Pre-embedded steel bar planting construction method

Through the pre-embedded rebar planting construction method, the template is fixed with embedded parts and positioning parts, and the rebar planting glue is destroyed by a stirring rod. The problems of weak steel anchorage and dust pollution in the post-rebar planting method are solved, and a stronger planting is achieved. reinforcement and a safer construction environment.

CN118774403AActive Publication Date: 2024-10-15CHINA MCC22 GROUP CORP LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411197908.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-10-15
Estimated Expiration
2044-08-29

AI Technical Summary

Technical Problem

In construction, the post-reinforcement method results in weak anchorage of the steel bars, which often results in problems such as misalignment, dust pollution, noise pollution, and occupational diseases due to irregular drilling, hole cleaning, and glue injection operations.

Method used

The pre-embedded rebar planting construction method is adopted, and tubular embedded parts and positioning parts are used to fix the formwork. The bagged rebar planting glue is destroyed with a stirring rod, and the steel bar glue is fully wrapped to ensure that the rebar planting holes are vertical and avoid damage to the concrete.

Benefits of technology

It improves the reliability of steel bar anchorage, reduces misalignment and dust pollution, and reduces noise pollution and occupational disease risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774403A_ABST
    Figure CN118774403A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to an embedded steel bar planting construction method. Comprising the following steps that S1, a tubular embedded part with one end blocked is prepared; and S2, bagged embedded steel bar glue is placed in the embedded part. And S3, after the main body formwork is installed, punching is conducted in the designed positions of the embedded steel bar holes. And S4, the embedded part is fixed to the formwork through the positioning part. And S5, the end of the stirring rod is connected to an electric pistol drill for stirring, the bagged bar-planting glue is damaged in the stirring process, and the stirring rod is taken out after the glue is stirred uniformly. And S6, the steel bars are poked into the embedded parts through the steel bar planting holes, it is guaranteed that the steel bars are fully wrapped by the glue, and steel bar planting is completed. Then the embedded part is fixed to a formwork through the positioning part to be embedded, the base is attached to the inner side face of the formwork to guarantee that the steel bar planting holes are perpendicular, after concrete is formed, a hand drill penetrates through the stirring holes to stir and damage bagged steel bar planting glue, steel bars are inserted into the embedded part, it is guaranteed that the steel bars are fully wrapped by the glue, and steel bar planting is completed. The damage to the concrete is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, in particular to a pre-buried reinforcement construction method. Background Art

[0002] In recent years, post-embedded reinforcement is often used in the construction of tie bars between infill walls and load-bearing walls, columns, beams and slabs. Although this construction method is convenient, it often leads to poor anchoring of the steel bars due to quality problems of anchor glue or grouting materials, and improper drilling, hole cleaning, glue injection or grouting operations, which fails to play the proper tie effect. Normally, after the main structure is completed, workers need to locate and drill holes on the end faces of the shear walls and the bottom faces of the beams and slabs according to the positions on the drawings. It often happens that the steel bars of the beams or walls are hit during drilling, causing the hole to be invalid. The workers will continue to drill holes nearby until they can reach the depth required by the specifications, which is usually 100mm-120mm. Secondary drilling is required to avoid the steel bars, and the resulting deviation accounts for about 30% of the total number of holes drilled. Secondly, because drilling requires manual operation with an electric hammer, more than 40% of the rebar holes are not vertical, causing them to be crooked after rebar is planted. After drilling, the holes need to be cleaned with a hair dryer and a brush. The dust left by drilling will seriously affect the pull-out strength after rebar is planted. When planting the rebar, the rebar glue must be mixed strictly according to the ratio, and the rebar should be fully coated with glue and stuffed in. It is better to wait for it to solidify if it overflows. At this point, the rebar planting work is completed. During this process, it involves a series of problems such as damage to the main structure steel bars, concrete appearance, structural column steel bar deviation causing difficulty in mold closing, rebar pulling strength not meeting requirements, drilling dust pollution, noise pollution, occupational diseases, etc. Summary of the invention

[0003] The present invention aims to solve the above problems, thereby providing a pre-buried reinforcement construction method which can firmly anchor the reinforcement bars.

[0004] The present invention solves the above-mentioned problem by adopting the following technical solution: A pre-buried reinforcement construction method comprises the following steps: S1: A prepared embedded component in a tubular shape with one end blocked, wherein a base is provided at the open end of the embedded component, and an internal thread is provided on the inner wall of the open end of the embedded component.

