Novel high and large shear wall reinforcing and positioning method

Through the new high shear wall reinforcement and positioning method, the problems of joint quality defects and leakage risks during construction are solved, the positioning accuracy and reinforcement strength of the high shear wall are achieved, and the cleaning work and cost are reduced.

CN118756945APending Publication Date: 2024-10-11ANHUI SANJIAN ENG +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411071149.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

In the construction of tall shear walls, since the one-time formwork cannot be fixed firmly, there is a risk of expansion and explosion of the formwork, resulting in increased risks of joint quality defects, displacement and leakage, and staged pouring increases the cleaning work and cost.

Method used

Adopt new high shear wall reinforcement and positioning methods, including construction of the guide wall at the bottom of the shear wall, installation of binding steel bars and formwork, installation of prefabricated protective layer pads, installation of drilling and water-stopping screws, back corrugation reinforcement, one-time pouring and vibration , remove the formwork and seal the screw holes, set up construction scaffolding and tie the upper steel bars to ensure positioning accuracy and reinforcement strength.

Benefits of technology

It effectively controls the positioning accuracy and reinforcement strength of tall shear walls, reduces the risk of leakage and quality defects caused by multiple staged pouring, avoids waste of concrete, and saves production costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118756945A_ABST
    Figure CN118756945A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of shear wall reinforcing construction, in particular to a novel high and large shear wall reinforcing and positioning method. The method is simple, assembling and disassembling are convenient, and positioning of the formwork support and reinforcing and adjusting of the formwork are achieved through the connection adjusting relation of the nuts and the screws; the operation construction efficiency is greatly improved, the traditional support dismounting cost is reduced, meanwhile, the reinforcing effect of the formwork is greatly enhanced by adding the prefabricated blocks, and a guarantee is provided for high-quality pouring of a high and large shear wall; according to the novel high and large shear wall reinforcing and positioning method, the hidden danger of leakage caused by secondary construction of the high and large shear wall is effectively eliminated, and meanwhile the position accuracy and the reinforcing strength of the high and large shear wall are ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shear wall reinforcement construction, in particular to a novel high shear wall reinforcement positioning method. Background Art

[0002] With the rapid development of urbanization, there are more and more urban sewage treatment stations and domestic water supply stations, and the pressure on urban sewage treatment and tap water supply is increasing. In order to alleviate the urban sewage treatment and domestic water supply, more and more treatment and supply equipment are needed.

[0003] Shear wall structures are often seen in high-rise residential projects, where the mid-story height of the basement structure is generally no more than 5m, and the upper main structure is generally no more than 3m. The height of the pools for sewage treatment and domestic water supply is mostly over 6m, and some even reach over 10m.

[0004] In the construction of such high shear walls, since one-time formwork cannot be fixed firmly and there is a risk of formwork expansion and explosion, segmented formwork, segmented reinforcement, and segmented concrete pouring are often adopted during the construction process. The more segmentation times, the more joint quality defects the shear wall will have due to construction reasons. When the concrete is poured and vibrated, it is easy to shift. If displacement occurs, additional chiseling work will be required later due to excessive displacement. Increasing the number of segmentation times will also increase the chiseling work and the risk of leakage.

[0005] Based on this, the present invention provides a new method for fixing and positioning tall shear walls to solve the above-mentioned technical problems! Summary of the invention

[0006] The purpose of the present invention is to provide a novel method for fixing and positioning tall shear walls, which can eliminate the leakage risk caused by multiple pouring of tall shear walls, ensure the position accuracy of tall shear walls, reduce the quality defects caused by secondary cleaning and inadequate surface treatment, avoid waste of concrete, and save production costs.

