Pressure-bearing water precipitation control method capable of achieving automatic adjustment
Through real-time monitoring and automatic calculation of pressurized water levels, the risk of pressurized water surge during foundation pit excavation is solved, the stability and safety of pressurized water are improved, the problem of excessive precipitation is avoided, and construction safety is improved. and accuracy.
Patent Information
- Application Number
- CN202410642838.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-23
- Publication Date
- 2024-10-01
AI Technical Summary
The sudden surge of pressurized water during foundation pit excavation is a major risk point. Existing technology is difficult to achieve real-time precipitation control, resulting in insufficient or excessive precipitation, affecting construction safety and the stability of surrounding buildings.
The monitoring equipment obtains the foundation pit excavation elevation and pressurized water head data in real time. The program automatically calculates the stable water level and alarm water level of the pressurized water, determines the stability and risk level of the pressurized water, and automatically adjusts the precipitation speed and work instructions to guide the site. Construction to avoid excessive precipitation.
It ensures the stability of pressurized water while avoiding excessive precipitation, improves construction safety and accuracy, and reduces construction costs and the risk of deformation and settlement of surrounding buildings.
Smart Images

Figure CN118727797A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of foundation pit construction, in particular to a pressure water dewatering control method capable of realizing automatic adjustment. Background Art
[0002] Confined water inrush is one of the main risk points in the foundation pit excavation process. When the deadweight pressure of the confined water layer is less than the head pressure of the confined water below, it is easy to cause sudden surges and may cause serious casualties and property losses.
[0003] At present, there are usually two ways to control the dewatering level of pressurized water during foundation pit construction. One is that the construction unit determines the dewatering depth based on its own experience, and the other is to determine the dewatering depth through theoretical calculation based on the standard of maintaining the stability of the pressurized water when the maximum excavation depth of the foundation pit is met. The first method has poor reliability and is prone to problems of insufficient or excessive dewatering; the second method can better ensure the stability of pressurized water throughout the foundation pit excavation process, but the problem of excessive dewatering is very prominent, which can easily lead to deformation and settlement of buildings and ground around the foundation pit.
[0004] Therefore, in order to solve the above problems, a method that can determine the real-time precipitation index and precipitation speed according to the excavation depth and the water level of the pressurized water is very necessary, which can avoid the problem of excessive precipitation while ensuring the stability of the pressurized water. Summary of the invention
[0005] In order to solve the above problems of the prior art, the present invention designs a pressure water dewatering control method that can realize automatic adjustment. Based on the construction information fed back by the monitoring equipment in real time, the invention automatically calculates and judges the stability and risk level of the pressure water in the foundation pit by the program, and automatically issues corresponding work instructions to guide the on-site construction. The instructions can avoid the problem of excessive dewatering while ensuring the stability of the pressure water. The process does not require human intervention, which improves work efficiency and accuracy.
[0006] In order to achieve the above object, the present invention adopts the following technical solutions:
[0007] A method for controlling the dewatering of pressurized water capable of realizing automatic adjustment, wherein the method obtains the real-time elevation B of foundation pit excavation and the real-time elevation Hs of pressurized water head through monitoring equipment, and the program automatically calculates and outputs the stable water level Hw of pressurized water and the alarm water level Hj of pressurized water, compares and judges the current stability and risk level of pressurized water, and the program automatically adjusts the dewatering speed of pressurized water according to the judgment result, and at the same time issues work instructions to guide the excavation of foundation pit and emergency evacuation on site.
[0008] Furthermore, the method specifically comprises the following steps:
[0009] Step 1: Arrange monitoring equipment; the monitoring content includes the real-time elevation B of the foundation pit excavation and the real-time elevation Hs of the confined water head.
[0010] Step 2: The program obtains the real-time elevation B of the foundation pit excavation;
[0011] Step 3: The program calculates the thickness D of the overburden layer of the confined water layer;
[0012] Step 4: The program obtains the real-time elevation Hs of the confined water head; the real-time elevation Hs of the confined water head is the real-time elevation of the confined water head within the foundation pit range;
[0013] Step 5: The program automatically calculates and outputs the stable water level Hw of the confined water;
[0014] Step 6: The program judges the stability situation of the confined water: if Hs = Hw, go to Step 7; if Hs < Hw, go to Step 8; if Hs > Hw, go to Step 9;
[0015] Step 7: When Hs = Hw, keep the power of the confined water dewatering pump unchanged, keep normal excavation, and continue monitoring;
[0016] Step 8: When Hs < Hw, keep normal excavation and reduce the power of the confined water dewatering pump;
[0017] Step 9: The program automatically calculates and outputs the alarm water level Hj of the confined water;
[0018] Step 10: The program judges the risk degree of confined water gushing; if Hs ≤ Hj, go to Step 11; if Hs > Hj, go to Step 12;
[0019] Step 11: When Hs ≤ Hj, suspend the foundation pit excavation and increase the power of the confined water dewatering pump;
[0020] Step 12: When Hs > Hj, the construction personnel inside and around the foundation pit are urgently evacuated;
[0021] Among them, the control of the power of the confined water dewatering pump in Steps 7, 8, and 11 is automatically completed by the program.
