Downhole drilling blowout prevention device and method based on hole bottom fast gas extraction
By utilizing components such as drilling rigs, sealing devices, and cinder processors during underground drilling, rapid gas extraction at the bottom of the borehole and effective gas drainage within the borehole are achieved, solving the problem of gas over-limit accidents during drilling. problem, ensuring safety.
Patent Information
- Application Number
- CN202410931637.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-10-08
AI Technical Summary
During the drilling process of coal mines, due to the non-uniformity of coal seam gas and the stress changes of the coal mass near the drilling, it is easy to cause blowout holes. It is difficult for traditional blowout hole prevention devices to quickly drain the gas in a timely manner, leading to the occurrence of gas over-limit accidents.
Design an underground drilling blowout prevention device based on rapid gas extraction at the bottom of the hole, including a drilling rig, a sealing device, a cinder processor, a water pump and a central processor. The gas at the bottom of the hole is realized through the water outlet and tee pipe on the drill pipe. Direct extraction, and use sealing devices and cinder processors to quickly extract gas from the borehole to ensure that the borehole opening is sealed to avoid gas escape.
It achieves rapid gas extraction and drilling hole sealing when a spray hole occurs, avoiding gas over-limit accidents and ensuring worker safety.
Smart Images

Figure CN118745875A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an underground drilling blowout prevention device and method based on quick gas extraction at the hole bottom, which is suitable for preventing and controlling accidents caused by blowout holes leading to gas exceeding the limit during coal seam drilling, and belongs to the technical field of coal mine gas disaster prevention and control. Background Art
[0002] With the depletion of shallow coal resources in my country, the depth of coal mining has gradually increased, resulting in many low-gas mines being converted into high-gas mines or outburst mines. For high-gas or outburst coal seams, gas pre-extraction is required before mining to prevent gas disasters. At present, gas extraction is mainly carried out through construction drilling in coal mines, generally including in-layer drilling and through-layer drilling. During the drilling construction process, due to the non-uniformity of coal seam gas occurrence, the anisotropy of coal seam mechanical properties and the drastic changes in coal body stress near the borehole, the blowhole phenomenon will occur. The blowhole phenomenon is manifested as a large amount of gas and coal slag ejected from the borehole in a short period of time, which causes gas over-limit accidents and threatens the safety of workers.
[0003] Since the blowout process is more intense and the gas is ejected quickly, traditional blowout prevention devices rely on manual control, which often results in the inability to quickly and quickly extract and treat the gas, thus causing the gas to exceed the limit. In addition, the blowout prevention device currently arranged near the orifice has a poor sealing effect with the drill rod and the hole wall, causing the ejected gas to escape into the working space. The inventors of the present invention have found that blowout generally occurs near the drill bit, that is, gas and coal slag are ejected from near the bottom of the borehole.
[0004] Therefore, how to provide a device and method that can directly extract the gas near the bottom of the borehole when a blowout occurs in the borehole, quickly extract the gas dissipated in the borehole, and effectively seal the borehole opening, ultimately ensuring that a gas over-limit accident will not occur when a blowout occurs, is the research direction required by the present invention. Summary of the invention
[0005] In view of the problems existing in the above-mentioned prior art, the present invention provides an underground drilling blowout prevention device and method based on quick gas extraction from the bottom of the hole. When a blowout occurs in the borehole, the gas near the bottom of the borehole can be directly extracted, and the gas escaped in the borehole can be quickly extracted and the borehole opening can be effectively sealed, thereby ultimately ensuring that a gas over-limit accident will not occur when a blowout occurs.
