Large open caisson drainage sinking construction method in flowing water soft stratum environment
Through the reinforcement of powder spray piles and the setting of water-stop curtains, combined with the drainage and sinking method, the problem of difficult control of caisson sinking in a weak stratum environment with dynamic water is solved, the safety and efficiency of construction are improved, and the stability and stability of caisson sinking are ensured. quality.
Patent Information
- Application Number
- CN202411057420.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-10-11
AI Technical Summary
In a weak stratum environment with dynamic water, the conventional construction method of caissons has problems such as long construction period and difficulty in controlling the amount of subsidence. In addition, undrained subsidence construction has high risks in underwater operations and difficulty in ensuring quality.
Steps such as powder spray pile reinforcement, water-stop curtain setting, dewatering well opening, foundation pit excavation and cushion pouring are adopted to control the sinking process of the caisson through drainage and sinking methods, improve the foundation bearing capacity and precipitation effect, and reduce quicksand. and surge risks.
The stability and safety of the caisson sinking have been improved, the construction period has been shortened, construction risks and costs have been reduced, and the quality and safety of the sinking have been ensured.
Smart Images

Figure CN118756740A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a large caisson drainage and sinking construction method in a water-dynamic soft stratum environment. Background Art
[0002] Caisson is a structure used as a deep foundation in water supply and drainage, bridge engineering, and industrial and civil construction projects. Currently, most caissons are built in riverside plains, estuary valleys, and other environments near rivers and lakes. The hydrological conditions in these environments are complex and soft soil is widely distributed. Therefore, the conventional construction method for caissons in these environments is to use the well wall (including the frame and some partition walls) to be made in sections on the ground and to use a non-drainage sinking construction process. However, non-drainage sinking has the disadvantages of long construction period, large economic investment, difficult to control sinking quality, and high risk of underwater operations.
[0003] The information disclosed in this background technology section is only intended to enhance the understanding of the overall background of the invention and should not be regarded as an acknowledgment or any form of suggestion that the information constitutes the prior art already known to a person skilled in the art. Summary of the invention
[0004] In order to overcome the defects of the prior art, a large caisson drainage sinking construction method in a dynamic water soft stratum environment is provided to solve the problems of long construction period and difficult to control sinking amount in conventional caisson construction methods.
[0005] To achieve the above object, a large caisson drainage and sinking construction method in a dynamic water soft stratum environment is provided, comprising the following steps:
[0006] The ground at the installation position of the blade foot of the caisson is reinforced with powder injection piles, and the powder injection piles are arranged in a circle along the circumferential direction of the caisson;
[0007] Constructing a water-stop curtain outside the installation location;
[0008] A plurality of drainage wells are opened in the stratum inside the water-stop curtain, and the plurality of drainage wells are arranged in a circle along the circumferential direction of the water-stop curtain;
[0009] excavating a foundation pit on the surface of the installation location;
[0010] pouring a cushion layer in the foundation pit;
[0011] Casting the caisson on the cushion layer to form the caisson;
[0012] The water is discharged from the water-stop curtain through the multiple drainage wells, and the cushion layer is chiseled off, so that the caisson sinks to the designed elevation and is placed on the powder injection piles;
[0013] After the caisson sinks to the designed elevation, the bottom of the caisson is sealed.
[0014] Furthermore, the cement content of the powder injection pile located above the design elevation of the blade foot is smaller than the cement content of the powder injection pile located below the design elevation of the blade foot.
[0015] Furthermore, the water-stop curtain is a double-row three-axis cement mixing pile.
[0016] Furthermore, when excavating the foundation pit, slope excavation is adopted, and the slope surface of the foundation pit is supported by sprayed anchors.
[0017] Furthermore, before the caisson is drained and sunk, guide soil is backfilled between the blade foot and the slope.
[0018] Furthermore, the cushion layer includes a sand cushion layer and a concrete cushion layer cast on the sand cushion layer, and a brick membrane supported by the blade foot is built on the concrete cushion layer.
[0019] Furthermore, when the cushion layer is removed, it is removed ring by ring from the plane center of the caisson to the outer edge of the caisson.
[0020] Furthermore, when sealing the bottom, the four foot chambers of the caisson are sealed first, and then the other chambers on the outer edge of the caisson are sealed. After the bottoms of the other chambers on the outer edge of the caisson are sealed, the bottoms of the chambers of the caisson are sealed in a ring from the outer edge of the caisson toward the center of the plane of the caisson.
