A method, device, equipment and medium for measuring junction temperature of a power semiconductor device
By controlling the DC bus voltage and cutting time in an inductive load converter, the rapid cut-off of the current of the power semiconductor device is solved, and the problem of inaccurate temperature measurement in the prior art is improved, and the accuracy and reliability of junction temperature measurement are improved.
Patent Information
- Application Number
- CN202411203665.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-08-30
AI Technical Summary
The prior art causes inaccurate temperature measurement when the high current and small current are switched quickly in the measurement of power semiconductor devices, which affects the accuracy of junction temperature measurement.
By controlling the driving signal of the inductive load converter, the DC bus voltage opposite to that in the operating condition is applied to the energy storage device, the minimum cutting time is determined, and the current of the measured power semiconductor device is quickly cut off, and based on the on-voltage drop data Obtain the junction temperature.
The rapid and reliable cut-off of the current of the power semiconductor device to be tested is achieved, the accuracy of junction temperature measurement is improved, and the junction temperature drop caused by the removal time is reduced.
Smart Images

Figure CN118731628B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power semiconductor technology, and in particular to a method, device, equipment and medium for measuring the junction temperature of a power semiconductor device. Background Art
[0002] Power semiconductor devices, also known as power electronic devices, are high-power electronic devices mainly used in power conversion and control circuits of power equipment. The junction temperature of a power semiconductor device refers to the actual operating temperature inside the power semiconductor device. The junction temperature is very important for the performance and reliability of power semiconductor devices. Normally, power semiconductor devices generate heat during operation. If the junction temperature is too high, it may affect its electrical characteristics and life.
[0003] At present, the method for obtaining the junction temperature of power semiconductor devices under working conditions is the on-state voltage drop method. The on-state voltage drop of the power semiconductor device when a large current (usually a DC current of more than 30A) or a small current (usually less than 100mA) is injected as a temperature-sensitive parameter to indirectly obtain the junction temperature of the power semiconductor device under working conditions. When obtaining the junction temperature of the power semiconductor device by injecting a small current, it is necessary to cut off the current flowing through the power semiconductor device at the time of temperature measurement and inject a small current of less than 100mA into the power semiconductor device. The technical difficulty of this method lies in achieving rapid switching between the large current under the working conditions of the power semiconductor device and the small current injected during temperature measurement.
[0004] In the prior art, a relay is used to directly cut off a large current under working conditions of a power semiconductor device. The cut-off time of the relay is about tens of milliseconds, resulting in a long time for the large current on the power semiconductor device to drop to zero. The junction temperature of the power semiconductor device drops significantly, resulting in inaccurate temperature measurement, thereby reducing the accuracy of the junction temperature measurement. Summary of the invention
[0005] In order to solve the above problems, the present invention provides a method, device, electronic equipment and storage medium for measuring the junction temperature of a power semiconductor device.
[0006] In a first aspect, the present invention provides a method for measuring the junction temperature of a power semiconductor device, which is applicable to measuring the junction temperature of a power semiconductor device under working conditions in an inductive load converter, comprising:
[0007] Controlling the driving signal of the power semiconductor device in the inductive load converter so that a DC bus voltage opposite to that in the working condition is applied to the energy storage device of the inductive load converter;
[0008] Determining a minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device;
[0009] When it is determined that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, current is injected into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test, and the junction temperature of the power semiconductor device under test is obtained based on the on-state voltage drop data.
[0010] Optionally, it also includes:
[0011] A target cut-off time is generated according to the minimum cut-off time, and it is determined that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the target cut-off time, and current is injected into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test.
[0012] Optionally, the target resection time is 1.5 to 2 times the minimum resection time.
[0013] Optionally, acquiring the junction temperature of the power semiconductor device under test based on the on-state voltage drop data includes:
[0014] Inputting the on-state voltage drop data into a preset linear function to obtain the junction temperature of the power semiconductor device under test;
[0015] The linear function is a linear relationship between the on-state voltage drop and the junction temperature.
[0016] Optionally, determining the minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device includes:
[0017] The DC bus voltage, the impedance and the current are processed based on a preset calculation model to obtain the minimum removal time.
[0018] Optionally, the operation model is:
[0019] ;
[0020] in, is the minimum removal time, is the impedance of the energy storage device, is the current on the energy storage device, is the DC bus voltage.
