Automatic control method and device for converter steelmaking
Through the generation and distribution of control parameters using hierarchical control strategies and preset time intervals, the problem of data delay and dispersion in traditional technology is solved, real-time and precise control of the converter steelmaking process is achieved, and steelmaking efficiency and product quality are improved. .
Patent Information
- Application Number
- CN202410960059.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-10-11
AI Technical Summary
Due to delays in data processing and transmission in traditional converter steelmaking technology, there is a delay in updating and issuing control parameters, making it difficult to achieve real-time and accurate control effects. Moreover, data acquisition at different monitoring locations is relatively scattered, lacking centralized integration and unified processing.
Adopting a hierarchical control strategy, the monitoring parameters of the target converter are obtained in real time through the sub-controller and uploaded to the first controller. The control parameters are generated and issued based on the preset time interval, and fine-tuned according to the current monitoring parameters to generate more accurate control parameters to achieve overall regulation and precise control of the converter steelmaking process.
It improves the flexibility and accuracy of control, adjusts control parameters in a timely manner according to changes in the steelmaking process, reduces errors caused by human intervention, improves steelmaking efficiency, reduces energy consumption, and brings economic and social benefits.
Smart Images

Figure CN118759980A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of converter steelmaking, and more specifically, relates to an automatic control method and device for converter steelmaking. Background Art
[0002] Converter steelmaking is one of the main steelmaking methods in current steel production. It uses molten iron as the main raw material, blows oxygen into the converter to oxidize impurity elements such as carbon, silicon, manganese, phosphorus, etc. in the molten iron, and removes impurities by adding slag-making materials, thereby obtaining molten steel of the required composition and quality. In the converter steelmaking process, controlling the flow rate, pressure, time of oxygen blowing, as well as the type and amount of slag-making materials is of great significance for improving molten steel quality, reducing costs and improving production efficiency.
[0003] However, in existing traditional technologies, delays in data processing and transmission may cause delays in updating and issuing control parameters, making it difficult for some adjustment measures taken based on the control parameters to achieve real-time and accurate control effects. Summary of the invention
[0004] The purpose of the present disclosure is to provide a converter steelmaking automatic control method and device to improve the accuracy of converter ironmaking automatic control.
[0005] In a first aspect of an embodiment of the present disclosure, a converter steelmaking automatic control method is provided, and the converter steelmaking automatic control method is applied to a sub-controller in a converter steelmaking control system. The converter steelmaking control system includes a first controller and a plurality of sub-controllers connected to the first controller, and each sub-controller controls a steelmaking parameter corresponding to a monitoring position. The monitoring position is a monitoring position corresponding to the converter. The converter steelmaking automatic control method includes: The current target monitoring parameters of the target converter are obtained, and the target monitoring parameters are uploaded to the first controller so that the first controller generates and issues the first control parameters based on the monitoring parameters uploaded by all sub-controllers at a preset time interval. The target monitoring parameters are the monitoring parameters of the monitoring position corresponding to the current sub-controller.
[0006] A first control parameter is received, and the first control parameter is adjusted based on a current monitoring parameter of the target converter to obtain a second control parameter.
[0007] The steelmaking parameters of the converter are automatically controlled based on the second control parameter.
[0008] In a second aspect of the embodiment of the present disclosure, a converter steelmaking automatic control device is provided, and the converter steelmaking automatic control method is applied to a sub-controller in a converter steelmaking control system. The converter steelmaking control system includes a first controller and a plurality of sub-controllers connected to the first controller, and each sub-controller controls a steelmaking parameter corresponding to a monitoring position. The monitoring position is a monitoring position corresponding to the converter. The converter steelmaking automatic control device includes: The first calculation module is used to obtain the current target monitoring parameters of the target converter, upload the target monitoring parameters to the first controller so that the first controller generates and issues the first control parameters based on the monitoring parameters uploaded by all sub-controllers at a preset time interval. The target monitoring parameters are the monitoring parameters of the monitoring position corresponding to the current sub-controller.
[0009] The second calculation module is used to receive the first control parameter and adjust the first control parameter based on the current monitoring parameter of the target converter to obtain the second control parameter.
[0010] The control module is used to automatically control the steelmaking parameters of the converter based on the second control parameter.
[0011] According to a third aspect of an embodiment of the present disclosure, an electronic device is provided, including a memory, a processor, and a computer program stored in the memory and running on the processor, wherein the processor implements the steps of the above-mentioned converter steelmaking automatic control method when executing the computer program.