[0021] The beneficial effect of the present invention is that the drainage and sinking construction method of a large caisson in a dynamic water soft stratum environment of the present invention takes cement powder injection pile composite foundation reinforcement measures in advance to improve the bearing capacity of the foundation soil and avoid overall sudden sinking and tilting during the sinking stage to cause safety accidents in view of the characteristics of the large sinking coefficient and sinking stability coefficient of the caisson in soft soil areas. Under complex hydrological conditions, a closed three-axis water-stopping curtain is set around the caisson to improve the precipitation effect during the caisson sinking stage to meet the drainage and sinking requirements, reduce the risk of quicksand and sudden surges during the caisson drainage and sinking process, and compared with non-drainage sinking, it does not involve underwater operations, reducing the risk of drainage sinking safety operations.
[0022] The drainage sinking construction method of a large caisson in a dynamic water soft stratum environment of the present invention can produce the bearing capacity of the caisson ground three times, and the ground production and construction are convenient and the construction speed is fast. It adopts drainage sinking and hydraulic machinery to suck mud and take soil. Compared with the undrainage sinking construction process, the sinking is continuous and easy to control, the soil taking is convenient and fast, the sinking is more balanced and easy to correct, and dry bottom sealing can be used, which can speed up the project progress and shorten the construction period significantly.
[0023] The drainage and sinking construction method of a large caisson in a dynamic water soft stratum environment of the present invention is used to improve the quality control of the production and sinking construction of large-volume caissons, ensure that the caisson sinks to perfection once, and that the displacement and height difference after the bottom is sealed meet the specification requirements, thereby avoiding delays in construction and increased costs caused by quality accidents caused by the sinking of the caisson. In addition, the drainage and sinking construction process, compared with the non-drainage sinking construction process, greatly reduces the amount of mud generated, does not require divers for hydraulic mechanical mud suction and soil extraction, and the dry bottom sealing is simple and easy to operate. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:
[0025] Figures 1 to 7 It is a schematic diagram of the steps of a large caisson drainage and sinking construction method in a dynamic water soft stratum environment according to an embodiment of the present invention.
[0026] Figure 8 This is a simplified diagram for calculating the sand cushion layer according to an embodiment of the present invention. DETAILED DESCRIPTION
[0027] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It is also necessary to explain that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.
[0028] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0029] Reference Figures 1 to 8 As shown, the present invention provides a large caisson drainage sinking construction method in a dynamic water soft stratum environment, comprising the following steps:
[0030] S1. The ground at the installation position of the blade foot 21 of the caisson 2 is reinforced with powder injection piles 1, and the powder injection piles 1 are arranged in a circle along the circumferential direction of the caisson 2.
[0031] As a preferred embodiment, the cement content of the powder injection pile 1 located above the design elevation of the blade foot 21 is less than the cement content of the powder injection pile 1 located below the design elevation of the blade foot 21.
[0032] Specifically, in this embodiment, the soft soil has low geological bearing capacity, high stratum water content, large foundation settlement and deformation, and the natural foundation cannot meet the bearing layer requirements, and cannot ensure the smooth sinking of the caisson. In order to control the uniform sinking of the caisson, the blade foot of the caisson is reinforced with powder injection piles to form a complete columnar reinforcement body with certain water stability and strength, thereby improving the stability and mechanical properties of the soil.
[0033] During construction, the powder injection piles need to reinforce the soil layer with higher bearing capacity below the blade foot, and the powder injection piles need to enter the bearing soil layer no less than 1.0m. The cement content below the blade foot is 15%, and the cement content above the blade foot is 8%. The pile diameter is 500mm and the pile spacing is 0.5m.
[0034] S2. Construct a water-stop curtain 3 on the outside of the installation location.
[0035] As a preferred embodiment, the water-stop curtain 3 is a double-row three-axis cement mixing pile.
[0036] Specifically, in order to cut off the hydraulic connection between the caisson and the river channel, prevent the generation of quicksand from the source, and reduce the disturbance of the surrounding soil during the sinking process, a water-stop curtain is constructed around the caisson. The water-stop curtain uses double rows of Φ850 three-axis cement mixing piles. The pile length enters the pressurized water waterproof layer, adopts the "one-hole socket" process, uses 42.5 grade ordinary Portland cement, the cement content is 20%, and the water-cement ratio is 1.5 to 2.0.
[0037] S3, a plurality of drainage wells 6 are opened in the stratum inside the water-stopping curtain 3, and the plurality of drainage wells 6 are arranged in a circle along the circumferential direction of the water-stopping curtain 3.
[0038] Specifically, in order to ensure the quality of the foundation pit and avoid the soaking of backfill soil by the upwelling of groundwater during the caisson production process, which could cause quality accidents, light well points are required to carry out dewatering in the foundation pit during the caisson production process.