[0005] S2: A bagged rebar embedding glue is placed in the embedded part, a glue blocking structure is provided on the inner side of the embedded part and adjacent to the inner end of the internal thread, and a stirring hole is provided at the center of the glue blocking structure.

[0006] S3: After the main formwork is installed, drill holes at the designed locations of the rebar holes.

[0007] S4: On the inner side of the template, the base of the embedded part is attached to the template with the open end facing the rebar hole. On the outer side of the template, a positioning piece is used to penetrate the rebar hole and screw it to the embedded part. The positioning piece fixes the embedded part to the template.

[0008] S5: Pour concrete. After the concrete is formed, take out the positioning parts. During the secondary structure construction, a stirring rod is passed through the anchor hole and the stirring hole and extends into the embedded parts. The end of the stirring rod is connected to an electric pistol drill for stirring. During the stirring process, the bagged anchor glue is destroyed. After the glue is stirred evenly, take out the stirring rod.

[0009] S6: Push the prepared steel bar into the embedded part through the embedding hole to ensure that the steel bar is fully wrapped by the glue to complete the embedding.

[0010] Compared with the prior art, the present invention adopting the above technical solution has the following outstanding features: First, determine the drilling position, and then fix the embedded parts on the template through the positioning parts for pre-embedding to prevent displacement, and fit the base on the inner side of the template to ensure the verticality of the rebar hole. After the concrete is formed, use a hand drill to pass through the mixing hole to stir and destroy the bagged rebar glue, insert the steel bars into the embedded parts, ensure that the steel bars are fully wrapped by the glue, complete the rebar planting, and avoid damage to the concrete. Secondly, it solves a series of problems such as dust pollution, noise pollution, occupational diseases, etc. caused by traditional drilling.

[0011] Preferably, a further technical solution of the present invention is: Furthermore, the embedded part includes a left shell and a right shell relative to each other, and the contact surfaces of the left shell and the right shell are provided with positioning grooves and positioning strips for use with each other, the shell sides of the right shell are provided with card slots, and the shell sides of the left shell are provided with buckles for use with the card slots.

[0012] Furthermore, two sides of the bagged anchor glue are clamped between the contact surfaces of the left shell and the right shell.

[0013] Furthermore, the rubber blocking structure includes semi-annular elastic thin partitions respectively arranged on the inner sides of the left shell and the right shell and close to the internal threads.

[0014] Furthermore, multiple layers of outer anti-slip ribs are provided in an annular direction along the outer periphery of the embedded part.

[0015] Furthermore, reinforcing ribs are arranged on the outer side of the embedded part and between adjacent outer anti-slip ribs.

[0016] Furthermore, multiple layers of inner anti-slip ribs are circumferentially arranged along the inner circumference of the embedded part.

[0017] Furthermore, a plurality of anti-tilt ribs are arranged outside the open end of the embedded part.

[0018] Furthermore, the positioning member includes a screw rod threadedly connected to the open end of the embedded member, the outer end of the screw rod is provided with a clamping platform clamped on the outer side of the template, and an operating rod is provided on the surface of the clamping platform away from the screw rod. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1This is a schematic diagram of the main structure of the embedded part of an embodiment of the present invention; Figure 2 This is a schematic diagram of the front view of the structure of the embedded part and the positioning part connected in an embodiment of the present invention; Figure 3 This is a schematic diagram of the front cross-sectional structure of the left housing of an embodiment of the present invention; Figure 4 It is a schematic diagram of the side cross-sectional structure of the right housing of an embodiment of the present invention; Figure 5 It is a schematic diagram of the side cross-sectional structure of the left housing of an embodiment of the present invention; Figure 6 This is a schematic diagram of the structure of a positioning member according to an embodiment of the present invention; Figure 7 It is a bottom view structural schematic diagram of the right housing of an embodiment of the present invention; Marked in the figure are: left shell 1, right shell 2, buckle 3, base 4, positioning piece 5, elastic thin partition 6, outer anti-skid rib 7, reinforcement rib 8, inner anti-skid rib 9, anti-tilt rib 10. DETAILED DESCRIPTION

[0020] The present invention will be further described below in conjunction with embodiments, the purpose of which is only to provide a better understanding of the content of the present invention. Therefore, the examples given do not limit the protection scope of the present invention.

