Drilling and blasting method tunnel whole-process blasting fine construction method
Through technical means such as geological sketching software and laser projectors, we have solved the problems of untargeted design and difficult quality assurance in the existing drill-and-blast tunnel blasting construction, achieved refined control of drill-and-blast tunnel construction, and improved the efficiency of blasting construction. Quality and efficiency, reduced costs.
Patent Information
- Application Number
- CN202410877069.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-02
- Publication Date
- 2024-10-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing drill-and-blast tunnel blasting construction lacks targeted design, resulting in poor blasting effects, lack of effective means to ensure construction quality, low blasting optimization efficiency, and few evaluation index parameters, which cannot truly assist on-site construction.
Geological sketching software is used to perform image recognition and processing on photos of the tunnel face, and the blasting design parameters and blast hole layout are generated based on the on-site conditions. The laser projector and total station are used to achieve accurate stakeout and positioning of the blast holes, and drilling, charging and detonation are carried out. , and use three-dimensional laser scanning and digital image recognition technology to conduct post-explosion quality evaluation and optimize blasting design parameters.
It has achieved refined control of drill-and-blast tunnel construction, standardized on-site construction, improved blasting construction quality and efficiency, reduced costs, and optimized the next blasting construction process.
Smart Images

Figure CN118734404A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel construction, and in particular to a whole-process blasting refined construction method for a tunnel using a drill and blast method. Background Art
[0002] At present, most of the drilling and blasting tunnel blasting construction is carried out according to the process of blasting design, blasting construction and blasting evaluation.
[0003] The blasting design was designed according to parameters such as the surrounding rock grade, and was not designed specifically according to the integrity and strength of the actual surrounding rock on site, resulting in poor post-blasting quality. During the blasting construction process, the blasthole layout was performed by the total station to lay out a few points and then determine the points based on experience or directly manually positioning them at will, resulting in a large gap between the actual blasthole spacing and the parameters of the blasthole layout diagram, and the blasting effect was difficult to meet the requirements; during the drilling and charging process, there was also a lack of effective means to ensure the quality of workers' construction. After the tunnel blasting, the post-blasting quality evaluation was carried out based on the on-site over-excavation and under-excavation values and half-hole rate. There were few evaluation index parameters, and the evaluation effect could not really assist on-site construction. It was also difficult to optimize the next blasting design based on only a few index parameters, and the inherent correlation between the index parameters was not considered, resulting in low blasting optimization efficiency and poor results. Summary of the invention
[0004] The purpose of the present invention is to solve the shortcomings of the above-mentioned background technology and provide a drilling and blasting tunnel whole-process blasting refined construction method which can effectively standardize on-site operations, improve blasting construction quality, improve blasting efficiency and reduce blasting costs.
[0005] To achieve this purpose, the present invention provides a refined construction method for whole-process blasting of a tunnel using the drilling and blasting method, which includes taking photos of the tunnel face, importing the photos into geological sketch software, obtaining a geological sketch report of the tunnel face, inputting the geological sketch report into a tunnel blasting design system in combination with on-site tunnel construction conditions, obtaining blasting design parameters and a blasthole layout diagram, drilling, charging and detonating according to the blasting design parameters and the blasthole layout diagram, conducting a post-blasting quality evaluation according to the blasting conditions, inputting the post-blasting quality parameters into a tunnel blasting dynamic auxiliary design system, and optimizing the blasting design parameters.
[0006] Furthermore, the geological sketching software performs image recognition processing on the photograph of the tunnel face, and the unclear positions in the image recognition are manually outlined.
[0007] Furthermore, the on-site tunnel construction conditions include tunnel surrounding rock parameters, excavation section parameters and cycle footage parameters.
[0008] Furthermore, the method of drilling, charging and detonating according to blasting design parameters and blasthole layout diagram includes: importing the blasthole layout diagram into a laser projector, and using a total station to complete one-time precise layout and positioning of all blastholes on the face.
[0009] Furthermore, the method of drilling, charging and detonating according to the blasting design parameters and the blasthole arrangement diagram includes: inspecting the blasthole depth, blasthole spacing and blasthole angle of the drilled blastholes, and re-drilling unqualified blastholes.
