Intelligent safety protection method for charging pile

Through intelligent safety protection methods, including multi-level safety inspections and real-time monitoring, the problem of poor safety protection at charging piles is solved, the safety of the charging process and the long-term stable operation of the equipment are achieved, and faults and operating costs are reduced.

CN118753084APending Publication Date: 2024-10-11SHANGHAI UNI SENTRY INTELLIGENT TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410951733.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

Existing charging pile safety protection methods have a single type of protection and poor effect. They cannot effectively ensure the safety of charging piles, leading to safety risks and equipment failures.

Method used

Intelligent security protection methods are adopted, including pre-start security check, user authentication and authorization, real-time monitoring, emergency response, remote monitoring and maintenance, and regular security inspection and maintenance, to ensure the safety of the charging process through multi-layered security measures.

Benefits of technology

Effectively prevent electrical failures, fires and electric shock accidents, extend the service life of equipment, reduce failure rates and operating costs, ensure stable operation of charging piles in harsh environments, and improve user experience and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118753084A_ABST
    Figure CN118753084A_ABST
Patent Text Reader

Abstract

The invention discloses an intelligent safety protection method for a charging pile, and the method comprises the following steps: 1, pre-starting safety inspection, and carrying out the overall inspection of the charging pile before the first use of the charging pile; step 2, user identity authentication and authorization: after the charging pile is put into use, when the user needs to use the charging pile, identity authentication and authentication are carried out on the user; step 3, real-time monitoring in the charging process: in the charging process, the charging pile continuously monitors the charging state, and gives an alarm when an abnormality is found; 4, emergency processing is carried out under the emergency condition, when an abnormal condition occurs, power-off processing is carried out, and meanwhile, the charging pile can send out an alarm signal to remind a user and a manager to carry out processing; 5, safety check is carried out after charging is finished, and after charging is finished, the state of the charging pile is checked again to prepare for next charging; safety protection can be better performed on the charging pile.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of safety protection of charging piles, and in particular to an intelligent safety protection method for charging piles. Background Art

[0002] A charging pile is a device that provides electric vehicles with energy. Its function is similar to that of a gas pump at a gas station. It can be fixed on the ground or on a wall and installed in public buildings (such as charging stations, shopping malls, public parking lots, etc.) and parking lots in residential areas. The input end of the charging pile is directly connected to the AC power grid, and the output end is equipped with a charging plug for charging electric vehicles.

[0003] When the charging pile is in use, it needs to be protected to ensure the safe and stable operation of the charging pile. Safety protection methods will be used during the charging pile safety protection process.

[0004] The existing safety protection methods have a single protection type and poor protection effect, and cannot perform good safety protection of charging piles, which has a certain impact on the use of safety protection methods. Therefore, an intelligent safety protection method for charging piles is proposed. Summary of the invention

[0005] The technical problem to be solved by the present invention is: how to solve the problem that the existing safety protection method has a single protection type, poor protection effect, and cannot perform good safety protection of charging piles, which has a certain impact on the use of the safety protection method. An intelligent safety protection method for a charging pile is provided.

[0006] The present invention solves the above technical problems through the following technical solutions, and the present invention comprises the following steps:

[0007] Step 1: Pre-startup safety check: perform a comprehensive check on the charging station before using it for the first time;

[0008] Step 2: User identity verification and authorization. After the charging pile is put into use, when the user needs to use the charging pile, the user's identity is authorized and verified;

[0009] Step 3: Real-time monitoring during charging: During the charging process, the charging pile will continuously monitor the charging status and issue an alarm if any abnormality is found;

[0010] Step 4: Carry out emergency treatment in emergency situations. When an abnormal situation occurs, the power will be cut off. At the same time, the charging pile will send out an alarm signal to remind users and managers to handle it;

[0011] Step 5: Perform a safety check after charging. After charging is completed, check the status of the charging pile itself again to prepare for the next charge;

[0012] Step 6: Remote monitoring and maintenance, set up the remote monitoring process to remotely monitor and maintain the charging pile.

[0013] Step 7: Regular safety inspection and maintenance. During the use of the charging pile, regular safety inspection and maintenance should be carried out on the charging pile.

[0014] Furthermore, the specific process of the pre-startup safety check is as follows:

[0015] First, check the appearance of the charging pile, including the outer shell, connection lines, display screen, and buttons to see if there are any abnormalities.

