Unbalanced cantilever beam body dismantling construction process
Through the split-leg mode and lateral movement technology of the bridge erecting machine, the overall hoisting and dismantling of the unbalanced cantilever beam body is realized, which solves the problems of small construction site and railway trunk line restrictions, reduces construction risks and costs, and improves construction efficiency.
Patent Information
- Application Number
- CN202410821357.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-24
- Publication Date
- 2024-10-15
AI Technical Summary
When dismantling an unbalanced cantilevered T-beam using the existing technology, due to the busy railway line below and the small construction site, it is impossible to erect brackets or use a crane, resulting in construction difficulties and high risks.
A bridge erecting machine is used to hoist and dismantle the unbalanced cantilever beam as a whole. The split-leg mode of the bridge erecting machine is used to dismantle the unbalanced cantilever beam without erecting a disassembly bracket or using a crane. This is achieved by utilizing the lateral movement of the bridge erecting machine and the transportation of the gun truck. Direct lifting of T-beam.
It reduces interference to railway traffic, reduces construction risks and costs, improves construction progress, meets the lifting requirements of the cantilever beam body, and reduces the impact on the construction site and surrounding environment.
Smart Images

Figure CN118774048A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge construction, and in particular relates to a construction process for dismantling an unbalanced cantilever beam. Background Art
[0002] The overall lifting and dismantling of the unbalanced cantilever T-beam (anchor beam) is usually supported by the earth bull method or the bracket method, and then disassembled and lifted. When there is a busy railway trunk line under the beam, it is impossible to set up a bracket under the beam to dismantle the bridge. At the same time, when the construction site is small, it is also impossible to meet the lifting and rotation needs of the crane. Therefore, for this type of bridge beam that cannot be constructed by crane and is not convenient to set up a bracket below, it is necessary to develop a new unbalanced cantilever T-beam dismantling process. Summary of the invention
[0003] The present invention aims to solve at least one of the above technical problems existing in the prior art. To this end, the present invention provides a construction process for dismantling an unbalanced cantilever beam, which can dismantle the unbalanced cantilever beam without setting up a dismantling bracket or using a crane.
[0004] The unbalanced cantilever beam dismantling construction process according to an embodiment of the present invention includes:
[0005] First, prepare for construction;
[0006] Then, the cantilever beam body of the demolished span is disassembled, and a T beam is decomposed from one side of the cantilever beam body;
[0007] Then, a bridge erection machine is installed on the cantilever beam body. During installation, one leg of the bridge erection machine is placed on the bridge pier cap beam, and the other leg of the bridge erection machine is placed on the cantilever beam body, so that the decomposed T-beam is located between the legs on both sides, and then hoisting and dismantling are performed;
[0008] Afterwards, the bridge erecting machine is controlled to move horizontally, and then the next T-beam is hoisted and removed.
[0009] The unbalanced cantilever beam dismantling construction process according to the embodiment of the present invention has at least the following beneficial effects: the unbalanced cantilever beam dismantling construction process of the present invention, by setting the legs of the bridge erecting machine separately, so that one leg is supported on the bridge pier cap beam, and the other leg is supported on the cantilever beam body, so that the T beam to be dismantled is located between the two legs, and the disassembled T beam can be directly hoisted and dismantled by the bridge erecting machine, and can be transported away by the gun carriage equipped with the bridge erecting machine. Therefore, compared with the segmented cutting and hoisting of the earth bull method and the bracket method, the method of the present invention reduces the interference with the railway traffic below, does not need to stop the railway transportation, and does not need to set up brackets on the railway, reduces the construction risk, speeds up the construction progress, and reduces the construction cost. The split-leg mode of the bridge erecting machine can meet the hoisting requirements of the cantilever beam body. In addition, the bridge erecting machine with split legs is used to hoist and dismantle the T beam as a whole. The bridge erecting machine operates in a straight-in and straight-out mode, which can reduce the requirements for the construction site, overcome the influence of surrounding buildings and protected trees, and overcome the defects that the hoisting and rotation of the crane cannot be realized. Therefore, the present invention can dismantle the unbalanced cantilever beam body without setting up a dismantling bracket and using a crane.
[0010] According to some embodiments of the present invention, the construction preparation includes: conducting on-site verification according to the drawings of the cantilever beam body, determining the disassembly sequence of the cantilever beam body, and arranging the construction sequence.
[0011] According to some embodiments of the present invention, when dismantling the cantilever beam body, the diaphragm of the cantilever beam body is firstly supported by padding, and then the bridge deck is dismantled and connected and reinforced, and then the diaphragm is dismantled.
[0012] According to some embodiments of the present invention, when dismantling the bridge deck, a temporary slag barrier is firstly provided at the side of the cantilever beam body, and then the asphalt layer of the bridge deck is chiseled off, and then cutting is performed from the beam seam position of the cantilever beam body.
[0013] According to some embodiments of the present invention, when the bridge deck is connected and reinforced, a combination of channel steel and chemical bolts is used for connection, and the combination is removed when the bridge erection machine is hoisted.
[0014] According to some embodiments of the present invention, when dismantling the diaphragm, the concrete diaphragm is cut by a rope saw, and the steel plate diaphragm is cut by oxygen cutting.
[0015] According to some embodiments of the present invention, when lifting and dismantling are performed, the lifting equipment is first installed. After the lifting equipment is installed and the beams are tied, a trial lifting is performed first, and then the T-beam is lifted onto the beam transport vehicle.
[0016] According to some embodiments of the present invention, during lifting and dismantling, the center of gravity of the T-beam is kept coincident with the center of gravity of the shoulder beam of the bridge erecting machine.
