Electrical equipment data monitoring and analyzing system and method based on Internet of Things

Through real-time monitoring and data analysis of Internet of Things technology, the status index of electrical equipment is classified and processed, and appropriate maintenance methods and cycles are selected to solve the problem of excess and insufficient maintenance and improve the utilization efficiency and safety of equipment.

CN118734174AInactive Publication Date: 2024-10-01JINGJIANG XINHUA PORT CO LTD

Patent Information

Application Number
CN202411117593.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology is prone to problems of over-maintenance or insufficient maintenance during the maintenance of electrical equipment, resulting in a loss of effective utilization time of the equipment or causing new faults, and there is a lack of personalized maintenance methods for equipment in different states.

Method used

Adopt an electrical equipment data monitoring and analysis system based on the Internet of Things, and select appropriate maintenance methods and cycles through real-time monitoring, historical data collection and classification processing to avoid excessive maintenance and ensure the rational use and safety of equipment.

Benefits of technology

Using big data technology to analyze the status index of electrical equipment, select the optimal classification method, plan targeted maintenance methods and cycles, effectively avoid excessive maintenance, improve the reliability and availability of equipment, and avoid new faults caused by maintenance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118734174A_ABST
    Figure CN118734174A_ABST
Patent Text Reader

Abstract

The invention discloses an electrical equipment data monitoring and analyzing system and method based on the Internet of Things, and relates to the technical field of equipment monitoring and overhauling, the electrical equipment data monitoring and analyzing system comprises an electrical equipment monitoring module, a historical operation data acquisition module, an equipment overhauling management module and an overhauling time planning module, and electrical equipment is monitored in real time through the electrical equipment monitoring module; historical operation data and fault data of the electrical equipment are acquired through a historical operation data acquisition module; performing classification processing on the electrical equipment through an equipment maintenance management module, and selecting maintenance modes for different types of processed electrical equipment; historical fault data of partial types of electrical equipment are retrieved and selectively complemented through a maintenance time planning module, the complemented data are analyzed, the equipment maintenance time is planned for the electrical equipment in the selected target maintenance mode, different maintenance modes are planned according to the equipment state, and the maintenance efficiency is improved. And the problem of excessive maintenance of the electrical equipment is effectively avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of equipment monitoring and maintenance technology, specifically to an electrical equipment data monitoring and analysis system and method based on the Internet of Things. Background Technology

[0002] To ensure safety during maintenance, electrical equipment maintenance is typically conducted with the power off. Currently, there are generally two methods for electrical equipment maintenance: one is to monitor the equipment's operating status in real time and perform targeted maintenance when abnormalities are detected; the other is a time-based preventative maintenance method, also known as planned maintenance. These two methods are suitable for electrical equipment in different states. Using inappropriate maintenance methods can easily lead to over- or under-maintenance. For equipment in good operating condition, planned maintenance is unnecessary. Using planned maintenance on such equipment, to some extent, hinders the effective utilization of the equipment. The loss of time can even lead to new faults in equipment that is not inherently faulty due to maintenance work. For example, the invention patent CN117635103A discloses "A Smart Substation Equipment Condition Maintenance Method Based on SNN", which describes the time constraints for maintenance of electrical equipment. However, it imposes full-range maintenance time constraints on all electrical equipment without adopting different maintenance methods for equipment in different states. This may result in over-maintenance, which is not conducive to improving the reliability and availability of electrical equipment through maintenance. Secondly, for electrical equipment using planned maintenance, improper planning of planned maintenance time can also easily lead to over-maintenance.

[0003] Therefore, there is an urgent need for an IoT-based electrical equipment data monitoring and analysis system and method to solve the above-mentioned technical problems. Summary of the Invention

[0004] The purpose of this invention is to provide an electrical equipment data monitoring and analysis system and method based on the Internet of Things (IoT) to solve the problems raised in the prior art.

[0005] To achieve the above objectives, the present invention provides the following technical solution: an electrical equipment data monitoring and analysis system based on the Internet of Things, comprising: an electrical equipment monitoring module, a historical operation data acquisition module, an equipment maintenance management module, and a maintenance time planning module; the electrical equipment monitoring module performs real-time monitoring of electrical equipment; the historical operation data acquisition module acquires historical operation data and fault data of electrical equipment; the equipment maintenance management module classifies electrical equipment and selects maintenance methods for different categories of electrical equipment; the maintenance time planning module retrieves and selectively completes historical fault data of some categories of electrical equipment, analyzes the completed data, and plans equipment maintenance time for electrical equipment for which target maintenance methods are selected.

[0006] Furthermore, the electrical equipment monitoring module includes an equipment operation monitoring unit and an operation fault early warning unit; the equipment operation monitoring unit monitors the operating status of the electrical equipment in real time; and the operation fault early warning unit sends an early warning signal to the monitoring terminal when an operation fault is detected in the electrical equipment.

