Train running line drawing method and device, electronic equipment and storage medium
By obtaining the technical parameters of the train operation diagram and comparing the key time nodes, the paving area is updated, which solves the problem of lack of logic and efficiency of traditional manual paving of train operation lines, realizes the automatic and reasonable paving of freight train operation lines, and improves the efficiency of freight trains. Through ability and logic.
Patent Information
- Application Number
- CN202410676468.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-29
- Publication Date
- 2024-10-15
AI Technical Summary
The traditional manual layout of train operating lines lacks logic and requires real-time adjustments, resulting in low utilization of railway section capacity, ignoring the transportation timeliness of freight trains, and failing to ensure the logic and rationality of freight train operating lines.
By obtaining the technical parameters of the train operation chart, mark the paving area that meets the station interval time by interval, compare the key moment nodes of the two adjacent intervals, update the longest continuous paving area of the freight train, and plot the freight train operation in this area Line, use the revenue function and state transition equation to solve the optimal paving area.
It realizes the automatic output of reasonable freight train operating lines, reduces the workload of manual adjustment, improves the cargo train passing capacity and the logic of operating lines, adapts to fluctuations in passenger and freight demand, and shortens the time limit for cargo delivery.
Smart Images

Figure CN118770321A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of railway operation management, and in particular to a train running line laying method, device, electronic equipment and storage medium. Background Art
[0002] The preparation of traditional railway train operation diagrams is completed by manually operating computers. In daily railway transportation work, the preparation of ordinary freight train operation diagrams is based on the train dispatcher receiving the traffic plan, laying out the freight train operation line according to the marshaling content, station operation progress, locomotive routes, arrival and departure line use and adjacent station conditions in the traffic plan, adjusting the operation line in real time during operation, and issuing a stage plan. This traditional method of manually laying out freight train operation lines lacks logic in its initialization state, requires manual real-time adjustment, and there are a lot of repeated operations, which cannot effectively improve the utilization rate of railway section capacity. In addition, when laying out the existing train operation diagram, passenger trains are given priority, and the transportation timeliness of freight trains is ignored, and the logic and rationality of freight train operation lines cannot be guaranteed. Summary of the invention
[0003] The present invention provides a train running line laying method, device, electronic equipment and storage medium, which are used to solve the defects of the traditional method of manually laying out train running lines, which requires manual real-time adjustment, cannot effectively improve the utilization rate of the railway section passing capacity, ignores the transportation cost of freight trains, and cannot ensure the logic and rationality of freight train running lines.
[0004] The present invention provides a train line laying method, comprising: Obtain technical parameters of train operation diagram; According to the technical parameters of the train operation diagram, marking the paving area that meets the station interval time by section; Compare multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area for freight trains; A freight train running line is laid out on the longest continuous paving area.
[0005] According to the train line drawing method provided by the present invention, the train line drawing technical parameters include: One or more of the interval time standards for each station, passenger train timetable, freight train timetable, technical speed of each train, and distance between each section.
[0006] According to the train line drawing method provided by the present invention, marking the drawing area that meets the station interval time according to the train operation diagram technical parameters by interval, comprises: Calculate the train interval time between two trains at the target station in the train operation basic diagram according to the interval time standard of each station, the passenger train timetable, the technical speed of the train, and the distance of each section; Determine whether the train interval between two trains at the target station in the train operation basic diagram in the first stage target drawing area is greater than the train interval standard of the target station; If so, the target station is marked as a paved area that meets the station interval time.
[0007] According to the train line paving method provided by the present invention, the step of comparing multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area of the freight train includes: Construct the revenue function of each interval based on multiple key time nodes of the same station; Constructing a state transfer equation in the uplink and downlink directions according to the profit function of each interval; The state transfer equation is solved to obtain the longest continuous paving area of the freight train.
