Construction quality risk evaluation method for railway tunnel engineering in complex mountainous area

Through the G1 weighting method and the matter-element extension model, a construction quality risk assessment model for complex mountainous railway tunnel projects is constructed, and the dependence and feedback relationships between factors are identified and analyzed, solving the problem that it is difficult to effectively identify and control construction quality risks with existing technologies. problems, provided improvement measures for high-risk factors, and improved construction quality risk management and control capabilities.

CN118747604APending Publication Date: 2024-10-08CHINA RAILWAY ERYUAN ENGINEERING GROUP CO LTD
View PDF 0 Cites 4 Cited by

Patent Information

Application Number
CN202411015123.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-10-08

AI Technical Summary

Technical Problem

The construction quality risk assessment method of complex mountainous railway tunnel projects is difficult to effectively identify and control. The existing methods cannot fully reflect the interdependence and feedback relationship between construction quality risk factors, and are difficult to meet the high standards and strict requirements for risk management and control of my country's complex mountainous railways. .

Method used

The G1 weighting method and matter-element extension model are used, combined with the Delphi expert consultation method and the entropy value method, to construct a matter-element extension model for tunnel engineering construction quality risk assessment. Through model calculation, the comprehensive correlation degree and risk of construction quality risk are obtained. levels and high-risk factors, revealing dependencies and feedback relationships between factors.

Benefits of technology

Help project managers to promptly grasp the causes of construction quality risks and propose improvement measures for high-risk factors, effectively providing reference for tunnel project construction quality risk management and control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118747604A_ABST
    Figure CN118747604A_ABST
Patent Text Reader

Abstract

The invention provides a complex mountainous area railway tunnel engineering construction quality risk evaluation method, which comprises the steps of forming an initial quality risk factor list based on an existing complex mountainous area railway tunnel engineering construction case; constructing a tunnel engineering construction quality risk index system by using a Delphi expert consultation method; weight empowerment is carried out on the quality risk indexes based on a standard deviation correction G1 empowerment method; by taking matter-element extension as a basic thought, a weight coefficient is determined by applying matter-element transformation and an entropy evaluation method, and a matter-element extension model for tunnel engineering construction quality risk evaluation is constructed. The comprehensive correlation degree of the tunnel engineering construction quality risks, the construction quality risk grade and the high-risk factors of the tunnel construction quality are obtained through model calculation, the relation problem of mutual dependence and feedback among the construction quality risk factors of the railway engineering in the complex mountainous area is revealed, and an important reference is provided for tunnel engineering construction quality risk management and control.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of railway engineering, and in particular to a method for risk assessment of construction quality of railway tunnel engineering in complex mountainous areas. Background Art

[0002] Due to the complex mountainous conditions and railway technical standards, tunnel engineering is the main engineering form of complex mountainous railways, and most of them are controlling projects. If the risk factors affecting the construction quality are not fully understood and control measures are not taken during the construction process, huge losses will be caused, which will bring risks to the construction quality management of railway tunnel engineering. In the research on the construction quality risk of railway tunnel engineering.

[0003] Foreign scholars have conducted some exploration, mainly based on risk theory to study tunnel costs and risk management criteria under uncertain factors. The relevant research provides a certain reference for the identification and prevention of construction quality risks of tunnel projects under complex construction environments, but it is mostly focused on construction safety risk assessment. Research on construction quality risks of complex mountain railway tunnel projects is extremely rare, which is difficult to meet the high standards and strict requirements for risk control put forward by my country's complex mountain railways.

[0004] At the same time, in the selection of risk assessment models, domestic and foreign scholars mostly use hierarchical analysis method, artificial neural network method, fuzzy comprehensive evaluation method, etc. for analysis. However, the construction quality risk factors of railway tunnel projects in complex mountainous areas are ambiguous and complex, and there is a relationship of mutual dependence and feedback between the factors. Using these methods alone cannot fully reflect the risk characteristics. Summary of the invention

[0005] The purpose of the present invention is to provide a method for evaluating the construction quality risk of railway tunnel projects in complex mountainous areas in view of the problems existing in the above-mentioned prior art. Combined with the tunnel construction quality risk evaluation index layer, the weight of the quality risk index is determined based on the G1 weighting method; the dynamic and complexity of the construction quality risk of railway tunnel projects in complex mountainous areas is fully considered, and the weight coefficient is determined by using the matter-element extension method and the entropy method to construct a matter-element extension model for the quality risk evaluation of tunnel projects. The comprehensive correlation degree of the quality risk of tunnel projects, the construction quality risk level and the high-risk factors of tunnel construction quality are calculated through the model. The relationship between the interdependence and feedback between the quality risk factors of railway projects in complex mountainous areas can be revealed, which is helpful for project managers to grasp the causes of the quality risk of tunnel projects in a timely manner, and propose improvement measures for personnel factors, management factors, technical factors and environmental factors for high-risk factors, providing an important reference for the quality risk control of tunnel projects.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is:

[0007] A method for risk assessment of construction quality of railway tunnel engineering in complex mountainous areas comprises the following steps:

[0008] S1. Based on the existing complex mountain railway tunnel construction cases, an initial list of quality risk factors is formed;

[0009] S2. Use the Delphi expert consultation method to build a tunnel engineering construction quality risk indicator system;

[0010] S3, weighting the quality risk indicators based on the G1 weighting method modified by standard deviation;

[0011] S4. Taking matter-element extension as the basic idea, applying matter-element transformation and entropy method, determining the weight coefficient, and constructing a matter-element extension model for tunnel engineering construction quality risk assessment.

