A high altitude large span eaves construction device and construction method
By using a combination device of locking parts, torsion rods and connecting rods in high-altitude large-span eaves construction, the problems of high construction difficulty and safety hazards are solved, efficient and safe eave construction is achieved, and leakage problems caused by embedded parts are avoided. .
Patent Information
- Application Number
- CN202411224158.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-09-03
AI Technical Summary
When conducting large-span cantilevered eaves construction in high altitudes, the construction is difficult, technical requirements are high, and there are low efficiency and safety risks. The existing technology requires embedded parts to cause leakage problems.
A high-altitude large span eave construction device is adopted, including at least six locking parts, torsion rods and connecting rods. Through the clamping of the upper and lower rows of locking parts and the matching of the torsion rods, the clamping and movement between the floor slabs can be achieved to avoid pre-burial. Improve construction efficiency.
Friction fixation is achieved through multiple clamping forces, extending the working span, simplifying the structure, improving construction efficiency, avoiding leakage problems, and no overall disassembly and handling are required, enhancing construction safety.
Smart Images

Figure CN118728044B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a high-altitude large-span eaves construction device and a construction method. Background Art
[0002] In modern construction projects, high-rise buildings and super high-rise buildings are the main building forms, and as people put forward more requirements on the performance of buildings, the structural forms of buildings are becoming more and more complex. At present, many sloping roof structures use large-span cantilevered eaves to meet the requirements of drainage and modeling. However, due to the large-span cantilevered sloping eaves construction at high altitudes, the overall construction is difficult, the technical requirements are high, the construction quality is extremely difficult to guarantee, and there are great safety hazards.
[0003] At present, most of the existing technologies adopt: 1. constructing a cantilever support frame on the roof layer, 2. setting up a full-height support frame from the ground to the construction layer; the cantilever support frame needs to be installed and dismantled layer by layer, and all materials need to be transported to the next layer for installation, resulting in low efficiency, and embedded parts are required, which makes leakage problems easy to occur, and the full-height support frame is set up from the ground to the construction layer, which is more unfavorable for the installation of eaves in high-rise structures. Therefore, a high-altitude large-span eaves construction device and construction method that can meet the requirements of high-altitude large-span eaves construction and is more efficient are needed. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a high-altitude large-span eaves construction device and a construction method which can meet the requirements of high-altitude large-span eaves construction and have higher efficiency.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0006] A high-altitude large-span eaves construction device comprises a locking piece, a torsion rod and a connecting rod, wherein the number of the locking pieces is at least six and is an even number, and the number of the torsion rods is half of the number of the locking pieces;
[0007] The locking pieces are arranged in two rows, the upper row of locking pieces are numbered in odd numbers such as 1, 3, 5, etc., and the lower row of locking pieces are numbered in even numbers such as 2, 4, 6, etc.; the locking pieces include a connecting portion, a U-shaped clamping portion and a rotating portion, the U-shaped clamping portion is connected to the rotating portion through the connecting portion, and the rotating portion is rotatably connected to the connecting portion; the rotating portions of the upper and lower adjacent locking pieces are connected through a torsion rod, and the connecting portions of the left and right adjacent locking pieces are connected through a connecting rod; when the high-altitude large-span eaves construction device is working, the U-shaped clamping portion is clamped on the floor slab, and the connecting portion and the rotating portion extend out of the floor slab;
[0008] When the high-altitude large-span eaves construction device climbs upward, the following steps are performed:
[0009] Step 11, disassemble the connecting rod between the locking pieces numbered 2 and 4 to separate / remove them;
[0010] Step 12, start the torsion rod between the locking pieces numbered 1 and 2 to rotate, separate the U-shaped clamping part of the locking piece numbered 2 from the floor slab and extend it out of the floor slab, then rotate it upward, align the U-shaped clamping part with the upper floor slab, and then rotate the torsion rod to clamp the U-shaped clamping part with the upper floor slab;
[0011] Step 13, repeat the actions of steps 11 and 12 to rotate all the even-numbered locking pieces upward, and when the even-numbered left and right adjacent locking pieces are clamped with the upper floor slab, they are fixed to each other through the connecting rod;
