Bridge construction method based on rhombic hanging basket

The construction method based on the diamond-shaped hanging basket solves the problems of simple structure and potential safety hazards of the bridge prefabricated main beam installation device in the existing technology. A triangular-structured diamond-shaped hanging basket composed of multiple diagonal bars is used to share the load and ensure that the beam body is hoisted. The stability and safety during the process are suitable for the installation of large-scale prefabricated beams, which improves construction efficiency and quality.

CN118774029APending Publication Date: 2024-10-15CHINA RAILWAY NO 3 GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410970224.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The existing bridge prefabricated main beam installation device has a simple structure and is difficult to deal with complex engineering environments and safety hazards. There are safety risks especially when hoisting heavy prefabricated beams, and it is not suitable for the installation of large prefabricated beams.

Method used

The construction method based on the diamond-shaped hanging basket is adopted, and the stability and safety of the hoisting equipment and hanging basket are ensured through detailed preparation work, hanging basket hoisting, prefabricated beam hoisting, adjustment and fixing, safety inspection and hanging basket removal. The triangular structure of the diamond-shaped hanging basket composed of two diagonal bars shares the load, improves the overall strength and stiffness, and ensures the stability and safety of the beam during the hoisting process.

Benefits of technology

Effectively share the hoisting load, improve the overall strength and stiffness, ensure that the beam body will not be deformed or damaged during the hoisting process, provide stable support and load-bearing capacity, and ensure safe and reliable beam hoisting. It is suitable for prefabricated beams of various specifications. Improve construction efficiency and quality and reduce the probability of accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774029A_ABST
    Figure CN118774029A_ABST
Patent Text Reader

Abstract

The invention discloses a bridge construction method based on a rhombic hanging basket, and relates to the technical field of bridge construction.The method comprises the steps of preparation work, hanging basket hoisting, precast beam hoisting, adjusting and fixing, safety inspection and hanging basket demolition.The rhombic hanging basket is adopted for construction, a triangular structure is formed by a plurality of inclined rods, hoisting loads can be effectively shared, and the construction efficiency is improved; according to the method, the overall strength and rigidity are improved, it is guaranteed that a beam body is not deformed or damaged in the hoisting process, the method is suitable for hoisting requirements of precast beams of various different specifications, the safety in the whole hoisting and dismantling process is emphasized in the construction process, and the method comprises the steps of hoisting equipment inspection, safety protection measure preparation and hoisting process monitoring. All details possibly involved in the hoisting process are integrally covered, such as adjustment of the hoisting point position, fixation of the connecting part, safety inspection and the dismounting process of the hanging basket, the change condition of hoisting operation can be better controlled through combination of the device and the method, and construction safety and quality are ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a diamond-shaped hanging basket-based bridge construction method. Background Art

[0002] Bridges generally refer to structures erected across rivers, lakes, and seas for vehicles and pedestrians to pass smoothly. In order to adapt to the modern, rapidly developing transportation industry, bridges are also extended to buildings that make travel more convenient by crossing mountain streams, poor geology, or meeting other transportation needs. Among them, the main beam refers to the beam in the superstructure that supports various loads and transfers them to piers and abutments. It is one of the main load-bearing structures of the bridge. In the construction of the main beam of the bridge, for cross-river bridges, when the river channel is an important transportation channel, the suspended casting method is usually used to ensure that its navigation capacity is not affected; for approach bridges and overpasses, when the foundation is good, the scaffolding cast-in-place method is usually used; when it costs too much to treat the foundation, precast beams are usually used; Under the prior art, the Chinese patent with application number "202211135317.7" discloses a prefabricated bridge girder installation device and construction method, which belongs to the field of bridge construction equipment technology. It includes a slide rail arranged on the bridge pier, a frame is slidably arranged on the slide rail, two guide plates are hingedly arranged at both ends of the frame, a driving assembly is arranged on the frame for driving the two guide plates to rotate to be close to or away from each other, a fixing mechanism is also arranged on the frame for fixing the frame on the bridge pier, a laser emitter and a ruler are also arranged on the frame, and the laser emitter extends away from the slide rail in the horizontal direction.