[0008] According to the train line laying method provided by the present invention, the multiple key moment nodes include: Freight train in Earliest departure time of the station Freight trains are operated at technical speed v k,x Run to Earliest arrival time at the station Latest arrival time at the station and according to the technical speed of the train v k,x The reverse calculation Latest departure time The update methods of each key moment node include: According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the train technical speed v k,x Run to Earliest arrival time at the station Greater than or equal to freight trains Earliest departure time of the station When the freight train is Earliest departure time of the station Updated to the train technical speed v k,x Run to Earliest arrival time at the station According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the train technical speed v k,x Run to Earliest arrival time at the station Less than or equal to freight train Earliest departure time of the station When the train technical speed v k,x Run to Earliest arrival time at the station Updated for the freight train Earliest departure time of the station According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the Latest arrival time at the station Greater than or equal to the technical speed v of the train k,x The reverse calculation Latest departure time When Latest arrival time at the station Updated to the train technical speed v k,x The reverse calculation Latest departure time According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the Latest arrival time at the station Less than or equal to the technical speed v of the train k,x The reverse calculation Latest departure time When the train technical speed v k,x The reverse calculation Latest departure time Updated as described Latest arrival time at the station
[0009] According to the train line laying method provided by the present invention, the profit function is: Among them, the profit function and They respectively indicate whether the paving range of the up and down freight trains in the kth stage meets the demand for the operation of freight trains.
[0010] According to the train line laying method provided by the present invention, the state transfer equation is: Among them, f(T k,s )、f(T k,x ) are the state transfer equations for the uplink and downlink directions respectively.
[0011] The present invention provides a train running line laying device, comprising: An acquisition module is used to obtain technical parameters of the train operation diagram; A marking module, used for marking the paving area that meets the station interval time according to the technical parameters of the train operation diagram; an updating module, used for comparing multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area of the freight train; The paving module is used to pave the freight train running line on the longest continuous paving area.
[0012] The present invention also provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the train running line drawing method described in any one of the above methods is implemented.
[0013] The present invention also provides a non-transitory computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the train running line laying method as described in any one of the above is implemented.
[0014] The present invention provides a train running line laying method, device, electronic device and storage medium, which obtains the technical parameters of the train running diagram; marks the laying area that meets the station interval time according to the technical parameters of the train running diagram by interval; compares multiple key time nodes of two adjacent intervals at the same station to update the laying area, and obtains the longest continuous laying area for freight trains; lays out the freight train running line on the longest continuous laying area, which can realize automatic output of reasonable freight train running lines, reduce the workload and difficulty of manual adjustment of train dispatchers, further improve the passing capacity of freight trains, improve the adaptability of train running diagram laying to fluctuations in passenger and freight demand, and improve the logic and rationality of freight train running lines, further shorten the railway freight delivery time limit. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0016] Figure 1 It is one of the flow diagrams of the train line laying method provided by the present invention; Figure 2 It is a schematic diagram of the freight train operation line provided by the present invention; Figure 3 This is the second flow chart of the train line laying method provided by the present invention; Figure 4 It is a relationship diagram of the interval time of trains at stations provided by the present invention; Figure 5 It is a structural schematic diagram of the train running line laying device provided by the present invention; Figure 6 It is a structural schematic diagram of the electronic device provided by the present invention. DETAILED DESCRIPTION
[0017] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0018] Figure 1 A flow chart of a train line drawing method provided by an embodiment of the present invention, such as Figure 1As shown, the train line laying method provided by the embodiment of the present invention includes: Step 101, obtaining technical parameters of the train operation diagram; Step 102: marking the drawing area that meets the station interval time according to the technical parameters of the train operation diagram; Step 103: compare multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area for freight trains; Step 104: laying out a freight train running line on the longest continuous laying area.
[0019] The traditional method of manually drawing freight train routes lacks logic in its initialization state and requires manual real-time adjustment, which is time-consuming and labor-intensive, and involves a large amount of repeated work, and cannot effectively improve the utilization rate of railway section capacity. In addition, when drawing the existing train operation diagram, passenger trains are given priority, while the transportation cost of freight trains is ignored, and the logic and rationality of the freight train route cannot be guaranteed.