[0021] In a second aspect, the present invention provides a device for measuring the junction temperature of a power semiconductor device, which is suitable for measuring the junction temperature of a power semiconductor device under working conditions in an inductive load converter, comprising:
[0022] A control module, used for controlling the driving signal of the power semiconductor device in the inductive load converter, so that a DC bus voltage opposite to that in the working condition is applied to the energy storage device of the inductive load converter;
[0023] A processing module, used for determining a minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device;
[0024] A measuring module is used to determine that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, inject current into the power semiconductor device under test on the inductive load converter to obtain the conduction voltage drop data of the power semiconductor device under test, and obtain the junction temperature of the power semiconductor device under test based on the conduction voltage drop data.
[0025] Optionally, it also includes:
[0026] A time module is used to generate a target cut-off time according to the minimum cut-off time, and to determine that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the target cut-off time, and then inject current into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test.
[0027] In a third aspect, the present invention provides an electronic device, including a memory and a processor;
[0028] The memory is used to store computer programs;
[0029] The processor is used to implement the method for measuring the junction temperature of a power semiconductor device as described in the first aspect when executing the computer program.
[0030] In a fourth aspect, the present invention provides a computer-readable storage medium having a computer program stored thereon. When the computer program is executed by a processor, the method for measuring the junction temperature of a power semiconductor device as described in the first aspect is implemented.
[0031] The method, device, electronic device and storage medium for measuring the junction temperature of a power semiconductor device of the present invention have the following beneficial effects:
[0032] By controlling the driving signal of the inductive load converter, the opposite DC bus voltage is applied to the energy storage device of the inductive load converter, so as to realize the rapid current cut-off of the power semiconductor device under test, and reduce the junction temperature drop of the power semiconductor device under test caused by the cut-off time. By determining the minimum cut-off time, it is convenient to accurately cut off the current. The current is injected into the power semiconductor device under test on the inductive load converter to obtain the conduction voltage drop data of the power semiconductor device under test, and the junction temperature of the power semiconductor device under test is obtained based on the conduction voltage drop data. No additional control device is required, and the current cut-off is realized only by changing the driving signal, so that the junction temperature can be obtained quickly and reliably and the accuracy of the junction temperature can be improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 A schematic flow chart of a method for measuring the junction temperature of a power semiconductor device provided in an embodiment of the present invention.
[0034] Figure 2 A schematic flow chart of a method for measuring the junction temperature of a power semiconductor device provided in an embodiment of the present invention.
[0035] Figure 3 Schematic diagram of the circuit working state at each stage in the embodiment of the present invention; wherein, Figure 3 A) is the heating stage of charging, B) is the heating stage of continuous current, C) is the cutting-off stage of discharge, and D) is the cooling stage of small current injection.
[0036] Figure 4 Schematic diagram of voltage and inductor current waveforms of a power semiconductor device under test in an embodiment of the present invention.
[0037] Figure 5 Schematic diagram of the discharge circuit in the removal stage in an embodiment of the present invention; wherein, Figure 5 A) in the figure is the positive half-cycle current discharge circuit, and B) is the negative half-cycle current discharge circuit.
[0038] Figure 6 Schematic diagram of the structure of a three-phase DC-AC inverter circuit in an embodiment of the present invention.
[0039] Figure 7 The present invention is a schematic structural diagram of a device for measuring the junction temperature of a power semiconductor device according to an embodiment of the present invention.
[0040] Figure 8 The figure is a schematic diagram of the structure of an electronic device according to an embodiment of the present invention. DETAILED DESCRIPTION
[0041] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. Although certain embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be interpreted as being limited to the embodiments described herein. On the contrary, these embodiments are provided to provide a more thorough and complete understanding of the present invention. It should be understood that the drawings and embodiments of the present invention are only for exemplary purposes and are not intended to limit the scope of protection of the present invention.
[0042] It should be understood that the various steps described in the method embodiments of the present invention may be performed in different orders and / or in parallel. In addition, the method embodiments may include additional steps and / or omit the steps shown. The scope of the present invention is not limited in this respect.
[0043] The term "including" and its variations used in this document are open inclusions, that is, "including but not limited to"; the term "based on" means "based at least in part on"; the term "one embodiment" means "at least one embodiment"; the term "another embodiment" means "at least one other embodiment"; the term "some embodiments" means "at least some embodiments"; the term "optionally" means "optional embodiments". The relevant definitions of other terms will be given in the following description. It should be noted that the concepts of "first", "second", etc. mentioned in the present invention are only used to distinguish different devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these devices, modules or units.
