Semiconductor wastewater water quality predictable maintenance method and system
The neural network model combined with the decision tree is used to analyze the water quality and consumable consumption of semiconductor wastewater treatment equipment to achieve prediction and dynamic management of future consumption, solve the problem of redundant equipment and consumables occupying space and management costs, and improve the adaptability of the system. sex and efficiency.
Patent Information
- Application Number
- CN202410972362.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-19
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-19
AI Technical Summary
In the wastewater treatment of semiconductor production lines in the existing technology, redundant equipment and consumables occupy extra space and increase management costs, and it is difficult to respond to demand changes in real time.
By obtaining the water quality, consumables and chemical usage of the semiconductor wastewater filtration equipment, we use the neural network model combined with the decision tree to conduct data analysis, predict future consumption, realize online inventory and inspection management, and dynamically update the maintenance plan.
It reduces maintenance costs, reduces the need for redundant equipment and consumables, improves the adaptability and efficiency of the system, and ensures that wastewater treatment meets standards and equipment operates normally.
Smart Images

Figure CN118754229A_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the field of wastewater treatment, and in particular to a method and system for predictably maintaining the water quality of semiconductor wastewater. Background Art
[0002] A lot of wastewater is generated in each semiconductor production process, and the total wastewater collected needs to reduce the concentration of harmful pollutants to a certain extent when discharged. In the prior art, the production line usually needs to detect the type and concentration of pollutants generated in each process, and sensors need to be installed in the corresponding discharge pipes to achieve this. Similarly, it is also necessary to remove or reduce the corresponding pollutants through relevant purification processes. For example, US20220365058A1 discloses pollutant analysis devices 100A, 100B and 100C on semiconductor production lines for detecting the ion components of pollutants contained in the effluent water; it also includes a pretreatment sampler 110 to achieve multiple filtration (including a first filter 114 and a second filter 116).
[0003] However, since the production capacity or pollutant emissions of semiconductor production lines are not fixed, the life of the sensors used for monitoring and the amount of consumables used for filtering and purifying pollutants are also not fixed. Of course, if there is sufficient funding, suppliers or consumables providers for sewage treatment can be required to provide redundant related equipment or consumables. However, in actual situations, such redundant equipment or consumables require additional storage space and management costs. Most semiconductor manufacturers will not pay extra for the redundant costs, and suppliers or consumables providers cannot know the required amount of redundancy. Therefore, it is necessary to cooperate with semiconductor manufacturers to achieve predictable maintenance of semiconductor wastewater quality, that is, to predict the equipment that needs to be replaced or maintained based on usage. Moreover, since the needs of semiconductor manufacturers are constantly changing, the system also needs to be able to update the maintenance method in real time, thereby reducing additional management, procurement and maintenance costs. Summary of the invention
[0004] The present disclosure provides a semiconductor wastewater water quality predictable maintenance method and system thereof to solve the problems existing in the related technologies. The technical solution is as follows: In a first aspect, the present disclosure provides a method for predictable maintenance of semiconductor wastewater quality, comprising the following steps: Obtain the water quality before and after treatment of semiconductor wastewater filtration equipment, the use of filtration consumables and the use of chemicals; Determine an operation and maintenance work order based on water quality, usage of filtration consumables and reagents, wherein the content of the operation and maintenance work order includes equipment maintenance items, online inventory of filtration consumables and reagents, and acquisition of on-site water quality sampling and measurement data, and update the data involved in the content to obtain updated data; Based on the updated data from operation and maintenance work order feedback and the expected amount of semiconductor wastewater to be treated, the future consumption of filtration consumables and chemicals is predicted, and then online inventory and inspection management are carried out to achieve predictable maintenance. Optionally, based on the updated data fed back by the operation and maintenance work order and the expected amount of semiconductor wastewater to be treated, the consumption of future filtration consumables and reagents is predicted, including: Collect historical operation and maintenance work order data, including the usage records of consumables and medicines; Collect historical on-site water quality sampling measurements; Performing data cleaning on the historical operation and maintenance work order data and the historical on-site water quality sampling and measurement data, processing missing values and removing outliers; According to historical on-site water quality sampling measurement data, on-site water quality data, historical expected water quality data and water quantity data, the change characteristics of water quality and quantity before and after treatment are extracted, and a relationship model between the change characteristics and the consumption of consumables and agents is constructed; the relationship model can be trained by a machine learning model of a decision tree neural network model, and the decision tree is used as the input layer of the neural network model. The decision tree is used to extract the change characteristics, and the extracted change characteristics are used to train the neural network model to adjust the model parameters in the neural network model; Collect data on the volume of semiconductor wastewater expected to be treated; Use the trained neural network model to predict the future consumption of consumables and chemicals. When determining the operation and maintenance work orders and inspection management, assign the operation and maintenance work orders and inspection management to the same or several staff members.