[0012] Step 14: When all the even-numbered locking pieces are clamped with the upper floor slab and the connecting rods are fixed to each other, the upward climb is completed;
[0013] When the high-altitude large-span eaves construction device moves downward, the following steps are performed:
[0014] Step 21, disassemble the connecting rod between the locking pieces numbered 1 and 3 to separate / remove them;
[0015] Step 22, start the torsion rod between the locking pieces numbered 1 and 2 to rotate, separate the U-shaped clamping part of the locking piece numbered 1 from the floor slab, extend it out of the floor slab, and then rotate it downward, align the U-shaped clamping part with the floor slab of the next layer, and then rotate the torsion rod to clamp the U-shaped clamping part with the floor slab of the next layer;
[0016] Step 23, repeat the actions of steps 21 and 22 to rotate all the odd-numbered locking pieces upward, and when the odd-numbered left and right adjacent locking pieces are clamped with the floor slab of the next layer, they are fixed to each other through the connecting rod;
[0017] Step 24: When all odd-numbered locking pieces are clamped with the floor slab of the next layer and the connecting rods are fixed to each other, the downward movement is completed.
[0018] In order to solve the above technical problems, another technical solution adopted by the present invention is:
[0019] A construction method of a high-altitude large-span eaves construction device, comprising:
[0020] Select a floor above the second floor and select an initial floor slab, use the locking member of the high-altitude large-span eaves construction device, install the locking member on the initial floor slab and the upper floor slab of the initial floor slab to form an upper and lower two-row arrangement, and install a torsion rod and a connecting rod to form a high-altitude large-span eaves construction device;
[0021] If you need to climb up, execute steps 11-14;
[0022] If it is necessary to move downward, execute steps 21-24.
[0023] The beneficial effects of the present invention are as follows: through the upper and lower rows of even-numbered locking pieces, the U-shaped clamping parts thereof can be clamped on the floor slab, forming clamping forces at multiple locations to achieve friction fixation, and the number of locking pieces can be increased to greatly extend the working span, meeting the requirements of large-span eaves construction, and through the setting of the connecting part, space for outward extension can be reserved, which is convenient for construction; combined with the setting of the torsion rod and the connecting rod, the upper and lower floor slabs can be clamped by force at the same time, without the need for embedded parts, and through the rotating part cooperating with the torsion rod, after the construction of each floor is completed, the rotating part cooperates with the torsion rod, and the torsion rod first aligns the locking piece with the original floor slab. The plate is rotated out and separated, and then the rotating rod can be used to rotate 180 degrees upward or downward to move to the upper or lower floor, and then the locking piece is rotated and inserted into the new floor through the torsion rod, and so on, to achieve the overall upward or downward movement. The structure is simple and the construction is convenient. There is no need to disassemble the whole plate and then transport it, which greatly improves the construction efficiency and avoids leakage problems caused by any embedded parts or anchor points. There is no need to construct from the ground. Through the construction device of the present application, the locking pieces can also be increased. When the number of locking pieces increases to a certain extent to cover the outer periphery of the entire floor, they can be connected end to end to form a ring, thereby achieving a more stable construction structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 This is a structural schematic diagram of a high-altitude large-span eaves construction device according to a specific embodiment of the present invention;
[0025] Figure 2 This is a schematic diagram of a first state of upward climbing of a high-altitude large-span eaves construction device according to a specific embodiment of the present invention;
[0026] Figure 3 It is a schematic diagram of a second state of upward climbing of a high-altitude large-span eaves construction device according to a specific embodiment of the present invention;
[0027] Figure 4 It is a schematic diagram of a third state of upward climbing of a high-altitude large-span eaves construction device according to a specific embodiment 1 of the present invention;
[0028] Figure 5 A high altitude large span eaves construction device for a specific embodiment of the present invention Figure 2 Enlarged view of part A;
[0029] Figure 6 This is a structural schematic diagram of a high-altitude large-span eaves construction device according to a second specific embodiment of the present invention;
[0030] Description of reference numerals: 1-6 are numbers for auxiliary descriptions of locking parts;
[0031] 10. Locking piece; 11. Connecting part; 12. U-shaped clamping part; 13. Rotating part; 14. Rotating shaft; 20. Torsion rod; 30. Connecting rod; 40. Floor; 50. Diagonal connecting rod; 60. Telescopic rod. DETAILED DESCRIPTION
[0032] In order to explain the technical content, achieved objectives and effects of the present invention in detail, the following is an explanation in combination with the implementation modes and the accompanying drawings.