[0044] It should be noted that the modifications of "one" and "plurality" mentioned in the present invention are illustrative rather than restrictive, and those skilled in the art should understand that, unless otherwise clearly indicated in the context, it should be understood as "one or more".
[0045] The names of the messages or information exchanged between multiple devices in the embodiments of the present invention are only used for illustrative purposes, and are not used to limit the scope of these messages or information.
[0046] In the related art, under the topological structure of the inductive load converter, it is necessary to issue a cut-off command to the power semiconductor device under test on the converter, and wait for the current flowing through the power semiconductor device under test to drop from the actual operating value to zero before starting to inject a small current, so as to ensure the safety of the power circuit and the small current injection device of the converter. Therefore, the selection of the time to wait for the current to drop after the cut-off is particularly critical for the junction temperature measurement method of small current injection. If the waiting time is too short, the current may not drop to the safety threshold at this time, causing damage to the small current injection device; if the waiting time is too long, the junction temperature of the device may drop significantly during the waiting process, resulting in inaccurate temperature measurement.
[0047] While the power semiconductor device under test switches rapidly between high current and low current, firstly, there is a lack of control methods to quickly reduce the current flowing through the power semiconductor device under test under the common resistive-inductive load converter topology. The method of using relays for cutting off in the power cycle test has a cutting off time of about tens of milliseconds, which will cause a significant reduction in the junction temperature of the power semiconductor device under test; by shutting off the cut-off current of the power semiconductor device under test, the current will continue to flow through the parasitic parameters of the power circuit, and the time waiting for it to naturally decrease is long, which cannot meet the instantaneous acquisition of junction temperature. Secondly, there is a lack of quantitative judgment basis for the cut-off waiting time under different currents, bus voltages and switching frequencies. The waiting time selected based on experience may not meet the measurement requirements of the device under test under all working conditions.
[0048] In view of the problems existing in the above-mentioned related technologies, the present embodiment provides a method, an apparatus, an electronic device and a storage medium for measuring the junction temperature of a power semiconductor device.
[0049] like Figure 1 As shown, a method for measuring the junction temperature of a power semiconductor device provided by an embodiment of the present invention is applicable to measuring the junction temperature of a power semiconductor device under working conditions in an inductive load converter, and includes:
[0050] S100: Controlling the driving signal of the power semiconductor device in the inductive load converter so that a DC bus voltage opposite to that in the working condition is applied to the energy storage device of the inductive load converter.
[0051] In this step, the driving signals of each power semiconductor device on the inductive load converter are controlled. By controlling the driving signals of each power semiconductor device, a DC bus voltage opposite to that in the operating condition is applied to both ends of the energy storage device of the inductive load converter to discharge rapidly, thereby reducing the time for the current flowing through the measured power semiconductor device to be reduced to zero to less than one millisecond. This can minimize the interval time from normal operating condition to small current injection state, and avoid the problem of excessive drop in junction temperature of the measured power semiconductor device and inaccurate temperature measurement due to too long an interval.
[0052] It should be noted that the inductive load converter has at least two power semiconductor devices, and the power semiconductor device under test is one of the multiple power semiconductor devices.
[0053] S200: Determine a minimum disconnection time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device, and the current on the energy storage device.
[0054] In this step, the key circuit parameters of the inductive load converter are determined, including: DC bus voltage, impedance of the energy storage device, and current of the energy storage device. The minimum cut-off time can be obtained based on the key circuit parameters of the inductive load converter, and the quantitative calculation of the cut-off time can be achieved. In actual use, it is ensured that the current on the tested power semiconductor device is cut off reliably and quickly, ensuring the safety of subsequent small current injection.
[0055] Specifically, the minimum cut-off time of the inductive load converter is determined according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device, including:
[0056] The DC bus voltage, the impedance and the current are processed based on a preset operation model to obtain the minimum removal time. The operation model is:
[0057] ;
[0058] in, is the minimum removal time, is the impedance of the energy storage device, is the current on the energy storage device, is the DC bus voltage.
[0059] S300: When it is determined that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, current is injected into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test, and the junction temperature of the power semiconductor device under test is obtained based on the on-state voltage drop data.