[0012] S5. The model is used to calculate the comprehensive correlation of tunnel construction quality risks, the construction quality risk level and the high-risk factors of tunnel construction quality.

[0013] The present invention provides a method for evaluating the construction quality risk of a railway tunnel project in a complex mountainous area. The method comprises the following steps: forming an initial list of quality risk factors based on existing construction cases of railway tunnel projects in complex mountainous areas; constructing a quality risk index system for tunnel project construction by using the Delphi expert consultation method; determining the weight of the quality risk index based on the G1 weighting method in combination with the tunnel construction quality risk evaluation index layer; taking full account of the dynamics and complexity of the construction quality risk of railway tunnel projects in complex mountainous areas, taking matter-element extension as the basic idea, applying matter-element transformation and entropy value method to determine the weight coefficient, constructing a matter-element extension model for tunnel project construction quality risk evaluation, and calculating the comprehensive correlation of tunnel project construction quality risk, construction quality risk level and high-risk factors of tunnel construction quality through the model. The problem of the relationship between the interdependence and feedback of the construction quality risk factors of railway projects in complex mountainous areas can be revealed, which is helpful for project managers to grasp the causes of the formation of tunnel project construction quality risks in a timely manner, and proposes improvement measures for personnel factors, management factors, technical factors and environmental factors for high-risk factors, providing an important reference for the management and control of tunnel project construction quality risks.

[0014] Furthermore, in S1, the initial list of quality risk factors includes level 1 indicators and level 2 indicators, where level 2 indicators are sub-indicators of level 1 indicators; level 1 indicators are at least three of environmental factors, technical factors, management factors, material and equipment factors, and personnel factors.

[0015] Furthermore, in S2, the Delphi expert survey method was used to obtain experts' suggestions on the risk indicators of tunnel construction quality, and the degree of consistency between the initial risk list and the actual project was judged; based on the Likert scale method, the degree of consistency of the indicators was set and the corresponding scores were given. By calculating the average of the expert opinions and testing the consistency of the expert opinions, the statistical indicators of the expert advice data were obtained, and a tunnel construction quality evaluation index system was constructed.

[0016] Furthermore, in S2, the average of the expert opinions is calculated using formula (1):

[0017]

[0018] In formula (1), mj represents the number of experts for the jth indicator; Cij represents the score of the i-th expert for the j-th indicator; Mj represents the importance of the corresponding indicator; the degree of conformity between the indicator and the actual situation is judged by whether the average value of the expert's score for each indicator is greater than 4.

[0019] Furthermore, in S2, the standard for testing the degree of consistency of expert opinions is: the Kendall harmony coefficient ω is selected for consistency test. When the value is greater than 0.6, it is considered that the experts have reached a consensus.

[0020] Furthermore, in S3, the G1 weighting method weights the quality risk indicators. The specific steps are as follows:

[0021] S31, the order relationship of each indicator;

[0022] Assume x 1 ,x 2 ,...,x n The n dimensionless evaluation indicators of the scheme to be evaluated are ranked by experts according to the project characteristics and their own work experience. 1 , x 2 , ..., x n} selects the most important indicator as x′; experts select the most important indicator as x′ from the remaining n-1 indicators 2 ; Similarly, the expert selects the most important indicator from the remaining n-(k-1) indicators and marks it as x′ k ; After n-1 selections, the remaining index is labeled x′ n ; Determine the unique order relation x′ of the evaluation index set 1 >x′ 2 >…>x′ n .

[0023] S32, determine the importance of adjacent indicators;

[0024] Experts on evaluation index xk-1 With x k The importance ratio of k-1 / ω k The rational judgment is:

[0025]

[0026] x k-1 and x k The importance of r k The larger the value, the greater the importance.

[0027] S33, calculating weight;

[0028] According to experts, k The rational assignment of n The calculation formula is:

[0029]

[0030] ω k-1 =ω k r k (k=n,n-1,...2);

[0031] Suppose there are m (m ≥ 2) experts to judge n (n ≥ 3) indicators. Assume that the kth (k = 1, 2, ..., m) expert sorts all indicators according to the G1 method, and the weight of each indicator is Assume that the weight coefficient of the first expert is The aggregate weight for each indicator is:

[0032]

[0033] Assume that the opinions of all experts are equally important, that is, l =1 / m, and the weight of each indicator is the arithmetic mean of the weights obtained by each expert using the G1 method principle:

[0034]

[0035] Furthermore, in S4, a matter-element extension model for risk assessment of tunnel engineering construction quality is constructed. The specific steps are as follows:

[0036] S41, determine the evaluation feature set and risk level domain;

