Temporary lifting point structure for dismantling ultrahigh large-span pole tower
By designing a temporary lifting point structure, using the upper arc plate, lower arc plate and spiral slot to fix the lifting rope, and combining the semicircular gear ring and the rotating motor to wrap the fixed wire, the problem of sliding displacement of the lifting rope is solved and the connection is ensured tube stability and safety.
Patent Information
- Application Number
- CN202410753526.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-12
- Publication Date
- 2024-10-11
AI Technical Summary
During the dismantling process of the pole tower, the hanging rope is easy to slide and shift at the binding place, causing the connecting pipe to shake and tilt, and even risk falling from high altitude.
A temporary lifting point structure is designed, including an upper arc plate and a lower arc plate, which are fixed on the connecting pipe through bolts, and have a spiral slot on its outer wall to fix the lifting rope, combined with a semicircular gear ring and a rotating motor , by driving the fixed wire to wrap around the connecting pipe to ensure that the hanging rope is stable.
It effectively prevents the hanging rope from sliding, ensures the stability of the connecting pipe during the lifting process, reduces the risk of falling, and improves safety.
Smart Images

Figure CN118757019A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pole tower dismantling, and in particular to a temporary hanging point structure for dismantling a super-high and long-span pole tower. Background Art
[0002] When dismantling a pole tower, a crane is needed to dismantle the tower body. The tower body includes 4 support columns, and there are multiple cross-arranged connecting pipes between adjacent support columns. When hoisting the connecting pipes, since the connecting pipes are multiple cross-arranged, the lifting ropes need to be tied to the extra positions on the connecting pipes to ensure the balance of the connecting pipes during hoisting. However, when hoisting the connecting pipes, since they are hoisted at high altitudes, the connecting pipes are easily blown by the wind, causing the connecting pipes to shake, which can easily cause the lifting ropes to slide and shift at the binding position, causing the connecting pipes to tilt during hoisting. In severe cases, there is a risk that the connecting pipes will fall from high altitudes. Therefore, a temporary lifting point structure for dismantling super-high and large-span pole towers is needed, which can be firmly fixed on the connecting pipes. Summary of the invention
[0003] The purpose of the embodiment of the present invention is to provide a temporary hanging point structure for dismantling super-high and long-span pole towers, which can solve the problem of sliding displacement of the hanging rope at the binding point, so that the hanging rope can be firmly fixed on the connecting pipe.
[0004] In order to achieve the above-mentioned object, an embodiment of the present invention provides a temporary hanging point structure for dismantling a super-high and long-span pole tower, the temporary hanging point structure comprising:
[0005] An upper arc plate, wherein the top and bottom of the upper arc plate are provided with symmetrical connecting plates;
[0006] A lower arc plate, together with the upper arc plate, forms a through cavity for the connecting pipe of the tower body to pass through, and symmetrical connecting plates are provided at the top and bottom of the lower arc plate;
[0007] Bolts, respectively passing through the connecting plates at the connection of the upper arc plate and the lower arc plate, and connected with nuts, so as to connect the upper arc plate and the lower arc plate together and fix them on the connecting pipe;
[0008] The outer side walls of the upper arc plate and the lower arc plate are provided with a first through groove which spirally extends along the length direction.
[0009] Optionally, the temporary hanging point structure includes:
[0010] Semicircular gear rings are respectively arranged on the top and bottom of the upper arc plate and the lower arc plate, and can form a circular gear ring when the upper arc plate and the lower arc plate are combined, and the teeth of the semicircular gear ring face outward;
[0011] An arc-shaped support plate, disposed on the semicircular gear ring and capable of sliding along the semicircular gear ring;
[0012] A first gear is rotatably disposed on the arc-shaped support plate and does not contact the upper arc plate or the lower arc plate;
[0013] A second gear, rotatably disposed on the arc-shaped support plate, disposed on the side of the first gear, and meshing with the first gear and the semicircular gear ring;
[0014] A third gear is rotatably disposed on the arc-shaped support plate and is symmetrically disposed on the side of the first gear with respect to the second gear, and the third gear is meshed with the first gear and the semicircular gear ring;
[0015] A rotating motor, disposed on the arc-shaped support plate and connected to the rotating shaft of the first gear, so as to drive the first gear to rotate;
[0016] The wire-releasing part is arranged on the arc-shaped supporting plate, so as to be driven by the arc-shaped supporting plate to move along the semicircular gear ring and wind the fixing wire around the connecting pipe.
