Anti-blocking device of geothermal tail water oscillation fracturing recharge system

By using vibration-cleaning impact bead technology in the geothermal recirculation system, the problem of screen tube clogging is solved, the cleaning process is simplified, the cost is reduced and the recirculation efficiency is improved, achieving efficient screen tube cleaning and resource utilization.

CN118728322APending Publication Date: 2024-10-01中核坤华能源发展有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410981735.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The screens of existing geothermal recharge wells are easily clogged after long-term use, resulting in a decrease in recharge efficiency. The complex structure of the device and the long-term flooding of the motor result in high cost and low practicability.

Method used

An anti-blocking device for the geothermal tail water shock fracturing recharge system is designed. By setting up an upper holder, a lower holder, a lifting unit and a cleaning unit, vibration is used to clean the impurities on the screen tube holes, and high-pressure gas-driven impact is used Bead cleaning method simplifies the cleaning mode and improves the cleaning effect.

Benefits of technology

It achieves efficient cleaning of screen tubes, reduces the complexity and cost of the device, improves recharge efficiency, and improves economy through detachable design and resource utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118728322A_ABST
    Figure CN118728322A_ABST
Patent Text Reader

Abstract

An anti-blocking device of a geothermal tail water vibration fracturing recharge system is arranged in a screen pipe with the bottom closed and the upper end open. Comprising an upper fixator arranged on an opening in the upper end of the screen pipe, a lower fixator arranged at the bottom of the screen pipe, a lifting unit arranged between the upper fixator and the lower fixator, and a cleaning unit arranged on the lifting unit. The cleaning unit comprises a fixed disc connected with the lifting unit, an emitter arranged on the fixed disc and provided with an opening facing the inner side wall of the screen pipe, an impact bead arranged at the opening of the emitter, and a high-pressure gas cylinder arranged on the fixed disc and used for providing compressed gas for the emitter. And the supplier is arranged on the fixed disc and is used for supplying the impact beads to the opening of the emitter. The purpose of cleaning impurities attached to holes of the screen pipe in a vibration mode is achieved, and the screen pipe cleaning device has the advantages of being simple in cleaning mode and good in cleaning effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of geothermal recharge, and in particular relates to an anti-blocking device for a geothermal tail water shock fracturing recharge system. Background Art

[0002] Geothermal recharge is a measure to avoid thermal and chemical pollution caused by direct discharge of geothermal wastewater, and plays an important role in maintaining heat storage pressure and ensuring the technical conditions for the exploitation of geothermal fields. Recharge is one of the main measures to achieve sustainable development and utilization of geothermal resources. At present, the liner method is mostly used in the construction of recharge wells, that is, the screen is attached to the well wall to support the well wall and prevent large volumes of rock debris from falling off. At the same time, a screen is set in the well to filter geothermal water in steam or liquid form; however, due to the complex environment of geothermal water and the large amount of impurities it contains, the screen will be blocked after the recharge well is used for a long time. If it is not cleaned in time, the working efficiency of the recharge well will be greatly reduced.

[0003] The document with authorization announcement number CN113062298B discloses a recharge well anti-blocking device for a geothermal operation system, including a main screen pipe, a dredging assembly, a cleaning assembly and a controller. The main screen pipe is provided with screen holes. The dredging assembly includes a mounting plate, a dredging rod, a first motor, a second motor and a driving mechanism. The first motor is arranged at the bottom of the main screen pipe, the mounting plate is arranged on the output shaft of the first motor, the dredging and driving mechanisms are both arranged inside the mounting plate, the driving mechanism is used to push the dredging rod in and out of the mounting plate, the second motor is used to drive the mounting plate to move in the main screen pipe, the cleaning assembly is arranged at the lower end of the mounting plate, and is used to clean pollutants attached to the inner wall of the main screen pipe, and the controller is electrically connected to the first motor and the second motor respectively.