[0005] Optionally, the water quality of the semiconductor wastewater filtration equipment before and after treatment, the use of filtration consumables and the use of chemicals are obtained, including: The water quality is obtained by regularly sampling and chemically analyzing the wastewater before and after treatment and feeding back the results; The usage of filtering consumables and chemicals is obtained through the consumables usage records and chemical usage records.
[0006] Optionally, an operation and maintenance work order is determined based on water quality, usage of filtration consumables, and usage of chemicals, including: Determine the filtration efficiency of semiconductor wastewater filtration equipment based on past water quality, usage of filtration consumables and reagents, and determine the equipment maintenance items required for semiconductor wastewater filtration equipment based on the filtration efficiency; Generate an operation and maintenance work order based on the local inventory status of equipment maintenance items, filtration consumables, and chemicals to update the above update data.
[0007] Optionally, the filtration efficiency of the semiconductor wastewater filtration equipment is determined based on past water quality conditions, usage of filtration consumables, and usage of reagents, including: The filtration efficiency is determined by the past water quality of the semiconductor wastewater filtration equipment, the amount of wastewater treated, and the use of filtration consumables and reagents, as shown below: in, is the filtration efficiency, For the cost of past consumables, The cost of past drug use, Indicates the difference in water quality before and after wastewater treatment. is the wastewater quality before wastewater treatment, It represents the quality of wastewater before treatment, and A represents the amount of wastewater treated.
[0008] Optionally, based on the updated data fed back by the operation and maintenance work order and the expected amount of semiconductor wastewater to be treated, the consumption of future filtration consumables and reagents is predicted, including: Based on the filtration efficiency, the on-site water quality sampling measurement data in the update data, and the expected amount of semiconductor wastewater to be treated, the expected filtration consumables and reagents to be used are calculated and expressed as follows:
[0009] in, For the future consumption of filtration consumables, For future drug consumption, is the filtration efficiency, To collect water quality samples and measure data on site, is the expected water quality data, The amount of semiconductor wastewater expected to be treated.
[0010] Optionally, online inventory and inspection management are performed to achieve predictable maintenance, including: formulating online inventory management based on the expected use of filtration consumables and chemicals and the online inventory of filtration consumables and chemicals, and formulating inspection plans for the actual consumption and operation of filtration consumables and chemicals of the semiconductor wastewater filtration equipment.
[0011] As another aspect of the present disclosure, a semiconductor wastewater water quality predictable maintenance system is provided, comprising: A historical data acquisition unit, which acquires the water quality before and after treatment by the semiconductor wastewater filtration equipment, the usage of filtration consumables, and the usage of chemicals; An operation and maintenance work order generation and data update unit determines an operation and maintenance work order based on water quality, usage of filtration consumables and reagents, wherein the content of the operation and maintenance work order includes equipment maintenance items, online inventory of filtration consumables and reagents, and acquisition of on-site water quality sampling and measurement data, and updates the data involved in the content to obtain updated data; The predictive maintenance unit predicts the future consumption of filtration consumables and chemicals based on the updated data fed back from the operation and maintenance work orders and the expected amount of semiconductor wastewater to be treated, and then conducts online inventory and inspection management to achieve predictive maintenance.
[0012] As another aspect of an embodiment of the present disclosure, there is provided an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the method for predictable maintenance of water quality of semiconductor wastewater when executing the computer program.
[0013] As another aspect of an embodiment of the present disclosure, a computer-readable storage medium is provided, on which a computer program is stored, and when the program is executed by a processor, the method for predictable maintenance of water quality of semiconductor wastewater is implemented.
[0014] The advantages or beneficial effects of the above technical solution include at least: Predictable maintenance of filtration consumables and chemicals can be achieved based on the operating conditions, inventory conditions and expected amount of semiconductor wastewater to be treated of the semiconductor wastewater filtration equipment, solving the problem of redundant equipment or consumables in the prior art that require additional storage space and management costs. While ensuring that wastewater treatment meets standards and that the equipment operates normally and healthily, maintenance costs are also reduced. System operation data and online inventory conditions can also be regularly updated based on feedback from operation and maintenance work orders. The use of a neural network model combined with a decision tree can make the system more adaptable to changes and can be used to update maintenance plans in real time [1], making the entire system more adaptable.
[0015] The above summary is for illustrative purposes only and is not intended to be limiting in any way. In addition to the illustrative aspects, embodiments and features described above, further aspects, embodiments and features of the present disclosure will be readily apparent by reference to the accompanying drawings and the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In the accompanying drawings, unless otherwise specified, the same reference numerals throughout the multiple drawings represent the same or similar parts or elements. These drawings are not necessarily drawn to scale. It should be understood that these drawings only depict some embodiments disclosed in accordance with the present disclosure and should not be regarded as limiting the scope of the present disclosure.
