A method, device, electronic equipment and storage medium for monitoring energy consumption of new energy buses
By obtaining the historical data and real-time information of new energy buses, predicting the power consumption of each section, and setting the charging prompt threshold based on the battery loss information, the problem of energy consumption monitoring error of new energy buses is solved and accurate energy consumption monitoring is achieved 和运营调度效果。
Patent Information
- Application Number
- CN202411220763.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-09-02
AI Technical Summary
There are large errors in the energy consumption monitoring of existing new energy buses under different road conditions and operating conditions, making it difficult to achieve accurate energy consumption monitoring, affecting the vehicle operation and scheduling effect.
By obtaining the historical mileage and charging information of new energy buses, combining real-time traffic and historical passenger numbers, predicting the power consumption of each section, and setting the charging prompt threshold based on the battery loss information, adjusting the charging prompts in real time to ensure energy consumption monitoring Accuracy.
It realizes accurate monitoring of energy consumption of new energy buses, reduces monitoring errors, improves the accuracy and efficiency of vehicle operation scheduling, and optimizes the line operation effect.
Smart Images

Figure CN118753116B_ABST
Abstract
Description
Technical Field
[0001] The embodiments of the present application relate to the field of data processing technology, and in particular to a method, device, electronic device and storage medium for monitoring energy consumption of a new energy bus. Background Art
[0002] At present, in the bus operation scenario, electric new energy buses are widely used in the transportation system due to their advantages such as zero emissions and low noise. During the operation of electric new energy buses, it is particularly important to monitor their energy consumption. By accurately monitoring the energy consumption of new energy buses and replenishing energy in time when the battery power is low, a good vehicle operation and dispatching effect can be achieved. When monitoring the energy consumption of new energy buses, by querying the real-time battery power, when the battery power is lower than the set threshold, a recharging reminder is issued to remind the driver to go to recharge in time to ensure the normal operation of the vehicle.
[0003] However, for the same route, the power consumption of new energy buses varies under different road conditions and operating conditions. In extreme cases, the power consumption of new energy buses increases exponentially compared to normal conditions. Simply giving a reminder to recharge when the power level is lower than the set threshold will result in large monitoring errors, making it difficult to achieve accurate energy consumption monitoring, resulting in deviations in vehicle operation and scheduling. Summary of the invention
[0004] The embodiments of the present application provide a method, device, electronic device and storage medium for monitoring energy consumption of a new energy bus, which can realize accurate energy consumption monitoring of the new energy bus and solve the problem of energy consumption monitoring error of the new energy bus.
[0005] In a first aspect, an embodiment of the present application provides a method for monitoring energy consumption of a new energy bus, comprising:
[0006] Obtain the historical mileage and historical charging information of the new energy bus, determine the mileage loss information of the new energy bus battery based on the historical mileage, determine the charging loss information of the new energy bus battery based on the historical charging information, and determine the battery loss information of the new energy bus based on the mileage loss information and the charging loss information;
[0007] Obtain the real-time traffic flow information of each section of the current driving route of the new energy bus, as well as the historical average traffic flow information of each section of the current driving route corresponding to the prediction period, and determine the predicted traffic flow information of each section of the current driving route corresponding to the prediction period based on the real-time traffic flow information and the historical average traffic flow information;
[0008] Obtain the historical number of passengers on each section of the current driving route of the new energy bus during the forecast period, predict the power consumption of each section based on the forecast traffic information and the historical number of passengers, and determine the total power consumption of the route based on the power consumption of each section;
[0009] The charging reminder threshold of the new energy bus is set based on the battery loss information, the real-time power information of the new energy bus is read, and the charging reminder of the new energy bus is given based on the real-time power information, the total power consumption of the route and the charging reminder threshold of the new energy bus.
[0010] Furthermore, the predicted traffic flow information for each section of the current driving route corresponding to the predicted time period is determined based on the real-time traffic flow information and the historical average traffic flow information, including:
[0011] Obtain the first passenger flow impact coefficient preset based on the real-time traffic flow information and the second passenger flow impact coefficient preset based on the historical average traffic flow information, and weightedly calculate the predicted traffic flow information for each section of the current driving route corresponding to the predicted period based on the first passenger flow impact coefficient, the second passenger flow impact coefficient, the real-time traffic flow information and the historical average traffic flow information.
[0012] Furthermore, the power consumption of each road section is predicted based on the predicted traffic flow information and the historical number of passengers, including:
[0013] Determine the passing time and passing speed of new energy buses on the corresponding road section based on the predicted traffic flow information, and calculate the basic power consumption based on the passing time and passing speed;
[0014] The additional power consumption is calculated based on the historical number of passengers, and the power consumption of each road section is calculated based on the basic power consumption and the additional power consumption.
[0015] Furthermore, the additional power consumption is calculated based on the historical number of passengers, including:
[0016] Based on the historical number of passengers, a pre-constructed correlation curve between the number of passengers and the additional power consumption is queried to obtain the corresponding power consumption correlation coefficient, and the additional power consumption is calculated based on the historical number of passengers and the power consumption correlation coefficient.
[0017] Furthermore, after determining the battery loss information of the new energy bus based on the mileage loss information and the charging loss information, the method further includes:
[0018] Collect historical driving data of new energy buses, determine frequency information of specified driving behaviors based on the historical driving data, and adjust battery loss information based on the frequency information of specified driving behaviors.
[0019] Furthermore, the designated driving behavior includes a predefined sudden start and stop behavior, and the frequency information of the designated driving behavior is determined based on the historical driving data, including:
[0020] The vehicle speed is calculated based on historical driving data to calculate the number of times the emergency start and emergency brake behavior of the new energy bus is triggered during the statistical period, and the frequency information of the specified driving behavior is calculated based on the number of triggers and the statistical period.
[0021] Furthermore, after predicting the power consumption of each road section according to the predicted traffic flow information and the historical number of passengers, it also includes:
[0022] Real-time temperature information is obtained. When the real-time temperature reaches a set temperature threshold, a power consumption growth coefficient is determined according to the temperature difference between the real-time temperature and the set temperature threshold, and the power consumption of each road section is adjusted based on the power consumption growth coefficient.