[0012] According to a fourth aspect of the embodiments of the present disclosure, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the above-mentioned converter steelmaking automatic control method are implemented.
[0013] The beneficial effect of the converter steelmaking automatic control method and device provided by the embodiment of the present disclosure is that the monitoring parameters of the target converter are obtained in real time by the sub-controller and uploaded to the first controller, thereby ensuring the real-time and accuracy of the steelmaking process data. The first controller generates and issues the first control parameter at a preset time interval based on the data of all sub-controllers, thereby realizing the overall regulation of the converter steelmaking process, and solving the problem that the data obtained at different monitoring positions by the traditional control technology are relatively scattered, lacking centralized integration and unified processing. After receiving the first control parameter, the sub-controller can fine-tune the first control parameter in combination with the real-time monitoring parameters of the current converter to generate a more accurate second control parameter. This hierarchical control strategy effectively improves the flexibility and accuracy of the control, and solves the problem that the generation of control parameters in the traditional technology may not fully consider the unique situation of each specific monitoring position. At the same time, the traditional control technology may cause delays in the update and issuance of control parameters due to delays in data processing and transmission. The embodiment of the present disclosure presets a time interval to generate and issue control parameters, which can be adjusted more timely according to changes in the steelmaking process. In addition, automatic control of the converter steelmaking parameters based on the second control parameter can achieve precise control of the converter steelmaking process, thereby improving steelmaking efficiency, reducing energy consumption, and reducing errors caused by human intervention, bringing significant economic and social benefits to converter steelmaking production. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present disclosure. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0015] Figure 1 A schematic flow chart of a converter steelmaking automatic control method provided in one embodiment of the present disclosure; Figure 2 A structural block diagram of a converter steelmaking automatic control device provided in one embodiment of the present disclosure; Figure 3 A schematic block diagram of an electronic device provided by an embodiment of the present disclosure. DETAILED DESCRIPTION
[0016] In the following description, specific details such as specific system structures and technologies are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present disclosure. However, it should be clear to those skilled in the art that the present disclosure may be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to avoid obstructing the description of the present disclosure with unnecessary details.
[0017] In order to make the purpose, technical solutions and advantages of the present disclosure more clear, specific embodiments will be described below in conjunction with the accompanying drawings.
[0018] Please refer to Figure 1 , Figure 1 The present invention is a flow chart of a converter steelmaking automatic control method provided by an embodiment of the present invention, and the converter steelmaking automatic control method is applied to a sub-controller in a converter steelmaking control system. The converter steelmaking control system includes a first controller and a plurality of sub-controllers connected to the first controller, and each sub-controller controls a steelmaking parameter at a monitoring position. The monitoring position is a monitoring position corresponding to the converter. The converter steelmaking automatic control method may include S101 to S103.
[0019] S101: Obtain the current target monitoring parameters of the target converter, upload the target monitoring parameters to the first controller so that the first controller generates and issues the first control parameters based on the monitoring parameters uploaded by all sub-controllers at a preset time interval. The target monitoring parameters are the monitoring parameters of the monitoring position corresponding to the current sub-controller.
[0020] In this embodiment, the first controller can be used to coordinate and coordinate multiple sub-controllers, and multiple sub-controllers can be used to be responsible for parameter control at different monitoring positions. Each sub-controller can obtain the target monitoring parameters of the target converter at its corresponding monitoring position in real time. The target monitoring parameters may include at least one of temperature, chemical composition (such as carbon content, silicon content and phosphorus content), oxygen content, and slag composition. The sub-controller uploads the collected target monitoring parameters to the first controller. The first controller can analyze and calculate the target monitoring parameters uploaded by all sub-controllers according to a preset time interval. The process may include using a neural network model to learn the complex nonlinear relationship between the target monitoring parameters and the optimal control parameters through a large amount of historical data training, thereby generating effective control parameters based on the current target monitoring parameters. Alternatively, the PI controller algorithm is used to calculate the output control parameters by combining the proportional term and the integral term of each target detection parameter. Alternatively, a chemical reaction kinetic model is used to analyze and calculate control parameters such as oxygen blowing intensity and slag forming agent addition based on the rate and degree of various chemical reactions (such as decarburization, dephosphorization, desulfurization, etc.) in the converter.