[0022] Furthermore, when arranging the confined water head monitoring equipment in Step 1, it should be determined according to the distribution of the confined water layer. If there are multiple discontinuous confined water layers, monitoring equipment should be set up for each confined water layer respectively.
[0023] Furthermore, in Steps 2 and 3, the program reads the real-time elevation B of the foundation pit excavation measured by the monitoring equipment and calculates the thickness D of the overburden layer of the confined water layer as D = B - A, where A is the elevation of the top of the confined water layer.
[0024] Furthermore, the calculation formula for the stable water level Hw of the confined water in Step 5 is:
[0025]
[0026] Where: Hw——stable water level of confined water;
[0027] D——thickness of the cover layer of the confined water layer;
[0028] γ——Natural weight of soil from the bottom of the pit to the top of the confined water layer;
[0029] γ w - the weight of water;
[0030] K h ——Surge stability safety factor, which can be 1.1;
[0031] A——Elevation of top of confined water layer.
[0032] Furthermore, the criteria for determining the stability of the pressurized water in step 6 are:
[0033] (1) When the measured value of the confined water level Hs is equal to the stable water level Hw of the confined water, the confined water not only meets the requirements of sudden surge stability, but also does not have the problem of excessive precipitation, which is an ideal state;
[0034] (2) When the measured value of the confined water level Hs is less than the stable water level Hw of the confined water, the confined water meets the requirements of sudden surge stability, but there is a problem of excessive precipitation, which is more likely to cause ground subsidence at the pit edge;
[0035] (3) When the measured value of the confined water level Hs is greater than the stable confined water level Hw, the confined water does not meet the sudden surge stability requirements and there is a sudden surge risk in the foundation pit.
[0036] Furthermore, step 7 is a work instruction when the confined water level is in an ideal state: keep the power of the confined water dewatering pump unchanged, maintain the foundation pit excavation operation, keep monitoring at the same time, and re-enter step 2.
[0037] Furthermore, step 8 is a work instruction when the pressurized water is excessively dewatered: reduce the power of the pressurized water dewatering pump, maintain the foundation pit excavation operation, keep monitoring, and re-enter step 2.
[0038] Furthermore, the calculation formula of the pressurized water alarm water level Hj in step 9 is:
[0039]
[0040] Where: Hj——pressure water alarm level;
[0041] D——thickness of the cover layer of the confined water layer;
[0042] γ——Natural weight of soil from the bottom of the pit to the top of the confined water layer;
[0043] γ w - the weight of water;
[0044] K d ——Surge stability critical coefficient, which can be taken as 1.0;
[0045] A——Elevation of top of confined water layer.
[0046] Furthermore, the criteria for determining the risk level of pressurized water inrush in step 10 are:
[0047] (1) When the measured value of the confined water level Hs is not greater than the confined water alarm level Hj, the risk of confined water inrush is relatively high;
[0048] (2) When the measured value of the confined water level Hs is greater than the confined water alarm level Hj, the risk of confined water inrush is serious.
[0049] Furthermore, step 11 is a work instruction when the risk of pressurized water inrush is relatively high: increase the power of the pressurized water dewatering pump, stop the foundation pit excavation operation, and re-enter step 4 to determine the stability of the pressurized water.
[0050] Furthermore, step 12 is a work instruction when the risk of pressurized water inrush is serious: construction personnel in and around the foundation pit are urgently evacuated, and step 11 is initiated at the same time.