[0023] In a second aspect, an embodiment of the present application provides an energy consumption monitoring device for a new energy bus, comprising:
[0024] A loss determination module is used to obtain the historical mileage and historical charging information of the new energy bus, determine the mileage loss information of the new energy bus battery based on the historical mileage, determine the charging loss information of the new energy bus battery based on the historical charging information, and determine the battery loss information of the new energy bus based on the mileage loss information and the charging loss information;
[0025] The traffic flow prediction module is used to obtain the real-time traffic flow information of each section of the current driving route of the new energy bus, as well as the historical average traffic flow information of each section of the current driving route corresponding to the prediction period, and determine the predicted traffic flow information of each section of the current driving route corresponding to the prediction period based on the real-time traffic flow information and the historical average traffic flow information;
[0026] The power prediction module is used to obtain the historical number of passengers in each section of the current driving route of the new energy bus during the prediction period, predict the power consumption of each section based on the predicted traffic information and the historical number of passengers, and determine the total power consumption of the route based on the power consumption of each section;
[0027] The prompt module is used to set the charging prompt threshold of the new energy bus based on the battery loss information, read the real-time power information of the new energy bus, and provide charging prompts for the new energy bus based on the real-time power information, the total power consumption of the route and the charging prompt threshold of the new energy bus.
[0028] In a third aspect, an embodiment of the present application provides an electronic device, including:
[0029] memory and one or more processors;
[0030] The memory is used to store one or more programs;
[0031] When the one or more programs are executed by the one or more processors, the one or more processors implement the new energy bus energy consumption monitoring method as described in the first aspect.
[0032] In a fourth aspect, an embodiment of the present application provides a storage medium comprising computer executable instructions, which, when executed by a computer processor, are used to execute the new energy bus energy consumption monitoring method as described in the first aspect.
[0033] The embodiment of the present application obtains the historical mileage and historical charging information of the new energy bus, determines the mileage loss information of the new energy bus battery based on the historical mileage, determines the charging loss information of the new energy bus battery based on the historical charging information, and determines the battery loss information of the new energy bus based on the mileage loss information and the charging loss information; obtains the real-time traffic flow information of each section of the current driving route of the new energy bus, and the historical average traffic flow information of each section of the current driving route corresponding to the prediction period, and determines the predicted traffic flow information of each section of the current driving route corresponding to the prediction period according to the real-time traffic flow information and the historical average traffic flow information; obtains the historical number of passengers in each section of the current driving route of the new energy bus during the prediction period, predicts the power consumption of each section according to the predicted traffic flow information and the historical number of passengers, and determines the total power consumption of the route based on the power consumption of each section; sets the charging reminder threshold of the new energy bus based on the battery loss information, reads the real-time power information of the new energy bus, and provides charging reminder for the new energy bus based on the real-time power information, the total power consumption of the route and the charging reminder threshold of the new energy bus. By adopting the above-mentioned technical means, the charging reminder threshold is set according to the real-time battery loss information of the new energy bus, and the total power consumption of the route is determined according to the predicted traffic information and the historical number of passengers. The real-time power information of the new energy bus, the total power consumption of the route and the charging reminder threshold of the new energy bus are combined to provide charging reminders for the new energy bus, so as to realize accurate energy consumption monitoring of the new energy bus, promptly remind the driver to recharge the vehicle, avoid affecting the line operation, and optimize the line operation effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 This is a flow chart of a method for monitoring energy consumption of a new energy bus provided in Example 1 of the present application;
[0035] Figure 2 is a flow chart for calculating power consumption in Example 1 of the present application;
[0036] Figure 3 This is a structural schematic diagram of a new energy bus energy consumption monitoring device provided in Example 2 of the present application;
[0037] Figure 4 It is a structural schematic diagram of an electronic device provided in Example 3 of the present application. DETAILED DESCRIPTION
[0038] In order to make the purpose, technical scheme and advantages of the present application clearer, the specific embodiments of the present application are further described in detail below in conjunction with the accompanying drawings. It is understood that the specific embodiments described herein are only used to explain the present application, rather than to limit the present application. It should also be noted that, for the convenience of description, only part of the present application is shown in the accompanying drawings, but not all of the content. Before discussing the exemplary embodiments in more detail, it should be mentioned that some exemplary embodiments are described as processes or methods depicted as flow charts. Although the flow chart describes each operation (or step) as a sequential process, many of the operations therein can be implemented in parallel, concurrently or simultaneously. In addition, the order of the operations can be rearranged. The process can be terminated when its operation is completed, but it can also have additional steps not included in the accompanying drawings. The process can correspond to a method, a function, a procedure, a subroutine, a subprogram, etc.
[0039] Embodiment 1:
[0040] Figure 1 A flowchart of a new energy bus energy consumption monitoring method provided in the first embodiment of the present application is given. The new energy bus energy consumption monitoring method provided in this embodiment can be executed by a new energy bus energy consumption monitoring device, which can be implemented by software and / or hardware. The new energy bus energy consumption monitoring device can be composed of two or more physical entities, or it can be composed of one physical entity. Generally speaking, the new energy bus energy consumption monitoring device can be a processing device such as a new energy bus onboard controller, a vehicle system server, etc.
[0041] The following description is made by taking the energy consumption monitoring device as the main body of the new energy bus energy consumption monitoring method as an example. Figure 1 , the new energy bus energy consumption monitoring method specifically includes:
[0042] S110. Obtain the historical mileage and historical charging information of the new energy bus, determine the mileage loss information of the new energy bus battery based on the historical mileage, determine the charging loss information of the new energy bus battery based on the historical charging information, and determine the battery loss information of the new energy bus based on the mileage loss information and the charging loss information.
[0043] This solution aims to achieve more accurate energy consumption monitoring and charging reminders for new energy buses by comprehensively considering the battery loss, real-time road conditions and historical operation data of new energy buses, thereby improving the efficiency of vehicle operation and dispatching.
[0044] Among them, the energy consumption monitoring method of the new energy bus of this application is triggered before the new energy bus departs, or when the new energy bus arrives at the terminal and other set time nodes. First, the battery loss information of the current new energy bus is determined. In order to obtain and analyze the battery loss of the new energy bus, the historical mileage and historical charging information of the new energy bus is obtained, and the mileage loss and charging loss of the battery are determined based on this information, and finally the overall loss information of the battery is obtained comprehensively.