[0007] Furthermore, the historical operation data acquisition module includes an operation time acquisition unit and a fault data acquisition unit; the operation time acquisition unit acquires the operation time data of different electrical devices, where the operation time refers to the interval between the current time and the time when the electrical device was first used; the fault data acquisition unit acquires the historical number of faults and the time data of previous faults of different electrical devices.

[0008] Furthermore, the equipment maintenance management module includes a status index analysis and comparison unit, an equipment classification and planning unit, and a maintenance method selection unit. The status index analysis and comparison unit analyzes and compares the status indices of different electrical equipment based on their operating time data and historical fault data. The equipment classification and planning unit arranges the electrical equipment in descending order of their status indices, classifies the arranged equipment into three categories, and plans the optimal classification method. The maintenance method selection unit obtains the three categories of electrical equipment classified according to the optimal classification method and selects the following maintenance methods for each category: The maintenance method selected for Class I electrical equipment is: no planned maintenance, real-time monitoring of the operating status of Class I electrical equipment, and maintenance of the corresponding faulty equipment when an operating fault occurs in Class I electrical equipment; The maintenance method selected for Class II and Class III electrical equipment is: planned maintenance + fault maintenance. For Class II electrical equipment, a maintenance cycle of H is set, and planned maintenance is carried out on Class II electrical equipment regularly according to the maintenance cycle H. For Class III electrical equipment, a maintenance cycle of L is set, where H>L, and planned maintenance is carried out on Class III electrical equipment regularly according to the maintenance cycle L. Real-time monitoring is performed on both types of equipment, and the corresponding faulty equipment is repaired when a fault is detected.

[0009] Furthermore, the maintenance time planning module includes a classified equipment data retrieval unit, an operation information analysis unit, and an optimal time planning unit. The classified equipment data retrieval unit retrieves historical fault time data for the second and third categories of electrical equipment. The operation information analysis unit analyzes the historical fault times of all electrical equipment in the second and third categories, generating a historical fault interval time dataset for all electrical equipment in the same category. The historical fault interval time refers to the time between the last fault time and the previous fault time. Each electrical equipment corresponds to one dataset. The number of items in the datasets corresponding to all electrical equipment in the same category is counted. If the number of items is different, the dataset with the most items is identified. Data completion processing is performed on the remaining datasets. After completion processing, the number of items in the datasets corresponding to all electrical equipment in the same category is equal, and the number of items is equal to the number of items in the dataset with the most items. The optimal time planning unit plans and sets the optimal maintenance cycles H and L based on the fault interval time datasets of the second and third categories of electrical equipment after data completion processing.

[0010] A method for monitoring and analyzing electrical equipment data based on the Internet of Things (IoT) includes the following steps: S1: Real-time monitoring of electrical equipment; S2: Collect historical operating data and fault data of electrical equipment; S3: Classify electrical equipment and select maintenance methods for different categories of electrical equipment after processing; S4: Retrieve and selectively complete historical fault data for certain categories of electrical equipment; S5: Analyze the data after completion to plan the equipment maintenance time for electrical equipment with the target maintenance method.

[0011] Furthermore, in S1: the operating status of electrical equipment is monitored in real time, and an early warning signal is sent to the monitoring terminal when an operating fault is detected in the electrical equipment; Furthermore, in S2: the set of operating times collected for different electrical devices is {t1, t2, ... t}. i , ...t c The set of past failures of the corresponding electrical equipment is {B1, B2, ... B}. i ...Bc}, where c represents the number of electrical devices, and data on the time of past failures of all electrical devices are collected.

