Enterprise project management system based on response feedback

By introducing real-time dynamic resource allocation, intelligent task priority adjustment and adaptive risk warning modules into the enterprise project management system, and using machine learning algorithms to dynamically adjust resources and task priorities, the shortcomings of resource allocation and risk management in traditional project management systems are solved. , achieving the improvement of project progress and quality and the effectiveness of risk management.

CN118735442AActive Publication Date: 2024-10-01ZHEJIANG XINWEI SCIENTIFIC & TECHNOLOGICAL ACHIEVEMENTS TRANSFORMATION SERVICE CO LTD

Patent Information

Application Number
CN202410799523.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-20
Publication Date
2024-10-01
Estimated Expiration
2044-06-20

AI Technical Summary

Technical Problem

The traditional project management system lacks the ability to monitor and adjust resource allocation in real time, resulting in a waste or shortage of resources. It is unable to adapt to changes in project progress, affecting project progress and quality. In addition, the existing risk management system lacks early warning and rapid response capabilities, which can easily lead to project failure. Interrupt or fail.

Method used

An enterprise project management system based on response feedback, including a real-time dynamic resource allocation module, an intelligent task priority adjustment module and an adaptive risk warning module. It uses machine learning algorithms to predict future investment needs and identify potential risks, and dynamically adjust resource allocation and task priorities. , and monitor project data in real time to provide early warning and response measures.

Benefits of technology

It achieves flexible and precise control of enterprise project management, improves project progress and quality, ensures efficient use of resources, predicts and responds to project risks in advance, and reduces the risk of project failure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735442A_ABST
    Figure CN118735442A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of enterprise project management, in particular to an enterprise project management system based on response feedback, which comprises a real-time dynamic resource allocation module, an intelligent task priority adjustment module, a self-adaptive risk early warning module and a visual analysis module. The real-time dynamic resource allocation module is used for dynamically adjusting resource allocation based on real-time feedback; the intelligent task priority adjustment module is used for dynamically adjusting the task priority according to the task completion state and the resource state; the self-adaptive risk early warning module is used for monitoring project data in real time and predicting potential risks of a project; the visual analysis module is used for integrating data of each module and performing data visual display on an integration result; according to the invention, through joint cooperation of all the modules, flexible and accurate control of enterprise project management can be realized; by constructing a linear programming equation, adaptive planning can be performed on resource allocation, and the overall progress and quality of a project are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of enterprise project management, and in particular to an enterprise project management system based on response feedback. Background Art

[0002] Enterprise project management is a systematic approach to planning, organizing, coordinating and controlling resources to achieve specific project goals; enterprise project management usually involves project planning, resource management, task management, schedule management, quality management and risk management;

[0003] Current enterprise management faces the following challenges:

[0004] 1. Traditional project management systems usually lack the ability to monitor and adjust resource allocation in real time, resulting in waste or shortage of resources, affecting project progress and quality;

[0005] 2. The priority and allocation of tasks in a project are often based on the initial plan, lacking a dynamic adjustment mechanism and unable to adapt to changes in actual progress, resulting in inefficiency;

[0006] 3. Existing risk management systems usually take countermeasures only after risks occur, lacking the ability to provide early warning and rapid response, which can easily lead to project interruption or failure;

[0007] 4. Project quality issues are often discovered after the fact, and there is a lack of prediction and prevention mechanisms, which affects the quality of the final deliverables and customer satisfaction. Summary of the invention

[0008] In view of the above-mentioned problems, the present invention is proposed.

[0009] To solve the above technical problems, the present invention provides the following technical solutions: an enterprise project management system based on response feedback, including a real-time dynamic resource allocation module, an intelligent task priority adjustment module, an adaptive risk warning module and a visual analysis module;

[0010] The real-time dynamic resource allocation module is used to dynamically adjust resource allocation based on real-time feedback;

[0011] The intelligent task priority adjustment module is used to dynamically adjust the task priority according to the task completion status and resource status;

[0012] The adaptive risk warning module is used to monitor project data in real time and predict potential risks of the project;

[0013] The visualization analysis module is used to integrate the data of each module and visualize the integration results.

[0014] As a preferred solution of the enterprise project management system based on response feedback described in the present invention, wherein: the real-time dynamic resource allocation module monitors the project progress and resource status in real time, and predicts future investment needs using a machine learning algorithm, automatically adjusts resource allocation according to the predicted investment needs, and feeds back the monitored resource status to the intelligent task priority adjustment module and the adaptive risk warning module; the prediction of future investment needs using a machine learning algorithm is to construct a future investment demand model using a machine learning algorithm, and the future investment demand model is constructed based on a linear regression algorithm, and is specifically constructed as follows:

[0015] y t =β0+β1x 1t +β2x 2t +...+β n x nt +ε t

[0016] Among them, y t represents the resource demand of the project at time t, β0 represents the intercept term of linear regression, which is calculated by substituting historical data, x it represents the i-th eigenvalue of the project at time t, including the project completion rate, current resource usage, human resource workload, equipment damage rate, and equipment usage status, ε t represents the error term, β i Represents each feature x it The regression coefficient, error term and regression coefficient are calculated by training the future investment demand model, as follows:

[0017] Use historical data as training data sets to train the constructed model and compare it with the current ongoing project.