[0004] However, the above device also has the following defects: the device has a complex structure, and the motor needs to be placed in the water body of the screen tube for a long time to work, which requires high sealing performance of the device, ultimately resulting in high device cost and low practicality. Summary of the invention

[0005] In view of the above-mentioned problems, the purpose of the present invention is to provide an anti-blocking device for a geothermal tail water shock fracturing reinjection system. By setting an upper fixer, a lower fixer, a lifting unit and a cleaning unit, the purpose of cleaning impurities attached to the screen tube holes by vibration is achieved. The device has the advantages of a simple cleaning mode and a good cleaning effect.

[0006] In order to achieve the above object, the technical solution of the present invention is as follows: A blocking prevention device for a geothermal tailwater shock fracturing reinjection system is arranged in a screen tube with a closed bottom and an open upper end, comprising an upper fixture arranged on the upper opening of the screen tube, a lower fixture arranged on the bottom of the screen tube, a lifting unit arranged between the upper fixture and the lower fixture, and a cleaning unit arranged on the lifting unit; the cleaning unit comprises a fixed plate connected to the lifting unit, a launcher arranged on the fixed plate and opening toward the inner wall of the screen tube, impact beads arranged at the opening of the launcher, a high-pressure gas cylinder arranged on the fixed plate and used to provide compressed gas to the launcher, and a supplier arranged on the fixed plate and used to provide the impact beads to the opening of the launcher.

[0007] As a further preferred embodiment of the present invention, the launcher includes a launching tube and a push rod slidably arranged in the launching tube; the supplier includes an input port arranged on the outer wall of the launching tube close to the launching end and connected to the interior of the launching tube, and an input pipe connected to the input port.

[0008] As a further preferred embodiment of the present invention, the fixed plate includes an inner plate body, connecting threaded holes arranged on the inner plate body, an outer ring body arranged on the outside of the inner plate body, a connecting plate for connecting the inner plate body and the outer ring body, and a fixed plate arranged on the outer peripheral side of the outer ring body; the transmitter is installed at the lower end of the outer ring body, the high-pressure gas cylinder is installed on the connecting plate, and the supplier is installed on the fixed plate.

[0009] As a further preferred embodiment of the present invention, the lifting unit includes an external threaded column rotatably arranged between the upper fixer and the lower fixer and connected to the connecting threaded hole, a motor arranged on the upper fixer and used to drive the external threaded column to rotate, a fixing hole arranged on the inner disk body, a fixing rod rotatably arranged on the upper fixer and passing through the fixing hole, and a control member arranged on the upper fixer and used to lock / unlock the position of the fixing rod on the upper fixer.

[0010] As a further preferred embodiment of the present invention, the upper fixer includes a cover body, a mounting opening arranged on the cover body, a mounting tube arranged on the mounting opening and used to close the mounting opening, and the external threaded column is installed at the center of the top surface inside the mounting tube.

[0011] As a further preferred embodiment of the present invention, the control member includes a first ring body and a second ring body which are concentrically arranged on the inner top surface of the mounting tube and used to constitute a track for the rotation of the fixed rod, two through holes arranged on the second ring body, two clamps which respectively pass through the two through holes and are used to fix the fixed rod, and a first driver for driving the two clamps to synchronously extend into / out of the track.

[0012] As a further preferred embodiment of the present invention, the lower fixer includes a mounting base, at least two rods arranged at side ends of the mounting base, and a second driver for driving the rods to extend and retract.

[0013] As a further preferred embodiment of the present invention, the lower fixer also includes a support rod arranged on a side end of the mounting base different from the side end where the rod body is mounted, and a collection net with two ends respectively connected to the rod body and the support rod.

[0014] As a further preferred embodiment of the present invention, the impact bead includes a body and a drag reduction channel arranged in the body.

[0015] As a further preferred embodiment of the present invention, a blocking body is provided on the inner wall of the launching tube close to the launching port.

