High-rise building construction accumulated water drainage device

By driving fixed pipes and electric telescopic rod assemblies via drones, the problem of pump clogging and worker inconvenience when water accumulates in foundation pits during high-rise building construction is solved, achieving efficient and convenient multi-point drainage effects.

CN118774154APending Publication Date: 2024-10-15YULIN UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410949370.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

During the construction of high-rise buildings, water accumulation in foundation pits causes blockage of water pipes when pumps pump water, making it difficult for workers to move and effectively drain multiple water accumulation points.

Method used

A water accumulation drainage device for high-rise building construction is designed. A drone is used to drive fixed pipes to move to multiple water accumulation points. Electric telescopic rods, filter components, return springs and other components are used to avoid blockage and improve pumping and drainage efficiency.

Benefits of technology

The drone can drive the fixed pipe to move to multiple water accumulation points, and the mud can be effectively filtered through the filter assembly and scraper rod to avoid clogging and improve drainage efficiency and convenience.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774154A_ABST
    Figure CN118774154A_ABST
Patent Text Reader

Abstract

The invention discloses a high-rise building construction accumulated water drainage device, and belongs to the technical field of construction drainage. The high-rise building construction accumulated water drainage device comprises a transport box, and box wheels are arranged on the periphery of the bottom of the transport box; a handle is arranged on the right side of the transport box, and a control box is arranged on the front side of the transport box. A pump machine is arranged in the transportation box, a hose is arranged on a water inlet of the pump machine, and a drainage pipe is arranged on a water outlet of the pump machine; a fixing pipe is connected to the hose, and a filtering assembly is arranged at the bottom of the fixing pipe; the two sides of the fixing pipe are connected with the containing assembly. And a fixing block on the unmanned aerial vehicle is fixedly connected with a fixing rod through a bolt, so that the unmanned aerial vehicle can drive a fixing pipe to move after flying out, then the fixing pipe can move to a plurality of water accumulation points of the foundation pit for water pumping and drainage, and the problem that after water accumulation in the foundation pit, workers are inconvenient to move, and water is inconvenient to drain the plurality of water accumulation points of the foundation pit is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction drainage, in particular to a high-rise building construction water accumulation drainage device. Background Art

[0002] The construction of high-rise buildings requires the excavation of foundation pits. When water accumulates in the foundation pits due to rainfall, water is generally pumped out by pumps. However, when the pumps are pumping water, the mud and ash produced during construction in the foundation pits are easily pumped into the water pipes, causing blockages. Moreover, after the foundation pits are flooded, workers are unable to move, which makes it too laborious to change the position of the water pipes during the pumping process, making it inconvenient to drain water from multiple waterlogged points in the foundation pits. For this reason, we propose a drainage device for water accumulation in high-rise building construction. Summary of the invention

[0003] The object of the present invention is to provide a high-rise building construction water drainage device to solve the problems raised in the above-mentioned background technology.

[0004] To achieve the above-mentioned object, the present invention provides the following technical solution: A high-rise building construction water drainage device, comprising a transport box, wherein box wheels are arranged around the bottom of the transport box; A handle is provided on the right side of the transport box, and a control box is provided on the front side of the transport box; A pump is arranged in the transport box, a hose is arranged on the water inlet of the pump, and a drain pipe is arranged on the water outlet of the pump; The hose is connected to a fixed pipe, and a filter assembly is arranged at the bottom of the fixed pipe; Both sides of the fixed tube are connected to the placement assembly; A fixing rod is arranged on the top of the fixing tube, and a moving assembly connected with the fixing rod is arranged on the transport box.

[0005] As a preferred solution of the high-rise building construction water drainage device described in the present invention, the filtering assembly includes a water pumping hood connected to the bottom of the fixed pipe, the bottom of the water pumping hood is fittedly connected with a mounting frame, and the mounting frame is provided with screws connected to the water pumping hood, the inner wall of the mounting frame is connected to a filter plate that penetrates the water pumping hood, and the bottom of the filter plate is located below the screws.

