column tilt. The righting bracket is designed to withstand the lateral force generated by the pier column tilting 3°, so that the load of the upper pier column is transmitted vertically downward.

[0018] In this implementation, the construction efficiency is improved, modular design and prefabrication are adopted, and the degree of streamlined operation is high, which can shorten the construction period, improve the quality, greatly reduce the on-site operations of bridge construction, and reduce the impact on urban traffic flow. It is energy-saving and environmentally friendly. The prefabricated components are all made in the factory, saving template materials and construction sites, avoiding the pollution of the environment by on-site construction, and reducing construction noise, reducing on-site material stacking, and improving the safety factor. The prefabricated components are constructed by assembly lines, and the division of labor among workers is more professional, and the proficiency is greatly improved, which effectively reduces the accident rate, and the product quality is excellent and the consistency of components is high; Adopt segmented prefabrication and segmented assembly: Compared with the traditional cast-in-place process, segmented prefabrication and aerial splicing construction technology of high piers can more effectively and quickly solve the traditional problems of quality, progress and safety in traditional construction. The use of UHPC ultra-high performance concrete ring seam connection can not only meet the construction progress requirements and safety production indicators, but also ensure the quality of important indicators of compression and tension resistance at the ring seam, thereby improving the overall quality of engineering construction. The application of segmented prefabrication and aerial splicing technology of piers can effectively improve the production capacity during the construction process, save construction time, and greatly improve the one-time acceptance rate. It can effectively avoid the pollution of the environment caused by on-site construction, while reducing construction noise and reducing on-site material stacking.

[0019] What is disclosed above is only a preferred embodiment of the present invention, and it certainly cannot be used to limit the scope of rights of the present invention. Ordinary technicians in this field can understand that all or part of the processes of the above embodiment and equivalent changes made according to the claims of the present invention still fall within the scope of the invention.

Claims

1. A method for prefabricating pier columns in sections and splicing them in the air, characterized in that: The steps include: Piers are prefabricated in sections; Install and fix the lower pier column, and pour UHPC; Straighten the guide bracket and install and fix it; Install and fix the upper pier column, and make fine adjustments to the posture of the upper pier column; UHPC annular joint connection, the casting material is UHPC material, the wet joint length is 60cm, and steel formwork is used for casting. The personnel operate on the frame operating platform, and curing is carried out after the casting is completed.

2. A method for prefabricating pier sections and splicing them in the air as claimed in claim 1, characterized in that: In the steps of prefabricating pier columns in sections: when prefabricating pier columns in sections, the pier column formwork is supported and installed on the trolley, and then the pier column reinforcement cage is installed, and the formwork is sealed, the formwork and reinforcement cage are turned over to a vertical state, and the pouring and demoulding maintenance are carried out.

3. A method for prefabricating pier sections and splicing them in the air as claimed in claim 1, characterized in that: In the steps of installing and fixing the lower section of the pier column: the pier column is transported horizontally into the site, the crane unloads the pier column horizontally, and then the crane moves backward with load to the pier column lifting radius. When moving with load, the lifting weight of a single machine is calculated as 70% of the rated lifting weight. After the pier column is unloaded, the sling and lifting equipment are installed, the steel shoulder pole is connected to the lifting wire rope up and down, and the shackle is used to connect the lifting beam shoulder pole and the pier column lifting point to avoid bending of the embedded steel bars. After the installation is completed, the pier column is turned over and unloaded horizontally, and one end of the column bottom is placed on the rubber shock-absorbing pad. One end of the column top is placed on the ground with sleepers, and then the column top is lifted by a crane. The pier is slowly turned over and erected, and the pier is rotated back to the pedestal, inserted into the exposed steel bars of the pedestal, and hoisted into place. When installing the pier, the crane station must maintain a safe distance from the edge of the foundation pit. The joint surface between the pier and the pedestal is a mortar cushion layer. Under the control of splicing, mortar seating, and verticality, the dense mortar seating effect must be ensured. After the mortar seating process is completed, the verticality must be controlled and calibrated within 30 minutes, and the verticality must be controlled and adjusted before the pier is moved away.

4. A method for prefabricating pier sections and splicing them in the air as claimed in claim 1, characterized in that: In the steps of straightening the guide bracket and installing and fixing it: after the installation of the lower pier column and the UHPC grouting are completed, the frame installation work is carried out after the strength test meets the standards. This tooling frame provides a construction work platform for the circumferential wet joint, which serves as an operating platform for the construction personnel to assist in straightening the upper pier column. The frame is designed to be quick-installed and quick-disassembled, and the whole can be split into two parts.

5. A method for prefabricating pier sections and splicing them in the air as claimed in claim 1, characterized in that: In the steps of installing and fixing the upper pier column: transport, unload and turn over the upper pier column. After the upper pier column is turned over and hoisted in a vertical state, use a total station to measure the verticality of the upper pier column to ensure that the upper and lower verticality deviations of the upper pier column are no more than 1°. Lift the lower end face of the upper pier column to be 1m higher than the guide frame, adjust the position of the crane to accurately align the upper and lower pier columns. After the upper and lower pier columns are accurately aligned, slowly lower the upper pier column until the upper and lower pier columns are in contact with each other. At this time, keep the crane bearing 90% of the weight of the pier column. Observe the alignment and verticality of the upper and lower pier columns by measuring to ensure that the four surfaces are accurately connected. The construction personnel operate on the flat Observe the gap of the contact surface on the platform. Use adjusting gaskets with appropriate thickness to adjust the gap. Adjust the screw on the guide frame. Set rubber gaskets between the screw and the pier body. Twist the screw to make the rubber gasket and the pier body tightly contact. Unload slowly with the crane. Do not unload at one time. Repeat the screw tightening operation each time unloading. Fine-tune the posture of the upper pier column by gaskets and screws. After the upper pier column and the lower pier column are stably connected, at least two steel bars are reliably welded on each surface of the upper pier column. Observation should be carried out continuously at the same time. The guide straightening bracket must not be subjected to the lateral pressure of the pier column tilt. The straightening bracket is designed to withstand the lateral force generated by the pier column tilting 3°, so that the load of the upper pier column is transmitted vertically downward.