[0017] Figure 1 It is a flow chart of the predictable maintenance method of semiconductor wastewater water quality according to Example 1 of the present disclosure; Figure 2 This is a schematic diagram of the predictable maintenance method in Example 1 of the present disclosure; Figure 3 This is a schematic diagram of the predictable maintenance system for semiconductor wastewater quality. DETAILED DESCRIPTION
[0018] Various exemplary embodiments, features and aspects of the present disclosure will be described in detail below with reference to the accompanying drawings. The same reference numerals in the accompanying drawings represent elements with the same or similar functions. Although various aspects of the embodiments are shown in the accompanying drawings, the drawings are not necessarily drawn to scale unless otherwise specified.
[0019] The word “exemplary” is used exclusively herein to mean “serving as an example, example, or illustration.” Any embodiment described herein as “exemplary” is not necessarily to be construed as preferred or advantageous over other embodiments.
[0020] The term "and / or" herein is only a description of the association relationship of the associated objects, indicating that there may be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the term "at least one" herein represents any combination of at least two of any one or more of a plurality of. For example, including at least one of A, B, and C can represent including any one or more elements selected from the set consisting of A, B, and C.
[0021] In addition, in order to better illustrate the present disclosure, numerous specific details are given in the following specific embodiments. It should be understood by those skilled in the art that the present disclosure can also be implemented without certain specific details. In some examples, methods, means, components and circuits well known to those skilled in the art are not described in detail in order to highlight the subject matter of the present disclosure.
[0022] It can be understood that the above-mentioned various method embodiments mentioned in the present disclosure can be combined with each other to form a combined embodiment without violating the principle logic. Due to space limitations, the present disclosure will not go into details.
[0023] In addition, the present disclosure also provides a semiconductor wastewater water quality predictable maintenance system, an electronic device, a computer-readable storage medium, and a program, all of which can be used to implement any semiconductor wastewater water quality predictable maintenance method provided by the present disclosure. The corresponding technical solutions and descriptions are referred to the corresponding records in the method part and will not be repeated here.
[0024] The execution subject of the semiconductor wastewater water quality predictable maintenance method can be a computer or other device capable of implementing the semiconductor wastewater water quality predictable maintenance. For example, the method can be executed by a terminal device or a server or other processing device, wherein the terminal device can be a user equipment (UE), a mobile device, a user terminal, a terminal, a cellular phone, a cordless phone, a personal digital assistant (PDA), a handheld device, a computing device, a vehicle-mounted device, a wearable device, etc. In some possible implementations, the semiconductor wastewater water quality predictable maintenance method can be implemented by a processor calling a computer-readable instruction stored in a memory.
[0025] Example 1 This embodiment provides a method for predictable maintenance of semiconductor wastewater quality. Figure 1 As shown, the following steps are included: S10, obtaining the water quality of the semiconductor wastewater filtration equipment before and after treatment, the use of filtration consumables and the use of chemicals; S20, determining an operation and maintenance work order based on water quality, usage of filtration consumables and reagents, wherein the content of the operation and maintenance work order includes equipment maintenance items, online inventory of filtration consumables and reagents, and acquisition of on-site water quality sampling and measurement data, and updating the data involved in the content to obtain updated data; S30. Based on the updated data from the operation and maintenance work order feedback and the expected amount of semiconductor wastewater to be treated, the future consumption of filtration consumables and chemicals is predicted, and then online inventory and inspection management are carried out to achieve predictable maintenance.
[0026] Based on the above configuration, the embodiment of the present disclosure proposes a predictable maintenance method, which can achieve predictable maintenance of filtration consumables and chemicals according to the operating conditions, inventory conditions and the expected amount of semiconductor wastewater to be treated of the semiconductor wastewater filtration equipment, solving the problem of redundant equipment or consumables in the prior art that requires additional storage space and management costs, while reducing maintenance costs while ensuring that wastewater treatment meets standards and the equipment operates normally and healthily.
[0027] The following describes in detail each step of the embodiment of the present disclosure.
[0028] S10, obtaining the water quality of the semiconductor wastewater filtration equipment before and after treatment, the use of filtration consumables and the use of chemicals; The water quality is obtained by regularly sampling and chemically analyzing the wastewater before and after treatment and feeding back the results; optionally, the wastewater can also be monitored online, such as fluoride, nitrogen, phosphate, turbidity and organic compounds.
[0029] The use of filtration consumables and reagents is obtained through consumables use records and reagent use records. Record the consumables used in the filtration equipment, such as ultrafiltration (UF) membranes and reverse osmosis (RO) membranes, as well as their replacement cycles and usage; record the chemical reagents used in the wastewater treatment process, including pH adjusters, coagulants, flocculants, etc. The records should include the usage, frequency of use and type of reagents to optimize the treatment process and control costs.