[0021] For example, in the converter steelmaking production of a steel plant, four sub-controllers are provided to monitor the temperature parameters of the converter top, middle, feed port and gas outlet respectively. The sub-controller at the top of the converter obtains parameters such as the furnace top temperature and gas composition, the sub-controller in the middle collects information such as the chemical composition and temperature of the molten steel in the middle, the sub-controller at the feed port masters the feed speed and raw material composition, and the sub-controller at the gas outlet obtains the temperature and composition of the exhaust gas. These sub-controllers upload their respective monitoring parameters to the first controller. The first controller calculates and processes these parameters every 1 minute. If the comprehensive analysis finds that the temperature is low, a first control parameter for increasing energy supply is generated, such as the calculated oxygen flow adjustment value or fuel supply adjustment value, and it is sent to each sub-controller, thereby achieving effective control of the converter steelmaking process.
[0022] S102: receiving a first control parameter, and adjusting the first control parameter based on a current monitoring parameter of a target converter to obtain a second control parameter.
[0023] In this embodiment, when the sub-controller receives the first control parameter sent by the first controller, it can immediately obtain the latest monitoring parameters of the target converter. Then, these latest monitoring parameters are associated and compared with the first control parameters. Through a specific algorithm or formula, the sub-controller can analyze the difference between the current monitoring parameters and the state expected by the first control parameters. According to the nature of this difference, the first control parameter is corrected and optimized, adjusted according to a preset formula or algorithm, and the second control parameter is calculated and generated.
[0024] For example, in a converter steelmaking plant, the sub-controller is responsible for monitoring the temperature and carbon content in the converter. The first control parameter issued by the first controller is a control parameter calculated based on the detection data from a certain time ago, and the control parameter can indicate that increasing a certain amount of oxygen blowing time will reduce the carbon content. When the sub-controller receives the control parameter, it also obtains the monitoring parameters of the current converter, and finds that the temperature is close to the upper limit and the carbon content is decreasing faster than expected. In order to avoid the impact of excessive temperature on the quality of molten steel, the sub-controller will adjust the first control parameter, such as recalculating the increase in oxygen blowing time according to a preset correction formula. While controlling the carbon content to continue to decrease based on the second control parameter, the temperature can still be prevented from exceeding the safety range, thereby achieving more accurate and safe steelmaking control.
[0025] S103: Automatically control the steelmaking parameters of the converter based on the second control parameter.
[0026] In this embodiment, after obtaining the second control parameter, the sub-controller converts it into specific control instructions. These instructions directly act on the relevant equipment and operation links of the converter, thereby automatically adjusting the steelmaking parameters. For example, if the second control parameter specifies a specific oxygen flow rate, feeding speed or temperature setting value, the sub-controller will adjust the oxygen valve opening, the operating speed of the feeding device or the power of the heating device accordingly, so as to achieve precise control of the steelmaking process in the converter.
[0027] For example, suppose that in converter steelmaking, the second control parameter indicates that the temperature in the converter needs to be increased to 1600 degrees Celsius and the oxygen flow rate needs to be increased by 10%. After receiving these parameters, the sub-controller will automatically turn on the heating device and increase the power to the corresponding level to increase the temperature in the furnace. At the same time, it will adjust the valve of the oxygen blowing equipment to increase the oxygen flow rate by 10%. Through this automatic control, it is ensured that the reaction in the converter proceeds in the desired direction, improving the quality of molten steel and production efficiency.
[0028] It can be concluded from the above that the monitoring parameters of the target converter are obtained in real time by the sub-controller and uploaded to the first controller, ensuring the real-time and accuracy of the steelmaking process data. The first controller generates and issues the first control parameter at a preset time interval based on the data of all sub-controllers, realizing the overall regulation of the converter steelmaking process, and solving the problem that the data obtained by the traditional control technology at different monitoring positions are relatively scattered, lacking centralized integration and unified processing. After receiving the first control parameter, the sub-controller can fine-tune the first control parameter in combination with the real-time monitoring parameters of the current converter to generate a more accurate second control parameter. This hierarchical control strategy effectively improves the flexibility and accuracy of the control, and solves the problem that the generation of control parameters in traditional technology may not fully consider the unique situation of each specific monitoring position. At the same time, the traditional control technology may cause delays in the update and issuance of control parameters due to delays in data processing and transmission. The embodiment of the present disclosure presets a time interval to generate and issue control parameters, which can be adjusted more timely according to changes in the steelmaking process. In addition, automatic control of the converter steelmaking parameters based on the second control parameter can achieve precise control of the converter steelmaking process, thereby improving steelmaking efficiency, reducing energy consumption, and reducing errors caused by human intervention, bringing significant economic and social benefits to converter steelmaking production.