[0007] To achieve the above object, the present invention provides the following technical solutions: The present invention provides a novel method for fixing and positioning a tall shear wall, comprising the following steps: S1. Construction of guide wall at the bottom of shear wall: pour concrete guide wall at the root of shear wall according to the positioning of design drawings; S2. Tie up the steel bars and install the formwork: tie up the guide wall steel bars and plate steel bars at the design position according to the design drawings and the steel bar construction plan, and support the wall side formwork; S3. Place prefabricated protective layer pads: During the reinforcement binding process of the shear wall, the prefabricated protective layer pads are installed according to the position of the shear wall reinforcement and the design drawings; S4. Drilling the tie holes: Drill holes on the shear wall formwork. When the upper part of the shear wall formwork is less than 400mm, add another tie hole and install the first water stop screw after drilling the hole. S5. Install the back ribs at one time: install a vertical back rib on both sides of the first water stop screw for reinforcement; S6. Pouring and vibrating of guide wall concrete: After pouring concrete into the mold, use an inserted vibrating rod to gradually pull it out from one end. When vibrating, the surface layer should be shiny and free of bubbles. S7, Guide wall formwork removal, maintenance and screw hole plugging: After removing the formwork, clean and maintain the surface, and clean and plug the screw holes; S8. Erecting construction scaffolding: Erecting construction scaffolding on the outside of the guide wall; S9. Tie up the upper reinforcement of the guide wall and install the formwork: tie up the upper reinforcement of the guide wall and install the upper shear wall side formwork in accordance with the design drawings and the reinforcement engineering construction plan at the design position of the drawings; S10. Place prefabricated protective layer pads on the upper wall of the guide wall: During the shear wall reinforcement binding process, the prefabricated protective layer pads are installed according to the position of the shear wall reinforcement and the design drawings; S11. Drilling holes in the upper wall of the guide wall: Drill holes on the shear wall formwork. When the upper part of the shear wall formwork is less than 400mm, add a tension hole and install the second water stop screw after drilling. S12, secondary installation of back ribs: install a horizontal square steel back rib on the upper wall of the concrete guide wall, and install a vertical back rib on both sides of the second water stop screw for reinforcement; S13, reinforcement: After installing the second water stop screw, as well as the horizontal and vertical back ribs on the shear wall, install the tie rod for reinforcement; S14. Concrete pouring and vibrating of the upper wall of the guide wall: After pouring the concrete into the mold, use an inserted vibrating rod to gradually pull it out from one end. When vibrating, the surface layer should be shiny and free of bubbles; S15. Maintenance of the upper wall of the guide wall, removal of formwork and sealing of screw holes: After removing the formwork, clean the surface and chisel and seal the screw holes.

[0008] The present invention is further configured as follows: in the step S1, the height of the concrete guide wall is 1 m.

[0009] The present invention is further configured as follows: in step S1, the first water stop bar at the root of the concrete guide wall is 250 mm away from the bottom plate, the second water stop bar is 250 mm away from the first water stop bar, and the third water stop bar is 300 mm away from the second water stop bar.

[0010] The present invention is further configured as follows: in step S3, the prefabricated protective layer pad is prefabricated in advance using concrete of the same grade as the shear wall, and the width and height of the prefabricated protective layer pad is not less than 40 mm, and the length is 15 mm less than the width of the shear wall.

[0011] The present invention is further configured as follows: in the step S4, when punching holes on the shear wall formwork, the hole spacing is 400×400 mm.

[0012] The present invention is further configured as follows: in step S8, the construction scaffold is 300 mm away from the outer edge of the guide wall concrete.

[0013] The present invention is further configured as follows: in the step S12, the spacing of the horizontal square steel back ribs installed on the upper wall of the concrete guide wall is not greater than 500×500mm, and the spacing of the vertical back rib reinforcement is not greater than 500×500mm.

[0014] The present invention is further configured as follows: in step S13, the tie rods are made of seamless steel pipes, the ends of which are welded with 3mm thick 100mm diameter round plates or 100×100mm square plates, and steel bars with a diameter of 16mm are passed through the middle.

[0015] Compared with the prior art, the present invention has the following beneficial effects: The novel tall shear wall reinforcement positioning method provided by the present invention can effectively control the positioning accuracy and reinforcement strength of the tall shear wall, ensure the one-time forming effect of the tall shear wall, eliminate the chiseling labor consumption and leakage risk caused by multiple segmented casting of the tall shear wall, and also reduce the quality defects caused by secondary cleaning and inadequate surface treatment, while avoiding the waste of concrete and saving production costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 is a cross-sectional view of the shear wall of the present invention; Figure 2 It is the elevation view of the shear wall of the present invention.

[0017] Legend: 100, first water-stop screw; 200, second water-stop screw; 300, tension rod; 400, square steel back rib. DETAILED DESCRIPTION

[0018] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Example

[0019] like Figure 1-Figure 2 As shown, this embodiment provides a novel method for fixing and positioning a tall shear wall, comprising the following steps: S1. Construction of guide wall at the bottom of shear wall: According to the positioning of the design drawings, pour concrete guide wall at the root of the shear wall.

[0020] Among them, the height of the concrete guide wall is 1m.

[0021] The first waterstop bar at the root of the concrete guide wall is 250mm away from the bottom plate, the second waterstop bar is 250mm away from the first waterstop bar, and the third waterstop bar is 300mm away from the second waterstop bar.

[0022] In this embodiment, it should be noted that, at the guide wall portion, the lateral spacing along the length direction is not greater than 600 mm.