[0003] The above patent can complete the installation of precast beams to a certain extent, but in actual operation, only the guide plate is used to fit the precast beams. The device structure described in the patent is too simple, which makes it difficult to cope with complex engineering environments and challenges in actual applications. In addition, due to the simple structure, the device lacks sufficient stability, especially when hoisting heavy precast beams, there will be safety hazards. It is not suitable for the installation of large precast beams. For this reason, we propose a bridge construction method based on a diamond hanging basket to solve the above problems. Summary of the invention

[0004] The purpose of the present invention is to provide a bridge construction method based on a diamond hanging basket to solve the problems raised in the above background technology.

[0005] In order to achieve the above-mentioned invention object, the present invention adopts the following technical scheme: The present invention provides a diamond-shaped hanging basket bridge construction method, comprising the following steps: S101. Preparation: Determine the installation location and the lifting plan for the beam, including the location of the lifting points and the configuration of the hanging basket, and inspect the lifting equipment, hanging basket, etc. to ensure that they are intact and meet safety requirements; S102, hanging basket installation: according to the design requirements, the hanging basket is installed on the bridge pier to ensure the stability of the hanging basket and the supporting structure; S103, prefabricated beam hoisting: hoist the prefabricated bridge beam onto the hanging basket through the hoisting equipment, and adjust the hoisting posture of the beam according to the design plan; S104, adjustment and fixing: adjust the position and posture of the beam to make it completely consistent with the design requirements, and ensure the horizontality and verticality of the beam by adjusting the position and length of the hanging point of the hanging basket. After the beam is hoisted and stabilized, fix it and connect the beam to the hanging basket with steel cables and bolts; S105. Safety inspection: After the lifting is completed, a safety inspection is carried out to ensure that no damage or looseness occurs during the lifting process. At the same time, the safety of the lifting site and surrounding areas is checked to avoid accidents such as casualties or equipment damage; S106. Removal of hanging basket: After the beam is installed and fixed, remove the hanging basket and carry out subsequent cleaning and sorting work.

[0006] The specific steps of the S102 hanging basket hoisting are: S1021, leveling: Use cement mortar to level the top surface of the beam at the pillow position, and the height difference of the top surface of the beam at the two front support points should be controlled within 3 mm; S1022. Install the walkway beam: Install the walkway beam in the middle, extend the fine-rolled threaded steel bars through connectors and then anchor the walkway beam. Level the top surface of the walkway beam. After measuring the center distance of the walkway beam, lock the walkway beam with nuts and connect the walkway beam into a whole at the joints with bolts. S1023. Install the front and rear supports: first insert the rear support from the front end of the track, and then place the front support after the rear support is in place; S1024. Hoisting the main frame: The main frame is hoisted in sections. First, hoist the section farthest from the crane, place it on the front and rear supports, and tighten the connecting bolts to prevent it from tipping over. Use scaffolding and wire ropes for temporary support, and then hoist the other section of the main frame in the same way as above. S1025. Install the connection system between the main frames; S1026. Use Ф25 finely rolled threaded steel bars and shoulder beams to anchor the rear end of the main frame to the top of the beam, and use open PVC pipes to protect the finely rolled threaded steel bars; S1027, hoisting the front upper crossbeam: before hoisting the front upper crossbeam, place a work platform at the front end of the main truss for people to work. After the protective railings around the work platform, the upper and lower cushion beams on the front upper crossbeam and two steel slings are assembled together, the whole is hoisted and installed. After the bottom formwork is assembled, install the jack; S1028. Install the rear sling: install the rear sling, jack and upper pad beam in the reserved hole of the bottom plate of the beam section, and pass the rear sling through the bottom plate to connect with the bottom formwork; S1029, hoisting the bottom formwork and bottom template: before hoisting the bottom formwork, remove the bottom bracket of the front beam section, insert the rear part of the bottom formwork into the bottom of the rear box beam, and connect the front end to the front sling with a pin; S10210, Install the outer formwork and install the outer guide beam: the outer formwork of the hanging basket uses the front section formwork, and the outer guide beam is fixed after hoisting; S10211. Install the inner formwork frame: After the slings are installed in place and the bottom plate reinforcement is tied, install the inner formwork; S10212. Install fences and close-mesh nets with a height of no less than 1.2 meters around the perimeter.