[0029] In one embodiment of the present disclosure, the first controller generates and issues the first control parameter based on the monitoring parameters uploaded by all sub-controllers, including: A first difference between the monitoring parameter uploaded by each sub-controller and the preset monitoring parameter is calculated.
[0030] The largest first difference is input into a preset feedback controller to obtain a first control parameter.
[0031] The first control parameter is sent to the sub-controller corresponding to the largest difference.
[0032] In this embodiment, the first controller can receive monitoring parameters uploaded from each sub-controller. The monitoring parameters of each sub-controller are compared with the preset ideal monitoring parameters, and the difference between the two is calculated. The maximum difference is found from these differences. This maximum difference reflects the most serious deviation from the ideal state. This maximum difference is input into the preset feedback controller for calculation and processing, and the corresponding first control parameter is generated and sent to the sub-controller that generates the maximum difference, so as to control it to perform subsequent adjustments and controls.
[0033] For example, in converter steelmaking, the preset molten steel temperature is 1500 degrees Celsius. The temperature monitoring parameter uploaded by sub-controller A is 1450 degrees Celsius, with a difference of 50 degrees Celsius. The temperature uploaded by sub-controller B is 1480 degrees Celsius, with a difference of 20 degrees Celsius. The first controller finds out that the difference of 50 degrees Celsius of sub-controller A is the maximum difference, and inputs it into the feedback controller to generate the first control parameter, such as increasing the heating power to P. Then this first control parameter is sent to sub-controller A for corresponding adjustment.
[0034] This embodiment takes into account that the temperatures in the same converter affect each other. If the steelmaking parameters at all positions are adjusted, the cost is high and unpredictable chain reactions or effects are likely to occur. This embodiment accurately locates the sub-controller with the largest deviation from the preset value, and then generates and issues targeted control parameters. This method not only improves the response speed and accuracy of the system, but also can solve key problems in a targeted manner, save resource costs, and ensure the stability and performance of the entire converter steelmaking project.
[0035] In one embodiment of the present disclosure, adjusting the first control parameter based on the current monitoring parameter of the target converter to obtain the second control parameter includes: A second difference between the first monitoring parameter and the second monitoring parameter is calculated. The first monitoring parameter is the target monitoring parameter uploaded to the first controller, and the second monitoring parameter is the target monitoring parameter obtained when the first control parameter is received.
[0036] The first control parameter is adjusted based on the second difference.
[0037] In this embodiment, when the sub-controller receives the first control parameter, it will obtain the current monitoring parameter of the target converter again. The monitoring parameter (first monitoring parameter) previously uploaded to the first controller is compared with the monitoring parameter (second monitoring parameter) obtained when the first control parameter is received at this moment, and the second difference between the two is calculated. This difference reflects the change in the state of the converter during the generation and transmission of the first control parameter. According to the size and direction of this second difference, the first control parameter is adjusted accordingly.
[0038] For example, assume that in converter steelmaking, the first monitoring parameter shows that the temperatures of the monitoring positions corresponding to the multiple self-controllers are 1300 degrees Celsius, 1280 degrees Celsius, and 1340 degrees Celsius, respectively, and are uploaded to the first controller, and then the first control parameter is received. At this time, the second monitoring parameter obtained shows that the temperatures of the monitoring positions corresponding to the multiple self-controllers are 1310 degrees Celsius, 1300 degrees Celsius, and 1290 degrees Celsius, respectively. The second differences calculated are 10 degrees Celsius, 20 degrees Celsius, and -50 degrees Celsius, respectively. Based on multiple second differences, the first control parameter is adjusted. For example, the first control parameter was originally to increase the heating of the A sub-controller by a degree Celsius, and now it may be adjusted to increase the heating of the A sub-controller by b degrees Celsius, where b is less than a, so as to more accurately control the temperature in the furnace and avoid overheating.
[0039] This embodiment can dynamically adjust the first control parameter based on the difference in the real-time monitoring parameters of the target converter to obtain the second control parameter. This adjustment ensures the accuracy and timeliness of the control parameter and effectively reduces the control error caused by time delay and state change. Especially in the converter steelmaking process, this real-time adjustment can more accurately control the temperature in the furnace, prevent overheating or insufficient temperature, thereby improving production efficiency and product quality.
[0040] In one embodiment of the present disclosure, adjusting the first control parameter based on the second difference includes: The first control parameter is adjusted based on the first formula.