[0006] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: an underground drilling blowout prevention hole device based on quick gas extraction at the bottom of the hole, comprising a drilling rig, a sealing device, a cinder processor, a water pump and a central processor;
[0007] The drilling rig is provided with a drill rod, one end of which is provided with a drill bit, a through hole is provided inside the drill rod along the axial direction, a water outlet is provided on the drill bit, and the water outlet is connected to one end of the through hole, and a tee is provided at the other end of the drill rod, and the tee enables the through hole to be connected to the underground gas extraction main pipe and the water pump respectively through the extraction pipeline 1 and the water injection pipe, wherein the underground gas extraction main pipe is used to extract gas from the bottom of the borehole through the through hole and the water outlet when spraying the hole; the water pump is used to inject water into the bottom of the borehole through the through hole and the water outlet when drilling;
[0008] The sealing device comprises a sealing flange, a sleeve and a buffer chamber, wherein the sealing flange is fixed at the borehole opening, the sleeve extends into the borehole and one end of the sleeve is sealed and fixedly connected to the sealing flange, the buffer chamber is outside the borehole, and one end of the sleeve is sealed and connected to the sleeve through the sealing flange; the drill pipe passes through the buffer chamber, the sealing flange and the sleeve in sequence from the other end of the buffer chamber and extends into the borehole, and the inner wall of the buffer chamber is provided with a plurality of sealing components, one end of each sealing component is in contact with the surface of the drill pipe, and is used for sealing between the buffer chamber and the drill pipe;
[0009] The coal slag processor is provided with a dust filter structure inside, which divides the inside of the coal slag processor into a coal dust settling space and a gas extraction space. The coal slag processor is provided with an inlet, an extraction port and a slag outlet outside. The inlet is connected with the buffer chamber through a hose, and is used to transport the coal dust and gas in the buffer chamber to the coal dust settling space. The coal dust is blocked by the dust filter structure and remains in the coal dust settling space, and the gas enters the gas extraction space through the dust filter structure; the extraction port is connected with the underground gas extraction main pipe through the extraction pipeline 2, so that the gas in the gas extraction space is extracted by the underground gas extraction main pipe; the slag outlet is used to discharge the coal dust settled in the coal dust settling space;
[0010] A solenoid valve 1 is installed at the extraction port, which is used to control the connection between the gas extraction space and the underground gas extraction main pipe; solenoid valve 2 and solenoid valve 4 are respectively installed at both ends of the water injection pipe, which are used to control the connection between the three-way pipe and the water pump; a solenoid valve 3 is installed on the extraction pipeline 1, which is used to control the connection between the three-way pipe and the underground gas extraction main pipe; the buffer chamber is provided with a sensor group 1, which is used to monitor the gas concentration and gas pressure in the buffer chamber; the gas extraction space is provided with a sensor group 2, which is used to monitor the gas concentration and gas pressure in the gas extraction space; the central processor is connected to sensor group 1 and sensor group 2 through a data transmission line, which is used to receive real-time monitoring data fed back by sensor group 1 and sensor group 2. After the central processor analyzes and processes the monitoring data, it transmits instructions through the instruction output line to control the opening and closing of solenoid valve 1, solenoid valve 2, solenoid valve 3 and solenoid valve 4 and the start and stop of the water pump.
[0011] Furthermore, the slag processor is fixed on the tunnel floor through a bracket, which is convenient for installation and fixing.
[0012] Furthermore, the coal slag processor is provided with a window for observing the deposition of coal dust in the coal dust settling space, and the slag outlet is provided with a valve for regularly opening the valve to discharge the coal dust in the coal dust settling space according to the situation observed in the window.
[0013] Furthermore, the dust filtering structure is a filter screen.
[0014] Furthermore, the sealing component is made of antistatic rubber material, which not only has a better sealing effect but also a longer service life.
[0015] Furthermore, the sensor group 1 and the sensor group 2 are both composed of a gas concentration sensor and a gas pressure sensor.
[0016] Furthermore, there are multiple water outlets, which are evenly distributed on the drill bit, which can not only ensure the stability of water injection, but also achieve better gas extraction effect when the water outlets are used as gas extraction ports in the later stage.