[0017] Optionally, the temporary hanging point structure includes a positioning groove, which is arranged on the side of one of the two semicircular gear rings in contact with each other; a positioning block, which is arranged on the side of the other of the two semicircular gear rings in contact with each other, and the positioning block can be stuck in the positioning groove.
[0018] Optionally, the fixing line is a flat strip.
[0019] Optionally, the pay-off unit includes:
[0020] A support platform, arranged on the arc-shaped support plate;
[0021] A pay-off roller is arranged on the arc-shaped support plate, and the top and the bottom of the pay-off roller are rotatably connected to the support platform and the arc-shaped support plate respectively, and a fixed line is wound around the pay-off roller.
[0022] Optionally, the wire-paying part includes two guide columns, the top of the guide columns is connected to the support platform, the bottom of the guide columns is connected to the arc-shaped support plate, and the two guide columns are arranged on the side of the wire-paying roller close to the through cavity, and the fixed line passes between the two guide columns.
[0023] Optionally, the line-releasing part includes a telescopic motor, which is arranged on the support platform, one of the two guide columns is fixedly arranged, and the top of the other guide column is connected to the telescopic shaft of the telescopic motor.
[0024] Optionally, an opening is provided on a side of the support platform away from the through cavity, and a top plate is provided on the top of the pay-off roller, and the top plate can be inserted into the opening.
[0025] Optionally, a T-shaped through slot is provided on the semicircular gear ring, and a T-shaped clamp is provided on one side of the arc-shaped support plate close to the semicircular gear ring, and the T-shaped clamp can be inserted into the T-shaped through slot and can slide along the T-shaped through slot.
[0026] Through the above technical scheme, the temporary suspension point structure for dismantling a super-high and large-span pole tower provided by the present invention is provided with an upper arc plate and a lower arc plate, and the upper arc plate and the lower arc plate can jointly form a through cavity for the connection pipe to pass through, so that the upper arc plate and the lower arc plate can be matched and fixed on the connection pipe, and symmetrical connection plates can be provided on the top and bottom of the upper arc plate and the lower arc plate. Bolts can pass through the connection plates at the connection of the upper arc plate and the lower arc plate respectively, and can be connected with nuts, so that the upper arc plate and the lower arc plate can be fixed on the connection pipe. A first through groove extending spirally along the length direction of the upper arc plate can be provided on the outer side wall of the upper arc plate and the lower arc plate. After the upper arc plate and the lower arc plate are fixed to the connection pipe, the lifting rope can be wound around the outer side wall of the upper arc plate and the lower arc plate along the first through groove, and because the first through groove is spiral, the lifting rope can be better fixed, so that the lifting rope will not shake at will when the connection pipe is hoisted.
[0027] Other features and advantages of the embodiments of the present invention will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The accompanying drawings are used to provide a further understanding of the embodiments of the present invention and constitute a part of the specification. Together with the following specific implementations, they are used to explain the embodiments of the present invention, but do not constitute a limitation on the embodiments of the present invention. In the accompanying drawings:
[0029] Figure 1 It is an overall schematic diagram of a temporary hanging point structure for dismantling a super-high and long-span pole tower according to one embodiment of the present invention;
[0030] Figure 2 is a top view of a temporary hanging point structure for dismantling a super-high and long-span pole tower according to an embodiment of the present invention;
[0031] Figure 3 is a cross-sectional view of a temporary hanging point structure for dismantling a super-high and long-span tower according to an embodiment of the present invention;
[0032] Figure 4 It is a bottom three-dimensional view of a wire-laying portion of a temporary hanging point structure for dismantling a super-high and long-span pole tower according to one embodiment of the present invention;
[0033] Figure 5It is a top three-dimensional view of a wire-laying portion of a temporary hanging point structure for dismantling a super-high and long-span pole tower according to one embodiment of the present invention;
[0034] Figure 6 The diagram is a three-dimensional view of a semicircular gear ring of a temporary suspension point structure for dismantling a super-high and long-span pole tower according to an embodiment of the present invention.