[0041] The first formula is:
[0042] in, represents the second control parameter, represents the first control parameter, , and represents the adjustment factor, represents the angular frequency, represents the attenuation coefficient, Represents the second difference.
[0043] In this embodiment, it is assumed that the first converter monitoring parameter is , the second converter monitoring parameter is , their time interval is t, and the second difference is = - , and Represents the adjustment coefficient, which is used to control the adjustment range of different parts according to actual conditions.
[0044] This embodiment can calculate the adjusted control parameters according to the formula, so that the adjustment strategy is more scientific and reasonable, and the stability of the adjustment process is guaranteed.
[0045] In one embodiment of the present disclosure, the converter steelmaking automatic control method further includes: The time interval is calculated based on the impurity content of the molten iron corresponding to the target converter and the capacity of the converter.
[0046] In this embodiment, in order to ensure the accuracy and timeliness of the automatic control of converter steelmaking, the sub-controller uploads monitoring parameters to the first controller at a specific time interval. The time interval represents the time interval for the sub-controller to collect data, and determines the frequency with which the sub-controller uploads monitoring data to the first controller. This time interval is not fixed, but firstly the initial time interval is calculated based on the impurity content of the molten iron corresponding to the target converter and the capacity of the converter. Considering that the impurity content of the molten iron will affect the speed and process of the steelmaking reaction, the time interval is subsequently adjusted according to the change of the impurity content of the molten iron.
[0047] In this embodiment, the impurity content is high, the reaction may be more complex, and more frequent acquisition and adjustment of parameters are required, and the time interval will be shortened accordingly. The capacity of the converter determines the scale of processing molten iron and the time required for the reaction. Large-capacity converters generally require a longer reaction time, and the time interval may be appropriately extended. By comprehensively considering these two factors, the most suitable time interval is calculated, and the sub-controller can be made to collect data and upload it at this interval, so that the first controller can more effectively analyze and generate control parameters.
[0048] The converter steelmaking automatic control method in this embodiment significantly improves the automation and accuracy of the steelmaking process by dynamically adjusting the time interval to adapt to the changes in the impurity content of molten iron and the converter capacity. This not only ensures the timeliness and accuracy of the steelmaking process, but also reduces production costs and energy consumption, and does not need to maintain a high-power information collection state all the time, providing strong support for the sustainable development of the steel industry.
[0049] In one embodiment of the present disclosure, the preset time interval is calculated based on the impurity content of the molten iron corresponding to the converter and the capacity of the target converter, including: A first time interval corresponding to the target converter is determined based on a preset mapping relationship between the converter capacity and the time interval.
[0050] The first time interval is adjusted based on the change rate of the impurity content within the preset time period to obtain a preset time interval.
[0051] In this embodiment, a preset mapping relationship between the converter capacity and the time interval that meets the actual situation of the converter steelmaking project is first given. According to the capacity of the target converter, a preliminary first time interval is determined through this mapping relationship. The time interval is adjusted by monitoring the rate of change of the impurity content in the molten iron within a preset time period. The rate of change reflects the severity of the impurity reaction. If the rate of change is greater than or equal to the preset change threshold, it means that the impurity removal and other reactions are rapid, then the time interval should be shortened to monitor real-time data more frequently and perform targeted adjustment and control. If the rate of change is less than the preset change threshold, the first time interval can be maintained, or the first time interval can be extended to obtain the final preset time interval.
[0052] For example, a 100-ton converter is currently producing steel. According to the preset mapping relationship, the first time interval is initially determined to be 5 minutes. The impurity content of the molten iron is monitored within a preset 15-minute time period, and it is found that its rate of change is greater than the preset rate of change threshold. This indicates that the reaction of the impurities is more intense and requires more frequent control and adjustment. Therefore, the first time interval is shortened, for example, adjusted to 3 minutes. The sub-controller can collect and upload monitoring parameters at 3-minute time intervals, so that the first controller can generate control parameters based on the latest data more promptly and accurately.