[0016] Internal structure inspection: dismantle the internal structure of the charging pile to check whether there is any internal fault;

[0017] Electrical safety inspection: check whether the power line of the charging pile is properly grounded, detect the insulation status of the charging pile, and check whether the overvoltage, undervoltage and other protection devices of the system are working properly;

[0018] Network security check: check whether the charging pile's network access point is at risk of malicious attacks and whether there is unauthorized access;

[0019] Check the grounding protection device to verify whether the grounding protection device of the charging pile is working properly;

[0020] Safety warning sign inspection: Check the safety warning signs around the charging piles;

[0021] Functional test: test the basic functions of the charging pile.

[0022] Furthermore, the specific process of user identity authentication and authorization is as follows:

[0023] User identity verification: Users first need to verify themselves through the identity verification method provided by the charging station;

[0024] User information comparison: The charging pile will compare the identity verification information submitted by the user with the user information pre-stored in the system; if the information comparison is successful, the charging pile will confirm the user's identity and allow them to proceed to the next step; if the information comparison fails, the charging pile will reject the user's access request and may prompt the user to re-enter or select other verification methods.

[0025] User authorization: After successful identity authentication, the charging station will check whether the user has charging authority;

[0026] When the user has charging authority, the charging pile will authorize the user and allow him to perform charging operations;

[0027] If the user does not have charging permission, the charging station will refuse authorization;

[0028] Recording and monitoring: The charging station will record the process of each user identity authentication and authorization.

[0029] Furthermore, the specific process of real-time monitoring during the charging process is as follows:

[0030] Parameter collection: The charging pile will continuously collect charging pile parameters during the charging process;

[0031] Data transmission: The collected charging pile parameters are transmitted to the background server or monitoring center in real time through the communication module inside the charging pile;

[0032] Data analysis and comparison: After receiving the charging pile parameters, the backend server or monitoring center will analyze and compare them;

[0033] Abnormal warning and processing: When the data charging pile parameter analysis and comparison finds any abnormality or exceeds the preset safety threshold, the system will immediately trigger the early warning mechanism to alarm.

[0034] Furthermore, the specific process of remote monitoring and maintaining the charging pile is as follows:

[0035] Remote connection is established, a remote maintenance system is established, and a connection system is established with the charging pile through the network;

[0036] Real-time data monitoring, remote maintenance system establishes connection successfully, and monitors charging pile data in real time.

[0037] Abnormal detection and early warning: analyze the monitored charging pile data to detect whether there are abnormalities and issue warnings when there are abnormalities;

[0038] Fault diagnosis and processing: After receiving the warning, the maintenance personnel will perform fault diagnosis according to the specific situation;

[0039] Records and reports: During the entire remote monitoring and maintenance process, all data, warning information, fault diagnosis results and treatment measures will be recorded and stored.

[0040] Furthermore, the process of the regular safety inspection and maintenance is as follows: external inspection: check whether the appearance of the charging pile is intact; check the surrounding environment of the charging pile and collect the number of flammable and explosive materials; check the integrity of the display screen, check whether the indicator light is working properly, check the status of the equipment door lock, electrical safety inspection, check whether the insulation resistance and grounding resistance of the charging facility meet the specified requirements, and verify whether the leakage protection and overcurrent protection devices of the charging pile are working properly;

[0041] Internal inspection: disassemble and inspect the internal structure of the charging pile, and check the status of the power module, charging control module, and safety protection module;

[0042] Use a voltmeter and an ammeter to detect the voltage and current of the charging pile;

[0043] Function test: check the charging function of the charging pile;

[0044] Test the payment function and data transmission function of the charging pile

[0045] The safety protection functions of the charging pile are tested, including verification of overcurrent protection, overvoltage protection, leakage protection, etc.

[0046] Mechanical safety inspection: Check whether the charging pile is firmly fixed, including the fixing device of the fixing base and charging gun;

[0047] Conduct mechanical performance tests on the charging gun, including plug-in force test and locking force test;

[0048] Maintenance measures: Maintain the charging pile based on the inspection results.