[0037] The tunnel construction quality risk studied is analyzed from two characteristics: the probability of occurrence of C1 risk and the degree of impact of the consequences of C2 risk. The risk feature set is expressed as:

[0038] C={c1,c2}={probability of risk occurrence, impact of consequences of risk occurrence}

[0039] Establish the tunnel engineering risk level domain according to the Technical Specifications for Risk Management of Railway Tunnel Engineering;

[0040] S42, determine the classical domain and the nodal domain;

[0041] First, construct the evaluation element R = (N, c, v), where N represents the subject of risk assessment; c1, c2, ..., cn are the n characteristics of the evaluation subject N; v1, v1, ..., vn are the corresponding values; its classical domain matrix is ​​calculated as:

[0042]

[0043] Among them, the evaluated subject N is divided into p levels, Rp represents the p-level risk classical domain object; N represents the p-th level of the risk assessment object; ci represents the main characteristic index of Np; v pi =(a pi ,b pi ) indicates that each characteristic index of N is in the value range of level p, which is called the classical domain;

[0044] The node domain is the value range of the corresponding characteristic index of all risk levels, and the node domain matter-element can be expressed as:

[0045]

[0046] Among them, U is the overall risk level; ci represents the characteristic index;; v Ui =(a Ui ,b Ui ) represents the value range of the overall risk level with respect to the corresponding characteristic indicator;

[0047] S43, determining the matter-element to be evaluated and the degree of association;

[0048] The matter-element to be evaluated is represented by the matter-element matrix R0:

[0049]

[0050] Among them, N0 represents the thing to be evaluated, that is, the risk factor indicator; ci represents the characteristic indicator; vi is the value of N0 with respect to the characteristic ci, that is, the specific value obtained by each indicator; the comprehensive score of the indicators at all levels is calculated according to the weight coefficient calculated by the G1 method, and the quantitative value of the indicators at all levels can be obtained.

[0051] The correlation function of the i-th indicator belonging to the p-th level is:

[0052]

[0053] ρ is the distance function, ρ(ν i , νpi ) represents the distance between the index and the classical domain, ρ(ν i , ν Ui ) represents the distance between the indicator and the node domain;

[0054] S44. Determine the comprehensive relevance and risk level;

[0055] According to the obtained weight and correlation, the comprehensive correlation is obtained:

[0056]

[0057] Among them, K p (N) represents the comprehensive correlation of thing N with respect to each risk level; ω i is the weight coefficient of each characteristic index; K p (v i ) is the correlation degree of each characteristic index with respect to the p level;

[0058] Determine the risk level based on the evaluation value and value range:

[0059]

[0060] Indicates that the comprehensive evaluation level of the thing to be evaluated is the pth level when the comprehensive correlation takes the maximum value; if the calculated comprehensive correlation K p (N), it means that the evaluation object belongs to the corresponding evaluation level.

[0061] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0062] The present invention provides a method for evaluating the construction quality risk of a railway tunnel project in a complex mountainous area. The method comprises the following steps: forming an initial list of quality risk factors based on existing construction cases of railway tunnel projects in complex mountainous areas; constructing a quality risk index system for tunnel project construction by using the Delphi expert consultation method; determining the weight of the quality risk index based on the G1 weighting method in combination with the tunnel construction quality risk evaluation index layer; taking full account of the dynamics and complexity of the construction quality risk of railway tunnel projects in complex mountainous areas, taking matter-element extension as the basic idea, applying matter-element transformation and entropy value method to determine the weight coefficient, constructing a matter-element extension model for tunnel project construction quality risk evaluation, and calculating the comprehensive correlation of tunnel project construction quality risk, construction quality risk level and high-risk factors of tunnel construction quality through the model. The problem of the relationship between the interdependence and feedback of the construction quality risk factors of railway projects in complex mountainous areas can be revealed, which is helpful for project managers to grasp the causes of the formation of tunnel project construction quality risks in a timely manner, and proposes improvement measures for personnel factors, management factors, technical factors and environmental factors for high-risk factors, providing an important reference for the management and control of tunnel project construction quality risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0063] Figure 1 This is a diagram of the construction quality risk assessment process of a railway tunnel project in a complex mountainous area in Example 1. DETAILED DESCRIPTION

[0064] The present invention will be described in detail below in conjunction with the accompanying drawings.

[0065] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0066] Example 1

[0067] YY Tunnel is located in the southeast of the Qinghai-Tibet Plateau in Tibet Autonomous Region, with high mountains, deep valleys, interlaced valleys and ridges, and undulating terrain. The total length of the tunnel is 8,755m, and the maximum burial depth of the tunnel is about 750m. The tunnel site cover is mainly Quaternary fine and coarse breccia soil, crushed stone soil and block stone soil. The underlying bedrock is granite, granodiorite and diorite. The bedrock in the tunnel site is exposed, and the rock layer is in angular unconformity contact. The tunnel body passes through 3 faults, and the regional fault structure is extremely developed. The rock is hard, the rock mass is broken, and the joints and fissures are developed. The main unfavorable geology includes earthquakes, dangerous rock falls, debris flows, rock bursts, ice and water deposits, and frost damage. No special rock and soil are found. The regional groundwater is abundant, permeable, and has a large permeability coefficient. It is mainly bedrock fissure water and Quaternary pore groundwater. The main sources of recharge are atmospheric precipitation and surface water.