[0030] S20. Determine an operation and maintenance work order based on water quality, usage of filtration consumables and reagents, wherein the content of the operation and maintenance work order includes equipment maintenance items, online inventory of filtration consumables and reagents, and acquisition of on-site water quality sampling and measurement data, and update the data involved in the content to obtain updated data.
[0031] In some embodiments, determining an operation and maintenance work order based on water quality, usage of filtration consumables, and usage of chemicals includes: Determine the filtration efficiency of semiconductor wastewater filtration equipment based on past water quality, usage of filtration consumables and reagents, and determine the equipment maintenance items required for semiconductor wastewater filtration equipment based on the filtration efficiency; Based on the equipment maintenance project, the local inventory status of filtering consumables and chemicals generates an operation and maintenance work order to update the above update data.
[0032] Among them, the equipment maintenance projects can arrange maintenance cycles according to the filtration efficiency. The maintenance projects include inspection and maintenance of wastewater treatment equipment to ensure the normal operation of all equipment components, such as pumps, pipes, valves, agitators, etc.; it also includes replacement of filtration consumables, such as ultrafiltration (UF) membranes and reverse osmosis (RO) membranes, to ensure the filtration effect and water quality meet the standards; in addition, it also includes sludge treatment systems and automated control systems, such as sludge collection, storage and disposal, PLC program control, etc.
[0033] In some embodiments, the filtration efficiency of the semiconductor wastewater filtration equipment is determined based on past water quality conditions, usage of filtration consumables, and usage of reagents, including: The filtration efficiency is determined by the past water quality of the semiconductor wastewater filtration equipment, the amount of wastewater treated, and the use of filtration consumables and reagents, as shown below: in, is the filtration efficiency, For the cost of past consumables, The cost of past drug use, Indicates the difference in water quality before and after wastewater treatment. is the wastewater quality before wastewater treatment, It indicates the quality of wastewater before treatment, and A indicates the amount of wastewater treated. The past cost of consumables and the past cost of chemicals are directly used to indicate the use of filtration consumables and chemicals. The entire maintenance plan requires the collaboration of multiple departments, which can be connected with procurement, finance and other data to bind the usage and unit price, which is conducive to the implementation of the entire maintenance plan. In addition, the amount of wastewater and the difference in water quality before and after wastewater treatment are inversely proportional to the amount of consumables and chemicals used. Using them as the basis for calculating filtration efficiency can better reflect the efficiency of the entire filtration system than the filtration efficiency of a single wastewater treatment device, that is, it directly reflects how much it costs to filter a certain amount of wastewater.
[0034] S30. Based on the updated data from the operation and maintenance work order feedback and the expected amount of semiconductor wastewater to be treated, the future consumption of filtration consumables and chemicals is predicted, and then online inventory and inspection management are carried out to achieve predictable maintenance.
[0035] In some embodiments, based on the updated data fed back by the operation and maintenance work order and the expected amount of semiconductor wastewater to be treated, the consumption of future filtration consumables and reagents is predicted, including: Based on the filtration efficiency, the on-site water quality sampling measurement data in the update data, and the expected amount of semiconductor wastewater to be treated, the expected filtration consumables and reagents to be used are calculated and expressed as follows:
[0036] in, For the future consumption of filtration consumables, For future drug consumption, is the filtration efficiency, To collect water quality samples and measure data on site, is the expected water quality data, The amount of semiconductor wastewater expected to be treated. The consumption of filtration consumables and future agent consumption calculated in the above manner is an overall parameter, and it is necessary to further determine the consumption of filtration consumables and future agent consumption according to the actual wastewater quality and the amount of wastewater, for example, which agents and the amount of agents to use are determined according to the chemical pollutants in the wastewater quality, and the consumption of filtration consumables is determined according to the organic flocculants or particulate matter in the water quality. The specific determination is determined by technicians in this field according to the actual filtration equipment used.
[0037] Preferably, when determining the operation and maintenance work order and the inspection management, the operation and maintenance work order and the inspection management should be assigned to the same staff or the same staff members, so that the staff members can be more familiar with the same type of processes to be performed.
[0038] In one embodiment, online inventory and inspection management are performed to achieve predictable maintenance, including: formulating online inventory management based on the expected use of filtration consumables and chemicals and the online inventory of filtration consumables and chemicals, and formulating an inspection plan for the actual consumption and operation of the filtration consumables and chemicals of the semiconductor wastewater filtration equipment.