[0049] Compared with the prior art, the present invention has the following advantages: the intelligent safety protection method of the charging pile can ensure charging safety: safety protection can effectively prevent fire or electric shock accidents caused by electrical failure, overheating or short circuit of the charging pile, thereby ensuring the safety of users during the charging process, and can monitor the charging status in real time, and cut off the power supply in time under abnormal circumstances to avoid potential safety risks and extend the service life of the charging pile: protective measures can reduce corrosion and damage of the charging pile caused by environmental factors, reduce the equipment failure rate, and thus extend its service life; regular safety inspections and maintenance can promptly discover and deal with potential problems, prevent small problems from expanding, ensure the long-term stable operation of the charging pile, and improve user experience: safety protection can ensure that the charging pile can still work normally in bad weather or special environments, and provide users with stable and reliable charging services; effective safety protection can reduce the maintenance and replacement costs caused by equipment failure, and reduce the operating costs of operators; through remote monitoring and fault diagnosis systems, the operating status of the charging pile can be grasped in real time, problems can be discovered and dealt with in time, and the demand and cost of on-site maintenance can be reduced, making this method more worthy of promotion and use. BRIEF DESCRIPTION OF THE DRAWINGS

[0050] Figure 1 It is the overall flow chart of the present invention. DETAILED DESCRIPTION

[0051] The following is a detailed description of an embodiment of the present invention. This embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation method and a specific operation process are given, but the protection scope of the present invention is not limited to the following embodiment.

[0052] like Figure 1As shown, this embodiment provides a technical solution: an intelligent safety protection method for a charging pile, comprising the following steps:

[0053] Step 1: Pre-startup safety check: perform a comprehensive check on the charging station before using it for the first time;

[0054] Step 2: User identity verification and authorization. After the charging pile is put into use, when the user needs to use the charging pile, the user's identity is authorized and verified;

[0055] Step 3: Real-time monitoring during charging: During the charging process, the charging pile will continuously monitor the charging status and issue an alarm if any abnormality is found;

[0056] Step 4: Carry out emergency treatment in emergency situations. When an abnormal situation occurs, the power will be cut off. At the same time, the charging pile will send out an alarm signal to remind users and managers to handle it;

[0057] Step 5: Perform a safety check after charging. After charging is completed, check the status of the charging pile itself again to prepare for the next charge;

[0058] Step 6: Remote monitoring and maintenance, set up the remote monitoring process to remotely monitor and maintain the charging pile.

[0059] Step 7: Regular safety inspection and maintenance. During the use of the charging pile, regular safety inspection and maintenance should be carried out on the charging pile.

[0060] The specific process of the pre-startup safety check is as follows:

[0061] Appearance inspection: Carefully observe the outer shell, connection lines, display screen, buttons and other parts of the charging pile to check for damage, corrosion, aging, etc. Pay special attention to check whether key components such as plugs and sockets are intact, without looseness, deformation and other problems.

[0062] Internal structure inspection: Under the guidance of professionals, disassemble and inspect the internal structure of the charging pile, including the power module, charging control module, safety protection module, etc. Check whether there are internal faults such as burning, leakage, short circuit, etc.

[0063] Electrical safety check: Check whether the power line of the charging pile is properly grounded to ensure that there are no short circuits, leakages, etc. during normal operation.

[0064] Use professional tools to detect the insulation status of the charging pile to ensure that the insulation resistance meets the requirements and prevent the risk of leakage.

[0065] Check whether the system's overvoltage, undervoltage and other protection devices are working properly and whether they can handle abnormal voltage conditions accordingly.

[0066] Network security check: Check whether the charging pile's network access point is at risk of malicious attacks and whether there is unauthorized access. Ensure the charging pile's network security to prevent data leakage or tampering.

[0067] Grounding protection device inspection: Verify whether the grounding protection device of the charging pile is working properly to ensure that the current can be promptly conducted to the ground in case of abnormal conditions such as leakage, thereby ensuring user safety.

[0068] Safety warning sign inspection: Check whether the safety warning signs around the charging pile are complete and clearly visible, and remind users to use them safely.

[0069] Functional testing: Under the premise of ensuring safety, the basic functions of the charging pile are tested, such as charging function, payment function, data transmission function, etc. Ensure that its various functions are normal and stable.

[0070] Recording and reporting: Record and analyze the results of the pre-startup safety check in detail, including the problems found, treatment measures and suggestions, etc. These records will help maintain and optimize the charging pile in the future.