[0006] As a preferred solution of the high-rise building construction water drainage device described in the present invention, the placement component includes two groups of mounting rods with the same structure, the mounting rods on both sides are respectively arranged on both sides of the fixed pipe, and electric telescopic rods are arranged on the front and rear sides of the tops of the mounting rods on both sides, and the output end of the electric telescopic rod passes through the mounting rod and is connected to a connecting rod, and a support seat is arranged at the bottom of the connecting rod.

[0007] As a preferred solution of the high-rise building construction water drainage device described in the present invention, a guide rail is arranged at the bottom of the mounting rod, a screw rod assembly is arranged on the guide rail, and a vertical rod is slidably connected to the guide rail, the screw rod assembly is connected to the vertical rod, and the screw rod assembly is used to drive the vertical rod to move, a connecting rod is slidably connected to the vertical rod, a scraping rod in contact with the bottom of the filter plate is arranged between the opposite sides of the connecting rods, and a reset spring connected to the vertical rod is arranged in the connecting rod.

[0008] As a preferred solution of the high-rise building construction water drainage device described in the present invention, a cavity is arranged in the connecting rod, and the cavity is located below the reset spring, a float bag is arranged on the top inner wall of the cavity, and through holes communicating with the cavity are opened on opposite sides of the connecting rods on both sides.

[0009] As a preferred solution of the high-rise building construction water drainage device described in the present invention, baffle bars are provided on both sides of the water pumping hood, the baffle bars on both sides are respectively in contact with the connecting rods on both sides, and the baffle bars on both sides cover the through holes on both sides respectively.

[0010] As a preferred solution of the high-rise building construction water drainage device described in the present invention, the mobile component includes a top plate arranged on the top of the transport box, a drone is arranged on the top plate, a fixing block is arranged on the drone, and bolts are arranged on the fixing block, a slot matching a fixing rod is arranged at the bottom of the fixing block, and screw holes matching the bolts are arranged on the fixing rod, a box cover located on the outside of the drone is arranged on the top of the top plate, and a box cover is hinged on the top of the box cover.

[0011] As a preferred solution of the high-rise building construction water drainage device described in the present invention, drainage holes are evenly opened on the bottom of the transport box.

[0012] Compared with the prior art, the present invention has the following beneficial effects: 1. The fixed block on the drone is connected and fixed to the fixed rod by bolts, so that the drone can drive the fixed pipe to move after flying out, and then the fixed pipe can be moved to multiple water accumulation points in the foundation pit for drainage, which solves the problem that workers are inconvenient to move after water accumulation in the foundation pit, making it inconvenient to drain water from multiple water accumulation points in the foundation pit; 2. After the drone drives the fixed pipe to move into the accumulated water, the electric telescopic rods on all sides drive the supporting seats on all sides to contact the ground, so as to place the fixed pipe stably. Then, when the pump is turned on to drain water, the mud in the accumulated water is filtered through the filter component to avoid clogging the fixed pipe and then clogging the pump; 3. The vertical rod is driven to move back and forth in the guide rail through the screw rod assembly, so that the connecting rod drives the scraper rod to move back and forth at the bottom of the filter plate to scrape off the mud and ash covering the bottom of the filter plate to ensure the efficiency of drainage; 4. The elastic force of the reset spring keeps the scraper rod pressed upward against the filter plate to prevent the top of the scraper rod from being unable to fit the filter plate after being worn. When the vertical rod drives the connecting rod to move in the front-to-back direction, the connecting rod no longer contacts the blocking rod, and the through hole is no longer covered by the blocking rod, so that the accumulated water can enter the cavity through the through hole to generate buoyancy on the float bag, thereby further pushing the connecting rod upward, so that the scraper rod keeps fitting with the filter plate, thereby reducing the influence of waves on the height of the scraper rod when the scraper rod is moved back and forth in the water. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the overall structure of a high-rise building construction water drainage device according to the present invention; Figure 2 This is a schematic diagram of the internal structure of a transport box described in a high-rise building construction water drainage device of the present invention; Figure 3 This is a schematic diagram of the structure of the filtering component and the placing component of a high-rise building construction water drainage device according to the present invention; Figure 4 The present invention is a schematic diagram of the structure of a return spring, a float bag and a baffle rod described in a high-rise building construction water drainage device.