[0039] In another embodiment, based on the updated data fed back by the operation and maintenance work order and the expected amount of semiconductor wastewater to be treated, the consumption of future filtration consumables and reagents is predicted, including: Collect historical operation and maintenance work order data, including the usage records of consumables and medicines; Collect historical on-site water quality sampling and measurement data, including indicators such as chemical pollutants, organic matter, and particulate matter; Performing data cleaning on the historical operation and maintenance work order data and the historical on-site water quality sampling and measurement data, processing missing values and removing outliers, wherein processing missing values can be achieved by interpolation; Based on historical on-site water quality sampling measurement data, on-site water quality data, historical expected water quality data and water quantity data, the change characteristics of water quality and quantity before and after treatment, such as pollutant types and concentrations, are extracted, and a relationship model between the change characteristics and consumables and drug consumption is constructed; the relationship model can be trained by a machine learning model of a decision tree neural network model, and the decision tree is used as the input layer of the neural network model. The decision tree is used to extract the change characteristics to provide a better explanation, and the extracted change characteristics are used to train the neural network model to adjust the model parameters in the neural network model; optionally, Keras can be used to build a neural network model, and DecisionTreeClassifier or DecisionTreeRegressor can be used to extract change characteristics.
[0040] Collect data on the volume of semiconductor wastewater expected to be treated; Use the trained neural network model to predict future consumables and drug consumption; According to the specific water quality of the wastewater, further refine the prediction results and determine the specific type and amount of reagents to be used; Formulate operation and maintenance work orders and inspection plans based on model prediction results and operation and maintenance work order feedback.
[0041] Optionally, ensure that tasks are assigned to staff familiar with the same type of process. Dynamically adjust inventory based on forecast results and real-time inventory data to ensure the supply of consumables and medicines.
[0042] In addition, the accuracy and efficiency of the neural network model can be regularly evaluated, and the neural network model can be optimized based on feedback. In addition, as new data is continuously collected, the neural network model can also continuously learn and update to adapt to changing environments and conditions. The use of a neural network model combined with a decision tree can make the system more adaptable to changes, and can be used to update maintenance plans in real time, making the entire system more adaptable.
[0043] Among them, the specific means of achieving predictable maintenance include formulating predictable maintenance plans, which include processes such as plan creation, maintenance work orders, consumables consumption statistics, and work order closure. Plan creation includes creating online inventory management plans and inspection plans, and then allocating maintenance work orders. Maintenance work orders include routine maintenance and emergency fault handling to ensure that the system can achieve stable wastewater treatment and meet the requirements of water quality and treated water volume. Consumables consumption generated during the maintenance process must be counted in the system, and the work order will be closed after data feedback is completed. In addition, online inventory management also includes procurement plans, inventory entry dates, etc., to ensure that the inventory is redundant while meeting demand in case of emergency.
[0044] Among them, Figure 2 As shown, routine maintenance includes regular maintenance such as system inspection, system full inspection and system annual inspection. The emergency fault handling in the embodiment of the present disclosure includes emergency repairs and expected maintenance in the foreseeable maintenance plan. For example, after considering the price adjustment of consumables, etc., when the filtration efficiency changes significantly, emergency fault handling is required. After on-site investigation, expert diagnosis, professional operation and effect verification, the predictable maintenance method implemented in the embodiment of the present disclosure can realize predictable maintenance of filtration consumables and agents according to the operation status, inventory status and the expected amount of semiconductor wastewater to be treated of the semiconductor wastewater filtration equipment, solving the problem of redundant equipment or consumables in the prior art that additional storage space and management costs are required, and the maintenance cost is reduced while ensuring that the wastewater treatment meets the standards and the equipment operates normally and healthily; the system operation data and online inventory status can also be regularly updated according to the feedback data of the operation and maintenance work order, and then the maintenance plan is updated, making the whole system more adaptable.
[0045] Example 2 This embodiment provides a semiconductor wastewater quality predictable maintenance system 100. Figure 3 As shown, including: A historical data acquisition unit 1 is used to acquire the water quality, the usage of filtering consumables and the usage of reagents before and after the treatment of the semiconductor wastewater filtration equipment; The operation and maintenance work order generation and data updating unit 2 determines the operation and maintenance work order based on the water quality, the use of the filter consumables and the use of the reagents, wherein the content of the operation and maintenance work order includes equipment maintenance items, online inventory of the filter consumables and reagents, and acquisition of on-site water quality sampling and measurement data, and updates the data involved in the content to obtain updated data; Predictive maintenance unit 3 predicts the future consumption of filtration consumables and chemicals based on the updated data fed back by the operation and maintenance work order and the expected amount of semiconductor wastewater to be treated, and then performs online inventory and inspection management to achieve predictive maintenance.
[0046] In the historical data acquisition unit 1, the water quality is obtained by regularly sampling and chemically analyzing the wastewater before and after treatment and feeding back the results; optionally, the wastewater can also be monitored online, such as fluoride, nitrogen, phosphate, turbidity and organic compounds.
[0047] The use of filtration consumables and reagents is obtained through consumables use records and reagent use records. Record the consumables used in the filtration equipment, such as ultrafiltration (UF) membranes and reverse osmosis (RO) membranes, as well as their replacement cycles and usage; record the chemical reagents used in the wastewater treatment process, including pH adjusters, coagulants, flocculants, etc. The records should include the usage, frequency of use and type of reagents to optimize the treatment process and control costs.