[0007] A diamond-shaped hanging basket comprises two upper chords, which are symmetrically distributed along the axis of the hanging basket, a vertical rod is fixed to the bottom of the ends of the two upper chords close to each other, a rear diagonal rod is fixedly connected to the ends of the two upper chords close to each other, a lower chord is fixedly connected to the bottom of the rear diagonal rod, an end of the lower chord close to the upper chord is in contact with the vertical rod and fixedly connected to the vertical rod, a front diagonal rod is provided at the end of the vertical rod that is away from the upper chord, the vertical rod is fixedly connected to the upper chord via the front diagonal rod, a triangular structure is formed between the multiple diagonal rods and are finally spliced ​​into a diamond structure.

[0008] Preferably, a front slide rail support is installed at the bottom of the lower chord, a walking track is fixedly connected to the top of the front slide rail support, a plurality of steel sleepers are fixedly connected to the bottom of the walking track, and the plurality of steel sleepers are evenly distributed along the length direction of the walking track.

[0009] Preferably, an upper guide beam is installed at the bottom of the lower chord, the end of the upper chord away from the center of the hanging basket is fixedly connected to the front sling, the end of the guide beam away from the lower chord is in contact with the front sling and fixedly connected thereto, the bottom of the front sling is fixedly connected to a bottom longitudinal beam, and a walking guide beam is installed at the bottom of the bottom longitudinal beam.

[0010] Preferably, the preparatory work includes determining the installation position of the beam and the lifting scheme to be adopted in the pre-construction stage, inspecting the lifting equipment, hanging basket, etc. before lifting, configuring the hanging basket according to the size and weight of the beam, ensuring the stability and safety of the hanging basket, and using a diamond hanging basket to carry out the lifting operation of the beam according to the predetermined lifting scheme, including lifting, hanging, adjusting and installing steps, to ensure that the lifting equipment and the hanging basket are intact.

[0011] Preferably, before the prefabricated beam hoisting is carried out, it is necessary to ensure that the hoisting equipment and the hanging basket are in place, the safety performance of the hoisting equipment is checked, and safety protection measures are required at the hoisting site. The prefabricated bridge beam is hoisted onto the hanging basket using the hoisting equipment, and the hoisting posture of the beam is adjusted, which involves fine-tuning of the hoisting point and adjustment of the beam angle. During the hoisting process, the hoisting posture and safety status are monitored.

[0012] Preferably, the adjustment and fixation requires that after the beam body is hoisted and stabilized, the position and posture of the beam body be changed according to the design requirements, which involves adjusting the position and length of the hanging point of the hanging basket to ensure the horizontality and verticality of the beam body. After completing the position and posture adjustment, the beam body is fixed, and the beam body is connected to the hanging basket using steel cables, bolts, etc., and the position and posture of the beam body are adjusted to be completely consistent with the design requirements.

[0013] Preferably, the safety inspection requires testing the beam being hoisted, including checking whether there are cracks or deformations on the surface of the beam, whether the connection parts are firm, the safety of the hoisting site and surrounding areas, including the status of the hoisting equipment, the stability of the work platform, and the integrity of the temporary support structure, to ensure that there are no safety hazards, confirm that the personnel at the hoisting site have been evacuated to a safe area, and conduct a status check on the hoisting equipment.