[0021] A pre-buried reinforcement construction method comprises the following steps: S1: A prepared embedded component in a tubular shape with one end blocked, a base 4 is provided at the open end of the embedded component, and an internal thread is provided on the inner wall of the open end of the embedded component.

[0022] S2: A bagged rebar embedding glue is placed in the embedded part, a glue blocking structure is provided on the inner side of the embedded part and adjacent to the inner end of the internal thread, and a stirring hole is provided at the center of the glue blocking structure.

[0023] S3: After the main formwork is installed, drill holes at the designed locations of the rebar holes.

[0024] S4: On the inner side of the template, the base 4 of the embedded part is attached to the template with the open end facing the anchor hole. On the outer side of the template, a positioning part 5 is used to penetrate the anchor hole and screw it to the embedded part. The positioning part 5 fixes the embedded part to the template.

[0025] S5: pour concrete. After the concrete is formed, take out the positioning part 5. During the secondary structure construction, a stirring rod is passed through the rebar embedding hole and the stirring hole and extends into the embedded part. The end of the stirring rod is connected to an electric pistol drill for stirring. The bagged rebar embedding glue is destroyed during the stirring process. After the glue is stirred evenly, the stirring rod is taken out. The hand drill enters the embedded part through the stirring hole to stir and damage the outer skin of the bagged rebar embedding glue. The glue blocking component ensures that the bagged rebar embedding glue does not leak out for a short time after being poked open.

[0026] S6: Push the prepared steel bar into the embedded part through the embedding hole to ensure that the steel bar is fully wrapped by the glue to complete the embedding.

[0027] Furthermore, the embedded parts include a left shell 1 and a right shell 2 relative to each other, the left shell 1 and the right shell 2 are made of nylon, and the surfaces where the left shell 1 and the right shell 2 contact each other are provided with positioning grooves and positioning strips for matching use, the left shell 1 is provided with a positioning groove, the right shell 2 is provided with a positioning strip, card slots are provided at intervals on both sides of the shell of the right shell 2, and buckles 3 for matching with the card slots are provided on both sides of the shell of the left shell 1.

[0028] Furthermore, the two sides of the bagged anchor glue are clamped between the contact surfaces of the left shell 1 and the right shell 2, and the position of the bagged anchor glue is fixed to facilitate puncturing, which can also prevent leakage between the left shell 1 and the right shell 2 when pouring concrete.

[0029] Furthermore, the rubber blocking structure includes a semi-annular elastic thin partition 6 respectively arranged on the inner side of the left shell 1 and the right shell 2 and close to the internal thread. The elastic thin partition 6 is made of nylon. After the left shell 1 and the right shell 2 are connected, the two semi-annular elastic thin partitions 6 form a ring with a stirring hole in the middle of the ring. The semi-annular elastic thin partition 6 is composed of a number of fan-shaped partition units. The elastic thin partition 6 ensures that the embedded steel bar rubber bag does not leak out in a short time after being pierced. The diameter of the steel bar is larger than the diameter of the stirring hole. The subsequent steel bars are directly pressed against the annular elastic thin partition 6 and inserted into the embedded parts.

[0030] Furthermore, multiple layers of outer anti-slip ribs 7 are provided in the circumferential direction of the outer periphery of the embedded part to enhance the bonding performance with the concrete.

[0031] Furthermore, reinforcing ribs 8 are provided on the outer side of the embedded part and between adjacent outer anti-slip ribs 7 to prevent the embedded part from being deformed.

[0032] Furthermore, multiple layers of inner anti-skid ribs 9 are circumferentially arranged along the inner circumference of the embedded part. The inner anti-skid ribs 9 and the outer anti-skid ribs 7 are located at the same horizontal position to increase the gripping force. The inner diameter of the inner anti-skid ribs 9 is adapted to the steel bar to increase the stability of the steel bar in the embedded part.

[0033] Furthermore, a plurality of anti-tilt ribs 10 are arranged outside the open end of the embedded part, one side of the anti-tilt rib 10 is in contact with the inner side of the template, and the anti-tilt rib 10 further ensures that the embedded part is perpendicular to the template.