[0068] In general, the YY tunnel is located in the section with the most complex geological conditions, the greatest construction difficulty and the highest risk, so it is listed as a key and difficult control "throat" project of the entire line. Its construction difficulties can be summarized into three aspects: 1) The geology is extremely complex. The tunnel passes through 7 unfavorable geological fault zones, the ice-water sedimentary layer section is as long as 960m, the continuous water-rich fault zone is 900m long, and the maximum deformation section caused by high ground stress has a cumulative horizontal convergence value of 3.1m. 2) It is highly technical, and adopts the construction methods of step curtain grouting, pipe shed plus small pipe advance support, and small section three-step excavation, and uses advanced geological forecasts and other means to assist construction, using double-layer steel support, long and short combined anchor rods and other measures. 3) The temperature difference in the area where the tunnel is located is large, with an average temperature of 8.2℃ for many years, an extreme minimum temperature of -11.5℃, and an extreme maximum temperature of 29℃, which has a great impact on outdoor concrete construction.

[0069] This embodiment mainly uses literature research and typical complex mountain railway tunnel project case analysis, and comprehensively uses the Delphi expert consultation method to construct the YY tunnel project construction quality risk index system. The G1 weighted-matter-element extension integrated model is introduced to calculate and determine the weight of each indicator and construct a risk assessment model. The specific operations are as follows:

[0070] S1: Based on the existing domestic complex mountain railway tunnel construction cases, a preliminary list of tunnel construction quality risk factors is formed according to environmental factors, technical factors, management factors, material and equipment factors, and personnel factors;

[0071] S2: In order to ensure that the list of risk factors for the construction quality of the YY tunnel project is more scientific and reasonable, the Delphi method is used to optimize the list of risk factors based on the preliminary list of risk factors. Experts involved in the construction of the XX railway are invited to obtain their suggestions on the risk indicators for the construction quality of the YY tunnel project through interviews, and the consistency between the initial evaluation indicators and the actual project is judged. The Likert scale is used to set the degree of consistency of the indicators as "very consistent", "consistent", "generally consistent", "non-compliant" and "very inconsistent", corresponding to scores of "5", "4", "3", "2" and "1" respectively. The statistical indicators of the expert advice data are mainly obtained through two steps of analysis: the average calculation of expert opinions and the consistency test of expert opinions.

[0072] The Delphi expert survey method was used to obtain experts' suggestions on the risk indicators of tunnel construction quality, and the consistency between the initial risk list and the actual project was judged. Based on the Likert scale method, the statistical indicators of the expert suggestion data were obtained through two steps: calculating the average of expert opinions and testing the consistency of expert opinions. Then, the initial risk list was optimized and a tunnel construction quality evaluation index system was constructed.

[0073] The Likert scale is shown in Table 1.

[0074] Table 1

[0075] Degree of compliance Very consistent conform to Generally in line with Not Compliant Very inconsistent Corresponding score 5 4 3 2 1

[0076] The degree of conformity between the indicator and the actual situation is judged by whether the average value of the expert's score on each indicator on the Likert scale is greater than 4, and the indicator factors with an average score less than 4 in the results are eliminated.

[0077] Specifically, the calculation formula for the average expert opinion is as follows:

[0078]

[0079] Among them, mj represents the number of experts for the jth indicator; Cij represents the number of scores given by the ith expert to the jth indicator; Mj represents the importance of the corresponding indicator. The degree of agreement is "compliant".

[0080] The importance of the corresponding initial indicators is calculated according to the Delphi method formula, which is convenient for later judging the consistency between the initial evaluation indicators and the actual project. Therefore, the degree of conformity between the indicators and the actual situation is judged by whether the average value of the expert's score for each indicator is greater than 4.

[0081] Expert consensus test: Kendall's harmony coefficient w is often used to compare the consistency of multiple groups of data, and focuses on analyzing the correlation between data. Selecting the Kendall harmony coefficient for consistency test can determine whether the experts have reached a consensus on each indicator. Its value range is between 0 and 1. When the value is greater than 0.6, it is considered that the experts have reached a consensus.

[0082] The calculation formula of Kendall's harmony coefficient is as follows:

[0083]

[0084] Among them, N represents the number of evaluated indicators; K represents the number of evaluation experts; Ri represents the sum of the scores of each evaluated indicator.

[0085] The Kendall harmony coefficient formula is selected for consistency test to determine whether the experts have reached a consensus on each indicator. Its value range is between 0 and 1. When the value is greater than 0.6, it is considered that the experts have reached a consensus. By calculating the average of expert opinions and the Kendall harmony coefficient, it is easy to judge the consistency between the initial evaluation indicators and the actual project, and then optimize the initial risk indicator list.

