Underwater rock drilling effect sensing method

By obtaining and analyzing the acceleration change value of the underwater module, it is judged whether rock drilling is completed at the rock drilling position, which solves the problem of inaccurate rock drilling in the existing technology, achieves precise rock drilling, improves rock drilling efficiency and reduces the cost of rework. cost.

CN118757142APending Publication Date: 2024-10-11CCCC FOURTH HARBOR ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410808426.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-21
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

During the underwater rock drilling process, the existing heavy hammer impact method is difficult to accurately determine whether the rock drilling has been completed at the rock drilling location, which often results in excessive or insufficient rock drilling, requiring secondary rework, affecting construction efficiency and cost.

Method used

By obtaining rock drilling information, including the drop height and acceleration change parameters of the underwater module, use the acceleration change value to determine whether the rock drilling operation is completed, control the free fall and lifting of the underwater module to achieve accurate rock drilling, update the rock layer strength and rock drilling Corresponding information of times to optimize the rock drilling process.

Benefits of technology

Effectively identify underwater rock drilling effects, reduce energy consumption and time caused by rework, improve rock drilling efficiency, and ensure the accuracy and efficiency of rock drilling operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118757142A_ABST
    Figure CN118757142A_ABST
Patent Text Reader

Abstract

The invention provides an underwater rock drilling effect sensing method, and relates to the technical field of underwater rock drilling. The underwater rock drilling effect sensing method comprises the steps that rock drilling information of a current rock drilling position is obtained, rock drilling of an underwater module is controlled based on the rock drilling information, the rock drilling information comprises the falling height of the underwater module and acceleration change parameters, and the acceleration change parameters correspond to dredging conditions; acquiring an acceleration change value of the underwater module; if it is determined that the acceleration change value meets a first preset condition, it is determined that the rock drilling operation of the current rock drilling position is finished, and the first preset condition includes that the acceleration change value is smaller than or equal to the acceleration change parameter. According to the embodiment of the invention, the underwater rock drilling effect can be effectively identified, energy consumption and rock drilling time and cost caused by excessive digging or secondary reworking of rock drilling equipment are reduced, and the rock drilling efficiency of the rock drilling equipment is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of underwater rock drilling, and specifically, to a method for sensing underwater rock drilling effects. Background Art

[0002] When the heavy hammer impact method is used to break underwater rocks for dredging, it is necessary to divide the rock drilling area into a plurality of rock drilling positions, and perform rock drilling operations on these rock drilling positions one by one.

[0003] However, the water depth will affect the direct observation of the rock drilling effect, and underwater rock drilling will also stir up dust and sand in the seabed, affecting visual observation including that of cameras. Therefore, after the initial excavation of the entire construction area, the seabed conditions in the area will no longer be directly observable, and construction workers on board or on land are unclear whether the rock drilling effect meets the requirements of excavation and dredging. Faced with unknown rock drilling results, people often rely on personal experience to judge whether the rock drilling position has been completed. It is often the case that a certain rock drilling position is over-drilled or under-drilled and needs to be reworked a second time. Summary of the invention

[0004] The embodiment of the present application provides a method for sensing the effect of underwater rock drilling, which can solve the problem that the existing heavy hammer impact method cannot accurately judge whether the rock drilling position is completed, and there is over-drilling or under-drilling, which requires secondary rework. In order to achieve this purpose, the embodiment of the present application provides the following solutions.

[0005] According to one aspect of an embodiment of the present application, a method for sensing underwater rock drilling effects is provided, which is used for rock drilling equipment, wherein the rock drilling equipment includes an underwater module for rock drilling, and the method for sensing underwater rock drilling effects includes:

[0006] Acquire rock drilling information of a current rock drilling position, and control the underwater module to freely fall to drill rocks based on the rock drilling information, wherein the rock drilling information includes a falling height of the underwater module and an acceleration change parameter;

[0007] Obtaining an acceleration change value of the underwater module;

[0008] If it is determined that the acceleration change value satisfies a first preset condition, it is determined that the rock drilling operation at the current rock drilling position is ended, and the first preset condition includes that the acceleration change value is less than or equal to the acceleration change parameter.

[0009] In a possible implementation, the obtaining rock drilling information of the current rock drilling position includes:

[0010] Obtaining corresponding information between rock formation strength and the drop height and acceleration change parameters of the underwater module according to historical data, wherein the historical data includes rock drilling operation information for rock formations of different strengths, and the rock drilling operation information includes the drop height and acceleration change parameters of the underwater module;

[0011] The drop height and acceleration change parameters of the underwater module corresponding to the current rock drilling position are determined according to the rock formation strength at the current rock drilling position.

[0012] In a possible implementation, the underwater module includes a jackhammer, and an effect sensing sensor is provided at the tail of the jackhammer;

[0013] The obtaining of the acceleration change value of the underwater module includes:

[0014] The acceleration information of the effect sensing sensor is acquired, and the acceleration change value when the rock hammer contacts the underwater rock is determined according to the acceleration information.

[0015] In a possible implementation, controlling the underwater module to freely fall to drill rocks based on the rock drilling information includes:

[0016] Determine the lifting height of the underwater module according to the falling height of the underwater module and the current height of the underwater module;

[0017] The underwater module is lifted based on the lifting height, and if it is determined that the lifting of the underwater module is completed, the underwater module is controlled to move in free fall.

