Method and system for automatically arranging progress plan of manufacturing, transporting and erecting integrated bridge
Through the automatic orchestration algorithm based on machine learning, the problem of low efficiency in the preparation of traditional bridge construction schedules is solved, the automatic orchestration of bridge construction schedules is realized, the preparation efficiency is improved and the workload is reduced, and the on-site constraints and multi-objective optimization are satisfied. need.
Patent Information
- Application Number
- CN202410870156.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2024-10-01
AI Technical Summary
The traditional bridge construction schedule preparation efficiency is low, the workload of the compiler is heavy, and it cannot effectively consider on-site man-machine, material, law, environmental constraints and multiple optimization objectives, and lacks dynamic optimization capabilities.
Using an automatic orchestration algorithm based on machine learning, the bridge is divided into different types according to the construction process and digitally expressed to determine the construction process and specific construction activities, obtain resource allocation data, and generate a process logical relationship table, including the tight connections between construction activities. Before and after relationships, implicit logic checks and constraint models are used for automatic sorting.
It improves the arrangement efficiency of the bridge construction schedule, reduces the workload of the compiler, and realizes the automated sequencing of the logical relationships of the processes and the dynamic optimization of the schedule.
Smart Images

Figure CN118735201A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of engineering management information technology, and in particular to a method and system for automatically arranging a progress plan for a manufacturing, transporting and framing integrated bridge. Background Art
[0002] Schedule management is one of the three major goals of project management. Reasonable preparation of schedule is an important basis for achieving the cost and quality goals of engineering projects. If the construction schedule of engineering projects is not prepared reasonably, it will reduce its guiding role in the project and affect the quality of the project. Formulating a reasonable construction schedule, optimizing it in combination with the actual situation of the project and achieving the project duration goal is a common problem in the industry.
[0003] The optimal construction schedule of a bridge is an important part of construction management, and plays a key role in scheme comparison and construction period control. The premise of the construction schedule is to compile a detailed list of procedures, but the detailed list of construction procedures needs to be manually compiled. Due to the large number of procedures and long construction period, the compiler needs to arrange multiple procedures, which requires high professional ability of the compiler, and there are problems such as strong subjectivity and high error rate; it cannot consider the constraints of man, machine, material, method and environment on site, cannot consider multiple optimization goals, and has no dynamic optimization capability. In view of the problems existing in traditional design methods and known bridge systems, a more general automated design method is urgently needed to complete the automatic compilation of the schedule of the integrated bridge of manufacturing, transportation and frame. Summary of the invention
[0004] The present application provides a method and system for automatically arranging a schedule for a bridge with integrated construction, transportation and frame, so as to solve the problems in the prior art of low efficiency in arranging a schedule for bridge construction and heavy workload for the compilers.
[0005] According to the first aspect, an embodiment provides a method for automatically arranging a schedule for a bridge with an integrated structure, transport and frame, the method comprising:
[0006] Classify the transport bridges into different bridge types according to the construction process and express them digitally;
[0007] Based on the combined information of different types of bridges in the transport frame bridge, the construction process of the transport frame bridge and the specific construction activities included in each construction process are determined;
[0008] Based on the resource allocation data of the bridge construction project, the time parameters of specific construction activities are obtained;
[0009] Based on the construction activity content of the bridge manufacturing and transportation and the time parameters of the construction activities, and based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, an automatic scheduling algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, which contains the close relationship between the construction activities.
[0010] Furthermore, the transport bridges are divided into different types according to the construction process, including:
[0011] According to the bridge construction technology, the bridge types are divided into continuous beams, segmental assembled beams and simply supported beams, and digitally expressed, where C1 represents simply supported beams, B1 represents segmental assembled beams, An represents continuous beams, and n represents the number of beam spans;
[0012] According to the actual combination order of different types of bridges in the transport frame bridge, the digital component sequence of the transport frame bridge is obtained, and the digital component sequence is converted into a mathematical expression form.
[0013] Furthermore, based on the combined information of different types of bridges in the transport and trestle bridge, the construction process of the transport and trestle bridge and the specific construction activities included in each construction process are determined, including:
[0014] Determine the main activities of the bridge construction project, including pile foundation, abutment, pier and beam;
[0015] Generate a visual model based on the actual composition sequence of the transport frame bridge and number each component in sequence;
[0016] Determine the construction process of bridge manufacturing, transportation and erection, including pile foundation, abutment, pier, continuous beam, segmental assembled beam, beam manufacturing and beam erection, where beam manufacturing and beam erection are simply supported beam processes; each construction process includes construction activities corresponding to components with different numbers;
[0017] The number of construction processes meets the following requirements: the number of pile foundations = the number of abutments = the number of piers; the number of beams manufactured = the number of beams erected.