[0086] Based on the summary of expert opinions, the indicator factors with an average score of less than 4 in the results were first eliminated. Then, the Kendall harmony coefficient w was calculated to be 0.608, which was greater than the consistency test threshold of 0.6, indicating that the opinions of the surveyed and statistical experts were consistent. Finally, the attributes of each factor were hierarchically summarized and classified to construct a YY tunnel project construction quality risk indicator system including 5 first-level indicators of personnel, materials and equipment, environment, technology and management factors, and 29 second-level indicators.

[0087] The specific level 2 indicators are:

[0088] Personnel factors include: insufficient comprehensive quality of labor workers, insufficient comprehensive quality of construction management and technical personnel, and poor supervision by supervisors.

[0089] Material and equipment factors: tunnel support equipment is in poor condition, tunnel ventilation equipment is in poor condition, and equipment inspection and maintenance are not in place.

[0090] Environmental factors: sensitive ecological environment, harsh construction environment, extreme weather such as thin air and strong convection, diverse strata and lithology, complex geological structure, high altitude and high terrain difference, complex groundwater hydrological conditions, high ground stress and unfavorable seismic geology, tunnel bias, and high surrounding rock level.

[0091] Technical factors: untimely closure, deep burial and span characteristics of the tunnel, improper drainage and waterproofing of the tunnel, over-excavation of the tunnel, unreasonable excavation method, improper timing of support, improper support method, unreasonable construction technical plan, inadequate monitoring and measurement, and insufficient reliability of advanced geological forecast.

[0092] Management factors: Inadequate implementation of accident warning and prevention measures, poor organization and management of the construction site, and inadequate employee education and training.

[0093] S3: Considering the pertinence and regional complexity of the risk assessment of construction quality of tunnel projects in complex mountainous areas, the evaluation indicators are weighted based on the G1 weighting method modified by the standard deviation;

[0094] Determine the order relationship of each indicator:

[0095] The order relationship of each index is assumed to be x 1 ,x 2 ,…,x n are n dimensionless evaluation indicators in the scheme to be evaluated. Experts rank them according to project characteristics and their own work experience. 1 , x 2 , ..., x n} selects the most important indicator as x′; experts select the most important indicator as x′ from the remaining n-1 indicators 2 ; Similarly, the expert selects the most important indicator from the remaining n-(k-1) indicators and marks it as x′ k ; After n-1 selections, the remaining index is labeled x′ n In summary, we can determine the unique order relation x′ of the evaluation index set 1 >x′ 2 >…>x′ n .

[0096] Experts arrange the order relationship according to the project characteristics and their own work experience, which facilitates the later determination of the unique order relationship of the evaluation indicator set.

[0097] Further: Formula for determining the importance of adjacent indicators:

[0098] Experts on evaluation index x k-1 With x k The importance ratio of k-1 / ω k The rational judgment is:

[0099]

[0100] Among them, x k-1 and x k The importance of r k The larger the value, the greater the importance.

[0101] Experts determine the importance ratio of adjacent indicators based on project characteristics and their own work experience, which facilitates the subsequent determination of the importance relationship of adjacent indicators.

[0102] Further: Calculate the indicator weight formula:

[0103] According to experts, k The rational assignment of n The calculation formula is:

[0104]

[0105] ω k-1 =ω k r k (k=n,n-1,...2);

[0106] Suppose there are m (m ≥ 2) experts to judge n (n ≥ 3) indicators. Assume that the kth (k = 1, 2, ..., m) expert sorts all indicators according to the G1 method, and the weight of each indicator is Assume that the weight coefficient of the first expert is The aggregate weight for each indicator is:

[0107]

[0108] Assume that the opinions of all experts are equally important, that is, l =1 / m, and the weight of each indicator is the arithmetic mean of the weights obtained by each expert using the G1 method principle:

[0109]

[0110] The above-mentioned quality risk indicator weight calculation based on the G1 weighting method facilitates the subsequent determination of the weight of each indicator.

[0111] By interviewing senior experts who participated in the project, the importance of each indicator of the construction quality risk of the YY tunnel project was judged. By sorting and analyzing the interview results, the weights assigned by 10 experts to each level 1 indicator were obtained, and the arithmetic mean of the data of the 10 experts was taken as the weight coefficient of the indicator. The indicator weights are shown in Table 2.

[0112] Table 2 Calculation of weights of indicators at all levels and results of risk level of evaluation indicators

[0113]

[0114] S4: Taking matter-element extension as the basic idea, applying matter-element transformation and entropy method, determining the weight coefficient, and constructing a matter-element extension model for tunnel engineering construction quality risk assessment.

[0115] Considering the fuzziness and complexity of the construction quality risk factors of railway tunnel projects in complex mountainous areas, the commonly used hierarchical analysis method, artificial neural network method, fuzzy comprehensive evaluation method, etc. cannot fully reflect the interdependence and feedback relationship between risk factors. The matter-element extension model is suitable for multi-index evaluation and has strong dynamics, which can make the risk assessment results more specific. The model takes matter-element extension as the basic idea, applies matter-element transformation and entropy method to determine the weight coefficient, which can avoid subjective problems, evaluate the quality of the object, and also consider the dynamics and variability of the evaluation object. Therefore, based on the above considerations, the matter-element extension model is selected for the construction quality risk assessment of the YY tunnel project.