[0014] Preferably, the dismantling of the hanging basket includes the dismantling of the rear lower beam platform. After the tensioning of the last suspended casting section is completed, the inner mold is first dismantled, and then part of the beam platform is dismantled, followed by the dismantling of the bottom basket system. The bottom basket system falls about one meter, the slings are removed and replaced with steel strands anchored on the beam surface, the entire bottom basket system is gradually lowered using an oil top, and finally the side formwork system is dismantled, the guide sliding beam is replaced with steel strands anchored on the beam surface using pre-embedded holes, and the entire side formwork system is gradually lowered using an oil top. The bottom basket and the side formwork system are stabilized after being lowered to the ground or water surface, the beam surface anchoring is released, and an air cutting tool is used to disassemble the connection between the longitudinal and transverse beams and the disassembled side formwork system. If the bottom basket does not meet the conditions for stopping the ship when it is lowered to the water surface, a small boat can be used to approach the bottom basket, the bottom basket can be disassembled and moved to the bridge deck using a tower crane.

[0015] Compared with the prior art, one or more of the above technical solutions have the following beneficial effects: The present invention adopts a diamond-shaped hanging basket for construction. The diamond-shaped hanging basket adopts a triangular structure composed of multiple oblique rods, which can effectively share the hoisting load, improve the overall strength and rigidity, and ensure that the beam body does not deform or damage during the hoisting process. The design is reasonable, and can provide stable support and bearing capacity, ensuring safe and reliable beam body hoisting. It can be adjusted and adapted according to the size and weight of different bridge precast beams, and is suitable for the hoisting requirements of precast beams of various specifications; During the construction process, emphasis was placed on safety during the entire lifting and dismantling process, including the inspection of lifting equipment, preparation of safety protection measures, monitoring of the lifting process, etc., to ensure the safety of personnel and equipment during the construction process. The operating steps of the lifting and dismantling process were described in detail, with clear guidance from preparation work to specific operations, which helped construction personnel to perform operations in accordance with prescribed procedures and improved construction efficiency. During the construction process, there were steps for adjusting the installation posture of precast beams, confirming their positions, and fixing them to ensure that the beams met the design requirements and were safe and stable, which was conducive to ensuring construction quality.

[0016] It covers all the details that may be involved in the lifting process, such as the adjustment of the lifting point position, the fixation of the connection parts, safety inspection and the removal process of the hanging basket. Comprehensive considerations will help avoid accidents. Through detailed planning and preparation, the changes in lifting operations can be better controlled and the probability of accidents can be reduced. The combination of devices and methods can better control the changes in lifting operations and reduce the probability of accidents, meet the lifting of large prefabricated beams, and ensure construction safety and quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.

[0018] Figure 1 It is a schematic diagram of the overall structure of the diamond hanging basket of the present invention; Figure 2 The present invention Figure 1 The enlarged structural diagram at A in the middle; Figure 3 is a flow chart of the prefabricated beam installation method of the present invention; Figure 4 It is a flow chart of a partial hanging basket hoisting method of the present invention; Figure 5 It is a flow chart of a partial hanging basket hoisting method of the present invention.

[0019] In the figure: 1. Upper chord; 2. Vertical bar; 3. Rear diagonal bar; 4. Lower chord; 5. Front diagonal bar; 6. Front slide rail support; 7. Walking track; 8. Steel sleeper; 9. Front sling; 10. Upper guide beam; 11. Bottom longitudinal beam; 12. Walking guide beam. DETAILED DESCRIPTION

[0020] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.