[0060] In this step, if the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, it indicates that the current flowing through the power semiconductor device under test has dropped to zero. After the current flowing through the power semiconductor device under test is zero, turn on the test current source to inject current into the power semiconductor device under test. Measure the conduction voltage drop data of the power semiconductor device under test, and determine the junction temperature of the power semiconductor device under the working condition based on the conduction voltage drop data.
[0061] Wherein, the junction temperature of the power semiconductor device under test is obtained based on the on-state voltage drop data, including:
[0062] The on-state voltage drop data is input into a preset linear function to obtain the junction temperature of the power semiconductor device under test; wherein the linear function is the linear relationship between the on-state voltage drop and the junction temperature, and the linear function is:
[0063] ;
[0064] in, is the junction temperature of the power semiconductor device under test, is the conduction voltage drop of the power semiconductor device under test, k and b Is a constant.
[0065] In this embodiment, by controlling the driving signal of the inductive load converter, an opposite DC bus voltage is applied to the energy storage device of the inductive load converter, so as to realize the rapid current cut-off of the power semiconductor device under test, and reduce the junction temperature drop of the power semiconductor device under test caused by the cut-off time. By determining the minimum cut-off time, it is convenient to accurately cut off the current. The current is injected into the power semiconductor device under test on the inductive load converter to obtain the conduction voltage drop data of the power semiconductor device under test, and the junction temperature of the power semiconductor device under test is obtained based on the conduction voltage drop data. No additional control device is required, and the current cut-off is realized only by changing the driving signal, so that the junction temperature can be obtained quickly and reliably and the accuracy of the junction temperature can be improved.
[0066] Based on the above embodiments, see Figure 2 , also includes:
[0067] S400: Generate a target cut-off time according to the minimum cut-off time, determine that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the target cut-off time, and then inject current into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test.
[0068] In this embodiment, taking a common 750V / 50A inductive load converter as an example, the inductance value is taken as 100uH, and the calculated minimum cut-off time is 6.7us, which is much less than the tens of milliseconds of relay cut-off, and can ensure the instantaneous acquisition of junction temperature. Based on the safety margin factor, the actual cut-off time is determined to be 1.5~2 times the minimum cut-off time. In other words, 1.5~2 times the minimum cut-off time is taken as the target cut-off time, and after determining that the duration of the DC bus voltage opposite to that in the working condition is applied to the energy storage device is greater than the target cut-off time, a current is injected into the power semiconductor device under test on the inductive load converter to obtain the conduction voltage drop data of the power semiconductor device under test.
[0069] In this embodiment, the minimum cut-off time is determined based on the key circuit parameters of the inductive load converter. The minimum cut-off time is much shorter than the cut-off time of the relay, which can ensure the instantaneous acquisition of the junction temperature.
[0070] To further illustrate the present solution, the present invention provides a specific example of a method for measuring the junction temperature of a power semiconductor device, taking the inductive load converter as a DC-DC full-bridge conversion circuit as an example. Figure 3As shown in the schematic diagram of the circuit working state in each stage, the control cycle of the control method of the DC-DC full-bridge conversion circuit includes: a heating stage, a removal stage and a cooling stage.
[0071] During the heating phase, the power semiconductor device under test is placed in a high-frequency PWM (Pulse Width Modulation) switching mode under actual operating conditions. During the cut-off phase, the current flowing through the power semiconductor device under test is quickly reduced to zero through current cut-off control. During the cooling phase, the operating junction temperature of the power semiconductor device under test is obtained according to the small current injection method.
[0072] It should be noted that during the heating stage, the power semiconductor device under test is in a normal operating state. In this state, self-heating is generated, including switching loss power generated by high-frequency switching and conduction loss power generated by turning on the current flowing through it, and the inductor is in a charging-freewheeling alternating state during the heating stage.
[0073] like Figure 3 The schematic diagram of the circuit working state in each stage is shown. Taking device T1 as an example to obtain the junction temperature of the power semiconductor device under test, when the circuit is running in the heating stage, the symmetrical side devices T1 and T4 are turned on, and the DC bus voltage is applied to both ends of the inductor to charge quickly, and the inductor current rises rapidly; then device T4 is turned off, and the inductor current is continued through the loop formed by device T1-device L-device D3, and the inductor current slowly decreases. In the heating stage, the above charging-continuous current process is performed alternately. After the next charging in the same control cycle, device T1 is turned off during continuous current, and the inductor current is continued through the loop formed by device D2-device L-device T4. The heating stage reflects the thermal behavior of the power semiconductor device under test when it is operating under normal operating conditions.