[0018] Furthermore, based on the resource allocation data of the bridge construction project, the time parameters of specific construction activities are obtained, including:
[0019] The resource allocation data includes the personnel composition of each process, process indicator system, environmental logistics constraints and shift reduction rate, and total resource constraints;
[0020] The time parameters are calculated by using the construction quota method to calculate the duration of component construction.
[0021] Furthermore, based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance, the constraints include:
[0022] Based on the relevant engineering experience, the process logic relationship is determined, and the order of bridge construction procedures is obtained as follows: pile foundation → pedestal → bridge → beam part, beam manufacturing → beam erection;
[0023] By combining the data of multiple similar bridge engineering cases, the specific organizational logical relationship between the processes is excavated. The engineering data includes site environment, engineering quantity, total investment, contract period, deployable resources, and process decomposition logical relationship information. The process decomposition logical relationship information includes process logic relationship information and organizational logic relationship information between each process.
[0024] Furthermore, based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance, the constraints include:
[0025] The specific organizational logic relationship between the processes includes: the lower part of the special structure has priority over the lower part of the ordinary structure; when comparing the pile foundation construction periods of multiple special structures, the lower part of the special structure with a long pile foundation construction period has priority; when constructing the lower part of the special structure, the middle pier has a higher priority than the side pier, and when the priorities are the same, the piers of the special structure with a long single-shift construction period will be constructed first; once the lower part of the special structure is completed, the upper part of the special structure will start construction immediately; the special structures include continuous beams and segmental assembled beams, and the ordinary structures include simply supported beams.
[0026] Furthermore, an automatic scheduling algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, including:
[0027] The ILC model and the constraint CC model are checked using implicit logic based on machine learning, and the ILC model and CC model are trained using the information from the critical path method (CPM) schedule.
[0028] Furthermore, an automatic scheduling algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, including:
[0029] The ILC model includes an activity description encoder, a WBS label encoder, and a machine learning classifier;
[0030] The activity description encoder encodes the input construction activity description;
[0031] The WBS label encoder is used to assign a predefined WBS label code to each construction activity;
[0032] During training, the output results of the activity description encoder and the WBS label encoder are used as inputs of the machine learning classifier. The trained machine learning classifier is used to predict the type and direction of the logical dependency of the relationship between the input activities.
[0033] Furthermore, the method further comprises:
[0034] Prepare a double-code network schedule based on the generated process logic relationship table, and calculate the construction period and cost according to the key lines of the double-code network diagram.
[0035] According to the second aspect, an embodiment provides a system for automatically arranging a schedule for a bridge with integrated structure, transportation and frame, the system comprising:
[0036] A digital expression module is used to classify the transport bridges into different bridge types according to the construction process and to express them digitally;
[0037] A construction process acquisition module is used to determine the construction process of the transport frame bridge and the specific construction activities included in each construction process based on the combined information of different types of bridges in the transport frame bridge;
[0038] The construction time acquisition module is used to obtain the time parameters of specific construction activities based on the resource allocation data of the bridge construction project;
[0039] The automatic scheduling module is used to automatically sort the construction activities based on the construction activity content of the manufacturing, transportation and erection bridge and the time parameters of the construction activities, and based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, using the automatic scheduling algorithm based on machine learning to generate a process logic relationship table, which contains the close relationship between the construction activities.
