Semi-fabricated biological reaction tank structure and construction method thereof
Through the semi-fabricated bioreactor structure, combined with cast-in-place and prefabricated materials, node connections are simplified, which solves the problems of long construction period and poor corrosion resistance of the existing bioreactor structure, and achieves fast and convenient construction and high connection strength.
Patent Information
- Application Number
- CN202411143907.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-08-20
AI Technical Summary
The existing biological reaction pool structure has problems such as long construction period, serious pollution, corrosion resistance and complex node connections. In particular, the prefabricated steel structure is not corrosion resistant, the concrete structure node formwork operation is complicated and the construction efficiency is low.
A semi-fabricated bioreactor pool structure is adopted, including a cast-in-place bottom plate, side wall structure and top structure. Through the combination of prefabricated pool walls and cast-in-place steel bars, precast pool walls and concrete pouring at intervals are used to simplify node connections and improve construction efficiency. , and uses UHPC high-performance concrete to enhance connection strength.
It achieves fast and convenient construction, strong corrosion resistance, integrity and reliability of node connections, and significantly improves construction efficiency and connection strength.
Smart Images

Figure CN118774464A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a semi-assembled biological reaction pool structure and a construction method thereof. Background Art
[0002] With the increasing severity of water pollution and the continuous increase in urban water demand, sewage treatment plants have been built on a large scale, and sewage purification is carried out in biological reactors.
[0003] The existing bioreactor structures are mostly cast-in-place reinforced concrete, which has the problems of long construction period and large pollution on the construction site. Among the existing prefabricated structures, the prefabricated steel structure has the disadvantage of not being resistant to corrosion, while the prefabricated concrete structure has the technical problems of complex node formwork operation, complex main and secondary beam connection construction and low construction efficiency. Summary of the invention
[0004] The object of the present invention is to provide a semi-assembled biological reaction tank structure and a construction method thereof, wherein the structure has strong corrosion resistance, fast and convenient construction, and can ensure the integrity and reliability of node connections.
[0005] To achieve this object, the present invention adopts the following technical solutions:
[0006] On the one hand, a semi-assembled bioreactor structure is provided, comprising:
[0007] A cast-in-place bottom plate, wherein a first connecting steel bar is convexly provided on the cast-in-place bottom plate;
[0008] Side wall structure, including:
[0009] A plurality of prefabricated pool walls arranged at intervals, wherein the bottom end of each of the prefabricated pool walls is clamped between two adjacent first connecting steel bars, and a first gap for pouring concrete is provided between two adjacent prefabricated pool walls;
[0010] A cast-in-place pool wall is arranged at the corner of the side wall structure and connected between the two prefabricated pool walls;
[0011] Top structure, including:
[0012] A prefabricated main beam is erected on the side wall structure, and concrete is poured at the connection with the side wall structure;
[0013] A prefabricated top plate is connected between the prefabricated main beam and the side wall structure, a bending module is arranged on the bottom side of the prefabricated top plate, two prefabricated top plates are arranged at intervals on one side of the prefabricated main beam, and the bending modules on the two prefabricated top plates and the prefabricated main beam surround a casting cavity;
[0014] A cast-in-place secondary beam is arranged in the casting cavity, and the cast-in-place secondary beam is connected between the prefabricated main beam and the side wall structure.
[0015] As an optional solution for the semi-assembled bioreactor structure, a second connecting steel bar is protruding from the side of the prefabricated pool wall at the corner of the side wall structure, and the second connecting steel bar is used to connect the cast-in-place pool wall.
[0016] As an optional solution for the semi-assembled biological reaction tank structure, first grooves are provided on both sides of the prefabricated tank wall, and the first grooves extend in the vertical direction.