[0033] Please refer to Figures 1 to 6 , a high altitude large span eaves construction device, comprising a locking member 10, a torsion rod 20 and a connecting rod 30, wherein the number of the locking members 10 is at least six and an even number, and the number of the torsion rod 20 is half of the locking members 10;
[0034] The locking members 10 are arranged in two rows, the upper row of locking members 10 are odd numbers 1, 3, 5, etc., and the lower row of locking members 10 are even numbers 2, 4, 6, etc.; the locking members 10 include a connecting portion 11, a U-shaped clamping portion 12 and a rotating portion 13, the U-shaped clamping portion 12 is connected to the rotating portion 13 through the connecting portion 11, and the rotating portion 13 is rotatably connected to the connecting portion 11; the rotating portions 13 of the upper and lower adjacent locking members 10 are connected by a torsion rod 20, and the connecting portions 11 of the left and right adjacent locking members 10 are connected by a connecting rod 30; when the high-altitude large-span eaves construction device is working, the U-shaped clamping portion 12 is clamped on the floor slab 40, and the connecting portion 11 and the rotating portion 13 extend out of the floor slab 40;
[0035] When the high-altitude large-span eaves construction device climbs upward, the following steps are performed:
[0036] Step 11, disassemble the connecting rod 30 between the locking members 10 numbered 2 and 4 to separate / remove;
[0037] Step 12, start the torsion bar 20 between the locking pieces 10 numbered 1 and 2 to rotate, separate the U-shaped clamping portion 12 of the locking piece 10 numbered 2 from the floor 40 and extend it out of the floor 40, and then rotate it upward, align the U-shaped clamping portion 12 with the upper floor 40, and then rotate the torsion bar 20 to cooperate and clamp the U-shaped clamping portion 12 with the upper floor 40;
[0038] Step 13, repeat the actions of steps 11 and 12 to rotate all the even-numbered locking members 10 upward, and when the even-numbered left and right adjacent locking members 10 cooperate with and clamp the upper floor slab 40, they are fixed to each other through the connecting rod 30;
[0039] Step 14: When all the even-numbered locking members 10 are clamped with the upper floor slab 40 and the connecting rods 30 are fixed to each other, the upward climbing is completed;
[0040] When the high-altitude large-span eaves construction device moves downward, the following steps are performed:
[0041] Step 21, disassemble the connecting rod 30 between the locking members 10 numbered 1 and 3 to separate / remove them;
[0042] Step 22, start the torsion bar 20 between the locking pieces 10 numbered 1 and 2 to rotate, separate the U-shaped clamping portion 12 of the locking piece 10 numbered 1 from the floor 40, extend it out of the floor 40, and then rotate it downward, align the U-shaped clamping portion 12 with the floor 40 of the next layer, and then rotate the torsion bar 20 to cooperate and clamp the U-shaped clamping portion 12 with the floor 40 of the next layer;
[0043] Step 23, repeat the actions of steps 21 and 22 to rotate all the odd-numbered locking members 10 upward, and when the odd-numbered left and right adjacent locking members 10 are clamped with the floor slab 40 of the next layer, they are fixed to each other through the connecting rod 30;
[0044] Step 24: When all odd-numbered locking members 10 are clamped with the floor slab 40 of the next layer and the connecting rods 30 are fixed to each other, the downward movement is completed.