[0020] The present invention provides a train line laying method, which obtains train operation diagram technical parameters; marks the laying area that meets the station interval time according to the train operation diagram technical parameters; compares multiple key time nodes of two adjacent sections at the same station to update the laying area, and obtains the longest continuous laying area for freight trains; lays out the freight train line on the longest continuous laying area, which can realize automatic output of reasonable freight train line, reduce the workload and difficulty of manual adjustment of train dispatchers, further improve the passing capacity of freight trains, improve the adaptability of train operation diagram laying to fluctuations in passenger and freight demand, and improve the logic and rationality of freight train line, further shorten the railway freight delivery time limit.
[0021] Based on any of the above embodiments, the train operation diagram technical parameters include but are not limited to the station interval time standard, passenger train timetable, freight train timetable, technical speed of each train, and distance of each section. The marking of the drawing area that meets the station interval time according to the train operation diagram technical parameters by section includes: Step 201, calculating the train interval time between two trains at the target station in the train operation basic diagram according to the interval time standard of each station, the passenger train timetable, the technical speed of the train, and the distance of each section; In the embodiment of the present invention, the basic train operation diagram is preset according to the train operation parameters.
[0022] Step 202: determine whether the train interval between two trains at the target station in the train operation basic diagram in the first stage target drawing area is greater than the train interval standard of the target station; Step 203: If yes, mark the target station as a paved area that meets the station interval time.
[0023] Based on any of the above embodiments, comparing multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area of the freight train includes: Step 301: construct a revenue function for each interval according to multiple key time nodes of the same station; Step 302: construct a state transfer equation in the uplink and downlink directions according to the profit function of each interval; Step 303: Solve the state transfer equation to obtain the longest continuous paving area of the freight train.
[0024] In an embodiment of the present invention, the multiple key moment nodes include: Freight train in Earliest departure time of the station Freight trains are operated at technical speed v k,x Run to Earliest arrival time at the station Latest arrival time at the station and according to the technical speed of the train v k,x The reverse calculation Latest departure time The update methods of each key moment node include: According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the train technical speed v k,x Run to Earliest arrival time at the station Greater than or equal to freight trains Earliest departure time of the station When the freight train is Earliest departure time of the station Updated to the train technical speed v k,x Run to Earliest arrival time at the station According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the train technical speed v k,x Run to Earliest arrival time at the station Less than or equal to freight train Earliest departure time of the station When the train technical speed v k,x Run to Earliest arrival time at the station Updated for the freight train Earliest departure time of the station According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the Latest arrival time at the station Greater than or equal to the technical speed v of the train k,x The reverse calculation Latest departure time When Latest arrival time at the station Updated to the train technical speed v k,x The reverse calculation Latest departure time According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the Latest arrival time at the station Less than or equal to the technical speed v of the train k,x The reverse calculation Latest departure time When the train technical speed v k,x The reverse calculation Latest departure time Updated as described Latest arrival time at the station
[0025] like Figure 2As shown, in the first case, the earliest arrival time at Yuanshi Station must be greater than the earliest departure time at the original station of the next interval. In this case, if the second calculation cycle plots it continuously, it is necessary to select the smallest value among these four times to update; the second case is that the earliest arrival time of the previous interval is less than the earliest departure time of the next interval. If the earliest arrival time of the previous interval is equal to the earliest departure time of the next interval, the two times can be repeatedly assigned, that is, the freight train Earliest departure time of the station Updated to the train technical speed v k,x Run to Earliest arrival time at the station And the train technical speed v k,x Run to Earliest arrival time at the station Updated for the freight train Earliest departure time of the station
[0026] In this embodiment of the present invention, the profit function is: Among them, the profit function and They respectively indicate whether the layout range of the up and down freight trains in the kth stage meets the demand for the operation of freight trains. If it does, the value is 1, otherwise, the value is 0.
[0027] In an embodiment of the present invention, the state transfer equation is: Among them, f(T k,s )、f(T k,k ) are the state transfer equations for the uplink and downlink directions respectively.
[0028] Based on any of the above inventions, on the basis of a given train operation basic diagram, within the limited space-time domain created by the running lines in the train operation basic diagram, with the goal of maximizing the paving range of the freight train running lines and satisfying constraints such as the station train interval time standard, the optimal paving area and paving plan of the freight train running lines are solved. From the spatial dimension, the line is divided into multiple interconnected decision stages according to the interval; from the time dimension, the time domain of the paving of the train running lines in the up and down directions of each stage is used as the state of the next stage; a set of decision sequences are constructed in chronological order, so as to solve the optimal paving area of the freight train running lines in the limited space-time domain.
