Backfilling construction method and structure for temporary contact channel of double-track tunnel
Through the technology of earth and stone outsourcing concrete mixed backfilling, the problems of high backfilling cost and low construction efficiency of temporary communication channels in tunnel projects are solved. The integrity and strength of the backfill body are achieved, cost is saved, construction efficiency is improved, and tunnel construction is optimized.
Patent Information
- Application Number
- CN202410882541.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-03
- Publication Date
- 2024-10-08
AI Technical Summary
Backfilling of temporary communication channels in existing tunnel projects is costly, inefficient, and requires expensive concrete temperature control.
The method of mixed backfilling with concrete wrapped around the earthwork is used to determine the position of the retaining wall in the communication channel, backfill the earthwork and reserve a grouting pipe on the retaining wall, use grouting technology to fill the remaining space, and pour a dense concrete layer at the interface.
It achieves the integrity and strength of the backfill body, saves project costs, reduces concrete temperature control costs, improves construction efficiency, shortens the construction period, and optimizes the tunnel construction organization.
Smart Images

Figure CN118745918A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tunnel engineering, and in particular relates to a backfill construction method and structure for a temporary communication channel in a double-track tunnel. Background Art
[0002] Shield tunnel construction is safe, economical and fast, and has been widely used in urban subway projects. As an important auxiliary project of shield tunnel construction, the construction of communication channels has also attracted more and more attention. Many tunnels adopt a double-line layout, and communication channels play an important role in construction ventilation, material transportation, and temporary escape. Some temporary communication channels are set up during the construction period to increase the working surface, and the temporary communication channels need to be backfilled during the operation period. In existing projects, the backfilling of temporary communication channels generally adopts the concrete backfilling method, but the cost of single concrete backfilling is often high, and the curing temperature needs to be controlled during the backfill concrete curing process, which results in high project cost and slow construction efficiency. Summary of the invention
[0003] The purpose of the present invention is to provide a backfill construction method and structure for a temporary connecting channel of a double-track tunnel, which adopts earthwork and concrete mixed backfill to ensure the integrity and strength of the backfill body, save project costs, improve construction efficiency, and save construction time.
[0004] The present invention is achieved through the following technical solutions:
[0005] A double-track tunnel temporary communication channel backfill construction method, comprising the following steps:
[0006] Determine the location of the retaining wall and backfill within the communication channel;
[0007] Backfill earth and stone to a preset height in the backfill location;
[0008] Construct a concrete retaining wall at the retaining wall location, and reserve several grouting pipes on the top of the concrete retaining wall;
[0009] Insert multiple anchor rods into the concrete retaining wall;
[0010] The remaining space at the backfill position is backfilled and grouted through a number of grouting pipes;
[0011] Pour concrete at the interface between the connecting channel and the tunnel and compact it.
[0012] Furthermore, the step of constructing a concrete retaining wall at the retaining wall position includes:
[0013] Lay a sand and gravel layer at the retaining wall location and compact it;
[0014] Install steel bars and formwork at the retaining wall location, and then carry out cast-in-place construction of the concrete retaining wall.
[0015] Furthermore, in the step of backfilling and grouting the remaining space at the backfill position, the slurry used for backfilling and grouting is cement slurry, and the water-cement ratio is 0.4-0.6.
[0016] Furthermore, in the step of backfilling and grouting the remaining space at the backfill position, the backfilling and grouting adopts the bottom hole grouting method, and the grouting pressure is not less than 0.2MPa.
[0017] Furthermore, a drainage pipe is provided on the concrete retaining wall.
[0018] The present invention also provides a backfill structure for a temporary connecting channel of a double-track tunnel, comprising two concrete retaining walls respectively arranged at both ends of the connecting channel, a plurality of grouting pipes being penetrated through the top of the concrete retaining walls, an earthwork layer being arranged and filled between the two concrete retaining walls, a first concrete layer being cast between the earthwork layer and the connecting channel, a plurality of anchor rods inserted into the earthwork layer or the first concrete layer being arranged on the concrete retaining walls, a second concrete layer being arranged on the side of the concrete retaining wall away from the earthwork layer, and the second concrete layer being respectively connected to the connecting channel and the tunnel.
[0019] Compared with the prior art, the beneficial effects of the present invention are as follows: earth and stone are used in the lower part of the connecting channel, and concrete is wrapped around the earth and stone for mixed backfilling, so that the integrity and strength of the backfill body in the connecting channel can be ensured, which not only utilizes the waste earth and stone of the project, thus saving the project cost, but also reduces the cost of temperature control of large-volume concrete, improves construction efficiency, and saves construction period; the present invention can realize the rapid backfilling of temporary connecting channels during the construction process, thereby optimizing the tunnel construction organization, reducing labor intensity, and realizing standardized operations and safe and civilized construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a flowchart of the steps of the backfill construction method of the temporary communication channel of the double-track tunnel of the present invention;
[0021] Figure 2 It is a structural schematic diagram of the temporary communication channel backfill structure of the double-track tunnel of the present invention;
[0022] Figure 3 It is a cross-sectional view of the backfill structure of the temporary communication channel of the double-track tunnel of the present invention.