[0018] In a possible implementation, the rock drilling information further includes the number of rock drilling times, and after determining that the acceleration change value satisfies the first preset condition, the method includes:

[0019] The rock drilling information corresponding to the current rock drilling position is obtained, the rock drilling information is uploaded, and the corresponding information of the rock formation strength and the number of rock drilling times, the drop height of the underwater module, and the acceleration change parameter is updated based on the rock drilling information.

[0020] In a possible implementation, updating the corresponding information of the rock formation strength and the number of rock drilling times, the drop height of the underwater module, and the acceleration change parameter based on the rock drilling information includes:

[0021] Update the rock formation strength and drilling number curve based on the rock drilling times corresponding to the current rock drilling position, the drop height of the underwater module, and the rock formation strength at the current rock drilling position;

[0022] The corresponding information of the rock formation strength, the rock drilling times, and the drop height of the underwater module is updated according to the updated rock formation strength and drilling times curve.

[0023] In a possible implementation, the method further includes:

[0024] If it is determined that the acceleration change value does not meet the first preset condition, the underwater module is lifted, and the underwater module is controlled to fall based on the rock drilling information to continue rock drilling.

[0025] In one possible implementation, the drilling is continued, including:

[0026] When the number of rock drilling is consistent with the number of rock drilling in the rock drilling information, obtaining a current acceleration change value of the underwater module;

[0027] If it is determined that the current acceleration change value does not satisfy the first preset condition, the rock drilling operation continues to be performed at the current rock drilling position until it is determined that the acceleration change value corresponding to the underwater module satisfies the first preset condition.

[0028] The beneficial effects of the technical solution provided by the embodiment of the present application are:

[0029] The underwater rock drilling effect perception method provided in the present application obtains the rock drilling information of the current rock drilling position, and controls the rock drilling of the underwater module based on the rock drilling information, wherein the rock drilling information includes the falling height of the underwater module and the acceleration change parameter corresponding to the dredging condition; obtains the acceleration change value of the underwater module; if it is determined that the acceleration change value satisfies the first preset condition, it is determined that the rock drilling operation at the current rock drilling position is completed, and the first preset condition includes that the acceleration change value is less than or equal to the acceleration change parameter. Therefore, the embodiment of the present application detects whether the rock drilling operation is completed at the current rock drilling position through the acceleration change value of the underwater module, so as to effectively identify the underwater rock drilling effect and accurately judge whether the rock drilling is completed, thereby reducing the energy consumption as well as the rock drilling time and cost caused by multiple drilling or secondary rework of the rock drilling equipment, and improving the rock drilling efficiency of the rock drilling equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the following is a brief introduction to the drawings required for use in describing the embodiments of the present application.

[0031] Figure 1 A flow chart of a method for sensing underwater rock drilling effects provided in an embodiment of the present application;

[0032] Figure 2 A structural diagram of a portion of the structure of a rock drilling device provided in an embodiment of the present application;

[0033] Figure 3 A top view of a portion of the structure of a rock drilling device provided in an embodiment of the present application;

[0034] Figure 4 A top view of a first track in the walking track provided in an embodiment of the present application;

[0035] Figure 5 A structural diagram of the amplitude variation mechanism provided in an embodiment of the present application;

[0036] Figure 6 A structural diagram of the walking mechanism provided in an embodiment of the present application;

[0037] Figure 7 This is a structural diagram of the walking drive unit provided in an embodiment of the present application.

[0038] Explanation of reference numerals: 101, hanging bracket; 1011, first bracket; 1012, luffing bracket; 102, traction rope; 103, luffing mechanism; 1031, push-pull unit; 1032, push-pull seat; 1033, luffing track; 104, walking chassis; 105, winch; 106, walking drive unit; 1061, driver; 1062, driving wheel; 1063, walking wheel; 107, walking track; 1071, removal pin; 21, rock hammer. DETAILED DESCRIPTION

[0039] The embodiments of the present application are described below in conjunction with the drawings in the present application. It should be understood that the implementation methods described below in conjunction with the drawings are exemplary descriptions for explaining the technical solutions of the embodiments of the present application and do not constitute a limitation on the technical solutions of the embodiments of the present application.

[0040] It will be understood by those skilled in the art that, unless specifically stated, the singular forms "one", "said", and "the" used herein may also include plural forms. It should be further understood that the terms "including" and "comprising" used in the embodiments of the present application refer to that the corresponding features can be implemented as the presented features, information, data, steps, operations, elements and / or components, but do not exclude the implementation of other features, information, data, steps, operations, elements, components and / or combinations thereof supported by the present technical field. It should be understood that when we say that an element is "connected" or "coupled" to another element, the one element may be directly connected or coupled to the other element, or it may refer to that the one element and the other element establish a connection relationship through an intermediate element. In addition, the "connection" or "coupling" used herein may include wireless connection or wireless coupling. The term "and / or" used herein indicates at least one of the items defined by the term, for example, "A and / or B" indicates that it is implemented as "A", or is implemented as "A", or is implemented as "A and B".

[0041] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below with reference to the accompanying drawings.

[0042] The following describes several exemplary embodiments to illustrate the technical solutions of the embodiments of the present application and the technical effects produced by the technical solutions of the present application. It should be noted that the following embodiments can refer to, draw on or combine with each other, and the same terms, similar features and similar implementation steps in different embodiments will not be described repeatedly.