[0017] According to some embodiments of the present invention, both side legs of the bridge-building machine are provided with transverse tracks. During transverse movement, the legs on both sides are controlled to be alternately in a stressed and empty state, and the transverse tracks at the bottom of the legs in the empty state are adjusted. After the two transverse guide rails are adjusted to the position to be moved transversely, the two legs are controlled to move on the transverse tracks.
[0018] According to some embodiments of the present invention, the leg comprises:
[0019] A column, wherein a plurality of latch holes are arranged on the column in the vertical direction, and the column can be matched with the bridge erecting machine through the latch holes to be moved up and down for adjustment;
[0020] The transverse wheel box is arranged at the bottom of the column.
[0021] Additional aspects and advantages of the present invention will be given in part in the following description, and some additional aspects and advantages will become obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] The present invention will be further described below with reference to the accompanying drawings and embodiments, wherein:
[0023] Figure 1 This is a schematic diagram of an application of a bridge erecting machine;
[0024] Figure 2 It is a schematic diagram of the overall structure of a bridge erecting machine;
[0025] Figure 3 A schematic diagram of a connection between the front wheel box of the bridge erecting machine and the transverse track;
[0026] Figure 4 A schematic diagram of the position relationship between the second beam and the supporting legs of the bridge erecting machine;
[0027] Figure 5 A schematic diagram of a process of the present invention;
[0028] Figure 6 A schematic diagram of a cantilever beam. DETAILED DESCRIPTION
[0029] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0030] In the description of the present invention, it should be understood that descriptions involving orientation, such as orientation or positional relationship indicated as up, down, etc., are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0031] In the description of the present invention, "a plurality" means more than two. If there is a description of "first" or "second", it is only used for the purpose of distinguishing technical features, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.
[0032] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0033] Reference Figure 6 The unbalanced cantilever T-beam (anchor beam) is usually lifted and dismantled by supporting it with a clay bull method or a bracket method, and then disassembled and lifted. When there is a busy railway trunk line under the beam, it is impossible to set up a bracket under the beam to dismantle the bridge. At the same time, when the construction site is small, it is also impossible to meet the lifting and rotation needs of the crane. Therefore, for this type of bridge beam that cannot be constructed by crane and is not convenient to set up a bracket below, it is necessary to develop a new unbalanced cantilever T-beam removal process.
[0034] To this end, the present invention provides a construction process for dismantling an unbalanced cantilever beam, which can dismantle the unbalanced cantilever beam without setting up a dismantling bracket or using a crane.
[0035] Reference Figure 5 A construction process for dismantling an unbalanced cantilever beam according to an embodiment of the present invention mainly includes the following steps: firstly preparing for construction; then dismantling the cantilever beam of the dismantled span, and decomposing a T-beam from one side of the cantilever beam; then installing a bridge erecting machine on the cantilever beam. During installation, one side leg of the bridge erecting machine is placed on the pier cap beam, and the other side leg of the bridge erecting machine is placed on the cantilever beam, so that the decomposed T-beam is located between the two side legs, and then hoisting and dismantling the T-beam; then controlling the bridge erecting machine to move horizontally, and then hoisting and dismantling the next T-beam.
[0036] It can be understood that the unbalanced cantilever beam dismantling construction process in the present invention is to separate the legs of the bridge erecting machine so that one leg is supported on the bridge pier cap beam and the other leg is supported on the cantilever beam body, so that the T beam to be dismantled is located between the two legs, and the disassembled T beam can be directly hoisted and dismantled by the bridge erecting machine, and can be transported away by the gun carriage equipped with the bridge erecting machine. Therefore, compared with the segmented cutting and hoisting of the earth bull method and the bracket method, the method of the present invention reduces the interference with the railway traffic below, does not need to stop the railway transportation, and does not need to set up brackets on the railway, reduces the construction risk, speeds up the construction progress, and reduces the construction cost. The split-leg mode of the bridge erecting machine can meet the hoisting requirements of the cantilever beam body. And the bridge erecting machine with split legs is used to hoist and dismantle the T beam as a whole. The bridge erecting machine operates in a straight-in and straight-out mode, which can reduce the requirements for the construction site, overcome the influence of surrounding buildings and protected trees, and overcome the defects that the hoisting and rotation of the crane cannot be realized. Therefore, the present invention can dismantle the unbalanced cantilever beam body without setting up a disassembly bracket or using a crane.
[0037] In some embodiments of the present invention, construction preparation mainly includes on-site verification according to the drawings of the cantilever beam body, determining the order of dismantling the cantilever beam body, and arranging the construction sequence. Specifically, it includes being familiar with the drawings of the old bridge and the project construction plan, and verifying the structure of the cantilever beam body on-site according to the drawings, such as the position of the diaphragm, the position of the wet joint of the beam body, the thickness of the leveling layer, the type of support, and the order of dismantling the beam body. In addition, the materials required for the construction are purchased in advance, and the construction sequence is reasonably arranged according to the blockade point plan approved by the project. In addition, when there is eccentricity in the cantilever beam body, a sling is designed, and a sling is selected for hoisting, and the sling is pre-tightened in advance after entering the site. The bridge erection machine is assembled and inspected after entering the site, and a 120t prefabricated box girder is selected for trial lifting by the bridge erection machine to check the performance of the bridge erection machine.
[0038] In some embodiments of the present invention, when dismantling the cantilever beam, the diaphragm of the cantilever beam is first supported by padding, and then the bridge deck is dismantled and connected and reinforced, and then the diaphragm is dismantled, thereby avoiding the instability of the cantilever beam structure due to dismantling.