[0053] This embodiment achieves refined control of the steelmaking process by comprehensively considering the change rate of converter capacity and molten iron impurity content, accurately calculating and adjusting the preset time interval. Specifically, when impurities change frequently during converter steelmaking, shortening the time interval helps to quickly respond to emergencies in the steelmaking process and timely adjust process parameters such as oxygen blowing intensity and feeding speed, thereby effectively avoiding the decline in molten steel quality, energy waste and possible equipment damage caused by uncontrolled reaction. When the reaction steps of converter steelmaking tend to be stable, extending the time interval for monitoring and adjusting data can reduce unnecessary data collection and processing work, reduce the system's computing load, and improve overall work efficiency. At the same time, it avoids interference with system stability caused by too frequent adjustments, and reduces errors and fluctuations that may be introduced due to frequent interventions. This helps to save resources, reduce production costs, and enable the steelmaking process to be carried out under relatively stable conditions, further ensuring the consistency and stability of molten steel quality.
[0054] In one embodiment of the present disclosure, adjusting the first time interval based on the change rate of the impurity content within a preset time period to obtain the preset time interval includes: The adjustment step size is determined based on the rate of change. The adjustment step size is positively correlated with the rate of change.
[0055] The first time interval is adjusted based on the adjustment step to obtain a preset time interval.
[0056] In this embodiment, the change of the impurity content within a preset time period is continuously monitored to calculate the change rate. The change rate can represent the change speed and trend of the impurity content. The adjustment step can be determined according to the change rate. When the change rate is greater than or equal to the preset change rate threshold, the first time interval should be adjusted to decrease, and when the change rate is less than the preset change rate threshold, the first time interval should be adjusted to increase. When the change rate is greater than or equal to the preset change rate threshold, the greater the change rate, the more drastic the change in the impurity content, and the adjustment step increases. Conversely, when the change rate is less than the preset change rate threshold, the smaller the change rate, the smaller the adjustment step is. The adjustment step is segmented positively correlated with the change rate. The first time interval is adjusted according to the determined adjustment step. If the change rate is less than the preset change rate threshold, the adjustment compensation is added to the first time interval. If the change rate is greater than or equal to the preset change rate threshold, it is subtracted from the first time interval to obtain the final preset time interval.
[0057] Exemplarily, in converter steelmaking, the first time interval preliminarily determined according to the converter capacity is 5 minutes. The impurity content is monitored within a preset 30-minute time period, and the rate of change is calculated to be x, where x is greater than the preset rate of change threshold. The adjustment step corresponding to x is 3 minutes. Since the rate of change is high, it indicates that the impurities react quickly and require more frequent monitoring and control, so the adjustment step is subtracted from the first time interval to obtain a preset time interval of 2 minutes. Conversely, if the rate of change is y, y is less than the preset rate of change threshold, the corresponding adjustment step is 3 minutes. A small rate of change can indicate that the impurity reaction is relatively stable, and the time interval can be appropriately extended to obtain a preset time interval of 8 minutes. Through such dynamic adjustment, the steelmaking process can be controlled more accurately, and the quality of molten steel and production efficiency can be improved.
[0058] Corresponding to the automatic control method for converter steelmaking in the above embodiment, Figure 2 This is a structural block diagram of a converter steelmaking automatic control device provided by an embodiment of the present disclosure. For ease of explanation, only the parts related to the embodiment of the present disclosure are shown. Figure 2The converter steelmaking automatic control method is applied to a sub-controller in a converter steelmaking control system. The converter steelmaking control system includes a first controller and a plurality of sub-controllers connected to the first controller, each sub-controller corresponding to a steelmaking parameter at a monitoring position. The monitoring position is a monitoring position corresponding to the converter. The converter steelmaking automatic control device 20 includes: The first calculation module 21 is used to obtain the current target monitoring parameters of the target converter, and upload the target monitoring parameters to the first controller so that the first controller generates and issues the first control parameters based on the monitoring parameters uploaded by all sub-controllers at a preset time interval. The target monitoring parameters are the monitoring parameters of the monitoring position corresponding to the current sub-controller.
[0059] The second calculation module 22 is used to receive the first control parameter and adjust the first control parameter based on the current monitoring parameter of the target converter to obtain the second control parameter.
[0060] The control module 23 is used to automatically control the steelmaking parameters of the converter based on the second control parameters.
[0061] In an embodiment of the present disclosure, the first calculation module 21 is specifically configured to calculate a first difference between a monitoring parameter uploaded by each sub-controller and a preset monitoring parameter.
[0062] The largest first difference is input into a preset feedback controller to obtain a first control parameter.
[0063] The first control parameter is sent to the sub-controller corresponding to the largest difference.
[0064] In one embodiment of the present disclosure, the second calculation module 22 includes: The first calculation unit is used to calculate a second difference between a first monitoring parameter and a second monitoring parameter. The first monitoring parameter is a target monitoring parameter uploaded to the first controller, and the second monitoring parameter is a target monitoring parameter obtained when the first control parameter is received.