[0043] The underwater rock drilling effect perception method provided in the present application is intended to solve at least one technical problem existing in the prior art.

[0044] The present application provides a method for sensing underwater rock drilling effects. Figure 1-Figure 7 As shown, the underwater rock drilling effect perception method is used for a rock drilling device, and the rock drilling device includes an underwater module for rock drilling.

[0045] Optionally, the underwater module may be a rock hammer 21. Specifically, when the rock hammer 21 strikes the rock, the head is downward and the tail is upward. The head is conical and the tail is provided with an effect sensing sensor. The effect sensing sensor detects the working parameters (such as acceleration information) of the rock hammer 21 and transmits it to the upper computer of the rock drilling equipment or the lower computer in the rock drilling equipment, and the lower computer transmits it to the upper computer. The upper computer or the lower computer can control the operation of the rock drilling equipment according to the working parameters transmitted by the sensor.

[0046] Optionally, the underwater rock drilling effect perception method includes:

[0047] S101: Obtain rock drilling information of a current rock drilling position, and control the underwater module to freely fall to drill rocks based on the rock drilling information.

[0048] Optionally, the rock drilling information includes the drop height of the underwater module and the acceleration change parameter, and the acceleration change parameter corresponds to the dredging conditions (which may include rock stratum crushing conditions such as rock stratum crushing degree and crushing depth), wherein different dredging conditions may correspond to different acceleration change parameters. Obtaining the rock drilling information of the current rock drilling position includes: obtaining the corresponding information of the rock stratum strength and the drop height and acceleration change parameter of the underwater module according to the historical data, the historical data includes the rock drilling operation information of the rock strata with different strengths, and the rock drilling operation information includes the drop height of the underwater module and the acceleration change parameter; determining the drop height and acceleration change parameter of the underwater module corresponding to the current rock drilling position according to the rock stratum strength of the current rock drilling position.

[0049] Optionally, the rock formation strength at the current drilling position can be determined by exploration, or the acceleration change information when the underwater module contacts the rock when the rock of different strengths or thicknesses is first struck can be pre-stored. When drilling, the underwater module is placed in water by free fall, and the acceleration change value when the underwater module touches the rock formation is obtained, and the rock formation strength at the current drilling position is determined according to the acceleration change value and the pre-stored acceleration change information.

[0050] Optionally, the rock drilling information may further include the number of rock drillings, which corresponds to the strength of the rock formation.

[0051] Optionally, the corresponding information between the rock formation strength and the underwater module drop height, acceleration change parameter, and rock drilling times can be determined based on the historical data of the rock drilling operation, the historical data includes multiple sets of rock formation strength and corresponding rock drilling operation information, the rock drilling operation information includes the underwater module drop height, acceleration change parameter, and rock drilling times, and the underwater module drop height, acceleration change parameter, and rock drilling times corresponding to the current rock drilling position are obtained based on the matching result of the historical data and the rock formation strength at the current rock drilling position. In order to improve the accuracy of the historical data, the historical data can be continuously collected until the rock drilling operation information corresponding to each rock formation strength in the historical data is a stable value (such as the underwater module drop height and acceleration change parameter corresponding to the same rock formation strength approach a stable value), and the stable value is used as the subsequent rock drilling information under the corresponding rock formation strength.

[0052] Optionally, self-learning (such as model training) can be performed based on historical data. When self-learning is model training, historical data is used as training samples, and neural network training is performed based on the training samples to obtain a rock drilling information prediction model. When drilling at the current rock drilling position, the rock formation strength information at the current rock drilling position is obtained, and the rock formation strength information is input into the rock drilling information prediction model. Based on the information output by the model, the drop height of the underwater module, the number of rock drilling times, and the acceleration change parameters corresponding to the current rock drilling position are determined.

[0053] In one embodiment, the number of rock drilling times corresponding to each rock drilling position may be obtained before the rock drilling equipment starts drilling, or may not be obtained before drilling starts, but the number of rock drilling times of the rock drilling positions may be obtained one by one. Specifically, the underwater module is controlled to initially drill the current rock drilling position, the rock formation strength of the current rock drilling position is determined according to the acceleration change information of the underwater module, and then the number of rock drilling times of the current rock drilling position is obtained according to the rock formation strength.

[0054] Optionally, the historical data may also include the number of drilling times corresponding to different drilling depths in each rock formation strength. When performing the drilling operation on the current drilling position, the rock formation strength and the required drilling depth of the current drilling position are obtained, and the number of drilling times at the current drilling position is obtained based on the rock formation strength of the current drilling position, the required drilling depth and the historical data.

[0055] Optionally, the underwater module is controlled to free fall to drill rocks based on the rock drilling information, including: determining the lifting height of the underwater module according to the falling height of the underwater module and the current height of the underwater module; lifting the underwater module based on the lifting height, and if it is determined that the lifting of the underwater module is completed, controlling the underwater module to free fall.

[0056] Optionally, the falling height of the underwater module may be the height of the falling position of the underwater module relative to the underwater rock, and the current height of the underwater module may be acquired by a positioning device (such as an RTK locator) in the rock drilling equipment.

[0057] S102: Obtain the acceleration change value of the underwater module.