[0048] In the operation and maintenance work order generation and data update unit 2, the operation and maintenance work order is determined based on the water quality, the use of the filtering consumables and the use of the reagents, including: Determine the filtration efficiency of semiconductor wastewater filtration equipment based on past water quality, usage of filtration consumables and reagents, and determine the equipment maintenance items required for semiconductor wastewater filtration equipment based on the filtration efficiency; Based on the equipment maintenance project, the local inventory status of filtering consumables and chemicals generates an operation and maintenance work order to update the above update data.
[0049] Among them, the equipment maintenance projects can arrange maintenance cycles according to the filtration efficiency. The maintenance projects include inspection and maintenance of wastewater treatment equipment to ensure the normal operation of all equipment components, such as pumps, pipes, valves, agitators, etc.; it also includes replacement of filtration consumables, such as ultrafiltration (UF) membranes and reverse osmosis (RO) membranes, to ensure the filtration effect and water quality meet the standards; in addition, it also includes sludge treatment systems and automated control systems, such as sludge collection, storage and disposal, PLC program control, etc.
[0050] In some embodiments, the filtration efficiency of the semiconductor wastewater filtration equipment is determined based on past water quality conditions, usage of filtration consumables, and usage of reagents, including: The filtration efficiency is determined by the past water quality of the semiconductor wastewater filtration equipment, the amount of wastewater treated, and the use of filtration consumables and reagents, as shown below: in, is the filtration efficiency, For the cost of past consumables, The cost of past drug use, Indicates the difference in water quality before and after wastewater treatment. is the wastewater quality before wastewater treatment, It indicates the quality of wastewater before treatment, and A indicates the amount of wastewater treated. The past cost of consumables and the past cost of chemicals are directly used to indicate the use of filtration consumables and chemicals. The entire maintenance plan requires the collaboration of multiple departments, which can be connected with procurement, finance and other data to bind the usage and unit price, which is conducive to the implementation of the entire maintenance plan. In addition, the amount of wastewater and the difference in water quality before and after wastewater treatment are inversely proportional to the amount of consumables and chemicals used. Using them as the basis for calculating filtration efficiency can better reflect the efficiency of the entire filtration system than the filtration efficiency of a single wastewater treatment device, that is, it directly reflects how much it costs to filter a certain amount of wastewater.
[0051] In the predictive maintenance unit 3, based on the updated data of the operation and maintenance work order feedback and the expected amount of semiconductor wastewater to be treated, the consumption of future filtration consumables and reagents is predicted, including: Based on the filtration efficiency, the on-site water quality sampling measurement data in the update data, and the expected amount of semiconductor wastewater to be treated, the expected filtration consumables and reagents to be used are calculated and expressed as follows:
[0052] in, For the future consumption of filtration consumables, For future drug consumption, is the filtration efficiency, To collect water quality samples and measure data on site, is the expected water quality data, The amount of semiconductor wastewater expected to be treated. The consumption of filtration consumables and future agent consumption calculated in the above manner is an overall parameter, and it is necessary to further determine the consumption of filtration consumables and future agent consumption according to the actual wastewater quality and the amount of wastewater, for example, which agents and the amount of agents to use are determined according to the chemical pollutants in the wastewater quality, and the consumption of filtration consumables is determined according to the organic flocculants or particulate matter in the water quality. The specific determination is determined by technicians in this field according to the actual filtration equipment used.
[0053] In one embodiment, online inventory and inspection management are performed to achieve predictable maintenance, including: formulating online inventory management based on the expected use of filtration consumables and chemicals and the online inventory of filtration consumables and chemicals, and formulating an inspection plan for the actual consumption and operation of the filtration consumables and chemicals of the semiconductor wastewater filtration equipment.
[0054] Among them, the specific means of achieving predictable maintenance include formulating predictable maintenance plans, which include processes such as plan creation, maintenance work orders, consumables consumption statistics, and work order closure. Plan creation includes creating online inventory management plans and inspection plans, and then allocating maintenance work orders. Maintenance work orders include routine maintenance and emergency fault handling to ensure that the system can achieve stable wastewater treatment and meet the requirements of water quality and treated water volume. Consumables consumption generated during the maintenance process must be counted in the system, and the work order will be closed after data feedback is completed. In addition, online inventory management also includes procurement plans, inventory entry dates, etc., to ensure that the inventory is redundant while meeting demand in case of emergency.