[0065] The first control parameter is adjusted based on the second difference.
[0066] In an embodiment of the present disclosure, the first calculation unit is specifically configured to adjust the first control parameter based on the first formula.
[0067] The first formula is:
[0068] in, represents the second control parameter, represents the first control parameter, , and represents the adjustment factor, represents the angular frequency, represents the attenuation coefficient, Represents the second difference.
[0069] In one embodiment of the present disclosure, the converter steelmaking automatic control device 20 further includes: The third calculation module is used to calculate the preset time interval based on the impurity content of the molten iron corresponding to the target converter and the capacity of the target converter.
[0070] In one embodiment of the present disclosure, the third computing module includes: The second calculation unit is used to determine a first time interval corresponding to the target converter based on a preset mapping relationship between the converter capacity and the time interval.
[0071] The first time interval is adjusted based on the change rate of the impurity content within the preset time period to obtain a preset time interval.
[0072] In one embodiment of the present disclosure, the second calculation unit is specifically configured to determine the adjustment step length based on the change rate. The adjustment step length is positively correlated with the change rate.
[0073] The first time interval is adjusted based on the adjustment step to obtain a preset time interval.
[0074] See also Figure 3 , Figure 3 A schematic block diagram of an electronic device provided by an embodiment of the present disclosure. Figure 3 The electronic device 300 in the embodiment shown may include: one or more processors 301, one or more input devices 302, one or more output devices 303 and one or more memories 304. The processors 301, input devices 302, output devices 303 and memories 304 communicate with each other via a communication bus 305. The memory 304 is used to store computer programs, which include program instructions. The processor 301 is used to execute the program instructions stored in the memory 304. The processor 301 is configured to call the program instructions to execute the functions of each module / unit in the above-mentioned device embodiments, such as Figure 2 The functions of modules 21 to 23 are shown.
[0075] It should be understood that in the embodiment of the present disclosure, the processor 301 may be a central processing unit (CPU), and the processor may also be other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc.
[0076] The input device 302 may include a touch panel, a fingerprint collection sensor (for collecting the user's fingerprint information and fingerprint direction information), a microphone, etc., and the output device 303 may include a display (LCD, etc.), a speaker, etc.
[0077] The memory 304 may include a read-only memory and a random access memory, and provide instructions and data to the processor 301. A portion of the memory 304 may also include a non-volatile random access memory. For example, the memory 304 may also store information about the device type.
[0078] In a specific implementation, the processor 301, input device 302, and output device 303 described in the embodiments of the present disclosure can execute the implementation methods described in the first and second embodiments of the converter steelmaking automatic control method provided in the embodiments of the present disclosure, and can also execute the implementation methods of the electronic device 300 described in the embodiments of the present disclosure, which will not be repeated here.
[0079] In another embodiment of the present disclosure, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program, wherein the computer program includes program instructions, and when the program instructions are executed by the processor, all or part of the processes in the above-mentioned embodiment method are implemented, and the computer program can also be completed by instructing the relevant hardware through the computer program. The computer program can be stored in a computer-readable storage medium, and when the computer program is executed by the processor, the steps of each of the above-mentioned method embodiments can be implemented. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form, etc. The computer-readable medium can include: any entity or device capable of carrying computer program code, recording medium, U disk, mobile hard disk, magnetic disk, optical disk, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), electric carrier signal, telecommunication signal and software distribution medium, etc.
[0080] The computer-readable storage medium may be an internal storage unit of the electronic device of any of the aforementioned embodiments, such as a hard disk or memory of the electronic device. The computer-readable storage medium may also be an external storage device of the electronic device, such as a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (SecureDigital, SD) card, a flash card (Flash Card), etc. equipped on the electronic device. Furthermore, the computer-readable storage medium may also include both an internal storage unit of the electronic device and an external storage device. The computer-readable storage medium is used to store computer programs and other programs and data required by the electronic device. The computer-readable storage medium may also be used to temporarily store data that has been output or is to be output.
[0081] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in terms of function in the above description. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this disclosure.
[0082] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the electronic devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0083] In the several embodiments provided in the present application, it should be understood that the disclosed electronic devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic, for example, the division of units is only a logical function division, and there may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. In addition, the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces or units, or it can be an electrical, mechanical or other form of connection.
[0084] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the embodiments of the present disclosure.