[0017] The working method of the underground drilling anti-blowout hole device based on quick gas extraction at the bottom of the hole comprises the following specific steps:
[0018] A. Device installation: Before drilling, drill a certain distance near the hole opening at the desired drilling location and expand the hole appropriately to form a sealing section. Then install a sealing device in the sealing section. After the sleeve and the sealing section are sealed and fixed, use a hose to connect the sealing device and the coal slag processor, and connect the water pump and the underground gas extraction main pipe to the three-way pipe; and set the gas concentration threshold and gas pressure threshold in the buffer chamber in the central processor, and the gas concentration threshold and gas pressure threshold in the coal slag processor;
[0019] B. Drilling operation: Turn on the water pump and open solenoid valve 2 and solenoid valve 4, solenoid valve 1 and solenoid valve 3 are in the closed state, and water is injected into the borehole through the water injection pipe, the tee pipe and the water outlet. Then start the drilling rig to make the drill rod pass through the sealing device and start drilling toward the coal seam. At this time, the coal dust and gas generated by the drilling enter the slag processor through the buffer chamber and the hose, and the coal dust is retained in the coal dust settling space through the dust filtering structure, and the gas enters the gas extraction space; observe the accumulation of coal slag and water inside the slag processor through the window. If there is too much accumulation of coal slag and water, open the valve to let the coal slag and water flow out from the slag outlet when gas extraction is not carried out;
[0020] C. Data transmission: During the drilling process, sensor group 1 monitors the gas concentration and gas pressure in the buffer chamber in real time, and sensor group 2 monitors the gas concentration and gas pressure in the slag processor in real time. Both of them feed back the monitoring data to the central processor;
[0021] D. Gas extraction and slag discharge: The central processor compares the feedback monitoring data with the set threshold value. If the monitoring data of sensor group 1 and sensor group 2 do not exceed the threshold value, it means that no blowhole has occurred. At this time, maintain the current drilling state and continue drilling; if only the monitoring data of sensor group 2 exceeds the gas concentration threshold and gas pressure threshold in the coal slag processor, it means that there is a lot of gas in the gas extraction space. At this time, the central controller controls the solenoid valve 1 to open, so that the underground gas extraction main pipe is connected to the gas extraction space to extract gas from the coal slag processor to avoid excessive gas pressure in the coal slag processor, which causes the gas flowing out of the borehole to accumulate in the buffer chamber until the monitoring data of sensor group 2 does not exceed the gas concentration threshold and gas pressure threshold in the coal slag processor, and the solenoid valve is closed. 1. If the monitoring data of sensor group 1 exceeds the gas concentration threshold and gas pressure threshold in the buffer chamber, and the monitoring data of sensor group 2 exceeds the gas concentration threshold and gas pressure threshold in the coal slag processor, it means that a blowhole phenomenon occurs. At this time, drilling is stopped, the central processor controls the water pump to stop, and closes solenoid valve 2 and solenoid valve 4, and opens solenoid valve 1 and solenoid valve 3 at the same time. At this time, the three-way pipe and the coal slag processor are connected to the underground gas extraction main pipe. At this time, the water outlet serves as the gas extraction port, and a part of the coal dust and gas in the bottom of the borehole enters the underground gas extraction main pipe through the drill pipe, the three-way pipe and the extraction pipeline 1; at the same time, another part of the coal dust and gas enters the coal slag processor through the buffer chamber, and the coal dust is separated from the gas so that the gas is extracted and enters the underground gas extraction main pipe;
[0022] E. Resume drilling: After the monitoring data of sensor group 1 and sensor group 2 do not exceed the corresponding threshold, the central processor controls to close solenoid valve 1 and solenoid valve 3 and open solenoid valve 2 and solenoid valve 4, and at the same time starts the water pump and the drilling rig to continue the drilling operation;
[0023] F. Continue drilling construction: Repeat steps B to E continuously during the drilling process until the drilling process is completed.
[0024] Furthermore, the gas concentration threshold in the buffer chamber and the gas concentration threshold in the slag processor are 1.5% and 0.75% respectively; the gas pressure threshold in the buffer chamber and the gas pressure threshold in the slag processor are both 1.5 times of the atmospheric pressure.