[0017] As an optional solution for the semi-assembled bioreactor structure, first connecting parts are protruding on both sides of the top of the prefabricated tank wall, and the first connecting parts are used to support the prefabricated main beam and the prefabricated top plate;
[0018] The bottom of the prefabricated pool wall is provided with a second connecting portion, and the second connecting portion is clamped between two adjacent first connecting steel bars on the cast-in-place bottom plate.
[0019] As an optional solution for the semi-assembled bioreactor structure, third connecting steel bars are protrudingly provided on all four sides of the prefabricated top plate, and the third connecting steel bars are connected to the side wall structure and the prefabricated main beam.
[0020] As an optional solution for the semi-assembled bioreactor structure, a fourth connecting steel bar is convexly provided on the upper end of the prefabricated main beam, and the fourth connecting steel bar is used to connect with the third connecting steel bar;
[0021] The prefabricated main beam has fifth connecting steel bars protruding from both ends along the length direction, and the fifth connecting steel bars are connected to the side wall structure.
[0022] As an optional solution for the semi-assembled bioreactor structure, a roughening area is provided on the side wall of the prefabricated main beam, and one end of the cast-in-place secondary beam is connected to the roughening area.
[0023] As an optional solution for the semi-assembled bioreactor structure, both ends of the prefabricated main beam along the length direction are provided with second grooves, and a plurality of the second grooves are arranged at intervals along the vertical direction.
[0024] As an optional solution for the semi-assembled bioreactor structure, the upper surfaces of the prefabricated tank wall, the prefabricated main beam and the prefabricated top plate are all protrudingly provided with hanging bars.
[0025] On the other hand, a construction method of a semi-assembled bioreactor structure is provided, which is applied to the above-mentioned semi-assembled bioreactor structure and comprises the following steps:
[0026] S1: tying the steel bars of the cast-in-place bottom plate, and clamping a plurality of the prefabricated pool walls between two adjacent first connecting steel bars;
[0027] S2: pouring concrete between the prefabricated pool wall and the cast-in-place bottom plate, and between two adjacent prefabricated pool walls, connecting the side wall structure to the cast-in-place bottom plate;
[0028] S3: erecting the prefabricated main beam on the side wall structure, then erecting the prefabricated top plate between the prefabricated main beam and the side wall structure, and pouring concrete at the connection;
[0029] S4: a casting cavity is enclosed between two prefabricated top plates spaced apart on one side of the prefabricated main beam, and concrete is poured into the casting cavity to form the cast-in-place secondary beam.
[0030] Beneficial effects of the present invention:
[0031] The present invention provides a semi-assembled bioreactor structure, including a cast-in-place bottom plate, a side wall structure and a top structure. A first connecting steel bar is convexly provided on the cast-in-place bottom plate, and the side wall structure includes a cast-in-place pool wall and a plurality of prefabricated pool walls arranged at intervals. Each prefabricated pool wall is clamped between two adjacent first connecting steel bars, and concrete is poured at the connection between the prefabricated pool wall and the first connecting steel bars; a first gap is provided between two adjacent prefabricated pool walls, and concrete is poured in the first gap to complete the connection between the two adjacent prefabricated pool walls. The top structure includes a prefabricated main beam, a prefabricated top plate and a cast-in-place secondary beam. The prefabricated main beam is erected on the side wall structure, and concrete is poured at the connection with the side wall structure. The prefabricated top plate is connected between the prefabricated main beam and the side wall structure. A bending module is provided on the bottom side of the prefabricated top plate, and two prefabricated top plates are arranged at intervals on one side of the prefabricated main beam. The bending modules of the two prefabricated top plates and the prefabricated main beam enclose a casting cavity, and concrete is poured into the casting cavity to form a cast-in-place secondary beam. The bioreactor structure adopts a semi-assembled structure, which can reduce the amount of node formwork construction and help speed up construction efficiency; at the same time, the reaction tank structure has high connection strength and good integrity. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 It is a top view of a semi-assembled bioreactor structure provided in a specific embodiment of the present invention;
