Continuous rigid frame bridge box girder construction quality control method based on Dynamo parametric modeling
The three-dimensional model of the continuous rigid frame bridge was established through Dynamo parametric modeling, which solved the problem of difficulty in accurately making formwork and construction safety in the cantilever construction of large-span bridge box girder, realized the coordinate correction of the cantilever pouring and the demonstration of the special construction plan, and improved the construction Quality and safety.
Patent Information
- Application Number
- CN202410840744.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-27
- Publication Date
- 2024-10-11
AI Technical Summary
During the construction process of box girders of large-span continuous rigid frame bridges, problems such as reduced precamber, cracking of the top and bottom plates of the box girders, and relaxation of internal and external prestresses are prone to occur, and traditional construction methods are difficult to ensure construction safety and linear accuracy.
Dynamo parametric modeling method was used to establish a three-dimensional model of the continuous rigid frame bridge, extract key control point elevations of special-shaped box girder, assist box girder formwork blanking and spatial positioning, simulate a special construction plan for cantilever pouring hanging basket, and ensure the safety of the construction process. and accuracy.
The three-dimensional model generated through Dynamo parametric modeling can accurately calibrate the cantilever pouring coordinates, assist in the design of special-shaped formwork, improve construction accuracy and safety, and ensure the construction quality of large-span continuous rigid frame bridge box girders.
Smart Images

Figure CN118761129A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building information management, and in particular to a method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling. Background Art
[0002] Long-span continuous rigid frame bridges have the characteristics of smooth line shape, uniform force and strong bearing capacity. They are suitable for combining with prestressed technology to cross deep mountain canyons and deep and large rivers. The box girder of a continuous rigid frame bridge is a key link in the construction of the bridge superstructure. Its construction quality directly affects the smoothness of the bridge and the durability of operation. Therefore, it has always been the focus of the quality control of the construction of such bridges. Domestic and foreign scientific researchers and engineering technology have conducted a lot of research on this, achieved many results, and applied them to actual engineering construction. However, after 10 years of operation, continuous rigid frame super-large bridges with a span of more than 150 meters often have problems such as reduced pre-arch, cracking of the top and bottom plates of the box girder, and relaxation of prestress inside and outside the body. The reason is that the box girder of the long-span continuous rigid frame bridge is not densely cast, there are deviations in the construction line shape, and the control of construction process details is insufficient. At the same time, long-span continuous rigid frame bridges are generally dangerous and large projects. Safety is more important than Mount Tai. How to ensure the rationality of the cantilever casting process is the focus of the demonstration of dangerous and large schemes. At present, the quality control of the box girder construction of continuous rigid frame bridges is still carried out in the traditional construction method, which is difficult to achieve good results. Summary of the invention
[0003] In view of the technical problems existing in the above-mentioned background technology, the present invention provides a method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling, which effectively solves the problem that it is difficult to accurately make templates, control the bridge line shape and ensure the construction safety of dangerous and major projects in cantilever construction of large-span continuous rigid frame bridge box girders.
[0004] In order to achieve the above-mentioned object of the invention, the present invention provides the following technical solutions:
[0005] The present invention provides a continuous rigid frame bridge box girder construction quality control method based on Dynamo parametric modeling, which comprises the following steps:
[0006] S1. Use Dynamo to parametrically establish a three-dimensional model of a continuous rigid frame bridge;
[0007] S2, extract the elevation of key control points of special-shaped box girders, auxiliary box girder template cutting and spatial positioning based on the 3D model;
[0008] S3. Simulate the special construction plan of cantilever casting hanging basket for continuous rigid frame bridge to help operators deduce the construction technology and ensure the review and demonstration of dangerous and major plans.
[0009] Furthermore, the specific method of step S1 is as follows:
[0010] S101, box girder structure splitting: split the box girder into three parts: top plate, web plate and bottom plate;
[0011] S102. Determine the civil engineering structure benchmark: Taking the vertical center axis of the box girder as the benchmark, determine the structural range of each component of the box girder;
[0012] S103, custom node: extract the geometric data of the straight lines, curves and chamfers of each part of the box girder, determine the internal and external prestressed tendon positioning information, and customize the Dynamo parametric modeling node based on the above information;
[0013] S104, parametric family preparation: based on the custom nodes in the above step S103, a sample family of top plate, web plate and bottom plate components that can be parametrically driven is compiled in Dynamo software;
[0014] S105, box girder model generation: using the parameterizable driven sample family in step S104, according to the variable cross-sectional size of the long-span continuous rigid frame bridge, drive section by section to generate a three-dimensional model of the box girder of the entire bridge.
[0015] Furthermore, the specific method of step S2 is as follows:
[0016] S201. Capture key control points, check segment misalignment and closing errors: Specifically, take the central axis of the bridge as the reference, start from block 0, extract the vertical elevations of the top and bottom plates of each variable-section box girder section by section, use these elevations as construction instructions for the bridge construction line shape in the construction project, and compare the box girder coordinates monitored during the construction process with the construction instructions to check segment misalignment and closing errors;
[0017] S202, auxiliary box girder formwork cutting and spatial positioning: split each variable-section box girder segment, starting from block No. 0, obtain the inner mold dimensions of the top plate, web plate and bottom plate segment by segment, and make the box girder inner formwork based on these inner mold dimensions; at the same time, analyze the spatial coordinates of each inner formwork in the three-dimensional model, and use these coordinates as the construction positioning points for formwork hoisting.