[0035] Description of Reference Numerals
[0036] 1. Upper arc plate 2. Connecting plate
[0037] 3. Lower arc plate 4. Through cavity
[0038] 5. Bolt 6. Nut
[0039] 7. First through groove 8. Semicircular gear ring
[0040] 9. Arc support plate 10. First gear
[0041] 11. Second gear 12. Third gear
[0042] 13. Rotating motor 14. Pay-off unit
[0043] 140, support platform 141, pay-off roller
[0044] 142. Guide column 143. Telescopic motor
[0045] 15. Positioning slot 16. Positioning block
[0046] 17. Opening 18. Top plate
[0047] 19. T-shaped slot 20. T-shaped block DETAILED DESCRIPTION
[0048] The specific implementation of the embodiment of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the embodiment of the present invention, and is not used to limit the embodiment of the present invention.
[0049] Figure 1It is an overall schematic diagram of a temporary suspension point structure for dismantling a super-high and long-span pole tower according to an embodiment of the present invention. In the present invention, the temporary suspension point structure may include: an upper arc plate 1, a lower arc plate 3, and bolts 5. Symmetrical connecting plates 2 may be provided at the top and bottom of the upper arc plate 1. The lower arc plate 3 may form a through cavity 4 for the connecting pipe of the tower body to pass through together with the upper arc plate 1. Symmetrical connecting plates 2 may be provided at the top and bottom of the lower arc plate 3. The number of the bolts 5 may be multiple, and each bolt 5 may pass through the corresponding connecting plate 2 at the connection of the upper arc plate 1 and the lower arc plate 3, and may be connected with a nut 6, so that the upper arc plate 1 and the lower arc plate 3 may be connected together and may be fixed on the connecting pipe. The outer side walls of the upper arc plate 1 and the lower arc plate 3 may be provided with a first through groove 7 that extends spirally along the length direction of the upper arc plate 1. The first through groove 7 may be a bolt extending along the length direction of the upper arc plate 1 when the upper arc plate 1 and the lower arc plate 3 are combined together. Because the outer side walls of the upper arc plate 1 and the lower arc plate 3 are provided with a first through groove 7, after the upper arc plate 1 and the lower arc plate 3 are fixed on the connecting pipe, the lifting rope can be wrapped around the outer side walls of the upper arc plate 1 and the lower arc plate 3 along the first through groove 7, and can be wrapped multiple times to prevent the lifting rope from sliding on the upper arc plate 1 and the lower arc plate 3, and the lifting rope can be better fixed so that the lifting rope will not shake at will when the connecting pipe is lifted.
[0050] In one embodiment of the present invention, Figure 2 , Figure 3 and Figure 4As shown, the temporary suspension point structure may include: a semicircular gear ring 8, an arc support plate 9, a first gear 10, a second gear 11, a third gear 12, a rotating motor 13 and a wire release part 14. The number of the semicircular gear rings 8 may be multiple, and they may be respectively arranged at the top and bottom of the upper arc plate 1 and the lower arc plate 3, and they may be combined into a circular gear ring when the upper arc plate 1 and the lower arc plate 3 are combined. The teeth of the semicircular gear ring 8 may face outward. The arc support plate 9 may be arranged on the semicircular gear ring 8 and may slide along the semicircular gear ring 8. The first gear 10 may be rotatably arranged on the arc support plate 9, and the first gear 10 may not contact the upper arc plate 1 or the lower arc plate 3. The second gear 11 may be rotatably arranged on the arc support plate 9, and may be arranged on the side of the first gear 10. The second gear 11 can be meshed with the first gear 10 and the semicircular gear ring 8. When the first gear 10 rotates, the second gear 11 can be driven to rotate by the first gear 10. Because the second gear 11 is meshed with the semicircular gear ring 8, and the semicircular gear ring 8 is fixed on the upper arc plate 1 and the lower arc plate 3, when the second gear 11 is driven to rotate, the second gear 11 can be driven to rotate along the semicircular gear ring 8, and the arc support plate 9 can be driven to rotate along the semicircular gear ring 8. When the two semicircular gear rings 8 are combined together, the arc support plate 9 can be driven to make a circular motion along the semicircular gear ring 8. The rotating motor 13 can be arranged on the arc