[0016] The present invention also provides a construction method of the anti-blocking device, the steps comprising: S1, fix the lower fixture on the bottom of the screen tube, then install the lifting unit and the cleaning unit, and finally install the upper fixture on the upper opening of the screen tube; S2, drive the entire cleaning unit to the bottom of the screen tube by controlling the lifting unit, and then start the launcher to launch the impact beads. During this process, the high-pressure gas cylinder continuously provides compressed gas to the launcher, and the supplier continuously provides impact beads to the launcher; S3. The cleaning unit is gradually lifted by controlling the lifting unit. The cleaning unit keeps working during the lifting process, thereby completing the cleaning of the entire screen tube side wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Attached Figure 1 It is a structural schematic diagram of the present invention.

[0018] Attached Figure 2 It is a schematic structural diagram of the fixing plate of the present invention when viewed from an upward angle.

[0019] Attached Figure 3 It is a partial structural schematic diagram of the transmitter of the present invention.

[0020] Attached Figure 4 A schematic diagram of the structure of the impact bead of the present invention.

[0021] Attached Figure 5 It is a schematic diagram of the structure of the control component of the present invention when viewed from an upward angle.

[0022] Description of the drawings: screen tube a, upper fixture 1, lower fixture 2, lifting unit 3, cleaning unit 4; Cover body 11, mounting opening 12, mounting tube 13; Install the base 21, the rod body 22, the second driver 23, the support rod 24, and the collection net 25; External thread column 31, motor 32, fixing rod 33, control member 34; A first ring body 341, a second ring body 342, a through hole 343, a clamping plate 344, and a first driver 345; Fixed plate 41, launcher 42, impact beads 43, high-pressure gas cylinder 44, supplier 45; Inner disc body 411, outer ring body 412, connecting plate 413, fixing plate 414, mounting groove 412a, air pipe fixing hole 413a; Launch tube 421, push rod 422, blocking body 421a; A body 431 and a drag reduction channel 432; Input port 451 and input pipe 452 . DETAILED DESCRIPTION

[0023] In the description of the present invention, it should be understood that the terms "upper", "lower", "inside", "outside", "left", "right", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, or are directions or positional relationships in which the product of the invention is usually placed when in use, or are directions or positional relationships commonly understood by those skilled in the art. These directions or positional relationships are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0024] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms such as "setting" and "connection" should be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection: it can be a mechanical connection or an electrical connection: it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0025] Example 1 The present embodiment provides an anti-blocking device for a geothermal tailwater shock fracturing reinjection system, which is arranged in a screen tube a with a closed bottom and an open upper end, and includes an upper fixer 1 arranged on the upper opening of the screen tube a, a lower fixer 2 arranged on the bottom of the screen tube a, a lifting unit 3 arranged between the upper fixer 1 and the lower fixer 2, and a cleaning unit 4 arranged on the lifting unit 3; the cleaning unit 4 includes a fixing plate 41 connected to the lifting unit 3, a launcher 42 arranged on the fixing plate 41 and opening toward the inner wall of the screen tube a, an impact bead 43 arranged at the opening of the launcher 42, a high-pressure gas cylinder 44 arranged on the fixing plate 41 and used to provide compressed gas to the launcher 42, and a supplier 45 arranged on the fixing plate 41 and used to provide the impact bead 43 to the opening of the launcher 42.

[0026] It is worth noting that the screen tube a is generally a water filter tube with bridge-type holes in the art, or a water filter composed of a skeleton tube, a padding bar, and a winding wire. Regardless of the type of screen tube structure, it has the characteristics of strong impact resistance but relatively hidden holes. Directly using general cleaning structures such as bristles, it is difficult for the bristles to directly contact the holes, so the cleaning effect is poor. Therefore, this embodiment adopts a method of impacting the inner wall of the screen tube, and the impurities blocking the holes are shaken off by vibration to achieve the cleaning of the hidden holes. It can be understood that the above-mentioned impurities are generally particulate matter such as mud and sand.