[0045] When collecting historical mileage, the total mileage of new energy buses is collected through interfaces such as the GPS tracking system, the on-board odometer, and the fleet management system. When collecting historical charging data, the start time, end time, charging amount (kWh), battery status before and after charging (such as SOC, i.e., power percentage) and other related charging information of new energy buses are obtained by calling interfaces such as the on-board battery management system (BMS). Based on the collected historical mileage and historical charging information, it is necessary to eliminate abnormal values, such as unreasonable long-distance driving records or abnormal charging data.
[0046] Then, by comparing the current total mileage of the new energy bus with the theoretical maximum mileage of the new bus (or the average maximum mileage of the same model of vehicles), the mileage loss information is calculated:
[0047] Mileage loss information = 1-(current total mileage / maximum mileage)*100%
[0048] The charging loss information is calculated by the ratio of the actual charging capacity of the most recent charge to the theoretical charging capacity (or average charging capacity) of the battery from low power to full power:
[0049] Charging loss information = 1-(actual charging amount / average charging amount)*100%
[0050] It should be noted that in the actual calculation process, the theoretical charge capacity needs to be adaptively adjusted according to the battery type, capacity and charging conditions.
[0051] It is understandable that based on the historical mileage data and mileage loss information, the life decay of each new energy bus battery can be evaluated. Similarly, the charging loss information can be used to determine the change in charging efficiency and analyze the energy loss during the charging process. Then, taking into account the battery's mileage loss and charging loss, a comprehensive battery loss information is formulated to evaluate the overall health of the new energy bus battery. The battery loss information is expressed as:
[0052] Battery loss information = α*mileage loss information + β charging loss information
[0053] Among them, α and β are weight coefficients set according to specific circumstances, which are used to balance the importance of mileage loss and charging loss. Based on the battery loss information, the vehicle management system can provide suggestions for maintenance, battery replacement or optimization of charging strategies, systematically collect, analyze and evaluate the battery loss of new energy buses, and provide a scientific basis for vehicle operation management and decision support.
[0054] Furthermore, after determining the battery loss information of the new energy bus based on the mileage loss information and the charging loss information, the method further includes:
[0055] Collect historical driving data of new energy buses, determine frequency information of specified driving behaviors based on the historical driving data, and adjust battery loss information based on the frequency information of specified driving behaviors.
[0056] In order to further refine and adjust the battery loss information, this application collects historical driving data of new energy buses, and determines the frequency of specific driving behaviors based on these data, and then adjusts the battery loss information.
[0057] First, historical driving data needs to be collected from the vehicle-mounted system or operation management system of the new energy bus. This data should include but not be limited to the following:
[0058] Driving time: The start and end time of each driving.
[0059] Mileage: The actual distance traveled during each trip.
[0060] Speed change: record of speed changes during driving, such as acceleration, deceleration, constant speed driving, etc.
[0061] Braking frequency: the number and intensity of braking operations.
[0062] Rapid Acceleration / Deceleration: The number and severity of rapid acceleration and deceleration events.
[0063] Loading conditions: the number of passengers or cargo carried by a vehicle at different time periods.
[0064] Next, the collected historical driving data needs to be analyzed to determine the frequency information of specific driving behaviors. These specific driving behaviors may include but are not limited to:
[0065] High-frequency braking: The number of braking operations per unit time exceeds a certain threshold.
[0066] Rapid acceleration: The vehicle accelerates rapidly from a stationary or low speed to a higher speed in a short period of time.
[0067] Sudden deceleration: The vehicle decelerates rapidly from a high speed to a lower speed or stops in a short period of time.
[0068] Heavy-load driving: The vehicle's passenger or cargo capacity exceeds a certain proportion of the rated load.
[0069] For each specific driving behavior, it is necessary to count its frequency of occurrence in historical driving data, that is, the proportion of the number of times the behavior occurs to the total number of driving times.
[0070] Based on the frequency information of the specified driving behavior, the initially determined battery loss information can be adjusted. Different driving behaviors have different effects on battery loss, so their effects on battery life need to be considered separately.
[0071] Among them, high-frequency braking and sudden acceleration / deceleration behaviors usually cause the battery to experience large current changes in a short period of time, thereby accelerating battery aging and loss. Therefore, if the frequency of these behaviors is high, the adjustment value of the battery loss information should be appropriately increased; for heavy-load driving behaviors, the vehicle's power demand will increase, thereby increasing the battery's discharge depth and cycle number, resulting in faster battery loss. Therefore, the frequency of heavy-load driving should also be used as an important factor in adjusting the battery loss information.
[0072] Finally, it is necessary to comprehensively consider the combined impact of mileage loss, charging loss, and the frequency of specific driving behaviors on battery loss, and make comprehensive adjustments to the battery loss information. This process can be achieved with the help of mathematical models or machine learning algorithms to ensure the accuracy and reliability of the adjustment results. For example, when it is determined that the frequency information of a certain driving behavior reaches a certain range, the above battery loss information is adjusted using the set adjustment coefficient. At the same time, as new data is continuously collected and analyzed, the battery loss model should be updated regularly to reflect the latest situation of battery loss during the actual operation of new energy buses. This helps vehicles and transportation operators to more accurately predict battery life, optimize charging strategies and scheduling plans, thereby improving vehicle and transportation operation efficiency and service quality.
[0073] Optionally, the specified driving behavior of the present application includes a predefined emergency start and emergency brake behavior, and the frequency information of the specified driving behavior is determined based on historical driving data, including:
[0074] The vehicle speed is calculated based on historical driving data to calculate the number of times the emergency start and emergency brake behavior of the new energy bus is triggered during the statistical period, and the frequency information of the specified driving behavior is calculated based on the number of triggers and the statistical period.