[0023] S2. Tie up the steel bars and install the formwork: According to the design drawings and the steel bar construction plan, tie up the guide wall steel bars and plate steel bars at the designed position in the drawings, and support the wall side formwork.

[0024] In this embodiment, it should be noted that the guide wall reinforcement and the plate reinforcement are tied and the template on one side of the guide wall is supported, and the template on the other side is installed after the prefabricated thin layer pad is installed.

[0025] S3. Place prefabricated protective layer pads: During the reinforcement binding process of the shear wall, the prefabricated protective layer pads are installed according to the position of the shear wall reinforcement and the design drawings.

[0026] Among them, the prefabricated protective layer pads are prefabricated in advance using concrete of the same grade as the shear wall, and the width and height of the prefabricated protective layer pads are not less than 40mm, and the length is 15mm smaller than the width of the shear wall.

[0027] S4. Drilling tension holes: Drill holes on the shear wall formwork. When the upper part of the shear wall formwork is less than 400 mm, add another tension hole and install the first water stop screw 100 after drilling the hole.

[0028] Among them, when drilling holes on the shear wall formwork, the drilling spacing is 400×400mm.

[0029] It should be noted that in this embodiment, the specification of the first water-stop screw 100 is 12#.

[0030] S5. Install the back ribs at one time: install a vertical back rib on both sides of the first water stop screw 100 for reinforcement.

[0031] S6. Pouring and vibrating of guide wall concrete: After pouring the concrete into the mold, use an inserted vibrating rod to gradually pull it out from one end. When vibrating, the surface layer should be shiny and free of bubbles.

[0032] In this embodiment, it should be noted that care should be taken when vibrating the bolt positions to avoid prolonged vibration and contact.

[0033] S7. Guide wall formwork removal, maintenance and screw hole sealing: After removing the formwork, clean and maintain the surface, and clean and seal the screw holes.

[0034] S8. Set up construction scaffolding: Set up construction scaffolding on the outside of the guide wall.

[0035] Among them, the construction scaffolding is 300mm away from the outer edge of the guide wall concrete.

[0036] S9. Binding of upper guide wall reinforcement and installation of formwork: According to the design drawings and the reinforcement construction plan, bind the upper guide wall reinforcement at the designed position in the drawings and support the upper shear wall side formwork.

[0037] S10. Place prefabricated protective layer pads on the upper wall of the guide wall: During the shear wall reinforcement binding process, the prefabricated protective layer pads are installed according to the position of the shear wall reinforcement and the design drawings.

[0038] In this embodiment, it should be noted that the prefabricated protective layer pads are prefabricated in advance using the same grade of concrete as the shear wall, with a width and height of not less than 40 mm, and a length that is 15 mm smaller than the width of the shear wall.

[0039] S11. Drilling holes on the upper wall of the guide wall: Drill holes on the shear wall formwork. When the upper part of the shear wall formwork is less than 400 mm, add a tension hole and install the second water stop screw 200 after drilling.

[0040] In this embodiment, it should be noted that when the height of the shear wall with tension holes is less than 5m, there should be no less than two, and when it is less than 8m, there should be no less than 3, and the lateral spacing should not be greater than 4m.

[0041] S12, secondary installation of back ribs: installing a horizontal square steel back rib 400 on the upper wall of the concrete guide wall, and installing a vertical back rib on both sides of the second water stop screw 200 for reinforcement.

[0042] Among them, the spacing of a horizontal square steel back rib 400 installed on the upper wall of the concrete guide wall is not greater than 500×500mm, the spacing of the vertical back rib reinforcement is not greater than 500×500mm, and the specification of the second water stop screw 200 is 16#.

[0043] S13, reinforcement: after installing the second water stop screw 200 and the horizontal and vertical back ribs on the shear wall, install the tie rod 300 for reinforcement.

[0044] The tie rod 300 is made of seamless steel pipe, the end of which is welded with a 3mm thick 100mm diameter round plate or a 100×100mm square plate, and a 16mm diameter steel bar is passed through the middle.

[0045] In this embodiment, it should be noted that the length of the tie rod 300 is determined according to construction requirements, and the length of the first section from the bottom plate upward is not less than 2 m.

[0046] S14. Pouring and vibrating of concrete for the upper part of the guide wall: After pouring the concrete into the mold, use an inserted vibrating rod to gradually pull it out from one end. When vibrating, the surface layer should be shiny and free of bubbles.

[0047] In this embodiment, it should be noted that the height of concrete entering the mold should not be greater than 1m, and the speed should not be too fast. In addition, attention should be paid to the vibration of the bolt position to avoid prolonged vibration and contact.

