Tunnel water burst risk assessment method and system based on big data and transient electromagnetic method

Through the combination of big data and transient electromagnetic method, the tunnel water inrush risk assessment method solves the problem of low efficiency of tunnel water inrush risk assessment, achieves high-precision water inrush volume assessment and risk level classification, and improves the prediction and prevention of tunnel water inrush risk. Effect.

CN118734529AActive Publication Date: 2024-10-01中国建设基础设施有限公司 +2

Patent Information

Application Number
CN202410626108.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-05-20
Publication Date
2024-10-01
Estimated Expiration
2044-05-20

AI Technical Summary

Technical Problem

During tunnel construction and operation, the existing technology has low water inrush risk assessment efficiency, detection and forecasting results are out of touch with engineering geological sections, insufficient front-end coverage, insufficient mid-end coverage, and insufficient back-end extension coverage, resulting in low efficiency in tunnel water inrush detection, forecasting, and risk assessment. .

Method used

Using the tunnel water inrush risk assessment method based on big data and transient electromagnetic method, by constructing a digital base map of the engineering geological section in the direction of the tunnel axis, combined with the resistivity, permeability characteristics and core hardness of different strata, the water-bearing structure of the tunnel is divided, and the calculation The amount of water inflow per unit time is divided into water inrush risk levels to form a physical property database. Based on database learning, regional experience values ​​are continuously accumulated to achieve efficient assessment and prevention and control.

Benefits of technology

It improves the detection accuracy of transient electromagnetic detection equipment and the efficiency of tunnel water inrush assessment, improves the effect of water inrush risk assessment, and ensures the accuracy and efficiency of water inrush risk assessment for tunnels under construction and operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118734529A_ABST
    Figure CN118734529A_ABST
Patent Text Reader

Abstract

The invention discloses a tunnel water burst risk assessment method and system based on big data and a transient electromagnetic method. The method comprises the steps that a tunnel water-containing structure is determined in a digital base map according to different stratum permeability characteristic grades and resistivity space distribution in front of a tunnel; dividing the water-containing structure of the tunnel into a saturated region and an unsaturated region according to the saturation interpretation threshold values of the resistivity of the rock cores of the different stratums; calculating the water inflow of the tunnel in unit time; dividing tunnel water gushing risk grades according to the tunnel water gushing amount in unit time and the hardness degrees of different stratum rock cores, and outputting countermeasures corresponding to the risk grades according to the tunnel water gushing risk grades; constructing a database comprising the interpretation threshold, the permeability coefficient, the hardness of different stratum rock cores, tunnel water-containing structure saturation partition, tunnel unit time water inflow calculation and tunnel water inflow risk grade division, and continuously accumulating to form regional empirical values based on database learning. And realizing efficient evaluation and prevention and control of the tunnel water burst risk according to the regional empirical value.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of tunnel water inrush prevention and control, and more specifically, relates to a tunnel water inrush risk assessment method and system based on big data and transient electromagnetic method. Background Art

[0002] Tunnels are typical underground projects with complex underground environments. They face safety threats caused by water during construction. As the burial depth and length increase, the safety risks and operation risks of tunnel construction caused by groundwater increase. The safety threats to tunnel projects caused by tunnel water gushing are severe, the consequences of the disaster are serious, and the project losses caused are huge.

[0003] The existing technology generally conducts hydrogeological special projects during the survey and design stage of the tunnel, evaluates the potential water inflow of the tunnel, estimates the safety risk of water inflow in the tunnel, designs certain pressure relief measures and engineering reinforcement measures, and prevents and controls the safety threat of water inflow in the tunnel; there are also advanced geological forecasts that combine long-distance and short-distance during the tunnel construction period, combined with advanced drilling and construction records, to evaluate the safety risk of water inflow caused by water-bearing structures to tunnel construction, and take certain drainage and engineering blocking measures to prevent and control the safety threat of water inflow in the tunnel. However, the geophysical methods used in these methods are not closely combined with the physical properties of the rock and soil itself, and the qualitative method is greater than the quantitative method. The front end is separated from the corresponding characteristics and physical properties of the rock and soil impedance, resulting in insufficient research on the mechanism of the influence of water on the resistance characteristics of the rock and soil; the detection and prediction results of the mid-term transient electromagnetic method are disconnected from the engineering geological section, making the detection results too rough and not specific; the back-end transient electromagnetic method tunnel water-bearing structure detection and prediction are disconnected from the tunnel water inflow assessment and water inflow risk assessment. In other words, the front-end coverage is insufficient, the middle-end coverage is not comprehensive enough, and the back-end extension coverage is insufficient, resulting in low efficiency in tunnel water inrush detection and prediction, and risk assessment.

[0004] Therefore, there is an urgent need for a tunnel water inrush risk assessment method based on high-precision detection of tunnel water-containing structures, high efficiency of tunnel water inrush risk assessment and good effect of tunnel water inrush risk assessment, and a coordinated and unified method of tunnel water inrush risk assessment based on transient electromagnetic method. Summary of the invention

[0005] In view of the above defects or improvement needs of the prior art, the present invention provides a tunnel water inrush risk assessment method and system based on big data and transient electromagnetic method, which utilizes the digitized base map of engineering geological profile in the direction of tunnel axis, core resistivity test data of different strata, permeability test data of different strata, spatial coupling law data of different strata and tunnel water-bearing structure, refined zoning data of water-bearing structure, spatial relationship data of tunnel and saturated zoning, tunnel water inrush quantitative valuation data, and water inrush risk classification data to form a physical property database, and combines the physical property database with transient electromagnetic method tunnel water inrush risk assessment, and continuously accumulates and forms regional experience values ​​based on database learning, and realizes efficient assessment and prevention of tunnel water inrush risk according to the regional experience values; the detection accuracy of transient electromagnetic method detection equipment is gradually improved, the efficiency of tunnel water inrush assessment is improved, and the effect of tunnel water inrush risk assessment is improved; and methods and technical support can be provided for water inrush risk assessment of tunnels under construction and in operation.

[0006] In order to achieve the above object, one aspect of the present invention provides a tunnel water inrush risk assessment method based on big data and transient electromagnetic method, comprising the following steps:

[0007] S1: constructing a digital base map of the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software, obtaining the saturation interpretation threshold of the resistivity of the core rocks of different strata in the digital base map, measuring the saturated permeability coefficients of different strata in the digital base map, and determining the softness and hardness of the core rocks of different strata;

[0008] S2: Use transient electromagnetic method to detect and obtain the spatial distribution of resistivity in front of the tunnel, and determine the water-bearing structure of the tunnel in the digital base map according to the classification of permeability characteristics of different formations and the spatial distribution of resistivity in front of the tunnel;

[0009] S3: dividing the tunnel water-bearing structure into saturated and unsaturated areas in the digital base map according to the saturation interpretation threshold of the core resistivity of the different formations;

[0010] S4: Calculate the tunnel water inflow per unit time according to the contact area between the tunnel and the saturated zone of each water-bearing structure and the saturated permeability coefficient of the different strata; divide the tunnel water inflow risk level according to the tunnel water inflow per unit time and the hardness of the core of different strata, and output the corresponding countermeasures for each risk level according to the tunnel water inflow risk level;

[0011] S5: Construct a database in the transient electromagnetic detection software that includes the saturation interpretation threshold of different stratum core resistivity, the saturated permeability coefficient of different strata, the hardness of different stratum cores, the saturation zoning of tunnel water-bearing structures, the calculation of tunnel water inflow per unit time, and the classification of tunnel water inflow risk levels. Based on database learning, regional experience values ​​are continuously accumulated, and step S4 is repeated according to the regional experience values ​​to achieve efficient assessment and prevention of tunnel water inflow risks.