[0039] Since the height of the cantilever beam to the ground is generally several meters to more than ten meters, when supporting the pad, a double-row portal frame is first set up next to the pier as a manual operation platform. The portal frame and the pier are connected and fixed with a frame pipe clamp, and then a 50cm long sleeper is set on the manual operation platform, and then tightened with a wooden tip. During the padding process, a position for disassembly and cutting is reserved. Of course, a buckle bracket can also be used to set up a construction platform. For the axillary position of the top plate of the side beam, a seamless steel pipe with a diameter of Φ108mm and a wall thickness of 5mm is used for support. The support angle is about 45-60 degrees, and the length is determined according to the actual situation on site. The 10# equal-angle steel with a length of 25cm and a thickness of 1cm is anchored on the pier cap beam as a reinforced support pad, which also plays an anti-slip limiter role. Bolt holes are opened on the angle steel, and Φ20mm chemical bolts are used to anchor it on the pier cap beam, and the anchoring depth is not less than 150mm.
[0040] In some embodiments of the present invention, when dismantling the bridge deck, first set a temporary slag barrier at the side of the cantilever beam body, then chisel off the asphalt layer of the bridge deck, and then cut from the beam seam of the cantilever beam body. Since the common structure of the cantilever beam body is a reinforced concrete structure, and an asphalt layer is laid on the upper end, in order to reduce the weight of the cantilever beam body, the asphalt layer is first chiseled off to facilitate subsequent lifting. The temporary slag barrier adopts a 50cm high plywood fixed at the edge of the cantilever beam body to prevent asphalt slag from falling into the traffic artery below. When chiseling, the nearby construction site is manually chiseled with a pneumatic pick, and the chiseled waste slag is promptly transported out of the beam surface with a wheelbarrow. When cutting the beam surface, find the beam seam position from the expansion joint or the beam end position, pop up an ink line along the beam seam as the cutting line, and mark the position of the contact network under the bridge with paint. The dismantling mainly adopts rope cutting, and coiling to assist cutting. The wire saw uses a diamond wire saw, and the cutting direction is identified and controlled in the following way: there is a clear arrow mark on each clip of the diamond wire saw, and it can also be identified by the beads of the diamond wire saw itself. The long part of the bead base is the tail, and the short part is the front end, so the short front end is the cutting direction of the diamond wire saw. During use, the direction of the wire saw must be correctly distinguished, and it must move forward in the direction of the arrow, and it cannot be cut in the opposite direction.
[0041] In addition, in order to prevent concrete blocks from falling into the railway trunk line during the disintegration of the bridge, protective measures were taken for the railway equipment, including protection of railway ground equipment through reinforcement and covering with steel plates and sandbags, and protection of railway contact network circuits by wrapping pre-twisted wires.
[0042] After the beam is cut, temporary reinforcement is performed to prevent the cantilever beam from becoming unstable. Specifically, in some embodiments of the present invention, when the bridge deck is connected and reinforced, a combination of channel steel and chemical bolts is used for connection, and the connection is removed when the bridge erection machine is hoisted. Specifically, along the length of the T beam, a temporary reinforcement is set every 4 meters, and the temporary reinforcement uses a plum blossom-shaped channel steel, and the channel steel is 16 channel steel, channel steel length 1m, use impact drill to drill holes on the beam surface, and clean the dust in the hole with a small air pump in time after drilling. The channel steel is anchored with Ф20mm chemical bolts, and the anchoring depth of the chemical bolts is not less than 20cm.
[0043] Since the diaphragms of the cantilever beam body are usually arranged in two forms, one is a concrete diaphragm and the other is a steel plate diaphragm, in some embodiments of the present invention, when the diaphragms are dismantled, the concrete diaphragms are cut by a rope saw and the steel plate diaphragms are cut by oxygen cutting.
[0044] The dismantling process of the concrete diaphragm is as follows: diaphragm position setting → diamond rope working hole construction → mechanical fixing → diamond rope threading → cutting → inspection and confirmation. After the rope saw cuts and blocks the key points, use a water drill to drill holes 50cm on both sides of the diaphragm, place the sawing machine next to the beam (diaphragm), and connect the saw rope around the beam (diaphragm) to the active drive wheel for cutting. During the cutting process, the sawing machine should move away from the beam (diaphragm) until the cutting is completed.
[0045] The dismantling process of the steel plate diaphragm is as follows: diaphragm position setting and positioning → elevator working hole construction → elevator hanging working basket → cutting → inspection and confirmation. For the diaphragm cut by oxygen cutting, use a water-grinding drill to drill holes on the left and right sides of the diaphragm, manually carry the processed hanging basket to the bottom of the diaphragm, fix the hoist at the drilling hole on the bridge deck, and lower the hoist wire rope from the drilling hole to the hanging basket position. The oxygen cutting operator rides the hanging basket and uses the hoist to rise to the diaphragm for oxygen cutting. To prevent the hanging basket from swinging, two people below use the cable wind rope to tension in opposite directions. During the lifting process, the oxygen cutter needs to wear a safety helmet and squat in the hanging basket, holding the handrail of the hanging basket with both hands. Sparks fly during oxygen cutting. The oxygen cutter needs to wear protective goggles and protective clothing, and spread fireproof cloth on the contact net. After oxygen cutting, knock the molten iron on the steel plate in time, and see light on the opposite side with the naked eye.
[0046] In some embodiments of the present invention, when lifting and dismantling are performed, the lifting equipment is first installed. After the lifting equipment is installed and the beams are tied, a trial lifting is performed first, and then the T-beam is lifted onto the beam transport vehicle.