[0039] Arrangement of well point dewatering wells: The light well point plane adopts a single-row ring arrangement. A circle of dewatering wells are set up inside the water-stop curtain and around the foundation pit. A dewatering well is set up every 2m. The length of each well is 7.5m. The dewatering operation is carried out until the caisson is completed to ensure that the groundwater level in the foundation pit drops to 0.5m below the excavation surface. In order to facilitate the observation of the water level, 4 observation wells are evenly set up in the site.
[0040] Equipment selection: ZBL-9-60 vacuum water absorption well point system is selected, and the main equipment consists of well point pipes, connecting pipes, water collection main pipes and vacuum pumps. The total length of each well point pipe is 40-50m, the total pipe diameter is 60mm, the well point pipe is 7.5m long and the pipe diameter is 48mm. Each well point pipe has 25-35 pipes, the filter pipe is 1.0m long, and the bottom of the pipe is 1.5m below the sand cushion layer of the caisson. The connecting hose uses PVC or rubber pipe.
[0041] Construction method: Well point dewatering uses high-pressure water gun water flushing method to punch holes, and the high-pressure water maintains a water pressure of 0.8~1.2Mpa.
[0042] S4. Excavate a foundation pit on the surface at the installation location.
[0043] As a preferred implementation method, when excavating the foundation pit, slope excavation is adopted, and the slope surface of the foundation pit is supported by sprayed anchors.
[0044] Specifically, in order to ensure sufficient operating space during the production of the caisson, the caisson design plane size is expanded 2.5m outward on all sides as the foundation pit excavation size. The foundation pit is excavated with a slope, and the slope is 1:1. In order to prevent the base soil from being soaked and softened, an open ditch plus a water collection well is used for foundation pit drainage.
[0045] In order to ensure the stability of the foundation pit slope, the slope is supported by sprayed anchors, which are composed of three parts: soil nails, sprayed concrete surface layer and steel mesh.
[0046] In this embodiment, Ф16 steel bar soil nails are used, the soil nail length L=1.5m, the soil nails are set at a spacing of 2000mm×2000mm, covered with Ф8mm 200mm×200mm steel mesh, and then 8cm thick C25 concrete is sprayed.
[0047] In this embodiment, the soil nails are selected from the hole-forming grouting type reinforced soil nails, which should meet the following requirements:
[0048] 1) The hole diameter is 70mm~120mm;
[0049] 2) Soil nails are made of HRB400 grade Ф16 deformed steel bars;
[0050] 3) Center supports should be set along the entire length of the soil nails, with a spacing of 2.0m, and the thickness of the soil nail protection layer should not be less than 20mm;
[0051] 4) Two grouting should be adopted, and the soil nail grouting material should be pure cement slurry or cement mortar, and its final setting strength should not be less than 20Mpa;
[0052] 5) The inclination angle between the soil nail axis and the horizontal plane is 15°~20°.
[0053] S5. Pour a cushion layer 4 in the foundation pit.
[0054] As a preferred embodiment, the cushion layer 4 includes a sand cushion layer and a concrete cushion layer cast on the sand cushion layer, and a brick membrane 5 supported by the blade foot 21 is built on the concrete cushion layer.
[0055] Specifically, in order to meet the requirement that the base pressure during caisson construction is not greater than the bearing capacity of the underlying foundation and to ensure the stability requirements during caisson construction, it is necessary to verify the area of the bottom of the caisson blade according to the following formula, reinforce the original surface soil according to the calculated results, and lay a sand cushion layer and pour a concrete cushion layer.
[0056] ①Sand cushion calculation: calculation diagram Figure 8 The formula is as follows
[0057] Standard value of base pressure:
[0058]
[0059] P≤fa,
[0060] Where: P is the standard value of base pressure (KN / m 2 );
[0061] H s is the thickness of the sand cushion layer (m);
[0062] G0 is the weight per unit length along the wall of the first section of the caisson (KN / m);
[0063] γ s is the natural density of sand (15KN / m 3 ), 15KN / m is acceptable 3 ;
[0064] B L is the width of the plain concrete cushion (m), B L =B+2b1, when calculating, take b1=h c ;
[0065] b is the width of the blade foot tread;
[0066] b1 is the cantilever width of plain concrete (m), and b1 ≥ h c (h c is the thickness of the plain concrete cushion layer);
[0067] n is the horizontal projection width of the contact surface between the blade foot slope and the soil;
[0068] α is the pressure diffusion angle of the sand cushion layer, which is 30°;
[0069] fa is the corrected characteristic value of foundation bearing capacity (KPa);
[0070] B is the blade width (m).