[0033] Figure 2 yes Figure 1 AA section view in;
[0034] Figure 3 yes Figure 1 BB section view in;
[0035] Figure 4It is an overall structural diagram of a prefabricated pool wall provided in a specific embodiment of the present invention;
[0036] Figure 5 It is a front view of a prefabricated pool wall provided in an embodiment of a specific implementation manner of the present invention;
[0037] Figure 6 is a partial cross-sectional view of a side wall structure provided in a specific embodiment of the present invention;
[0038] Figure 7 It is a structural schematic diagram of the connection between the prefabricated pool wall and the cast-in-place bottom plate provided in a specific implementation example of the present invention;
[0039] Figure 8 It is an overall structural diagram of a prefabricated main beam provided in an embodiment of a specific implementation manner of the present invention;
[0040] Fig. 9 is a top view of a prefabricated top plate provided in an embodiment of a specific implementation manner of the present invention;
[0041] Fig.10 It is a structural schematic diagram of the connection between the prefabricated main beam, the prefabricated top plate and the prefabricated pool wall before pouring concrete provided by the specific implementation example of the present invention;
[0042] Fig.11 It is a schematic diagram of the structure after pouring concrete at the connection between the prefabricated main beam, the prefabricated top plate and the prefabricated pool wall provided in the specific implementation example of the present invention.
[0043] In the figure:
[0044] 1. Cast-in-place base plate; 11. First connecting steel bar;
[0045] 2. Side wall structure;
[0046] 21. Prefabricated pool wall; 211. Second connecting steel bar; 212. First groove; 213. First connecting portion; 214. Second connecting portion; 215. Sixth connecting steel bar;
[0047] 22. Cast-in-place pool wall;
[0048] 3. Top structure;
[0049] 31. Prefabricated main beam; 311. Fourth connecting steel bar; 312. Fifth connecting steel bar; 313. Roughening area; 314. Second groove; 315. Hanging bar; 316. Third connecting part;
[0050] 32. Prefabricated top plate; 321. Bending module; 322. Third connecting steel bar; 323. Casting hole;
[0051] 33. Cast-in-place secondary beam. DETAILED DESCRIPTION
[0052] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0053] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0054] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0055] In the description of this embodiment, the terms "upper", "lower", "right", etc., directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplification of operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.
[0056] The technical solution of the present invention is further described below with reference to the accompanying drawings and through specific implementation methods.
[0057] like Figures 1 to 11As shown, this embodiment provides a semi-assembled bioreactor structure, including a cast-in-place bottom plate 1, a side wall structure 2 and a top structure 3. Among them, a first connecting steel bar 11 is convexly provided on the cast-in-place bottom plate 1, and the side wall structure 2 includes a cast-in-place pool wall 22 and a plurality of prefabricated pool walls 21 arranged at intervals, each prefabricated pool wall 21 is clamped between two adjacent first connecting steel bars 11, and concrete is poured at the connection between the prefabricated pool wall 21 and the first connecting steel bars 11; a first gap is provided between two adjacent prefabricated pool walls 21, and concrete is poured in the first gap to complete the connection of the two adjacent prefabricated pool walls 21. The top structure 3 includes a prefabricated main beam 31, a prefabricated top plate 32 and a cast-in-place secondary beam 33. The prefabricated main beam 31 is erected on the side wall structure 2, and concrete is poured at the connection with the side wall structure 2. The prefabricated top plate 32 is connected between the prefabricated main beam 31 and the side wall structure 2. A bending module 321 is arranged on the bottom side of the prefabricated top plate 32. Two prefabricated top plates 32 are arranged at intervals on one side of the prefabricated main beam 31. The bending modules 321 of the two prefabricated top plates 32 and the prefabricated main beam 31 enclose a casting cavity, and concrete is poured into the casting cavity to form a cast-in-place secondary beam 33. The bioreactor structure adopts a semi-assembled structure, which can reduce the amount of node formwork construction, which is conducive to accelerating construction efficiency; at the same time, the reaction tank structure has high connection strength and good integrity.