[0045] As can be seen from the above description, the locking members 10 arranged in two rows and having an even number can be clamped on the floor slab 40 through their U-shaped clamping parts 12, forming multiple clamping forces to achieve friction fixation, and the working span can be greatly extended by increasing the number of locking members 10 to meet the requirements of large-span eaves construction, and the space for outward extension can be reserved through the setting of the connecting part 11, which is convenient for construction; combined with the setting of the torsion rod 20 and the connecting rod 30, the upper and lower floor slabs 40 can be clamped at the same time without embedded parts, and the rotating part 13 can cooperate with the torsion rod 20 after the construction of each layer is completed. The torsion rod 20 first locks the locking member 1 0 is rotated out and separated from the original floor slab 40, and then the rotating rod can be used to rotate 180° upward or downward to rotate to the upper or lower floor slab 40, and then the locking piece 10 is rotated and inserted into the new floor slab 40 through the torsion rod 20, and so on, to achieve the overall upward or downward movement. The structure is simple and the construction is convenient. There is no need to disassemble the entire floor slab and then transport it, which greatly improves the construction efficiency while avoiding leakage problems caused by any embedded parts or anchor points, and there is no need to construct from the ground. Through the construction device of the present application, the locking piece 10 can also be increased. When the number of the locking pieces 10 increases to a certain extent to cover the outer periphery of the entire floor, they can be connected end to end to form a ring, thereby achieving a more stable construction structure.
[0046] Furthermore, the high-altitude large-span eaves construction device also includes an oblique connecting rod 50, one end of which is connected to the locking piece 10 of the lower row with an even number of N, and the other end is connected to the locking piece 10 of the upper row with an odd number of N+1.
[0047] It can be seen from the above description that, by providing the oblique connecting rod 50 , the rectangular structure formed by every four locking members 10 can be decomposed into two triangular structures, thereby ensuring mechanical properties and improving stability.
[0048] Furthermore, the diagonal connecting rod 50 is removed before the high-altitude large-span eaves construction device climbs upward or moves downward.
[0049] Furthermore, the high-altitude large-span eaves construction device also includes a telescopic rod 60 with adjustable length, and the end of the U-shaped clamping portion 12 away from the connecting portion 11 is a free end, and connecting ports are respectively provided on the upper and lower surfaces of the free end, and the connecting ports of the upper and lower adjacent locking members 10 are connected by the telescopic rod 60.
[0050] From the above description, it can be known that by setting the telescopic rod 60, internal support can be formed, which can form downward pressure on the floor slab 40 and upward support on the upper floor slab 40, increase friction, improve stability, and can be shortened when disassembling.
[0051] Furthermore, the telescopic rod 60 is removed before the high-altitude large-span eaves construction device climbs upward or moves downward.
[0052] Furthermore, a scaffolding metal mesh is laid on the connecting rod 30; and the upper and lower adjacent connecting rods 30 are connected by the scaffolding metal mesh.
[0053] From the above description, it can be seen that the provision of the scaffolding metal mesh can facilitate construction workers to perform footwork construction, or prevent foreign objects from falling or affecting the construction safety of personnel.
[0054] Furthermore, the rotating part 13 includes a rotating motor and a rotating shaft 14 . The rotating motor is fixedly connected to the connecting part 11 . The rotating motor drives the rotating shaft 14 to rotate. The torsion rod 20 is connected to the rotating shaft 14 .
[0055] Furthermore, the connecting portion 11 is a hollow pipe, and the rotating motor is arranged on the connecting portion 11 .
[0056] It can be seen from the above description that by adopting the hollow pipe, the weight can be reduced while reserving installation space for the rotating electrical machine and providing protection.
[0057] Furthermore, the U-shaped opening surface of the U-shaped clamping portion 12 is serrated; and the connecting portion 11 and the U-shaped clamping portion 12 are detachably fixedly connected.