[0023] In the figure, 1-concrete retaining wall, 2-grouting pipe, 3-earth and stone layer, 4-first concrete layer, 5-anchor rod, 6-second concrete layer, 7-tunnel, 8-communication passage. DETAILED DESCRIPTION
[0024] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0025] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0026] It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. At the same time, in the description of the present invention, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.
[0027] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0028] In the description of the present invention, it should be noted that the terms "upper", "lower", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, or are directions or positional relationships in which the product of the invention is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.
[0029] See also Figure 1 , Figure 2 and Figure 3 , Figure 1This is a flowchart of the steps of the backfill construction method of the temporary communication channel of the double-track tunnel of the present invention. Figure 2 This is a schematic diagram of the structure of the temporary communication channel backfill structure of the double-track tunnel of the present invention. Figure 3 A method for backfilling a temporary communication channel in a double-track tunnel comprises the following steps:
[0030] S1. Determine the position of the retaining wall and the backfill position within the range of the communication channel 8;
[0031] S2. Backfill earth and stone to a preset height in the backfill position;
[0032] S3, constructing a concrete retaining wall 1 at the retaining wall position, and reserving a number of grouting pipes 2 on the top of the concrete retaining wall 1;
[0033] S4, inserting a plurality of anchor rods 5 on the concrete retaining wall 1;
[0034] S5, backfilling and grouting the remaining space at the backfill position through a plurality of grouting pipes 2;
[0035] S6. Pour concrete at the interface between the connecting passage 8 and the tunnel 7 and compact it.
[0036] In the above step S1, the construction site is first cleaned to ensure that there are no debris and obstacles, and the retaining wall position is positioned in the communication channel 8 to determine the two retaining wall positions in the communication channel 8. The area between the two retaining wall positions is the backfill position.
[0037] In the above step S2, the earth and stone that need to be discarded in the project are prepared, and the prepared earth and stone are backfilled to the backfill position, wherein the height of the backfill earth and stone can be determined according to the actual height of the communication channel 8, and generally a 1.8m to 2m space is reserved for the upper supply part of the communication channel 8, that is, the distance between the top of the backfill earth and stone and the top of the communication channel 8 is 1.8m to 2m. The earth and stone are backfilled in layers, and the thickness of each backfill layer does not exceed 1m. The earth and stone can be backfilled manually or by small machinery to form an earth and stone layer 3. In the process of backfilling in layers, the earth and stone can be compacted by vibration impact if conditions permit.
[0038] In the above step S3, concrete retaining walls 1 are cast in place at two retaining wall positions, and when casting the concrete retaining wall 1, a plurality of steel pipes are pre-buried on the top of the concrete retaining wall 1 as grouting pipes 2 for grouting the backfill position. The length of the steel pipe can be selected to be 2m. Furthermore, a drain pipe is provided on the concrete retaining wall 1 for drainage. A drain hole can be provided every 2 meters in the vertical direction. The drain pipe can be a PVC pipe, and the pipe diameter is usually 100mm.
[0039] Further, in step S3, the step of constructing the concrete retaining wall 1 at the retaining wall position includes:
[0040] S31, laying a gravel layer at the bottom of the retaining wall and compacting it;
[0041] S32. Install steel bars and formwork at the retaining wall location, and then perform cast-in-place construction of the concrete retaining wall 1.
[0042] In the above steps S31 to S32, when constructing the concrete retaining wall 1, a gravel layer is first laid at the retaining wall position and compacted. The gravel layer can increase the bearing capacity, transfer the load of the concrete retaining wall 1 to the foundation, and prevent rain from softening the concrete retaining wall 1. Then, install the steel bars and the vertical formwork according to the design requirements, and then pour concrete into the formwork to ensure that the concrete fully fills the groove, and use a vibrator to remove air bubbles, level the concrete surface, and perform preliminary maintenance to complete the construction of the concrete retaining wall 1. The concrete poured in the concrete retaining wall 1 can be C25 concrete.
[0043] In the above step S4, multiple anchor rods 5 are installed on the concrete retaining wall 1. The anchor rods 5 can be mortar anchor rods 5. The installation position and spacing of the anchor rods 5 can be determined according to actual conditions. In this embodiment, the row spacing (longitudinal direction) of the anchor rods 5 is 2m, and the circumferential spacing is 1.5m to 2m.
[0044] In the above step S5, the remaining space of the backfill position is backfilled and grouted through a plurality of grouting pipes 2, so that the cement slurry wraps the earthwork layer 3 to form a first concrete layer 4. Thus, by using earthwork at the bottom of the connecting channel 8 and mixing concrete outside the earthwork for backfilling, the integrity and strength of the backfill body in the connecting channel 8 can be guaranteed, which not only utilizes the waste earthwork of the project and saves the project cost, but also reduces the cost of temperature control of large-volume concrete, improves construction efficiency, and saves construction period. Further, the backfill grouting adopts the bottom hole grouting method, and the grouting pipe is inserted to about 50mm from the bottom of the hole, and is gradually pulled out with the injection of cement slurry. The grouting pressure should be not less than 0.2MPa. Further, the slurry used for backfill grouting is cement slurry, and the water-cement ratio is 0.4-0.6.