[0025] Compared with the prior art, the present invention adopts a combination of a drilling rig, a sealing device, a cinder processor, a water pump and a central processor, which has the following advantages:
[0026] 1. In the normal drilling process without blowhole, the water outlet on the drill bit continuously injects water into the borehole, so that the coal dust and coal slag generated during drilling are mixed with water and discharged from the borehole, and enter the coal slag processor from the buffer chamber, and at the same time, part of the gas also enters and is separated from the coal-water mixture; sensor group 1 and sensor group 2 respectively monitor the gas concentration and pressure in the buffer chamber and the coal slag processor and feed back to the central processor, and the central processor can judge whether a blowhole occurs and whether it is necessary to extract gas from the coal slag processor based on the feedback data; when it is judged that a blowhole occurs, the water injection process is automatically stopped, and the water injection port is used as a gas extraction port to extract gas from the bottom of the hole, and gas is extracted from the source of the blowhole. At the same time, the buffer chamber and the coal slag processor also extract gas synchronously, and the two cooperate with each other and the whole process is fully automated, ultimately ensuring that a blowhole does not cause a gas over-limit accident.
[0027] 2. The sleeve of the sealing device in the present invention is sealed and fixed to the sealing section, so that the gas inside the borehole can only enter the buffer chamber for a certain buffering when it is discharged, and the drill rod and the buffer chamber are sealed and contacted by multiple sealing components, so as to ensure that the gas remains in the buffer chamber and enters the cinder processor through the hose, which greatly reduces the escape of gas from the borehole orifice and realizes effective sealing of the borehole orifice. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0029] Figure 2 It is a schematic diagram of the structure of the sealing device in the present invention.
[0030] In the figure: 1-coal seam roof, 2-water outlet, 3-drill rod, 4-drill hole, 5-sealing section, 6-sealing device, 61-sealing flange, 62-sleeve, 63-buffer chamber, 7-coal seam bottom plate, 8-drill bit, 9-coal seam, 10-hose, 11-bracket, 12-sealing assembly, 13-sensor group 1, 14-dust filter structure, 15-coal slag processor, 151-inlet, 152-extraction port, 153 -slag outlet, 16-sensor group 2, 17-window, 18-valve, 19-solenoid valve 1, 20-water pump, 21-drilling rig, 22-solenoid valve 2, 23-water injection pipe, 24-tee pipe, 25-extraction pipeline 1, 26-solenoid valve 3, 27-solenoid valve 4, 28-extraction pipeline 2, 29-central processor, 30-data transmission line, 31-command output line, 32-underground gas extraction main pipe. DETAILED DESCRIPTION
[0031] The present invention will be further described below.
[0032] like Figure 1As shown, a downhole drilling blowout prevention device based on quick gas extraction at the bottom of the hole comprises a drilling rig, a sealing device 6, a cinder processor 15, a water pump 20 and a central processor 29;
[0033] The drilling rig is provided with a drill rod 3, one end of the drill rod 3 is provided with a drill bit 8, a through hole is provided inside the drill rod 3 along the axial direction, a water outlet 2 is provided on the drill bit 8, and the water outlet 2 is connected with one end of the through hole, and a tee pipe 24 is provided at the other end of the drill rod 3, and the tee pipe 24 connects the through hole with the underground gas extraction main pipe 32 and the water pump 20 respectively through the extraction pipeline 25 and the water injection pipe 23, wherein the underground gas extraction main pipe 32 is used to extract gas from the bottom of the borehole through the through hole and the water outlet when spraying; the water pump is used to inject water into the bottom of the borehole through the through hole and the water outlet 2 when drilling;
[0034] like Figure 2 As shown, the sealing device 6 includes a sealing flange 61, a sleeve 62 and a buffer chamber 63. The sealing flange 61 is fixed at the borehole opening. The sleeve 62 extends into the borehole 4 and one end of the sleeve 62 is sealed and fixedly connected to the sealing flange 61. The buffer chamber 63 is outside the borehole 4 and one end of the sleeve 62 is sealed and connected to the sleeve 62 through the sealing flange 61. The drill rod 3 passes through the buffer chamber 63, the sealing flange 61 and the sleeve 62 from the other end of the buffer chamber 63 and extends into the borehole 4. The inner wall of the buffer chamber 63 is provided with a plurality of sealing components 12. One end of each sealing component 12 contacts the surface of the drill rod 3 and is used for sealing between the buffer chamber 63 and the drill rod 3. The sealing component 20 is made of antistatic rubber material. This material not only has a better sealing effect, but also has a longer service life.