[0040] The present application provides a method and system for automatically arranging the progress plan of a bridge with integrated transport and scaffolding, which divides the transport and scaffolding bridge into different bridge types according to the construction process and expresses them digitally; based on the combined information of different types of bridges in the transport and scaffolding bridge, the construction process of the transport and scaffolding bridge and the specific construction activities included in each construction process are determined; based on the resource allocation data of the construction project of the transport and scaffolding bridge, the time parameters of the specific construction activities are obtained; based on the construction activity content of the transport and scaffolding bridge and the time parameters of the construction activities, and based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, the automatic arrangement algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, wherein the process logic relationship table contains the close relationship between the construction activities. The present invention realizes the automatic arrangement of the progress plan of the transport and scaffolding bridge based on the automatic arrangement algorithm, which can effectively improve the arrangement efficiency of the bridge construction progress plan and reduce the workload of the compilers. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] Figure 1 A flowchart of a method for automatically arranging a progress plan for a bridge with integrated construction, transportation and support provided by an embodiment of the present invention;
[0042] Figure 2 A model diagram of a bridge with a transport frame in a method for automatically arranging a progress plan for a bridge with a transport frame integrated structure provided by an embodiment of the present invention;
[0043] Figure 3 A schematic diagram of the logical structure of an automatic scheduling system for a bridge with integrated construction, transportation and frame is provided for one embodiment of the present invention. DETAILED DESCRIPTION
[0044] The present invention is further described in detail below by specific embodiments in conjunction with the accompanying drawings. Wherein similar elements in different embodiments adopt associated similar element numbers. In the following embodiments, many detailed descriptions are for making the present application better understood. However, those skilled in the art can easily recognize that some features can be omitted in different situations, or can be replaced by other elements, materials, methods. In some cases, some operations related to the present application are not shown or described in the specification, this is to avoid the core part of the present application being overwhelmed by too much description, and for those skilled in the art, it is not necessary to describe these related operations in detail, and they can fully understand the related operations according to the description in the specification and the general technical knowledge in the art.
[0045] In addition, the features, operations or characteristics described in the specification can be combined in any appropriate manner to form various implementations. At the same time, the steps or actions in the method description can also be interchanged or adjusted in a manner that is obvious to those skilled in the art. Therefore, the various sequences in the specification and the drawings are only for the purpose of clearly describing a certain embodiment and are not meant to be a required sequence, unless otherwise specified that a certain sequence must be followed.
[0046] The first embodiment of the present invention provides a method for automatically arranging a progress plan for a bridge with integrated construction, transportation and erection. Figure 1 Provide detailed explanation.
[0047] like Figure 1 As shown, in step S100, the transport and erection bridges are divided into different bridge types according to the construction process and digitally expressed.
[0048] The above steps specifically include: dividing the bridge types into continuous beams, segmental assembled beams and simply supported beams according to the bridge construction technology, and expressing them digitally, where C1 represents a simply supported beam, B1 represents a segmental assembled beam, An represents a continuous beam, and n represents the number of beam spans; according to the actual combination order of different types of bridges in the transport frame bridge, the digital component sequence of the transport frame bridge is obtained, and the digital component sequence is converted into a mathematical expression form.
[0049] This embodiment obtains information on different bridge construction projects based on design and construction drawings and related materials, analyzes bridge characteristics, divides bridge types into different subsets according to bridge construction techniques, and digitally expresses the combination patterns.
[0050] Specifically, according to the design and construction drawings and relevant information, bridges are divided into three subsets: continuous beams, segmental assembled beams, and simply supported beams. C1 represents simply supported beams, B1 represents segmental assembled beams, and An represents continuous beams (n represents the number of beam spans). Different subset combinations are digitally expressed, for example, a transport bridge is represented as:
[0051] C1 C1 C1A3C1 C1 C1 C1 C1 B1 C1 C1 C1 C1 C1=C1*3+A3+C1*5+B1+C1*5.
[0052] Project information includes project start time and process decomposition logical relationship information.
[0053] The process decomposition logic relationship information refers to the process logic information and organizational logic information between the processes. The process decomposition logic relationship information can ensure the consistency of the structure set division and realize the automatic association between the bridge components and the construction schedule.
[0054] The process logic relationship is a sequential relationship determined by the process or project. It exists objectively and cannot be changed at will. According to the relevant engineering experience, the process logic relationship can be determined, and the sequence of bridge construction procedures can be obtained: pile foundation → foundation → bridge → beam, beam manufacturing → beam erection.
[0055] like Figure 1 As shown, in step S200, based on the combined information of different types of bridges in the transport and erection bridge, the construction process of the transport and erection bridge and the specific construction activities included in each construction process are determined.
[0056] The above steps specifically include: determining the main activities of the bridge construction project, including pile foundations, caps, piers, and beams;
[0057] Generate a visual model based on the actual composition sequence of the transport frame bridge and number each component in sequence;
[0058] Determine the construction process of bridge manufacturing, transportation and erection, including pile foundation, abutment, pier, continuous beam, segmental assembled beam, beam manufacturing and beam erection, where beam manufacturing and beam erection are simply supported beam processes; each construction process includes construction activities corresponding to components with different numbers;
[0059] The number of construction processes meets the following requirements: the number of pile foundations = the number of abutments = the number of piers; the number of beams manufactured = the number of beams erected.