[0027] In this embodiment, the fixed plate 41 includes an inner plate body 411, a connecting threaded hole arranged on the inner plate body 411, an outer ring body 412 arranged on the outside of the inner plate body 411, a connecting plate 413 for connecting the inner plate body 411 and the outer ring body 412, and a fixing plate 414 arranged on the outer peripheral side of the outer ring body 412; the transmitter 42 is installed at the lower end of the outer ring body 412, the high-pressure gas cylinder 44 is installed on the connecting plate 413, and the supplier 45 is installed on the fixing plate 414.

[0028] It is worth noting that in this embodiment, the number of emitters 42 is 3 to 6, which are evenly spaced along the circumference of the outer ring body 412, so as to be used to launch impact beads 43 at different positions on the inner wall of the screen tube a. The first function of the connecting plate 413 is to connect the concentrically arranged inner disk body 411 and the outer ring body 412, and the second function is to fix the high-pressure gas cylinder 44. Therefore, the number and installation position of the connecting plate 413 correspond to the emitters 42 one by one, so as to ensure that each high-pressure gas cylinder 44 corresponds to a emitter 42. At the same time, in order to ensure the fixing effect of the connecting plate 413 on the high-pressure gas cylinder 44, a limit plate with a limit opening for passing the high-pressure gas cylinder 44 can also be installed in parallel on the upper end of the connecting plate 413. The emitter 42 is connected to the high-pressure gas cylinder 44 through a gas pipe, so a gas pipe fixing hole 413a for fixing the gas pipe is also provided on the connecting plate 413. In order to make the impact bead 43 have a greater impact speed, the launcher 42 can be installed tilted downward, and the lower surface of the outer ring body 412 is provided with a mounting groove 412a, and the bottom surface of the mounting groove 412a has a certain slope. The position and number of the fixing plate 414 correspond to the launcher 42 one by one, and one supplier 45 corresponds to one launcher 42. The fixing plate 414 is provided with a circular through hole, and the circular through hole is used to insert and fix the supplier 45.

[0029] In this embodiment, the launcher 42 includes a launch tube 421 and a push rod 422 slidably disposed in the launch tube 421. A stopper 421a is disposed on the inner wall of the launch tube 421 near the launch port, and the stopper 421a is used to prevent the impact ball 43 from rolling out of the launcher 42 under its own gravity.

[0030] It is worth noting that the launcher 42 also has other structures for improving the effect of the push rod 422 on the impact ball 43. The launcher 42 includes a first cavity, a second cavity, a third cavity, an inner wall of the launch tube and an outer wall of the launch tube. The inner wall of the launch tube and the outer wall of the launch tube form a first cavity. The second cavity is embedded in the inner wall of the launch tube at an angle toward the launch end of the launch tube. One end of the second cavity is connected to the first cavity, and the other end is connected to the cavity of the launch tube. The third cavity is vertically embedded in the upper side wall of the inner wall of the launch tube. The third cavity is a downward converging conical structure that penetrates the inner wall of the launch tube. A floating piston is placed in the third cavity. After the high-pressure gas pushes the push rod out of the launch tube, the high-pressure gas in the cavity of the launch tube at this time The pressure inside the body is greater than the pressure inside the first cavity, the floating piston is lifted by the high-pressure gas, and the high-pressure gas quickly enters the first cavity to disperse the high-pressure gas inside the cavity of the launch tube. When the remaining high-pressure gas inside the cavity of the launch tube rushes out of the launch tube, the pressure inside the cavity of the launch tube decreases, and the floating piston returns to its original position due to gravity to seal the third cavity. At this time, the pressure inside the first cavity is greater than the pressure inside the cavity of the launch tube. At this time, the gas dispersed into the first cavity is dispersed out of the launch tube along the second cavity; this design reduces the instantaneous expansion range of the compressed gas when it rushes out of the launch tube mouth. The above structure refers to the content disclosed in the document CN118323512A.