[0018] Select similar projects from historical data, where the similar projects are matched according to the scheduled construction period, project objectives, construction team and acceptance unit of the current project, and the number of matches is not less than 2;

[0019] According to the schedule date of the current project, select the corresponding time schedule data from the historical data, including the historical resource demand y t ′ and historical eigenvalue x i ' t ;

[0020] Finally, the constructed model is trained with the selected data, and the regression coefficient β corresponding to each eigenvalue can be calculated. i , and maps the calculated regression coefficients to the current project to predict resource requirements at future time points.

[0021] As a preferred solution of the enterprise project management system based on response feedback described in the present invention, wherein: the automatic adjustment of resource allocation according to the predicted investment demand is the calculation result of constructing a linear programming equation, and the constructed equation is constrained by dynamically adjusting the constraint condition to realize the automatic adjustment of resource allocation according to the predicted investment demand, which is specifically implemented as follows:

[0022] Construct the linear programming equation,

[0023] Use dynamic adjustment constraints to constrain,

[0024]

[0025]

[0026]

[0027] Among them, X ij represents the number of resources assigned to task j, a ij The contribution coefficient of the jth task of the i-th resource is set based on the historical data as reference data before the current project is launched, according to the importance of the resource to the task. j represents the predicted demand for the jth task, w j represents the priority weight of the jth task. It is the priority weight set for each task in advance based on historical data as reference data before the current project starts. Y represents the total resource investment of the current project, and w ij represents the priority weight of the jth task of the i-th resource. It is the priority weight set for each resource in advance based on historical data as reference data before the current project starts. ij Represents the predicted demand for the i-th resource of the j-th task.

[0028] As a preferred solution of the enterprise project management system based on response feedback described in the present invention, wherein: the use of dynamic adjustment constraints to constrain the constructed equation is to constrain the linear programming equation through the establishment of the constraints to complete the adaptive allocation of resources, which is specifically as follows:

[0029] For different task resource allocations, ij ≥0 is used as a constraint, which means that when allocating resources according to the linear programming equation, it is necessary to ensure that the number of resources allocated to the task is greater than 0;

[0030] For the priority weight of the task, A constraint is imposed, indicating that the actual resource allocation for the current task is greater than the predicted resource quantity predicted based on the current task priority weight;

[0031] For adaptive allocation of resources, the calculation result f of the linear programming equation is used for allocation, y ij w ij It represents the comprehensive score for the current task, which is obtained through comprehensive analysis of the predicted resource volume and priority weight of the current task. It represents the sum of the comprehensive scores of all tasks in the current project, Y represents the total resource input of the current project, and f represents the allocation quantity of the ith resource allocated to task j. It is adaptively allocated according to the proportion of the comprehensive score of the current task in the entire project.

[0032] As a preferred solution of the enterprise project management system based on response feedback described in the present invention, wherein: the intelligent task priority adjustment module resets the task priority weight of the current project according to the task completion rate and the amount of resource allocation, and feeds back the adjustment result to the real-time dynamic resource allocation module, and performs secondary regulation on the resource allocation of tasks in the real-time dynamic resource allocation module;

[0033] The resetting of the task priority weight of the current project is carried out by comprehensively considering the task completion rate and resource allocation results. The specific calculation formula is as follows:

[0034]

[0035]

[0036] Among them, λ represents the completion rate of the current task, t represents the time of the current task, T represents the specified duration of the entire project, and w j represents the priority weight set for the task before the project starts, f represents the number of resources allocated to the current project, and w′ j Indicates the priority weight of the current task's adaptive allocation. The specific adaptive allocation is as follows:

[0037] Sort the task completion rates λ in descending order, and compare the task completion rate of the current project with the completion rate λ′ of the historical projects in the same duration. Adaptively adjust the task priority weights based on the comparison results. Specifically,

[0038] When the comparison result satisfies the formula λ≤λ′, it means that the completion rate of the current task is lower than the completion rate of the historical tasks. The priority weight of the current task is increased, and the increased priority weight is fed back to the real-time dynamic resource allocation module to increase the resource allocation quantity of the current task, thus completing the secondary regulation of the resource allocation of the task.

[0039] When the comparison result satisfies the formula λ>λ′, it means that the completion rate of the current task is higher than the completion rate of the historical tasks. The priority weight of the current task is reduced, and the reduced priority weight is fed back to the real-time dynamic resource allocation module to reduce the number of resources allocated to the current task, thus completing the secondary regulation of the resource allocation of the task.