[0012] Furthermore, in S3: according to formula X i =1 / [t i / ∑ c i=1 (t i )]+1 / [B i / ∑ c i=1 (B i )]Analyze the state index X of a random electrical device i The set of state indices for all electrical equipment is obtained as X = {X1, X2, ... X}. i , ...X c Let} represent the i-th electrical device. Compare the state indices of all electrical devices, arrange the state indices of all electrical devices in descending order, and randomly divide the arranged electrical devices into three categories. In the first category, the state indices of all electrical devices are greater than the state indices of every electrical device in the second category. The classification result obtained by the random classification method is: the state index sets of the three categories of electrical devices are D = {D1, D2, ... D}. e}、R={R1,R2,...R f} and F = {F1, F2, ... F g The average state index of each set is calculated to be {A1, A2, A3}, where e, f, and g represent the number of electrical devices in the first, second, and third categories respectively in the classification results obtained by a random classification method, A1 represents the average state index of electrical devices in set D, and set X contains set D, set R, and set F. Analyze the goodness-of-fact measure W of a random classification method according to the following formula: W=[(∑ 3 u=1 ((A u )-(A1+A2+A3) / 3) 2 ) / 3] 1 / 2 ; Analyze the dominance metrics of different classification methods, compare the dominance metrics, and select the classification method with the highest dominance metric as the optimal classification method. This yields three categories of electrical equipment classified according to the optimal classification method. The following maintenance methods are then selected for these three categories of electrical equipment: The maintenance method selected for Class I electrical equipment is: no planned maintenance, real-time monitoring of the operating status of Class I electrical equipment, and maintenance of the corresponding faulty equipment when an operating fault occurs in Class I electrical equipment; The maintenance method selected for Class II and Class III electrical equipment is: planned maintenance + fault maintenance. For Class II electrical equipment, a maintenance cycle of H is set, and planned maintenance is carried out on Class II electrical equipment regularly according to the maintenance cycle H. For Class III electrical equipment, a maintenance cycle of L is set, where H>L, and planned maintenance is carried out on Class III electrical equipment regularly according to the maintenance cycle L. Real-time monitoring is performed on both types of equipment, and the corresponding faulty equipment is repaired when a fault is detected. By collecting operational time data and past failure frequency data of different electrical equipment using big data technology, the longer the operational time, the more severe the aging of the electrical equipment and the more prone it is to operational failures. Combining operational time data and historical failure frequency data, the state index of the electrical equipment is analyzed. The higher the state index, the better the operating condition of the corresponding equipment. The equipment is divided into three categories according to the size of the state index. Considering that random classification may lead to indistinct classification results and fail to effectively distinguish between the three categories of electrical equipment, a goodness-of-presence metric is calculated to select the optimal classification method. The larger the metric value, the better the distinction between the state indices of the three categories of equipment. The system selects the classification method with the highest metric value as the optimal classification method, and then selects appropriate maintenance methods for the three types of equipment based on the results of the optimal classification method. This improves the purposefulness and rationality of maintenance method planning. The first type of equipment is in the best condition, so the system selects fault maintenance instead of planned maintenance. The other two types of equipment are in relatively poor condition, so the system selects a combination of planned maintenance and fault maintenance, with only the length of the set maintenance cycle being different. This allows for targeted maintenance planning for electrical equipment, effectively avoiding the problem of over-maintenance, i.e., the equipment itself is not faulty, but the planned periodic maintenance work leads to the loss of effective utilization time of the equipment or even causes new faults.

[0013] Furthermore, in S4: retrieve the past failure time data of a random type of electrical equipment from the second or third category, generate a historical failure interval time dataset for all electrical equipment in the random category, and count the number of data items for all electrical equipment in the corresponding category. If the number of items is the same, no data completion is performed; if the number of items is different: the dataset with the most items is counted to be n, and a random dataset {T1, T2, ... T} is obtained, excluding the dataset with n items. m}, m+1 represents the number of times a random electrical device in a random class has previously failed, T m Let T represent the time interval between the (m+1)th failure and the mth failure of a random electrical device, where n = m + 2. According to the formula T... m+1 =δ*T m +(1-δ)*Z m Predict the time interval T between the (m+2)th failure and the (m+1)th failure of a random electrical device. m+1 In the prediction of Tm+1 Then, according to formula T m+2 =δ*T m+1 +(1-δ)*Z m+1 Predict the time interval T between the (m+3)th failure and the (m+2)th failure of a random electrical device. m+2 Z m Let Z represent the exponentially smoothed time interval between the (m+1)th failure and the mth failure of a random electrical device. Z1 is calculated using Z1=δ*T1+(1-δ)*[(T1+T2+T3) / 3], Z2 is calculated using Z2=δ*T1+(1-δ)*Z1, Z3 is calculated using Z3=δ*T2+(1-δ)*Z2, and so on. m and Z m+1 0 < δ < 1, where δ represents the smoothing coefficient, and T m+1 and T m+2 Fill in the set {T1, T2, ... T} m In the dataset, the completed dataset is {T1, T2, ..., T}. m T m+1 T m+2 The same completion process is applied to all datasets except the dataset with n items.

[0014] Furthermore, in S5: After data completion, a dataset of past fault intervals for all electrical equipment in either the second or third category is obtained. The time interval with the highest frequency in the statistical dataset is analyzed. If only one time interval appears most frequently in the dataset, that time interval is taken as the optimal maintenance cycle for the corresponding category of electrical equipment. If more than one time interval appears with the same frequency and the frequency is the maximum value, the set of time intervals with the same frequency and the maximum value is selected from the dataset as {U1, U2, ... U...}. r}, then (∑ r j=1 (U j )) / r is the optimal maintenance cycle for the corresponding category of electrical equipment; For the remaining two categories of equipment using a combined planned maintenance and fault-based maintenance approach, regarding planned maintenance, the maintenance cycle is planned based on the historical failure times of each piece of equipment. The more frequently the same failure interval occurs, the more frequently the corresponding category of equipment is expected to fail after that interval. The failure interval with the highest frequency within the same category is selected as the optimal maintenance cycle. Considering that different equipment within the same category may have different past failure frequencies when counting the frequency of the interval item, leading to differences in the number of data items in the equipment's failure interval data, for equipment with significantly different numbers of data items, the historical failure times of these devices are statistically analyzed to determine the optimal maintenance cycle. The reference value of the previous period is not great. Therefore, by analyzing the variation pattern of the historical failure interval time of equipment with missing data items, the time when the corresponding equipment will fail in the future is predicted. The predicted data is then added to the data set of the corresponding equipment to ensure that the number of failure interval time data items of all equipment in the same type is the same. Then, the number of occurrences of statistical data items is used to set the maintenance cycle. This improves the reference value of using the historical failure data of all equipment as a reference to set the optimal maintenance cycle. It further improves the adaptability of the maintenance cycle setting to the condition of the electrical equipment itself and solves the problem that random planning of maintenance time can easily lead to over-maintenance. For example, if the maintenance interval time is too short, it can easily lead to over-maintenance.