[0058] Specifically, the concrete poured in this embodiment is UHPC high-performance concrete, which has high strength and excellent durability, and can ensure the connection strength of the joints, thereby improving the integrity of the bioreactor structure.
[0059] Illustratively, in this embodiment, the sidewall structure 2 is in a quadrilateral shape; in other embodiments, the sidewall structure 2 may also be in other shapes.
[0060] Optionally, combined Figures 1 to 6 As shown, a plurality of second connecting steel bars 211 are protrudingly provided on the side of the prefabricated pool wall 21 at the corner of the side wall structure 2, and the second connecting steel bars 211 are used to connect the cast-in-place pool wall 22. That is, the second connecting steel bars 211 protrudingly provided on the two prefabricated side walls at the corner are connected, and then concrete is poured to form the cast-in-place pool wall 22.
[0061] Specifically, one end of the second connecting steel bar 211 away from the prefabricated pool wall 21 is bent to strengthen the connection strength between the prefabricated pool wall 21 and the cast-in-place pool wall 22 .
[0062] Further, refer to Figure 4 , both sides of the prefabricated pool wall 21 are provided with a first groove 212, and the first groove 212 extends in the vertical direction. Figure 6A first gap is provided between two adjacent prefabricated pool walls 21, and concrete is poured into the first gap to connect the two adjacent prefabricated pool walls 21. The provision of the first groove 212 can strengthen the connection strength between the two prefabricated pool walls 21, thereby improving the shear resistance of the side wall structure 2.
[0063] Optionally, continue to refer to Figure 4 and Figure 5 The first connecting parts 213 are protruding on both sides of the top of the prefabricated pool wall 21. The first connecting parts 213 are used to support the prefabricated main beam 31 and the prefabricated top plate 32, which is convenient for placing the prefabricated main beam 31 and the prefabricated top plate 32 and is conducive to forming a reliable connection. Figure 7 A second connecting portion 214 is provided at the bottom of the prefabricated pool wall 21, and the second connecting portion 214 is clamped between two adjacent first connecting steel bars 11 on the cast-in-place bottom plate 1 to facilitate the preliminary connection between the prefabricated pool wall 21 and the cast-in-place pool wall 22, and then the connection between the prefabricated pool wall 21 and the first connecting steel bars 11 is completed by pouring concrete at the connection between the prefabricated pool wall 21 and the cast-in-place bottom plate 1.
[0064] Specifically, Figure 4 and Figure 5 As shown, the top and bottom of the prefabricated pool wall 21 are both convexly provided with sixth connecting steel bars 215, the sixth connecting steel bars 215 at the top are used to connect with the prefabricated main beam 31 and the prefabricated top plate 32, and the sixth connecting steel bars 215 at the bottom are used to connect with the first connecting steel bars 11 on the cast-in-place bottom plate 1 to improve the tightness of the connection. In addition, the prefabricated pool wall 21 is provided with an inlet and outlet (not shown) for allowing sewage to enter and exit the biological reaction tank structure.
[0065] Alternatively, if Figure 8 As shown, third connecting steel bars 322 are protrudingly provided on all four sides of the prefabricated top plate 32, and the third connecting steel bars 322 are connected to the side wall structure 2 and the prefabricated main beam 31 to enhance the connection strength between the prefabricated top plate 32 and the side wall structure 2 and between the prefabricated top plate 32 and the prefabricated main beam 31.
[0066] Furthermore, if Fig. 9 As shown, the upper end of the prefabricated main beam 31 is provided with a fourth connecting steel bar 311, combined with Fig.10 The fourth connecting steel bar 311 is used to connect with the third connecting steel bar 322 on the prefabricated top plate 32 to improve the connection strength between the prefabricated main beam 31 and the prefabricated top plate 32. Fig. 9 The prefabricated main beam 31 is provided with fifth connecting steel bars 312 at both ends along the length direction. Fig.10 The fifth connecting steel bar 312 is used to connect to the sixth connecting steel bar 215 arranged on the top of the prefabricated pool wall 21 to improve the connection strength between the prefabricated main beam 31 and the prefabricated pool wall 21.