[0075] In the operation and management of new energy buses, designated driving behaviors such as predefined emergency start and emergency brake behaviors have an important impact on battery loss and vehicle maintenance. In order to accurately evaluate the contribution of these behaviors to battery loss, it is necessary to determine the frequency information of these behaviors based on historical driving data. Among them, it is necessary to clarify what emergency start and emergency brake behaviors are. This involves a large change in vehicle speed in a short period of time. Specifically, certain acceleration and deceleration thresholds can be set. When the acceleration or deceleration of the vehicle exceeds these thresholds, it is considered that an emergency start or emergency brake behavior has occurred. By extracting vehicle speed data from historical driving data, these data are usually recorded in the form of time series. The vehicle speed data is cleaned to remove outliers (such as erroneous readings caused by sensor failure) and missing values. At the same time, the vehicle speed data needs to be converted into acceleration or deceleration data for subsequent analysis. Based on the preprocessed vehicle speed data, the acceleration or deceleration at each time point is calculated. This involves differentiating and normalizing the vehicle speed data. The calculated acceleration / deceleration values are compared with the preset thresholds. Whenever the acceleration or deceleration exceeds its corresponding threshold, it is considered that a sudden start or sudden braking behavior has occurred, and the number of triggers is recorded. Select an appropriate statistical period according to the analysis requirements, such as daily, weekly or monthly. Divide the total number of triggers of sudden starts and sudden braking behaviors during the statistical period by the total duration of the statistical period (or the total number of driving times) to obtain the frequency information of the specified driving behavior. This frequency information can be expressed as the number of sudden starts and sudden braking behaviors per unit time (such as per hour) or per unit number of driving times. By analyzing the frequency of sudden starts and sudden braking behaviors in different time periods, different routes or different drivers, combining the frequency information of sudden starts and sudden braking behaviors with the battery loss information, and further refining the battery loss model, the impact of different driving behaviors on battery life can be more accurately evaluated.
[0076] S120, obtaining the real-time traffic flow information of each section of the current driving route of the new energy bus, as well as the historical average traffic flow information of each section of the current driving route corresponding to the prediction period, and determining the predicted traffic flow information of each section of the current driving route corresponding to the prediction period based on the real-time traffic flow information and the historical average traffic flow information.
[0077] Furthermore, the real-time traffic flow of each section on the current driving route is obtained through the traffic monitoring system or third-party data sources. The historical average traffic flow data of each section in the same time period is obtained by querying the historical database. Then, the real-time traffic flow information and the historical average traffic flow information are combined, and time series analysis, machine learning and other methods are used to predict the traffic flow of each section in the future.
[0078] Among them, the predicted traffic flow information for each section of the current driving route corresponding to the predicted period is determined based on the real-time traffic flow information and the historical average traffic flow information, including:
[0079] Obtain the first passenger flow impact coefficient preset based on the real-time traffic flow information and the second passenger flow impact coefficient preset based on the historical average traffic flow information, and weightedly calculate the predicted traffic flow information for each section of the current driving route corresponding to the predicted period based on the first passenger flow impact coefficient, the second passenger flow impact coefficient, the real-time traffic flow information and the historical average traffic flow information.
[0080] When determining the predicted traffic flow information for each section of the current driving route in the corresponding prediction period based on the real-time traffic flow information and the historical average traffic flow information, the first passenger flow impact coefficient a and the second passenger flow impact coefficient b are introduced. These two coefficients can respectively reflect the importance of real-time traffic flow and historical traffic flow to future traffic flow prediction. Among them, the first passenger flow impact coefficient is used to measure the importance of real-time traffic flow information in predicting future traffic flow. Usually, when the real-time data is very accurate and reflects the current traffic conditions, the value of the first passenger flow impact coefficient will be relatively high. The second passenger flow impact coefficient is used to measure the importance of historical average traffic flow information in predicting future traffic flow. Historical data can provide a reference for long-term trends and cyclical changes.
[0081] The current traffic volume of each road section on the current driving route is obtained in real time from the traffic monitoring system or sensor. The historical average traffic volume of each road section in the same time period (such as the same day and the same hour in the past week) is queried from the database. For each road section on the current driving route, within the forecast period (such as the next hour), the following formula is used for weighted calculation to obtain the forecast traffic flow information:
[0082] Predicted traffic flow information = a*real-time traffic flow information+b*historical average traffic flow information
[0083] Among them, the sum of the values of a and b should be 1 (or close to 1) to ensure the rationality of the weighted calculation. The specific values of these two coefficients can be adjusted according to the actual situation, the accuracy of historical data, the reliability of real-time data, and the performance of the prediction model. When the system is initialized, an initial value can be set for a and b based on experience or preliminary tests. As the system runs and data accumulates, the values of a and b can be dynamically adjusted by analyzing the deviation between the predicted results and the actual traffic flow to improve the accuracy of the prediction. In addition, machine learning algorithms such as linear regression and random forests can be introduced to automatically learn and optimize the values of a and b to adapt to the dynamic changes in traffic flow. The predicted traffic information obtained based on the above calculation can be applied to the subsequent power consumption prediction and charging reminder logic to achieve more accurate energy consumption monitoring and scheduling of new energy buses.
[0084] S130, obtaining the historical number of passengers on each section of the current driving route of the new energy bus during the predicted period, predicting the power consumption of each section according to the predicted traffic information and the historical number of passengers, and determining the total power consumption of the route based on the power consumption of each section.
[0085] In order to predict the power consumption of new energy buses in each section during the forecast period, it is necessary to obtain the historical passenger data of new energy buses in each section (or between stations). These data may come from the ticketing system or passenger counting system of the vehicle company. At the same time, collect the historical traffic data of each section, including traffic volume, speed, etc. These data may come from traffic monitoring cameras, GPS tracking systems or databases of traffic management departments.
[0086] In addition, by reading the power consumption data of the new energy bus in the corresponding scenario, the power consumption data of the new energy bus under different loads and speeds can be determined.
[0087] Based on the collected data, the number of passengers, traffic information and power consumption data are matched by time and road section. Then extract the features that have a significant impact on power consumption, such as time period (peak hours in the morning and evening, flat peak), weather conditions, road section type (urban main roads, secondary roads, branch roads), etc. By analyzing the above historical data, identify the correlation between power consumption and factors such as the number of passengers, traffic density, and vehicle speed. Then, according to the data characteristics and analysis results, select a suitable prediction model, such as linear regression, multivariate linear regression, random forest, gradient boosting tree (GBDT) or neural network. If the data volume is large and the relationship is complex, a deep learning model can also be used. Train the model by using historical data and evaluate the performance of the model through methods such as cross-validation. Adjust the model parameters to optimize the prediction accuracy. Then input the previously predicted traffic information and the corresponding historical number of passengers into the power consumption model to obtain the power consumption prediction value of each road section during the prediction period.