[0051] Compared with the prior art, the present invention has the following beneficial technical effects:
[0052] This method can ensure that the water level of the confined water within the excavation range of the foundation pit is dynamically maintained in an ideal state, that is, the stability of the confined water is met without excessive precipitation. According to the real-time data obtained by the monitoring equipment, the program automatically calculates and judges the stability and risk level of the confined water. The result is highly real-time and targeted, and can reduce labor costs while improving the accuracy of confined water control. It can effectively avoid the danger of sudden surges of confined water in the foundation pit caused by manual judgment or operational errors, and improve the safety of foundation pit construction. It can effectively avoid the problem of excessive precipitation of confined water, thereby reducing the deformation and settlement of buildings and ground around the foundation pit, and simultaneously reduce the cost of construction precipitation. When the confined water in the foundation pit is at the alarm water level, this method can detect the risk at the first time and immediately notify the site for emergency evacuation to ensure the safety of construction personnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0053] Figure 1 It is a workflow diagram in a specific implementation mode. DETAILED DESCRIPTION
[0054] To enable those skilled in the art to better understand the solution of the present invention, the following specific embodiments and drawings will be used to further elaborate on the inventive method in detail. However, the present invention is not limited to the scope of the embodiments thereby.
[0055] Please refer to Figure 1 , the method includes the following steps:
[0056] Step 1: Arrange monitoring equipment; the monitoring content includes the real-time elevation B of the foundation pit excavation and the real-time elevation Hs of the confined water head; when arranging the confined water head monitoring equipment, it should be determined according to the distribution of the confined water layer. If there are multiple discontinuous confined water layers, monitoring equipment should be set up separately for each confined water layer;
[0057] Step 2: The program obtains the real-time elevation B of the foundation pit excavation;
[0058] Step 3: The program calculates the thickness D of the overlying layer of the confined water layer; the program reads the real-time elevation B of the foundation pit excavation measured by the monitoring equipment and calculates the thickness D of the overlying layer of the confined water layer as D = B - A, where A is the elevation of the top of the confined water layer;
[0059] Step 4: The program obtains the real-time elevation Hs of the confined water head, and Hs should be the real-time elevation of the confined water head within the foundation pit.
[0060] Step 5: The program automatically calculates and outputs the stable water level Hw of the confined water;
[0061] Step 6: The program determines the stability of the confined water: if Hs = Hw, go to Step 7; if Hs < Hw, go to Step 8; if Hs > Hw, go to Step 9;
[0062] Step 7: When Hs = Hw, keep the power of the confined water pumping pump unchanged, keep normal excavation, and continue monitoring;
[0063] Step 8: When Hs < Hw, keep normal excavation and reduce the power of the confined water pumping pump;
[0064] Step 9: The program automatically calculates and outputs the alarm water level Hj of the confined water;
[0065] Step 10: The program determines the risk degree of confined water gushing; if Hs ≤ Hj, go to Step 11; if Hs > Hj, go to Step 12;
[0066] Step 11: When Hs ≤ Hj, suspend the foundation pit excavation and increase the power of the confined water pumping pump;
[0067] Step 12: When Hs > Hj, the construction personnel inside and around the foundation pit are urgently evacuated.
[0068] In this embodiment, the calculation formula for the stable water level Hw of the confined water in Step 5 is:
[0069]
[0070] Where: Hw——stable water level of confined water;
[0071] D——thickness of the cover layer of the confined water layer;
[0072] γ——Natural weight of soil from the bottom of the pit to the top of the confined water layer;
[0073] γ w - the weight of water;
[0074] K h ——Surge stability safety factor, which can be 1.1;
[0075] A——the elevation of the top of the confined water layer;
[0076] In this embodiment, the criterion for determining the stability of the pressurized water in step 6 is:
[0077] (1) When the measured value of the confined water level Hs is equal to the stable water level Hw of the confined water, the confined water not only meets the requirements of sudden surge stability, but also does not have the problem of excessive precipitation, which is an ideal state;
[0078] (2) When the measured value of the confined water level Hs is less than the stable water level Hw of the confined water, the confined water meets the requirements of sudden surge stability, but there is a problem of excessive precipitation, which is more likely to cause ground subsidence at the pit edge;
[0079] (3) When the measured value of the confined water level Hs is greater than the stable confined water level Hw, the confined water does not meet the sudden surge stability requirements and there is a sudden surge risk in the foundation pit.
[0080] In this embodiment, step 7 is the working instruction when the pressurized water level is in an ideal state: keep the power of the pressurized water dewatering pump unchanged, maintain the foundation pit excavation operation, keep monitoring at the same time, and re-enter step 2.
[0081] In this embodiment, step 8 is the work instruction when the pressurized water is excessively dewatered: reduce the power of the pressurized water dewatering pump, maintain the foundation pit excavation operation, keep monitoring, and re-enter step 2.