[0035] The slag processor 15 is fixed on the bottom plate of the tunnel by a bracket 11. This makes it easy to install and fix; a dust filter structure 14 is provided inside the slag processor 15, and the dust filter structure 14 divides the inside of the slag processor 15 into a coal dust settling space and a gas extraction space, and the dust filter structure 14 is a filter net; an inlet 151, an extraction port 152 and a slag outlet 153 are provided outside the slag processor 15, and the inlet 151 is connected to the buffer chamber 63 through a hose 10, and is used to transport the coal dust and gas in the buffer chamber 63 to the coal dust settling space, and the coal dust is blocked by the dust filter structure 14 and remains in the coal dust settling space, and the gas enters the gas extraction space through the dust filter structure 14; the extraction port 152 is connected to the underground gas extraction main pipe 32 through the extraction pipeline 28, so that the gas in the gas extraction space is extracted by the underground gas extraction main pipe 32; the slag outlet 153 is used to discharge the coal dust settled in the coal dust settling space;
[0036] The extraction port 152 is provided with a solenoid valve 19 for controlling the connection between the gas extraction space and the underground gas extraction main pipe 32; the two ends of the water injection pipe 23 are provided with a solenoid valve 22 and a solenoid valve 4 27 for controlling the connection between the three-way pipe 24 and the water pump 20; the extraction pipeline 25 is provided with a solenoid valve 3 26 for controlling the connection between the three-way pipe 24 and the underground gas extraction main pipe 32; the buffer chamber 63 is provided with a sensor group 13 for monitoring the gas concentration and gas pressure in the buffer chamber 63; the gas extraction space is provided with a sensor group 2 16 for monitoring the gas concentration and gas pressure in the buffer chamber 63; the gas extraction space is provided with a sensor group 17 for monitoring the gas concentration and gas pressure in the buffer chamber 63; the gas extraction space is provided with a sensor group 18 for monitoring the gas concentration and gas pressure in the buffer chamber 63; the gas extraction space is provided with a sensor group 19 ... The gas concentration and gas pressure in the extraction space; the central processor 29 is connected to the sensor group 13 and the sensor group 2 16 through the data transmission line 30, and is used to receive the real-time monitoring data fed back by the sensor group 13 and the sensor group 2 16. After the central processor 29 analyzes and processes the monitoring data, it transmits instructions through the instruction output line 31 to control the opening and closing of the solenoid valve 19, the solenoid valve 22, the solenoid valve 3 26 and the solenoid valve 4 27 and the start and stop of the water pump 20; the sensor group 13 and the sensor group 2 16 are both composed of a gas concentration sensor and a gas pressure sensor.
[0037] As an improvement of the present invention, the coal slag processor 15 is provided with a window 17 for observing the deposition of coal dust in the coal dust settling space, and the slag outlet 153 is provided with a valve 18 for regularly opening the valve 18 according to the observation situation of the window 17 to discharge the coal dust in the coal dust settling space.
[0038] As another improvement of the present invention, there are multiple water outlets 2, and the multiple water outlets 2 are evenly distributed on the drill bit 8. This can not only ensure the stability of water injection, but also obtain better gas extraction effect when the water outlet 2 is used as a gas extraction port in the later stage.