[0021] See also Figure 1-Figure 5 The present invention provides a construction method of a bridge based on a diamond hanging basket, including preparation work, hanging basket hoisting, prefabricated beam hoisting, adjustment and fixing, safety inspection and hanging basket dismantling, wherein the diamond hanging basket includes two upper chord rods 1, the two upper chord rods 1 are symmetrically distributed along the hanging basket axis, a vertical rod 2 is fixed to the bottom of the ends of the two upper chord rods 1 close to each other, a rear oblique rod 3 is fixedly connected to the ends of the two upper chord rods 1 close to each other, a lower chord rod 4 is fixedly connected to the bottom of the rear oblique rod 3, an end of the lower chord rod 4 close to the upper chord rod 1 is in contact with the vertical rod 2 and fixedly connected to the vertical rod 2, an end of the vertical rod 2 and the upper chord rod 1 away from each other is provided with a front oblique rod 5, the vertical rod 2 is fixedly connected to the upper chord rod 1 through the front oblique rod 5, a plurality of oblique rods are triangular structures and are finally spliced ​​into a diamond structure, a front slide rail support 6 is installed at the bottom of the lower chord rod 4, a walking track 7 is fixedly connected to the top of the front slide rail support 6, a plurality of steel sleepers 8 are fixedly connected to the bottom of the walking track 7, and a plurality of steel sleepers 8 Evenly distributed along the length of the walking track 7, an upper guide beam 10 is hoisted at the bottom of the lower chord 4, and the end of the upper chord 1 away from the center of the hanging basket is fixedly connected to the front sling 9, and the end of the upper guide beam 10 away from the lower chord 4 is in contact with the front sling 9 and fixedly connected thereto, and the bottom of the front sling 9 is fixedly connected to the bottom of the bottom longitudinal beam 11, and a walking guide beam 12 is installed at the bottom of the bottom longitudinal beam 11. The diamond hanging basket adopts a triangular structure composed of multiple oblique rods, which can provide stable support and carrying capacity to ensure safe and reliable beam lifting, can effectively share the lifting load, improve the overall strength and rigidity, and ensure that the beam is not deformed or damaged during the lifting process. The diamond hanging basket can be adjusted and adapted according to the size and weight of different bridge precast beams, and is suitable for the lifting needs of precast beams of various specifications. The stable connection and support structure can effectively avoid the safety hazards such as tilting and swinging during the lifting of the beam body, and ensure the safety of workers and equipment.

[0022] It is very important to determine the installation position of the beam and the hoisting scheme to be adopted during the preparatory work, which will directly affect the smooth progress of the subsequent hoisting operation. Before hoisting, a comprehensive inspection of the hoisting equipment, hanging basket, etc. should be carried out to ensure that they are intact and meet safety requirements. This can effectively avoid safety accidents caused by equipment failure or damage. According to the size and weight of the beam, the hanging basket is reasonably configured to ensure the stability and safety of the hanging basket. According to the predetermined hoisting scheme, the diamond hanging basket is used to carry out the hoisting operation of the beam, including lifting, hanging, adjustment and installation. Through strict preparation and inspection procedures, the hoisting equipment and hanging basket are ensured to be intact, thereby improving the safety of the hoisting operation. Determining the installation position and hoisting scheme in advance, as well as reasonably configuring the hanging basket, can make the entire hoisting operation more efficient and smooth, emphasizing the normative requirements for hoisting equipment and operation processes, which helps to avoid improper operation and safety hazards during construction.

[0023] Before the prefabricated beam is hoisted, it is necessary to ensure that the hoisting equipment and the hanging basket are in place, the safety performance of the hoisting equipment has been checked, and the safety protection measures have been taken at the hoisting site. The prefabricated bridge beam is hoisted onto the hanging basket using the hoisting equipment. This process needs to be carried out strictly in accordance with the design plan to ensure that the hoisting process is smooth and orderly. According to the design plan, the hoisting posture of the beam is adjusted to ensure that it does not become unstable during the hoisting process. It may involve operations such as fine-tuning of the hoisting point and adjustment of the angle of the beam. During the entire hoisting process, it is necessary to continuously monitor the hoisting posture and safety status to ensure the safety of the hoisting operation. Through strict hoisting preparation and monitoring, the instability of the beam during the hoisting process is avoided, which improves the safety of the hoisting operation. According to the design plan, the posture adjustment can ensure that the beam is accurately installed on the hanging basket, and can avoid safety hazards caused by improper posture. Accurate posture adjustment can ensure the installation quality of the prefabricated beam.