[0058] Optionally, the acceleration change value of the underwater module is obtained when the underwater module is drilling rock. An effect sensing sensor is provided at the tail of the rock hammer 21. The acceleration change value of the underwater module is obtained, including: obtaining acceleration information of the effect sensing sensor, and determining the acceleration change value when the rock hammer 21 contacts the underwater rock according to the acceleration information.

[0059] Optionally, the acceleration change value is the acceleration change value of the rock hammer 21 from touching the rock formation to the speed becoming zero. When obtaining the acceleration change value, it is possible to detect whether the rock hammer 21 touches the rock formation based on the acceleration information after the rock hammer 21 is lowered (such as the acceleration of the rock hammer 21 is less than a predetermined threshold or becomes negative after contacting the rock).

[0060] Optionally, the acceleration change value of the underwater module can be obtained each time the underwater module drills the rock. Considering that the drilling times corresponding to rock layers of the same strength are often similar or the same, the number of times the acceleration change value is obtained can also be reduced. Specifically, obtaining the acceleration change value of the underwater module includes: obtaining the drilling times at the current drilling position; if it is determined that the drilling times are consistent with the drilling times in the drilling information, obtaining the current acceleration change value of the underwater module.

[0061] S103: If it is determined that the acceleration change value satisfies the first preset condition, it is determined that the rock drilling operation at the current rock drilling position is finished.

[0062] Optionally, the first preset condition includes that the acceleration change value is less than or equal to the acceleration change parameter. The historical data also includes the acceleration change parameter corresponding to the same rock formation strength; the acceleration change parameter matching the current rock drilling position is obtained from the historical data according to the rock formation strength of the current rock drilling position. The acceleration change parameter setting instruction input by the user can also be obtained, and the acceleration change parameter corresponding to the current rock drilling position is determined according to the instruction.

[0063] Optionally, the acceleration change value when the underwater module contacts the underwater rock when the current rock drilling position meets the dredging conditions can be obtained according to historical data, and the acceleration change value can be determined as the acceleration change parameter corresponding to the current rock drilling position.

[0064] Optionally, if it is determined that the current acceleration change value of the underwater module is greater than the acceleration change parameter, it is determined that the rock drilling effect does not meet expectations, that is, the rock drilling operation at the current rock drilling position is not completed, and the rock drilling at the current rock drilling position continues. If it is determined that the current acceleration change value of the underwater module is less than or equal to the acceleration change parameter, it is determined that the first preset condition is met, the rock drilling effect reaches the expected effect, the rock drilling operation at the current rock drilling position is stopped, and when it is determined that there is a next rock drilling position, the underwater module is moved to the next rock drilling position.

[0065] Optionally, in order to provide reference data for other rock drilling operations and improve the rock drilling effect, after determining that the acceleration change value meets the first preset condition, it includes: obtaining the rock drilling information corresponding to the current rock drilling position, uploading the rock drilling information, and updating the corresponding information of the rock formation strength and the number of rock drilling times, the falling height of the underwater module, and the acceleration change parameters based on the rock drilling information.

[0066] In one embodiment, the drilling times are transmitted to the upper computer of the drilling equipment, and the upper computer provides assistance for setting the drilling information corresponding to the next drilling operation through the repeatedly collected drilling times and rock formation strength data.

[0067] Optionally, updating the corresponding information of the rock formation strength and the rock drilling times based on the actual rock drilling times includes: updating the rock formation strength and drilling times curve based on the actual rock drilling times, the drop height of the underwater module and the rock formation strength at the current rock drilling position; and determining the corresponding information of the rock formation strength and the rock drilling times according to the updated rock formation strength and drilling times curve. The relationship between the rock formation strength and the drilling times under the same acceleration change parameter can be reflected according to the rock formation strength and drilling times curve, and the rock drilling times corresponding to each rock drilling position can be determined based on the relationship.

[0068] Optionally, the rock drilling equipment includes a hanging bracket 101, a traction rope 102 and a luffing mechanism 103, one end of the traction rope 102 is connected to the underwater module and passes through the top of the hanging bracket 101, and the traction rope 102 transmits power to the underwater module through the top to drive the underwater module to rise and fall; the hanging bracket 101 includes a first bracket 1011 and a luffing bracket 1012 that are rotatably connected at the top, and the luffing mechanism 103 is connected to the bottom of the luffing bracket 1012; moving the underwater module to the next rock drilling position includes: determining the luffing information of the luffing mechanism 103 according to the next rock drilling position; and controlling the luffing mechanism 103 to adjust the bottom position based on the luffing information so that the top position of the hanging bracket 101 corresponds to the next rock drilling position. The luffing information includes the luffing mode of the luffing mechanism 103 (including the distance that the bottom of the luffing bracket 1012 needs to move).

[0069] Optionally, since the underwater module drills the rock by vertically descending, the lifting position of the underwater module is the rock drilling position, and the lifting position corresponds to the position of the top of the hanging bracket 101. Therefore, the position of the top of the hanging bracket 101 can be calculated according to the rock drilling position.

[0070] In one embodiment, the position change information of the top of the hanging bracket 101 corresponding to different luffing modes of the luffing mechanism 103 can be stored, the position information of the next rock drilling position can be obtained, and the position change information of the hanging bracket 101 can be determined according to the position information and the position information of the current rock drilling position. If there is an luffing mode corresponding to the position change information, it is determined that the underwater module can be moved by the luffing mechanism 103, and the luffing mode is obtained based on the position change information, so as to control the action of the luffing mechanism 103 according to the luffing mode.