[0012] Furthermore, the step S1 of obtaining the saturation interpretation threshold of the core resistivity of different formations in the digital base map comprises the following steps:

[0013] S11: obtaining rock cores of different strata in the digital base map of the engineering geological profile in the direction of the tunnel axis through tunnel exploration holes, face tracking sampling or advance drilling, and conducting indoor tests to determine the resistivity evolution curves of the rock cores of different strata at different water contents;

[0014] S12: The linear intersection point of the two ends of one of the curves is taken as the inflection point; the resistivity value corresponding to the inflection point is the upper limit value R of the resistivity of the corresponding formation core s1 The resistivity value corresponding to the end point of the curve is the lower limit of the resistivity of the corresponding formation core R s2 ; The resistivity value R corresponding to the inflection point s1 The range of resistivity values ​​corresponding to the end points of the curve is R s2 ~R s1 As the saturation interpretation threshold of the corresponding formation core resistivity;

[0015] S13: Repeat step S12 to obtain the saturation interpretation threshold of core resistivity of different formations.

[0016] Furthermore, the step S2 uses the transient electromagnetic method to detect and obtain the resistivity spatial distribution in front of the tunnel, and determines the water-bearing structure of the tunnel in the digital base map according to the permeability characteristics of different formations and the resistivity spatial distribution in front of the tunnel; including:

[0017] S21: Use transient electromagnetic method to detect the spatial distribution law of resistivity in a certain range in front of the tunnel, and obtain the suspected area of ​​the tunnel water-bearing structure determined based on the traditional electromagnetic signal characteristics of transient electromagnetic method; that is, use the difference in resistivity change and the difference in change amount to circle the suspected water-bearing structure represented by low resistance;

[0018] S22: Match the suspected water-bearing structure areas of the tunnel determined in different batches with the stake numbers of the tunnel face on the base map of the digital engineering geological section of the tunnel axis strata, and overlay and display them on the digital engineering geological section to form the coupling law between the resistivity of the suspected water-bearing structure areas of the tunnel and the stratum space;

[0019] S23: Based on the classification of permeability characteristics of each stratum and the resistivity of suspected areas of water-bearing structures in the tunnel and the spatial coupling law of the strata, a comprehensive judgment is made and the water-bearing structures in the tunnel are delineated.

[0020] Furthermore, in step S23, a comprehensive judgment is made based on the permeability characteristics classification of each stratum and the resistivity of the suspected area of ​​the tunnel water-bearing structure and the spatial coupling law of the stratum, and the tunnel water-bearing structure is circled, including:

[0021] The permeability of the suspected water-bearing structure is k<6×10 -6 m / min, it is determined to be a non-water-containing structure;

[0022] The permeability of the formation in the suspected water-bearing structure is k≥6×10 -6 m / min, it is determined to be a water-containing structure.

[0023] Furthermore, in step S3, the resistivity of the tunnel water-bearing structure is divided into a saturated zone within the saturation interpretation threshold range of the core resistivity of the different formations, otherwise it is divided into an unsaturated zone, so as to achieve refined zoning of each tunnel water-bearing structure.

[0024] Furthermore, the tunnel water inflow in step S4 is calculated by formula (1):

[0025]

[0026] In the formula, Q is the water inflow per unit time, t is the unit time (usually per minute), n is the number of strata crossed by the saturated zone, S is i is the contact area of ​​the ith formation, k i is the saturated permeability coefficient of the ith formation.

[0027] Furthermore, in step S4, the risk level of water inrush in the tunnel is determined according to the water inrush per unit time of the tunnel and the hardness of the core of different strata, including:

[0028] Regardless of the hardness of the rock core in different strata, the water inflow per unit time of the tunnel Q≤1m 3 / min, the risk of water inrush in the tunnel is judged to be low;

[0029] The uniaxial compressive strength of the core of different strata is greater than 20MPa, and the water inflow per unit time of the tunnel is greater than 1m 3 / min, the tunnel water inrush risk is judged to be medium risk;

[0030] The uniaxial compressive strength of the core of different strata is ≤20MPa, and the water inflow per unit time of the tunnel is Q>1m 3 / min, the risk of water inrush in the tunnel is judged to be high.

[0031] Furthermore, the step S1 of obtaining a digital base map of the engineering geological profile in the tunnel axis direction includes compiling the engineering geological profile in the tunnel axis direction through advanced horizontal drilling holes, core sampling and borehole photography to form a digital base map of the engineering geological profile in the tunnel axis direction.

[0032] Further, the measuring of the saturated permeability coefficients of different strata in the digital base map in step S1 includes: measuring the saturated permeability coefficients of different strata in the digital base map by performing water injection or pumping tests on tunnel exploration holes, or performing indoor permeability tests on cores obtained from the tunnel face or advance drilling to determine the saturated permeability coefficients of different strata; in the absence of the above conditions, the saturated permeability coefficients of different strata can also be determined by engineering analogy;

[0033] Determining the hardness of rock cores in different strata in step S1 includes performing indoor uniaxial compressive strength tests or on-site rebound tests on rock cores obtained from tunnel exploration holes, face sampling or advance drilling to comprehensively determine the hardness of rock cores in different strata.

[0034] The second aspect of the present invention provides a tunnel water inrush risk assessment system based on big data and transient electromagnetic method, which is used to implement the tunnel water inrush risk assessment method based on big data and transient electromagnetic method, comprising a first main module, a second main module, a third main module, a fourth main module and a fifth main module; wherein,

[0035] The first main module is used to construct a digital base map of the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software, obtain the saturation interpretation threshold of the resistivity of the core of different strata in the digital base map, measure the saturated permeability coefficient of different strata in the digital base map, and determine the softness and hardness of the core of different strata;

[0036] The second main module is used to detect and obtain the resistivity spatial distribution in front of the tunnel using the transient electromagnetic method, and determine the water-bearing structure of the tunnel in the digital base map according to the classification of permeability characteristics of different formations and the resistivity spatial distribution in front of the tunnel;

[0037] The third main module is used to divide the tunnel water-bearing structure into saturated and unsaturated areas in the digital base map according to the saturation interpretation threshold of the core resistivity of different formations;

[0038] The fourth main module is used to calculate the tunnel water inflow per unit time according to the contact area between the tunnel and the saturated zone of each water-bearing structure and the saturated permeability coefficient of the different strata; classify the tunnel water inflow risk level according to the tunnel water inflow per unit time and the hardness of the core of different strata, and output the corresponding countermeasures for each risk level according to the tunnel water inflow risk level;

[0039] The fifth main module is used to construct a database in the transient electromagnetic detection software that includes the saturation interpretation threshold of core resistivity of different formations, the saturated permeability coefficient of different formations, the hardness of cores of different formations, the saturation zoning of tunnel water-bearing structures, the calculation of tunnel water inflow per unit time, and the classification of tunnel water inflow risk levels. Based on database learning, regional experience values ​​are continuously accumulated to achieve efficient assessment of tunnel water inflow risk based on the regional experience values.