[0047] When installing the sling, the sling is manually lifted to the corresponding position of the lifting point under the bridge in the blockade point, and two 20mm hemp ropes are lowered through the lifting holes on the bridge deck and tied to the rope holes of the sling. Then the hemp ropes are manually lifted on the bridge deck to lift the sling to the bottom of the beam and tied to the beam body as a whole. Sacks are laid between the sling and the bottom of the beam to increase the friction between the sling and the bottom of the beam; before installing the sling, the size of the bottom of the beam is checked to ensure that the sling can be installed smoothly, and the uneven surface of the bottom of the T-beam is chiseled off in advance; and when the sling is fixed, the ropes tied to the sling cannot affect the beam binding.
[0048] The hoist is customized according to the center of gravity of the T-beam. By establishing a beam model, the center of gravity of the beam is calculated for the three parts of the cantilever anchor beam standard section, the variable section section, and the cantilever anchor beam head cast-in-place section. The final center of gravity of the beam is calculated by weighted average. After the center of gravity of the beam is determined, the hoist is customized according to the eccentric size to ensure that the center line of the bridge erection machine shoulder beam coincides with the center of gravity of the beam. Another function of the hoist is to prevent the sling from sliding during the lifting process of the beam. Semicircular lifting holes are punched on the wing plate of the beam, and the lifting ring is anchored to prevent the sling from moving forward and backward. According to the size of the bridge erection machine shoulder pole, the angle between the top plate of the beam and the sling after the beam is tied is not greater than 60°.
[0049] Note when tying beams:
[0050] 1. Use a water drill to drill the lifting hole at the lifting point in advance. The size of the lifting hole is 20X50cm, and use a grinding wheel to grind the hole wall smooth;
[0051] 2. The lifting rope must be stuck in the rope groove of the lifting equipment;
[0052] 3. Use two sleepers to plug the shoulder pole and beam surface tightly;
[0053] 4. Because the beam surface is narrow, ensure that there is an acute angle between the lifting rope and the beam surface, and anchor 2cm thick steel plate and weld round steel on the beam surface as much as possible as a lifting hole;
[0054] 5. The center of gravity of the bridge erecting machine shoulder pole beam and the center of gravity of the T beam are coincident, and the deviation is controlled within 5mm. The on-site technicians will check with a plumb bob;
[0055] 6. The shoulder beam of the bridge erection machine must be horizontal to ensure that the length of the lifting rope is consistent.
[0056] In one embodiment, the beam body is hoisted with Dyneema ropes. Dyneema ropes and Dyneema slings have more advantages than steel wire ropes: ① High strength: more than 10 times stronger than high-quality steel; ② High modulus: second only to special-grade carbon fiber; ③ Low density: less than water and can float on the water; ④ The physical properties of high-strength and high-modulus polyethylene fibers are very good; due to the high crystallinity and chemical groups that are not easy to react with chemical agents, they are resistant to water, moisture, chemical corrosion, ultraviolet radiation, and wear, and are soft and easy to construct. The slings installed at the bottom of the beam during the hoisting process also have the function of reducing the concentrated stress on the rope during hoisting.
[0057] During the trial lifting, first check the pre-tightening of the sling and verify whether the left and right lengths of the sling are symmetrical to the center of gravity of the beam (the maximum deviation shall not exceed 1cm), and plug the end of the shoulder pole beam and the beam surface with a wooden block. Before the trial lifting, since the bridge pier may have rusted, it is necessary to use a 100t oil jack to assist the bridge erection machine to lift the beam. The oil jack is placed on the web of the bottom of the beam at the bridge pier support, and a 1cm thick steel plate is placed between the oil jack and the web of the beam to prevent the web of the beam from being damaged. After all the preparations are completed, start to lift the beam. When the beam is lifted by 1cm, stop the oil jack and slowly lift the beam with the bridge erection machine. First, lift the beam 5 to 20cm and then stop lifting, and check the stability of the bridge erection machine, the reliability of the braking device, the balance of the beam and the firmness of the binding. Only after confirmation can the lifting continue. The lifted beam shall not be stagnant in the air for a long time. It can be understood that the beam in this paragraph refers to the decomposed T beam.
[0058] After the trial lifting is completed, the lifting is coordinated again, and the lifting speed should be steady and slow. The lifting of the T-beam is completed in two steps, following the principle of low-displacement beams. In the first step, the beam is lifted as a whole, so that the bottom of the abutment end beam exceeds the top surface of the abutment back wall, and the crane of the bridge erection machine begins to move longitudinally synchronously, so that the T-beam passes through the front legs of the bridge erection machine. In the second step, the T-beam is lifted as a whole again, ensuring that the bottom of the beam and the beam transport vehicle are at the same height, and the crane begins to move longitudinally synchronously again to transport the T-beam to the beam feeding area.
[0059] The gun carriage is driven to the beam feeding area in advance. When the rear carriage of the bridge erecting machine lifts the beam to the beam dropping position in front of the gun carriage, the front and rear carriages are slightly adjusted synchronously to make the T beam above the center line of the gun carriage. The rear carriage slowly drops the T beam onto the gun carriage, and diagonal braces are opened in time at the armpits on both sides of the T beam. The T beam and the gun carriage are tied together with wire ropes, and the wire ropes are tightened by hand winches. The front gun carriage and the front carriage move forward synchronously, keeping the speed consistent and even. When the front carriage reaches directly above the rear gun carriage, it starts to drop the beam, using the same method as the rear carriage.