[0015] Compared with the prior art, the beneficial effects of the present invention are: By collecting data on the operating time and the number of past failures of different electrical equipment using big data technology, and combining the operating time data and historical failure data, the state index of the electrical equipment is analyzed. The equipment is divided into three categories according to the size of the state index. Considering that random classification may lead to indistinct classification results and fail to distinguish the three categories of electrical equipment to the greatest extent, the optimal classification method is selected by calculating the goodness metric. The classification method with the highest metric value is selected as the optimal classification method. Based on the results of the optimal classification method, appropriate maintenance methods are selected for the three categories of equipment. This improves the purposefulness and rationality of maintenance method planning, and allows for targeted maintenance planning for electrical equipment. It effectively avoids the problem of over-maintenance, that is, the problem of equipment without faults losing effective utilization time or even causing new faults due to planned regular maintenance work. For the remaining two types of equipment using a planned maintenance + fault-based maintenance approach, regarding planned maintenance, maintenance cycles are planned based on the historical fault times of each piece of equipment. By analyzing the changing patterns of historical fault interval times for equipment with missing data items, the timing of subsequent faults for the corresponding equipment is predicted. The predicted data is then added to the corresponding equipment's dataset to ensure that the number of fault interval time data items is the same for all equipment in the same category. Furthermore, the frequency of occurrence of statistical data items is used to set the maintenance cycle. This improves the reference value of using historical fault data of all equipment as a reference to set the optimal maintenance cycle, further enhances the adaptability of maintenance cycle settings to the condition of the electrical equipment itself, and solves the problem of over-maintenance that can easily result from random planning of maintenance time. Attached Figure Description

[0016] Figure 1 This is a schematic diagram of the structure of an electrical equipment data monitoring and analysis system based on the Internet of Things according to the present invention; Figure 2 This is a flowchart illustrating an Internet of Things-based method for monitoring and analyzing electrical equipment data according to the present invention. Detailed Implementation

[0017] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0018] like Figures 1-2 As shown, the present invention provides the following technical solution: an electrical equipment data monitoring and analysis system based on the Internet of Things, comprising: an electrical equipment monitoring module, a historical operation data acquisition module, an equipment maintenance management module, and a maintenance time planning module; The output terminals of the electrical equipment monitoring module and the historical operation data acquisition module are connected to the input terminal of the equipment maintenance management module, and the output terminal of the equipment maintenance management module is connected to the input terminal of the maintenance time planning module. The electrical equipment is monitored in real time through the electrical equipment monitoring module; Historical operating data and fault data of electrical equipment are collected through the historical operating data acquisition module; The equipment maintenance management module categorizes electrical equipment and selects maintenance methods for different categories of electrical equipment after processing. The maintenance time planning module retrieves and selectively completes historical fault data for certain categories of electrical equipment. The completed data is then analyzed to plan maintenance times for electrical equipment with the target maintenance method.

[0019] The electrical equipment monitoring module includes an equipment operation monitoring unit and an operation fault early warning unit; The output of the equipment operation monitoring unit is connected to the input of the operation fault early warning unit; The operating status of electrical equipment is monitored in real time through the equipment operation monitoring unit; When an electrical equipment malfunction is detected by the fault early warning unit, an early warning signal is sent to the monitoring terminal.

[0020] The historical operation data acquisition module includes an operation time acquisition unit and a fault data acquisition unit; The running time data of different electrical equipment is collected by the running time acquisition unit. The running time refers to the time interval between the current time and the time when the electrical equipment was first turned on. The fault data acquisition unit collects historical fault counts and past fault times for different electrical equipment.

[0021] The equipment maintenance management module includes a status index analysis and comparison unit, an equipment classification and planning unit, and a maintenance method selection unit; The input of the status index analysis and comparison unit is connected to the output of the running time acquisition unit and the fault data acquisition unit. The output of the status index analysis and comparison unit is connected to the input of the equipment classification and planning unit. The output of the equipment classification and planning unit and the operation fault early warning unit are connected to the input of the maintenance mode selection unit. The condition index analysis and comparison unit analyzes and compares the condition indices of different electrical equipment based on the operating time data and historical fault data of the electrical equipment. The electrical equipment is arranged in descending order of state index using the equipment classification planning unit. The arranged electrical equipment is divided into three categories, and the optimal classification method is planned. The maintenance method selection unit yields three categories of electrical equipment classified according to the optimal classification method. The following maintenance methods are selected for these three categories of electrical equipment: The maintenance method selected for Class I electrical equipment is: no planned maintenance, real-time monitoring of the operating status of Class I electrical equipment, and maintenance of the corresponding faulty equipment when an operating fault occurs in Class I electrical equipment; The maintenance method selected for Class II and Class III electrical equipment is: planned maintenance + fault maintenance. For Class II electrical equipment, a maintenance cycle of H is set, and planned maintenance is carried out on Class II electrical equipment regularly according to the maintenance cycle H. For Class III electrical equipment, a maintenance cycle of L is set, where H>L, and planned maintenance is carried out on Class III electrical equipment regularly according to the maintenance cycle L. Real-time monitoring is performed on both types of equipment, and the corresponding faulty equipment is repaired when a fault is detected.