[0071] ② Calculation of concrete cushion: The calculation formula is as follows:
[0072] Compressive strength: R = G / A1,
[0073] Where: A1 is the contact area between the caisson blade and the concrete;
[0074] Shear strength: τ = G / 2A2;
[0075] Where: A2 is the cross-sectional area of concrete.
[0076] After verification, reasonable thickness and width of sand cushion and concrete cushion are adopted to ensure that the bearing capacity of the underlying foundation meets the requirements. The bearing capacity of the sand cushion and the compressive and shear bearing capacity of the concrete are verified. After they meet the requirements, the construction of the sand cushion and concrete cushion is carried out.
[0077] After calculation, the thickness of the sand cushion layer is 1.2m and the width is 3m. The width of the C20 plain concrete cushion layer is 1.6m and the thickness is 20cm, which meets the bearing capacity requirements of the underlying foundation of the caisson.
[0078] ③Sand cushion filling:
[0079] The sand cushion layer of the caisson adopts the form of paving around the well wall. The foundation trench is excavated by an excavator, and the sand cushion layer in the foundation trench is filled in layers. Each time shall not exceed 25cm. Watering should be done layer by layer to control the optimal moisture content. The sand cushion layer is filled with medium-coarse sand with good particle grading. After each layer is paved, it is compacted by dragging and vibrating back and forth with a flat vibrator. After each layer of sand cushion is compacted, it is measured by the ring knife method or the steel chisel method. The lower layer can be constructed only after the density test is qualified (≥93%) and the compaction of each layer is accepted. When paving the sand cushion layer, the water collection well in the caisson foundation pit must continuously drain the accumulated water on the soil foundation to facilitate the consolidation of the soil foundation. It is strictly forbidden to immerse the sand cushion layer in water. In order to prevent the sand cushion layer from being soaked in water, a permeable concealed pipe can be buried in the sand cushion layer to connect it to the foundation pit water collection well.
[0080] The sand cushion layer of the caisson is paved in the form of a ring around the well wall. The foundation trench is excavated by an excavator, and the sand cushion layer in the foundation trench is filled in layers. Each time shall not exceed 25cm. Watering should be done layer by layer to control the optimal moisture content. The sand cushion layer is filled with medium-coarse sand with good particle grading. After each layer is paved, it is compacted by dragging and vibrating with a flat vibrator. After each layer of sand cushion is compacted, it is measured by the ring knife method or the steel chisel method. The lower layer can be constructed only after the density test is qualified (≥93%) and the compaction of each layer is accepted. When paving the sand cushion layer, the water collection well in the caisson foundation pit must continuously drain the accumulated water on the soil foundation to facilitate the consolidation of the soil foundation. It is strictly forbidden to soak the sand cushion layer in water. To prevent the sand cushion layer from being soaked in water, a permeable concealed pipe can be buried in the sand cushion layer and connected to the foundation pit water collection well.
[0081] The concrete grade of the cushion layer is C20, and commercial concrete is used. The concrete is transported to the site by a concrete mixer truck and pumped to the concrete pouring site by a concrete pump truck. The concrete is vibrated and compacted with a flat vibrator. It is required to be vibrated and compacted. After the concrete is leveled, the concrete surface is required to be plastered. When it is in the initial setting state, but the surface is still wet, it is plastered with an iron plaster. The concrete surface after plastering is flat and dense, without sand, plaster marks, bubbles, sand holes, cracks, etc. The flatness requirement of the concrete surface is to check with a 3m ruler, and the allowable deviation is 5.0mm.
[0082] After the plain concrete on the sand cushion layer reaches a certain strength, the plane position of the caisson is accurately measured and placed on the plain concrete cushion layer according to the design positioning, and the brick formwork is constructed. The dry coding method is adopted for bricklaying, and low-grade cement mortar is used. Ensure that the inclined surface of the blade foot is flat, and the brick formwork is painted with lime and a small amount of cement mixture. The brick formwork should reserve holes for the tie rod bolts of the caisson wall formwork.
[0083] The blade foot is built with brick membrane, with a width of one brick (240mm) on the top, and is built along the designed blade foot angle to increase the force-bearing area of the blade foot, reduce stress concentration, and keep the caisson stable during production.
[0084] S6. Casting on the cushion layer forms caisson 2.
[0085] (I) Scaffolding installation
[0086] The scaffolding must be calculated. The project mainly uses socket-type disc-type steel pipe bracket system scaffolding, and the safety net uses an external light gray safety net. Considering the structural construction, the distance between the inner side of the scaffolding pole against the wall and the outer wall is 0.30m, the disc-type scaffolding has a horizontal distance of 0.9m, a vertical distance of 1.5m, and a local distance of 1.2m, 0.9m, and 0.6m, and a step distance of 2.0m. Set up a standardized diagonal rod, and set one continuously in the height direction for every four spans in the horizontal and vertical directions of the end span. Set a base at the bottom, connected to the adjustable screw, and the sweeping rod is no more than 550mm from the ground. The external frame arranges stairs according to the site requirements, and a hook pedal is set at each step. The disc-type scaffolding is considered to be constructed on two floors at the same time, and the construction load control shall not exceed 3kN / ㎡.