[0039] The working method of the underground drilling anti-blowout hole device based on quick gas extraction at the bottom of the hole comprises the following specific steps:
[0040] A. Installation of the device: Before drilling, drill a certain distance near the hole opening at the desired drilling position and expand the hole appropriately to form a sealing section 5, then install the sealing device 6 on the sealing section 5, and after the sleeve 62 is sealed and fixed to the sealing section 5, use the hose 10 to connect the sealing device 6 and the coal slag processor 15, and connect the water pump 20 and the underground gas extraction main pipe 32 to the three-way pipe 24; and set the gas concentration threshold in the buffer chamber 63 and the gas concentration threshold in the coal slag processor 15 in the central processor 29 to 1.5% and 0.75% respectively; the gas pressure threshold in the buffer chamber 63 and the gas pressure threshold in the coal slag processor 15 are both 1.5 times the atmospheric pressure;
[0041] B. Drilling operation: Turn on the water pump 20 and open the solenoid valve 2 22 and the solenoid valve 4 27. The solenoid valve 1 19 and the solenoid valve 3 26 are in the closed state. Water is injected into the borehole 4 through the water injection pipe 23, the three-way pipe 24 and the water outlet 2. Then the drilling rig is started to make the drill rod 3 pass through the sealing device 6 and start the drilling operation 4 toward the coal seam 9. At this time, the coal dust and gas generated by the borehole 4 enter the slag processor 15 through the buffer chamber 63 and the hose 10, and the coal dust is left in the coal dust settling space through the dust filtering structure 14, and the gas enters the gas extraction space; observe the accumulation of coal slag and water in the coal slag processor 15 through the window 17. If the coal slag and water accumulate too much, open the valve 18 when gas extraction is not performed to allow the coal slag and water to flow out from the slag outlet;
[0042] C. Data transmission: During the drilling process, the sensor group 13 monitors the gas concentration and gas pressure in the buffer chamber 63 in real time, and the sensor group 2 16 monitors the gas concentration and gas pressure in the slag processor 15 in real time, and both feed back the monitoring data to the central processor 29;
[0043] D. Gas extraction and slag discharge: The central processor 29 compares the feedback monitoring data with the set threshold value. If the monitoring data of both sensor group 13 and sensor group 2 16 do not exceed the threshold value, it means that no blowhole has occurred. At this time, the current drilling state is maintained and drilling is continued; if only the monitoring data of sensor group 2 16 exceeds the gas concentration threshold and gas pressure threshold in the coal slag processor 15, it means that there is a lot of gas in the gas extraction space. At this time, the central controller 29 controls the solenoid valve 19 to open, so that the underground gas extraction main pipe 32 is connected to the gas extraction space to extract gas from the inside of the coal slag processor 15, so as to avoid excessive gas pressure in the coal slag processor 15, which causes the gas flowing out of the borehole to accumulate in the buffer chamber 63, until the monitoring data of sensor group 2 16 does not exceed the gas concentration threshold and gas pressure threshold in the coal slag processor 15, and the solenoid valve 19 is closed; if the sensor If the monitoring data of the sensor group 13 exceeds the gas concentration threshold and the gas pressure threshold in the buffer chamber 63, and the monitoring data of the sensor group 2 16 exceeds the gas concentration threshold and the gas pressure threshold in the coal slag processor 15, it means that a blowhole phenomenon occurs. At this time, drilling is stopped, the central processor 29 controls the water pump 20 to stop, and closes the solenoid valve 22 and the solenoid valve 4 27, and opens the solenoid valve 19 and the solenoid valve 3 26. At this time, the three-way pipe 24 and the coal slag processor 15 are connected to the underground gas extraction main pipe 32. At this time, the water outlet 2 serves as the gas extraction port, and a part of the coal dust and gas in the bottom of the borehole enters the underground gas extraction main pipe 32 through the drill pipe 3, the three-way pipe 24 and the extraction pipeline 1 25; at the same time, another part of the coal dust and gas enters the coal slag processor 15 through the buffer chamber 63, and the coal dust is separated from the gas so that the gas is extracted and enters the underground gas extraction main pipe 32;
[0044] E. Resume drilling: After the monitoring data of sensor group 1 13 and sensor group 2 16 do not exceed the corresponding threshold, the central processor 29 controls the closing of solenoid valve 1 19 and solenoid valve 3 26 and the opening of solenoid valve 2 22 and solenoid valve 4 27, and at the same time starts the water pump 20 and the drilling rig to continue the drilling operation;
[0045] F. Continue drilling construction: Continue to repeat steps B to E during the drilling process until the construction process of the drilling hole 4 is completed.