[0022] The maintenance time planning module includes a classified equipment data retrieval unit, an operation information analysis unit, and an optimal time planning unit; The input end of the classification equipment data retrieval unit is connected to the output end of the maintenance mode selection unit, the output end of the classification equipment data retrieval unit is connected to the input end of the operation information analysis unit, and the output end of the operation information analysis unit is connected to the input end of the optimal time planning unit. Historical fault time data of Class II and Class III electrical equipment are retrieved through the classified equipment data retrieval unit; By running the information analysis unit, the historical failure times of all electrical equipment in the second and third categories are analyzed respectively, and a historical failure interval time dataset of all electrical equipment in the same category is generated. The historical failure interval time refers to the time interval between the last failure time and the previous failure time. One electrical equipment corresponds to one dataset. The number of items in the datasets corresponding to all electrical equipment in the same category is counted. If the number of items is different, the number of items in the dataset with the most items is determined. Data completion processing is performed on the remaining datasets. After the completion processing, the number of items in the datasets corresponding to all electrical equipment in the same category is equal, and the number of items is equal to the number of items in the dataset with the most items. The optimal time planning unit plans and sets the optimal maintenance cycles H and L based on the fault interval time dataset of Class II and Class III electrical equipment after data completion processing.

[0023] A method for monitoring and analyzing electrical equipment data based on the Internet of Things (IoT) includes the following steps: S1: Real-time monitoring of electrical equipment: Real-time monitoring of the operating status of electrical equipment, and sending an early warning signal to the monitoring terminal when an operating fault is detected in the electrical equipment; S2: Collect historical operating data and fault data of electrical equipment: Collect the set of operating times of different electrical equipment as {t1, t2, ... t} i , ...t c The set of past failures of the corresponding electrical equipment is {B1, B2, ... B}. i ...B c}, where c represents the number of electrical devices, and data on the time of past failures of all electrical devices are collected; S3: Classify electrical equipment and select maintenance methods for different categories of equipment: based on formula X. i =1 / [t i / ∑ c i=1 (t i )]+1 / [B i / ∑ c i=1 (B i )]Analyze the state index X of a random electrical devicei The set of state indices for all electrical equipment is obtained as X = {X1, X2, ... X}. i , ...X c Let} represent the i-th electrical device. Compare the state indices of all electrical devices, arrange the state indices of all electrical devices in descending order, and randomly divide the arranged electrical devices into three categories. In the first category, the state indices of all electrical devices are greater than the state indices of every electrical device in the second category. The classification result obtained by the random classification method is: the state index sets of the three categories of electrical devices are D = {D1, D2, ... D}. e}、R={R1,R2,...R f} and F = {F1, F2, ... F g The average state index of each set is calculated to be {A1, A2, A3}, where e, f, and g represent the number of electrical devices in the first, second, and third categories respectively in the classification results obtained by a random classification method, A1 represents the average state index of electrical devices in set D, and set X contains set D, set R, and set F. Analyze the goodness-of-fact measure W of a random classification method according to the following formula: W=[(∑ 3 u=1 ((A u )-(A1+A2+A3) / 3) 2 ) / 3] 1 / 2 ; Analyze the dominance metrics of different classification methods, compare the dominance metrics, and select the classification method with the highest dominance metric as the optimal classification method. This yields three categories of electrical equipment classified according to the optimal classification method. The following maintenance methods are then selected for these three categories of electrical equipment: The maintenance method selected for Class I electrical equipment is: no planned maintenance, real-time monitoring of the operating status of Class I electrical equipment, and maintenance of the corresponding faulty equipment when an operating fault occurs in Class I electrical equipment; The maintenance method selected for Class II and Class III electrical equipment is: planned maintenance + fault maintenance. For Class II electrical equipment, a maintenance cycle of H is set, and planned maintenance is carried out on Class II electrical equipment regularly according to the maintenance cycle H. For Class III electrical equipment, a maintenance cycle of L is set, where H>L, and planned maintenance is carried out on Class III electrical equipment regularly according to the maintenance cycle L. Real-time monitoring is performed on both types of equipment, and the corresponding faulty equipment is repaired when a fault is detected. S4: Retrieve and selectively complete historical fault data for certain categories of electrical equipment: Retrieve the past fault time data of a random category of electrical equipment from the second or third category, generate a historical fault interval time dataset for all electrical equipment in the random category, and count the number of data items for all electrical equipment in the corresponding category. If the number of items is the same, no data completion is performed; if the number of items is different: the dataset with the most items is counted to be n, and a random dataset is obtained other than the dataset with n items, which is {T1, T2, ... T}. m}, m+1 represents the number of times a random electrical device in a random class has previously failed, T m Let T represent the time interval between the (m+1)th failure and the mth failure of a random electrical device, where n = m + 2. According to the formula T... m+1 =δ*T m +(1-δ)*Z m Predict the time interval T between the (m+2)th failure and the (m+1)th failure of a random electrical device. m+1 In the prediction of T m+1 Then, according to formula T m+2 =δ*T m+1 +(1-δ)*Z m+1 Predict the time interval T between the (m+3)th failure and the (m+2)th failure of a random electrical device. m+2 Z m Let Z represent the exponentially smoothed time interval between the (m+1)th failure and the mth failure of a random electrical device. Z1 is calculated using Z1=δ*T1+(1-δ)*[(T1+T2+T3) / 3], Z2 is calculated using Z2=δ*T1+(1-δ)*Z1, Z3 is calculated using Z3=δ*T2+(1-δ)*Z2, and so on. m and Z m+1 0 < δ < 1, where δ represents the smoothing coefficient, and T m+1 and T m+2 Fill in the set {T1, T2, ... T} m In the dataset, the completed dataset is {T1, T2, ..., T}. m T m+1 T m+2 The same completion process is applied to all datasets except those with n items. S5: Analyze the completed data to plan equipment maintenance time for electrical equipment with the target maintenance method: Obtain the dataset of past fault intervals for all electrical equipment in either the second or third category after data completion. Analyze the time intervals that appear most frequently in the dataset: If only one time interval appears most frequently in the dataset, then that time interval is taken as the optimal maintenance cycle for the corresponding category of electrical equipment; if more than one time interval appears with the same frequency and the frequency is the maximum value, then select the set of time intervals with the same frequency and the maximum value from the dataset as {U1, U2, ... U...}. r}, then (∑ r j=1 (U j )) / r is the optimal maintenance cycle for the corresponding category of electrical equipment, U j Represents the set {U1, U2, ... U} r If the j-th time interval in the equation corresponds to Class II electrical equipment, then this time interval is taken as the optimal maintenance cycle H for Class II electrical equipment; if the corresponding electrical equipment corresponds to Class III electrical equipment, then this time interval is taken as the optimal maintenance cycle L for Class III electrical equipment.