[0087] The wall connecting parts are arranged in two steps and two spans, and adopt a soft-pull and hard-bracing connection form to prevent uneven settlement of the caisson and cause collapse of the frame.
[0088] (II) Steel bar engineering
[0089] The steel bars of this caisson are made on site, and the feeding and configuration are strictly in accordance with the specifications and construction drawings. The steel bar construction personnel should strictly follow the design drawings to make samples, and bend and match the steel bars according to the samples to ensure the accuracy of the size of each steel bar, strictly follow the construction drawings to tie them, ensure the accuracy of the position of each steel bar, and the tying must be firm. Electric welding should be used to strengthen the necessary places, and the steel bar protection layer will be strictly controlled with mortar pads.
[0090] (III) Formwork Engineering
[0091] The formwork uses 1.8cm thick nine-ply plywood, with 5×10cm square wood standing on the side as vertical ribs; behind the vertical ribs, double-jointed Φ48×3.5 steel pipes are used as horizontal ribs, and M16 tension bolts are installed, with a horizontal spacing of 45cm and a vertical spacing of 45cm.
[0092] The tension bolts used to fix the formwork should be removable at both ends. The tension bolts are welded in the middle. The 60×60mm square water stop is fully welded to the bolts. After removing the formwork, cut off the screws and seal the holes with polymer cement mortar. The formwork joints are flat seams, and sponge strips are used to stop the mortar, or the formworks are sealed with sealing tape to prevent leakage.
[0093] The formwork must have sufficient strength and rigidity, and the support must be firm. The formwork at the corner of the caisson should be prepared, supported, and ensured to be firm and reliable. Install the inner formwork first, tie the steel bars, then install the outer formwork, and finally calibrate the formwork. Control the size, verticality, and flatness of the formwork, design and arrange the reserved steel bars, embedded parts, and reserved holes in the construction to ensure accurate positioning and reliable fixing. For larger holes, additional tamping holes should be added at the bottom to facilitate the compaction of the concrete at the bottom of the hole.
[0094] (IV) Concrete Engineering
[0095] Commercial concrete is used. During pouring, the material must be fed evenly and poured in layers. The layer thickness should not exceed 50cm, and the pouring should be symmetrical. After the entire caisson is poured, the next layer can be poured. The gap time between the upper and lower layers should not exceed the initial setting time of the concrete. After the concrete is poured, cover it with geotextile and sprinkle water to moisten it. The curing time is not less than 7 days. Set a construction joint on the interface of the secondary production or install a water-stop steel plate in advance.
[0096] S7, draining the water from the water-stop curtain 3 through a plurality of drainage wells 6, and chiseling away the cushion layer, so that the caisson 2 sinks to the designed elevation and is placed on the powder injection pile 1.
[0097] ① Anti-surge stability verification
[0098] This project adopts drainage sinking, which may cause the risk of water and sand gushing during the caisson sinking process, so it is necessary to first verify whether there is a risk of sudden gushing.
[0099] The stability of the pit bottom surge under the action of pressurized water shall comply with the following formula:
[0100]
[0101] Where:
[0102] K ty is the surge stability safety factor; K ty Should not be less than 1.1;
[0103] D is the thickness of the soil layer from the top of the confined aquifer to the bottom of the pit (m);
[0104] γ is the natural weight of the soil layer from the top of the confined aquifer to the bottom of the pit (kN / m 3 );
[0105] Δh is the water head difference between inside and outside the foundation pit (m);
[0106] γ w is the density of water (kN / m 3 ).
[0107] According to empirical calculations, when the caisson drainage of this project sinks to an elevation of -7.30m (submerged water level), there will be no sudden surge. If it continues to sink to an elevation of -11.65, a sudden surge will occur as the drainage sinks.
[0108] Therefore, the following water reduction scheme is adopted:
[0109] 1. When the caisson blade foot sinks to -7.30m, only the lowering diving plan is adopted;
[0110] 2. When the caisson continues to sink from -7.30m to -11.65, a dewatering + pressure reduction plan is adopted (the pressure water control elevation is -4.00m).