[0014] In the figure: 1. transport box; 2. box wheels; 3. handle; 4. control box; 5. pump; 6. hose; 7. fixing pipe; 8. water extraction hood; 9. installation frame; 10. screw; 11. filter plate; 12. installation rod; 13. electric telescopic rod; 14. connecting rod; 15. support seat; 16. fixing rod; 17. top plate; 18. drone; 19. fixing block; 20. bolt; 21. box cover; 22. box lid; 23. drainage hole; 24. guide rail; 25. screw assembly; 26. vertical rod; 27. connecting rod; 28. scraper rod; 29. ​​reset spring; 30. cavity; 31. through hole; 32. float bag; 33. stop rod. DETAILED DESCRIPTION

[0015] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0016] As mentioned in the background technology, in the prior art, when pumping water, the inside of the water pipe is easy to draw mud and ash generated during construction in the foundation pit, thus causing blockage. Moreover, after the foundation pit is flooded, workers are inconvenient to move, which makes it too laborious to change the position of the water pipe during the pumping process, making it inconvenient to drain the multiple water accumulation points in the foundation pit. The present invention proposes a high-rise building construction water drainage device.

[0017] Example 1 Reference Figures 1 to 4 , a high-rise building construction water drainage device, comprising a transport box 1, the bottom of the transport box 1 is provided with box wheels 2 around, to facilitate the movement of the transport box 1; A handle 3 is provided on the right side of the transport box 1 for workers to push, and a control box 4 is provided on the front side of the transport box 1 for controlling the electrical components in the text; A pump 5 is arranged in the transport box 1, a hose 6 is arranged on the water inlet of the pump 5, and a drain pipe is arranged on the water outlet of the pump 5; The hose 6 is connected to a fixed pipe 7, and a filter assembly is arranged at the bottom of the fixed pipe 7; Both sides of the fixed tube 7 are connected to the placement assembly; A fixing rod 16 is disposed on the top of the fixing tube 7 , and a moving component connected to the fixing rod 16 is disposed on the transport box 1 .

[0018] The filter assembly includes a water extraction hood 8 connected to the bottom of the fixed pipe 7, the bottom of the water extraction hood 8 is fittedly connected to a mounting frame 9, and the mounting frame 9 is provided with screws 10 connected to the water extraction hood 8, the inner wall of the mounting frame 9 is connected to a filter plate 11 which is mutually interpenetrating with the water extraction hood 8, and the bottom of the filter plate 11 is located below the screw 10. The filter plate 11 is located below the screw 10 to avoid the subsequent scraper rod 28 from contacting the screw 10 when scraping the bottom of the filter plate 11 back and forth, and filtering the mud in the accumulated water through the filter plate 11 to prevent the mud from entering the fixed pipe 7 and causing subsequent clogging of the pump 5.

[0019] The placement assembly includes two groups of mounting rods 12 with the same structure. The mounting rods 12 on both sides are respectively arranged on both sides of the fixed tube 7. Electric telescopic rods 13 are arranged on the front and rear sides of the tops of the mounting rods 12 on both sides, and the output ends of the electric telescopic rods 13 pass through the mounting rods 12 and are connected to connecting rods 14. A support seat 15 is arranged at the bottom of the connecting rod 14. The connecting rod 14 is driven to move downward by the electric telescopic rods 13 on all sides, so that the support seats 15 on all sides are in contact with the ground, so as to facilitate the stable placement of the fixed tube 7.