[0046] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A device for preventing blowout holes in underground drilling based on quick gas extraction from the bottom of the hole, comprising a drilling rig, a drill rod provided on the drilling rig, a drill bit provided at one end of the drill rod, and characterized in that: Also included are sealing devices, cinder handlers, water pumps and central processors; A through hole is axially arranged inside the drill pipe, a water outlet is arranged on the drill bit, and the water outlet is connected to one end of the through hole, and a tee is arranged at the other end of the drill pipe, and the tee connects the through hole to the underground gas extraction main pipe and the water pump respectively through the extraction pipeline 1 and the water injection pipe, wherein the underground gas extraction main pipe is used to extract gas from the bottom of the borehole through the through hole and the water outlet when spraying the hole; the water pump is used to inject water into the bottom of the borehole through the through hole and the water outlet when drilling; The sealing device comprises a sealing flange, a sleeve and a buffer chamber, wherein the sealing flange is fixed at the borehole opening, the sleeve extends into the borehole and one end of the sleeve is sealed and fixedly connected to the sealing flange, the buffer chamber is outside the borehole, and one end of the sleeve is sealed and connected to the sleeve through the sealing flange; the drill pipe passes through the buffer chamber, the sealing flange and the sleeve in sequence from the other end of the buffer chamber and extends into the borehole, and the inner wall of the buffer chamber is provided with a plurality of sealing components, one end of each sealing component is in contact with the surface of the drill pipe, and is used for sealing between the buffer chamber and the drill pipe; The coal slag processor is provided with a dust filter structure inside, which divides the inside of the coal slag processor into a coal dust settling space and a gas extraction space. The coal slag processor is provided with an inlet, an extraction port and a slag outlet outside. The inlet is connected with the buffer chamber through a hose, and is used to transport the coal dust and gas in the buffer chamber to the coal dust settling space. The coal dust is blocked by the dust filter structure and remains in the coal dust settling space, and the gas enters the gas extraction space through the dust filter structure; the extraction port is connected with the underground gas extraction main pipe through the extraction pipeline 2, so that the gas in the gas extraction space is extracted by the underground gas extraction main pipe; the slag outlet is used to discharge the coal dust settled in the coal dust settling space; A solenoid valve 1 is installed at the extraction port, which is used to control the connection between the gas extraction space and the underground gas extraction main pipe; solenoid valve 2 and solenoid valve 4 are respectively installed at both ends of the water injection pipe, which are used to control the connection between the three-way pipe and the water pump; a solenoid valve 3 is installed on the extraction pipeline 1, which is used to control the connection between the three-way pipe and the underground gas extraction main pipe; the buffer chamber is provided with a sensor group 1, which is used to monitor the gas concentration and gas pressure in the buffer chamber; the gas extraction space is provided with a sensor group 2, which is used to monitor the gas concentration and gas pressure in the gas extraction space; the central processor is connected to sensor group 1 and sensor group 2 through a data transmission line, which is used to receive real-time monitoring data fed back by sensor group 1 and sensor group 2. After the central processor analyzes and processes the monitoring data, it transmits instructions through the instruction output line to control the opening and closing of solenoid valve 1, solenoid valve 2, solenoid valve 3 and solenoid valve 4 and the start and stop of the water pump.
2. The downhole drilling blowout prevention device based on quick gas extraction from the bottom of the hole according to claim 1 is characterized in that: The cinder processor is fixed on the tunnel floor through a bracket.
3. The downhole drilling blowout prevention device based on quick gas extraction from the bottom of the hole according to claim 1 is characterized in that: The coal slag processor is provided with a window for observing the deposition of coal dust in the coal dust settling space, and the slag outlet is provided with a valve for regularly opening the valve to discharge the coal dust in the coal dust settling space according to the situation observed in the window.
4. The downhole drilling blowout prevention device based on quick gas extraction from the bottom of the hole according to claim 1 is characterized in that: The dust filtering structure is a filter screen.
5. The downhole drilling blowout prevention device based on quick gas extraction from the bottom of the hole according to claim 1 is characterized in that: The sealing component is made of antistatic rubber material.
6. The downhole drilling blowout prevention device based on quick gas extraction from the bottom of the hole according to claim 1 is characterized in that: The sensor group 1 and the sensor group 2 are both composed of a gas concentration sensor and a gas pressure sensor.
7. The downhole drilling blowout prevention device based on quick gas extraction from the bottom of the hole according to claim 1 is characterized in that: There are multiple water outlets, and the multiple water outlets are evenly distributed on the drill bit.