[0040] As a preferred solution of the enterprise project management system based on response feedback described in the present invention, the adaptive risk warning module monitors the project data in real time and identifies the potential risks of the project according to the monitoring results. The specific implementation is as follows:

[0041] The monitored project data is constructed into a data set R = [r1, r2, r3, ..., r n ], where each eigenvector r i It includes multiple feature values, and the feature vector includes project progress data, resource usage data, quality data, and environmental data. The feature values ​​of the project progress data include task completion time and task extension status;

[0042] The Bayesian network is used to calculate the probability of risk of the feature vector. The specific calculation formula is as follows:

[0043]

[0044] Among them, P(R|r) represents the feature vector r i The probability of project risk occurring under the appearance of i ) represents the feature vector r i The probability of occurrence of the risk, P(R) represents the initial probability of the project risk, P(r i |R) indicates that when a project encounters risk, the eigenvector r i The probability of occurrence.

[0045] As a preferred solution of the enterprise project management system based on response feedback described in the present invention, the identification of potential risks of the project based on the monitoring results is based on the calculation of the probability of risk occurrence, and the support vector machine model is used to predict the risk type. The specific prediction is as follows:

[0046] The calculated risk probability P(R|r i ) as a new feature vector, construct a new feature set R′, and satisfy the formula R′=[r1,r2,r3,..,r n ,P(R1|r i ),P(R2|r i ),...,P(R m |r i )], where n represents the total number of original features and m represents the total number of project risk types, which are set based on historical data;

[0047] Construct a support vector machine model to complete the prediction of risk types. The specific model is as follows:

[0048]

[0049] Among them, R T represents the risk type prediction result, W represents the weight vector, which controls the accuracy of risk classification, b represents the bias term, and R i ′ represents the true risk type of the i-th eigenvector.

[0050] As a preferred solution of the enterprise project management system based on response feedback described in the present invention, wherein: the visual analysis module integrates feedback data from the real-time dynamic resource allocation module, the intelligent task priority adjustment module and the adaptive risk warning module, and uses data technology to display the data in the form of page interaction to the visual terminal;

[0051] The integration of feedback data from the real-time dynamic resource allocation module, the intelligent task priority adjustment module, and the adaptive risk warning module is to evaluate the data of each module in a comprehensive scoring manner, and use the evaluation results as the data basis for subsequent page interactions. The specific implementation is as follows:

[0052] For any task j in the current project, the data from the real-time dynamic resource allocation model is f j , represents the number of resources allocated to the current task, and the data from the intelligent task priority adjustment module is w j , indicating the priority of the current task, and the data from the adaptive risk warning module is R Tj , indicating the risk type caused by the current task;

[0053] The data of each module is evaluated by weighted average, as follows:

[0054]

[0055] Among them, f j represents the data from the real-time dynamic resource allocation model, w j represents the data from the intelligent task priority adjustment module, R Tj Represents data from the adaptive risk early warning module;

[0056] The weighted average data will be evaluated comprehensively, and the specific evaluation is as follows:

[0057] E=W f ·f J +W w ·w J +WR ·R Tj

[0058] Among them, W f , W w , W R Respectively represent the weight of each module data, which is set according to the contribution of the current task to the project in the historical data. E represents the calculated comprehensive score, which is used as the ordinate basis for the visualization terminal display;

[0059] Finally, the calculated comprehensive score is used as the basis for the vertical axis in the visualization terminal display, and the time progress is used as the basis for the horizontal axis in the visualization terminal display, so that relevant staff can make quick decisions based on the visualization terminal display results.

[0060] The beneficial effects of the present invention are as follows: through the joint collaboration of various modules, the results of the front module affect the output of the rear module, and the feedback of the front module triggers the real-time response of the rear module, thereby realizing flexible and precise control of enterprise project management; by constructing linear programming equations, the allocation of resources can be adaptively planned to improve the overall progress and quality of the project; through real-time monitoring and prediction of project risks, project risks can be predicted in advance, and targeted measures can be taken for the predicted risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. Among them:

[0062] Figure 1 It is a schematic diagram of the overall composition structure of the enterprise project management system based on response feedback of the present invention. DETAILED DESCRIPTION

[0063] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the drawings of the specification. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary persons in the art without creative work should fall within the scope of protection of the present invention.

[0064] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0065] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0066] The present invention is described in detail with reference to schematic diagrams. When describing the embodiments of the present invention, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0067] Meanwhile, in the description of the present invention, it should be noted that the terms "first, second or third" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.

[0068] In the present invention, unless otherwise clearly specified and limited, the terms "install, connect, connect" should be understood in a broad sense, for example: it can be a fixed connection, a detachable connection or an integral connection; it can also be a mechanical connection, an electrical connection or a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0069] Example 1

[0070] Reference Figure 1 , which is the first embodiment of the present invention, provides an enterprise project management system based on response feedback, including a real-time dynamic resource allocation module, an intelligent task priority adjustment module, an adaptive risk warning module and a visual analysis module;

[0071] Furthermore, the real-time dynamic resource allocation module is used to dynamically adjust resource allocation based on real-time feedback, the intelligent task priority adjustment module is used to dynamically adjust task priority according to task completion status and resource status, the adaptive risk warning module is used to monitor project data in real time and predict potential project risks, and the visual analysis module is used to integrate data from various modules and display the integration results in a data visualization manner.