[0074] In the removal stage, by removing the driving signal of the power semiconductor device under test, the two ends of the inductor are subjected to the reverse bus voltage and discharged quickly, thereby reducing the time for the current flowing through the power semiconductor device under test to zero to less than one millisecond, which can minimize the interval time from normal operation to the small current injection state, and avoid excessive drop in the junction temperature of the power semiconductor device under test and inaccurate temperature measurement due to too long an interval. When it is necessary to obtain the junction temperature of device T1, the removal stage is entered, and the drive circuit sends a shutdown drive signal to the four devices (device T1, device T2, device T3 and device T4). Since the inductor current cannot change suddenly, it is commutated through the device D2-device L-device D3 path. At this time, the reverse bus voltage is applied to both ends of the inductor, which can ensure that the inductor current decreases at the maximum rate, and then quickly and safely enters the subsequent cooling stage of small current injection.
[0075] During the cooling phase, after the current flowing through the power semiconductor device under test drops to zero, the test current source is turned on to measure the on-state voltage drop data of the power semiconductor device under test, and the junction temperature of the power semiconductor device under test is obtained through the relationship function of the on-state voltage drop-junction temperature under the pre-set small current. After the removal phase is over, the cooling phase begins, and the on-state drive signal is sent to the power semiconductor device under test again. At the same time, the small current injection device is turned on to inject a small current of tens of milliamperes into the power semiconductor device under test. According to the pre-set junction temperature under the small current With the on-state voltage drop Relationship , according to the conduction voltage drop after entering the cooling stage The junction temperature is calculated indirectly from the data.
[0076] It should be noted that the voltage and inductor current waveforms of the power semiconductor device under test in the above-mentioned junction temperature acquisition method are as follows: Figure 4 The circuit topology is Figure 3 The full-bridge DC-DC circuit shown has a DC bus voltage of 400V, an inductor current of 30A, and an inductor value of 500uH. A cut-off command is issued at a certain moment in the heating stage, and the inductor current is quickly cut off according to the above control method, which can quickly reduce the inductor current to a safe range in a very short time. Then enter the cooling stage, turn on the test current source to inject a small current of 60mA into the device, and calculate the device junction temperature when the current is cut off based on the on-state voltage drop data recorded in the cooling stage.
[0077] From the above description, it can be seen that the method for measuring the junction temperature of the power semiconductor device in this embodiment uses a specific drive control signal to quickly cut off the current of the measured power semiconductor device, thereby safely entering the small current injection state while reducing the junction temperature drop of the device caused by the cut-off time as much as possible. There is no need to introduce additional circuit control devices, and the current is cut off only by changing the drive signal. The cut-off instruction can be issued at any time when the circuit is running. In addition, for key circuit parameters, the minimum cut-off time of current cut-off is clearly given, and the current is cut off based on the minimum cut-off time, which has the beneficial effects of high sensitivity, good accuracy, and no delay in temperature acquisition. Moreover, the current cut-off is fast and reliable, and the junction temperature acquisition accuracy is high, which can effectively improve the accuracy of device reliability analysis related to junction temperature.
[0078] It should be noted that the current removal method provided in this embodiment is not only applicable to full-bridge DC-DC conversion circuits, but also applicable to DC-AC inverter applications. Except that the control method in the heating stage is different from that in the single-phase full-bridge DC-DC, the current rapid discharge removal control method in the removal stage is the same, and both of them discharge by applying a reverse bus voltage to both ends of the inductor by sending a shutdown drive signal to the specified device.
[0079] When applied to single-phase DC-AC inverter applications, the current discharge method in the cut-off stage is as follows Figure 5 As shown. If the inductor current is in the positive half cycle when the cut-off command is issued, it is discharged through the circuit formed by device D1-device L-device D4; if the inductor current is in the negative half cycle, it is discharged through the circuit of device D2-device L-device D3. In the above two discharge modes, the reverse bus voltage is loaded at both ends of the inductor. The current cut-off time needs to consider the maximum current on the AC side . Minimum current cut-off time The calculation formula is:
[0080]
[0081] When applied to three-phase DC-AC inverters, the discharge circuit in the cut-off phase when each phase current is in the positive and negative half cycles is the same as that of single-phase DC-AC inverters. In addition, since the discharge circuit passes through two inductors ,like Figure 6 As shown in the figure, assuming that the three-phase inductance used is the same, the minimum cut-off time is The calculation formula is:
[0082] .