[0060] Considering that the traditional bridge erection machine is used to erect bridges, and the present scheme is for dismantling bridges, there must be a height difference between the two sides of the front legs of the bridge erection machine. To this end, in some embodiments of the present invention, a modified bridge erection machine is proposed, comprising a main beam 100, front legs, middle legs, rear legs, a crane and a transverse track 300, wherein the front legs, middle legs and rear legs are respectively arranged below the front end, middle position and rear end of the main beam 100, for supporting the main beam 100. The crane is adjustable and arranged on the main beam 100 along the longitudinal movement of the main beam 100, for lifting the beam body and moving it along the length direction (i.e. longitudinal direction) of the main beam 100. The transverse track 300 is arranged at the bottom of the middle legs and the front legs, for supporting the middle legs and the front legs so that they can move laterally.
[0061] Among them, the front support leg includes two independently arranged support legs 200, the two support legs 200 are distributed side by side along the length direction of the transverse track 300, a transverse track 300 is arranged at the bottom of each support leg 200, and the support legs 200 can be raised and lowered and adjusted.
[0062] Since the middle leg and the rear leg of the bridge-building machine can be installed on the bridge deck, while the front leg is installed on the pier, when there is a height difference between the left and right piers, the traditional bridge-building machine cannot be erected and moved laterally. The bridge-building machine in the present invention has two independent support legs 200 on the front leg. The two support legs 200 can be independently raised and lowered to adapt to the erection situation of the left and right height difference, and a transverse track 300 is separately provided at the bottom of each support leg 200. Therefore, it can also move laterally when there is a height difference between the left and right piers, thereby solving the shortcomings of the prior art.
[0063] Reference Figure 2 In some embodiments of the present invention, each support leg 200 includes an upper support 201, a column, a lower support 203 and a front wheel box 204, wherein the upper support 201 is connected to the bottom of the main beam 100, the column is connected to the upper support 201 in an adjustable manner, the lower support 203 is connected to the bottom of the column, and the front wheel box 204 is arranged at the bottom of the lower support 203. With the structural arrangement of this embodiment, during installation, it is only necessary to install a support leg 200 on the corresponding pier according to the height difference between the left and right piers, and use the column to adjust up and down relative to the upper support 201 to adapt the height of the pier, so as to ensure that the two support legs 200 stably support the main beam 100 and ensure the levelness of the main beam 100. For example, when the left pier is higher than the right pier, the column on the left pier is adjusted to move upward relative to the upper support 201, reducing the distance between the upper support 201 and the lower support 203, thereby reducing the support height of the upper support 201 to be at the same level as the upper support 201 of the support leg 200 on the right pier. Of course, it is not limited to the case of pier height difference, and one support leg 200 can also be supported on the pier and the other support leg 200 can be supported on the bridge deck. In any case where there is a height difference, the structural setting of this embodiment can be considered.
[0064] Reference Figure 2 In some embodiments of the present invention, the column is provided with a plurality of latch holes 2021 in the vertical direction, and the upper support 201 is provided with a latch assembly matching the latch holes 2021. In some scenarios, the height difference between the left and right sides is as high as several meters. The structural setting of this embodiment is adopted, and the latch holes 2021 are used in conjunction with the latch assembly to realize the locking and adjustment between the upper support 201 and the column. The structure is simple, which is conducive to controlling the equipment cost, and the locking is reliable and the stability is good. It is understandable that a hydraulic telescopic structure can also be used to adjust the column up and down.
[0065] Reference Figure 2 and Figure 4 In some embodiments of the present invention, the column includes two groups of I-beams 202 arranged side by side, the web of the I-beam 202 is provided with a latch hole 2021, the lower end of the I-beam 202 is connected to the upper end surface of the lower support 203, and the upper support 201 is provided with a card interface for the I-beam 202 to pass through on both sides, and the upper support 201 is provided with a latch plate on both sides of the card interface, and the latch assembly is installed on the corresponding two latch plates. The I-beam 202 passes through the card interface, and is locked by inserting the latch hole 2021 through the latch on the latch plate at a suitable height. After the latch is inserted into the latch hole 2021, it passes through the latch plate on the other side and is locked with a nut. The structural setting of this embodiment can effectively ensure the support strength of the column and facilitate adjustment.
[0066] Reference Figure 2 In some embodiments of the present invention, the main beam 100 includes a first beam body 101 and a second beam body 102, the first beam body 101 and the second beam body 102 are respectively located directly above the two supporting legs 200, and the two groups of I-beams 202 of each column are located on both sides of the first beam body 101 and the second beam body 102, and are used to move upward from both sides of the first beam body 101 and the second beam body 102 when adjusting upward. With the structural arrangement of this embodiment, since the first beam body 101 and the second beam body 102 are located directly above the two columns, it is helpful to ensure that the center of gravity of the first beam body 101, the second beam body 102 and the column are located in the same vertical plane, which is helpful to ensure the stability of the support. At the same time, when the column is adjusted upward, the I-beam 202 moves upward close to both sides of the first beam body 101 and the second beam body 102, which is helpful to ensure the overall stability during the adjustment process and the stability of the support after the adjustment.
[0067] Reference Figure 2 An upper crossbeam 103 and a lower crossbeam 104 are also provided between the first beam body 101 and the second beam body 102. The upper crossbeam 103 and the lower crossbeam 104 are used to connect the first beam body 101 and the second beam body 102 into a whole. To avoid interference, the support leg 200 is staggered with the upper crossbeam 103 and the lower crossbeam 104.