[0024] After the beam is hoisted and stabilized, the position and posture of the beam are adjusted according to the design requirements. This may involve adjusting the position and length of the hanging point of the hanging basket to ensure the horizontal and vertical degree of the beam. After completing the position and posture adjustment, the beam needs to be fixed immediately to prevent position offset or posture change during the subsequent construction process. Usually, steel cables, bolts, etc. are used to connect the beam to the hanging basket to ensure that it is firmly fixed. After fixing, a safety inspection is required to ensure that the beam is fixed reliably and there is no looseness or other safety hazards. By adjusting the position and posture of the beam to make it completely consistent with the design requirements, the smooth progress of subsequent construction can be guaranteed to avoid problems caused by inaccurate position of the beam. Adjusting the position and length of the hanging point of the hanging basket can effectively ensure the horizontal and vertical degree of the beam and ensure the construction quality. Timely connection and fixing of the beam to the hanging basket can ensure that the beam will not have position offset or posture change during the subsequent construction process, ensuring construction safety. Timely adjustment and fixing of the beam can reduce the time for readjustment during the subsequent construction process and improve construction efficiency.

[0025] After the lifting is completed, the hoisted beams are fully inspected to ensure that no damage or looseness occurs during the lifting process. This includes checking whether there are cracks, deformations, etc. on the surface of the beams, whether the connection parts are firm, the safety of the lifting site and surrounding areas, including the status of the lifting equipment, the stability of the working platform, the integrity of the temporary support structure, etc., to ensure that there are no hidden safety hazards, confirm that the personnel at the lifting site have been evacuated to a safe area to avoid casualties, and conduct a status check on the lifting equipment to ensure that the equipment is operating normally and there are no faults or loopholes. Through a comprehensive safety inspection, possible damage or looseness during the lifting process can be discovered in time to avoid safety accidents caused by this during subsequent construction. The safety of the lifting site and surrounding areas can timely discover and eliminate potential safety hazards, effectively prevent the occurrence of accidents, and discover problems with the equipment in advance and repair them in time to protect the equipment from further damage.

[0026] Finally, the hanging basket is dismantled, and the lower beam platform is dismantled first. After the tensioning of the last suspended casting section is completed, the inner mold is dismantled first, and then the part of the beam platform is dismantled, followed by the bottom basket system. The bottom basket system falls about one meter, the sling is removed and replaced with a steel strand anchored on the beam surface, and the entire bottom basket system is gradually lowered using an oil top. Finally, the side formwork system is dismantled, and the guide slide beam is replaced with a steel strand anchored on the beam surface using the embedded hole, and the entire side formwork system is gradually lowered using an oil top to ensure that the bottom basket and the side formwork system are stable after being lowered to the ground or water surface, and the beam surface anchoring is released. The gas cutting tool is used to disassemble the connection between the longitudinal and transverse beams and the disassembled side formwork system. If the bottom basket is lowered to the water surface and does not meet the conditions for stopping the ship, a small boat can be used to approach the bottom basket, disassemble the bottom basket, and use a tower crane to adjust it to the bridge deck. By gradually dismantling and safely lowering the bottom basket and side formwork system, the safety of the entire dismantling process can be ensured and the risk of accidents can be reduced. The entire dismantling process is carried out in accordance with detailed steps to ensure that each link is handled reasonably and the construction efficiency is improved.

[0027] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A method for constructing a bridge based on a diamond hanging basket, characterized in that: The following steps are involved: S101. Preparation: Determine the installation location and the lifting plan for the beam, including the location of the lifting points and the configuration of the hanging basket, and inspect the lifting equipment, hanging basket, etc. to ensure that they are intact and meet safety requirements; S102, hanging basket installation: according to the design requirements, the hanging basket is installed on the bridge pier to ensure the stability of the hanging basket and the supporting structure; S103, prefabricated beam hoisting: hoist the prefabricated bridge beam onto the hanging basket through the hoisting equipment, and adjust the hoisting posture of the beam according to the design plan; S104, adjustment and fixing: adjust the position and posture of the beam to make it completely consistent with the design requirements, and ensure the horizontality and verticality of the beam by adjusting the position and length of the hanging point of the hanging basket. After the beam is hoisted and stabilized, fix it and connect the beam to the hanging basket with steel cables and bolts; S105. Safety inspection: After the lifting is completed, a safety inspection is carried out to ensure that no damage or looseness occurs during the lifting process. At the same time, the safety of the lifting site and surrounding areas is checked to avoid accidents such as casualties or equipment damage; S106. Removal of hanging basket: After the beam is installed and fixed, remove the hanging basket and carry out subsequent cleaning and sorting work.