[0058] The friction force of clamping can be increased by the serrated U-shaped opening surface.
[0059] It can be seen from the above description that, through the detachable fixed connection, the U-shaped clamping part 12 often experiences friction, which causes the U-shaped clamping part 12 to wear out faster, and can be replaced after being worn out.
[0060] A construction method of a high-altitude large-span eaves construction device, comprising:
[0061] Select a floor above the second floor and select an initial floor slab 40, use the locking member 10 of the high-altitude large-span eaves construction device, install the locking member 10 on the initial floor slab 40 and the upper floor slab 40 of the initial floor slab 40 to form an upper and lower two-row arrangement, and install the torsion rod 20 and the connecting rod 30 to form a high-altitude large-span eaves construction device;
[0062] If you need to climb up, execute steps 11-14;
[0063] If it is necessary to move downward, execute steps 21-24. Embodiment 1
[0064] Reference Figures 1 to 5 , a high altitude large span eaves construction device, comprising a locking member 10, a torsion rod 20 and a connecting rod 30, wherein the number of the locking members 10 is at least six and an even number, and the number of the torsion rod 20 is half of the locking members 10;
[0065] The locking members 10 are arranged in two rows, the upper row of locking members 10 are odd numbers 1, 3, 5, etc., and the lower row of locking members 10 are even numbers 2, 4, 6, etc.; the locking members 10 include a connecting portion 11, a U-shaped clamping portion 12 and a rotating portion 13, the U-shaped clamping portion 12 is connected to the rotating portion 13 through the connecting portion 11, and the rotating portion 13 is rotatably connected to the connecting portion 11; the rotating portions 13 of the upper and lower adjacent locking members 10 are connected by a torsion rod 20, and the connecting portions 11 of the left and right adjacent locking members 10 are connected by a connecting rod 30; when the high-altitude large-span eaves construction device is working, the U-shaped clamping portion 12 is clamped on the floor slab 40, and the connecting portion 11 and the rotating portion 13 extend out of the floor slab 40;
[0066] When the high-altitude large-span eaves construction device climbs upward, the following steps are performed:
[0067] Step 11, disassemble the connecting rod 30 between the locking members 10 numbered 2 and 4 to separate / remove;
[0068] Step 12, start the torsion bar 20 between the locking pieces 10 numbered 1 and 2 to rotate, separate the U-shaped clamping portion 12 of the locking piece 10 numbered 2 from the floor 40 and extend it out of the floor 40, and then rotate it upward, align the U-shaped clamping portion 12 with the upper floor 40, and then rotate the torsion bar 20 to cooperate and clamp the U-shaped clamping portion 12 with the upper floor 40;
[0069] Step 13, repeat the actions of steps 11 and 12 to rotate all the even-numbered locking members 10 upward, and when the even-numbered left and right adjacent locking members 10 cooperate with and clamp the upper floor slab 40, they are fixed to each other through the connecting rod 30;
[0070] Step 14: When all the even-numbered locking members 10 are clamped with the upper floor slab 40 and the connecting rods 30 are fixed to each other, the upward climbing is completed;
[0071] When the high-altitude large-span eaves construction device moves downward, the following steps are performed:
[0072] Step 21, disassemble the connecting rod 30 between the locking members 10 numbered 1 and 3 to separate / remove them;
[0073] Step 22, start the torsion bar 20 between the locking pieces 10 numbered 1 and 2 to rotate, separate the U-shaped clamping portion 12 of the locking piece 10 numbered 1 from the floor 40, extend it out of the floor 40, and then rotate it downward, align the U-shaped clamping portion 12 with the floor 40 of the next layer, and then rotate the torsion bar 20 to cooperate and clamp the U-shaped clamping portion 12 with the floor 40 of the next layer;
[0074] Step 23, repeat the actions of steps 21 and 22 to rotate all the odd-numbered locking members 10 upward, and when the odd-numbered left and right adjacent locking members 10 are clamped with the floor slab 40 of the next layer, they are fixed to each other through the connecting rod 30;
[0075] Step 24: When all odd-numbered locking members 10 are clamped with the floor slab 40 of the next layer and the connecting rods 30 are fixed to each other, the downward movement is completed.