[0068] Reference Figure 2 and Figure 4 In some embodiments of the present invention, a tie rod 206 is provided between the two support legs 200, and the tie rod 206 is detachably connected to the latch hole 2021. With the structural setting of this embodiment, the overall strength between the two support legs 200 can be improved by the tie rod 206. In addition, the tie rod 206 is installed by using the latch hole 2021 on the column, which can simplify the structural setting and ensure the stability of the connection.
[0069] Since the main beam 100 cannot move laterally during the construction process, in some embodiments of the present invention, a locking mechanism is detachably provided at the end of the transverse track 300, and a locking seat for connecting the locking mechanism is provided on the side of the front wheel box 204. The transverse track 300 is usually fixed with anchor bolts, that is, the transverse track 300 remains fixed and does not move under normal conditions, so it is only necessary to keep the front wheel box 204 and the transverse track 300 fixed. With the structural setting of this embodiment, the locking mechanism can be used in conjunction with the locking seat to lock the front wheel box 204 so that it is fixed on the transverse track 300.
[0070] Furthermore, rubber plates are provided on both sides of the front wheel box 204 along its own moving direction, and the rubber plates abut against the transverse track 300 to clean foreign objects on the transverse track 300 to avoid derailment.
[0071] Specifically, refer to Figure 3 and Figure 4 The locking mechanism includes a limit plate 303 and a swing arm 302, wherein the limit plate 303 is installed at the end of the transverse track 300 and partially protrudes upward, thereby blocking the front wheel box 204 from moving out at the end of the transverse track 300. The swing arm 302 is rotatably installed on the upper end of the limit plate 303, and a bolt pin is provided at the end of the swing arm 302. The locking seat is arranged on the side of the front wheel box 204, and a locking hole for the bolt pin to pass through is opened. When the front wheel box 204 moves to abut the limit plate 303, the swing arm 302 is rotated to abut the side wall of the front wheel box 204, and the locking seat can be automatically aligned, and then the bolt pin is passed through the locking hole, and the front wheel box 204 can be fixed by locking with a nut to prevent it from falling off. When the front wheel box 204 needs to be moved and moved laterally, the locking mechanism is also easy to disassemble.
[0072] Reference Figure 3 In some embodiments of the present invention, the transverse track 300 is formed by two track units 301 that are detachably spliced together, a splicing structure is provided at the end of the track unit 301, and a locking mechanism is detachably connected to the splicing structure. In this way, there is no need to specially provide a mounting structure for the locking mechanism at the end of the track unit 301, and the locking mechanism can be directly installed by using the splicing structure, which helps to reduce equipment costs and improve splicing efficiency. Specifically, the track unit 301 includes track steel and end panels provided at both ends of the track steel. Four mounting holes are provided on the end panels. The two track units 301 can be connected to each other through the end panels and then locked by bolts provided through the mounting holes. The locking mechanism is also installed in the form of a structure in which bolts are provided through the mounting holes.
[0073] Reference Figure 2In some embodiments of the present invention, a hydraulic lifting mechanism 400 is provided between the main beam 100 and the upper support 201. Since the support legs 200 only play a supporting role, during the operation of the bridge erection machine, the lifting of the main beam 100 and the lifting and leveling of a single support leg 200 are also involved. With the structural setting of this embodiment, the hydraulic lifting mechanism 400 can be used to achieve the above-mentioned operation adjustment. The hydraulic lifting mechanism 400 can use a hydraulic cylinder as a driving member.
[0074] Reference Figure 2 In some embodiments of the present invention, the front support leg further includes a transverse connecting rod 205, which is disposed at the lower end of the main beam 100 and connects the two support legs 200. With the structural arrangement of this embodiment, the transverse connecting rod 205 is used to connect the two support legs 200, that is, to connect the I-beam 202 of each support leg 200, so as to improve the stability of the support legs 200. Specifically, the transverse connecting rod 205 is also installed and connected through the pin hole 2021 on the I-beam 202.
[0075] Reference Figures 1 to 4 In some embodiments of the present invention, the bridge erecting machine includes a main beam 100, a front leg, a middle leg, a rear leg, a crane and a transverse track 300. The main beam 100 is provided with a first beam body 101 and a second beam body 102 along the length direction, and a plurality of upper beams 103 are connected between the upper ends of the first beam body 101 and the second beam body 102, and a plurality of lower beams 104 are connected between the lower ends. The crane is installed on the first beam body 101 and the second beam body 102, and can be moved and adjusted along the length direction thereof. It is understandable that one or more cranes can be provided as needed. The front leg, the middle leg and the rear leg are correspondingly arranged at the front end, the middle position and the rear end of the main beam 100, for supporting the main beam 100. Among them, the front leg includes a horizontal connecting rod 205 and two supporting legs 200, and the horizontal connecting rod 205 is fixed to the first beam body 101 and the second beam body 102 by bolts, and the two ends extend outward. The two support legs 200 are respectively located below the first beam body 101 and the second beam body 102 and connected to the horizontal connecting rod 205. The support legs 200 include an upper support 201, a lower support 203, two groups of I-beam beams 202, and a front wheel box 204. The upper end of the upper support 201 is connected to the main beam 100 through a hydraulic jacking mechanism 400. The two groups of I-beam beams 202 are located on both sides of the upper support 201, and the webs of the I-beam beams 202 are provided with a plurality of latch holes 2021 in the vertical direction. The lower support 203 is fixed to the lower ends of the two groups of I-beam beams 202. The upper support 201 is connected and fixed to the I-beam beam 202 by installing a latch assembly through the latch holes 2021. The upper end of the front wheel box 204 is connected and fixed to the bottom of the lower support 203 through a hinge structure. There are multiple sets of transverse tracks 300 , one of which is arranged at the bottom of the middle support leg, and the other is arranged at the bottom of the front wheel boxes 204 of the two support legs 200 .