2. A diamond-shaped hanging basket bridge construction method according to claim 1, characterized in that: The specific steps of the S102 hanging basket hoisting are: S1021, leveling: Use cement mortar to level the top surface of the beam at the pillow position, and the height difference of the top surface of the beam at the two front support points should be controlled within 3 mm; S1022. Install the walkway beam: Install the walkway beam in the middle, extend the fine-rolled threaded steel bars through connectors and then anchor the walkway beam. Level the top surface of the walkway beam. After measuring the center distance of the walkway beam, lock the walkway beam with nuts and connect the walkway beam into a whole at the joints with bolts. S1023. Install the front and rear supports: first insert the rear support from the front end of the track, and then place the front support after the rear support is in place; S1024. Hoisting the main frame: The main frame is hoisted in sections. First, hoist the section farthest from the crane, place it on the front and rear supports, and tighten the connecting bolts to prevent it from tipping over. Use scaffolding and wire ropes for temporary support, and then hoist the other section of the main frame in the same way as above. S1025. Install the connection system between the main frames; S1026. Use Ф25 finely rolled threaded steel bars and shoulder beams to anchor the rear end of the main frame to the top of the beam, and use open PVC pipes to protect the finely rolled threaded steel bars; S1027, hoisting the front upper crossbeam: before hoisting the front upper crossbeam, place a work platform at the front end of the main truss for people to work. After the protective railings around the work platform, the upper and lower cushion beams on the front upper crossbeam and two steel slings are assembled together, the whole is hoisted and installed. After the bottom formwork is assembled, install the jack; S1028. Install the rear sling: install the rear sling, jack and upper pad beam in the reserved hole of the bottom plate of the beam section, and pass the rear sling through the bottom plate to connect with the bottom formwork; S1029, hoisting the bottom formwork and bottom template: before hoisting the bottom formwork, remove the bottom bracket of the front beam section, insert the rear part of the bottom formwork into the bottom of the rear box beam, and connect the front end to the front sling (9) with a pin; S10210, Install the outer formwork and install the outer guide beam: the outer formwork of the hanging basket uses the front section formwork, and the outer guide beam is fixed after hoisting; S10211. Install the inner formwork frame: After the slings are installed in place and the bottom plate reinforcement is tied, install the inner formwork; S10212. Install fences and close-mesh nets with a height of no less than 1.2 meters around the perimeter.

3. The diamond hanging basket used in the diamond hanging basket bridge construction method according to claim 1-2 is characterized in that: The invention comprises two upper chord rods (1), the two upper chord rods (1) are symmetrically distributed along the axis of the hanging basket, a vertical rod (2) is fixed at the bottom of the ends of the two upper chord rods (1) close to each other, a rear diagonal rod (3) is fixedly connected to the ends of the two upper chord rods (1) close to each other, a lower chord rod (4) is fixedly connected to the bottom of the rear diagonal rod (3), an end of the lower chord rod (4) close to the upper chord rod (1) contacts the vertical rod (2) and is fixedly connected to the vertical rod (2), a front diagonal rod (5) is provided at the ends of the vertical rod (2) and the upper chord rod (1) away from each other, the vertical rod (2) is fixedly connected to the upper chord rod (1) via the front diagonal rod (5), and a plurality of diagonal rods form a triangular structure and are finally spliced ​​into a diamond structure.

4. The diamond hanging basket used in the diamond hanging basket bridge construction method according to claim 3 is characterized in that: A front slide rail support (6) is installed at the bottom of the lower chord (4), a travel track (7) is fixedly connected to the top of the front slide rail support (6), and a plurality of steel sleepers (8) are fixedly connected to the bottom of the travel track (7), and the plurality of steel sleepers (8) are evenly distributed along the length direction of the travel track (7).