[0072] It should be noted that the real-time dynamic resource allocation module feeds back the monitored resource status to the intelligent task priority adjustment module and the adaptive risk warning module. The intelligent task priority adjustment module receives resource status feedback from the real-time dynamic resource allocation module, adjusts task allocation, and feeds back task completion status to the adaptive risk warning module and the visualization analysis module. The adaptive risk warning module receives task progress feedback from the intelligent task priority adjustment module and resource status feedback from the real-time dynamic resource allocation module, identifies risks and adjusts response measures. The visualization analysis module integrates feedback data from the real-time dynamic resource allocation module, the intelligent task priority adjustment module and the adaptive risk warning module, and uses data technology to display the data in the form of page interaction to the visualization terminal, so that relevant staff can supervise the project and make quick decisions.

[0073] It should be noted that through the joint collaboration of various modules, the modules are closely linked to each other, and the front module has an effect on the rear module. The results of the front module affect the output of the rear module. The feedback of the front module triggers the real-time response of the rear module, thereby realizing flexible and precise control of enterprise project management.

[0074] Furthermore, the real-time dynamic resource allocation module monitors the project progress and resource status in real time, and uses machine learning algorithms to predict future investment needs, automatically adjusts resource allocation according to the predicted investment needs, and feeds back the monitored resource status to the intelligent task priority adjustment module and the adaptive risk warning module.

[0075] Specifically, the real-time monitoring of project progress and resource status is to use data acquisition equipment to capture enterprise data from the enterprise database in real time, and the enterprise data includes project progress data, resource usage data and historical project data;

[0076] The method of using a machine learning algorithm to predict future investment demand is to use a machine learning algorithm to construct a future investment demand model. The future investment demand model is constructed based on a linear regression algorithm. The specific construction is as follows:

[0077] y t =β0+β1x 1t +β2x 2t +...+β n x nt +ε t

[0078] Among them, y t represents the resource demand of the project at time t, β0 represents the intercept term of linear regression, which is calculated by substituting historical data, x itrepresents the i-th eigenvalue of the project at time t, including the project completion rate, current resource usage, human resource workload, equipment damage rate, and equipment usage status, ε t represents the error term, β i Represents each feature x it The regression coefficient, error term and regression coefficient are calculated by training the future investment demand model, as follows:

[0079] Use historical data as training data sets to train the constructed model and compare it with the current ongoing project.

[0080] Select similar projects from historical data, where the similar projects are matched according to the scheduled construction period, project objectives, construction team and acceptance unit of the current project, and the number of matches is not less than 2;

[0081] According to the schedule date of the current project, select the corresponding time schedule data from the historical data, including the historical resource demand y t ′ and historical eigenvalue x i ' t ;

[0082] Finally, the constructed model is trained with the selected data, and the regression coefficient β corresponding to each eigenvalue can be calculated. i , and maps the calculated regression coefficients to the current project to predict resource requirements at future time points.

[0083] Furthermore, the automatic adjustment of resource allocation according to the predicted investment demand is achieved by constructing the calculation result of a linear programming equation, and constraining the constructed equation using dynamic adjustment constraints to achieve automatic adjustment of resource allocation according to the predicted investment demand, which is specifically implemented as follows:

[0084] Construct the linear programming equation,

[0085] Use dynamic adjustment constraints to constrain,

[0086]

[0087]

[0088]

[0089] Among them, X ij represents the number of resources assigned to task j, a ij The contribution coefficient of the jth task of the i-th resource is set based on the historical data as reference data before the current project is launched, according to the importance of the resource to the task.j represents the predicted demand for the jth task, w j represents the priority weight of the jth task. It is the priority weight set for each task in advance based on historical data as reference data before the current project starts. Y represents the total resource investment of the current project, and w ij represents the priority weight of the jth task of the i-th resource. It is the priority weight set for each resource in advance based on historical data as reference data before the current project starts. ij Represents the predicted demand for the i-th resource of the j-th task.

[0090] It should be noted that the use of dynamic adjustment constraints to constrain the constructed equations is to constrain the linear programming equations through the establishment of the constraints to complete the adaptive allocation of resources, as follows:

[0091] For different task resource allocations, ij ≥0 is used as a constraint, which means that when allocating resources according to the linear programming equation, it is necessary to ensure that the number of resources allocated to the task is greater than 0;

[0092] For the priority weight of the task, A constraint is imposed, indicating that the actual resource allocation for the current task is greater than the predicted resource quantity predicted based on the current task priority weight;

[0093] For adaptive allocation of resources, the calculation result f of the linear programming equation is used for allocation, y ij w ij It represents the comprehensive score for the current task, which is obtained through comprehensive analysis of the predicted resource volume and priority weight of the current task. represents the sum of the comprehensive scores of all tasks in the current project, Y represents the total resource input of the current project, and f represents the allocation quantity of the i-th resource assigned to task j, which is adaptively allocated according to the proportion of the comprehensive score of the current task in the entire project.