[0111] ② Diving precipitation plan (precipitation to -7.80m)
[0112] Calculation of total water inflow:
[0113] According to the Technical Code for Construction Foundation Pit Support (JGJ120-2012), the total water inflow of the foundation pit of a complete well with homogeneous aquifer can be calculated according to the following formula:
[0114]
[0115] in:
[0116] Calculation of water output of a single well:
[0117]
[0118] According to calculation, 18 diving wells with a depth of 19m are planned to be set up outside the foundation pit for submergence dewatering. They are evenly arranged around the caisson foundation pit (inside the water-stop curtain), and 4 spare and observation wells are also evenly set up.
[0119] ③Precipitation scheme for pressurized water (precipitation to -7.80m)
[0120] Calculation of total water inflow:
[0121]
[0122] in:
[0123] Calculation of water output of a single well:
[0124] According to calculations, 12 pressure water wells with a depth of 40m are planned to be set up outside the foundation pit for pressurized water dewatering. They are evenly arranged around the caisson foundation pit (inside the water-stop curtain), and another 2 are evenly set up as backup.
[0125] Table 1. Water reduction control table for caisson sinking stage
[0126]
[0127] Before the formal operation of dewatering, a pumping test should be carried out in time to verify the dewatering effect and the on-site dewatering circuit and drainage conditions, and to adjust or optimize the proposed foundation pit dewatering plan.
[0128] Preparation for sinking of caisson.
[0129] ① Opening sealing: With steel as the framework and brick wall as the content, rubber sheet and steel pressure plate are used to stop water at the joint between the opening and the caisson (inside). The steel is 400mm×300mm×10mm×16H steel; the 500mm thick brick wall is made of MU non-clay sintered ordinary bricks and M10 cement mortar;
[0130] ②Measurement control
[0131] (1) Set up vertical and horizontal cross control piles on the ground outside the well; spray measurement level marking lines on the outside of the well wall at four places on the vertical and horizontal axes perpendicular to each other to observe settlement.
[0132] (2) Observation of the center line and verticality of the well: mark the vertical axis on the outside of the well wall with the longitudinal and transverse axes perpendicular to each other, hang a plumb ball on each side, and align it with the lower mark plate for control, as shown in the figure below.
[0133] (3) A clear leveling mark line must be marked on the inner wall of the wellbore from the end face of the blade to the top of the wellbore on the mutually perpendicular longitudinal and transverse axes to observe the water level in the well and the geometric dimensions of the well bottom excavation.
[0134] ③ Set up protective passages and ladders
[0135] A protective passage is set up on the top of the caisson and the internal bottom beam. The setting principle of the protective passage is to meet the needs of the caisson sinking construction. The protective passage is constructed with steel pipe fasteners, and a life rope is set up and a safety net is hung at the protective passage. Customized galvanized ladders are used for the upper and lower caissons. According to the caisson structure, a reasonable ladder installation position is selected to ensure that each chamber can be reached smoothly.
[0136] As a preferred embodiment, when the cushion layer 4 is removed, it is removed ring by ring from the plane center of the caisson 2 toward the outer edge of the caisson 2 .
[0137] After the sinking preparation work is completed, the internal and external scaffolding are removed from top to bottom.
[0138] Before chiseling the concrete cushion of the beam, the concrete cushion should be divided into zones and numbered, and then chiseled in the order of the zone numbers. To ensure that the cushion is chiseled symmetrically and evenly, the concrete cushion under the bottom beam of the well should be chiseled first, and then the concrete cushion under the well wall should be chiseled. The chiseling should be carried out symmetrically, evenly and synchronously in order, with unified command and consistent pace. During the concrete chiseling process, the settlement observation of the caisson should be strengthened, and the observation records should be kept well.
[0139] For example: See Figure 5 As shown, the chiseling sequence is as follows: Sequence 1: A1, B1, C1, and D1 are chiseled out simultaneously;
[0140] Sequence 2: A2, B2, C2, and D2 are chiseled out simultaneously;
[0141] …
[0142] As a preferred implementation, before the caisson 2 is drained and sunk, guide soil is backfilled between the blade foot 21 and the slope.
[0143] Specifically, before the caisson sinks, the soil outside the blade foot must be backfilled to +4.5m to give the caisson a good fixed guiding effect.
[0144] According to the characteristics of the soil layer, the sinking coefficient under each working condition is verified and necessary measures are taken according to the sinking coefficient. If the sinking coefficient is large, the sinking is smooth, and the sinking speed is controlled (increasing friction resistance and reversing the bottom of the pot); if the sinking coefficient is small, measures to assist sinking are taken (deep bottom of the pot, weight, air curtain, mud wall resistance reduction), which is generally controlled by controlling the blade foot and bottom beam to take soil. When hydraulic machinery is used to suck mud and sink the soil, a sufficiently large mud pool (soil: mud = 1:3) must be set up outside the site to ensure the continuity of the caisson sinking process.