[0071] Through strict pre-start safety checks, it is possible to ensure that the charging pile is in a safe and reliable state before starting, providing strong protection for the subsequent charging process. At the same time, it also helps to enhance users' trust in charging piles and promote the promotion and application of electric vehicles.

[0072] The specific process of user identity authentication and authorization is as follows:

[0073] The specific process of user identity authentication and authorization plays a vital role in the security protection of charging piles. This process ensures that only authenticated and authorized users can use charging piles for charging, thereby improving the safety and reliability of charging pile use.

[0074] The following is the specific process of user authentication and authorization:

[0075] User identity verification: The user first needs to verify through the identity verification method provided by the charging station. This usually includes swiping a card, scanning a code, or entering a password.

[0076] If it is a card swipe verification, the user needs to place a specific card (such as an RFID card, IC card, etc.) in the sensing area of ​​the charging pile. The charging pile will read the card information and compare it with the pre-stored user information.

[0077] If it is a QR code verification, the user needs to use the mobile phone to scan the QR code displayed on the charging pile, and log in or authorize through the mobile application or website.

[0078] If it is password verification, the user needs to enter the preset password on the input interface of the charging pile.

[0079] User information comparison: The charging station will compare the identity verification information submitted by the user with the user information pre-stored in the system. This information may include user ID, card number, mobile phone number, account password, etc.

[0080] If the information comparison is successful, the charging pile will confirm the user's identity and allow him to proceed to the next step; if the information comparison fails, the charging pile will reject the user's access request and may prompt the user to re-enter or select other verification methods.

[0081] User authorization: After successful identity authentication, the charging station will check whether the user has charging authority. This usually involves factors such as the user's account status, balance, credit record, etc.

[0082] If the user has charging permission, the charging pile will authorize the user to perform charging operations. This is usually manifested as a charging interface displayed on the display screen of the charging pile, and the user can start setting charging parameters or start the charging process.

[0083] If the user does not have charging authority (such as insufficient account balance, poor credit record, etc.), the charging station will refuse authorization and may prompt the user to recharge, repair credit record or contact customer service to resolve the problem.

[0084] Recording and monitoring: The charging station will record the process of each user identity verification and authorization, including verification time, verification method, user information, and authorization results.

[0085] These records help the management and maintenance personnel of charging piles to track user usage and promptly identify and handle abnormal problems.

[0086] Through the above process, the charging pile can ensure that only authenticated and authorized users can use the charging pile for charging, thereby improving the safety and reliability of the use of the charging pile. At the same time, it also helps to protect the legitimate rights and interests of users and prevent unauthorized users from abusing the charging pile resources.

[0087] The specific process of remote monitoring and maintenance of charging piles is as follows:

[0088] The specific process of remote monitoring and maintenance of charging piles involves multiple links, which together ensure the safe operation and efficient maintenance of charging piles. The following is the detailed process of remote monitoring and maintenance:

[0089] Remote connection establishment: First, maintenance personnel need to use special remote monitoring equipment or software to establish a connection with the charging pile through the network. This connection is usually based on a wireless network, cloud platform or remote monitoring system to ensure secure data transmission and real-time interaction.

[0090] Real-time data monitoring: Once the connection is established, maintenance personnel can view various data of the charging pile in real time, including key parameters such as charging status, current, voltage, temperature, etc. These data are collected in real time through sensors and communication modules inside the charging pile and transmitted to the remote monitoring platform.

[0091] Abnormal detection and early warning: The remote monitoring platform will analyze the received data to detect whether there are any abnormal conditions. For example, if the current or voltage exceeds the normal range, or the temperature rises abnormally, the system will immediately issue an early warning notification. These early warning notifications can be sent to maintenance personnel via SMS, email or system interface.

[0092] Fault diagnosis and treatment: After receiving the early warning notification, maintenance personnel will perform fault diagnosis according to the specific situation. Through the remote monitoring system, they can view more detailed fault information, such as fault code, fault occurrence time, etc. Based on this information, maintenance personnel can preliminarily determine the cause of the fault and take corresponding treatment measures, such as remotely restarting the charging pile, adjusting charging parameters or sending maintenance instructions.

[0093] Remote software upgrade and maintenance: In addition to real-time monitoring and troubleshooting, the remote monitoring and maintenance system also supports remote software upgrades and configuration adjustments for charging piles. This can greatly improve maintenance efficiency and reduce the need and cost of on-site maintenance.