[0094] Furthermore, the intelligent task priority adjustment module resets the task priority weight of the current project according to the task completion rate and the amount of resource allocation, thereby completing the adaptive adjustment of the priority of the current project task, and feeds back the adjustment result to the real-time dynamic resource allocation module, and performs secondary regulation on the resource allocation of the tasks in the real-time dynamic resource allocation module.

[0095] Specifically, the task priority weight of the current project is reset by comprehensively considering the task completion rate and resource allocation results. The specific calculation formula is as follows:

[0096]

[0097]

[0098] Among them, λ represents the completion rate of the current task, t represents the time of the current task, T represents the specified duration of the entire project, and w j represents the priority weight set for the task before the project starts, f represents the number of resources allocated to the current project, and w′ j Indicates the priority weight of the current task's adaptive allocation. The specific adaptive allocation is as follows:

[0099] Sort the task completion rates λ in descending order, and compare the task completion rate of the current project with the completion rate λ′ of the historical projects in the same duration. Adaptively adjust the task priority weights based on the comparison results. Specifically,

[0100] When the comparison result satisfies the formula λ≤λ′, it means that the completion rate of the current task is lower than the completion rate of the historical tasks. The priority weight of the current task is increased, and the increased priority weight is fed back to the real-time dynamic resource allocation module to increase the resource allocation quantity of the current task, thus completing the secondary regulation of the resource allocation of the task.

[0101] When the comparison result satisfies the formula λ>λ′, it means that the completion rate of the current task is higher than the completion rate of the historical tasks. The priority weight of the current task is reduced, and the reduced priority weight is fed back to the real-time dynamic resource allocation module to reduce the number of resources allocated to the current task, thus completing the secondary regulation of the resource allocation of the task.

[0102] Furthermore, the adaptive risk warning module monitors project data in real time and identifies potential risks of the project based on the monitoring results. The specific implementation is as follows:

[0103] The monitored project data is constructed into a data set R = [r1, r2, r3, ..., r n ], where each eigenvector r i It includes multiple feature values, and the feature vector includes project progress data, resource usage data, quality data, and environmental data. The feature values ​​of the project progress data include task completion time and task extension status;

[0104] The Bayesian network is used to calculate the probability of risk of the feature vector. The specific calculation formula is as follows:

[0105]

[0106] Among them, P(R|r) represents the feature vector r i The probability of project risk occurring under the appearance of i ) represents the feature vector r iThe probability of occurrence of the risk, P(R) represents the initial probability of the project risk, P(r i |R) indicates that when a project encounters risk, the eigenvector r i The probability of occurrence.

[0107] Furthermore, the identification of potential risks of the project based on the monitoring results is based on the calculation of the probability of risk occurrence and the use of a support vector machine model to predict the risk type. The specific prediction is as follows:

[0108] The calculated risk probability P(R|r i ) as a new feature vector, construct a new feature set R′, and satisfy the formula R′=[r1,r2,r3,..,r n ,P(R1|r i ),P(R2|r i ),...,P(R m |r i )], where n represents the total number of original features and m represents the total number of project risk types, which are set based on historical data;

[0109] Construct a support vector machine model to complete the prediction of risk types. The specific model is as follows:

[0110]

[0111] Among them, R T represents the risk type prediction result, W represents the weight vector, which controls the accuracy of risk classification, b represents the bias term, and R i ′ represents the true risk type of the i-th eigenvector.

[0112] It should be noted that the values ​​of the weight vector and bias term in the support vector machine model are obtained by training with historical data, as follows:

[0113] The feature vector data r in the historical data that is the same as the current feature set R′ i ′ and the corresponding risk occurrence probability P′(R|r i ), as input into the constructed support vector machine model, after inputting multiple sets of input, the value of the weight vector W and the value of the bias term b in the model can be obtained;

[0114] Substitute the calculated value of the weight vector W and the value of the bias term b into the constructed support vector machine model to complete the prediction of the risk type.

[0115] Furthermore, the visualization analysis module integrates feedback data from the real-time dynamic resource allocation module, the intelligent task priority adjustment module and the adaptive risk warning module, and uses data technology to display the data in the form of page interaction on the visualization terminal, so that relevant staff can supervise the project and make quick decisions.