[0040] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art:

[0041] (1) A method and system for assessing the risk of water inrush in a tunnel based on big data and transient electromagnetic method is disclosed. The method comprises the following steps: by drilling horizontal holes ahead of the tunnel, taking core samples and photographing boreholes, the engineering geological profile in the direction of the tunnel axis is recorded in the transient electromagnetic method detection software to form a digital base map of the engineering geological profile in the direction of the tunnel axis; indoor tests are conducted on the cores of different strata in the digital base map of the engineering geological profile in the direction of the tunnel axis to obtain the saturation interpretation thresholds of the resistivity of the cores of different strata, measure the saturated permeability coefficients of different strata in the digital base map, and determine the hardness of the cores of different strata; the water-bearing structure of the tunnel is determined in the digital base map according to the classification of the permeability characteristics of different strata and the spatial distribution of the resistivity in front of the tunnel; the digital engineering geological profile is combined with the detection of water-bearing structure by transient electromagnetic method to realize the combination of the corresponding characteristics of the impedance of the rock and soil body and the physical properties; the water-bearing structure of the tunnel is saturated according to the saturation interpretation thresholds of the cores of different strata, the connectivity of the saturated areas of the water-bearing structures of each tunnel is evaluated, and the saturation of the tunnel and the water-bearing structure of each tunnel is judged. The spatial relationship between the tunnel and the saturated zone makes the detection and prediction results of the transient electromagnetic method closely linked with the engineering geological section; the tunnel water inflow per unit time is calculated according to the contact area between the tunnel and each saturated zone of the water-bearing structure and the saturated permeability coefficient of the different strata; the tunnel water inflow risk level is divided according to the tunnel water inflow per unit time and the softness and hardness of the core of different strata, and the corresponding countermeasures for each risk level are output according to the tunnel water inflow risk level. The detection and prediction of the tunnel water-bearing structure using the transient electromagnetic method is combined with the tunnel water inflow assessment and the water inflow risk assessment, so as to realize the efficient prediction of the tunnel water inflow risk assessment; the following three problems existing in the use of transient electromagnetic method detection to evaluate the potential water inflow of the tunnel and estimate the safety risk of tunnel water inflow during the construction period of the tunnel can be solved: the influence mechanism of water on the resistance characteristics of the rock and soil at the front end is insufficient, and it is separated from the corresponding characteristics and physical properties of the impedance of the rock and soil; the detection and prediction results of the transient electromagnetic method at the middle end are disconnected from the engineering geological section; the detection and prediction of the tunnel water-bearing structure using the transient electromagnetic method at the back end is disconnected from the tunnel water inflow assessment and the tunnel water inflow risk assessment.

[0042] (2) The present invention provides a method and system for assessing the risk of water inrush in a tunnel based on big data and transient electromagnetic method, which combines digital engineering geological profiles with transient electromagnetic method water-bearing structure prediction, detects and predicts water inrush risks in tunnels through more sophisticated and rich transient electromagnetic method, and couples and displays all results on a digital stratigraphic profile, making it convenient to compare and analyze with other advanced geological prediction results. Compared with the prior art, the prediction results are more intuitive and can greatly improve the efficiency and effect of comprehensive risk prediction of water inrush in tunnels.

[0043] (3) A method and system for assessing the risk of water inrush in a tunnel based on big data and transient electromagnetic method is provided in the present invention. A database is constructed in the transient electromagnetic method detection software, which includes the saturation interpretation threshold of the core resistivity of different strata, the saturated permeability coefficient of different strata, the hardness of the core of different strata, the saturation zoning of the water-bearing structure of the tunnel, the calculation of the water inrush volume per unit time of the tunnel, and the classification of the risk level of water inrush in the tunnel. The physical property database is combined with the risk assessment of water inrush in the tunnel by transient electromagnetic method. Based on database learning, regional experience values ​​are continuously accumulated to achieve efficient assessment and prevention of water inrush in the tunnel according to the regional experience values. The present invention utilizes the physical property characteristics to affect the accuracy, and vice versa, the results are used to invert the physical property characteristics. The two are fed back to form a big data system including forward data and inversion data. The model is trained by big data to improve the detection accuracy and evaluation efficiency of the model. This improves the detection accuracy of the transient electromagnetic method detection equipment, the efficiency of tunnel water inrush assessment, and the effect of tunnel water inrush risk assessment. The method and technical support can be provided for the risk assessment of water inrush in tunnels under construction and in operation. The present invention has broad application prospects and great promotion value. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] Figure 1 A schematic diagram of a process for assessing the risk of water inrush in a tunnel based on big data and transient electromagnetic method according to an embodiment of the present invention;

[0045] Figure 2 A schematic diagram of the evolution curve of core saturation and resistivity in a tunnel water inrush risk assessment method based on big data and transient electromagnetic method in an embodiment of the present invention;

[0046] Figure 3 It is a structural schematic diagram of fine zoning of tunnel water-bearing structure in a tunnel water inrush risk assessment method based on big data and transient electromagnetic method in an embodiment of the present invention;

[0047] Figure 4 A schematic diagram of a tunnel and a water-containing structure having no intersection in a tunnel water inrush risk assessment method based on big data and transient electromagnetic method according to an embodiment of the present invention;

[0048] Figure 5 A schematic diagram of the intersection of a tunnel and a water-containing structure in a tunnel water inrush risk assessment method based on big data and transient electromagnetic method according to an embodiment of the present invention;

[0049] Figure 6 A schematic diagram of a tunnel and a water-containing structure completely intersecting in a tunnel water inrush risk assessment method based on big data and transient electromagnetic method according to an embodiment of the present invention;

[0050] Figure 7 This is a schematic diagram of the structure of a tunnel water inrush risk assessment system based on big data and transient electromagnetic method according to an embodiment of the present invention;

[0051] Figure 8 The figure is a schematic diagram of the structure of an electronic device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0052] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0053] The geophysical exploration methods used in the existing technology to prevent and control the threat of tunnel water inrush are not closely integrated with the physical properties of the rock and soil itself, and the qualitative method is more important than the quantitative method. The influence mechanism of water on the resistivity of the rock and soil is insufficiently studied at the front end; the detection and prediction results of the mid-term transient electromagnetic method are disconnected from the engineering geological section; the detection and prediction of the water-bearing structure of the tunnel by the back-end transient electromagnetic method is disconnected from the assessment of the tunnel water inrush volume and the assessment of the risk of water inrush; that is, the front-end coverage is insufficient, the mid-term is not comprehensive enough, and the back-end extension coverage is insufficient, resulting in low detection and prediction efficiency. Based on the above reasons, such as Figure 1 As shown, one aspect of the present invention provides a tunnel water inrush risk assessment method based on big data and transient electromagnetic method, comprising the following steps:

[0054] S1: constructing a digital base map of the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software, obtaining the saturation interpretation threshold of the resistivity of the core rocks of different strata in the digital base map, measuring the saturated permeability coefficients of different strata in the digital base map, and determining the softness and hardness of the core rocks of different strata;

[0055] S2: Use transient electromagnetic method to detect and obtain the spatial distribution of resistivity in front of the tunnel, and determine the water-bearing structure of the tunnel in the digital base map according to the classification of permeability characteristics of different formations and the spatial distribution of resistivity in front of the tunnel;

[0056] S3: dividing the tunnel water-bearing structure into saturated and unsaturated areas in the digital base map according to the saturation interpretation threshold of the core resistivity of the different formations;

[0057] S4: Calculate the tunnel water inflow per unit time according to the contact area between the tunnel and the saturated zone of each water-bearing structure and the saturated permeability coefficient of the different strata; divide the tunnel water inflow risk level according to the tunnel water inflow per unit time and the hardness of the core of different strata, and output the corresponding countermeasures for each risk level according to the tunnel water inflow risk level;

[0058] S5: Construct a database in the transient electromagnetic detection software that includes the saturation interpretation threshold of core resistivity of different formations, the saturated permeability coefficient of different formations, the hardness of cores of different formations, the saturation zoning of tunnel water-bearing structures, the calculation of tunnel water inflow per unit time, and the classification of tunnel water inflow risk levels. Based on database learning, regional experience values ​​are continuously accumulated to achieve efficient assessment of tunnel water inflow risk based on the regional experience values.

[0059] Furthermore, the step S1 comprises obtaining a digital base map of the engineering geological profile in the direction of the tunnel axis; comprising compiling the engineering geological profile in the direction of the tunnel axis through advanced horizontal drilling holes, core sampling and borehole photography of the tunnel, forming a digital base map of the engineering geological profile in the direction of the tunnel axis; and using it as a base map for comparing subsequent transient electromagnetic detection results, which can solve the shortcomings of the prior art of separation of geophysical prospecting and engineering exploration.

[0060] Furthermore, the step S1 of obtaining the saturation interpretation threshold of the core resistivity of different formations in the digital base map comprises the following steps:

[0061] S11: Obtain rock cores of different strata in the digital base map of the engineering geological profile in the direction of the tunnel axis through tunnel exploration holes, face tracking sampling or advance drilling, and conduct indoor tests to determine the resistivity evolution curves of rock cores of different strata at different water contents (saturations), such as Figure 2 As shown;

[0062] S12: The linear intersection point of the two ends of one of the curves is taken as the inflection point; the resistivity value corresponding to the inflection point is the upper limit value R of the resistivity of the corresponding formation core s1 The resistivity value corresponding to the end point of the curve is the lower limit of the resistivity of the corresponding formation core R s2 ; The resistivity value R corresponding to the inflection point s1 The range of resistivity values ​​corresponding to the end points of the curve is R s2 ~R s1 As the saturation interpretation threshold of the corresponding formation core resistivity;

[0063] S13: Repeat step S12 to obtain the saturation interpretation threshold of the core resistivity of different formations;

[0064] The saturation interpretation thresholds of the core resistivity of different formations are used as interpretation threshold support for further refined saturation zoning based on the preliminary detection results of the tunnel water-bearing structure and formation space coupling detected by the subsequent transient electromagnetic method, and simultaneously used as a database to accumulate learning data.

[0065] Furthermore, the step S1 of measuring the saturated permeability coefficients of different strata in the digital base map includes:

[0066] The saturated permeability coefficients of different strata in the digital base map are measured by performing water injection or pumping tests on tunnel exploration holes, or by performing indoor permeability tests on cores obtained from the face or advance drilling to determine the saturated permeability coefficients of different strata. In the absence of the above conditions, the saturated permeability coefficients of different strata can also be determined by engineering analogy. The saturated permeability coefficients of different strata are used as parameter support for subsequent water inflow estimation, and are simultaneously used as a database to accumulate learning data.

[0067] Furthermore, the determination of the hardness of rock cores in different strata described in step S1 includes conducting indoor uniaxial compressive strength tests or on-site rebound tests on rock cores obtained from tunnel exploration holes, face sampling or advance drilling to comprehensively determine the hardness of rock cores in different strata, and using it as parameter support for subsequent comprehensive evaluation of water inrush risk, and simultaneously accumulating learning data as a database.

[0068] Furthermore, the step S2 uses the transient electromagnetic method to detect and obtain the resistivity spatial distribution in front of the tunnel, and determines the water-bearing structure of the tunnel in the digital base map according to the permeability characteristics of different formations and the resistivity spatial distribution in front of the tunnel; including:

[0069] S21: Use transient electromagnetic method to detect the spatial distribution law of resistivity in a certain range in front of the tunnel, and obtain the suspected area of ​​the tunnel water-bearing structure determined based on the traditional electromagnetic signal characteristics of transient electromagnetic method; that is, use the difference in resistivity change and the difference in change amount to circle the suspected water-bearing structure represented by low resistance;

[0070] S22: Match the suspected water-bearing structure areas of the tunnel determined in different batches with the stake numbers of the tunnel face on the base map of the digital engineering geological section of the tunnel axis strata, and overlay and display them on the digital engineering geological section to form the coupling law between the resistivity of the suspected water-bearing structure areas of the tunnel and the stratum space;

[0071] S23: Based on the classification of permeability characteristics of each stratum and the resistivity of suspected areas of water-bearing structures in the tunnel and the spatial coupling law of the strata, a comprehensive judgment is made and the water-bearing structures in the tunnel are delineated.

[0072] Further, as shown in Table 1, in step S23, a comprehensive judgment is made based on the permeability characteristics classification of each stratum and the resistivity of the suspected area of ​​the tunnel water-bearing structure and the spatial coupling law of the stratum, and the tunnel water-bearing structure is circled, including:

[0073] The permeability of the formation in the suspected water-bearing structure is low permeability (k<6×10 -6 m / min), it is determined to be a non-water-containing structure;

[0074] The permeability of the formation in the suspected water-bearing structure is medium or above (k ≥ 6×10 -6 m / min), it is determined to be a water-containing structure;

[0075] Table 1 Comprehensive delineation standard for the scope of water-bearing structures in tunnels

[0076]

[0077] Furthermore, in step S3, the tunnel water-bearing structure is divided into saturated zone and unsaturated zone in the digital base map according to the saturation interpretation threshold of the core resistivity of the different formations; including dividing the resistivity of the tunnel water-bearing structure within the saturation interpretation threshold of the core resistivity of the different formations into a saturated zone, otherwise into an unsaturated zone, thereby achieving refined zoning of each tunnel water-bearing structure.