[0076] With the structural setting of this embodiment, two supporting legs 200 are provided on the front legs. When there is a height difference in the lateral direction, a single supporting leg 200 can be adjusted so that the front legs match the height difference between the left and right sides, thereby providing stable support for the main beam 100 .
[0077] In some embodiments of the present invention, when the front support leg 200 moves laterally, the two support legs are controlled to be alternately in a state of force and release, and the transverse track at the bottom of the support leg in the release state is adjusted. After the two transverse guide rails are adjusted to the position to be moved laterally, the two support legs are controlled to move on the transverse track.
[0078] In some embodiments of the present invention, the unbalanced cantilever beam dismantling construction process adopts a special bridge erecting machine for dismantling, and the bridge erecting machine includes a main beam 100, a front leg, a middle leg, a rear leg, a front crane, a rear crane and a transverse track 300. The main beam 100 is provided with a first beam body 101 and a second beam body 102 along the length direction, and a plurality of upper beams 103 are connected between the upper ends of the first beam body 101 and the second beam body 102, and a plurality of lower beams 104 are connected between the lower ends. The front and rear cranes are installed on the first beam body 101 and the second beam body 102, and can be moved and adjusted along the length direction thereof. The front leg, the middle leg and the rear leg are correspondingly arranged at the front end, the middle position and the rear end of the main beam 100, and are used to support the main beam 100. The front leg includes a horizontal connecting rod 205 and two supporting legs 200, and the horizontal connecting rod 205 is fixed to the first beam body 101 and the second beam body 102 by bolts, and the two ends extend outward. The two support legs 200 are respectively located below the first beam body 101 and the second beam body 102 and connected to the horizontal connecting rod 205. The support legs 200 include an upper support 201, a lower support 203, two groups of I-beam beams 202, and a front wheel box 204. The upper end of the upper support 201 is connected to the main beam 100 through a hydraulic jacking mechanism 400. The two groups of I-beam beams 202 are located on both sides of the upper support 201, and the webs of the I-beam beams 202 are provided with a plurality of latch holes 2021 in the vertical direction. The lower support 203 is fixed to the lower ends of the two groups of I-beam beams 202. The upper support 201 is connected and fixed to the I-beam beam 202 by installing a latch assembly through the latch holes 2021. The upper end of the front wheel box 204 is connected and fixed to the bottom of the lower support 203 through a hinge structure. There are multiple sets of transverse tracks 300 , one of which is arranged at the bottom of the middle support leg, and the other is arranged at the bottom of the front wheel boxes 204 of the two support legs 200 .
[0079] Reference Figure 5 The unbalanced cantilever beam dismantling construction process of the present invention comprises:
[0080] S001 Construction preparation: Conduct on-site verification according to the drawings of the cantilever beam, determine the dismantling sequence of the cantilever beam, and arrange the construction sequence;
[0081] S002 diaphragm pad support;
[0082] S003 beam surface dismantling: first chisel off the asphalt layer, then cut along the beam seam with a rope, and use a coil to assist in cutting;
[0083] S004 Beam surface connection reinforcement: set a connection at a set distance along the length of the cantilever beam to prevent instability;
[0084] S005 diaphragm disassembly: Cutting by wire saw or oxygen cutting to separate the T beam;
[0085] S006 Installation of lifting equipment: According to the center of gravity and eccentricity of the T-beam, the lifting equipment is designed so that the symmetry center of the lifting ropes on both sides coincides with the center of gravity of the T-beam during lifting;
[0086] S007 beam tying: connect and fix the sling with the front and rear cranes of the bridge erecting machine through the sling rope; the installation of the bridge erecting machine can be carried out after the completion of step S002; when installing the bridge erecting machine, one of the two supporting legs 200 of the front legs is supported on the bridge pier cap beam, and the other is supported on the beam surface of the cantilever beam body, so that the T beam to be decomposed is between the two supporting legs 200; the rear legs and the middle legs are both set on the bridge deck adjacent to the span, so that the length direction of the bridge erecting machine is consistent with the length direction of the T beam;
[0087] S008 trial lifting: set up an oil jack under the T beam, and lift the T beam to a certain height in combination with the lifting of the bridge erection machine to observe the stability;
[0088] S009 Lifting the beam: After the trial lifting is completed, continue to lift the beam until the height of the T beam meets the longitudinal movement conditions, then move it longitudinally, then lift the T beam again until its height meets the docking height with the gun carriage, and move it longitudinally above the gun carriage again;
[0089] S010 Beam lowering: Use the front and rear cranes to lift the T-beam and place it on two gun carriages in turn;
[0090] S011 bridge erection machine transverse movement: first control one supporting leg to be stressed and the other supporting leg to be free, move the transverse movement track under the supporting leg in the free state, then repeat the operation to move the transverse movement track under the other supporting leg, then control the two supporting legs to be stressed, and move the middle supporting leg and the front supporting leg, so that the bridge erection machine moves to the top of the next T-beam;
[0091] S012 proceeds to dismantle the next beam.
[0092] It is understandable that when performing steps S002 to S005, either a single T-beam or all T-beams may be decomposed, and the arrangement may be flexible according to actual conditions.