[0088] It is understandable that the power consumption of new energy buses varies with different numbers of passengers and traffic conditions. By combining the predicted traffic information of each section with the corresponding historical number of passengers, the power consumption of new energy buses in each section under the corresponding load and vehicle conditions can be accurately predicted. Then, the predicted power consumption of each section is accumulated to obtain the total power consumption of the entire driving route.
[0089] Optionally, refer to Figure 2 , based on the predicted traffic flow information and historical passenger numbers, the power consumption of each road section is predicted, including:
[0090] S1301, determining the passing time and passing speed of the new energy bus on the corresponding road section according to the predicted traffic flow information, and calculating the basic power consumption based on the passing time and passing speed;
[0091] S1302: Calculate additional power consumption based on the historical number of passengers, and calculate the power consumption of each road section based on the basic power consumption and the additional power consumption.
[0092] Based on the predicted traffic volume and section length, the average passing time of new energy buses on the section is estimated. The average passing time of new energy buses on the section is estimated by dividing the section length by the average vehicle speed (which can be adjusted based on historical data or real-time traffic conditions). Similarly, based on the predicted traffic volume and possible traffic congestion, the average driving speed of new energy buses on the section is estimated, that is, the passing speed.
[0093] Then, the estimated passing time and passing speed are converted into basic power consumption using the energy consumption model of new energy buses or the relationship between energy consumption, speed and time in historical data. This model needs to consider factors such as vehicle type, vehicle load (although this step does not directly involve the number of passengers, it can be indirectly considered through historical data), and road conditions (such as slope and road surface conditions).
[0094] Then, the relationship between the number of historical passengers and the power consumption of new energy buses is analyzed. Generally, an increase in the number of passengers will lead to an increase in the load of systems such as air conditioning and lighting, thereby increasing power consumption. Based on the relationship between the number of passengers and the increase in power consumption in the historical data, an estimation model is established. This model can be linear or nonlinear, depending on the distribution characteristics of the actual data. Using this model, the historical average number of passengers (or the predicted number of passengers, if available) for each section during the forecast period is used as input to calculate the additional power consumption caused by the increase in the number of passengers. The above basic power consumption is added to the calculated additional power consumption to obtain the power consumption of the new energy bus for each section during the forecast period.
[0095] Optionally, the above calculation of additional power consumption based on the historical number of passengers includes:
[0096] Based on the historical number of passengers, a pre-constructed correlation curve between the number of passengers and the additional power consumption is queried to obtain the corresponding power consumption correlation coefficient, and the additional power consumption is calculated based on the historical number of passengers and the power consumption correlation coefficient.
[0097] In order to calculate the additional power consumption based on the historical number of passengers, that is, to consider the additional impact of the increase in the number of passengers on the energy consumption of new energy buses, this application calculates by constructing a correlation curve between the number of passengers and the additional power consumption. First, by collecting the actual power consumption data of new energy buses under different numbers of passengers, the collected data is cleaned and sorted to ensure the accuracy and consistency of the data. Use statistical analysis or machine learning methods to analyze the relationship between the number of passengers and power consumption. A scatter plot can be drawn to observe the distribution trend of the data points, and try to fit a curve (such as linear, polynomial, exponential, etc.) to describe this relationship. The accuracy and generalization ability of the fitting curve are verified by methods such as cross-validation or retention. After constructing the correlation curve between the number of passengers and the additional power consumption, it can be converted into a queryable model or table. When it is necessary to calculate the additional power consumption under a specific number of passengers, the power consumption correlation coefficient can be queried in the following way. If the correlation curve is given in the form of a mathematical expression, the number of passengers can be directly substituted into the expression to calculate the power consumption correlation coefficient. If the correlation curve is stored in the form of a table, the corresponding power consumption correlation coefficient can be found in the table according to the number of passengers by looking up the table. Finally, based on the queried power consumption correlation coefficient and the number of passengers on the current road section, the additional power consumption of the road section is calculated by multiplying the two.
[0098] Optionally, after predicting the power consumption of each road section according to the predicted traffic flow information and the historical number of passengers, the method further includes:
[0099] Acquire real-time temperature information. When the real-time temperature reaches a set temperature threshold, determine a power consumption growth coefficient based on the temperature difference between the real-time temperature and the set temperature threshold, and adjust the power consumption of each road section based on the power consumption growth coefficient.
[0100] In the prediction of power consumption of new energy buses, in addition to considering the predicted traffic information and the historical number of passengers, the real-time temperature is also an important influencing factor. High or low temperature conditions may increase the power consumption of new energy buses because the air conditioning system requires more energy to maintain a comfortable temperature inside the car. Therefore, after predicting the power consumption of each section based on the predicted traffic information and the historical number of passengers, the impact of the real-time temperature on power consumption can be further considered and the prediction results can be adjusted accordingly.
[0101] Among them, the real-time temperature information of the new energy bus during driving is obtained through the meteorological data interface or the on-board meteorological sensor. According to the operating experience and vehicle performance of the new energy bus, one or more temperature thresholds are set. These thresholds are used to determine whether the current temperature will have a significant impact on the power consumption of the new energy bus. For example, a high temperature threshold (such as 30°C) and a low temperature threshold (such as 5°C) can be set. When the real-time temperature exceeds or falls below these thresholds, it is considered that the power consumption forecast needs to be adjusted. The real-time temperature is compared with the set temperature threshold to determine whether the current temperature has reached the condition that the power consumption needs to be adjusted. If the real-time temperature reaches the set temperature threshold, the power consumption growth coefficient is determined according to the temperature difference between the real-time temperature and the set temperature threshold. This coefficient reflects the degree of influence of temperature changes on the power consumption of the new energy bus. Generally, the larger the temperature difference, the larger the power consumption growth coefficient, indicating that the power consumption increases more. The determined power consumption growth coefficient is applied to the power consumption of each section previously predicted based on the predicted traffic information and the historical number of passengers, and the power consumption is adjusted accordingly. Specifically, the predicted power consumption of each section can be multiplied by the power consumption growth coefficient to obtain the adjusted power consumption forecast value. Through the above steps, the impact of real-time temperature on the power consumption of new energy buses can be more comprehensively considered, thereby obtaining more accurate power consumption prediction results, providing strong support for the operation management and energy conservation and emission reduction of new energy buses.