[0060] For the transport frame bridge with the above mathematical expression, a visual model of the transport frame bridge is generated as follows: Figure 2 As shown in the figure, the components are numbered according to a certain coordinate system, as follows: piles 0 to 17, caps 0 to 17, piers 0 to 17, beams 1 to 17, etc.
[0061] like Figure 1 As shown, in step S300, the time parameters of specific construction activities are obtained based on the resource configuration data of the bridge construction project.
[0062] The above steps specifically include: the resource allocation data includes the personnel composition of each process, the process indicator system, the environmental logistics constraints and the shift reduction rate, and the total resource constraints;
[0063] The time parameters are calculated by using the construction quota method to calculate the duration of component construction.
[0064] Resource allocation data mainly includes the personnel composition of each process, process indicator system, environmental logistics constraints and shift reduction rate, total resource constraints, etc. The details are as follows:
[0065] 1) Single-shift staff composition
[0066]
[0067] 2) Process indicator system
[0068] Engineering Projects Rate Unit Number of groups Project quantity per group Single shift rate Time taken by each group Cost index (yuan / day) Pile foundation m / day 18 190 10 19 9142 Platform m3 / day 18 120 20 6 3007 Bridge pier m3 / day 18 240 20 12 2778 Segmental beam Hole / day 1 1 0.05 20 6699 Continuous beam Joint / Day 1(3 holes 1 connection) 1 0.01 100 7532 Beam Making Hole / day 13 1 0.08 12.5 8004 Beam Hole / day 13 1 1 1 96330
[0069] 3) Shift-rate comparison table
[0070]
[0071]
[0072] 4) Total resource constraints
[0073]
[0074] Obtain basic construction costs and duration of construction activities based on resource allocation data.
[0075] Calculate the labor volume based on the engineering volume and labor efficiency of each activity to obtain the comprehensive working day; analyze the resources invested in each activity based on the existing resources; calculate the duration of each activity based on the labor volume and resource input; when the engineering volume of the construction activity is accurately obtained, the construction quota method is used to determine the engineering volume based on the building information model, and the quota is converted into the workload per person per working hour. The number of manpower or equipment is set and input according to the actual situation on site. The calculation formula for the duration of construction activities is as follows:
[0076] D=Q / RS
[0077] In the formula, D is the duration of work, Q is the amount of work done in the construction activity, R is the number of manpower or equipment, and S is the production quota.
[0078] like Figure 1 As shown, in step S400, based on the content of the construction activities of manufacturing, transporting and erecting the bridge and the time parameters of the construction activities, and based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, an automatic scheduling algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, which includes the close relationship between the construction activities.
[0079] The above steps specifically include: combining multiple similar case bridge engineering data to mine specific organizational logical relationships between processes, wherein the engineering data include site environment, engineering quantity, total investment, contract duration, deployable resources, and process decomposition logical relationship information, wherein the process decomposition logical relationship information includes process logical relationship information and organizational logical relationship information between each process.
[0080] Organizational logic relationship refers to the artificial arrangement of construction sequence without violating the process logic relationship.
[0081] The specific organizational logic relationships between the excavated processes include: the lower part of the special structure has priority over the lower part of the ordinary structure; when comparing the pile foundation construction periods of multiple special structures, the lower part of the special structure with a long pile foundation construction period has priority; when constructing the lower part of the special structure, the middle pier has a higher priority than the side pier, and when the priorities are the same, the piers of the special structure with a long single-shift construction period will be constructed first; once the lower part of the special structure is completed, the upper part of the special structure will start construction immediately; the special structures include continuous beams and segmental assembled beams, and the ordinary structures include simply supported beams.
[0082] The above steps specifically also include: using implicit logic based on machine learning to check the ILC model and the constraint CC model, and using information in the critical path method CPM schedule to train the ILC model and the CC model.
[0083] In this embodiment, the ILC model includes an activity description encoder, a WBS label encoder and a machine learning classifier; the activity description encoder encodes the input construction activity description; the WBS label encoder is used to assign a predefined WBS label code to each construction activity; during training, the output results of the activity description encoder and the WBS label encoder are used as inputs to the machine learning classifier, and the trained machine learning classifier is used to predict the type and direction of the logical dependency of the relationship between the input activities.