[0031] In this embodiment, the supplier 45 includes an input port 451 disposed on the outer wall of the launch tube 421 near the launch end and communicating with the interior of the launch tube 421, and an input pipe 452 connected to the input port 451. It is worth noting that the input port 451 is disposed obliquely and is sealedly connected to the input pipe 452. The input port 451 is sealed from the first cavity and is directly connected to the inner cavity of the launch tube.

[0032] In this embodiment, the impact bead 43 includes a body 431 and a drag reduction channel 432 disposed in the body 431. The drag reduction channel 432 is mainly provided to reduce the resistance generated by the water body when the impact bead 43 moves, thereby ensuring the impact speed of the impact bead 432 on the inner wall of the screen tube a.

[0033] It is understandable that the lifting unit 3 can adopt any device in the prior art that can lift / lower the cleaning unit 4, so it will not be described in detail in this embodiment.

[0034] This embodiment also provides a construction method, the steps comprising: S1, fix the lower fixture 2 on the bottom of the screen tube a, then install the lifting unit 3 and the cleaning unit 4, and finally install the upper fixture 1 on the upper end opening of the screen tube a; S2, driving the entire cleaning unit 4 to the bottom of the screen tube a by controlling the lifting unit 3, and then starting the launcher 42 to launch the impact beads 43. During this process, the high-pressure gas cylinder 44 continuously provides compressed gas to the launcher 42, and the supplier 45 continuously provides the impact beads 43 to the launcher 42; S3, gradually lifting the cleaning unit 4 by controlling the lifting unit 3, during which the cleaning unit 4 keeps working, thereby completing the cleaning of the side wall of the entire screen tube a.

[0035] Compared with the prior art, the anti-blocking device provided in this embodiment has at least the following advantages: first, the entire device can be installed when the screen needs to be cleaned, and can be removed when the cleaning is completed, without affecting the amount of water during the re-injection of the screen tube; second, the impurities attached to the holes of the screen tube are cleaned by vibration, which is determined according to the characteristics of the screen tube itself and the characteristics of the impurities, and the cleaning mode is simple and the cleaning effect is good; third, the impact beads dropped into the screen tube can be recycled or not, and when not recycled, they can serve as filtering fillers in the screen, making full use of resources and having the advantage of good economy.

[0036] Example 2 This embodiment optimizes the structure on the basis of the embodiment 1, in order to enable the device to have the function of recovering the impact beads. The specific structure is as follows: In this embodiment, the lower fixture 2 includes a mounting base 21, at least two rods 22 arranged at the side ends of the mounting base 21, and a second driver 23 for driving the rod 22 to extend and retract. The second driver 23 can be an existing structure such as a cylinder or a hydraulic rod, in order to enable the rod 22 to have a telescopic function, so as to tighten the inner wall of the screen with different diameters, thereby ensuring the fixing effect of the lower fixture 2. Furthermore, a ball is provided at the end of the rod 22 close to the inner wall of the screen tube to reduce the friction between the rod 22 and the inner wall.

[0037] In this embodiment, the lower fixture 2 further includes a support rod 24 disposed on the side end of the mounting base 21 different from the side end of the rod body 22, and a collection net 25 connected to the rod body 22 and the support rod 24 at both ends. The support rod 24 is a rod body of fixed length, and its length is less than the radius length of the general inner diameter of the screen tube to ensure that it does not interfere with the installation of the lower fixture. A collection net is installed along the entire side of the support rod, and the other side of the collection net is connected to the side of the rod body 22. The collection net is a flexible net that can be deformed as the position of the rod body 22 changes. The area where the collection net is unfolded is the area where the impact beads are collected. This area cannot completely cover the entire inside of the screen tube, so the collection net can recover a part of the impact beads for the next cleaning use. The impact beads that fall to the bottom surface of the screen tube will not affect the operation of the screen tube.