[0116] Determine the evaluation feature set and risk level domain

[0117] The tunnel construction quality risk studied is analyzed from two characteristics: the probability of occurrence of C1 risk and the degree of impact of the consequences of C2 risk. The risk feature set is expressed as:

[0118] C = {c1, c2} = {the probability of risk occurrence, the degree of impact of the consequences of risk occurrence};

[0119] The tunnel engineering risk level domain is established in accordance with the Technical Specifications for Risk Management of Railway Tunnel Engineering, as shown in Table 3.

[0120] Table 3

[0121] Risk Level Level I Level II Grade III class meaning Low risk Moderate risk High risk Very high risk Value range (0,2.5] (2.5,5] (5,7.5] (7.5,10]

[0122] Determine the classical domain and the nodal domain

[0123] First, construct the evaluation element R = (N, c, v), where N represents the subject of risk assessment; c1, c2, ..., cn are the n features of the evaluation subject N; v1, v1, ..., vn are the corresponding values. Its classic domain matrix is ​​calculated as:

[0124]

[0125] Among them, the evaluated subject N is divided into p levels, Rp represents the p-level risk classical domain object; N represents the p-th level of the risk assessment object; ci represents the main characteristic index of Np; v pi =(a pi ,b pi) indicates that the characteristic indicators of N are in the value range of level p, which is called the classical domain.

[0126] The node domain is the value range of the corresponding characteristic index of all risk levels, and the node domain matter-element can be expressed as:

[0127]

[0128] Among them, U is the overall risk level; ci represents the characteristic index; v Ui =(a Ui ,b Ui ) represents the value range of the overall risk level with respect to the corresponding characteristic indicator.

[0129] Specific:

[0130] The classical domain of YY tunnel engineering is expressed as:

[0131]

[0132] The section domain is:

[0133]

[0134] S5: The model is used to calculate the comprehensive correlation of tunnel construction quality risks, the construction quality risk level, and the high-risk factors of tunnel construction quality.

[0135] Determine the matter-element to be evaluated and the degree of association

[0136] The matter-element to be evaluated is represented by the matter-element matrix R0:

[0137]

[0138] Among them, N0 represents the thing to be evaluated, that is, the risk factor index; ci represents the characteristic index; vi is the value of N0 with respect to the characteristic ci, that is, the specific value obtained by each indicator. The comprehensive score of each level of indicators is calculated according to the weight coefficient calculated by the G1 method, and the quantitative value of each level of indicators can be obtained.

[0139] The correlation function of the i-th indicator belonging to the p-th level is:

[0140]

[0141] ρ is the distance function, ρ(ν i , ν pi ) represents the distance between the index and the classical domain, ρ(ν i , ν Ui ) represents the distance between the indicator and the node domain.

[0142] Determine the overall relevance and risk level

[0143] According to the obtained weight and correlation, the comprehensive correlation is obtained:

[0144]

[0145] Among them, K p (N) represents the comprehensive correlation of thing N with respect to each risk level; ω i is the weight coefficient of each characteristic index; K p (v i ) is the correlation degree of each characteristic index with respect to the p level. According to the evaluation value and the range of values ​​determined above, the risk level is determined:

[0146]

[0147] The above formula indicates that the comprehensive evaluation level of the object to be evaluated is the pth level when the comprehensive correlation takes the maximum value. If the calculated comprehensive correlation K p (N), it means that the evaluation object belongs to the corresponding evaluation level.

[0148] Specific:

[0149] Experts are invited to score according to the risk level range, and the quantitative value of each level 2 indicator is determined by the arithmetic average method. The object elements to be evaluated are as follows:

[0150] (1) Personnel risks

[0151]

[0152] (2) Material and equipment risks

[0153]

[0154] (3) Risk management

[0155]

[0156] (4) Technical risks

[0157]

[0158]

[0159] (5) Environmental risks

[0160]

[0161] The comprehensive scores of the second-level indicators are calculated to form the quantitative values ​​of the first-level evaluation indicators. The calculation results are as follows:

[0162]

[0163]

[0164] Calculation of comprehensive correlation and risk level The correlation and risk level of each level of indicators are shown in Table 2. The comprehensive correlation of the construction quality risk of the YY tunnel project is 0.2016, and the construction quality risk level is medium level II. The actual situation of the early construction project shows that no quality accidents occurred during the construction of the YY tunnel, and there are no parts that need to be repaired. Therefore, the evaluation results are basically consistent with the actual situation.

[0165] S6: Propose improvement measures for personnel factors, management factors, technical factors and response measures for environmental factors for high-risk factors.