[0084] This embodiment uses an arrangement algorithm to automatically arrange the process logic relationship table according to the process logic and reasoning organization logic required by the project, which mainly includes the following contents:
[0085] S410: Analyze the nature and flexibility of the constraints on the logical relationships between activities in the schedule and the underlying rationale.
[0086] In regular CPM scheduling, the constraints that create dependencies between activities are not clearly available. Instead, these constraints exist in the mind of the planner who originally created the schedule. For example, a planner creates multiple activities to schedule the execution of a paint job. They will typically create one activity for applying the main coat and another for applying the final coat, and they will link these two activities via a FS relationship. But the reason why this relationship exists in the schedule as a FS dependency is omitted (i.e. main coat is covered by final coat).
[0087] All that is recorded in the schedule is a FS link between two activities. This becomes a problem when rescheduling is required. When an activity is expected to be delayed, its expected delay will propagate through its critical successor activities and affect their expected end dates. If the planner (whether human or AI agent) does not know the implicit cause of the logical delay that caused the successor to become critical, they will not know whether the planned activities can be reorganized to accommodate the delay. On the other hand, if the planner knows that the successor activity is critical because of a flexible constraint (such as competing resources), then it can be resolved by bringing in new staff or moving the activity.
[0088] To help planners reschedule actions to accommodate unavoidable delays. It is assumed that flexible schedule constraints can be modified while inflexible schedule constraints need to remain unchanged when rescheduling activities. Since the flexibility of logical constraints is not easily available in the input schedule, the present invention uses NLP to add a new method for construction scheduling with implicit dependency constraints. Once the schedule is enriched with implicit dependency information, the knowledge of relational flexibility is used to modify the forward plan and account for expected activity delays.
[0089] S420: Perform different sorting selections on subsequent activities in the schedule, train the reasoning rules based on the organizational logic constraint relationship, and use the reasoning organizational logic constraint rules to automatically sort new cases and verify the priority.
[0090] Based on the LC model, the implicit logic checker (ILC) model is used to predict the implicit dependency constraints of the lookahead plan; the flexibility of each relationship is identified according to its dependency constraints; and a revised lookahead plan is generated by respecting inflexible constraints and modifying flexible constraints using sequencing knowledge learned from previous construction records.
[0091] The ILC model input is a pair of predecessor and successor activity descriptions and WBS labels, transforms them using a series of decoder blocks and classification heads, and outputs one or more dependency constraints defined in the following table.
[0092]
[0093] Using the logic checker (LC) function, it maps activity pairs from A to D, representing A as the set of all possible activities and D as the set of all possible logical dependencies.
[0094] D={FS,FS f ,SF,SF f ,SS,SS f ,FF,FFf,NR}
[0095] Among them, F and S represent Finish and Start respectively (ie, FS = Finish-to-Start), NR means no relationship, and the subscript "f" represents a flip relationship.
[0096] LC:A 2 →D
[0097] Each activity in A is defined by an activity description and its associated WBS label. Both entities are text strings and consist of English words.
[0098] Define V as the vocabulary or the set of all possible words that can be used to express an activity description or a WBS label. Hence, LC can be described as a mapping function between V and D.
[0099] LC:V 4 →D
[0100] The LC function is modeled as a deep neural network. The model learns from existing scheduling data using supervised machine learning and a fully automated process, requiring no additional human annotation beyond the information explicitly available in existing project schedules. While labeled data is required for training, the training examples and labels are constructed entirely by the model using the direct relationships available in the construction schedule and formalized indirect dependency rules.
[0101] The model consists of an activity description encoder, a WBS label encoder, and a machine learning classifier. The encoder reads and encodes the information embedded in the predecessor description and the information in the successor activity description and its corresponding WBS label. The encoded inputs - the descriptors of the input activities and WBS labels - are used as inputs to the classifier. The classifier predicts the type and direction of the logical dependencies that govern the relationships between these input activities.
[0102] The CC model achieves the decoupling and weighting of different optimization constraints. It is built on the basis of the LC model. Changing the optimization criteria (such as duration, cost, work continuity, etc.) does not require retraining the LC model. The LC model is used in conjunction with the CC model to create a schedule from an unordered list of activities. The CC model uses an A-search algorithm to solve equations to optimize the consistency of the predictions made by the LC model. The reason for doing this is to correct the inaccurate predictions made by the LC model at the activity level and make all pairs of results optimal. The constraint condition (CC) model can be used to ensure that the classifier returns a structured output that obeys certain constraints. These constraints are expressed through integer linear programming (ILP) so that the optimal solution of the optimization procedure consists of the predicted outputs that the classifier assigns high scores and obeys the desired constraints.