8. A working method of a downhole drilling blowout prevention hole device based on quick gas extraction at the bottom of the hole according to any one of claims 1 to 7, characterized in that: The specific steps are: A. Device installation: Before drilling, drill a certain distance near the hole opening at the desired drilling location and expand the hole appropriately to form a sealing section. Then install a sealing device in the sealing section. After the sleeve and the sealing section are sealed and fixed, use a hose to connect the sealing device and the coal slag processor, and connect the water pump and the underground gas extraction main pipe to the three-way pipe; and set the gas concentration threshold and gas pressure threshold in the buffer chamber in the central processor, and the gas concentration threshold and gas pressure threshold in the coal slag processor; B. Drilling operation: Turn on the water pump and open solenoid valve 2 and solenoid valve 4, solenoid valve 1 and solenoid valve 3 are in the closed state, and water is injected into the borehole through the water injection pipe, the tee pipe and the water outlet. Then start the drilling rig to make the drill rod pass through the sealing device and start drilling toward the coal seam. At this time, the coal dust and gas generated by the drilling enter the slag processor through the buffer chamber and the hose, and the coal dust is retained in the coal dust settling space through the dust filtering structure, and the gas enters the gas extraction space; observe the accumulation of coal slag and water inside the slag processor through the window. If there is too much accumulation of coal slag and water, open the valve to let the coal slag and water flow out from the slag outlet when gas extraction is not carried out; C. Data transmission: During the drilling process, sensor group 1 monitors the gas concentration and gas pressure in the buffer chamber in real time, and sensor group 2 monitors the gas concentration and gas pressure in the slag processor in real time. Both of them feed back the monitoring data to the central processor; D. Gas extraction and slag discharge: The central processor compares the feedback monitoring data with the set threshold value. If the monitoring data of sensor group 1 and sensor group 2 do not exceed the threshold value, it means that no blowhole has occurred. At this time, maintain the current drilling state and continue drilling; if only the monitoring data of sensor group 2 exceeds the gas concentration threshold and gas pressure threshold in the coal slag processor, it means that there is a lot of gas in the gas extraction space. At this time, the central controller controls the solenoid valve 1 to open, so that the underground gas extraction main pipe is connected to the gas extraction space to extract gas from the coal slag processor to avoid excessive gas pressure in the coal slag processor, which causes the gas flowing out of the borehole to accumulate in the buffer chamber until the monitoring data of sensor group 2 does not exceed the gas concentration threshold and gas pressure threshold in the coal slag processor, and the solenoid valve is closed.
1. If the monitoring data of sensor group 1 exceeds the gas concentration threshold and gas pressure threshold in the buffer chamber, and the monitoring data of sensor group 2 exceeds the gas concentration threshold and gas pressure threshold in the coal slag processor, it means that a blowhole phenomenon occurs. At this time, drilling is stopped, the central processor controls the water pump to stop, and closes solenoid valve 2 and solenoid valve 4, and opens solenoid valve 1 and solenoid valve 3 at the same time. At this time, the three-way pipe and the coal slag processor are connected to the underground gas extraction main pipe. At this time, the water outlet serves as the gas extraction port, and a part of the coal dust and gas in the bottom of the borehole enters the underground gas extraction main pipe through the drill pipe, the three-way pipe and the extraction pipeline 1; at the same time, another part of the coal dust and gas enters the coal slag processor through the buffer chamber, and the coal dust is separated from the gas so that the gas is extracted and enters the underground gas extraction main pipe; E. Resume drilling: After the monitoring data of sensor group 1 and sensor group 2 do not exceed the corresponding threshold, the central processor controls to close solenoid valve 1 and solenoid valve 3 and open solenoid valve 2 and solenoid valve 4, and at the same time starts the water pump and the drilling rig to continue the drilling operation; F. Continue drilling construction: Repeat steps B to E continuously during the drilling process until the drilling process is completed.
9. The working method according to claim 8, characterized in that: The gas concentration threshold in the buffer chamber and the gas concentration threshold in the coal slag processor are 1.5% and 0.75% respectively; the gas pressure threshold in the buffer chamber and the gas pressure threshold in the coal slag processor are both 1.5 times the atmospheric pressure.
Citation Information
Cited By
Totally-closed water seal type blowout prevention hole device
CN119288373A
Blowout preventer for coal mine drilling orifice
CN121497259A