[0083] It should be noted that the junction temperature measurement method provided in this embodiment, the power electronic topology of the measured power semiconductor device includes but is not limited to two-level H-bridge, three-level H-bridge, three-phase full-bridge circuit, MMC cascade converter and other application scenarios, and can be applied to DC-DC voltage conversion, DC-AC inversion and other working states involving PWM switching conditions of power semiconductor devices.
[0084] like Figure 7 As shown, a device 700 for measuring the junction temperature of a power semiconductor device provided in an embodiment of the present invention is suitable for measuring the junction temperature of a power semiconductor device under working conditions in an inductive load converter, and includes:
[0085] A control module 710, configured to control a drive signal of the power semiconductor device in the inductive load converter so that a DC bus voltage opposite to that in a working condition is applied to the energy storage device of the inductive load converter;
[0086] A processing module 720, configured to determine a minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device;
[0087] The measurement module 730 is used to determine that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, then inject current into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test, and obtain the junction temperature of the power semiconductor device under test based on the on-state voltage drop data.
[0088] Optionally, it also includes:
[0089] A time module is used to generate a target cut-off time according to the minimum cut-off time, and to determine that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the target cut-off time, and then inject current into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test.
[0090] Optionally, the target resection time is 1.5 to 2 times the minimum resection time.
[0091] Optionally, acquiring the junction temperature of the power semiconductor device under test based on the on-state voltage drop data includes:
[0092] Inputting the on-state voltage drop data into a preset linear function to obtain the junction temperature of the power semiconductor device under test;
[0093] The linear function is a linear relationship between the on-state voltage drop and the junction temperature.
[0094] Optionally, determining the minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device includes:
[0095] The DC bus voltage, the impedance and the current are processed based on a preset calculation model to obtain the minimum removal time.
[0096] Optionally, the operation model is:
[0097] ;
[0098] in, is the minimum removal time, is the impedance of the energy storage device, is the current on the energy storage device, is the DC bus voltage.
[0099] The device for measuring the junction temperature of a power semiconductor device in this embodiment is used to implement the method for measuring the junction temperature of a power semiconductor device as described above. Its advantages over the prior art are the same as the advantages of the method for measuring the junction temperature of a power semiconductor device as described above over the prior art, and will not be repeated here.
[0100] like Figure 8 As shown, an electronic device 800 provided by an embodiment of the present invention includes a memory 820 and a processor 810; the memory 820 is used to store a computer program; the processor 810 is used to implement the above-mentioned method for measuring the junction temperature of a power semiconductor device when executing the computer program.
[0101] In other words, an electronic device 800 includes a memory 820 and a processor 810 coupled to the memory 820; the memory 820 is configured to store a computer program; and the processor 810 is configured to perform the following operations when executing the computer program:
[0102] Controlling the driving signal of the power semiconductor device in the inductive load converter so that a DC bus voltage opposite to that in the working condition is applied to the energy storage device of the inductive load converter;
[0103] Determining a minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device;
[0104] When it is determined that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, current is injected into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test, and the junction temperature of the power semiconductor device under test is obtained based on the on-state voltage drop data.
[0105] An embodiment of the present invention provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the above-mentioned method for measuring the junction temperature of a power semiconductor device is implemented.
[0106] In other words, a non-volatile computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the processor performs the following operations:
[0107] Controlling the driving signal of the power semiconductor device in the inductive load converter so that a DC bus voltage opposite to that in the working condition is applied to the energy storage device of the inductive load converter;
[0108] Determining a minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device;
[0109] When it is determined that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, current is injected into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test, and the junction temperature of the power semiconductor device under test is obtained based on the on-state voltage drop data.
[0110] An electronic device 800 that can be used as a server or client of the present invention will now be described, which is an example of a hardware device that can be applied to various aspects of the present invention. The electronic device 800 is intended to represent various forms of digital electronic computer equipment, such as laptop computers, desktop computers, workbenches, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device 800 can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices, and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples, and are not intended to limit the implementation of the present invention described herein and / or required.
[0111] The electronic device 800 includes a computing unit, which can perform various appropriate actions and processes according to a computer program stored in a read-only memory (ROM) or a computer program loaded from a storage unit into a random access memory (RAM). In the RAM, various programs and data required for the operation of the device can also be stored. The computing unit, ROM, and RAM are connected to each other via a bus. An input / output (I / O) interface is also connected to the bus.