[0166] According to the calculation results, the high-risk factors of level III that affect the quality of tunnel construction mainly include insufficient comprehensive quality of labor workers (A 1), inadequate implementation of accident warning and prevention measures (C 1), etc., as shown in Table 2. The high-risk factors revealed in Table 2 are also basically consistent with the causes of construction risks discovered and focused on by the construction unit on site. The identification of these risk factors helps project managers understand the causes of the construction quality risks of the XX railway tunnel project. At the same time, this paper proposes countermeasures for the high-risk factors of level III analyzed in Table 2, in order to reduce the risks of the YY tunnel project. The main countermeasures include:

[0167] 1) Measures to improve personnel factors. Construction units should formulate special measures for labor workers to protect their legitimate rights and interests and regulate their behavior. Management should raise the threshold for labor entry to ensure that they are qualified. Secondly, they should strengthen labor training to improve their technical level and quality awareness in a targeted manner.

[0168] 2) Management factor improvement measures. In view of management factors such as inadequate implementation of accident warning and prevention measures, inadequate employee education and training, and poor organization and management of the construction site, it is necessary to improve the construction quality management system, including implementing accident warning and prevention measures, strengthening communication and coordination and risk monitoring, improving construction site organization and management, establishing and improving the quality management control system, and doing a good job in construction scheduling management.

[0169] 3) Technical factors improvement measures. In view of the insufficient reliability of advanced geological forecasts, inadequate monitoring and measurement, inappropriate timing of support methods and other technical factors, it is necessary to reasonably grasp the timing of support, understand the geological conditions and surrounding rock characteristics of the tunnel site in detail, select reasonable support methods according to the surrounding rock grade, strictly carry out real-time monitoring, measurement and early warning, and take timely treatment measures.

[0170] 4) Measures to deal with environmental factors. It is necessary to reduce the negative impact of complex environments. For complex environments such as bias pressure and poor geology, we should strengthen surveys and real-time monitoring, make construction emergency plans, determine treatment measures, and ensure the quality of engineering construction.

[0171] in conclusion

[0172] 1) Relying on the YY Tunnel, a key and difficult control "throat" project of XX Railway, the Delphi expert consultation method was used to determine the YY Tunnel project construction quality risk indicator system consisting of 5 first-level indicators and 29 second-level indicators of personnel, materials and equipment, environment, technology and management factors.

[0173] 2) A tunnel engineering construction quality risk assessment model based on the G1 weighted-matter-element extension integrated model was constructed. The evaluation results show that the comprehensive correlation of the YY tunnel engineering construction quality risk is 0.2016, and the construction quality risk level is medium II. The correctness and reliability of the evaluation results are verified through the actual situation of the early engineering construction.

[0174] 3) The results of the YY tunnel project construction quality risk assessment revealed the level III high risk factors that affect the tunnel construction quality, which helped the project managers to understand the causes of the construction quality risks of the XX railway tunnel project. They also proposed improvement measures for personnel factors, management factors, technical factors and response measures for environmental factors for these high risk factors, providing a reference for risk management.

[0175] The present invention fully considers the fuzziness and complexity of construction quality risk factors and the construction quality evaluation of tunnel engineering in complex and dangerous mountainous areas under the joint action of multiple factors, and can effectively analyze the interdependence and feedback relationship between risk factors.

[0176] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for risk assessment of construction quality of railway tunnel projects in complex mountainous areas. It is characterized in that The following steps are involved: S1. Based on the existing complex mountain railway tunnel construction cases, an initial list of quality risk factors is formed; S2. Use the Delphi expert consultation method to build a tunnel engineering construction quality risk indicator system; S3, weighting the quality risk indicators based on the G1 weighting method modified by standard deviation; S4. Taking matter-element extension as the basic idea, applying matter-element transformation and entropy method, determining the weight coefficient, and constructing a matter-element extension model for tunnel engineering construction quality risk assessment. S5. The model is used to calculate the comprehensive correlation of tunnel construction quality risks, the construction quality risk level and the high-risk factors of tunnel construction quality.

2. According to the method for risk assessment of construction quality of railway tunnel projects in complex mountainous areas as described in claim 1, It is characterized in that In S1, the initial list of quality risk factors includes level 1 indicators and level 2 indicators. Level 2 indicators are sub-indicators of level 1 indicators; level 1 indicators are at least three of the following: environmental factors, technical factors, management factors, material and equipment factors, and personnel factors.

3. According to the method for risk assessment of construction quality of railway tunnel projects in complex mountainous areas as described in claim 1, It is characterized in that In S2, the Delphi expert survey method was used to obtain experts' suggestions on tunnel engineering construction quality risk indicators to determine the degree of consistency between the initial risk list and the actual project. Based on the Likert scale method, the degree of consistency of indicators was set and the corresponding scores were given. By calculating the average of expert opinions and testing the consistency of expert opinions, the statistical indicators of expert advice data were obtained to construct a tunnel engineering construction quality evaluation index system.

4. The method for risk assessment of construction quality of railway tunnel projects in complex mountainous areas according to claim 3, It is characterized in that In S2, the average of the expert opinions is calculated using formula (1): In formula (1), mj represents the number of experts for the jth indicator; Cij represents the score of the i-th expert for the j-th indicator; Mj represents the importance of the corresponding indicator; the degree of conformity between the indicator and the actual situation is judged by whether the average value of the expert's score for each indicator is greater than 4.