[0116] Specifically, the feedback data from the real-time dynamic resource allocation module, the intelligent task priority adjustment module, and the adaptive risk warning module are integrated to evaluate the data of each module in a comprehensive scoring manner, and the evaluation results are used as the data basis for subsequent page interactions. The specific implementation is as follows:

[0117] For any task j in the current project, the data from the real-time dynamic resource allocation model is f j , represents the number of resources allocated to the current task, and the data from the intelligent task priority adjustment module is w j , indicating the priority of the current task, and the data from the adaptive risk warning module is R Tj , indicating the risk type caused by the current task;

[0118] The data of each module is evaluated by weighted average, as follows:

[0119]

[0120] Among them, f j represents the data from the real-time dynamic resource allocation model, w j represents the data from the intelligent task priority adjustment module, R Tj Represents data from the adaptive risk early warning module;

[0121] The weighted average data will be comprehensively evaluated to determine the stability of the current project progress. The specific evaluation is as follows:

[0122] E=W f ·f J +W w ·w J +W R ·R Tj

[0123] Among them, W f , W w , W R Respectively represent the weight of each module data, which is set according to the contribution of the current task to the project in the historical data. E represents the calculated comprehensive score, which is used as the ordinate basis for the visualization terminal display;

[0124] Finally, the calculated comprehensive score is used as the basis for the vertical axis in the visualization terminal display, and the time progress is used as the basis for the horizontal axis in the visualization terminal display, so that relevant staff can make quick decisions based on the visualization terminal display results.

[0125] It should be noted that when the staff makes a quick decision based on the results displayed by the visualization terminal, they first analyze the main factors affecting the project progress. The specific analysis is as follows:

[0126] For data with abnormal item composite scores, secondary analysis was performed;

[0127] Secondary analysis is to conduct detailed analysis on nodes with abnormal comprehensive scores and analyze the data in each module of the comprehensive score.

[0128] When the data from the real-time dynamic resource allocation module is abnormal, the cause of the project abnormality is uneven allocation of task resources. Immediately readjust the task resource allocation so that the project can return to normal working status;

[0129] When the data from the intelligent task priority adjustment module is abnormal, the cause of the project abnormality is improper task priority adjustment, resulting in uneven distribution of task resources. The priority needs to be readjusted according to the urgency of the task so that the project can resume normal working status;

[0130] When the data from the adaptive risk warning module is abnormal, the cause of the project abnormality is an error in the assessment of the project risk type, which leads to errors in the implementation of preventive measures, and then to project abnormalities. It is necessary to re-evaluate the entire project risk type in order to formulate a correct implementation plan so that the project can return to normal working status.

[0131] Example 2

[0132] The second embodiment of the present invention provides a practical application case of an enterprise project management system based on response feedback, which is as follows:

[0133] The project team first conducted a detailed needs analysis to determine the key objectives and resource requirements of the project, and deployed the enterprise project management system based on response feedback into the company's existing IT infrastructure, including servers and cloud services;

[0134] Make preliminary resource allocation based on project requirements and existing resources;

[0135] During the project, the system monitors the project progress and resource usage in real time, uses machine learning algorithms to predict future resource needs, and dynamically adjusts resource allocation based on the prediction results to ensure efficient use of resources;

[0136] The system adjusts the priority of tasks in real time according to the task completion status and resource status;

[0137] The task completion status will be fed back to the system in real time, and the system will dynamically adjust the task priority based on the feedback data to ensure that key tasks can be completed first and improve the overall progress and quality of the project;

[0138] The system monitors project data in real time and predicts potential risks through data analysis;

[0139] When potential risks are detected, the system will immediately issue an early warning and provide corresponding response suggestions. The project team can quickly adjust the project plan and resource allocation based on the early warning information to reduce the impact of risks on the project;

[0140] Finally, through visualization technology, the integrated data is displayed on the visualization terminal in the form of page interaction, which makes it convenient for project managers to monitor the project in real time and make quick decisions.

[0141] In order to further highlight the beneficial effects of the technical solution of the present invention, the technical features of the present invention are compared with the prior art, as shown in the following table:

[0142]

[0143] It is not difficult to find from the above comparison table that the enterprise project management system based on response feedback has shown significant improvements in various key indicators, especially in resource utilization efficiency, task completion rate and project risk reduction rate, showing its significant superiority; through data comparison, we can intuitively see the huge improvement that the implementation of the system has brought to enterprise project management.

[0144] Furthermore, if the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product, which is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods described in various embodiments of the present invention. The aforementioned storage medium includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk.

[0145] The logic and / or steps represented in the flowchart or otherwise described herein, for example, may be considered as an ordered list of executable instructions for implementing logical functions, and may be embodied in any computer-readable medium for use by, or in conjunction with, an instruction execution method, apparatus, or device (such as a computer-based method, a method including a processor, or other method that can fetch instructions from and execute instructions to an instruction execution method, apparatus, or device). For purposes of this specification, a "computer-readable medium" may be any device that can contain, store, communicate, propagate, or transmit a program for use by, or in conjunction with, an instruction execution method, apparatus, or device.

[0146] More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk case (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), an optical fiber device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be a paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium, followed by editing, deciphering or, if necessary, processing in another suitable manner, and then stored in a computer memory.

[0147] Additionally, in order to provide a concise description of exemplary embodiments, all features of an actual embodiment (ie, those features that are not relevant to the best mode presently contemplated for carrying out the invention or those that are not relevant to implementing the invention) may not be described.

[0148] It will be appreciated that in the development of any actual implementation, as in any engineering or design project, numerous implementation-specific decisions may be made. Such a development effort may be complex and time-consuming, but will be a routine task of design, fabrication, and production for those of ordinary skill having the benefit of this disclosure without undue experimentation.