[0102] S140, setting a charging reminder threshold for the new energy bus based on the battery loss information, reading the real-time power information of the new energy bus, and providing a charging reminder for the new energy bus based on the real-time power information, the total power consumption of the route and the charging reminder threshold for the new energy bus.
[0103] Finally, the power threshold of the charging reminder is dynamically adjusted according to the battery loss information of the new energy bus (including mileage loss and charging loss). For example, for vehicles with large battery loss, the threshold can be appropriately increased to remind charging in advance. The current power information of the new energy bus is read in real time through the on-board system. Then compare the real-time power, the total power consumption of the route and the charging reminder threshold. If the real-time power minus the total power consumption of the route is lower than the charging reminder threshold, the charging reminder is triggered to remind the driver to go to the charging station in time.
[0104] After that, after each charging event, the battery loss model and historical charging information are updated to optimize the accuracy of future predictions and prompts. The implementation effect of the energy consumption monitoring and charging prompt system is regularly evaluated, including the operating efficiency and energy consumption cost of new energy buses, and the optimization strategy is adjusted according to the evaluation results. Through the above process, accurate monitoring of energy consumption and charging prompts for new energy buses can be achieved, effectively reducing monitoring errors and improving the intelligent level of vehicle operation and scheduling.
[0105] In the above, by obtaining the historical mileage and historical charging information of the new energy bus, the mileage loss information of the new energy bus battery is determined based on the historical mileage, the charging loss information of the new energy bus battery is determined based on the historical charging information, and the battery loss information of the new energy bus is determined based on the mileage loss information and the charging loss information; the real-time traffic flow information of each section of the current driving route of the new energy bus and the historical average traffic flow information of each section of the current driving route corresponding to the prediction period are obtained, and the predicted traffic flow information of each section of the current driving route corresponding to the prediction period is determined according to the real-time traffic flow information and the historical average traffic flow information; the historical number of passengers in each section of the current driving route of the new energy bus in the prediction period is obtained, the power consumption of each section is predicted according to the predicted traffic flow information and the historical number of passengers, and the total power consumption of the route is determined based on the power consumption of each section; the charging reminder threshold of the new energy bus is set based on the battery loss information, the real-time power information of the new energy bus is read, and the charging reminder of the new energy bus is given based on the real-time power information, the total power consumption of the route and the charging reminder threshold of the new energy bus. By adopting the above-mentioned technical means, the charging reminder threshold is set according to the real-time battery loss information of the new energy bus, and the total power consumption of the route is determined according to the predicted traffic information and the historical number of passengers. The real-time power information of the new energy bus, the total power consumption of the route and the charging reminder threshold of the new energy bus are combined to provide charging reminders for the new energy bus, so as to realize accurate energy consumption monitoring of the new energy bus, promptly remind the driver to recharge the vehicle, avoid affecting the line operation, and optimize the line operation effect.
[0106] Embodiment 2:
[0107] Based on the above embodiments, Figure 3 This is a schematic diagram of the structure of a new energy bus energy consumption monitoring device provided in Example 2 of this application. Figure 3 The energy consumption monitoring device for new energy buses provided in this embodiment specifically includes:
[0108] The loss determination module 21 is used to obtain the historical mileage and historical charging information of the new energy bus, determine the mileage loss information of the battery of the new energy bus based on the historical mileage, determine the charging loss information of the battery of the new energy bus based on the historical charging information, and determine the battery loss information of the new energy bus based on the mileage loss information and the charging loss information;
[0109] The traffic flow prediction module 22 is used to obtain the real-time traffic flow information of each section of the current driving path of the new energy bus, as well as the historical average traffic flow information of each section of the current driving path corresponding to the prediction period, and determine the predicted traffic flow information of each section of the current driving path corresponding to the prediction period according to the real-time traffic flow information and the historical average traffic flow information;
[0110] The power prediction module 23 is used to obtain the historical number of passengers in each section of the current driving route of the new energy bus during the prediction period, predict the power consumption of each section according to the predicted traffic flow information and the historical number of passengers, and determine the total power consumption of the route based on the power consumption of each section;
[0111] The prompt module 24 is used to set the charging prompt threshold of the new energy bus based on the battery loss information, read the real-time power information of the new energy bus, and provide charging prompts for the new energy bus based on the real-time power information, the total power consumption of the route and the charging prompt threshold of the new energy bus.
[0112] Furthermore, the predicted traffic flow information for each section of the current driving route corresponding to the predicted time period is determined based on the real-time traffic flow information and the historical average traffic flow information, including:
[0113] Obtain the first passenger flow impact coefficient preset based on the real-time traffic flow information and the second passenger flow impact coefficient preset based on the historical average traffic flow information, and weightedly calculate the predicted traffic flow information for each section of the current driving route corresponding to the predicted period based on the first passenger flow impact coefficient, the second passenger flow impact coefficient, the real-time traffic flow information and the historical average traffic flow information.
[0114] Furthermore, the power consumption of each road section is predicted based on the predicted traffic flow information and the historical number of passengers, including:
[0115] Determine the passing time and passing speed of new energy buses on the corresponding road section based on the predicted traffic flow information, and calculate the basic power consumption based on the passing time and passing speed;
[0116] The additional power consumption is calculated based on the historical number of passengers, and the power consumption of each road section is calculated based on the basic power consumption and the additional power consumption.
[0117] Furthermore, the additional power consumption is calculated based on the historical number of passengers, including:
[0118] Based on the historical number of passengers, a pre-constructed correlation curve between the number of passengers and the additional power consumption is queried to obtain the corresponding power consumption correlation coefficient, and the additional power consumption is calculated based on the historical number of passengers and the power consumption correlation coefficient.
[0119] Furthermore, after determining the battery loss information of the new energy bus based on the mileage loss information and the charging loss information, the method further includes:
[0120] Collect historical driving data of new energy buses, determine frequency information of specified driving behaviors based on the historical driving data, and adjust battery loss information based on the frequency information of specified driving behaviors.