[0093] The unbalanced cantilever beam dismantling construction process of the present invention has the following characteristics:
[0094] 1. The unbalanced cantilever beam is hoisted and removed as a whole by a special bridge-building machine. Compared with the earth-bull method and the bracket method, the segmented cutting and hoisting reduces the interference with railway traffic. There is no need to stop railway transportation or set up brackets on the railway, which reduces the construction risk, speeds up the construction progress, and reduces the construction cost. The front legs of the bridge-building machine are changed to the split-leg mode to meet the cantilever beam hoisting needs and meet the requirements of the bridge-building machine to move horizontally when there is a large height difference between the left and right sides.
[0095] 2. Use a special bridge-building machine for overall lifting and dismantling. The bridge-building machine can move in and out directly to reduce the requirements on the construction site and overcome the impact of surrounding buildings and protect trees.
[0096] 3. Stress analysis of the stability of the unbalanced cantilever beam hanging point, check the safety of the old bridge structure for the existing hanging point working conditions, use finite element analysis software to establish a finite element overall model for calculation and analysis, perform structural analysis according to the plane bar system, discretize the structure, establish the upper structure model, and simulate the boundary conditions at the hanging point according to the general support. Mainly analyze the beam cross-section stress, bending bearing capacity, shear bearing capacity, hanging point reaction analysis, and main beam displacement analysis. All parameters must meet the requirements of the specification for safe lifting.
[0097] 4. Method of using eccentric slings to adjust the lifting axis of unbalanced beams. In view of the characteristics of the asymmetric balanced structure of the side beam, 3D modeling is used to extract the center of gravity of the structure, and eccentric slings are designed for different weights. The symmetrical center of gravity is adjusted to be completely symmetrical on the left and right, so that the beam lifting forms a left-favorable situation, and the tilt of the beam caused by different rope lengths (the contraction of the Dyneema material rope is 7%-9%) can be avoided, which reduces the difficulty of quality control of the lifting work and improves the stability and safety of the lifting.
[0098] 5. In terms of energy saving and environmental protection, compared with large truck cranes and crawler cranes, it reduces mechanical operation noise and exhaust pollution, and compared with the earth bull method and the bracket method, it reduces the rope saw cutting area.
[0099] It is understandable that in the initial stage, the erection of the bridge-building machine can use the main piers on the side of the cantilever beam to assist the erection, ensuring the installation of the two supporting legs, and then gradually moving to the pier cap beam of the cantilever beam as the T-beam is lifted and removed.
[0100] The present invention has been described in detail above in conjunction with the embodiments, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of ordinary technicians in the relevant technical field without departing from the purpose of the present invention.
Claims
1. A construction process for dismantling an unbalanced cantilever beam, characterized in that: include: First, prepare for construction; Then, the cantilever beam body of the demolished span is disassembled, and a T beam is decomposed from one side of the cantilever beam body; Then, a bridge erection machine is installed on the cantilever beam body. During installation, one leg of the bridge erection machine is placed on the bridge pier cap beam, and the other leg of the bridge erection machine is placed on the cantilever beam body, so that the decomposed T-beam is located between the legs on both sides, and then hoisting and dismantling are performed; Afterwards, the bridge erecting machine is controlled to move horizontally, and then the next T-beam is hoisted and removed.
2. The unbalanced cantilever beam dismantling construction process according to claim 1 is characterized in that: The construction preparation includes: conducting on-site verification according to the drawings of the cantilever beam body, determining the dismantling sequence of the cantilever beam body, and arranging the construction sequence.
3. The unbalanced cantilever beam dismantling construction process according to claim 1 is characterized in that: When dismantling the cantilever beam body, the diaphragm of the cantilever beam body is firstly supported by padding, and then the bridge deck is dismantled and connected and reinforced, and then the diaphragm is dismantled.
4. The unbalanced cantilever beam dismantling construction process according to claim 3 is characterized in that: When dismantling the bridge deck, firstly, a temporary slag stop is set at the side of the cantilever beam body for protection, then the asphalt layer of the bridge deck is chiseled off, and then cutting is performed from the beam seam position of the cantilever beam body.
5. The unbalanced cantilever beam dismantling construction process according to claim 3 is characterized in that: When the bridge deck is connected and reinforced, a combination of channel steel and chemical bolts is used for connection, and the combination is removed when the bridge erection machine is hoisted.
6. The unbalanced cantilever beam dismantling construction process according to claim 3 is characterized in that: When dismantling the diaphragm, the concrete diaphragm is cut by a rope saw, and the steel plate diaphragm is cut by oxygen cutting.
7. The unbalanced cantilever beam dismantling construction process according to claim 1 is characterized in that: When lifting and dismantling, first install the lifting equipment. After installing the lifting equipment and tying the beams, conduct a trial lift and then lift the T-beam onto the beam transport vehicle.
8. The unbalanced cantilever beam dismantling construction process according to claim 7 is characterized in that: During hoisting and dismantling, the center of gravity of the T-beam is kept coincident with the center of gravity of the shoulder pole beam of the bridge erecting machine.
9. The unbalanced cantilever beam dismantling construction process according to claim 1 is characterized in that: The legs on both sides of the bridge-building machine are provided with transverse tracks. When moving laterally, the legs on both sides are controlled to be alternately in a stressed and empty state, and the transverse tracks at the bottom of the legs in the empty state are adjusted. After the two transverse guide rails are adjusted to the position to be moved laterally, the two legs are controlled to move on the transverse tracks.
10. The unbalanced cantilever beam dismantling construction process according to claim 1, characterized in that: The legs include: A column, wherein a plurality of latch holes are arranged on the column in the vertical direction, and the column can be matched with the bridge erecting machine through the latch holes to be moved up and down for adjustment; The transverse wheel box is arranged at the bottom of the column.