[0045] In the above step S6, concrete backfill is performed at the interface between the communication channel 8 and the tunnel 7. The concrete is 30m 3 / h concrete pump is pumped into the warehouse, and the inserted vibrator is vibrated and compacted, and the corners connected to the communication channel 8 are sprayed with C25 concrete to backfill the interface between the communication channel 8 and the tunnel 7 to form the first concrete layer 6. The tunnel lining is repaired by the first concrete layer 6, thereby completing the backfill construction of the temporary communication channel 8. Furthermore, in order to ensure that there is no water seepage at the connection between the first concrete layer 6 and the tunnel 7, a rubber water stop can be set at the connection between the tunnel 7 and the first concrete layer 6, and then the construction of the first concrete layer 6 is carried out.
[0046] Corresponding to the above method embodiments, the present invention also provides a backfill structure for a temporary communication channel in a double-track tunnel. The above-mentioned backfill construction method for the temporary communication channel in a double-track tunnel is adopted. The backfill structure for the temporary communication channel in a double-track tunnel includes two concrete retaining walls 1 respectively arranged at both ends of the communication channel 8. A plurality of grouting pipes 2 are penetrated through the top of the concrete retaining wall 1. An earthwork layer 3 is arranged between the two concrete retaining walls 1. A first concrete layer 4 is cast between the earthwork layer 3 and the communication channel 8. A plurality of anchor rods 5 inserted into the earthwork layer 3 or the first concrete layer 4 are provided on the concrete retaining wall 1. A first concrete layer 6 is provided on the side of the concrete retaining wall 1 away from the earthwork layer 3. The first concrete layer 6 is respectively connected to the communication channel 8 and the tunnel 7.
[0047] By adopting the above technical solution, the earth and stone and the concrete mixed backfill outside the earth and stone are used in the connecting channel 8, so as to ensure the integrity and strength of the backfill body in the connecting channel 8. It not only utilizes the waste earth and stone of the project, saves the project cost, but also reduces the cost of temperature control of large-volume concrete, improves construction efficiency, and saves construction period; at the same time, the temporary connecting channel 8 can be quickly backfilled during the construction process, thereby optimizing the construction organization of the tunnel 7, reducing labor intensity, and realizing standardized operation and safe and civilized construction.
[0048] In one embodiment, the concrete retaining wall 1 includes a reinforced concrete layer and a sand and gravel layer arranged at the bottom of the reinforced concrete layer.
[0049] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Therefore, any simple modification, equivalent change and modification made to the above embodiment according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still fall within the scope of the technical solution of the present invention.
Claims
1. A backfill construction method for a temporary communication channel of a double-track tunnel, characterized in that: The following steps are involved: Determine the location of the retaining wall and backfill within the communication channel; Backfilling earth and stone to a preset height in the backfill position; Construct a concrete retaining wall at the retaining wall location, and reserve a number of grouting pipes at the top of the concrete retaining wall; Inserting a plurality of anchor rods on the concrete retaining wall; Backfilling and grouting the remaining space at the backfill position through a plurality of grouting pipes; Concrete is poured and compacted at the interface between the communication channel and the tunnel.
2. The double-track tunnel temporary communication channel backfill construction method according to claim 1 is characterized in that: The step of constructing a concrete retaining wall at the retaining wall position comprises: Laying a sand and gravel layer at the retaining wall position and compacting it; Reinforcement bars and formwork are installed at the retaining wall position, and then cast-in-place construction of the concrete retaining wall is carried out.
3. The double-track tunnel temporary communication channel backfill construction method according to claim 1 is characterized in that: In the step of backfilling and grouting the remaining space of the backfill position, the slurry used for backfilling and grouting is cement slurry, and the water-cement ratio is 0.4-0.
6.
4. The double-track tunnel temporary communication channel backfill construction method according to claim 1 is characterized in that: In the step of backfilling and grouting the remaining space at the backfill position, the backfilling and grouting adopts the bottom hole grouting method, and the grouting pressure is not less than 0.2MPa.
5. The double-track tunnel temporary communication channel backfill construction method according to claim 1, characterized in that: A drainage pipe is arranged on the concrete retaining wall.
6. A double-line tunnel temporary communication channel backfill structure, characterized in that: It includes two concrete retaining walls respectively arranged at both ends of the connecting channel, a plurality of grouting pipes are passed through the top of the concrete retaining walls, an earthwork layer is arranged between the two concrete retaining walls, a first concrete layer is poured between the earthwork layer and the connecting channel, a plurality of anchor rods inserted into the earthwork layer or the first concrete layer are arranged on the concrete retaining walls, a second concrete layer is arranged on the side of the concrete retaining wall away from the earthwork layer, and the second concrete layer is respectively connected to the connecting channel and the tunnel.