[0103] The orchestration algorithm in this embodiment uses a natural language processing method based on deep learning to fully automatically identify the constraints of the logical dependencies that control the input construction progress without any manual input.
[0104] The natural language processing (NLP) method based on deep learning can be used to fully and automatically identify the constraints of the logical dependencies that control the input construction progress, mine the specific organizational logical relationships, and automatically arrange the sequence of construction activities for the new case to obtain a new process logic relationship table as follows.
[0105]
[0106]
[0107]
[0108] In this embodiment, the method further includes step S500, compiling a dual-code network schedule diagram based on the generated process logic relationship table, and calculating the construction period and cost according to the key paths of the dual-code network diagram.
[0109] Prepare a dual-code network diagram:
[0110] ① Process numbering: Determine the start and end nodes of the process according to the processes of the bridge project and the relationship between the processes; ② Layout: Determine the relative positions between the nodes and place them on the canvas in an appropriate manner with the processes; ③ Form a double-code network diagram.
[0111] Process numbering: Follow the drawing principle of double-code network diagram to number the processes, set the starting nodes of all processes without immediate predecessors as the initial starting nodes, and add end nodes for them, and then use breadth-first to add the numbers of the immediate successors of each process. In this process, complete the detection and processing of virtual processes. When all processes are numbered, gather the network diagram to a meeting point.
[0112] There are two main ways to arrange nodes: hierarchical and layered. Node grading means that the level of the first node is 1, and all nodes are traversed. According to relevant rules, the level of the current node in the traversal is determined; node layering means that the level of the first node is 1. On the basis of node grading, the following operations are performed on each level in turn: for the node in the current level, the level of the current node is equal to the smallest level of its predecessor node; after completing the layering of all nodes in the current level, the layering operation of the subsequent nodes of each node is completed in order from small to large according to the size of each node layer in the current level. After completing the grading and layering of nodes, the position of the node on the canvas has been determined, that is, the node arrangement work is completed.
[0113] The bridge construction design process is cumbersome, with a large amount of repetitive work and diverse logical relationships. From bottom to top, multiple points are parallel, and the component structure and construction requirements vary greatly. The method of this embodiment is proposed for the preparation of bridge progress plan, and has the following important features:
[0114] (1) The method of this embodiment organizes the construction organization design configuration resource data template, does not need to establish an efficiency index library, and the process index can be changed arbitrarily, thereby reducing the workload.
[0115] (2) The method of this embodiment adopts the logical relationship of similar engineering organization, which effectively corresponds to the complexity of bridge construction organization design. To a certain extent, it can draw on engineering cases with high similarity to provide technical support for scientific allocation of bridge construction project resources, reasonable optimization of construction period, high-quality engineering, controllable safety risks and efficient and coordinated management.
[0116] An automatic arrangement method for the progress plan of a bridge with integrated transport frame provided by an embodiment of the present invention divides the transport frame bridge into different bridge types according to the construction process and expresses them digitally; based on the combined information of different types of bridges in the transport frame bridge, the construction process of the transport frame bridge and the specific construction activities included in each construction process are determined; based on the resource configuration data of the construction project of the transport frame bridge, the time parameters of the specific construction activities are obtained; based on the construction activity content of the transport frame bridge and the time parameters of the construction activities, and based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, the automatic arrangement algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, wherein the process logic relationship table contains the close relationship between the construction activities. The present invention realizes the automatic arrangement of the progress plan of the transport frame bridge based on the automatic arrangement algorithm, which can effectively improve the arrangement efficiency of the bridge construction progress plan and reduce the workload of the compilers.