[0121] Furthermore, the designated driving behavior includes a predefined sudden start and stop behavior, and the frequency information of the designated driving behavior is determined based on the historical driving data, including:
[0122] The vehicle speed is calculated based on historical driving data to calculate the number of times the emergency start and emergency brake behavior of the new energy bus is triggered during the statistical period, and the frequency information of the specified driving behavior is calculated based on the number of triggers and the statistical period.
[0123] Furthermore, after predicting the power consumption of each road section according to the predicted traffic flow information and the historical number of passengers, it also includes:
[0124] Real-time temperature information is obtained. When the real-time temperature reaches a set temperature threshold, a power consumption growth coefficient is determined according to the temperature difference between the real-time temperature and the set temperature threshold, and the power consumption of each road section is adjusted based on the power consumption growth coefficient.
[0125] In the above, by obtaining the historical mileage and historical charging information of the new energy bus, the mileage loss information of the new energy bus battery is determined based on the historical mileage, the charging loss information of the new energy bus battery is determined based on the historical charging information, and the battery loss information of the new energy bus is determined based on the mileage loss information and the charging loss information; the real-time traffic flow information of each section of the current driving route of the new energy bus and the historical average traffic flow information of each section of the current driving route corresponding to the prediction period are obtained, and the predicted traffic flow information of each section of the current driving route corresponding to the prediction period is determined according to the real-time traffic flow information and the historical average traffic flow information; the historical number of passengers in each section of the current driving route of the new energy bus in the prediction period is obtained, the power consumption of each section is predicted according to the predicted traffic flow information and the historical number of passengers, and the total power consumption of the route is determined based on the power consumption of each section; the charging reminder threshold of the new energy bus is set based on the battery loss information, the real-time power information of the new energy bus is read, and the charging reminder of the new energy bus is given based on the real-time power information, the total power consumption of the route and the charging reminder threshold of the new energy bus. By adopting the above-mentioned technical means, the charging reminder threshold is set according to the real-time battery loss information of the new energy bus, and the total power consumption of the route is determined according to the predicted traffic information and the historical number of passengers. The real-time power information of the new energy bus, the total power consumption of the route and the charging reminder threshold of the new energy bus are combined to provide charging reminders for the new energy bus, so as to realize accurate energy consumption monitoring of the new energy bus, promptly remind the driver to recharge the vehicle, avoid affecting the line operation, and optimize the line operation effect.
[0126] The new energy bus energy consumption monitoring device provided in the second embodiment of the present application can be used to execute the new energy bus energy consumption monitoring method provided in the above-mentioned first embodiment, and has corresponding functions and beneficial effects.
[0127] Embodiment three:
[0128] Embodiment 3 of the present application provides an electronic device, referring to Figure 4The electronic device includes: a processor 31, a memory 32, a communication module 33, an input device 34 and an output device 35. The number of processors in the electronic device can be one or more, and the number of memories in the electronic device can be one or more. The processor, memory, communication module, input device and output device of the electronic device can be connected via a bus or other means.
[0129] As a computer-readable storage medium, the memory can be used to store software programs, computer executable programs and modules, such as the program instructions / modules corresponding to the new energy bus energy consumption monitoring method described in any embodiment of the present application (for example, the various modules in the new energy bus energy consumption monitoring device). The memory may mainly include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function; the data storage area may store data created according to the use of the device, etc. In addition, the memory may include a high-speed random access memory, and may also include a non-volatile memory, such as at least one disk storage device, a flash memory device, or other non-volatile solid-state storage device. In some instances, the memory may further include a memory remotely arranged relative to the processor, and these remote memories may be connected to the device via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0130] The communication module is used for data transmission.
[0131] The processor executes various functional applications and data processing of the device by running the software programs, instructions and modules stored in the memory, that is, realizes the above-mentioned new energy bus energy consumption monitoring method.
[0132] The input device can be used to receive input digital or character information and generate key signal input related to user settings and function control of the device. The output device can include display devices such as display screens.
[0133] The electronic device provided above can be used to execute the new energy bus energy consumption monitoring method provided in the above embodiment 1, and has corresponding functions and beneficial effects.
[0134] Embodiment 4:
[0135] The embodiment of the present application also provides a storage medium containing computer executable instructions, which are used to execute a new energy bus energy consumption monitoring method when executed by a computer processor. The new energy bus energy consumption monitoring method includes: obtaining historical mileage and historical charging information of the new energy bus, determining mileage loss information of the new energy bus battery based on the historical mileage, determining charging loss information of the new energy bus battery based on the historical charging information, and determining battery loss information of the new energy bus based on the mileage loss information and the charging loss information; obtaining real-time traffic flow information of each section of the current driving route of the new energy bus, and each section of the current driving route; The historical average traffic flow information of the road section corresponding to the prediction period, determine the predicted traffic flow information of each section of the current driving route corresponding to the prediction period based on the real-time traffic flow information and the historical average traffic flow information; obtain the historical number of passengers in each section of the current driving route of the new energy bus during the prediction period, predict the power consumption of each section based on the predicted traffic flow information and the historical number of passengers, and determine the total power consumption of the route based on the power consumption of each section; set the charging reminder threshold of the new energy bus based on the battery loss information, read the real-time power information of the new energy bus, and provide charging reminders for the new energy bus based on the real-time power information, the total power consumption of the route and the charging reminder threshold of the new energy bus.
[0136] Storage medium - any of various types of memory devices or storage devices. The term "storage medium" is intended to include: installation media, such as CD-ROM, floppy disk or tape device; computer system memory or random access memory, such as DRAM, DDR RAM, SRAM, EDO RAM, Rambus RAM, etc.; non-volatile memory, such as flash memory, magnetic media (such as hard disk or optical storage); registers or other similar types of memory elements, etc. Storage media may also include other types of memory or combinations thereof. In addition, the storage medium may be located in the first computer system in which the program is executed, or may be located in a different second computer system, which is connected to the first computer system via a network (such as the Internet). The second computer system can provide program instructions to the first computer for execution. The term "storage medium" may include two or more storage media residing in different locations (for example, in different computer systems connected by a network). The storage medium may store program instructions (for example, embodied as a computer program) that can be executed by one or more processors.