[0018] Furthermore, the specific method of step S3 is as follows:
[0019] S301, Dangerous and Major Project Simulation: Based on the prepared dangerous and major project, simulate the cantilever casting process of a large-span continuous rigid frame bridge to enable construction management personnel to verify the operability of the project;
[0020] S302, Analysis, Demonstration and Optimization: Based on the simulation of the above-mentioned critical plan, focus on the construction period and verify whether the plan needs to be optimized;
[0021] S303. Expert review: A simulation animation of the critical plan analyzed and demonstrated above will be demonstrated, and a technical expert group will review whether the plan is implemented accordingly.
[0022] Furthermore, in S102, half the size of the left top plate and bottom plate is extracted as the basic parameter, and the whole size of the web plate is extracted as the basic parameter.
[0023] Compared with the prior art, the method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling described in the present invention has the following beneficial effects:
[0024] 1. The Dynamo parametric modeling of the present invention has key technical features such as box girder structure splitting, determination of civil structure benchmarks, custom nodes, parametric family production and box girder model generation. Based on the above technical features, the continuous rigid frame bridge box girder generated by parametric modeling can have the spatial coordinate data of the top and bottom plates and webs as well as each segment. This geometric data is consistent with the design drawings, and can be used to calibrate the construction accuracy of the cantilever cast box girder. In addition, the parametric drive can enable the programming modeling technology to quickly adapt to the modeling requirements of box girders of different sizes, making the present invention have good universality.
[0025] 2. The present invention focuses on the geometric and non-geometric data of the box girder of the continuous rigid frame bridge. The geometric data includes the cantilever casting spatial coordinates, box girder dimensions and template dimensions; the non-geometric data includes the planned construction period, cantilever casting process and scheme optimization simulation functions. The above geometric and non-geometric data can effectively control the cantilever casting coordinate correction of the continuous rigid frame bridge, the auxiliary design of the special-shaped box girder template and the special scheme demonstration of the cantilever casting hanging basket construction of the continuous rigid frame bridge. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a flow chart of the implementation of the present invention;
[0027] Figure 2 A schematic diagram of generating a three-dimensional model of a standard section of a box girder according to the present invention;
[0028] Figure 3 A schematic diagram of generating a three-dimensional model of a full-bridge box girder for the present invention;
[0029] Figure 4 Capturing key control points, checking segment misalignment and closing error (bridge deck elevation) in step S201 of the present invention;
[0030] Figure 5 It is a schematic diagram of the inner formwork of the box girder of the present invention. DETAILED DESCRIPTION
[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Unless otherwise defined, the technical terms or scientific terms used herein should be the usual meanings understood by people with general skills in the field to which the present disclosure belongs. What is not described in detail in the present invention is the known technology of technicians in this technical field.
[0032] Please refer to Figure 1-5 The present invention discloses a method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling, which can realize the coordinate correction of the cantilever casting of the continuous rigid frame bridge, the auxiliary design of the special-shaped formwork of the box girder, and the demonstration of the special scheme for the cantilever casting of the continuous rigid frame bridge. Thus, the problems of the cantilever construction of the box girder of a large-span continuous rigid frame bridge being difficult to accurately make the formwork, control the line shape of the bridge, and ensure the safety of the construction of dangerous and large projects are solved. The construction quality of the box girder of the continuous rigid frame bridge is improved based on the above technology. The method specifically includes the following steps:
[0033] S1. Use Dynamo to parametrically establish a three-dimensional model of a continuous rigid frame bridge;
[0034] S2, extract the elevation of key control points of special-shaped box girders, auxiliary box girder template cutting and spatial positioning based on the 3D model;
[0035] S3. Simulate the special construction plan of cantilever casting hanging basket for continuous rigid frame bridge to help operators deduce the construction technology and ensure the review and demonstration of dangerous and major plans.
[0036] The specific method of using Dynamo parametric modeling in the above step S1 is as follows:
[0037] S101: Box girder structure splitting, specifically splitting the box girder into three parts: top plate, web plate and bottom plate;
[0038] S102: Determine the civil structure benchmark. Specifically, take the vertical center axis of the box girder as the benchmark to determine the construction range of each component of the box girder. Take half the size of the left top plate and bottom plate as the basic parameters, and take the full size of the web plate as the basic parameter.
[0039] S103: Customize nodes, specifically extract geometric data such as straight lines, curves, and chamfers of each part of the box girder, determine the internal and external prestressed tendon positioning information, and customize Dynamo parametric modeling nodes based on the above information;
[0040] S104: Parametric family production. Specifically, based on the above-mentioned custom nodes, a sample family of top plates, web plates, bottom plates and other components that can be parametrically driven is compiled in Dynamo software, such as Figure 2 As shown;
[0041] S105: box girder model generation, specifically using a sample family that can be driven parametrically, according to the variable cross-section size of the long-span continuous rigid frame bridge, drive section by section to generate a three-dimensional model of the box girder of the entire bridge, such as Figure 3 shown.