[0149] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

Claims

1. Enterprise project management system based on response feedback, Features: include, Real-time dynamic resource allocation module, intelligent task priority adjustment module, adaptive risk warning module and visual analysis module; The real-time dynamic resource allocation module is used to dynamically adjust resource allocation based on real-time feedback; The intelligent task priority adjustment module is used to dynamically adjust the task priority according to the task completion status and resource status; The adaptive risk warning module is used to monitor project data in real time and predict potential risks of the project; The visualization analysis module is used to integrate the data of each module and visualize the integration results.

2. The enterprise project management system based on response feedback as claimed in claim 1, Features: The real-time dynamic resource allocation module monitors the project progress and resource status in real time, and uses machine learning algorithms to predict future investment needs, automatically adjusts resource allocation according to the predicted investment needs, and feeds back the monitored resource status to the intelligent task priority adjustment module and the adaptive risk warning module; the use of machine learning algorithms to predict future investment needs is to use machine learning algorithms to build a future investment demand model, and the future investment demand model is built based on a linear regression algorithm, and the specific construction is as follows: y t =b 0 +b 1 x 1t +b 2 x 2t +...+b n x nt +e t Among them, y t represents the resource demand of the project at time t, β 0 Represents the intercept term of linear regression, which is calculated by substituting historical data into x it represents the i-th eigenvalue of the project at time t, including the project completion rate, current resource usage, human resource workload, equipment damage rate, and equipment usage status, ε t represents the error term, β i Represents each feature x it The regression coefficient, error term and regression coefficient are calculated by training the future investment demand model, as follows: Use historical data as training data sets to train the constructed model and compare it with the current ongoing project. Select similar projects from historical data, where the similar projects are matched according to the scheduled construction period, project objectives, construction team and acceptance unit of the current project, and the number of matches is not less than 2; According to the schedule date of the current project, select the corresponding time schedule data from the historical data, including the historical resource demand y t ′ and historical eigenvalue x i ' t ; Finally, the constructed model is trained with the selected data, and the regression coefficient β corresponding to each eigenvalue can be calculated. i , and maps the calculated regression coefficients to the current project to predict resource requirements at future time points.

3. The enterprise project management system based on response feedback as claimed in claim 2, Features: The automatic adjustment of resource allocation according to the predicted investment demand is achieved by constructing the calculation result of a linear programming equation and constraining the constructed equation using dynamic adjustment constraints to achieve automatic adjustment of resource allocation according to the predicted investment demand. The specific implementation is as follows: Construct the linear programming equation, Use dynamic adjustment constraints to constrain, Among them, X ij represents the number of resources assigned to task j, a ij The contribution coefficient of the jth task of the i-th resource is set based on the historical data as reference data before the current project is launched, according to the importance of the resource to the task. j represents the predicted demand for the jth task, w j represents the priority weight of the jth task. It is the priority weight set for each task in advance based on historical data as reference data before the current project starts. Y represents the total resource investment of the current project, and w ij represents the priority weight of the jth task of the i-th resource. It is the priority weight set for each resource in advance based on historical data as reference data before the current project starts. ij Represents the predicted demand for the i-th resource of the j-th task.

4. The enterprise project management system based on response feedback as claimed in claim 3, Features: The method of constraining the constructed equation by dynamically adjusting the constraint condition is to constrain the linear programming equation by the establishment of the constraint condition to complete the adaptive allocation of resources, as follows: For different task resource allocations, ij ≥0 is used as a constraint, which means that when allocating resources according to the linear programming equation, it is necessary to ensure that the number of resources allocated to the task is greater than 0; For the priority weight of the task, A constraint is imposed, indicating that the actual resource allocation for the current task is greater than the predicted resource quantity predicted based on the current task priority weight; For adaptive allocation of resources, the calculation result f of the linear programming equation is used for allocation, y ij w ij It represents the comprehensive score for the current task, which is obtained through comprehensive analysis of the predicted resource volume and priority weight of the current task. It represents the sum of the comprehensive scores of all tasks in the current project, Y represents the total resource input of the current project, and f represents the allocation quantity of the ith resource allocated to task j. It is adaptively allocated according to the proportion of the comprehensive score of the current task in the entire project.