[0078] Furthermore, step S3 also includes evaluating the connectivity of the saturated areas of the water-containing structures of each tunnel to determine whether the saturated areas are spatially connected; if they are connected, all the connected saturated areas are evaluated as a large area for spatial relationship with the tunnel. If they are not connected, each saturated area is evaluated as a separate area for spatial relationship with the tunnel; step S3 also includes determining the spatial relationship between the tunnel and the saturated areas of the water-containing structures of each tunnel, and the spatial relationship between the tunnel and the saturated areas of the water-containing structures includes no intersection and intersection; intersection is divided into partial intersection and complete intersection; if Figure 4-Figure 6 As shown in the figure, S is the contact area between the tunnel and the saturated zone; if the tunnel intersects with the saturated zone of each tunnel water-containing structure, the contact area between the tunnel and the saturated zone of each water-containing structure is estimated.

[0079] Furthermore, the tunnel water inflow in step S4 is calculated by formula (1):

[0080]

[0081] In the formula, Q is the water inflow per unit time, t is the unit time (usually per minute), n is the number of strata crossed by the saturated zone, S is i is the contact area of ​​the ith formation, k i is the saturated permeability coefficient of the ith formation.

[0082] Further, Table 2 is a tunnel water inrush risk determination standard; Step S4 determines the tunnel water inrush risk level according to the tunnel water inrush per unit time and the hardness of the rock core of different strata, including:

[0083] Regardless of the hardness of the rock core in different strata, the water inflow per unit time of the tunnel Q≤1m 3 / min, the risk of water inrush in the tunnel is judged to be low;

[0084] The uniaxial compressive strength of the core of different strata is greater than 20MPa, and the water inflow per unit time of the tunnel is greater than 1m 3 / min, the tunnel water inrush risk is judged to be medium risk;

[0085] The uniaxial compressive strength of the core of different strata is ≤20MPa, and the water inflow per unit time of the tunnel is Q>1m 3 / min, the tunnel water inrush risk is judged to be high risk;

[0086] Table 2 Tunnel water inrush risk assessment criteria

[0087]

[0088] Furthermore, in step S4, the countermeasures corresponding to each risk level are output according to the tunnel water inrush risk level, including:

[0089] When the risk of water inrush in the tunnel is low, no special measures are required;

[0090] When the risk of water inrush in the tunnel is medium, measures such as open drainage need to be taken to strengthen drainage and avoid the adverse effects caused by long-term immersion and softening of the construction area between the face and the secondary lining;

[0091] When the risk of tunnel water inrush is high, it is necessary to take proactive measures to strengthen protection or actively relieve pressure. Alternatively, a combination of both engineering measures can be adopted to control the safety risk of tunnel water inrush.

[0092] Furthermore, step S5 includes constructing a database in the database of the software system that includes saturation interpretation thresholds of core resistivities of different formations, saturated permeability coefficients of different formations, hardness of cores of different formations, saturated zoning of water-bearing structures in tunnels, calculation of water inflow per unit time in tunnels, and classification of water inflow risk levels in tunnels, and continuously accumulating to form regional experience values. According to the regional experience values, step S4 is repeated to achieve efficient assessment and prevention of tunnel water inflow risks. With the increase of regional experience values, the software summarizes successful and failed experiences, so that the detection accuracy of transient electromagnetic detection equipment is gradually improved, the efficiency of tunnel water inflow assessment is improved, and the effect of tunnel water inflow risk assessment is improved.

[0093] The present invention provides a tunnel water inrush risk assessment method based on big data and transient electromagnetic method. The method utilizes the digitization of engineering geological profiles in the tunnel axis direction, core resistivity and permeability test, spatial coupling law of strata and water-bearing structures, refined saturation zoning of water-bearing structures, and spatial relationship between tunnels and saturated zoning to quantify and estimate the tunnel water inrush per unit time. The tunnel water inrush risk is graded according to the tunnel water inrush per unit time and the hardness of core rocks in different strata. The physical property database is combined with the transient electromagnetic method tunnel water inrush risk assessment, which can provide method and technical support for water inrush risk assessment of tunnels under construction and in operation.

[0094] like Figure 7 As shown, the second aspect of the present invention provides a tunnel water inrush risk assessment system based on big data and transient electromagnetic method, which is used to implement the above risk assessment method, including: a first main module, a second main module, a third main module, a fourth main module and a fifth main module; wherein,

[0095] The first main module is used to construct a digital base map of the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software, obtain the saturation interpretation threshold of the resistivity of the core of different strata in the digital base map, measure the saturated permeability coefficient of different strata in the digital base map, and determine the softness and hardness of the core of different strata;

[0096] The second main module is used to detect and obtain the resistivity spatial distribution in front of the tunnel using the transient electromagnetic method, and determine the water-bearing structure of the tunnel in the digital base map according to the classification of permeability characteristics of different formations and the resistivity spatial distribution in front of the tunnel;

[0097] The third main module is used to divide the tunnel water-bearing structure into saturated and unsaturated areas in the digital base map according to the saturation interpretation threshold of the core resistivity of different formations;

[0098] The fourth main module is used to calculate the tunnel water inflow per unit time according to the contact area between the tunnel and the saturated zone of each water-bearing structure and the saturated permeability coefficient of the different strata; classify the tunnel water inflow risk level according to the tunnel water inflow per unit time and the hardness of the core of different strata, and output the corresponding countermeasures for each risk level according to the tunnel water inflow risk level;

[0099] The fifth main module is used to construct a database in the transient electromagnetic detection software that includes the saturation interpretation threshold of core resistivity of different formations, the saturated permeability coefficient of different formations, the hardness of cores of different formations, the saturation zoning of tunnel water-bearing structures, the calculation of tunnel water inflow per unit time, and the classification of tunnel water inflow risk levels. Based on database learning, regional experience values ​​are continuously accumulated to achieve efficient assessment of tunnel water inflow risk based on the regional experience values.

[0100] It should be noted that the tunnel water inrush risk assessment system based on big data and transient electromagnetic method provided in this embodiment can be a computer program (including program code) running in a computer device, for example, the tunnel water inrush risk assessment system based on big data and transient electromagnetic method is an application software; the tunnel water inrush risk assessment system based on big data and transient electromagnetic method can be used to execute the corresponding steps in the above method provided in the embodiment of the present application.

[0101] In some feasible implementations, the tunnel water inrush risk assessment system based on big data and transient electromagnetic method provided in the present embodiment can be implemented by a combination of software and hardware. As an example, the tunnel water inrush risk assessment system based on big data and transient electromagnetic method provided in the present embodiment can be a processor in the form of a hardware decoding processor, which is programmed to execute the tunnel water inrush risk assessment method based on big data and transient electromagnetic method provided in the embodiment of the present application. For example, the processor in the form of a hardware decoding processor can adopt one or more application specific integrated circuits (ASIC, Application Specific Integrated Circuit), digital signal processors (digital signal processor, DSP), programmable logic devices (PLD, Programmable Logic Device), complex programmable logic devices (CPLD, Complex Programmable Logic Device), field programmable gate arrays (FPGA, Field-Programmable Gate Array) or other electronic components.