[0076] The high-altitude large-span eaves construction device also includes an oblique connecting rod 50, one end of which is connected to the locking piece 10 of the lower row with an even number of N, and the other end is connected to the locking piece 10 of the upper row with an odd number of N+1.
[0077] The diagonal connecting rod 50 is removed before the high-altitude large-span eaves construction device climbs upward or moves downward.
[0078] The high-altitude large-span eaves construction device also includes a telescopic rod 60 with adjustable length. The end of the U-shaped clamping portion 12 away from the connecting portion 11 is a free end. The upper surface and the lower surface of the free end are respectively provided with connecting ports, and the connecting ports of the upper and lower adjacent locking members 10 are connected by the telescopic rod 60.
[0079] The telescopic rod 60 is removed before the high-altitude large-span eaves construction device climbs upward or moves downward.
[0080] The connecting rods 30 are covered with scaffolding metal mesh; the upper and lower adjacent connecting rods 30 are connected by the scaffolding metal mesh.
[0081] The rotating part 13 includes a rotating motor and a rotating shaft 14 . The rotating motor is fixedly connected to the connecting part 11 . The rotating motor drives the rotating shaft 14 to rotate. The torsion bar 20 is connected to the rotating shaft 14 .
[0082] The connecting portion 11 is a hollow pipe, and the rotating motor is arranged on the connecting portion 11 .
[0083] The U-shaped opening surface of the U-shaped clamping portion 12 is serrated; the connecting portion 11 and the U-shaped clamping portion 12 are detachably fixedly connected. Embodiment 2
[0084] Reference Figure 6 , a high altitude large span eaves construction device, the same as the first embodiment will not be repeated, wherein:
[0085] The high-altitude large-span eaves construction device also includes an oblique connecting rod 50, one end of which is connected to the locking piece 10 of the lower row with an even number of N, and the other end is connected to the locking piece 10 of the upper row with an odd number of N+1. Embodiment 3
[0086] A construction method of a high-altitude large-span eaves construction device, comprising:
[0087] Select a floor above the second floor and select an initial floor slab 40, use the locking member 10 of the high-altitude large-span eaves construction device described in Example 1 or Example 2, install the locking member 10 on the initial floor slab 40 and the upper floor slab 40 of the initial floor slab 40 to form an upper and lower two-row arrangement, and install the torsion rod 20 and the connecting rod 30 to form a high-altitude large-span eaves construction device;
[0088] If you need to climb up, execute steps 11-14;
[0089] If it is necessary to move downward, execute steps 21-24.
[0090] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent transformations made using the contents of the present invention's specification and drawings, or directly or indirectly applied in related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A high altitude large span eaves construction device, characterized in that: It comprises a locking piece, a torsion rod and a connecting rod, wherein the number of the locking pieces is at least six and is an even number, and the number of the torsion rods is half of the number of the locking pieces; The locking pieces are arranged in two rows, the upper row of locking pieces are numbered in odd numbers such as 1, 3, 5, etc., and the lower row of locking pieces are numbered in even numbers such as 2, 4, 6, etc.; the locking pieces include a connecting portion, a U-shaped clamping portion and a rotating portion, the U-shaped clamping portion is connected to the rotating portion through the connecting portion, and the rotating portion is rotatably connected to the connecting portion; the rotating portions of the upper and lower adjacent locking pieces are connected through a torsion rod, and the connecting portions of the left and right adjacent locking pieces are connected through a connecting rod; when the high-altitude large-span eaves construction device is working, the U-shaped clamping portion is clamped on the floor slab, and the connecting portion and the rotating portion extend out of the floor slab; When the high-altitude large-span eaves construction device climbs upward, the following steps are performed: Step 11, disassemble the connecting rod between the locking pieces numbered 2 and 4 to separate / remove them; Step 12, start the torsion rod between the locking pieces numbered 1 and 2 to rotate, separate the U-shaped clamping part of the locking piece numbered 2 from the floor slab and extend it out of the floor