[0071] Optionally, the luffing mechanism 103 includes a push-pull unit 1031, and a push-pull end of the push-pull unit 1031 is connected to the bottom of the support.

[0072] Optionally, the push-pull unit 1031 may be a push-pull cylinder or a screw stepping motor, and the push-pull end of the push-pull unit 1031 is extended and retracted to drive the support column of the variable amplitude bracket 1012 to move, thereby changing the inclination angle of the support column.

[0073] Optionally, the luffing mechanism 103 further includes a push-pull base and a push-pull base 1032, the push-pull base 1032 is movably fixed on the push-pull base, the top of the push-pull base 1032 is rotatably connected to the corresponding support, and one side of the push-pull base 1032 is connected to the push-pull end of the push-pull unit 1031. The push-pull unit 1031 is placed flat on the push-pull base, and the push-pull base 1032 is driven by the push-pull unit 1031 to move along the push-pull base.

[0074] Optionally, the push-pull base includes an amplitude-changing track 1033, and the push-pull seat 1032 is movably fixed to the amplitude-changing track 1033. A first pin hole is provided on the side of the amplitude-changing track 1033, and a second pin hole corresponding to the first pin hole is provided on the side of the push-pull seat 1032. The first pin hole and the second pin hole are used to insert a pin shaft to fix the push-pull seat 1032.

[0075] In one embodiment, the cross section of the amplitude changing track 1033 is rectangular, and the push-pull seat 1032 is sleeved on the amplitude changing track 1033 to prevent the push-pull seat 1032 from being separated from the amplitude changing track 1033 .

[0076] Optionally, there are two boom rails 1033 , which are arranged in parallel, and a push-pull seat 1032 is correspondingly arranged on each boom rail 1033 ; the boom bracket 1012 includes two pillars, the tops of the two pillars are connected, and the push-pull seats 1032 connected to the bottoms of the two pillars are different, and the number of push-pull units 1031 is also two, and a push-pull unit 1031 is provided on each boom rail 1033 .

[0077] Optionally, the position of the first pin hole is within the travel of the push-pull end, the number of the second pin holes can be one or more, and the first pin holes on the variable amplitude track 1033 can be multiple groups, and the number of the first pin holes in each group is consistent with the number of the second pin holes. In addition, the distances between different groups of first pin holes can be determined according to the position adjustment information of the underwater module during the rock drilling process.

[0078] Optionally, in order to increase the amplitude changing speed of the amplitude changing mechanism 103, the amplitude changing mechanism 103 also includes a pin shaft plug-in and pull-out member. When performing the amplitude changing operation, the pin shaft plug-in and pull-out member pulls out the pin shaft inserted into the second pin hole, and after the push-pull end moves to a predetermined position, the pin shaft is inserted into the second pin hole and the first pin hole corresponding to the second pin hole, and the push-pull seat 1032 is fixed to complete the amplitude changing operation.

[0079] Optionally, a third pin hole is provided on the side of the push-pull unit 1031 away from the push-pull end; a plurality of fourth pin holes corresponding to the third pin hole are provided on the push-pull base, and the fourth pin holes are arranged at intervals, and the third pin hole is opposite to the fourth pin hole corresponding to the current rock drilling position of the push-pull unit 1031 to insert a pin shaft to fix the push-pull unit 1031.

[0080] In one embodiment, the fourth pin hole is set at the top of the variable amplitude track 1033, located at the end of the variable amplitude track 1033 away from the push-pull seat 1032. The fixed position of the push-pull unit 1031 is changed by adjusting the fourth pin hole through which the pin shaft is inserted, thereby changing the range of movement of the push-pull seat 1032.

[0081] Optionally, the above-water module further includes a walking mechanism and a walking track 107, the walking track 107 is laid along the direction of the ship, the walking mechanism is installed on the walking track 107, and the hanging bracket 101 is fixed to the side of the walking mechanism away from the walking track 107; switching to the next rock drilling position includes: if it is determined that the next rock drilling position satisfies the second preset condition, the second preset condition includes that the next rock drilling position matches the walking track of the walking mechanism (that is, the hanging bracket 101 can be moved to the lifting position corresponding to the next rock drilling position by moving the walking mechanism); then the hanging bracket 101 is moved to the position corresponding to the next rock drilling position by the walking mechanism, and the underwater module is raised and lowered at this position to realize the rock drilling work.

[0082] Optionally, the water module also includes a positioning device, which is installed on the walking mechanism and is used to collect positioning information of the walking mechanism. During the movement of the walking mechanism, the position information of the walking mechanism is collected in real time by the positioning device, and the movement of the walking mechanism is controlled based on the position information.

[0083] Optionally, the traveling mechanism includes a traveling chassis 104, and the hanging bracket 101 and the luffing mechanism 103 are fixed to the traveling chassis 104 on a side away from the traveling track 107. The movement of the traveling chassis 104 drives the movement of the hanging bracket 101 and the luffing mechanism 103.

[0084] Optionally, the travel track 107 includes a first track and a second track arranged in parallel, the first end of the travel chassis 104 is placed on the first track, and the second end of the travel chassis 104 is placed on the second track. The travel chassis 104 can be placed horizontally on the travel track 107, and the distance between the first track and the second track corresponds to the length of the travel chassis 104.