[0082] In this embodiment, the calculation formula of the pressurized water alarm water level Hj in step 9 is:
[0083]
[0084] Where: Hj——pressure water alarm level;
[0085] D——thickness of the cover layer of the confined water layer;
[0086] γ——Natural weight of soil from the bottom of the pit to the top of the confined water layer;
[0087] γ w - the weight of water;
[0088] K d ——Surge stability critical coefficient, which can be taken as 1.0;
[0089] A——Elevation of top of confined water layer.
[0090] In this embodiment, the criteria for determining the risk level of pressurized water inrush in step 10 are:
[0091] (1) When the measured value of the confined water level Hs is not greater than the confined water alarm level Hj, the risk of confined water inrush is relatively high;
[0092] (2) When the measured value of the confined water level Hs is greater than the confined water alarm level Hj, the risk of confined water inrush is serious.
[0093] In this embodiment, step 11 is a work instruction when the risk of pressurized water inrush is relatively high: increase the power of the pressurized water dewatering pump, stop the foundation pit excavation operation, and re-enter step 4 to determine the stability of the pressurized water.
[0094] In this embodiment, step 12 is a work instruction when the risk of pressurized water inrush is serious: construction personnel in and around the foundation pit are urgently evacuated, and step 11 is started at the same time.
[0095] The following describes how to use this method:
[0096] Before the foundation pit construction, monitoring equipment is installed according to the project conditions to monitor the real-time elevation of the foundation pit excavation and the real-time elevation of the confined water head. During the construction process, the monitoring data is automatically transmitted to the program. The program automatically calculates and outputs the stable water level and alarm water level of the confined water in combination with the pre-entered confined water layer top elevation, and judges the current confined water stability and risk level by comparing with the real-time confined water level. The program automatically adjusts the confined water precipitation speed based on the judgment results, and issues work instructions to guide the site to carry out foundation pit excavation and emergency evacuation.
[0097] In addition, the present invention also includes an electronic device, which may include: a processor, a communications interface, a memory, and a bus, wherein the processor, the communications interface, and the memory communicate with each other via the bus. The communications interface can be used for information transmission of the electronic device. The processor can call the logic instructions in the memory to execute the following method:
[0098] Controlling the power of the pressurized water precipitation pump in steps 7, 8 and 11;
[0099] Compare and judge the current stability and risk level of the pressurized water, automatically adjust the dewatering speed of the pressurized water according to the judgment results, and issue work instructions to guide the excavation of the foundation pit and emergency evacuation on site;
[0100] And the steps that require automatic processing and judgment by the program in the pressurized water precipitation control method that can realize automatic adjustment.
[0101] In addition, the logic instructions in the above-mentioned memory can be implemented in the form of software functional units and can be stored in a computer-readable storage medium when sold or used as an independent product. Based on such an understanding, the technical solution of the present invention can be essentially or partly embodied in the form of a software product that contributes to the prior art, and the computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the above-mentioned method embodiments of the present invention. The aforementioned storage medium includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk.
[0102] The automatic judgment result of the program of the present invention has strong real-time pertinence, which can improve the accuracy of pressurized water control and ensure that the water level of pressurized water in the excavation range of the foundation pit is dynamically maintained in an ideal state - that is, the stability of the pressurized water is met without excessive precipitation, effectively avoiding the sudden surge of pressurized water in the foundation pit, improving the safety of foundation pit construction, and at the same time avoiding the deformation and settlement of surrounding buildings, structures, ground, etc. caused by excessive precipitation.
Claims
1. A pressure water precipitation control method capable of realizing automatic adjustment, characterized in that: The method obtains the real-time elevation B of the foundation pit excavation and the real-time elevation Hs of the confined water head through a monitoring device. The program automatically calculates and outputs the stable water level Hw of the confined water and the alarm water level Hj of the confined water, compares and judges the current stability and risk degree of the confined water, and the program automatically adjusts the precipitation speed of the confined water according to the judgment result, and at the same time issues a work instruction to guide the on-site foundation pit excavation and emergency evacuation.
2. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1 is characterized in that: The method specifically includes the following steps: Step 1: Arrange the monitoring device; the monitoring content includes the real-time elevation B of the foundation pit excavation and the real-time elevation Hs of the confined water head. Step 2: The program obtains the real-time elevation B of the foundation pit excavation; Step 3: The program calculates the thickness D of the overburden layer of the confined water layer; Step 4: The program obtains the real-time elevation Hs of the confined water head; the real-time elevation Hs of the confined water head is the real-time elevation of the confined water head within the foundation pit range; Step 5: The program automatically calculates and outputs the stable water level Hw of the confined water; Step 6: The program judges the stability of the confined water: if Hs = Hw, go to Step 7; if Hs < Hw, go to Step 8; if Hs > Hw, go to Step 9; Step 7: When Hs = Hw, keep the power of the confined water precipitation pump unchanged, keep normal excavation, and continuously monitor; Step 8: When Hs < Hw, keep normal excavation and reduce the power of the confined water precipitation pump; Step 9: The program automatically calculates and outputs the alarm water level Hj of the confined water; Step 10: The program judges the risk degree of confined water gushing; if Hs ≤ Hj, go to Step 11; if Hs > Hj, go to Step 12; Step 11: When Hs ≤ Hj, suspend the foundation pit excavation and increase the power of the confined water precipitation pump; Step 12: When Hs > Hj, the construction personnel inside and around the foundation pit are evacuated urgently; Among them, the control of the power of the confined water precipitation pump in Step 7, Step 8, and Step 11 is automatically completed by the program.
3. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1 is characterized in that: When arranging the monitoring device of the confined water head in Step 1, it should be determined according to the distribution of the confined water layer. If there are multiple discontinuous confined water layers, monitoring devices should be set separately for each confined water layer.
4. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1 is characterized in that: In Step 2 and Step 3, the program reads the real-time elevation B of the foundation pit excavation measured by the monitoring device, and calculates that the thickness D of the overburden layer of the confined water layer = B - A, where A is the elevation of the top of the confined water layer.
5. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1, characterized in that: The calculation formula for the stable water level Hw of the confined water in Step 5 is: In the formula: Hw - stable water level of the confined water; D - thickness of the overburden layer of the confined water layer; γ - natural unit weight of the soil from the bottom of the pit to the top of the confined water layer; γ w - the weight of water; K h ——Surge stability safety factor, which can be taken as 1.1; A - elevation of the top of the confined water layer.
6. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1 is characterized in that: The discrimination standard for the stability of the confined water in Step 6 is: (1) When the measured value Hs of the confined water level is equal to the stable water level Hw of the confined water, the confined water not only meets the requirements of gushing stability, but also there is no problem of excessive precipitation, which is an ideal state; (2) When the measured value Hs of the confined water level is less than the stable water level Hw of the confined water, the confined water meets the requirements of gushing stability, but there is a problem of excessive precipitation, which is more likely to cause ground settlement on the pit side; (3) When the measured value Hs of the confined water level is greater than the stable water level Hw of the confined water, the confined water does not meet the requirements of gushing stability, and there is a gushing risk in the foundation pit.
7. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1, characterized in that: Step 7 is the work instruction when the confined water level is in an ideal state: keep the power of the confined water dewatering pump unchanged, maintain the foundation pit excavation operation, keep monitoring at the same time, and re-enter step 2.
8. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1, characterized in that: Step 8 is the work instruction when the pressurized water is excessively dewatered: reduce the power of the pressurized water dewatering pump, maintain the foundation pit excavation operation, keep monitoring, and re-enter step 2.
9. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1, characterized in that: The calculation formula for the pressurized water alarm level Hj in step 9 is: Where: Hj——pressure water alarm level; D——thickness of the cover layer of the confined water layer; γ——Natural weight of soil from the bottom of the pit to the top of the confined water layer; γ w - the weight of water; K d ——Surge stability critical coefficient, which can be taken as 1.0; A——Elevation of top of confined water layer.
10. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1, characterized in that: The criteria for determining the risk level of pressurized water inrush in step 10 are: (1) When the measured value of the confined water level Hs is not greater than the confined water alarm level Hj, the risk of confined water inrush is relatively high; (2) When the measured value of the confined water level Hs is greater than the confined water alarm level Hj, the risk of confined water inrush is serious.
11. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1, characterized in that: Step 11 is a work instruction when the risk of pressurized water inrush is high: increase the power of the pressurized water dewatering pump, stop the foundation pit excavation operation, and re-enter step 4 to determine the stability of the pressurized water.
12. The pressurized water precipitation control method capable of realizing automatic adjustment according to claim 1, characterized in that: Step 12 is a work instruction when the risk of pressurized water inrush is serious: construction personnel in and around the foundation pit are evacuated urgently, and step 11 is initiated at the same time.