[0024] Example: The set of state indices for all electrical devices is obtained as X = {X1, X2, X3, X4, X5, X6, X7, X8, X9, X...} 10The values ​​} = {8.95, 6.63, 59.80, 89.50, 79.60, 38.00, 33.20, 17.90, 22.99, 22.76} are arranged in descending order of state index, resulting in {89.50, 79.60, 69.80, 38.00, 33.20, 22.99, 22.76, 17.90, 8.95, 6.63}. The classification results obtained by randomly selecting a classification method are as follows: the state index sets for the three categories of electrical equipment are D={89.50, 79.60}, R={69.80, 38.00, 33.20}, and F={22.99, 22.76, 17.90, 8.95, 6.63}, respectively. The average state index in each set is calculated to be {A1, A2, A3}={84.55, 47, 15.85}. The goodness-of-presence metric for the corresponding classification method is calculated to be 28.09. The goodness-of-presence metrics of different classification methods are analyzed and compared. The classification method with the highest goodness metric value is selected as the optimal classification method. The state index sets of the three categories of electrical equipment after classification according to the optimal classification method are {89.50, 79.60, 69.80}, {38.00, 33.20}, and {22.99, 22.76, 17.90, 8.95, 6.63}, respectively. The maintenance method selected for the first category of electrical equipment is: no planned maintenance, but fault maintenance. The maintenance method selected for the second and third categories of electrical equipment is: planned maintenance + fault maintenance, with different maintenance cycles set.

[0025] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the invention can be implemented in other specific forms without departing from its spirit or essential characteristics. Therefore, the embodiments should be considered in all respects as exemplary and non-limiting, and the scope of the invention is defined by the appended claims rather than the foregoing description. Thus, all variations falling within the meaning and scope of equivalents of the claims are intended to be included within the present invention. No reference numerals in the claims should be construed as limiting the scope of the claims.

Claims

1. An electrical equipment data monitoring and analysis system based on the Internet of Things, characterized in that: include: Electrical equipment monitoring module, historical operation data collection module, equipment maintenance management module and maintenance time planning module; Performing real-time monitoring of electrical equipment through the electrical equipment monitoring module; Collecting historical operation data and fault data of electrical equipment through the historical operation data collection module; Classify the electrical equipment through the equipment maintenance management module, and select maintenance methods for the processed electrical equipment of different categories; The maintenance time planning module retrieves and selectively completes historical fault data of some categories of electrical equipment, analyzes the completed data, and plans equipment maintenance time for electrical equipment that selects a target maintenance method.