[0010] Furthermore, the error requirement of the blasthole depth is ±5 cm, the error requirement of the blasthole spacing is ±0.5°, and the error requirement of the blasthole angle is ±3 cm.
[0011] Furthermore, the method of drilling, charging and detonating according to the blasting design parameters and the blasthole arrangement diagram includes: charging the blastholes located at the periphery of the tunnel face at intervals and charging the other blastholes on the tunnel face continuously.
[0012] Furthermore, the post-blasting quality evaluation indicators include over-excavation and under-excavation values, half-porosity, cycle footage parameters and blasting fragmentation.
[0013] Furthermore, the over-break and under-break values are measured by a three-dimensional laser scanner, the semi-porosity and blasting block size are quickly acquired by digital image recognition technology, and the cycle footage parameters are measured by a total station.
[0014] Furthermore, the method for evaluating the post-blasting quality according to the blasting situation includes: assigning indicator weight values to the over-excavation and under-excavation values, half-hole rate, cycle footage and blasting block size, and comprehensively evaluating the blasting effect according to the scores of each indicator.
[0015] The beneficial effects of the present invention are as follows: the present invention adopts digitalization, intelligence and other means by combining construction software to design a standardized construction process. It can be applied to the construction of urban subway tunnels, mountain tunnels and other tunnels excavated by drilling and blasting. Compared with conventional blasting construction, the present invention effectively standardizes the on-site construction standards and improves the quality of blasting construction on the one hand, and improves the blasting efficiency and reduces the blasting cost on the other hand. While realizing the refined control process of blasting quickly and conveniently and ensuring the blasting effect, it also optimizes the next blasting construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a flow chart of the whole process blasting refined construction method of the drilling and blasting tunnel in the present invention;
[0017] Figure 2 It is the geological sketch route map in the present invention;
[0018] Figure 3This is a schematic diagram of the blasthole laser projection in the present invention;
[0019] Among them, 1 is laser projector, 2 is laser point, 3 is laser line, 4 is palm face, and 5 is tripod. DETAILED DESCRIPTION
[0020] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.
[0021] like Figure 1 The figure shows the refined construction method for the whole process blasting of a tunnel by the drilling and blasting method designed by the present invention, comprising: taking a photo of the tunnel face 4, importing the photo into a geological sketch software, obtaining a geological sketch report of the tunnel face, inputting the geological sketch report into a tunnel blasting design system in combination with the on-site tunnel construction situation, obtaining blasting design parameters and a blasthole arrangement diagram, drilling, charging and detonating according to the blasting design parameters and the blasthole arrangement diagram, conducting a post-blasting quality evaluation according to the blasting situation, inputting the post-blasting quality parameters into a tunnel blasting dynamic auxiliary design system, and optimizing the blasting design parameters.
[0022] like Figure 2 As shown, the geological sketching software performs image recognition processing on the photo of the tunnel face 4, and the unclear positions in the image recognition are manually outlined to form a sketch of the tunnel face of the rock structure trace. At the same time, the geological sketching software performs three-dimensional point cloud and texture grid processing on the photo of the tunnel face 4, and forms a rock structure occurrence and structural surface model based on automatic recognition of the three-dimensional model and manual identification of the three-dimensional model. The rock structure occurrence and structural surface model and the sketch of the tunnel face of the rock structure trace constitute the three-dimensional and two-dimensional cataloging data of the tunnel face.
[0023] In the present invention, the on-site tunnel construction conditions include tunnel surrounding rock parameters, excavation section parameters, cycle footage parameters, and the like.
[0024] The methods of drilling, charging and detonating according to the blasting design parameters and the blasthole layout include: Figure 3 As shown, the blasthole arrangement diagram is imported into the laser projector 1, and combined with the total station, all blastholes on the face are precisely laid out and positioned at one time.
[0025] The method of drilling, charging and detonating according to the blasting design parameters and the blasthole layout diagram includes: inspecting the blasthole depth, blasthole spacing and blasthole angle of the blasthole after drilling, and re-drilling the unqualified blastholes. The error requirement for the blasthole depth is ±5cm, the error requirement for the blasthole spacing is ±0.5°, and the error requirement for the blasthole angle is ±3cm.
[0026] The method of drilling, charging and detonating according to the blasting design parameters and the blasthole arrangement diagram includes: performing interval charging on the blastholes located around the tunnel face 4 and performing continuous charging on other blastholes on the tunnel face 4 .