[0055] Among them, routine maintenance includes regular maintenance such as system inspection, system full inspection and system annual inspection. The emergency fault handling in the embodiment of the present disclosure includes emergency repairs and expected maintenance in the foreseeable maintenance plan. For example, after considering the price adjustment of consumables, when the filtration efficiency changes significantly, emergency fault handling is required. After on-site investigation, expert diagnosis, professional operation and effect verification, the predictable maintenance method implemented in the embodiment of the present disclosure can realize predictable maintenance of filtration consumables and agents according to the operation status, inventory status and the expected amount of semiconductor wastewater to be treated of the semiconductor wastewater filtration equipment, which solves the problem of redundant equipment or consumables in the prior art that they need to occupy additional storage space and management costs, and reduces maintenance costs while ensuring that wastewater treatment meets standards and the equipment operates normally and healthily; the system operation data and online inventory status can also be regularly updated according to the feedback data of the operation and maintenance work order, and then the maintenance plan can be updated, making the entire system more adaptable. Example 3 The presently disclosed embodiment also provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the semiconductor wastewater water quality predictable maintenance method in Embodiment 1 when executing the computer program.
[0056] Embodiment 3 of the present disclosure is merely an example and should not bring any limitation to the functions and scope of use of the embodiments of the present disclosure.
[0057] The electronic device may be in the form of a general-purpose computing device, for example, it may be a server device. The components of the electronic device may include, but are not limited to: at least one processor, at least one memory, and a bus connecting different system components (including the memory and the processor).
[0058] The bus includes data bus, address bus and control bus.
[0059] The memory may include volatile memory, such as random access memory (RAM) and / or cache memory, and may further include read-only memory (ROM).
[0060] The memory may also include a program tool having a set (at least one) of program modules, such program modules including but not limited to: an operating system, one or more application programs, other program modules and program data, each of which or some combination may include the implementation of a network environment.
[0061] The processor executes various functional applications and data processing by running computer programs stored in the memory.
[0062] The electronic device may also communicate with one or more external devices (e.g., keyboards, pointing devices, etc.). Such communication may be performed through an input / output (I / O) interface. In addition, the electronic device may also communicate with one or more networks (e.g., local area networks (LANs), wide area networks (WANs), and / or public networks, such as the Internet) through a network adapter. The network adapter communicates with other modules of the electronic device through a bus. It should be understood that, although not shown in the figure, other hardware and / or software modules may be used in conjunction with the electronic device, including but not limited to: microcode, device drivers, redundant processors, external disk drive arrays, RAID (disk array) systems, tape drives, and data backup storage systems, etc.
[0063] It should be noted that although several units / modules or sub-units / modules of the electronic device are mentioned in the above detailed description, this division is merely exemplary and not mandatory. In fact, according to the embodiments of the present application, the features and functions of two or more units / modules described above can be embodied in one unit / module. Conversely, the features and functions of one unit / module described above can be further divided into multiple units / modules to be embodied.
[0064] Example 4 The presently disclosed embodiment also provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the program is executed by a processor, the steps of the semiconductor wastewater water quality predictable maintenance method in embodiment 1 are implemented.
[0065] The readable storage medium may include but is not limited to: a portable disk, a hard disk, a random access memory, a read-only memory, an erasable programmable read-only memory, an optical storage device, a magnetic storage device or any suitable combination of the above.
[0066] In a possible implementation, the present disclosure can also be implemented in the form of a program product, which includes a program code. When the program product is run on a terminal device, the program code is used to enable the terminal device to execute the steps of the semiconductor wastewater water quality predictable maintenance method described in Example 1.
[0067] Among them, the program code for executing the present disclosure can be written in any combination of one or more programming languages, and the program code can be executed completely on the user device, partially on the user device, as an independent software package, partially on the user device and partially on a remote device, or completely on the remote device.
[0068] The above are only specific embodiments of the present disclosure, but the protection scope of the present disclosure is not limited thereto. Any technician familiar with the technical field can easily think of various changes or substitutions within the technical scope disclosed in the present disclosure, which should be included in the protection scope of the present disclosure. Therefore, the protection scope of the present disclosure should be based on the protection scope of the claims.
Claims
1. A method for predictable maintenance of semiconductor wastewater quality, characterized in that: The steps include: Obtain the water quality before and after treatment of semiconductor wastewater filtration equipment, the use of filtration consumables and the use of chemicals; Determine an operation and maintenance work order based on water quality, usage of filtration consumables and reagents, wherein the content of the operation and maintenance work order includes equipment maintenance items, online inventory of filtration consumables and reagents, and acquisition of on-site water quality sampling and measurement data, and update the data involved in the content to obtain updated data; Based on the updated data from operation and maintenance work order feedback and the expected amount of semiconductor wastewater to be treated, the future consumption of filtration consumables and chemicals is predicted, and then online inventory and inspection management are carried out to achieve predictable maintenance.