[0117] Corresponding to the above-disclosed method for automatically arranging a progress plan for a bridge with an integrated structure and transport frame, the embodiment of the present invention further discloses a system for automatically arranging a progress plan for a bridge with an integrated structure and transport frame, such as Figure 3 As shown, it specifically includes:
[0118] A digital expression module is used to classify the transport bridges into different bridge types according to the construction process and to express them digitally;
[0119] A construction process acquisition module is used to determine the construction process of the transport frame bridge and the specific construction activities included in each construction process based on the combined information of different types of bridges in the transport frame bridge;
[0120] The construction time acquisition module is used to obtain the time parameters of specific construction activities based on the resource allocation data of the bridge construction project;
[0121] The automatic scheduling module is used to automatically sort the construction activities based on the construction activity content of the manufacturing, transportation and erection bridge and the time parameters of the construction activities, and based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, using the automatic scheduling algorithm based on machine learning to generate a process logic relationship table, which contains the close relationship between the construction activities.
[0122] It should be noted that the detailed description of the automatic scheduling system for a bridge schedule with an integrated transport frame provided in an embodiment of the present invention can refer to the relevant description of the automatic scheduling method for a bridge schedule with an integrated transport frame provided in an embodiment of the present application, which will not be repeated here.
[0123] In addition, an embodiment of the present invention also provides an electronic device, which includes: a processor and a memory; the memory is used to store one or more program instructions; the processor is used to run one or more program instructions to execute the steps of a method for automatically arranging a schedule for an integrated bridge system as described in any of the above items.
[0124] It should be noted that, for the detailed description of an electronic device provided in an embodiment of the present invention, reference can be made to the relevant description of an automatic scheduling method for a bridge schedule with integrated manufacturing, transportation and racking provided in an embodiment of the present application, which will not be repeated here.
[0125] In addition, an embodiment of the present invention further provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of a method for automatically arranging a schedule for an integrated bridge system as described in any of the above items are implemented.
[0126] It should be noted that, for the detailed description of a computer-readable storage medium provided in an embodiment of the present invention, reference can be made to the relevant description of a method for automatically arranging a schedule plan for an integrated bridge system with a transport frame provided in an embodiment of the present application, which will not be repeated here.
[0127] Those skilled in the art will appreciate that all or part of the functions of the various methods in the above-mentioned embodiments can be implemented by hardware or by computer programs. When all or part of the functions in the above-mentioned embodiments are implemented by computer programs, the program can be stored in a computer-readable storage medium, and the storage medium can include: read-only memory, random access memory, disk, optical disk, hard disk, etc., and the program is executed by a computer to implement the above-mentioned functions. For example, the program is stored in the memory of the device, and when the program in the memory is executed by the processor, all or part of the above-mentioned functions can be implemented. In addition, when all or part of the functions in the above-mentioned embodiments are implemented by computer programs, the program can also be stored in a storage medium such as a server, another computer, disk, optical disk, flash disk or mobile hard disk, and can be downloaded or copied and saved in the memory of the local device, or the system of the local device is updated, and when the program in the memory is executed by the processor, all or part of the functions in the above-mentioned embodiments can be implemented.
[0128] The above specific examples are used to illustrate the present invention, which is only used to help understand the present invention and is not intended to limit the present invention. For those skilled in the art, according to the concept of the present invention, some simple deductions, modifications or substitutions can be made.
Claims
1. A method for automatically arranging a progress plan for a bridge with integrated construction, transportation and erection, characterized in that: The method comprises: Classify the transport bridges into different bridge types according to the construction process and express them digitally; Based on the combined information of different types of bridges in the transport frame bridge, the construction process of the transport frame bridge and the specific construction activities included in each construction process are determined; Based on the resource allocation data of the bridge construction project, the time parameters of specific construction activities are obtained; Based on the construction activity content of the bridge manufacturing and transportation and the time parameters of the construction activities, and based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, an automatic scheduling algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, which contains the close relationship between the construction activities.
2. The method for automatically arranging the progress plan of a bridge with integrated construction, transportation and erection as claimed in claim 1, characterized in that: The transport bridges are divided into different types according to the construction technology, including: According to the bridge construction technology, the bridge types are divided into continuous beams, segmental assembled beams and simply supported beams, and digitally expressed, where C1 represents simply supported beams, B1 represents segmental assembled beams, An represents continuous beams, and n represents the number of beam spans; According to the actual combination order of different types of bridges in the transport frame bridge, the digital component sequence of the transport frame bridge is obtained, and the digital component sequence is converted into a mathematical expression form.