slab, then rotate it upward, align the U-shaped clamping part with the upper floor slab, and then rotate the torsion rod to clamp the U-shaped clamping part with the upper floor slab; Step 13, repeat the actions of steps 11 and 12 to rotate all the even-numbered locking pieces upward, and when the even-numbered left and right adjacent locking pieces are clamped with the upper floor slab, they are fixed to each other through the connecting rod; Step 14: When all the even-numbered locking pieces are clamped with the upper floor slab and the connecting rods are fixed to each other, the upward climb is completed; When the high-altitude large-span eaves construction device moves downward, the following steps are performed: Step 21, disassemble the connecting rod between the locking pieces numbered 1 and 3 to separate / remove them; Step 22, start the torsion rod between the locking pieces numbered 1 and 2 to rotate, separate the U-shaped clamping part of the locking piece numbered 1 from the floor slab, extend it out of the floor slab, and then rotate it downward, align the U-shaped clamping part with the floor slab of the next layer, and then rotate the torsion rod to clamp the U-shaped clamping part with the floor slab of the next layer; Step 23, repeat the actions of steps 21 and 22 to rotate all the odd-numbered locking pieces upward, and when the odd-numbered left and right adjacent locking pieces are clamped with the floor slab of the next layer, they are fixed to each other through the connecting rod; Step 24: When all odd-numbered locking pieces are clamped with the floor slab of the next layer and the connecting rods are fixed to each other, the downward movement is completed.
2. The high altitude large span eaves construction device according to claim 1 is characterized in that: The high-altitude large-span eaves construction device also includes an oblique connecting rod, one end of which is connected to the locking piece with an even number of N in the lower row, and the other end is connected to the locking piece with an odd number of N+1 in the upper row.
3. The high altitude large span eaves construction device according to claim 2 is characterized in that: The diagonal connecting rod is removed before the high-altitude large-span eaves construction device climbs upward or moves downward.
4. The high altitude large span eaves construction device according to claim 1 is characterized in that: The high-altitude large-span eaves construction device also includes a telescopic rod with adjustable length. The end of the U-shaped clamping part away from the connecting part is a free end. The upper surface and the lower surface of the free end are respectively provided with connecting ports, and the connecting ports of the upper and lower adjacent locking parts are connected by the telescopic rod.
5. The high altitude large span eaves construction device according to claim 4 is characterized in that: The telescopic rod is removed before the high-altitude large-span eaves construction device climbs upward or moves downward.
6. The high altitude large span eaves construction device according to claim 1 is characterized in that: The connecting rods are paved with scaffolding metal meshes; the upper and lower adjacent connecting rods are connected by the scaffolding metal meshes.
7. The high altitude large span eaves construction device according to claim 1 is characterized in that: The rotating part comprises a rotating motor and a rotating shaft. The rotating motor is fixedly connected to the connecting part. The rotating motor drives the rotating shaft to rotate. The torsion bar is connected to the rotating shaft.
8. The high altitude large span eaves construction device according to claim 7 is characterized in that: The connecting part is a hollow pipe, and the rotating motor is arranged on the connecting part.
9. The high altitude large span eaves construction device according to claim 1, characterized in that: The U-shaped opening surface of the U-shaped clamping portion is serrated; the connecting portion and the U-shaped clamping portion are detachably fixedly connected.
10. A construction method for a high altitude large span eaves construction device, characterized in that: include: Select a floor above the second floor and select an initial floor slab, use the locking member of the high-altitude large-span eaves construction device described in any one of claims 1 to 9, install the locking member on the initial floor slab and the upper floor slab of the initial floor slab to form an upper and lower two-row arrangement, and install a torsion rod and a connecting rod to form a high-altitude large-span eaves construction device; If you need to climb up, execute steps 11-14; If it is necessary to move downward, execute steps 21-24.