[0145] When the blade foot is used to cut the soil and sink, the sinking coefficient should be calculated as follows:
[0146]
[0147] In the formula, k st is the sinking coefficient;
[0148] G k is the standard value of deadweight;
[0149] F t is the buoyancy of groundwater during the sinking process (kN), which is taken as 0 when drainage sinking is adopted;
[0150] T f is the total friction between soil and side wall;
[0151] R1 is the ultimate bearing capacity of the soil under the blade tread and the slope (kN);
[0152] R2 is the ultimate bearing capacity of the soil under the partition wall and bottom beam (kN).
[0153] The caisson sinking adopts 4 sets of hydraulic machinery to suck mud and take soil for sinking. The soil is taken symmetrically and evenly layer by layer and bin by bin from the middle of the caisson to the surrounding blades. During the sinking construction process, if the phenomenon of soil and sand flow is found to be serious and has a great impact on the surrounding environment, water will be poured into the caisson for non-drainage sinking.
[0154] The soil extraction such as flushing and suctioning should be carried out evenly and symmetrically to make the caisson sink evenly. The order of soil extraction should follow the principle of starting from the middle and gradually digging to the surroundings, that is, first take the soil under the bottom beam, and then gradually expand to the vicinity of the blade foot, to ensure that the caisson sinks steadily and evenly, and the height difference of the excavated soil surface in the well should not be greater than 0.5m. It is strictly forbidden to dig the soil under the blade foot surface and outside the blade foot surface.
[0155] During the whole process of caisson sinking construction, the excavation scope and method should be flexibly adjusted according to the change of sinking coefficient and soil conditions. In particular, the depth of the central "bottom of the pot" should be strictly controlled to prevent the "bottom of the pot" from being too deep, causing "sudden sinking" phenomenon, uneven settlement or large displacement, and the landslide area outside the well caused by sinking should be backfilled in time.
[0156] During the sinking process of the caisson, frequent measurements, frequent corrections and slow corrections should be made to keep it within the allowable range. In the final sinking stage (when it sinks to 1.5m from the design elevation), tracking and monitoring are required. The control of the sinking and excavation should be slow and steady. According to the sinking coefficient, the bottom beam support can be adopted, the soil under the blade foot can be washed, the oversinking can be strictly controlled, and a pre-sinking amount of 10 to 15 cm should be reserved.
[0157] When the caisson sinks close to the design elevation, the sinking speed is very slow due to the effect of the powder injection piles. According to the settlement observation records, the piles should be removed evenly little by little so that the height difference of the caisson blade foot is controlled within 5cm.
[0158] S8. After caisson 2 sinks to the designed elevation, the bottom of caisson 2 is sealed.
[0159] As a preferred embodiment, when sealing the bottom, the four foot chambers of the caisson 2 are sealed first, and then the other chambers on the outer edge of the caisson 2 are sealed. After the bottoms of the other chambers on the outer edge of the caisson 2 are sealed, the bottoms of the chambers of the caisson 2 are sealed in a ring from the outer edge of the caisson 2 toward the center of the plane of the caisson 2.
[0160] The bottom seal of the caisson is sunk to the designed elevation by drainage. When the self-sinking amount of the caisson is no more than 10mm within 8 hours, the settlement can be considered stable. At this time, the elevation, displacement and inclination of the well body must be within the allowable range. When there is no sudden surge, dry bottom seal is adopted. Underwater bottom seal is adopted as an emergency measure when dry bottom seal is not available.
[0161] Once the caisson sinks to the right position and the settlement is stable, the bottom sealing will be organized. The caisson bottom sealing should first be laid with geotextile, and then a 300mm crushed stone filter layer should be laid and compacted. Before the bottom sealing, the bottom of the pot must be dug out, and the thickness of the bottom sealing concrete must be ensured. The notch position must be rinsed clean, and water-expanding rubber strips must be added. Figure 6 As shown, when sealing the bottom of the caisson, seal the 4 foot compartments first, and then seal the other compartments around them, and then seal the other compartments from the outside to the inside. During the bottom sealing process, the compartments should be poured symmetrically, and each compartment should be poured continuously.
[0162] See also Figure 7 As shown, a water collection well is set up in the well, and the accumulated water is continuously pumped out to keep the well free of water. A pressure relief well 20 is set up at an appropriate position of the caisson before the bottom is sealed. The well is sealed after the internal structure of the caisson is completed and meets the anti-floating requirements. After the bottom of the caisson is sealed, the precipitation cannot be stopped immediately. According to calculation, the precipitation water level is controlled until the upper structure construction is completed.