2. The electrical equipment data monitoring and analysis system based on the Internet of Things according to claim 1 is characterized in that: The electrical equipment monitoring module includes an equipment operation monitoring unit and an operation fault early warning unit; The operation status of the electrical equipment is monitored in real time by the equipment operation monitoring unit; When an operation failure of the electrical equipment is detected, the operation failure warning unit sends a warning signal to the monitoring terminal.

3. The electrical equipment data monitoring and analysis system based on the Internet of Things according to claim 2 is characterized in that: The historical operation data collection module includes an operation time collection unit and a fault data collection unit; Collecting the running time data of different electrical equipment by the running time collection unit; The fault data collection unit collects the historical fault times of different electrical equipment and the time data of previous fault occurrences.

4. The electrical equipment data monitoring and analysis system based on the Internet of Things according to claim 3 is characterized in that: The equipment maintenance management module includes a status index analysis and comparison unit, an equipment classification planning unit and a maintenance mode selection unit; The state index analysis and comparison unit analyzes and compares the state indexes of different electrical devices based on the running time data of the electrical devices and the historical fault data; Arrange the electrical equipment in descending order of state index through the equipment classification planning unit, classify the arranged electrical equipment into three categories, and plan the optimal classification method; The maintenance mode selection unit obtains three types of electrical equipment classified according to the optimal classification mode, and selects the following maintenance modes for the three types of electrical equipment: The maintenance method selected for the first category of electrical equipment is: no planned maintenance, real-time monitoring of the operating status of the first category of electrical equipment, and maintenance of the corresponding faulty equipment when the first category of electrical equipment has an operating failure; The maintenance method selected for the second and third category electrical equipment is: planned maintenance + fault maintenance method: set the maintenance cycle to H for the second category electrical equipment, and perform planned maintenance on the second category electrical equipment regularly according to the maintenance cycle H; set the maintenance cycle to L for the third category electrical equipment, H>L, and perform planned maintenance on the third category electrical equipment regularly according to the maintenance cycle L, and monitor the two types of equipment in real time, and repair the corresponding faulty equipment when equipment failure is detected.

5. The electrical equipment data monitoring and analysis system based on the Internet of Things according to claim 4 is characterized in that: The maintenance time planning module includes a classification equipment data retrieval unit, an operation information analysis unit and an optimal time planning unit; Retrieving historical failure time data of the second and third category electrical equipment through the classification equipment data retrieving unit; The operation information analysis unit analyzes the historical fault times of all electrical equipment in the second category and the third category respectively, generates a historical fault interval time data set of all electrical equipment in the same category, counts the number of data set items corresponding to all electrical equipment in the same category, and if the number of items is different, confirms the number of items in the data set with the largest number of items, performs data completion processing on the remaining data sets, and after the completion processing, the number of items in the data sets corresponding to all electrical equipment in the same category is equal, and the number of items is equal to the number of items in the data set with the largest number of items; The optimal time planning unit plans and sets the optimal maintenance cycles H and L according to the fault interval time data set of the second and third category electrical equipment after data completion processing.

6. A method for monitoring and analyzing electrical equipment data based on the Internet of Things, characterized in that: The following steps are involved: S1: Real-time monitoring of electrical equipment; S2: Collect historical operation data and fault data of electrical equipment; S3: Classify the electrical equipment and select maintenance methods for the processed electrical equipment of different categories; S4: retrieve and selectively complete the historical fault data of some types of electrical equipment; S5: Analyze the completed data and plan equipment maintenance time for the electrical equipment with the target maintenance method selected.

7. The method for monitoring and analyzing electrical equipment data based on the Internet of Things according to claim 6 is characterized in that: In S1: real-time monitoring of the operating status of the electrical equipment, and sending an early warning signal to the monitoring terminal when an operating failure of the electrical equipment is detected; In S2: the running time set of different electrical equipment is collected as {t1, t2, ...t i ,...t c }, the corresponding number of electrical equipment failures in the past is {B1, B2, ...B i , ... B c }, c represents the number of electrical equipment, and the time data of previous failures of all electrical equipment are collected.