[0112] A person of ordinary skill in the art can understand that all or part of the processes in the above-mentioned embodiment method can be implemented by instructing the relevant hardware through a computer program, and the program can be stored in a computer-readable storage medium. When the program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, the storage medium can be a disk, an optical disk, a read-only memory (ROM) or a random access memory (RAM), etc. In the present application, the unit described as a separate component may or may not be physically separated, and the component displayed as a unit may or may not be a physical unit, that is, it may be located in one place, or it may be distributed on multiple network units. Some or all of the units can be selected according to actual needs to achieve the purpose of the embodiment of the present invention. In addition, each functional unit in each embodiment of the present invention can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of a software functional unit.
[0113] Although the present invention is disclosed as above, the protection scope of the present invention is not limited thereto. Those skilled in the art may make various changes and modifications without departing from the spirit and scope of the present invention, and these changes and modifications will fall within the protection scope of the present invention.
Claims
1. A method for measuring the junction temperature of a power semiconductor device, which is suitable for measuring the junction temperature of a power semiconductor device under working conditions in an inductive load converter. It is characterized in that include: Controlling the driving signal of the power semiconductor device in the inductive load converter so that a DC bus voltage opposite to that in the working condition is applied to the energy storage device of the inductive load converter; Determining a minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device; When it is determined that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, current is injected into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test, and the junction temperature of the power semiconductor device under test is obtained based on the on-state voltage drop data.
2. The method for measuring the junction temperature of a power semiconductor device according to claim 1, It is characterized in that Also includes: A target cut-off time is generated according to the minimum cut-off time, and it is determined that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the target cut-off time, and current is injected into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test.
3. The method for measuring the junction temperature of a power semiconductor device according to claim 2, It is characterized in that The target resection time is 1.5 to 2 times of the minimum resection time.
4. The method for measuring the junction temperature of a power semiconductor device according to claim 1, It is characterized in that The step of acquiring the junction temperature of the power semiconductor device under test based on the on-state voltage drop data comprises: Inputting the on-state voltage drop data into a preset linear function to obtain the junction temperature of the power semiconductor device under test; The linear function is a linear relationship between the on-state voltage drop and the junction temperature.
5. The method for measuring the junction temperature of a power semiconductor device according to claim 1, It is characterized in that Determining the minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device includes: The DC bus voltage, the impedance and the current are processed based on a preset calculation model to obtain the minimum removal time.
6. The method for measuring the junction temperature of a power semiconductor device according to claim 5, It is characterized in that The operation model is: ; in, is the minimum removal time, is the impedance of the energy storage device, is the current on the energy storage device, is the DC bus voltage.
7. A device for measuring the junction temperature of a power semiconductor device, suitable for measuring the junction temperature of a power semiconductor device under working conditions in an inductive load converter. It is characterized in that include: A control module, used for controlling the driving signal of the power semiconductor device in the inductive load converter, so that a DC bus voltage opposite to that in the working condition is applied to the energy storage device of the inductive load converter; A processing module, used for determining a minimum cut-off time of the inductive load converter according to the DC bus voltage, the impedance of the energy storage device and the current on the energy storage device; A measuring module is used to determine that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the minimum cut-off time, inject current into the power semiconductor device under test on the inductive load converter to obtain the conduction voltage drop data of the power semiconductor device under test, and obtain the junction temperature of the power semiconductor device under test based on the conduction voltage drop data.
8. The device for measuring junction temperature of a power semiconductor device according to claim 7, It is characterized in that Also includes: A time module is used to generate a target cut-off time according to the minimum cut-off time, and to determine that the duration of applying a DC bus voltage opposite to that in the working condition to the energy storage device is greater than the target cut-off time, and then inject current into the power semiconductor device under test on the inductive load converter to obtain the on-state voltage drop data of the power semiconductor device under test.
9. An electronic device, It is characterized in that including memory and processor; The memory is used to store computer programs; The processor is used to implement the method for measuring the junction temperature of a power semiconductor device as claimed in any one of claims 1 to 6 when executing the computer program.
10. A computer-readable storage medium, It is characterized in that The storage medium stores a computer program, and when the computer program is executed by a processor, the method for measuring the junction temperature of a power semiconductor device according to any one of claims 1 to 6 is implemented.