[0094] Records and reports: During the entire remote monitoring and maintenance process, all data, warning information, fault diagnosis results and treatment measures will be recorded in detail. These records can be used for post-analysis, troubleshooting and performance optimization, providing strong support for improving the safety and stability of charging piles.

[0095] Through remote monitoring and maintenance, real-time monitoring, fault diagnosis and remote operation of charging piles can be achieved, which greatly improves the operation efficiency and maintenance level of charging piles. At the same time, it also reduces the cost and risk of on-site maintenance and provides users with more convenient and safe charging services.

[0096] The process of regular safety inspection and maintenance is as follows: The specific process of regular safety inspection and maintenance of charging piles includes the following key steps:

[0097] Appearance inspection: Check the appearance of the charging station to see if it is in good condition, including any scratches, rust or other damage.

[0098] Check the environment around the charging station to ensure there are no flammable or explosive substances, and clean up the surrounding debris.

[0099] Check whether the display screen is intact and has no abnormalities such as screen distortion.

[0100] Check whether the indicator lights are working properly and can display the status correctly.

[0101] Check that the equipment door lock is intact and locked.

[0102] Electrical safety check: Use professional tools to check the electrical system of the charging station, including whether the wires and cables are damaged and whether the grounding is good.

[0103] Check whether the insulation resistance and grounding resistance of the charging facilities meet the specified requirements and record the test results.

[0104] Verify whether the leakage protection and overcurrent protection devices of the charging pile are working properly to ensure that they can cut off the power supply in time under abnormal circumstances.

[0105] Internal inspection: Disassemble and inspect the internal structure of the charging pile, including the power module, charging control module, safety protection module, etc., to find out whether there are internal faults such as burning, leakage, short circuit, etc.

[0106] Use instruments such as voltmeters and ammeters to test the voltage and current of the charging pile to verify whether its performance is normal.

[0107] Function test: Check the charging function of the charging pile to ensure that the charging interface is not damaged and the charging rate is normal.

[0108] Test the payment function, data transmission function, etc. of the charging pile to ensure that its various functions are normal and stable.

[0109] Test the safety protection functions of the charging pile, including verification of overcurrent protection, overvoltage protection, leakage protection, etc.

[0110] Mechanical safety inspection: Check whether the fixing method of the charging pile is firm, including the fixing base, the fixing device of the charging gun, etc.

[0111] Conduct mechanical performance tests on the charging gun, including plug-in force test, locking force test, etc.

[0112] Recording and Analysis: During the entire inspection process, record the inspection results in detail, including normal and abnormal situations.

[0113] Analyze the inspection results, identify possible problems and hidden dangers, and formulate corresponding maintenance measures.

[0114] Maintenance measures: Based on the inspection results, perform necessary maintenance on the charging pile, such as replacing worn parts, repairing damaged lines, etc.

[0115] Clean the surface of the charging station regularly to ensure it is clean and tidy to avoid malfunctions caused by dust or dirt.

[0116] Through these regular safety inspections and maintenance steps, you can ensure that the charging pile is in good working condition, improve the safety and efficiency of the charging process, and extend the service life of the charging pile. At the same time, these measures also help to promptly discover and deal with potential safety hazards and ensure the safety of users' charging.

[0117] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0118] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0119] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may change, modify, replace and vary the above embodiments within the scope of the present invention.

Claims

1. An intelligent safety protection method for a charging pile, characterized in that: The following steps are involved: Step 1: Pre-startup safety check: perform a comprehensive check on the charging station before using it for the first time; Step 2: User identity verification and authorization. After the charging pile is put into use, when the user needs to use the charging pile, the user's identity is authorized and verified; Step 3: Real-time monitoring during charging: During the charging process, the charging pile will continuously monitor the charging status and issue an alarm if any abnormality is found; Step 4: Carry out emergency treatment in emergency situations. When an abnormal situation occurs, the power will be cut off. At the same time, the charging pile will send out an alarm signal to remind users and managers to handle it; Step 5: Perform a safety check after charging. After charging is completed, check the status of the charging pile itself again to prepare for the next charge; Step 6: Remote monitoring and maintenance: Set up a remote monitoring process to remotely monitor and maintain the charging pile; Step 7: Regular safety inspection and maintenance. During the use of the charging pile, regular safety inspection and maintenance should be carried out on the charging pile.