5. The enterprise project management system based on response feedback as claimed in claim 4, Features: The intelligent task priority adjustment module resets the task priority weight of the current project according to the task completion rate and the amount of resource allocation, and feeds back the adjustment result to the real-time dynamic resource allocation module to perform secondary regulation on the resource allocation of tasks in the real-time dynamic resource allocation module; The resetting of the task priority weight of the current project is carried out by comprehensively considering the task completion rate and resource allocation results. The specific calculation formula is as follows: Among them, λ represents the completion rate of the current task, t represents the time of the current task, T represents the specified duration of the entire project, and w j represents the priority weight set for the task before the project starts, f represents the number of resources allocated to the current project, and w′ j Indicates the priority weight of the current task's adaptive allocation. The specific adaptive allocation is as follows: Sort the task completion rates λ in descending order, and compare the task completion rate of the current project with the completion rate λ′ of the historical projects in the same duration. Adaptively adjust the task priority weights based on the comparison results. Specifically, When the comparison result satisfies the formula λ≤λ′, it means that the completion rate of the current task is lower than the completion rate of the historical tasks. The priority weight of the current task is increased, and the increased priority weight is fed back to the real-time dynamic resource allocation module to increase the resource allocation quantity of the current task, thus completing the secondary regulation of the resource allocation of the task. When the comparison result satisfies the formula λ>λ′, it means that the completion rate of the current task is higher than the completion rate of the historical tasks. The priority weight of the current task is reduced, and the reduced priority weight is fed back to the real-time dynamic resource allocation module to reduce the number of resources allocated to the current task, thus completing the secondary regulation of the resource allocation of the task.

6. The enterprise project management system based on response feedback as claimed in claim 5, Features: The adaptive risk warning module monitors project data in real time and identifies potential risks of the project based on the monitoring results. The specific implementation is as follows: The monitored project data is constructed into a data set R = [r 1 ,r 2 ,r 3 ,...,r n ], where each eigenvector r i It includes multiple feature values, and the feature vector includes project progress data, resource usage data, quality data, and environmental data. The feature values ​​of the project progress data include task completion time and task extension status; The Bayesian network is used to calculate the probability of risk of the feature vector. The specific calculation formula is as follows: Among them, P(R|r) represents the feature vector r i The probability of project risk occurring under the appearance of i ) represents the feature vector r i The probability of occurrence of the risk, P(R) represents the initial probability of the project risk, P(r i |R) indicates that when a project encounters risk, the eigenvector r i The probability of occurrence.

7. The enterprise project management system based on response feedback as claimed in claim 6, Features: The identification of potential risks of the project based on the monitoring results is based on the calculation of the probability of risk occurrence and the use of the support vector machine model to predict the risk type. The specific prediction is as follows: The calculated risk probability P(R|r i ) as a new feature vector, construct a new feature set R′, and satisfy the formula R′=[r 1 ,r 2 ,r 3 ,..,r n ,P(R 1 |r i ),P(R 2 |r i ),...,P(R m |r i )], where n represents the total number of original features and m represents the total number of project risk types, which are set based on historical data; Construct a support vector machine model to complete the prediction of risk types. The specific model is as follows: Among them, R T represents the risk type prediction result, W represents the weight vector, which controls the accuracy of risk classification, b represents the bias term, and R i ′ represents the true risk type of the i-th eigenvector.

8. The enterprise project management system based on response feedback as claimed in claim 7, Features: The visualization analysis module integrates the feedback data from the real-time dynamic resource allocation module, the intelligent task priority adjustment module and the adaptive risk warning module, and uses data technology to display the data in the form of page interaction to the visualization terminal; The integration of feedback data from the real-time dynamic resource allocation module, the intelligent task priority adjustment module, and the adaptive risk warning module is to evaluate the data of each module in a comprehensive scoring manner, and use the evaluation results as the data basis for subsequent page interactions. The specific implementation is as follows: For any task j in the current project, the data from the real-time dynamic resource allocation model is f j , represents the number of resources allocated to the current task, and the data from the intelligent task priority adjustment module is w j , indicating the priority of the current task, and the data from the adaptive risk warning module is R Tj , indicating the risk type caused by the current task; The data of each module is evaluated by weighted average, as follows: Among them, f j represents the data from the real-time dynamic resource allocation model, w j represents the data from the intelligent task priority adjustment module, R Tj Represents data from the adaptive risk early warning module; The weighted average data will be evaluated comprehensively, and the specific evaluation is as follows: E=W f ·f J +W w ·w J +W R ·R Tj Among them, W f , W w , W R Respectively represent the weight of each module data, which is set according to the contribution of the current task to the project in the historical data. E represents the calculated comprehensive score, which is used as the ordinate basis for the visualization terminal display; Finally, the calculated comprehensive score is used as the basis for the vertical axis in the visualization terminal display, and the time progress is used as the basis for the horizontal axis in the visualization terminal display, so that relevant staff can make quick decisions based on the visualization terminal display results.

Citation Information

Patent Citations

  • Building construction optimization system based on big data and cloud computing

    CN116862199A

  • Highway construction safety monitoring system

    CN117575334A

  • Construction personnel warning protection system based on attitude risk degree analysis

    CN117711131A

  • Project management monitoring method and system based on multi-stage analysis

    CN117787434A

  • Failure prediction diagnosis system and method through pattern analysis according to failure type

    KR102618023B1

Cited By

  • Numerical control tool production integrated management system

    CN118965288A

  • Work task management system

    CN119026894A

  • A work task management system

    CN119026894B

  • Production project implementation progress intelligent statistical analysis method and system

    CN119578806A

  • Service fault tolerance method and system based on context awareness

    CN119902899A