8. The method for monitoring and analyzing electrical equipment data based on the Internet of Things according to claim 7, characterized in that: In S3: According to formula X i =1 / [t i / ∑ c i=1 (t i )]+1 / [B i / ∑ c i=1 (B i )] Analyze the status index X of a random electrical device i , the state index set of all electrical equipment is obtained as X={X1, X2, ...X i , ...X c }, i represents the i-th electrical equipment, compare the state indexes of all electrical equipment, arrange the state indexes of all electrical equipment in order from large to small, and randomly divide the arranged electrical equipment into three categories. The classification result obtained by a random classification method is: the state index sets of the three types of electrical equipment are D={D1, D2, ...D e }, R = {R1, R2, ... R f } and F = {F1, F2, ... F g }, the average value of the state index in each set is calculated to be {A1, A2, A3}, e, f, g respectively represent the number of electrical equipment of the first, second and third categories in the classification results obtained by a random classification method, A1 represents the average value of the state index of electrical equipment in set D, and the goodness metric value W of a random classification method is analyzed according to the following formula: <h2 style=";text-align:left;direction:ltr">W=[(∑<h2 style=";text-align:left;direction:ltr"> 3 <h2 style=";text-align:left;direction:ltr"> u=1 <h2 style=";text-align:left;direction:ltr"> ((A<h2 style=";text-align:left;direction:ltr"> u <h2 style=";text-align:left;direction:ltr"> )-(A1+A2+A3) / 3)<h2 style=";text-align:left;direction:ltr"> 2 <h2 style=";text-align:left;direction:ltr"> ) / 3]<h2 style=";text-align:left;direction:ltr"> 1 / 2 <h2 style=";text-align:left;direction:ltr"> ; Analyze the goodness metrics of different classification methods, compare the goodness metrics, select the classification method with the highest goodness metric value as the optimal classification method, obtain three types of electrical equipment classified according to the optimal classification method, and select the following maintenance methods for the three types of electrical equipment: The maintenance method selected for the first category of electrical equipment is: no planned maintenance, real-time monitoring of the operating status of the first category of electrical equipment, and maintenance of the corresponding faulty equipment when the first category of electrical equipment has an operating failure; The maintenance method selected for the second and third category electrical equipment is: planned maintenance + fault maintenance method: set the maintenance cycle to H for the second category electrical equipment, and perform planned maintenance on the second category electrical equipment regularly according to the maintenance cycle H; set the maintenance cycle to L for the third category electrical equipment, H>L, and perform planned maintenance on the third category electrical equipment regularly according to the maintenance cycle L, and monitor the two types of equipment in real time, and repair the corresponding faulty equipment when equipment failure is detected.

9. The method for monitoring and analyzing electrical equipment data based on the Internet of Things according to claim 8, characterized in that: In S4: retrieve the time data of past failures of a random type of electrical equipment in the second or third category, generate a historical failure interval time data set of all electrical equipment in the random category, count the number of data set items corresponding to all electrical equipment in the corresponding category, if the number of items is different: the number of items of the data set with the largest number of items is n, and the remaining random data set {T1, T2, ...T m }, m+1 represents the number of failures of a random electrical device in a random class in the past, T m It represents the time interval between the m+1th fault of a random electrical equipment and the mth fault, n=m+2. According to the formula T m+1 =δ*T m +(1-δ)*Z m Predict the time interval T between the m+2th failure of a random electrical device and the m+1th failure m+1 , in the prediction of T m+1 Then, according to the formula T m+2 =δ*T m+1 +(1-δ)*Z m+1 Predict the time interval T between the m+3th failure of a random electrical device and the m+2th failure m+2 , Z m It represents the exponential smoothing value of the time interval between the m+1th failure of a random electrical device and the mth failure. According to Z1=δ*T1+(1-δ)*[(T1+T2+T3) / 3], the exponential smoothing value Z1 of the time interval between the second failure of a random electrical device and the first failure is calculated. According to Z2=δ*T1+(1-δ)*Z1, the exponential smoothing value Z2 of the time interval between the third failure of a random electrical device and the second failure is calculated. According to Z3=δ*T2+(1-δ)*Z2, the exponential smoothing value Z3 of the time interval between the fourth failure of a random electrical device and the third failure is calculated. And so on to get Z m and Z m+1 , 0<δ<1, δ represents the smoothing coefficient, T m+1 and T m+2 Add the set {T1, T2, ...T m }, the completed data set is {T1, T2, ...T m , T m+1 , T m+2 }, and complete all remaining data sets except the data set with n items in the same way.

10. The method for monitoring and analyzing electrical equipment data based on the Internet of Things according to claim 9, characterized in that: In S5: a data set of intervals of all electrical equipment in the second or third category that have previously experienced failures after data completion is obtained, and the time interval with the largest number of occurrences in the data set is counted: if only one time interval in the data set has the largest number of occurrences, then the time interval is used as the optimal maintenance cycle for the corresponding category of electrical equipment; if more than one time interval in the data set has an equal number of occurrences and the number of occurrences is the maximum, a set of time intervals with an equal number of occurrences and the number of occurrences being the maximum is selected from the data set as {U1, U2, ...U r }, then (∑ r j=1 (U j )) / r is the optimal maintenance cycle for electrical equipment of the corresponding category.

Citation Information

Patent Citations

  • Hydroelectric equipment monitoring and fault diagnosis system based on big data technology

    CN104281130A

  • Industrial system process monitoring and adjusting system based on Internet of Things

    CN112162531A

  • Power distribution network monitoring method based on Internet of Things technology

    CN115224794A

  • Freight transport safety monitoring system and method based on big data

    CN116433136A

  • Repair task scheduling method based on predictive maintenance

    CN116644898A

Cited By

  • Building energy consumption monitoring management system and method

    CN119295257A

  • Electrical equipment data monitoring and analyzing method based on Internet of Things

    CN120705782A

  • Electrical equipment data monitoring and analysis system based on Internet of Things and use method

    CN122796617A