[0027] The indicators for post-blasting quality evaluation include over-excavation and under-excavation values, half-hole ratio, cycle footage parameters, blasting block size, explosive consumption per unit and blasthole utilization rate. The over-excavation and under-excavation values are measured by a 3D laser scanner, the half-hole ratio and blasting block size are quickly acquired through digital image recognition technology, and the cycle footage parameters are measured by a total station.
[0028] The method of evaluating the post-blasting quality according to the blasting situation includes: assigning index weight values to the over-excavation and under-excavation values, half-hole rate, cycle footage and blasting block size, and comprehensively evaluating the blasting effect according to the scores of each index.
[0029] Based on the above-mentioned drilling and blasting tunnel whole process blasting refined construction method, the specific steps are as follows:
[0030] Step 1: Take a photo of the tunnel face 4, import the high-definition photo or picture of the tunnel face 4 into the geological sketch software, and output a geological sketch report based on image recognition processing and online sketching by geological engineers;
[0031] Step 2: Based on the geological sketch report and on-site construction conditions, the blasting design system performs tunnel blasting design according to tunnel surrounding rock parameters, excavation section parameters and footage requirements, outputs blasting design drawings and blasting parameter tables, and forms a blasting design plan;
[0032] Step 3: Import the designed blasthole layout into the laser projector 1, and complete the precise positioning of all blastholes on the face in one layout by combining with the total station;
[0033] Step 4: The drilling is carried out by workers determining the holes and responsibilities. After the drilling is completed, the drilling quality is checked and re-drilled if it is unqualified;
[0034] Step 5: During the charging process, the charging operators are fixed according to the area and process. The amount of charge in the peripheral holes is small. In order to ensure uniform charging, interval charging is adopted. The remaining holes are charged continuously. After the charging is completed, industrial digital electronic detonators are used for detonation (the drilling and charging processes are based on the principle of fixed positions, fixed personnel, and fixed areas, and after the corresponding process is completed, inspections are carried out and records are kept);
[0035] Step 6: After the blasting is completed, the blasting effect is evaluated based on the over-break and under-break data, blast mark residual rate, cycle footage, blasting block size and other parameters collected on site (the weight value of each indicator is assigned differently according to the on-site blasting requirements. The over-break and under-break value is mainly related to the amount of concrete backfill, the semi-pore rate is mainly related to the excavation flatness, the cycle footage is mainly related to the excavation efficiency, and the blasting block size is mainly related to the slag discharge efficiency);
[0036] Step 7: Re-enter the parameters collected on-site after the blasting into the blasting dynamic optimization design system to optimize the parameters before the blasting.
[0037] In the above steps, the geological sketching software is a developed software, which analyzes the surrounding rock of the tunnel face through on-site photography, online sketching by geological engineers and image recognition to form a geological sketch report; the blasting design system is a developed software, which converts the calculation process of blasting design into computer language, inputs the geological information provided by the geological sketch report and the on-site tunnel engineering conditions into the blasting design system, and realizes efficient and automatic output of blasting design.
[0038] The method for fine blasting construction of the whole process of drilling and blasting tunnels described in the present invention can realize fine and standardized control of the whole process of drilling and blasting tunnel construction, reduce the influence of human subjective factors, greatly improve the on-site blasting effect, and have obvious advantages in on-site construction cost and progress control. The present invention uses digitalization, intelligence and other means in combination with construction software to design a standardized construction process. It can be applied to the construction of tunnels excavated by drilling and blasting, such as urban subway tunnels and mountain tunnels. Compared with conventional blasting construction, the present invention effectively standardizes on-site construction standards and improves the quality of blasting construction on the one hand, and improves blasting efficiency and reduces blasting costs on the other hand. While conveniently and quickly realizing the fine control process of blasting and ensuring the blasting effect, it also optimizes the next blasting construction process.
[0039] It should be noted that the description of the above technical solutions is exemplary, and this specification can be embodied in different forms and should not be interpreted as being limited to the technical solutions set forth herein. On the contrary, providing these descriptions will make the disclosure of the present invention thorough and complete, and will fully convey the scope disclosed in this specification to those skilled in the art. In addition, the technical solution of the present invention is limited only by the scope of the claims. In the case of using "including", "having" and "comprising" described in this specification, there may also be another part or other parts, and the terms used may generally be singular but may also represent plural forms. It should be noted that the above embodiments are only more representative examples of the present invention. Obviously, the present invention is not limited to the above embodiments, and there may be many variations. Any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention shall be deemed to belong to the protection scope of the present invention.