[0029] The embodiment of the present invention is based on a dual computing cycle, constructs a dynamic programming model of the state transfer equation and solves it, and the execution process is as follows: Figure 2Step 1 and step 2 are the first calculation cycle, and step 3 is the second calculation cycle.
[0030] Step 1: Substitute and initialize various system parameters, input basic data such as station interval time standard, passenger train schedule, train technical speed, and interval distance into the mathematical model of the present invention. Convert the time format into floating point data for easy calculation. Divide the trains into four categories from high to low according to the speed level of 160km / h, 140km / h, 120km / h, and 80km / h, i = {1, 2, 3, 4}; use S to represent the station set, S = {s1, s2, ..., s n}; Station node s in the up and down directions of stage k k and k+1 , respectively Indicates that there is Defining states and For the i-th type of train, Station downlink direction and The departure time range of the station in the upward direction, that is, the feasible decision set of the kth stage.
[0031] Determine whether the train interval time between the two trains at the s1 station in the basic diagram meets the drawing requirements in the target drawing area of the first stage, that is, whether it is greater than the train interval time standard of the station. If it is greater, proceed to step 2; if it is equal, return to the starting point of the model and reselect the drawing area.
[0032] Step 2: Lay out the painting according to the interval (stage), using Indicates that the i-th type of train in the downlink direction is The earliest departure time of the station; Indicates that the i-th type of train in the downlink direction is The latest arrival time at the station; Indicates that the i-th type of train in the upward direction is The earliest departure time of the station; Indicates that the i-th type of train in the upward direction is The latest arrival time at the station; express The sum of discrete time periods within the minimum departure interval of the station; express The sum of discrete time periods within the minimum inter-arrival time of a station.
[0033] Downward freight train at stage k and Depends on the departure or passing time of the preceding train and the arrival or passing time of the following train As well as the station interval time of the station. Among them, since the model solves the freight train layout range in a limited time and space domain, the value of the tracking interval time between freight trains and passenger trains is determined according to the time when the following train is ready to depart. Figure 4 As shown, there are 12 mutually exclusive Boolean variables σ c ={0,1},c={1,2,…,12}.
[0034] Then, in the kth stage, within the limited space-time domain between the two trains in the basic graph, the layout range of the freight train depends on the following eight key time nodes, where i = {1, 2, 3}, σ c ={0,1},c={1,2,…,12}: In the formula, For freight trains The earliest departure time of the station; Technical speed for freight trains Run to The earliest arrival time of the station; Latest arrival time at the station And by technology speed Reverse Latest departure time l k is the distance of the kth stage / km, that is and The absolute value of the coordinate difference.
[0035] Only when or Only when the freight train layout range is guaranteed to be non-negative; when or When , the range of freight train layout is negative, indicating that the conditions for laying out the freight train line are not met within the limited space-time domain of this stage.
[0036] Step 3: Optimize the output results of step 2 and output the area that can be paved continuously; compare the four key time nodes at the same station in two adjacent stages, and update and assign values to them to achieve the effect of optimizing the continuous effective paving area.
[0037] In daily railway transportation work, the preparation of ordinary freight train operation diagrams is based on the train dispatcher accepting the traffic plan uploaded by the plan dispatcher, laying out the freight train operation line according to the marshaling content, station operation progress, locomotive routes, arrival and departure line use and adjacent station conditions, adjusting the operation line in real time during operation, and issuing stage plans. In order to meet the freight demand in special periods, the railway department often adopts the operation diagram optimization method of "adjusting passengers and increasing cargo", and still relies heavily on manual laying of freight train operation lines. This traditional method of manually laying out freight train operation lines lacks logic in its initialization state, requires a lot of manual real-time adjustment, is time-consuming and laborious, involves a large number of repeated operations, and lacks automatic analysis and compilation methods. Based on the above problems, the present invention combines the needs of train diagram compilation, transforms the problem of conventional railway train diagram compilation into a dynamic programming problem, takes space and time dimensions as the decision-making stage and the next stage state respectively, and constructs a dynamic programming model based on two calculation cycles. It can automatically output reasonable freight train routes by inputting known parameters such as stop plans and station intervals, reduce the workload and difficulty of manual adjustments by train dispatchers, further improve the throughput capacity of freight trains, and improve the adaptability of train diagram layout to fluctuations in passenger and freight demand.