[0137] Of course, the storage medium containing computer executable instructions provided in the embodiment of the present application is not limited to the new energy bus energy consumption monitoring method described above, and can also execute related operations in the new energy bus energy consumption monitoring method provided in any embodiment of the present application.
[0138] The new energy bus energy consumption monitoring device, storage medium and electronic device provided in the above embodiments can execute the new energy bus energy consumption monitoring method provided in any embodiment of the present application. For technical details not described in detail in the above embodiments, please refer to the new energy bus energy consumption monitoring method provided in any embodiment of the present application.
[0139] The above are only preferred embodiments of the present application and the technical principles used. The present application is not limited to the specific embodiments described herein, and various obvious changes, readjustments and substitutions that can be made by those skilled in the art will not deviate from the scope of protection of the present application. Therefore, although the present application is described in more detail through the above embodiments, the present application is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present application, and the scope of the present application is determined by the scope of the claims.
Claims
1. A method for monitoring energy consumption of a new energy bus, characterized in that: include: Acquire historical mileage and historical charging information of the new energy bus, determine mileage loss information of the new energy bus battery based on the historical mileage, determine charging loss information of the new energy bus battery based on the historical charging information, and determine battery loss information of the new energy bus based on the mileage loss information and the charging loss information; Acquire the real-time traffic flow information of each section of the current driving route of the new energy bus, as well as the historical average traffic flow information of each section of the current driving route corresponding to the prediction period, and determine the predicted traffic flow information of each section of the current driving route corresponding to the prediction period according to the real-time traffic flow information and the historical average traffic flow information; Obtain the historical number of passengers on each section of the current driving route of the new energy bus during the predicted period, predict the power consumption of each section according to the predicted traffic flow information and the historical number of passengers, and determine the total power consumption of the route based on the power consumption of each section; A charging reminder threshold of the new energy bus is set based on the battery loss information, real-time power information of the new energy bus is read, and a charging reminder for the new energy bus is given based on the real-time power information, the total power consumption of the route and the charging reminder threshold of the new energy bus.
2. The method for monitoring energy consumption of new energy buses according to claim 1, characterized in that: The step of determining predicted traffic flow information corresponding to a predicted time period for each road section of the current driving route according to the real-time traffic flow information and the historical average traffic flow information includes: Obtain a first passenger flow impact coefficient preset in the real-time traffic flow information and a second passenger flow impact coefficient preset in the historical average traffic flow information, and weightedly calculate the predicted traffic flow information for each section of the current driving route corresponding to the predicted time period based on the first passenger flow impact coefficient, the second passenger flow impact coefficient, the real-time traffic flow information and the historical average traffic flow information.
3. The method for monitoring energy consumption of new energy buses according to claim 1, characterized in that: The predicting the power consumption of each road section according to the predicted traffic flow information and the historical number of passengers includes: Determine the passing time and passing speed of the new energy bus on the corresponding road section according to the predicted traffic flow information, and calculate the basic power consumption based on the passing time and the passing speed; The additional power consumption is calculated based on the historical number of passengers, and the power consumption of each road section is calculated according to the basic power consumption and the additional power consumption.
4. The method for monitoring energy consumption of new energy buses according to claim 3 is characterized in that: The calculating the additional power consumption based on the historical number of passengers comprises: Based on the historical number of passengers, a pre-constructed correlation curve between the number of passengers and the additional power consumption is queried to obtain a corresponding power consumption correlation coefficient, and the additional power consumption is calculated based on the historical number of passengers and the power consumption correlation coefficient.
5. The method for monitoring energy consumption of new energy buses according to claim 1, characterized in that: After determining the battery loss information of the new energy bus based on the mileage loss information and the charging loss information, the method further includes: Collect historical driving data of new energy buses, determine frequency information of specified driving behaviors based on the historical driving data, and adjust the battery loss information based on the frequency information of the specified driving behaviors.
6. The method for monitoring energy consumption of new energy buses according to claim 5, characterized in that: The specified driving behavior includes a predefined sudden start and sudden brake behavior, and the frequency information of the specified driving behavior is determined based on the historical driving data, including: The number of times the sudden start and stop behavior of the new energy bus is triggered in the statistical period is calculated based on the historical driving data and the statistical speed, and the frequency information of the specified driving behavior is calculated based on the triggering number and the statistical period.
7. The method for monitoring energy consumption of new energy buses according to claim 1, characterized in that: After predicting the power consumption of each road section according to the predicted traffic flow information and the historical number of passengers, the method further includes: Real-time temperature information is obtained. When the real-time temperature reaches a set temperature threshold, a power consumption growth coefficient is determined according to the temperature difference between the real-time temperature and the set temperature threshold, and the power consumption of each road section is adjusted based on the power consumption growth coefficient.
8. A new energy bus energy consumption monitoring device, characterized in that: include: A loss determination module, used to obtain historical mileage and historical charging information of the new energy bus, determine the mileage loss information of the new energy bus battery based on the historical mileage, determine the charging loss information of the new energy bus battery based on the historical charging information, and determine the battery loss information of the new energy bus based on the mileage loss information and the charging loss information; The traffic flow prediction module is used to obtain the real-time traffic flow information of each section of the current driving route of the new energy bus, as well as the historical average traffic flow information of each section of the current driving route corresponding to the prediction period, and determine the predicted traffic flow information of each section of the current driving route corresponding to the prediction period according to the real-time traffic flow information and the historical average traffic flow information; The power prediction module is used to obtain the historical number of passengers in each section of the current driving route of the new energy bus during the prediction period, predict the power consumption of each section according to the predicted traffic information and the historical number of passengers, and determine the total power consumption of the route based on the power consumption of each section; The prompt module is used to set the charging prompt threshold of the new energy bus based on the battery loss information, read the real-time power information of the new energy bus, and provide charging prompts for the new energy bus based on the real-time power information, the total power consumption of the route and the charging prompt threshold of the new energy bus.
9. An electronic device, characterized in that: include: memory and one or more processors; The memory is used to store one or more programs; When the one or more programs are executed by the one or more processors, the one or more processors implement the new energy bus energy consumption monitoring method as described in any one of claims 1-7.
10. A storage medium containing computer executable instructions, characterized in that: The computer executable instructions, when executed by a computer processor, are used to execute the new energy bus energy consumption monitoring method as described in any one of claims 1-7.