support plate 9 and can be connected to the rotating shaft of the first gear 10, so as to drive the first gear 10 to rotate, and then drive the arc support plate 9 to make a circular motion. The wire-releasing part 14 can be arranged on the arc-shaped support plate 9, so that when the arc-shaped support plate 9 is driven to move along the semicircular gear ring 8, the wire-releasing part 14 can wind the fixed wire (not shown in the figure) around the connecting pipe. Because the semicircular gear ring 8 and the wire-releasing part 14 are both arranged on the top and bottom of the upper arc plate 1 and the lower arc plate 3, after the wire-releasing part 14 winds the fixed wire around the connecting pipe, the top and bottom of the upper arc plate 1 and the lower arc plate 3 will be fixed by the wound fixed wire, thereby further increasing the stability of the upper arc plate 1 and the lower arc plate 3, so that the upper arc plate 1 and the lower arc plate 3 will not shake on the connecting pipe during the hoisting process, so that the hoisting rope can stably hoist the connecting pipe.
[0051] In the present invention, the temporary suspension point structure may further include a third gear 12. The third gear 12 may be rotatably disposed on the arc-shaped support plate 9, and the third gear 12 may be symmetrically disposed on the side of the first gear 10 with the second gear 11. The third gear 12 may mesh with the first gear 10 and the semicircular gear ring 8. The third gear 12 and the second gear 11 are symmetrically disposed and both mesh with the semicircular gear ring 8. When the size of the connecting pipe is too large and the two semicircular gear rings 8 cannot be completely merged into one circular gear ring, the second gear 11 and the third gear 12 are disposed to ensure that when one gear passes through the connection of the two semicircular gear rings 8, the other gear may mesh with the semicircular gear ring 8 to ensure that the arc-shaped support plate 9 may slide smoothly along the semicircular gear ring 8.
[0052] In one embodiment of the present invention, Figure 3 and Figure 6 As shown. The temporary suspension point structure may include a positioning groove 15 and a positioning block 16. The positioning groove 15 may be provided on the side of one of the two semicircular gear rings 8 that are in contact with each other. The positioning block 16 may be provided on the side of the other of the two semicircular gear rings 8 that are in contact with each other, and the positioning block 16 may be inserted into a positioning groove 15. The provision of the positioning block 16 and the positioning groove 15 may enable the upper arc plate 1 and the lower arc plate 3 to be accurately combined when combined, and will not be misaligned.
[0053] In one embodiment of the present invention, the fixing line may be a flat strip, and when it is wound onto the connecting tube, the flat structure may be more stably fixed onto the connecting tube, thereby more stably fixing the upper arc plate 1 and the lower arc plate 3.
[0054] In one embodiment of the present invention, Figure 5 As shown, the pay-off section 14 may include: a support platform 140 and a pay-off roller 141. The support platform 140 may be arranged on the arc support plate 9. The pay-off roller 141 may be arranged on the arc support plate 9, and the top and bottom of the pay-off roller 141 may be rotatably connected to the support platform 140 and the arc support plate 9, respectively. A fixed line may be wound around the pay-off roller 141. After the upper arc plate 1 and the lower arc plate 3 are fixed to the connecting tube, one end of the fixed line on the pay-off roller 141 may be connected to the connecting tube, and then the pay-off roller 141 may be driven to rotate around the connecting tube, and then the fixed line on the pay-off roller 141 may be wound around the connecting tube, so that the upper arc plate 1 and the lower arc plate 3 can be further fixed.
[0055] In one embodiment of the present invention, Figure 5As shown, the wire-releasing part 14 may include two guide posts 142. The tops of the two guide posts 142 may be connected to the support platform 140, and the tops of the guide posts 142 may be connected to the arc-shaped support plate 9. The two guide posts 142 may be arranged on one side of the wire-releasing roller 141 close to the through cavity 4, and the fixed wire may pass between the two guide posts 142. The two guide posts 142 may allow the fixed wire to be stably wound around the connecting pipe when winding around the connecting pipe.