3. The method for automatically arranging the progress plan of a bridge with integrated construction, transportation and erection as claimed in claim 1, characterized in that: Based on the combined information of different types of bridges in the transport frame bridge, the construction process of the transport frame bridge and the specific construction activities included in each construction process are determined, including: Determine the main activities of the bridge construction project, including pile foundation, abutment, pier and beam; Generate a visual model based on the actual composition sequence of the transport frame bridge and number each component in sequence; Determine the construction process of bridge manufacturing, transportation and erection, including pile foundation, abutment, pier, continuous beam, segmental assembled beam, beam manufacturing and beam erection, where beam manufacturing and beam erection are simply supported beam processes; each construction process includes construction activities corresponding to components with different numbers; The number of construction processes meets the following requirements: the number of pile foundations = the number of abutments = the number of piers; the number of beams manufactured = the number of beams erected.
4. The method for automatically arranging the progress plan of a bridge with integrated construction, transportation and erection as claimed in claim 1, characterized in that: Based on the resource allocation data of the bridge construction project, the time parameters of specific construction activities are obtained, including: The resource allocation data includes the personnel composition of each process, process indicator system, environmental logistics constraints and shift reduction rate, and total resource constraints; The time parameters are calculated by using the construction quota method to calculate the duration of component construction.
5. The method for automatically arranging the progress plan of a bridge with integrated construction, transportation and erection as claimed in claim 1, characterized in that: Based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, specifically including: Based on the relevant engineering experience, the process logic relationship is determined, and the order of bridge construction procedures is obtained as follows: pile foundation → pedestal → bridge → beam part, beam manufacturing → beam erection; By combining the data of multiple similar bridge engineering cases, the specific organizational logical relationship between the processes is excavated. The engineering data includes site environment, engineering quantity, total investment, contract period, deployable resources, and process decomposition logical relationship information. The process decomposition logical relationship information includes process logic relationship information and organizational logic relationship information between each process.
6. The method for automatically arranging the progress plan of a bridge with integrated construction, transportation and erection as claimed in claim 5, characterized in that: Based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, specifically including: The specific organizational logic relationship between the processes includes: the lower part of the special structure has priority over the lower part of the ordinary structure; when comparing the pile foundation construction periods of multiple special structures, the lower part of the special structure with a long pile foundation construction period has priority; when constructing the lower part of the special structure, the middle pier has a higher priority than the side pier, and when the priorities are the same, the piers of the special structure with a long single-shift construction period will be constructed first; once the lower part of the special structure is completed, the upper part of the special structure will start construction immediately; the special structures include continuous beams and segmental assembled beams, and the ordinary structures include simply supported beams.
7. The method for automatically arranging the progress plan of a bridge with integrated construction, transportation and erection as claimed in claim 1, characterized in that: The automatic scheduling algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, including: The ILC model and the constraint CC model are checked using implicit logic based on machine learning, and the ILC model and CC model are trained using the information in the critical path method CPM schedule.
8. The method for automatically arranging the progress plan of a bridge with integrated construction, transportation and erection as claimed in claim 7, characterized in that: The automatic scheduling algorithm based on machine learning is used to automatically sort the construction activities and generate a process logic relationship table, including: The ILC model includes an activity description encoder, a WBS label encoder, and a machine learning classifier; The activity description encoder encodes the input construction activity description; The WBS label encoder is used to assign a predefined WBS label code to each construction activity; During training, the output results of the activity description encoder and the WBS label encoder are used as inputs of the machine learning classifier. The trained machine learning classifier is used to predict the type and direction of the logical dependency of the relationship between the input activities.
9. The method for automatically arranging the progress plan of a bridge with integrated construction, transportation and erection as claimed in claim 1, characterized in that: The method further comprises: Prepare a double-code network schedule based on the generated process logic relationship table, and calculate the construction period and cost according to the key lines of the double-code network diagram.
10. An automatic scheduling system for the progress of a bridge with integrated construction, transportation and erection, characterized in that: The system comprises: A digital expression module is used to classify the transport bridges into different bridge types according to the construction process and to express them digitally; A construction process acquisition module is used to determine the construction process of the transport frame bridge and the specific construction activities included in each construction process based on the combined information of different types of bridges in the transport frame bridge; The construction time acquisition module is used to obtain the time parameters of specific construction activities based on the resource allocation data of the bridge construction project; The automatic scheduling module is used to automatically sort the construction activities based on the construction activity content of the manufacturing, transportation and erection bridge and the time parameters of the construction activities, and based on the process logic relationship between each process and the specific organizational logic relationship between each process mined in advance as constraints, using the automatic scheduling algorithm based on machine learning to generate a process logic relationship table, which contains the close relationship between the construction activities.