5. According to the method for risk assessment of construction quality of railway tunnel engineering in complex mountainous area as claimed in claim 4, It is characterized in that In S2, the standard for testing the degree of consistency of expert opinions is: select the Kendall harmony coefficient ω for consistency test. When the value is greater than 0.6, it is considered that the experts have reached a consensus.

6. The construction quality risk assessment method for railway tunnel engineering in complex mountainous areas according to claim 1, It is characterized in that In S3, the G1 weighting method assigns weights to quality risk indicators. The specific steps are as follows: S31, the order relationship of each indicator; Assume x 1 ,x 2 ,…,x n The n dimensionless evaluation indicators of the scheme to be evaluated are ranked by experts according to the project characteristics and their own work experience. 1 , x 2 , ..., x n } selects the most important indicator as x′; experts select the most important indicator as x′ from the remaining n-1 indicators 2 ; Similarly, the expert selects the most important indicator from the remaining n-(k-1) indicators and marks it as x′ k ; After n-1 selections, the remaining index is labeled x′ n ; Determine the unique order relation x′ of the evaluation index set 1 >x′ 2 >…>x′ b . S32, determine the importance of adjacent indicators; Experts on evaluation index x k-1 With x k The importance ratio of k-1 / ω k The rational judgment is: x k-1 and x k The importance of r k The larger the value, the greater the importance. S33, calculating weight; According to experts, k The rational assignment of n The calculation formula is: oh k-1 =ω k r k (k=n,n-1,...2); Suppose there are m (m ≥ 2) experts to judge n (n ≥ 3) indicators. Assume that the kth (k = 1, 2, ..., m) expert sorts all indicators according to the G1 method, and the weight of each indicator is Assume that the weight coefficient of the first expert is The aggregate weight for each indicator is: Assume that the opinions of all experts are equally important, that is, l =1 / m, and the weight of each indicator is the arithmetic mean of the weights obtained by each expert using the G1 method principle:

7. The method for risk assessment of construction quality of railway tunnel projects in complex mountainous areas according to any one of claims 1 to 6, It is characterized in that In S4, a matter-element extension model for tunnel engineering construction quality risk assessment is constructed. The specific steps are as follows: S41, determine the evaluation feature set and risk level domain; The tunnel construction quality risk studied is analyzed from two characteristics: the probability of occurrence of C1 risk and the degree of impact of the consequences of C2 risk. The risk feature set is expressed as: C={c1,c2}={probability of risk occurrence, impact of consequences of risk occurrence} Establish the tunnel engineering risk level domain according to the Technical Specifications for Risk Management of Railway Tunnel Engineering; S42, determine the classical domain and the nodal domain; First, construct the evaluation element R = (N, c, v), where N represents the subject of risk assessment; c1, c2, ..., cn are the n features of the evaluation subject N; v1, v2, ..., vn are the corresponding values; Its classical domain matrix is ​​calculated as: Among them, the evaluated subject N is divided into p levels, Rp represents the p-level risk classical domain object; N represents the p-th level of the risk assessment object; ci represents the main characteristic index of Np; v pi =(a pi ,b pi ) indicates that each characteristic index of N is in the value range of level p, which is called the classical domain; The node domain is the value range of the corresponding characteristic index of all risk levels, and the node domain matter-element can be expressed as: Among them, U is the overall risk level; ci represents the characteristic index;; v Ui =(a Ui ,b Ui ) represents the value range of the overall risk level with respect to the corresponding characteristic indicator; S43, determining the matter-element to be evaluated and the degree of association; The matter-element to be evaluated is represented by the matter-element matrix R0: Among them, N0 represents the thing to be evaluated, that is, the risk factor indicator; ci represents the characteristic indicator; vi is the value of N0 with respect to the characteristic ci, that is, the specific value obtained by each indicator; the comprehensive score of the indicators at all levels is calculated according to the weight coefficient calculated by the G1 method, and the quantitative value of the indicators at all levels can be obtained. The correlation function of the i-th indicator belonging to the p-th level is: ρ is the distance function, ρ(ν i , ν pi ) represents the distance between the index and the classical domain, ρ(ν i , ν Ui ) represents the distance between the indicator and the node domain; S44. Determine the comprehensive relevance and risk level; According to the obtained weight and correlation, the comprehensive correlation is obtained: Among them, K p (N) represents the comprehensive correlation of thing N with respect to each risk level; ω i is the weight coefficient of each characteristic index; K p (v i ) is the correlation degree of each characteristic index with respect to the p level; Determine the risk level based on the evaluation value and value range: Indicates that the comprehensive evaluation level of the thing to be evaluated is the pth level when the comprehensive correlation takes the maximum value; if the calculated comprehensive correlation K p (N), it means that the evaluation object belongs to the corresponding evaluation level.

Citation Information

Cited By

  • Extra-long inclined shaft auxiliary tunnel double-track main tunnel construction effect evaluation device and use method thereof

    CN119379075A

  • Power transmission and transformation construction model and data matching method and data acquisition system

    CN119760439A

  • Tunnel construction risk assessment method based on ANP and matter-element normal cloud model