[0056] In one embodiment of the present invention, Figure 5 As shown, the wire-releasing part 14 may include a telescopic motor 143. The telescopic motor 143 may be arranged on the support platform 140. One of the two guide posts 142 may be fixedly arranged, and the top of the other guide post 142 may be connected to the telescopic shaft of the telescopic motor 143, so that it can be driven by the telescopic shaft of the telescopic motor 143 to move closer to or away from the guide post 143 on its side. This arrangement allows the fixed line to remain in a taut state when it is wound around the connecting tube, so that it can be better wound around the connecting tube. When the winding stops, the two guide posts 142 can be further approached to clamp the fixed line, so that the taut state of the fixed line can be maintained, so that the fixed line will not loosen after being wound around the connecting tube, so as to better fix the upper arc plate 1 and the lower arc plate 3.
[0057] In one embodiment of the present invention, Figure 5 As shown, the side of the support platform 140 away from the through cavity 4 may be provided with an opening 17. The top of the pay-off roller 141 may be provided with a top plate 18, and the top plate 18 may be stuck in the opening 17. Because the top plate 18 provided on the top of the pay-off roller 141 can be stuck in the opening 17, the pay-off roller 141 is detachable. After the fixed line on the pay-off roller 141 is used up, the pay-off roller 141 can be removed, and then the fixed line can be rewound to be stuck on the support platform 140 again, so as to wind the connecting pipe again.
[0058] In one embodiment of the present invention, a T-shaped through groove 19 may be provided on the semicircular gear ring 8. A T-shaped block 20 may be provided on one side of the arc-shaped support plate 9 close to the semicircular gear ring 8. The T-shaped block 20 may be inserted into the T-shaped through groove 19 and may slide along the T-shaped through groove 19, so that the arc-shaped support plate 9 may be fixed to the semicircular gear ring 8 and may slide along the semicircular gear ring 8. There may be a certain gap between the T-shaped block 20 and the T-shaped through groove 19, so that the T-shaped block 20 may slide along the T-shaped through groove 19, and when the two semicircular gear rings 8 cannot be combined together, the T-shaped block 20 may slide along the T-shaped through groove 19 of one semicircular gear ring 8 into the T-shaped through groove 19 on the other semicircular gear ring 8, so that the arc-shaped support plate 9 may slide stably along the semicircular gear ring 8.
[0059] In the present invention, the top and bottom of the upper arc plate 1 and the lower arc plate 3 can be symmetrically arranged, so when the upper arc plate 1 and the lower arc plate 3 are fixed to the connecting pipe, the connecting pipe can be fixed at the top and bottom of the upper arc plate 1 and the lower arc plate 3 together.
[0060] Through the above technical scheme, the temporary suspension point structure for dismantling a super-high and large-span pole tower provided by the present invention is provided with an upper arc plate and a lower arc plate, and the upper arc plate and the lower arc plate can jointly form a through cavity for the connection pipe to pass through, so that the upper arc plate and the lower arc plate can be matched and fixed on the connection pipe, and symmetrical connection plates can be provided on the top and bottom of the upper arc plate and the lower arc plate. Bolts can pass through the upper arc plate and the lower arc plate to obtain the connection plates at the connection, and can be connected with nuts, so that the upper arc plate and the lower arc plate can be fixed on the connection pipe. A first through groove extending spirally along the length direction of the upper arc plate can be provided on the outer side wall of the upper arc plate and the lower arc plate. After the upper arc plate and the lower arc plate are fixed to the connection pipe, the lifting rope can be wound around the outer side wall of the upper arc plate and the lower arc plate along the first through groove, and because the first through groove is spiral, the lifting rope can be better fixed, so that the lifting rope will not shake at will when the connection pipe is hoisted.
[0061] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.
[0062] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.