Claims
1. A drilling and blasting tunnel whole process blasting refined construction method, characterized by: The method comprises taking a photo of the tunnel face (4), importing the photo into a geological sketch software, obtaining a geological sketch report of the tunnel face, inputting the geological sketch report into a tunnel blasting design system in combination with the on-site tunnel construction situation, obtaining blasting design parameters and a blasthole arrangement diagram, drilling, charging and detonating according to the blasting design parameters and the blasthole arrangement diagram, conducting a post-blasting quality evaluation according to the blasting situation, inputting the post-blasting quality parameters into a tunnel blasting dynamic auxiliary design system, and optimizing the blasting design parameters.
2. The method for fine blasting of the whole process of tunneling by drilling and blasting method as claimed in claim 1, characterized in that: The geological sketching software performs image recognition processing on the photo of the tunnel face (4), and manually outlines the unclear positions in the image recognition.
3. The method for fine blasting of the whole process of tunnel construction by drilling and blasting method as claimed in claim 1, characterized in that: The on-site tunnel construction conditions include tunnel surrounding rock parameters, excavation section parameters and cycle footage parameters.
4. The method for fine blasting of the whole process of tunnel construction by drilling and blasting method according to claim 1, characterized in that: The method for drilling, charging and detonating according to blasting design parameters and a blasthole layout diagram comprises: importing the blasthole layout diagram into a laser projector (1), and combining with a total station to complete one-time accurate layout and positioning of all blastholes on the face.
5. The method for fine blasting of the whole process of tunnel construction by drilling and blasting method as claimed in claim 4, characterized in that: The method of drilling, charging and detonating according to blasting design parameters and blasthole arrangement diagram comprises: inspecting the blasthole depth, blasthole spacing and blasthole angle of the drilled blastholes, and re-drilling unqualified blastholes.
6. The method for fine blasting of the whole process of tunnel construction by drilling and blasting method as claimed in claim 5, characterized in that: The error requirement for the blasthole depth is ±5 cm, the error requirement for the blasthole spacing is ±0.5°, and the error requirement for the blasthole angle is ±3 cm.
7. The method for fine blasting of the whole process of tunnel construction by drilling and blasting method as claimed in claim 6, characterized in that: The method of drilling, charging and detonating according to blasting design parameters and a blasthole arrangement diagram comprises: charging blastholes located around a tunnel face (4) at intervals and charging other blastholes on the tunnel face (4) continuously.
8. The method for fine blasting of the whole process of tunnel construction by drilling and blasting method according to claim 1, characterized in that: The indicators for post-blasting quality evaluation include over-excavation and under-excavation values, half-porosity, cycle footage parameters and blasting block size.
9. The method for fine blasting of the whole process of tunnel construction by drilling and blasting method as claimed in claim 8, characterized in that: The over-break and under-break values are measured by a three-dimensional laser scanner, the semi-porosity and blasting block size are quickly acquired by digital image recognition technology, and the cycle footage parameters are measured by a total station.
10. The method for fine blasting of the whole process of tunnel construction by drilling and blasting method according to claim 8 or 9, characterized in that: The method for evaluating the post-blasting quality according to the blasting situation comprises: assigning index weight values to the over-excavation and under-excavation values, half-hole ratio, cycle footage and blasting block size, and comprehensively evaluating the blasting effect according to the scores of each index.
Citation Information
Patent Citations
Tunnel blast hole lofting positioning method
CN112576257A
Tunnel smooth blasting comprehensive quality evaluation method
CN115660487A
Tunnel dynamic blasting equipment, system and method based on geologic body intelligent perception
CN116123955A
Dynamic control method and system for blasting section in drilling and blasting method tunnel excavation
CN117216842A
Tunnel intelligent blasting design system based on multi-element geological information
CN117610315A
Cited By
Tunnel intelligent blasting design method based on geological sketch
CN120012546A
Multi-element blasting effect evaluation method and system based on point cloud data
CN120088249A