[0042] Based on the three-dimensional model of the long-span continuous rigid frame bridge established in S1, the target problem is analyzed. The specific method of step S2 is as follows:
[0043] S201: Capture key control points, check segment misalignment and closing errors. Specifically, take the central axis of the bridge as the reference, start from block 0, extract the vertical elevations of the top and bottom plates of each variable-section box girder section by section, use these elevations as construction instructions for the bridge construction line shape in the construction project, and compare the box girder coordinates monitored during the construction process with the construction instructions to check segment misalignment and closing errors, such as Figure 4 As shown;
[0044] S202: Assist in the blanking and spatial positioning of the box girder template. Specifically, the variable-section box girder segments are split, starting from block 0, and the inner mold dimensions of the top plate, web plate, and bottom plate are obtained segment by segment. Based on these inner mold dimensions, the box girder inner template is made; at the same time, the spatial coordinates of each inner template in the 3D model are analyzed, and these coordinates are used as the construction positioning points for template hoisting, such as Figure 5 shown.
[0045] Based on the analysis of S2, a special demonstration of the S3 critical plan is further carried out. The specific methods are as follows:
[0046] S301: Simulation of dangerous and major schemes. Based on the prepared dangerous and major schemes, the cantilever casting process of a large-span continuous rigid frame bridge is simulated to enable construction management personnel to verify the feasibility of the scheme;
[0047] S302: Analyze and demonstrate optimization, specifically based on the simulation of the above-mentioned dangerous and major schemes, focus on the construction period, and demonstrate whether the scheme needs to be optimized;
[0048] S303: Expert review. Specifically, the simulation animation of the dangerous plan analyzed and demonstrated above will be demonstrated at the plan review meeting, and the technical expert group will review whether the plan is implemented accordingly.
Claims
1. A method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling, characterized in that: The following steps are involved: S1. Use Dynamo to parametrically establish a three-dimensional model of a continuous rigid frame bridge; S2, extract the elevation of key control points of special-shaped box girders, auxiliary box girder template cutting and spatial positioning based on the 3D model; S3. Simulate the special construction plan of cantilever casting hanging basket for continuous rigid frame bridge to help operators deduce the construction technology and ensure the review and demonstration of dangerous and major plans.
2. The method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling as claimed in claim 1, characterized in that: The specific method of step S1 is as follows: S101, box girder structure splitting: split the box girder into three parts: top plate, web plate and bottom plate; S102. Determine the civil engineering structure benchmark: Taking the vertical center axis of the box girder as the benchmark, determine the structural range of each component of the box girder; S103, custom node: extract the geometric data of the straight lines, curves and chamfers of each part of the box girder, determine the internal and external prestressed tendon positioning information, and customize the Dynamo parametric modeling node based on the above information; S104, parametric family preparation: based on the custom nodes in the above step S103, a sample family of top plate, web plate and bottom plate components that can be parametrically driven is compiled in Dynamo software; S105, box girder model generation: using the parameterizable driven sample family in step S104, according to the variable cross-sectional size of the long-span continuous rigid frame bridge, drive section by section to generate a three-dimensional model of the box girder of the entire bridge.
3. A method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling as claimed in claim 2, characterized in that: The specific method of step S2 is as follows: S201. Capture key control points, check segment misalignment and closing errors: Specifically, take the central axis of the bridge as the reference, start from block 0, extract the vertical elevations of the top and bottom plates of each variable-section box girder section by section, use these elevations as construction instructions for the bridge construction line shape in the construction project, and compare the box girder coordinates monitored during the construction process with the construction instructions to check segment misalignment and closing errors; S202, auxiliary box girder formwork cutting and spatial positioning: split each variable-section box girder segment, starting from block No. 0, obtain the inner mold dimensions of the top plate, web plate and bottom plate segment by segment, and make the box girder inner formwork based on these inner mold dimensions; at the same time, analyze the spatial coordinates of each inner formwork in the three-dimensional model, and use these coordinates as the construction positioning points for formwork hoisting.
4. A method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling as claimed in claim 3, characterized in that: The specific method of step S3 is as follows: S301, Dangerous and Major Project Simulation: Based on the prepared dangerous and major project, simulate the cantilever casting process of a large-span continuous rigid frame bridge to enable construction management personnel to verify the operability of the project; S302, Analysis, Demonstration and Optimization: Based on the simulation of the above-mentioned critical plan, focus on the construction period and verify whether the plan needs to be optimized; S303. Expert review: A simulation animation of the critical plan analyzed and demonstrated above will be demonstrated, and a technical expert group will review whether the plan is implemented accordingly.
5. A method for controlling the construction quality of a continuous rigid frame bridge box girder based on Dynamo parametric modeling as claimed in claim 3, characterized in that: In S102, half the size of the left top plate and bottom plate is extracted as the basic parameter, and the whole size of the web plate is extracted as the basic parameter.