[0038] Example 3 This embodiment limits the lifting unit 3 on the basis of the embodiment 1, in order to ensure the cleaning effect of the screen tube while reducing the number of emitters 42 .

[0039] In this embodiment, the number of the emitters 42 is one or two, and the lifting unit 3 can not only lift the cleaning unit 4, but also drive the cleaning unit 4 to rotate. The specific structure is as follows: The lifting unit 3 includes an external threaded column 31 rotatably arranged between the upper fixer 1 and the lower fixer 2 and connected to the connecting threaded hole, a motor 32 arranged on the upper fixer 1 and used to drive the external threaded column 31 to rotate, a fixing hole arranged on the inner disk body 411, a fixing rod 33 rotatably arranged on the upper fixer 1 and passing through the fixing hole, and a control member 34 arranged on the upper fixer 1 and used to lock / unlock the position of the fixing rod 33 on the upper fixer 1.

[0040] The upper fixture 1 includes a cover body 11 , a mounting opening 12 disposed on the cover body 11 , and a mounting tube 13 disposed on the mounting opening 12 and used to close the mounting opening 12 . The external threaded column 31 is installed at the center of the inner top surface of the mounting tube 13 .

[0041] The control member 34 includes a first ring body 341 and a second ring body 342 which are arranged concentrically on the inner top surface of the mounting tube 13 and are used to form a track for the rotation of the fixing rod 33, two through holes 343 arranged on the second ring body 342, two clamping plates 344 respectively passing through the two through holes 343 and used to fix the fixing rod 33, and a first driver 345 used to drive the two clamping plates 344 to synchronously extend into / exit the track. The upper end of the fixing rod 33 is inserted into the track formed by the two ring bodies. In order to reduce resistance, a roller or other structure can be arranged on the upper end of the fixing rod 33; a section of the two clamping plates 344 away from the through holes 343 can be connected by a same plate to ensure the synchronous movement of the two clamping plates 344; the first driver 345 can be a push cylinder installed on the mounting tube 13, and the end of the cylinder is connected to the plate.

[0042] In this embodiment, the working principle of the control part is as follows: the first driver drives the two clamping plates to exit the track, at which time the fixed rod can rotate in the track, and the inner disk loses the fixing effect of the fixed rod. Therefore, driven by the rotation of the external threaded column, the inner disk rotates, and the height on the external threaded column remains unchanged. At this time, the launcher can rotate in a fixed position, so as to completely clean the inner wall of the screen tube at the same height; after the first driver drives the two clamping plates to enter the track and clamp the fixed rod, the position of the fixed rod is fixed. At this time, the inner disk is driven by the rotation of the external threaded column to rise and fall along the external threaded column, completing the adjustment of the height position of the entire cleaning unit. Therefore, this embodiment repeats the above two modes to complete the cleaning of the entire inner wall of the screen tube.

[0043] It is worth noting that the number of clamping structures formed by the clamping plate and the first driver for clamping the fixing rod can be one or more. In the case of a single clamping structure, the clamping plate can only clamp the fixing rod when the fixing rod needs to move to a preset position. At this time, the height of the cleaning unit that can be adjusted at one time is fixed; as the number of clamping structures increases, the height options for the cleaning unit to be adjusted at one time are more, so the structure is selected according to the actual scene requirements.

[0044] The anti-blocking device provided in this embodiment has the following advantages: two modes of cleaning unit lifting and cleaning unit rotation are realized through the setting of the control component, the number of emitters is reduced, and the cost is further reduced, and it has the advantages of strong practicality and good economy.

[0045] The specific embodiments described herein are merely examples of the spirit of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in similar ways, but they will not deviate from the spirit of the present invention or exceed the scope defined by the appended claims.