[0102] In some feasible implementations, the tunnel water inrush risk assessment system based on big data and transient electromagnetic method provided in this embodiment can be implemented in software form, which can be software in the form of programs and plug-ins, and includes a series of modules to implement the tunnel water inrush risk assessment method based on big data and transient electromagnetic method provided in the embodiment of the present invention.

[0103] The tunnel water inrush risk assessment system based on big data and transient electromagnetic method provided in this embodiment constructs a digital base map of engineering geological profiles in the direction of the tunnel axis in the transient electromagnetic method detection software, obtains the saturation interpretation threshold of the resistivity of the core of different strata in the digital base map, measures the saturated permeability coefficient of different strata in the digital base map, and determines the softness and hardness of the core of different strata; uses transient electromagnetic method to detect and obtain the spatial distribution of resistivity in front of the tunnel, and determines the tunnel water-bearing structure in the digital base map according to the classification of permeability characteristics of different strata and the spatial distribution of resistivity in front of the tunnel; divides the tunnel water-bearing structure into saturated areas and unsaturated areas in the digital base map according to the saturation interpretation threshold of the resistivity of the core of different strata; evaluates the connectivity of the saturated areas of the water-bearing structures of each tunnel, and judges the spatial relationship between the tunnel and the saturated areas of the water-bearing structures of each tunnel. If there is an intersection, the contact area between the tunnel and the saturated areas of each water-bearing structure is estimated; and the contact area between the tunnel and the saturated areas of each water-bearing structure is estimated according to the contact area between the tunnel and the saturated areas of each water-bearing structure. The tunnel water inrush per unit time is calculated based on the saturation permeability coefficient of the different strata; the tunnel water inrush risk level is divided according to the tunnel water inrush per unit time and the hardness of the core of different strata, and the corresponding countermeasures are output according to the tunnel water inrush risk level; a database including the saturation interpretation threshold of the core resistivity of different strata, the saturated permeability coefficient of different strata, the hardness of the core of different strata, the saturation zoning of the water-bearing structure of the tunnel, the calculation of the tunnel water inrush per unit time and the classification of the tunnel water inrush risk level is constructed in the transient electromagnetic method detection software; the physical property database is combined with the transient electromagnetic method tunnel water inrush risk assessment, and based on database learning, regional experience values ​​are continuously accumulated to form, and efficient assessment and prevention of tunnel water inrush risk is achieved according to the regional experience values; the detection accuracy of the transient electromagnetic method detection equipment is gradually improved, the efficiency of tunnel water inrush assessment is improved, and the effect of tunnel water inrush risk assessment is improved; it can provide method and technical support for the water inrush risk assessment of tunnels under construction and in operation.

[0104] A third aspect of the present invention further provides an electronic device, Figure 8 Schematic diagram of the structure of the electronic device of this embodiment. Figure 8As shown, the electronic device 1000 in this embodiment may include: a processor 1001, a network interface 1004 and a memory 1005. In addition, the above-mentioned electronic device 1000 may also include: a user interface 1003, and at least one communication bus 1002. Among them, the communication bus 1002 is used to realize the connection and communication between these components. Among them, the user interface 1003 may include a display screen (Display), a keyboard (Keyboard), and the user interface 1003 may optionally include a standard wired interface and a wireless interface. The network interface 1004 may optionally include a standard wired interface and a wireless interface (such as a WI-FI interface). The memory 1004 may be a high-speed RAM memory, or it may be a non-volatile memory (non-volatile memory), such as at least one disk storage. The memory 1005 may optionally also be at least one storage device located away from the aforementioned processor 1001. As Figure 8 As shown, the memory 1005 as a computer-readable storage medium may include an operating system, a network communication module, a user interface module, and a device control application program.

[0105] like Figure 8 In the electronic device 1000 shown, the network interface 1004 can provide a network communication function; the user interface 1003 is mainly used to provide an input interface for the user; and the processor 1001 can be used to call the device control application stored in the memory 1005 to achieve:

[0106] Constructing a digital base map of the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software, obtaining the saturation interpretation threshold of the resistivity of the core rocks of different strata in the digital base map, measuring the saturated permeability coefficients of different strata in the digital base map, and determining the softness and hardness of the core rocks of different strata;

[0107] The transient electromagnetic method is used to detect and obtain the spatial distribution of resistivity in front of the tunnel, and the water-bearing structure of the tunnel is determined in the digital base map according to the classification of permeability characteristics of different strata and the spatial distribution of resistivity in front of the tunnel;

[0108] Dividing the tunnel water-bearing structure into saturated and unsaturated zones in the digital base map according to the saturation interpretation threshold of the core resistivity of the different strata;

[0109] Calculate the tunnel water inflow per unit time according to the contact area between the tunnel and the saturated zone of each water-bearing structure and the saturated permeability coefficient of the different strata; divide the tunnel water inflow risk level according to the tunnel water inflow per unit time and the hardness of the rock core of different strata, and output the corresponding countermeasures for each risk level according to the tunnel water inflow risk level;

[0110] A database is constructed in the transient electromagnetic detection software, which includes the saturation interpretation threshold of core resistivity of different formations, the saturated permeability coefficient of different formations, the hardness of cores of different formations, the saturation zoning of tunnel water-bearing structures, the calculation of tunnel water inflow per unit time, and the classification of tunnel water inflow risk levels. Based on database learning, regional experience values ​​are continuously accumulated to achieve efficient assessment and prevention of tunnel water inflow risks.

[0111] It should be understood that in some feasible implementations, the processor 1001 may be a central processing unit (CPU), or other general-purpose processors, DSPs, ASICs, FPGAs or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or the processor may be any conventional processor, etc. The memory may include a read-only memory and a random access memory, and provide instructions and data to the processor. A portion of the memory may also include a non-volatile random access memory. For example, the memory may also store information about the device type.

[0112] In a specific implementation, the electronic device 1000 can execute the above-mentioned functions through its built-in functional modules. Figure 1 For the implementation methods provided in each step, please refer to the implementation methods provided in the above steps for details, which will not be repeated here.