2. The intelligent safety protection method for a charging pile according to claim 1, characterized in that: The specific process of the pre-startup safety check is as follows: First, check the appearance of the charging pile, observe the outer shell, connection lines, display screen, and buttons to see if there are any abnormalities; Internal structure inspection: dismantle the internal structure of the charging pile to check whether there is any internal fault; Electrical safety inspection: check whether the power line of the charging pile is properly grounded, detect the insulation status of the charging pile, and check whether the overvoltage and undervoltage protection devices of the system are working properly; Network security check: check whether the charging pile's network access point is at risk of malicious attacks and whether there is unauthorized access; Check the grounding protection device to verify whether the grounding protection device of the charging pile is working properly; Safety warning sign inspection: Check the safety warning signs around the charging piles; Functional test: test the basic functions of the charging pile.

3. The intelligent safety protection method for a charging pile according to claim 1, characterized in that: The specific process of user identity authentication and authorization is as follows: User identity verification: Users first need to verify themselves through the identity verification method provided by the charging station; User information comparison: The charging pile will compare the identity verification information submitted by the user with the user information pre-stored in the system; if the information comparison is successful, the charging pile will confirm the user's identity and allow the user to proceed to the next step; if the information comparison fails, the charging pile will reject the user's access request and may prompt the user to re-enter or select other verification methods; User authorization: After successful identity authentication, the charging station will check whether the user has charging authority; When the user has charging authority, the charging pile will authorize the user and allow him to perform charging operations; If the user does not have charging authority, the charging station will refuse authorization; Recording and monitoring: The charging station will record the process of each user identity authentication and authorization.

4. The intelligent safety protection method for a charging pile according to claim 1, characterized in that: The specific process of real-time monitoring during the charging process is as follows: Parameter collection: The charging pile will continuously collect charging pile parameters during the charging process; Data transmission: The collected charging pile parameters are transmitted to the background server or monitoring center in real time through the communication module inside the charging pile; Data analysis and comparison: After receiving the charging pile parameters, the backend server or monitoring center will analyze and compare them; Abnormal warning and processing: When the data charging pile parameter analysis and comparison finds any abnormality or exceeds the preset safety threshold, the system will immediately trigger the early warning mechanism to alarm.

5. The intelligent safety protection method for a charging pile according to claim 1, characterized in that: The specific process of remote monitoring and maintenance of charging piles is as follows: Remote connection is established, a remote maintenance system is established, and a connection system is established with the charging pile through the network; Real-time data monitoring, remote maintenance system establishes connection successfully, real-time monitoring of charging pile data; Abnormal detection and early warning: analyze the monitored charging pile data to detect whether there are abnormalities and issue warnings when there are abnormalities; Fault diagnosis and processing: After receiving the warning, the maintenance personnel will perform fault diagnosis according to the specific situation; Records and reports: During the entire remote monitoring and maintenance process, all data, warning information, fault diagnosis results and treatment measures will be recorded and stored.

6. The intelligent safety protection method for a charging pile according to claim 1, characterized in that: The process of the regular safety inspection and maintenance is as follows: External inspection: Check whether the appearance of the charging pile is intact; Check the environment around the charging pile and collect the number of flammable and explosive materials; Check the integrity of the display screen, check whether the indicator light is working properly, check the status of the equipment door lock, electrical safety inspection, check whether the insulation resistance and grounding resistance of the charging facility meet the specified requirements, and verify whether the leakage protection and overcurrent protection devices of the charging pile are working properly; Internal inspection: disassemble and inspect the internal structure of the charging pile, and check the status of the power module, charging control module, and safety protection module; Use a voltmeter and an ammeter to detect the voltage and current of the charging pile; Function test: check the charging function of the charging pile; Test the payment function and data transmission function of the charging pile Test the safety protection function of the charging pile, including verification of overcurrent protection, overvoltage protection, and leakage protection; Mechanical safety inspection: Check whether the charging pile is firmly fixed, including the fixing device of the fixing base and charging gun; Conduct mechanical performance tests on the charging gun, including plug-in force test and locking force test; Maintenance measures: Maintain the charging pile based on the inspection results.