2. The semiconductor wastewater water quality predictable maintenance method according to claim 1, characterized in that: Based on the updated data from the operation and maintenance work order feedback and the expected amount of semiconductor wastewater to be treated, the future consumption of filtration consumables and reagents is predicted, including: Collect historical operation and maintenance work order data, including the usage records of consumables and medicines; Collect historical on-site water quality sampling measurements; Performing data cleaning on the historical operation and maintenance work order data and the historical on-site water quality sampling and measurement data, processing missing values and removing outliers; According to historical on-site water quality sampling measurement data, on-site water quality data, historical expected water quality data and water quantity data, the change characteristics of water quality and quantity before and after treatment are extracted, and a relationship model between the change characteristics and the consumption of consumables and agents is constructed; the relationship model can be trained by a machine learning model of a decision tree neural network model, and the decision tree is used as the input layer of the neural network model. The decision tree is used to extract the change characteristics, and the extracted change characteristics are used to train the neural network model to adjust the model parameters in the neural network model; Collect data on the volume of semiconductor wastewater expected to be treated; Use the trained neural network model to predict the future consumption of consumables and chemicals. When determining the operation and maintenance work orders and inspection management, assign the operation and maintenance work orders and inspection management to the same or several staff members.
3. The semiconductor wastewater water quality predictable maintenance method according to claim 1 or 2, characterized in that: Obtain the water quality before and after treatment of semiconductor wastewater filtration equipment, the use of filtration consumables and the use of chemicals, including: The water quality is obtained by regularly sampling and chemically analyzing the wastewater before and after treatment and feeding back the results; The usage of filtering consumables and chemicals is obtained through the consumables usage records and chemical usage records.
4. The semiconductor wastewater water quality predictable maintenance method according to claim 3, characterized in that: Determine the operation and maintenance work order based on water quality, usage of filtration consumables and reagents, including: Determine the filtration efficiency of semiconductor wastewater filtration equipment based on past water quality, usage of filtration consumables and reagents, and determine the equipment maintenance items required for semiconductor wastewater filtration equipment based on the filtration efficiency; Generate an operation and maintenance work order based on the local inventory status of equipment maintenance items, filtration consumables, and chemicals to update the above update data.
5. The semiconductor wastewater water quality predictable maintenance method according to claim 4, characterized in that: The filtration efficiency of semiconductor wastewater filtration equipment is determined based on past water quality, filtration consumables usage, and reagent usage, including: The filtration efficiency is determined by the past water quality of the semiconductor wastewater filtration equipment, the amount of wastewater treated, and the use of filtration consumables and reagents, as shown below: in, is the filtration efficiency, For the cost of past consumables, The cost of past drug use, Indicates the difference in water quality before and after wastewater treatment. is the wastewater quality before wastewater treatment, It represents the quality of wastewater before treatment, and A represents the amount of wastewater treated.
6. The semiconductor wastewater water quality predictable maintenance method according to claim 5, characterized in that: Based on the updated data from the operation and maintenance work order feedback and the expected amount of semiconductor wastewater to be treated, the future consumption of filtration consumables and reagents is predicted, including: Based on the filtration efficiency, the on-site water quality sampling measurement data in the update data, and the expected amount of semiconductor wastewater to be treated, the expected filtration consumables and reagents to be used are calculated and expressed as follows: in, For the future consumption of filtration consumables, For future drug consumption, is the filtration efficiency, To collect water quality samples and measure data on site, is the expected water quality data, The amount of semiconductor wastewater expected to be treated.
7. The semiconductor wastewater water quality predictable maintenance method according to claim 6, characterized in that: Conduct online inventory and inspection management to achieve predictable maintenance, including: formulate online inventory management based on the expected use of filtration consumables and chemicals and the online inventory of filtration consumables and chemicals, and formulate an inspection plan for the actual consumption and operation of the filtration consumables and chemicals of the semiconductor wastewater filtration equipment.
8. A semiconductor wastewater water quality predictable maintenance system, characterized in that: include: A historical data acquisition unit, which acquires the water quality before and after treatment by the semiconductor wastewater filtration equipment, the usage of filtration consumables, and the usage of chemicals; An operation and maintenance work order generation and data update unit determines an operation and maintenance work order based on water quality, usage of filtration consumables and reagents, wherein the content of the operation and maintenance work order includes equipment maintenance items, online inventory of filtration consumables and reagents, and acquisition of on-site water quality sampling and measurement data, and updates the data involved in the content to obtain updated data; The predictive maintenance unit predicts the future consumption of filtration consumables and chemicals based on the updated data fed back from the operation and maintenance work orders and the expected amount of semiconductor wastewater to be treated, and then conducts online inventory and inspection management to achieve predictive maintenance.
9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the predictable maintenance method for semiconductor wastewater water quality described in any one of claims 1 to 7 is implemented.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by the processor, the predictable maintenance method of semiconductor wastewater water quality described in any one of claims 1 to 7 is implemented.
Citation Information
Patent Citations
An equipment predictive maintenance system and method for subterranean reclaimed water plant
CN111333131A
Water purification plant operation and maintenance system and method based on BIM and Internet of Things technology
CN112765718A
Big data analysis system for sewage operation and maintenance platform
CN117892094A
Management support system of water treatment plant
JP2020095604A