[0163] The drainage and sinking construction method of a large caisson in a dynamic water soft stratum environment of the present invention takes cement powder injection pile composite foundation reinforcement measures in advance in view of the large sinking coefficient and sinking stability coefficient of the caisson in soft soil areas, improves the bearing capacity of the foundation soil, and avoids overall sudden sinking and tilting during the sinking stage, which may cause safety accidents. Under complex hydrological conditions, a closed three-axis water-stopping curtain is set around the caisson to improve the precipitation effect during the caisson sinking stage to meet the drainage and sinking requirements, reduce the risk of quicksand and sudden surges during the caisson drainage and sinking process, and compared with non-drainage sinking, it does not involve underwater operations, reducing the risk of drainage sinking safety operations.
[0164] The drainage sinking construction method of a large caisson in a dynamic water soft stratum environment of the present invention can produce the bearing capacity of the caisson ground three times, and the ground production and construction are convenient and the construction speed is fast. It adopts drainage sinking and hydraulic machinery to suck mud and take soil. Compared with the undrainage sinking construction process, the sinking is continuous and easy to control, the soil taking is convenient and fast, the sinking is more balanced and easy to correct, and dry bottom sealing can be used, which can speed up the project progress and shorten the construction period significantly.
[0165] The drainage and sinking construction method of a large caisson in a dynamic water soft stratum environment of the present invention is used to improve the quality control of the production and sinking construction of large-volume caissons, ensure that the caisson sinks to perfection once, and that the displacement and height difference after the bottom is sealed meet the specification requirements, thereby avoiding delays in construction and increased costs caused by quality accidents caused by the sinking of the caisson. In addition, the drainage and sinking construction process, compared with the non-drainage sinking construction process, greatly reduces the amount of mud generated, does not require divers for hydraulic mechanical mud suction and soil extraction, and the dry bottom sealing is simple and easy to operate.
[0166] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the present application.
Claims
1. A large caisson drainage and sinking construction method in a dynamic water soft stratum environment, characterized in that: The following steps are involved: The ground at the installation position of the blade foot of the caisson is reinforced with powder injection piles, and the powder injection piles are arranged in a circle along the circumferential direction of the caisson; Constructing a water-stop curtain outside the installation location; A plurality of drainage wells are opened in the stratum inside the water-stop curtain, and the plurality of drainage wells are arranged in a circle along the circumferential direction of the water-stop curtain; excavating a foundation pit on the surface of the installation location; pouring a cushion layer in the foundation pit; Casting the caisson on the cushion layer to form the caisson; The water is discharged from the water-stop curtain through the multiple drainage wells, and the cushion layer is chiseled off, so that the caisson sinks to the designed elevation and is placed on the powder injection piles; After the caisson sinks to the designed elevation, the bottom of the caisson is sealed.
2. The large-scale caisson drainage and sinking construction method in a dynamic water soft stratum environment according to claim 1 is characterized in that: The cement content of the powder injection pile located above the design elevation of the blade foot is less than the cement content of the powder injection pile located below the design elevation of the blade foot.
3. The large caisson drainage and sinking construction method in a dynamic water soft stratum environment according to claim 1 is characterized in that: The water-stop curtain is a double-row three-axis cement mixing pile.
4. The large-scale caisson drainage and sinking construction method in a dynamic water soft stratum environment according to claim 1 is characterized in that: When excavating the foundation pit, slope excavation is adopted, and the slope surface of the foundation pit is supported by sprayed anchors.
5. The large caisson drainage and sinking construction method in a dynamic water soft stratum environment according to claim 4 is characterized in that: Before the caisson is drained and sunk, guide soil is backfilled between the blade foot and the slope.
6. The large caisson drainage and sinking construction method in a dynamic water soft stratum environment according to claim 1 is characterized in that: The cushion layer comprises a sand cushion layer and a concrete cushion layer poured on the sand cushion layer, and a brick membrane supported by the blade foot is built on the concrete cushion layer.
7. The large-scale caisson drainage and sinking construction method in a dynamic water soft stratum environment according to claim 1 is characterized in that: When the cushion layer is removed, it is removed ring by ring from the plane center of the caisson to the outer edge of the caisson.
8. The method for constructing a large caisson by draining and sinking in a water-dynamic soft stratum environment according to claim 1, characterized in that: When sealing the bottom, the four foot chambers of the caisson are sealed first, and then the other chambers on the outer edge of the caisson are sealed. After the other chambers on the outer edge of the caisson are sealed, the bottom of the chambers of the caisson are sealed in a ring from the outer edge of the caisson to the center of the plane of the caisson.