5. The diamond hanging basket used in the diamond hanging basket bridge construction method according to claim 3 is characterized in that: An upper guide beam (10) is hoisted at the bottom of the lower chord (4); an end of the upper chord (1) away from the center of the hanging basket is fixedly connected to a front sling (9); an end of the upper guide beam (10) away from the lower chord (4) is in contact with the front sling (9) and is fixedly connected thereto; a bottom longitudinal beam (11) is fixedly connected to the bottom of the front sling (9); and a walking guide beam (12) is installed at the bottom of the bottom longitudinal beam (11).

6. The method for constructing a bridge based on a diamond hanging basket according to claim 1 is characterized in that: The preparation work includes determining the installation position of the beam and the lifting scheme to be adopted in the pre-construction stage, inspecting the lifting equipment, hanging basket, etc. before lifting, configuring the hanging basket according to the size and weight of the beam, ensuring the stability and safety of the hanging basket, and using the diamond hanging basket to lift the beam according to the predetermined lifting scheme, including lifting, hanging, adjusting and installing steps, to ensure the integrity of the lifting equipment and the hanging basket.

7. The method for constructing a bridge based on a diamond hanging basket according to claim 1 is characterized in that: The prefabricated beam hoisting requires that before the prefabricated beam hoisting is carried out, the hoisting equipment and the hanging basket must be in place, the safety performance of the hoisting equipment must be checked, and safety protection measures must be taken at the hoisting site. The prefabricated bridge beam must be hoisted onto the hanging basket using the hoisting equipment, and the hoisting posture of the beam must be adjusted, which involves fine-tuning of the hoisting points and adjustment of the beam angle. During the hoisting process, the hoisting posture and safety status must be monitored.

8. The method for constructing a bridge based on a diamond hanging basket according to claim 1 is characterized in that: The adjustment and fixation require that after the beam body is hoisted and stabilized, the position and posture of the beam body must be changed according to the design requirements. This involves adjusting the position and length of the hanging point of the hanging basket to ensure the horizontality and verticality of the beam body. After completing the position and posture adjustment, the beam body is fixed, and the beam body is connected to the hanging basket using steel cables, bolts, etc., and the position and posture of the beam body are adjusted to make it completely consistent with the design requirements.

9. The method for constructing a bridge based on a diamond hanging basket according to claim 1, characterized in that:The safety inspection requires testing the beam being hoisted, including checking whether there are cracks or deformations on the surface of the beam, and whether the connection parts are firm, the safety of the hoisting site and surrounding areas, including the status of the hoisting equipment, the stability of the work platform, and the integrity of the temporary support structure, to ensure that there are no safety hazards, confirm that the personnel at the hoisting site have been evacuated to a safe area, and conduct a status inspection of the hoisting equipment.

10. The method for constructing a bridge based on a diamond hanging basket according to claim 1, characterized in that: The dismantling of the hanging basket includes the dismantling of the rear lower beam platform. After the tensioning of the last suspended casting section is completed, the inner mold is first dismantled, and then the part of the beam platform is dismantled, followed by the dismantling of the bottom basket system. The bottom basket system drops about one meter, the slings are removed and replaced with steel strands anchored on the beam surface, and the entire bottom basket system is gradually lowered using an oil jack. Finally, the side formwork system is dismantled, and the guide sliding beam is replaced with steel strands anchored on the beam surface using pre-buried holes, and the entire side formwork system is gradually lowered using an oil jack. The bottom basket and the side formwork system are stabilized after being lowered to the ground or water surface, the beam surface anchoring is released, and an air cutting tool is used to disassemble the connection between the longitudinal and transverse beams and the disassembled side formwork system. If the bottom basket does not meet the conditions for stopping the ship when it is lowered to the water surface, a small boat can be used to approach the bottom basket, the bottom basket can be disassembled and moved to the bridge deck using a tower crane.