[0113] The electronic device provided in the present embodiment constructs a digital base map of the engineering geological profile in the direction of the tunnel axis in the transient electromagnetic detection software, obtains the saturation interpretation threshold of the resistivity of the core of different strata in the digital base map, measures the saturated permeability coefficient of different strata in the digital base map, and determines the softness and hardness of the core of different strata; uses the transient electromagnetic method to detect and obtain the spatial distribution of the resistivity in front of the tunnel, and determines the tunnel water-bearing structure in the digital base map according to the classification of the permeability characteristics of different strata and the spatial distribution of the resistivity in front of the tunnel; divides the tunnel water-bearing structure into saturated areas and unsaturated areas in the digital base map according to the saturation interpretation threshold of the resistivity of the core of different strata; evaluates the connectivity of the saturated areas of the water-bearing structures of each tunnel, and judges the spatial relationship between the tunnel and the saturated areas of the water-bearing structures of each tunnel. If there is an intersection, the contact area between the tunnel and the saturated areas of each water-bearing structure is estimated; according to the contact area between the tunnel and the saturated areas of each water-bearing structure and the spatial relationship between the saturated areas of the different strata The saturated permeability coefficient is used to calculate the tunnel water inflow per unit time; the tunnel water inflow risk level is divided according to the tunnel water inflow per unit time and the hardness of the core of different strata, and the corresponding countermeasures are output according to the tunnel water inflow risk level; a database is constructed in the transient electromagnetic detection software, which includes the saturation interpretation threshold of the core resistivity of different strata, the saturated permeability coefficient of different strata, the hardness of the core of different strata, the saturation zoning of the water-bearing structure of the tunnel, the calculation of the tunnel water inflow per unit time, and the classification of the tunnel water inflow risk level; the physical property database is combined with the transient electromagnetic tunnel water inflow risk assessment, and based on database learning, regional experience values ​​are continuously accumulated to form, and efficient assessment and prevention of tunnel water inflow risks are achieved according to the regional experience values; the detection accuracy of the transient electromagnetic detection equipment is gradually improved, the efficiency of tunnel water inflow assessment is improved, and the effect of tunnel inflow risk assessment is improved; it can provide methods and technical support for the water inflow risk assessment of tunnels under construction and in operation.

[0114] The present application also provides a computer-readable storage medium, which stores a computer program and is executed by a processor to implement Figure 1 For the methods provided in each step, please refer to the implementation methods provided in the above steps for details, which will not be repeated here.

[0115] The computer-readable storage medium provided in the embodiment constructs a digital base map of the engineering geological profile in the direction of the tunnel axis in the transient electromagnetic detection software, obtains the saturation interpretation threshold of the resistivity of the core of different strata in the digital base map, measures the saturated permeability coefficient of different strata in the digital base map, and determines the softness and hardness of the core of different strata; uses the transient electromagnetic method to detect and obtain the spatial distribution of the resistivity in front of the tunnel, and determines the tunnel water-bearing structure in the digital base map according to the classification of the permeability characteristics of different strata and the spatial distribution of the resistivity in front of the tunnel; divides the tunnel water-bearing structure into saturated areas and unsaturated areas in the digital base map according to the saturation interpretation threshold of the resistivity of the core of different strata; evaluates the connectivity of the saturated areas of the water-bearing structures of each tunnel, and judges the spatial relationship between the tunnel and the saturated areas of the water-bearing structures of each tunnel. If there is an intersection, the contact area between the tunnel and the saturated areas of each water-bearing structure is estimated; and according to the contact area between the tunnel and the saturated areas of the different strata and the spatial distribution of the resistivity in front of the tunnel, the water-bearing structure of the tunnel is determined in the digital base map. The saturated permeability coefficient of the layer is used to calculate the tunnel water inflow per unit time; the tunnel water inflow risk level is divided according to the tunnel water inflow per unit time and the hardness of the core of different strata, and the countermeasures corresponding to each risk level are output according to the tunnel water inflow risk level; a database including the saturation interpretation threshold of the core resistivity of different strata, the saturated permeability coefficient of different strata, the hardness of the core of different strata, the saturation zoning of the water-bearing structure of the tunnel, the calculation of the tunnel water inflow per unit time and the classification of the tunnel water inflow risk level is constructed in the transient electromagnetic method detection software; the physical property database is combined with the transient electromagnetic method tunnel water inflow risk assessment, and based on database learning, regional experience values ​​are continuously accumulated to form, and efficient assessment and prevention of tunnel water inflow risk are achieved according to the regional experience values; the detection accuracy of the transient electromagnetic method detection equipment is gradually improved, the efficiency of tunnel water inflow assessment is improved, and the effect of tunnel inflow risk assessment is improved; it can provide method and technical support for the water inflow risk assessment of tunnels under construction and in operation.

[0116] Any reference to memory, storage, database or other medium used in the embodiments provided in the present application may include non-volatile and / or volatile memory. Non-volatile memory may include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory may include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in various forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).

[0117] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A tunnel water inrush risk assessment method based on big data and transient electromagnetic method, characterized by: The steps include: S1: constructing a digital base map of the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software, obtaining the saturation interpretation threshold of the resistivity of the core rocks of different strata in the digital base map, measuring the saturated permeability coefficients of different strata in the digital base map, and determining the softness and hardness of the core rocks of different strata; S2: Use transient electromagnetic method to detect and obtain the spatial distribution of resistivity in front of the tunnel, and determine the water-bearing structure of the tunnel in the digital base map according to the classification of permeability characteristics of different formations and the spatial distribution of resistivity in front of the tunnel; S3: dividing the tunnel water-bearing structure into saturated and unsaturated areas in the digital base map according to the saturation interpretation threshold of the core resistivity of the different formations; S4: Calculate the tunnel water inflow per unit time according to the contact area between the tunnel and the saturated zone of each water-bearing structure and the saturated permeability coefficient of the different strata; divide the tunnel water inflow risk level according to the tunnel water inflow per unit time and the hardness of the core of different strata, and output the corresponding countermeasures for each risk level according to the tunnel water inflow risk level; S5: Construct a database in the transient electromagnetic detection software that includes the saturation interpretation threshold of core resistivity of different formations, the saturated permeability coefficient of different formations, the hardness of cores of different formations, the saturation zoning of tunnel water-bearing structures, the calculation of tunnel water inflow per unit time, and the classification of tunnel water inflow risk levels. Based on database learning, regional experience values ​​are continuously accumulated to achieve efficient assessment and prevention of tunnel water inflow risks.

2. The method for assessing tunnel water inrush risk based on big data and transient electromagnetic method according to claim 1, characterized in that: The step S1 of obtaining the saturation interpretation threshold of the core resistivity of different formations in the digital base map includes the following steps: S11: obtaining rock cores of different strata in the digital base map of the engineering geological profile in the direction of the tunnel axis through tunnel exploration holes, face tracking sampling or advance drilling, and conducting indoor tests to determine the resistivity evolution curves of the rock cores of different strata at different water contents; S12: The linear intersection point of the two ends of one of the curves is taken as the inflection point; the resistivity value corresponding to the inflection point is the upper limit value R of the resistivity of the corresponding formation core s1 The resistivity value corresponding to the end point of the curve is the lower limit of the resistivity of the corresponding formation core R s2 ; The resistivity value R corresponding to the inflection point s1 The range of resistivity values ​​corresponding to the end points of the curve is R s2 ~R s1 As the saturation interpretation threshold of the corresponding formation core resistivity; S13: Repeat step S12 to obtain the saturation interpretation threshold of core resistivity of different formations.