[0085] Optionally, the walking mechanism further includes a walking drive unit 106 , which is fixed to the bottom of the walking chassis 104 and contacts the walking track 107 to move along the walking track 107 . The walking chassis 104 is provided with a walking drive unit 106 at both ends corresponding to the walking track 107 .

[0086] In one embodiment, the number of the travel drive units 106 is 4, and the number of the travel drive units 106 corresponding to the first track and the second track is the same.

[0087] Optionally, the travel drive unit 106 includes a driver 1061 and a driving wheel 1062 , the driving wheel 1062 is installed on the top of the travel track 107 , the output end of the driver 1061 is connected to the driving wheel 1062 , and the movement of the travel mechanism on the travel track 107 is achieved by the rotation of the driving wheel 1062 .

[0088] In one embodiment, the driver 1061 may be a driving motor, and there may be multiple driving motors, which work synchronously to drive the walking mechanism to move stably.

[0089] Optionally, both ends of the traveling chassis 104 move synchronously along the first track and the second track. The first track and the second track are arranged along the direction of the ship to ensure that the rock drilling equipment moves along the direction of the ship.

[0090] In one embodiment, the structures of the first track and the second track may be the same, and may be an “I” shaped structure.

[0091] Optionally, the driving wheel 1062 may be a sprocket, and a row of pins 1071 matching the sprocket is provided at the top of the walking track 107, and the row of pins 1071 includes first pins arranged at equal intervals, and the interval of the first pins matches the tooth pitch of the sprocket. The cooperation between the row of pins 1071 and the sprocket provides the travel driving unit 106 with the force required to move on the walking track 107.

[0092] Optionally, the row pin 1071 further includes a first fixing member, which is arranged in parallel on both sides of the first pin shaft, and both ends of the first pin shaft are connected to different first fixing members; the top height of the first fixing member is higher than the height of the first pin shaft.

[0093] In one embodiment, a through hole corresponding to the first pin is provided on the side of the first fixing member, and both ends of the first pin are fixed in the through hole. In addition, in order to improve the stability of the first fixing member, a slanted plate is provided on the side of the first fixing member away from the first pin, and the slanted plate is vertically fixed to the side of the first fixing member away from the first pin and the top of the walking track 107. There are multiple slanted plates, and they are arranged at intervals on the side of the first fixing member.

[0094] Optionally, limit switches are provided at both ends of the pin 1071, and the limit switches are used to generate limit signals after detecting the travel drive unit 106. The setting position of the limit switch corresponds to the travel of the travel mechanism on the travel track 107.

[0095] Optionally, a positioning device is disposed on the traveling chassis 104, and the positioning device is utilized to realize real-time detection of the current rock drilling position of the rock drilling equipment.

[0096] Optionally, the detection result of the positioning device can be transmitted to the control module corresponding to the travel drive unit 106, and the control module controls the moving direction, moving speed and moving trajectory of the rock drilling equipment based on the detection result. Among them, the control module can be a host computer connected to the underwater rock drilling effect perception method or a control device set on the travel chassis 104. In addition, the control module can also receive a limit signal generated by a limit switch, and control the driver 1061 of the travel drive unit 106 to stop working or change the direction of movement based on the limit signal.

[0097] Optionally, the number of the positioning devices may be two or three. When the number of the positioning devices is three, one of the positioning devices is arranged on the ship, and the other two are arranged on the traveling chassis 104 .

[0098] In one embodiment, the positioning device may be a RTK (Real-time kinematic) device, and the number of the positioning device is two, wherein the connection line of the two positioning devices may be perpendicular to the travel track 107 .

[0099] Optionally, in order to prevent the walking chassis 104 from tilting up or detaching from the walking track 107, the two sides of the walking track 107 are recessed to form fixed grooves, and the length of the fixed grooves corresponds to the stroke length of the walking mechanism; the walking drive unit 106 includes at least one walking wheel 1063, and at least a portion of the walking wheel 1063 is located in the fixed groove to contact the walking track 107 when the walking chassis 104 is offset or tilted.

[0100] In one embodiment, the circular surface of the running wheel 1063 is opposite to the side of the fixing groove, and the whole of the running wheel 1063 is located in the fixing groove. Wherein, grooves may be provided on both sides of the second track and the first track, and a running wheel 1063 is provided in each groove.

[0101] Optionally, in order to transmit the power of the driver 1061, the walking drive unit 106 also includes a reducer, which is respectively connected to the output end of the driver 1061 and the driving wheel 1062 to transmit the power of the driver 1061 to the driving wheel 1062. Through the action of the reducer, the rotational speed of the driving wheel 1062 is inconsistent with the rotational speed of the driver 1061, so that the rotational speed of the driving wheel 1062 corresponds to the movement speed of the walking mechanism.

[0102] Optionally, the travel drive unit 106 further includes a wheel frame, a driving wheel 1062 is fixed inside the wheel frame, a balancing frame 1064 is provided on the top of the wheel frame, and the balancing frame 1064 is connected to the travel chassis 104 at a side away from the driving wheel 1062. The driver 1061 is provided at one side of the wheel frame, and the reducer is provided inside the wheel frame and is connected to the output ends of the driving wheel 1062 and the driver 1061, respectively.

[0103] In one embodiment, there are two walking wheels 1063, and a connecting shaft and a card plate are provided at the bottom of the wheel frame. The card plate is arranged on the side of the walking wheel 1063 away from the fixed groove, and the rotating shaft of the walking wheel 1063 is fixed on the card plate. The connecting shaft is arranged at the top of the walking track 107, and the two ends are connected to different card plates.