[0085] In addition, each functional unit in each embodiment of the present disclosure may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0086] The above are only specific embodiments of the present disclosure, but the protection scope of the present disclosure is not limited thereto. Any technician familiar with the technical field can easily think of various equivalent modifications or replacements within the technical scope disclosed in the present disclosure, and these modifications or replacements should be included in the protection scope of the present disclosure. Therefore, the protection scope of the present disclosure should be based on the protection scope of the claims.
Claims
1. A converter steelmaking automatic control method, characterized in that: The converter steelmaking automatic control method is applied to a sub-controller in a converter steelmaking control system; the converter steelmaking control system comprises a first controller and a plurality of sub-controllers connected to the first controller, each sub-controller corresponding to a steelmaking parameter at a monitoring position; The monitoring position is the monitoring position corresponding to the converter; The converter steelmaking automatic control method comprises: Acquire the current target monitoring parameters of the target converter, upload the target monitoring parameters to the first controller so that the first controller generates and issues the first control parameters based on the monitoring parameters uploaded by all sub-controllers at a preset time interval; the target monitoring parameters are the monitoring parameters of the monitoring position corresponding to the current sub-controller; receiving the first control parameter, and adjusting the first control parameter based on the current monitoring parameter of the target converter to obtain a second control parameter; The steelmaking parameters of the converter are automatically controlled based on the second control parameters.
2. The automatic control method for converter steelmaking according to claim 1, characterized in that: The first controller generates and issues a first control parameter based on the monitoring parameters uploaded by all sub-controllers, including: Calculating a first difference between the monitoring parameter uploaded by each sub-controller and the preset monitoring parameter; Inputting the maximum first difference into a preset feedback controller to obtain a first control parameter; The first control parameter is sent to the sub-controller corresponding to the largest difference.
3. The automatic control method for converter steelmaking according to claim 1, characterized in that: The adjusting the first control parameter based on the current monitoring parameter of the target converter to obtain the second control parameter includes: Calculating a second difference between a first monitoring parameter and a second monitoring parameter; the first monitoring parameter is a target monitoring parameter uploaded to the first controller, and the second monitoring parameter is a target monitoring parameter obtained when the first control parameter is received; The first control parameter is adjusted based on the second difference.
4. The automatic control method for converter steelmaking according to claim 3, characterized in that: The adjusting the first control parameter based on the second difference includes: Adjusting the first control parameter based on a first formula; The first formula is: in, represents the second control parameter, represents the first control parameter, , and represents the adjustment factor, represents the angular frequency, represents the attenuation coefficient, Represents the second difference.
5. The automatic control method for converter steelmaking according to claim 1, characterized in that: Also includes: The preset time interval is calculated based on the impurity content of the molten iron corresponding to the target converter and the capacity of the target converter.
6. The automatic control method for converter steelmaking according to claim 5, characterized in that: The calculating the preset time interval based on the impurity content of the molten iron corresponding to the target converter and the capacity of the target converter includes: Determining a first time interval corresponding to the target converter based on a preset mapping relationship between converter capacity and time interval; The first time interval is adjusted based on the change rate of the impurity content within a preset time period to obtain the preset time interval.
7. The automatic control method for converter steelmaking according to claim 6, characterized in that: The adjusting the first time interval based on the change rate of the impurity content within a preset time period to obtain the preset time interval includes: Determining an adjustment step size based on the change rate; the adjustment step size is positively correlated with the change rate; The first time interval is adjusted based on the adjustment step to obtain the preset time interval.
8. A converter steelmaking automatic control device, characterized in that: The converter steelmaking automatic control method is applied to a sub-controller in a converter steelmaking control system; the converter steelmaking control system comprises a first controller and a plurality of sub-controllers connected to the first controller, each sub-controller corresponding to a steelmaking parameter at a monitoring position; The monitoring position is the monitoring position corresponding to the converter; The converter steelmaking automatic control device comprises: A first calculation module is used to obtain the current target monitoring parameters of the target converter, and upload the target monitoring parameters to the first controller so that the first controller generates and issues the first control parameters based on the monitoring parameters uploaded by all sub-controllers at a preset time interval; the target monitoring parameters are the monitoring parameters of the monitoring position corresponding to the current sub-controller; a second calculation module, configured to receive the first control parameter, and adjust the first control parameter based on the current monitoring parameter of the target converter to obtain a second control parameter; A control module is used to automatically control the steelmaking parameters of the converter based on the second control parameter.
9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and running on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 7 are implemented.
10. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 7 are implemented.