3. The method for assessing tunnel water inrush risk based on big data and transient electromagnetic method according to claim 1, characterized in that: The step S2 uses the transient electromagnetic method to detect and obtain the resistivity spatial distribution in front of the tunnel, and determines the water-bearing structure of the tunnel in the digital base map according to the permeability characteristics of different formations and the resistivity spatial distribution in front of the tunnel; including: S21: Use transient electromagnetic method to detect the spatial distribution law of resistivity in a certain range in front of the tunnel, and obtain the suspected area of ​​the tunnel water-bearing structure determined based on the traditional electromagnetic signal characteristics of transient electromagnetic method; that is, use the difference in resistivity change and the difference in change amount to circle the suspected water-bearing structure represented by low resistance; S22: Match the suspected water-bearing structure areas of the tunnel determined in different batches with the stake numbers of the tunnel face on the base map of the digital engineering geological section of the tunnel axis strata, and overlay and display them on the digital engineering geological section to form the coupling law between the resistivity of the suspected water-bearing structure areas of the tunnel and the stratum space; S23: Based on the classification of permeability characteristics of each stratum and the resistivity of suspected areas of water-bearing structures in the tunnel and the spatial coupling law of the strata, a comprehensive judgment is made and the water-bearing structures in the tunnel are delineated.

4. The method for assessing tunnel water inrush risk based on big data and transient electromagnetic method according to claim 3 is characterized by: In step S23, a comprehensive judgment is made based on the classification of the permeability characteristics of each stratum and the resistivity of the suspected area of ​​the tunnel water-bearing structure and the spatial coupling law of the stratum, and the tunnel water-bearing structure is circled, including: The permeability of the suspected water-bearing structure is k<6×10 -6 m / min, it is determined to be a non-water-containing structure; The permeability of the formation in the suspected water-bearing structure is k≥6×10 -6 m / min, it is determined to be a water-containing structure.

5. A tunnel water inrush risk assessment method based on big data and transient electromagnetic method according to any one of claims 1 to 4, characterized in that: In step S3, the resistivity of the tunnel water-bearing structure is divided into a saturated zone within the saturation interpretation threshold range of the core resistivity of the different formations, otherwise it is divided into an unsaturated zone, so as to realize the refined zoning of each tunnel water-bearing structure.

6. A tunnel water inrush risk assessment method based on big data and transient electromagnetic method according to any one of claims 1 to 4, characterized in that: The tunnel water inflow in step S4 is calculated by formula (1): In the formula, Q is the water inflow per unit time, t is the unit time (usually per minute), n is the number of strata crossed by the saturated zone, S is i is the contact area of ​​the ith formation, k i is the saturated permeability coefficient of the ith formation.

7. A tunnel water inrush risk assessment method based on big data and transient electromagnetic method according to any one of claims 1 to 4, characterized in that: Step S4 determines the tunnel water inrush risk level according to the tunnel water inrush per unit time and the hardness of the rock cores of different strata, including: Regardless of the hardness of the rock core in different strata, the water inflow per unit time of the tunnel Q≤1m 3 / min, the risk of water inrush in the tunnel is judged to be low; The uniaxial compressive strength of the core of different strata is greater than 20MPa, and the water inflow per unit time of the tunnel is greater than 1m 3 / min, the tunnel water inrush risk is judged to be medium risk; The uniaxial compressive strength of the core of different strata is ≤20MPa, and the water inflow per unit time of the tunnel is Q>1m 3 / min, the risk of water inrush in the tunnel is judged to be high.

8. A tunnel water inrush risk assessment method based on big data and transient electromagnetic method according to any one of claims 1 to 4, characterized in that: The step S1 described in constructing a digital base map of the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software includes compiling the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software through advanced horizontal drilling holes in the tunnel, core sampling and borehole photography to form a digital base map of the engineering geological profile in the tunnel axis direction.

9. A tunnel water inrush risk assessment method based on big data and transient electromagnetic method according to any one of claims 1 to 4, characterized in that: The step S1 measures the saturated permeability coefficients of different strata in the digital base map, including: measuring the saturated permeability coefficients of different strata in the digital base map by performing water injection or pumping tests on tunnel exploration holes, or performing indoor permeability tests on cores obtained from tunnel faces or advance drilling holes to determine the saturated permeability coefficients of different strata; in the absence of the above conditions, the saturated permeability coefficients of different strata can also be determined by engineering analogy; Determining the hardness of rock cores in different strata in step S1 includes performing indoor uniaxial compressive strength tests or on-site rebound tests on rock cores obtained from tunnel exploration holes, face sampling or advance drilling to comprehensively determine the hardness of rock cores in different strata.

10. A tunnel water inrush risk assessment system based on big data and transient electromagnetic method, characterized in that: The method for evaluating the risk of water inrush in a tunnel based on big data and transient electromagnetic method according to any one of claims 1 to 9 comprises: a first main module, a second main module, a third main module, a fourth main module and a fifth main module; wherein: The first main module is used to construct a digital base map of the engineering geological profile in the tunnel axis direction in the transient electromagnetic detection software, obtain the saturation interpretation threshold of the resistivity of the core of different strata in the digital base map, measure the saturated permeability coefficient of different strata in the digital base map, and determine the softness and hardness of the core of different strata; The second main module is used to detect and obtain the resistivity spatial distribution in front of the tunnel using the transient electromagnetic method, and determine the water-bearing structure of the tunnel in the digital base map according to the classification of permeability characteristics of different formations and the resistivity spatial distribution in front of the tunnel; The third main module is used to divide the tunnel water-bearing structure into saturated and unsaturated areas in the digital base map according to the saturation interpretation threshold of the core resistivity of different formations; The fourth main module is used to calculate the tunnel water inflow per unit time according to the contact area between the tunnel and the saturated zone of each water-bearing structure and the saturated permeability coefficient of the different strata; classify the tunnel water inflow risk level according to the tunnel water inflow per unit time and the hardness of the core of different strata, and output the corresponding countermeasures for each risk level according to the tunnel water inflow risk level; The fifth main module is used to construct a database in the transient electromagnetic detection software that includes the saturation interpretation threshold of core resistivity of different formations, the saturated permeability coefficient of different formations, the hardness of cores of different formations, the saturation zoning of tunnel water-bearing structures, the calculation of tunnel water inflow per unit time, and the classification of tunnel water inflow risk levels. Based on database learning, regional experience values ​​are continuously accumulated to achieve efficient assessment of tunnel water inflow risk based on the regional experience values.

Citation Information

Patent Citations

  • Forecasting method and system for tunnel geology

    CN103399358A

  • Tunnel counter-slope drainage design method based on water inflow estimation and dynamic monitoring

    CN104948226A

  • Life-cycle treatment method of water inrush in tunnel

    CN105041345A

  • Tunnel gushing risk grade fuzzy prediction method based on comprehensive advanced geological prediction technology

    CN110705795A

  • Tunnel inrush water disaster prediction method and device, electronic equipment and storage medium

    CN112465191A

Cited By

  • Non-coal mine intelligent inspection method and intelligent inspection unmanned vehicle

    CN118938941A

  • Multi-perception-path tunnel risk prediction method and device and computer equipment

    CN119149996A

  • A tunnel risk prediction method, device and computer equipment based on multi-sensing approach

    CN119149996B

  • Tunnel karst cave water inflow prediction analysis method and system based on geological radar

    CN121049901A

  • Tunnel cave water inflow prediction analysis method and system based on ground penetrating radar

    CN121049901B