Claims

1. An anti-blocking device for a geothermal tailwater shock fracturing reinjection system, arranged in a screen tube (a) with a closed bottom and an open top, characterized in that: It comprises an upper fixer (1) arranged on the upper end opening of the screen tube (a), a lower fixer (2) arranged on the bottom of the screen tube (a), a lifting unit (3) arranged between the upper fixer (1) and the lower fixer (2), and a cleaning unit (4) arranged on the lifting unit (3); The cleaning unit (4) comprises a fixing plate (41) connected to the lifting unit (3), a launcher (42) arranged on the fixing plate (41) and opening toward the inner wall of the screen tube (a), impact beads (43) arranged at the opening of the launcher (42), a high-pressure gas cylinder (44) arranged on the fixing plate (41) and used to supply compressed gas to the launcher (42), and a supplier (45) arranged on the fixing plate (41) and used to supply the impact beads (43) to the opening of the launcher (42).

2. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 1 is characterized in that: The launcher (42) comprises a launch tube (421) and a push rod (422) slidably disposed in the launch tube (421); the supplier (45) comprises an input port (451) disposed on an outer wall of the launch tube (421) close to a launch end and communicating with the interior of the launch tube (421), and an input pipe (452) connected to the input port (451).

3. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 1 is characterized in that: The fixed disk (41) comprises an inner disk body (411), a connecting threaded hole arranged on the inner disk body (411), an outer ring body (412) arranged outside the inner disk body (411), a connecting plate (413) for connecting the inner disk body (411) and the outer ring body (412), and a fixing plate (414) arranged on the outer peripheral side of the outer ring body (412); the transmitter (42) is mounted on the lower end of the outer ring body (412), the high-pressure gas cylinder (44) is mounted on the connecting plate (413), and the supplier (45) is mounted on the fixing plate (414).

4. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 3 is characterized in that: The lifting unit (3) includes an external threaded column (31) rotatably arranged between the upper fixer (1) and the lower fixer (2) and connected to the connecting threaded hole, a motor (32) arranged on the upper fixer (1) and used to drive the external threaded column (31) to rotate, a fixing hole arranged on the inner disk (411), a fixing rod (33) rotatably arranged on the upper fixer (1) and passing through the fixing hole, and a control member (34) arranged on the upper fixer (1) and used to lock / unlock the position of the fixing rod (33) on the upper fixer (1).

5. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 4 is characterized in that: The upper fixer (1) comprises a cover body (11), a mounting opening (12) arranged on the cover body (11), and a mounting tube (13) arranged on the mounting opening (12) and used to close the mounting opening (12), wherein the external threaded column (31) is mounted at the center of the inner top surface of the mounting tube (13).

6. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 5 is characterized in that: The control member (34) comprises a first ring body (341) and a second ring body (342) which are arranged concentrically on the inner top surface of the mounting tube (13) and used to form a track for the rotation of the fixing rod (33), two through holes (343) arranged on the second ring body (342), two clamping plates (344) respectively passing through the two through holes (343) and used to fix the fixing rod (33), and a first driver (345) for driving the two clamping plates (344) to synchronously extend into / out of the track.

7. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 1 is characterized in that: The lower fixer (2) comprises a mounting base (21), at least two rod bodies (22) arranged at the side ends of the mounting base (21), and a second driver (23) for driving the rod bodies (22) to extend and retract.

8. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 7 is characterized in that: The lower fixer (2) further comprises a support rod (24) arranged on a side end of the mounting base (21) different from the side end on which the rod body (22) is mounted, and a collection net (25) having two ends respectively connected to the rod body (22) and the support rod (24).

9. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 1, characterized in that: The impact bead (43) comprises a body (431) and a drag reduction channel (432) arranged in the body (431).

10. The anti-blocking device of the geothermal tail water shock fracturing reinjection system according to claim 2, characterized in that: A blocking body (421a) is provided on the inner wall of the launching tube (421) close to the launching port.