[0048] S15. Maintenance of the upper wall of the guide wall, removal of formwork and sealing of screw holes: After removing the formwork, clean the surface and chisel and seal the screw holes.

[0049] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0050] The preferred embodiments of the present invention disclosed above are only used to help illustrate the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. A new type of high shear wall reinforcement and positioning method, characterized in that: The following steps are involved: S1. Construction of guide wall at the bottom of shear wall: pour concrete guide wall at the root of shear wall according to the positioning of design drawings; S2. Tie up the steel bars and install the formwork: tie up the guide wall steel bars and plate steel bars at the design position according to the design drawings and the steel bar construction plan, and support the wall side formwork; S3. Place prefabricated protective layer pads: During the reinforcement binding process of the shear wall, the prefabricated protective layer pads are installed according to the position of the shear wall reinforcement and the design drawings; S4. Drilling the tie holes: Drill holes on the shear wall formwork. When the upper part of the shear wall formwork is less than 400mm, add another tie hole and install the first water stop screw after drilling the hole. S5. Install the back ribs at one time: install a vertical back rib on both sides of the first water stop screw for reinforcement; S6. Pouring and vibrating of guide wall concrete: After pouring concrete into the mold, use an inserted vibrating rod to gradually pull it out from one end. When vibrating, the surface layer should be shiny and free of bubbles. S7, Guide wall formwork removal, maintenance and screw hole plugging: After removing the formwork, clean and maintain the surface, and clean and plug the screw holes; S8. Erection of construction scaffolding: Erection of construction scaffolding on the outside of the guide wall; S9. Tie up the upper reinforcement of the guide wall and install the formwork: tie up the upper reinforcement of the guide wall and install the upper shear wall side formwork in accordance with the design drawings and the reinforcement engineering construction plan at the design position of the drawings; S10. Prefabricated protective layer pads are placed on the upper wall of the guide wall: during the shear wall reinforcement binding process, the prefabricated protective layer pads are installed according to the position of the shear wall reinforcement and the design drawings; S11. Drilling holes in the upper wall of the guide wall: Drill holes in the shear wall formwork. When the upper part of the shear wall formwork is less than 400mm, add a tension hole and install the second water stop screw after drilling. S12, secondary installation of back ribs: install a horizontal square steel back rib on the upper wall of the concrete guide wall, and install a vertical back rib on both sides of the second water stop screw for reinforcement; S13, reinforcement: After installing the second water stop screw, as well as the horizontal and vertical back ribs on the shear wall, install the tie rod for reinforcement; S14. Concrete pouring and vibrating of the upper wall of the guide wall: After pouring the concrete into the mold, use an inserted vibrating rod to gradually pull it out from one end. When vibrating, the surface layer should be shiny and free of bubbles; S15. Maintenance of the upper wall of the guide wall, removal of formwork and sealing of screw holes: After removing the formwork, clean the surface and chisel and seal the screw holes.

2. A novel high shear wall reinforcement and positioning method according to claim 1, characterized in that: In the step S1, the height of the concrete guide wall is 1 m.

3. A novel high shear wall reinforcement and positioning method according to claim 1, characterized in that: In step S1, the first water stop bar at the root of the concrete guide wall is 250 mm away from the bottom plate, the second water stop bar is 250 mm away from the first water stop bar, and the third water stop bar is 300 mm away from the second water stop bar.

4. A novel high shear wall reinforcement and positioning method according to claim 1, characterized in that: In step S3, the prefabricated protective layer pad is prefabricated in advance using concrete of the same grade as the shear wall, and the width and height of the prefabricated protective layer pad are not less than 40 mm, and the length is 15 mm less than the width of the shear wall.

5. A novel high shear wall reinforcement and positioning method according to claim 1, characterized in that: In the step S4, when punching holes on the shear wall formwork, the hole spacing is 400×400 mm.

6. A novel high shear wall reinforcement and positioning method according to claim 1, characterized in that: In step S8, the construction scaffold is 300 mm away from the outer edge of the guide wall concrete.

7. A novel high shear wall reinforcement and positioning method according to claim 1, characterized in that: In the step S12, the spacing of the transverse square steel back ribs installed on the upper wall of the concrete guide wall is not greater than 500×500mm, and the spacing of the vertical back ribs for reinforcement is not greater than 500×500mm.

8. A novel high shear wall reinforcement and positioning method according to claim 1, characterized in that: In step S13, the tie rods are made of seamless steel pipes, the ends of which are welded with 3mm thick 100mm diameter round plates or 100×100mm square plates, and steel bars with a diameter of 16mm are passed through the middle.