[0034] Furthermore, the positioning member 5 includes a screw threadedly connected to the open end of the embedded part, and a clamping platform that is clamped on the outside of the template is provided at the outer end of the screw. An operating rod is provided on the surface of the clamping platform away from the screw. The operating rod controls the rotation of the screw, and the clamping platform is pressed against the outside of the template for limiting the position.

[0035] First, determine the drilling position, and then fix the embedded parts on the template through the positioning parts 5 for pre-embedded to prevent deviation, and fit the base 4 on the inner side of the template to ensure the verticality of the rebar hole. After the concrete is formed, use a hand drill to pass through the mixing hole to stir and destroy the bagged rebar glue, insert the steel bars into the embedded parts, ensure that the steel bars are fully wrapped by the glue, complete the rebar planting, and avoid damage to the concrete. Secondly, it solves a series of problems such as dust pollution, noise pollution, occupational diseases, etc. caused by traditional drilling.

[0036] The above description is only a preferred feasible embodiment of the present invention, and does not limit the scope of rights of the present invention. All equivalent changes made using the contents of the present specification and its drawings are included in the scope of rights of the present invention.

Claims

1. A pre-buried reinforcement construction method, Features: The steps include: S1: a prepared embedded part in a tubular shape with one end blocked, a base being provided at the open end of the embedded part, and an internal thread being provided on the inner wall of the open end of the embedded part; S2: a bag of anchor glue is placed in the embedded part, a glue blocking structure is provided on the inner side of the embedded part and adjacent to the inner end of the internal thread, and a stirring hole is provided at the center of the glue blocking structure; S3: After the main formwork is installed, drill holes at the designed locations of the rebar holes; S4: On the inner side of the template, the base of the embedded part is attached to the template with the open end facing the rebar hole. On the outer side of the template, a positioning piece is used to penetrate the rebar hole and screw it to the embedded part. The positioning piece fixes the embedded part to the template. S5: Concrete pouring is performed. After the concrete is formed, the positioning piece is taken out. During the secondary structure construction, a stirring rod is inserted into the embedding hole and the stirring hole and extends into the embedded piece. The end of the stirring rod is connected to an electric pistol drill for stirring. During the stirring process, the bagged embedding glue is destroyed. After the glue is stirred evenly, the stirring rod is taken out; S6: Push the prepared steel bar into the embedded part through the embedding hole to ensure that the steel bar is fully wrapped by the glue to complete the embedding.

2. The pre-buried reinforcement construction method according to claim 1, Features: The embedded part includes a left shell and a right shell relative to each other. The contact surfaces of the left shell and the right shell are provided with positioning grooves and positioning strips for matching use. The right shell is provided with card slots on both sides of the shell, and the left shell is provided with buckles for matching use with the card slots on both sides of the shell.

3. The pre-buried reinforcement construction method according to claim 2, Features: The two sides of the bagged anchor glue are clamped between the contact surfaces of the left shell and the right shell.

4. The pre-buried reinforcement construction method according to claim 1, Features: The rubber blocking structure comprises semi-annular elastic thin partitions which are respectively arranged on the inner sides of the left shell and the right shell and are arranged close to the internal threads.

5. The pre-buried reinforcement construction method according to claim 1, Features: Multiple layers of outer anti-slip ribs are arranged in the circumferential direction of the outer periphery of the embedded part.

6. The pre-buried reinforcement construction method according to claim 5, Features: Reinforcing ribs are arranged on the outer side of the embedded part and between adjacent outer anti-slip ribs.

7. The pre-buried reinforcement construction method according to claim 5, Features: The inner circumference of the embedded part is circumferentially provided with multiple layers of inner anti-slip ribs.

8. The pre-buried reinforcement construction method according to claim 1, Features: A plurality of anti-tilt ribs are arranged outside the open end of the embedded part.

9. The pre-buried reinforcement construction method according to claim 1, Features: The positioning piece comprises a screw rod which is threadedly connected with the open end of the embedded piece, a clamping platform which is clamped on the outer side of the template is arranged at the outer end of the screw rod, and an operating rod is arranged on the surface of the clamping platform which is away from the screw rod.

Citation Information

Patent Citations

  • Concrete steel bar planting method

    CN105888259A

  • Drilling-free brickwork bar planting method

    CN113756588A

  • Combined embedded steel bar embedded part and using method thereof

    CN116623807A

  • Structural embedded steel bar embedding device

    CN210483084U

  • Masonry embedded steel bar structure free of grouting

    CN215926314U