[0020] A guide rail 24 is provided at the bottom of the mounting rod 12, a screw assembly 25 is provided on the guide rail 24, and a vertical rod 26 is slidably connected to the guide rail 24, the screw assembly 25 is connected to the vertical rod 26, and the screw assembly 25 is used to drive the vertical rod 26 to move, and a connecting rod 27 is slidably connected to the vertical rod 26, and a scraper rod 28 in contact with the bottom of the filter plate 11 is provided between the opposite sides of the connecting rods 27 on both sides, and a return spring 29 connected to the vertical rod 26 is provided in the connecting rod 27, and the vertical rod 26 is driven by the screw assembly 25 to move in the guide rail. The rail 24 moves back and forth in the front-to-back direction, so that the connecting rod 27 drives the scraper rod 28 to move back and forth on the bottom of the filter plate 11, scraping off the mud and lime covering the bottom of the filter plate 11 to ensure the efficiency of drainage. When the scraper rod 28 contacts the bottom of the filter plate 11, the return spring 29 is in a stretched state. Therefore, the return spring 29 can use the return elastic force to cause the connecting rod 27 to be subjected to an upward force, thereby keeping the scraper rod 28 pressed upward against the filter plate 11 to prevent the top of the scraper rod 28 from being unable to fit the filter plate 11 after being worn.

[0021] A cavity 30 is provided in the connecting rod 27, and the cavity 30 is located below the reset spring 29. A float 32 is provided on the top inner wall of the cavity 30. Through holes 31 connected to the cavity 30 are provided on the opposite sides of the connecting rods 27 on both sides. When accumulated water enters the cavity 30 through the through holes 31, buoyancy can be generated on the float 32, thereby further pushing the connecting rod 27 upward, so that the scraper rod 28 maintains contact with the filter plate 11, thereby reducing the influence of water waves on the height of the scraper rod 28 when the scraper rod 28 is moved back and forth in the water.

[0022] Baffle rods 33 are provided on both sides of the water extraction hood 8, and the baffle rods 33 on both sides are respectively in contact with the connecting rods 27 on both sides, and the baffle rods 33 on both sides cover the through holes 31 on both sides respectively. When the vertical rod 26 drives the connecting rod 27 to move along the front and rear directions, the connecting rod 27 no longer contacts the baffle rods 33, and then the through hole 31 is no longer covered by the baffle rods 33, so that the accumulated water can enter the cavity 30 through the through hole 31 to generate buoyancy for the float bag 32. The reason for setting the baffle rods 33 is to avoid being affected by the buoyancy of the accumulated water on the float bag 32 when entering the accumulated water, so as to reduce the buoyancy obstacle when the drone 18 drives the fixed pipe 7 into the accumulated water.

[0023] The mobile component includes a top plate 17 arranged on the top of the transport box 1, a drone 18 is arranged on the top plate 17, a fixing block 19 is arranged on the drone 18, and a bolt 20 is arranged on the fixing block 19, a slot matching the fixing rod 16 is arranged at the bottom of the fixing block 19, and a screw hole matching the bolt 20 is arranged on the fixing rod 16, a box cover 21 located on the outside of the drone 18 is arranged on the top of the top plate 17, and a box cover 22 is hinged on the top of the box cover 21. The box cover 22 is opened, the fixing block 19 on the drone 18 is put on the fixing rod 16, and then fixed by the bolt 20, so that the drone 18 can fly out and drive the fixing pipe 7 to move, and then the fixing pipe 7 can be moved to multiple water accumulation points in the foundation pit for pumping and drainage, which solves the problem that after the foundation pit is watered, the workers are inconvenient to move, which makes it inconvenient to drain the multiple water accumulation points in the foundation pit.

[0024] Example 2 Reference Figure 2 Drain holes 23 are evenly arranged at the bottom of the transport box 1 , so that after the fixing pipe 7 is retracted into the transport box 1 , the water stains remaining on the surface can be discharged through the drainage holes 23 .