[0104] Optionally, two travel drive units 106 are provided at each end of the walking chassis 104, and the drivers 1061 of the travel drive units 106 are arranged on both sides of the ends of the walking chassis 104. In addition, in order to realize the synchronous control of the driver 1061, the walking drive unit 106 also includes a signal acquisition device, which is connected to the output end of the driver 1061 to collect the working parameters of the driver 1061, wherein the signal device collects the working parameters of the driver 1061 and transmits the working parameters to the control module corresponding to the driver 1061. The control module controls the driver 1061 to work synchronously according to the working parameters to realize the synchronous movement of the two ends of the walking chassis 104.

[0105] In one embodiment, the driver 1061 may be a driving motor, and the signal acquisition device may include an encoder. The encoder is disposed at the output end of the driver 1061 to collect the rotation speed, operating frequency, and other data that can be used to detect whether the driver 1061 is working synchronously.

[0106] Optionally, the above-water module further includes a retractable drive unit for providing the power required for lifting the underwater module. The retractable drive unit is fixed to the side of the variable amplitude bracket 1012 away from the first bracket 1011, and the retractable drive unit is connected to the traction rope 102 to provide the power for traction and lifting the underwater module. The arrangement direction of the hanging bracket 101 and the retractable drive unit is perpendicular to the direction of the ship. One end of the hanging bracket 101 is fixed to the walking chassis 104, and the other end extends in the direction away from the ship; one end of the traction rope 102 is connected to the retractable drive unit, and the other end extends along the top of the hanging bracket 101 toward the underwater module to connect with the underwater module. The retractable drive unit lifts or puts into the underwater module through the traction rope 102.

[0107] Optionally, the retracting and extending driving unit includes a winch 105, which is connected to the traction rope 102, and the winch 105 is used to provide power for lifting and lowering the underwater module.

[0108] Optionally, the hanging bracket 101 further includes a first bracket 1011, which is rotatably fixed to the end of the traveling chassis 104 close to the ship's side, and the end of the first bracket 1011 away from the traveling chassis 104 is inclined away from the ship's side; the top of the luffing bracket 1012 is connected to the end of the first bracket 1011 away from the traveling chassis 104, and the bottom of the luffing bracket 1012 is fixed to the luffing mechanism 103. Among them, the first end of the first bracket 1011 is arranged on the side of the traveling chassis 104 close to the ship's side, and the second end extends in a direction away from the retracting and releasing driving unit, and the second end is provided with a pulley matching the traction rope 102. The traction rope 102 is placed in the pulley, and its extension direction is changed by the pulley.

[0109] Optionally, a pulley may also be provided at the first end of the first bracket 1011, and the traction rope 102 first passes through the pulley provided at the first end, and then passes through the pulley provided at the second end.

[0110] In one embodiment, the first bracket 1011 is an A-shaped frame, a first end of the A-shaped frame is fixed to two sides of the same end of the traveling chassis 104 , and a second end of the A-shaped frame extends to a side away from the traveling chassis 104 .

[0111] Optionally, the underwater rock drilling effect perception method of the present application further includes: if it is determined that the acceleration change value does not meet the first preset condition, lifting the underwater module, and controlling the underwater module to fall based on the rock drilling information to continue rock drilling.

[0112] Optionally, continuing rock drilling includes: when the number of rock drilling is consistent with the number of rock drilling in the rock drilling information, obtaining the current acceleration change value of the underwater module; if it is determined that the current acceleration change value does not meet the first preset condition, continuing to perform the rock drilling operation at the current rock drilling position until it is determined that the acceleration change value corresponding to the underwater module meets the first preset condition, and after completing the rock drilling, uploading the actual rock drilling information of the current rock drilling position to the host computer to update the historical data.

[0113] The method for sensing underwater rock drilling effects will be further described below through a specific embodiment.

[0114] In one embodiment, the underwater module is a rock hammer 21, and an effect sensing sensor is provided at the tail of the rock hammer 21, and the acceleration data of the rock hammer 21 is collected through the effect sensing sensor. Based on the collected acceleration data, the strength of the rock formation is learned through a preset algorithm (such as a neural network algorithm) and historical data (the change in acceleration will be different for different rock formation strengths. The harder the rock formation, the greater the change in acceleration. The softer the rock formation or the rock formation has been cracked, the smaller the change in acceleration). According to the learning result, the acceleration change parameter a of the current rock drilling position is adaptively determined (the reference parameter a is a reference value reflecting the rock formation fragmentation effect given by the upper computer corresponding to the rock drilling equipment. The reference table indicates that the rock formation has been fragmented). If the acceleration change value of the rock hammer 21 when it contacts the underwater rock is greater than a, then rock drilling still needs to continue; if the acceleration change When the value is ≤a, record the number of rock drilling x, and send x back to the host computer for processing, then it is determined that the rock drilling has met the expected effect (through multiple collections of rock drilling times and corresponding rock strengths, it can be known that the number of rock drilling times required when drilling such a strong rock layer, and then the acceleration change data obtained after the initial drilling can be used to judge the rock layer strength, and then the number of rock drilling times recorded in the past for the rock layer of this strength can be automatically set. If the measured acceleration change value under the set number of times does not reach the acceleration change parameter a, then repeat the rock drilling until the acceleration change parameter a is met, and record the number of rock drilling at this time), then you can move to the next rock drilling position for rock drilling operations. The rock drilling effect perception measurement can well identify the effect of underwater rock drilling operations, and the computer draws a curve of rock layer strength and drilling times (intuitively reflects the relationship between strength and drilling times under the same parameter a. It is the basis for the computer to set the number of hits), and promptly move to the next position to continue rock drilling operations to improve work efficiency.