[0038] The train line laying method provided by the embodiment of the present invention transforms the problem of laying out the freight train line in the conventional railway train operation diagram into a dynamic programming problem, constructs a mathematical model for automatic laying out of the freight train line, and automatically outputs a reasonable continuous laying area of the freight train line by inputting known parameters into the model algorithm. It has theoretical and practical significance for improving the throughput capacity of conventional railway freight trains and optimizing the structure of conventional railway passenger and freight trains. It not only automatically marks out the reasonable laying range of the freight train line in the conventional railway operation diagram; it also provides algorithm support for the automatic laying out of railway train lines; it can effectively reduce the workload of train dispatchers and improve the quality of railway operation diagrams; it meets the future railway's demand for precise adaptation of the market and capacity, and helps to further optimize the division of labor between high-speed and conventional railways in the channel, and improve the throughput capacity of conventional railway freight trains.
[0039] The train line paving device provided by the present invention is described below. The train line paving device described below and the train line paving method described above can be referenced to each other.
[0040] Figure 5 A schematic diagram of a train running line laying device provided in an embodiment of the present invention, such as Figure 5 As shown, the train running line laying device provided by the embodiment of the present invention includes: An acquisition module 501 is used to acquire technical parameters of a train operation diagram; A marking module 502 is used to mark the paving area that meets the station interval time according to the technical parameters of the train operation diagram; An updating module 503 is used to compare multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area of the freight train; The drawing module 504 is used to draw a freight train running line on the longest continuous drawing area.
[0041] The present invention provides a train running line laying device, which obtains the technical parameters of the train running diagram; marks the laying area that meets the station interval time according to the technical parameters of the train running diagram by interval; compares multiple key time nodes of two adjacent intervals at the same station to update the laying area, and obtains the longest continuous laying area for freight trains; lays out the freight train running line on the longest continuous laying area, which can realize automatic output of reasonable freight train running lines, reduce the workload and difficulty of manual adjustment of train dispatchers, further improve the passing capacity of freight trains, improve the adaptability of train running diagram laying to fluctuations in passenger and freight demand, and improve the logic and rationality of freight train running lines, further shorten the railway freight delivery time limit.
[0042] Figure 6 An example of a physical structure diagram of an electronic device is shown in FIG. Figure 6 As shown, the electronic device may include: a processor 610, a communication interface 620, a memory 630 and a communication bus 640, wherein the processor 610, the communication interface 620 and the memory 630 communicate with each other through the communication bus 640. The processor 610 may call the logic instructions in the memory 630 to execute the train line laying method, which includes: obtaining the technical parameters of the train operation diagram; marking the laying area that meets the station interval time according to the interval according to the technical parameters of the train operation diagram; comparing the multiple key time nodes of two adjacent intervals at the same station to update the laying area, and obtaining the longest continuous laying area of the freight train; laying the freight train line on the longest continuous laying area.
[0043] In addition, the logic instructions in the above-mentioned memory 630 can be implemented in the form of a software functional unit and can be stored in a computer-readable storage medium when it is sold or used as an independent product. Based on such an understanding, the technical solution of the present invention can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium, including several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc. Various media that can store program codes.
[0044] On the other hand, the present invention also provides a computer program product, which includes a computer program, which can be stored on a non-transitory computer-readable storage medium. When the computer program is executed by a processor, the computer can execute the train line laying method provided by the above methods, which method includes: obtaining technical parameters of the train operation diagram; marking the laying area that meets the station interval time according to the interval according to the technical parameters of the train operation diagram; comparing multiple key time nodes of two adjacent intervals at the same station to update the laying area, and obtaining the longest continuous laying area for freight trains; and laying out the freight train line on the longest continuous laying area.