Claims
1. A temporary suspension point structure for dismantling super-high and long-span towers, characterized in that: The temporary hanging point structure comprises: An upper arc plate (1), wherein the top and bottom of the upper arc plate (1) are provided with symmetrical connecting plates (2); A lower arc plate (3) and the upper arc plate (1) together form a through cavity (4) for the connecting pipe of the tower body to pass through, and symmetrical connecting plates (2) are provided at the top and bottom of the lower arc plate (3); Bolts (5) are respectively passed through the connecting plates (2) at the connection points of the upper arc plate (1) and the lower arc plate (3) and connected with nuts (6) to connect the upper arc plate (1) and the lower arc plate (3) together and fix them on the connecting pipe; The outer side walls of the upper arc plate (1) and the lower arc plate (3) are provided with a first through groove (7) which extends spirally along the length direction.
2. The temporary hanging point structure according to claim 1, characterized in that: The temporary hanging point structure comprises: A semicircular gear ring (8) is respectively arranged on the top and bottom of the upper arc plate (1) and the lower arc plate (3), and can form a circular gear ring when the upper arc plate (1) and the lower arc plate (3) are combined, and the teeth of the semicircular gear ring (8) face outwards; An arc-shaped support plate (9) is arranged on the semicircular gear ring (8) and is capable of sliding along the semicircular gear ring (8); A first gear (10) is rotatably disposed on the arc-shaped support plate (9) and does not contact the upper arc plate (1) or the lower arc plate (3); A second gear (11) is rotatably disposed on the arc-shaped support plate (9), disposed on a side of the first gear (10), and meshing with the first gear (10) and the semicircular gear ring (8); a third gear (12) rotatably disposed on the arc-shaped support plate (9) and symmetrically disposed on the side of the first gear (10) with respect to the second gear (11), the third gear (12) being meshed with the first gear (10) and the semicircular gear ring (8); a rotating motor (13), which is arranged on the arc-shaped support plate (9) and connected to the rotating shaft of the first gear (10) to drive the first gear (10) to rotate; The wire-releasing part (14) is arranged on the arc-shaped support plate (9) so as to be driven by the arc-shaped support plate (9) to move along the semicircular gear ring (8) and wind the fixing wire around the connecting pipe.
3. The temporary hanging point structure according to claim 2, characterized in that: The temporary hanging point structure comprises a positioning groove (15) arranged on the side of one of two semicircular gear rings (8) in contact with each other; a positioning block (16) arranged on the side of the other of the two semicircular gear rings (8) in contact with each other, and the positioning block (16) can be inserted into the positioning groove (15).
4. The temporary hanging point structure according to claim 2, characterized in that: The fixing line is a flat strip.
5. The temporary hanging point structure according to claim 4, characterized in that: The wire-releasing unit (14) comprises: A support platform (140) is arranged on the arc-shaped support plate (9); A pay-off roller (141) is arranged on the arc-shaped support plate (9), and the top and bottom of the pay-off roller (141) are rotatably connected to the support platform (140) and the arc-shaped support plate (9) respectively, and a fixed line is wound around the pay-off roller (141).
6. The temporary hanging point structure according to claim 5, characterized in that: The wire-releasing portion (14) comprises two guide columns (142), the top of each guide column (142) being connected to the support platform (140), the bottom of each guide column (142) being connected to the arc-shaped support plate (9), and the two guide columns (142) being arranged on one side of the wire-releasing roller (141) close to the through cavity (4), and the fixed line passing between the two guide columns (142).
7. The temporary hanging point structure according to claim 6, characterized in that: The wire-releasing part (14) comprises a telescopic motor (143) which is arranged on the support platform (140); one of the two guide columns (142) is fixedly arranged, and the top of the other guide column (142) is connected to the telescopic shaft of the telescopic motor (143).
8. The temporary hanging point structure according to claim 5, characterized in that: An opening (17) is provided on a side of the support platform (140) away from the through cavity (4), and a top plate (18) is provided on the top of the pay-off roller (141), and the top plate (18) can be inserted into the opening (17).
9. The temporary hanging point structure according to claim 2, characterized in that: The semicircular gear ring (8) is provided with a T-shaped through groove (19), and the arc-shaped support plate (9) is provided with a T-shaped clamping block (20) on one side close to the semicircular gear ring (8), and the T-shaped clamping block (20) can be inserted into the T-shaped through groove (19) and can slide along the T-shaped through groove (19).