[0115] The terms "first", "second", "third", "fourth", "1", "2", etc. (if any) in the specification and claims of this application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the numbers used in this way can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than that shown or described in the drawings.

[0116] It should be understood that, although each operation step is indicated by arrows in the flowchart of the embodiment of the present application, the implementation order of these steps is not limited to the order indicated by the arrows. Unless clearly stated herein, in some implementation scenarios of the embodiment of the present application, the implementation steps in each flowchart can be performed in other orders according to demand. In addition, some or all of the steps in each flowchart may include multiple sub-steps or multiple stages based on actual implementation scenarios. Some or all of these sub-steps or stages may be executed at the same time, and each sub-step or stage in these sub-steps or stages may also be executed at different times respectively. In different scenarios of execution time, the execution order of these sub-steps or stages may be flexibly configured according to demand, and the embodiment of the present application does not limit this.

[0117] The above is only an optional implementation method for some implementation scenarios of the present application. It should be pointed out that for ordinary technicians in this technical field, without departing from the technical concept of the solution of the present application, other similar implementation methods based on the technical ideas of the present application are also within the protection scope of the embodiments of the present application.

Claims

1. A method for sensing underwater rock drilling effects. It is characterized in that Used for rock drilling equipment, the rock drilling equipment includes an underwater module for rock drilling, and the underwater rock drilling effect perception method includes: Acquire rock drilling information of a current rock drilling position, and control the underwater module to freely fall to drill rocks based on the rock drilling information, wherein the rock drilling information includes a falling height of the underwater module and an acceleration change parameter, and the acceleration change parameter corresponds to a dredging condition; Obtaining an acceleration change value of the underwater module; If it is determined that the acceleration change value satisfies a first preset condition, it is determined that the rock drilling operation at the current rock drilling position is ended, and the first preset condition includes that the acceleration change value is less than or equal to the acceleration change parameter.

2. The underwater rock drilling effect sensing method according to claim 1, It is characterized in that The obtaining of rock drilling information of the current rock drilling position includes: Obtaining corresponding information between rock formation strength and the drop height and acceleration change parameters of the underwater module according to historical data, wherein the historical data includes rock drilling operation information for rock formations of different strengths, and the rock drilling operation information includes the drop height and acceleration change parameters of the underwater module; The drop height and acceleration change parameters of the underwater module corresponding to the current rock drilling position are determined according to the rock formation strength at the current rock drilling position.

3. The underwater rock drilling effect sensing method according to claim 1, It is characterized in that The underwater module includes a rock hammer, and an effect sensing sensor is provided at the tail of the rock hammer; The obtaining of the acceleration change value of the underwater module includes: The acceleration information of the effect sensing sensor is acquired, and the acceleration change value when the rock hammer contacts the underwater rock is determined according to the acceleration information.

4. The underwater rock drilling effect sensing method according to claim 2, It is characterized in that The step of controlling the underwater module to freely fall to drill rocks based on the rock drilling information comprises: Determine the lifting height of the underwater module according to the falling height of the underwater module and the current height of the underwater module; The underwater module is lifted based on the lifting height, and if it is determined that the lifting of the underwater module is completed, the underwater module is controlled to move in free fall.

5. The underwater rock drilling effect sensing method according to claim 2, It is characterized in that The rock drilling information also includes the number of rock drilling times. After determining that the acceleration change value meets the first preset condition, the method includes: The rock drilling information corresponding to the current rock drilling position is obtained, the rock drilling information is uploaded, and the corresponding information of the rock formation strength and the number of rock drilling times, the drop height of the underwater module, and the acceleration change parameter is updated based on the rock drilling information.

6. The underwater rock drilling effect sensing method according to claim 5, It is characterized in that The updating of the corresponding information of the rock formation strength and the number of rock drilling times, the drop height of the underwater module and the acceleration change parameter based on the rock drilling information includes: Update the rock formation strength and drilling number curve based on the rock drilling times corresponding to the current rock drilling position, the drop height of the underwater module, and the rock formation strength at the current rock drilling position; The corresponding information of the rock formation strength, the rock drilling times, and the drop height of the underwater module is updated according to the updated rock formation strength and drilling times curve.

7. The underwater rock drilling effect sensing method according to claim 5, It is characterized in that The method further comprises: If it is determined that the acceleration change value does not meet the first preset condition, the underwater module is lifted, and the underwater module is controlled to fall based on the rock drilling information to continue rock drilling.

8. The rock drilling position switching method according to claim 7, It is characterized in that Continue drilling, including: When the number of rock drilling is consistent with the number of rock drilling in the rock drilling information, obtaining a current acceleration change value of the underwater module; If it is determined that the current acceleration change value does not satisfy the first preset condition, the rock drilling operation continues to be performed at the current rock drilling position until it is determined that the acceleration change value corresponding to the underwater module satisfies the first preset condition.