[0045] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.
[0046] Through the description of the above implementation methods, those skilled in the art can clearly understand that each implementation method can be implemented by means of software plus a necessary general hardware platform, and of course, it can also be implemented by hardware. Based on this understanding, the above technical solution is essentially or the part that contributes to the prior art can be embodied in the form of a software product, and the computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, a disk, an optical disk, etc., including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each embodiment or some parts of the embodiments.
[0047] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for laying out a train running line, characterized in that: include: Obtain technical parameters of train operation diagram; According to the technical parameters of the train operation diagram, marking the paving area that meets the station interval time by section; Compare multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area for freight trains; A freight train running line is laid out on the longest continuous paving area.
2. A train line laying method according to claim 1, characterized in that: The train operation diagram technical parameters include: One or more of the following: time standards for station intervals, passenger train timetables, freight train timetables, various train technical speeds, and distances between various sections.
3. A train line laying method according to claim 1, characterized in that: The marking of the drawing area satisfying the station interval time according to the technical parameters of the train operation diagram includes: Calculate the train interval time between two trains at the target station in the train operation basic diagram according to the interval time standard of each station, the passenger train timetable, the technical speed of the train, and the distance of each section; Determine whether the train interval between two trains at the target station in the train operation basic diagram in the first stage target drawing area is greater than the train interval standard of the target station; If so, the target station is marked as a paved area that meets the station interval time.
4. A train line laying method according to claim 1, characterized in that: The comparing of multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area of the freight train includes: Construct the revenue function of each interval based on multiple key time nodes of the same station; Constructing a state transfer equation in the uplink and downlink directions according to the profit function of each interval; The state transfer equation is solved to obtain the longest continuous paving area of the freight train.
5. A train line laying method according to claim 4, characterized in that: The multiple key moment nodes include: Freight train in Earliest departure time of the station Freight trains are operated at technical speed v k,x Run to Earliest arrival time at the station Latest arrival time at the station and according to the technical speed of the train v k,x The reverse calculation Latest departure time The update methods of each key moment node include: According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the train technical speed v k,x Run to Earliest arrival time at the station Greater than or equal to freight trains Earliest departure time of the station When the freight train is Earliest departure time of the station Updated to the train technical speed v k,x Run to Earliest arrival time at the station According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the train technical speed v k,x Run to Earliest arrival time at the station Less than or equal to freight train Earliest departure time of the station When the train technical speed v k,x Run to Earliest arrival time at the station Updated for the freight train Earliest departure time of the station According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the Latest arrival time at the station Greater than or equal to the technical speed v of the train k,x The reverse calculation Latest departure time When Latest arrival time at the station Updated to the train technical speed v k,x The reverse calculation Latest departure time According to the technical speed of the train v k,x The reverse calculation Latest departure time Greater than or equal to the technical speed v of the train k,x Run to Earliest arrival time at the station And the Latest arrival time at the station Less than or equal to the technical speed v of the train k,x The reverse calculation Latest departure time When the train technical speed v k,x The reverse calculation Latest departure time Updated as described Latest arrival time at the station 6. A train line laying method according to claim 4, characterized in that: The profit function is: Among them, the profit function and They respectively indicate whether the paving range of the up and down freight trains in the kth stage meets the demand for the operation of freight trains.
7. A train line laying method according to claim 4, characterized in that: The state transfer equation is: Among them, f(T k,s )、f(T k,x ) are the state transfer equations for the uplink and downlink directions respectively.
8. A train line laying device, characterized in that: include: An acquisition module is used to obtain technical parameters of the train operation diagram; A marking module, used for marking the paving area that meets the station interval time according to the technical parameters of the train operation diagram; An updating module is used to compare multiple key time nodes of two adjacent sections at the same station to update the paving area and obtain the longest continuous paving area of the freight train; The paving module is used to pave the freight train running line on the longest continuous paving area.
9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein: When the processor executes the program, the train line laying method as described in any one of claims 1 to 7 is implemented.
10. A non-transitory computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the train line drawing method according to any one of claims 1 to 7 is implemented.