[0025] The rest of the structure is the same as that of Example 1.

[0026] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A high-rise building construction water drainage device, characterized in that: include, A transport box (1), wherein box wheels (2) are arranged around the bottom of the transport box (1); A handle (3) is provided on the right side of the transport box (1), and a control box (4) is provided on the front side of the transport box (1); A pump (5) is arranged in the transport box (1), a hose (6) is arranged on the water inlet of the pump (5), and a drain pipe is arranged on the water outlet of the pump (5); The hose (6) is connected to a fixed tube (7), and a filter assembly is provided at the bottom of the fixed tube (7); Both sides of the fixed tube (7) are connected to the placement assembly; A fixing rod (16) is provided on the top of the fixing tube (7), and a moving component connected to the fixing rod (16) is provided on the transport box (1).

2. A high-rise building construction water drainage device according to claim 1, characterized in that: The filter assembly comprises a water extraction hood (8) connected to the bottom of the fixed pipe (7); the bottom of the water extraction hood (8) is fittedly connected to a mounting frame (9); the mounting frame (9) is provided with screws (10) connected to the water extraction hood (8); the inner wall of the mounting frame (9) is connected to a filter plate (11) which penetrates the water extraction hood (8); and the bottom of the filter plate (11) is located below the screws (10).

3. A high-rise building construction water drainage device according to claim 2, characterized in that: The placement assembly comprises two groups of mounting rods (12) of identical structure, the mounting rods (12) on both sides being respectively arranged on both sides of the fixed tube (7), electric telescopic rods (13) being arranged on both front and rear sides of the tops of the mounting rods (12) on both sides, and the output ends of the electric telescopic rods (13) passing through the mounting rods (12) are connected to connecting rods (14), and the bottoms of the connecting rods (14) are provided with support seats (15).

4. A high-rise building construction water drainage device according to claim 3, characterized in that: A guide rail (24) is provided at the bottom of the mounting rod (12), a screw assembly (25) is provided on the guide rail (24), and a vertical rod (26) is slidably connected to the guide rail (24), the screw assembly (25) is connected to the vertical rod (26), and the screw assembly (25) is used to drive the vertical rod (26) to move, a connecting rod (27) is slidably connected to the vertical rod (26), a scraper rod (28) in contact with the bottom of the filter plate (11) is provided between opposite sides of the connecting rods (27), and a return spring (29) connected to the vertical rod (26) is provided inside the connecting rod (27).

5. A high-rise building construction water drainage device according to claim 4, characterized in that: A cavity (30) is provided in the connecting rod (27), and the cavity (30) is located below the return spring (29). A float bag (32) is provided on the top inner wall of the cavity (30), and through holes (31) communicating with the cavity (30) are provided on opposite sides of the connecting rods (27) on both sides.

6. A high-rise building construction water drainage device according to claim 5, characterized in that: Baffle rods (33) are provided on both sides of the water extraction cover (8), the baffle rods (33) on both sides are in contact with the connecting rods (27) on both sides respectively, and the baffle rods (33) on both sides cover the through holes (31) on both sides respectively.

7. The high-rise building construction water drainage device according to claim 1, characterized in that: The mobile assembly comprises a top plate (17) arranged on the top of the transport box (1), a drone (18) being arranged on the top plate (17), a fixing block (19) being arranged on the drone (18), a bolt (20) being arranged on the fixing block (19), a slot matching a fixing rod (16) being arranged at the bottom of the fixing block (19), a screw hole matching the bolt (20) being arranged on the fixing rod (16), a box cover (21) being arranged on the top of the top plate (17) and being located outside the drone (18), and a box lid (22) being hingedly connected to the top of the box cover (21).

8. The high-rise building construction water drainage device according to claim 1, characterized in that: The bottom of the transport box (1) is evenly provided with drainage holes (23).