[0067] Optionally, continue to refer to Fig. 9 The precast main beam 31 is provided with a second groove 314 at both ends along the length direction, and a plurality of second grooves 314 are provided at intervals along the vertical direction. When two precast main beams 31 need to be connected, a second gap is left between the two precast main beams 31, and concrete is poured into the second gap and the second groove 314 to connect the two precast main beams 31. The provision of the second groove 314 can ensure the connection strength of the connection between the two precast main beams 31.
[0068] Illustratively, in this embodiment, two second grooves 314 are arranged at intervals along the vertical direction.
[0069] Specifically, third connecting parts 316 are provided on both sides of the upper end of the prefabricated main beam 31 , and the third connecting parts 316 are used to support the prefabricated top plate 32 to facilitate the placement of the prefabricated top plate 32 , and at the same time, can improve the connection strength between the prefabricated main beam 31 and the prefabricated top plate 32 .
[0070] Alternatively, if Fig.10 As shown, a roughened area 313 is provided on the side wall of the precast main beam 31, and one end of the cast-in-place secondary beam 33 is connected to the roughened area 313. The provision of the roughened area 313 can improve the connection strength between the precast main beam 31 and the cast-in-place secondary beam 33.
[0071] Specifically, in the present embodiment, reserved steel bars are protruding from the roughened area 313 to further improve the connection strength between the prefabricated main beam 31 and the cast-in-place secondary beam 33 .
[0072] Optionally, the upper end surfaces of the prefabricated pool wall 21, the prefabricated main beam 31 and the prefabricated top plate 32 are all protrudingly provided with hanging rods 315, and the hanging rods 315 are configured to be connected to upward hoisting equipment to facilitate hoisting during the construction process.
[0073] On the other hand, a construction method of a semi-assembled bioreactor structure is also provided, which is applied to the above-mentioned bioreactor structure and comprises the following steps:
[0074] S1: Tie up the steel bars of the cast-in-place bottom plate 1, and clamp a plurality of prefabricated pool walls 21 between two adjacent first connecting steel bars 11;
[0075] The above steps, specifically in this embodiment, are to tie the steel bars of the cast-in-place bottom plate 1 and the first connecting steel bars 11, and pour concrete to form the cast-in-place bottom plate 1. A plurality of prefabricated pool walls 21 are hoisted onto the cast-in-place bottom plate 1 by an upward hoisting device, and the second connecting portion 214 at the bottom of each prefabricated pool wall 21 is clamped between two adjacent first connecting steel bars 11, so that the sixth connecting steel bar 215 at the bottom of the prefabricated pool wall 21 is connected to the first connecting steel bar 11.
[0076] S2: pouring concrete between the prefabricated pool wall 21 and the cast-in-place bottom plate 1, and between two adjacent prefabricated pool walls 21, connecting the side wall structure 2 to the cast-in-place bottom plate 1;
[0077] In the above steps, specifically in this embodiment, concrete is poured at the position where the sixth connecting steel bar 215 and the first connecting steel bar 11 are connected to each other, so as to realize the connection between the prefabricated pool wall 21 and the cast-in-place bottom plate 1. Then, concrete is poured into the first gap set between the two prefabricated pool walls 21 to complete the connection of the two adjacent prefabricated pool walls 21. In addition, the side wall of the prefabricated pool wall 21 located at the corner of the side wall structure 2 is convexly provided with a second connecting steel bar 211, and concrete is poured at the second connecting steel bar 211 to form a cast-in-place pool wall 22, thereby completing the overall construction of the side wall structure 2.
[0078] S3: erecting a prefabricated main beam 31 on the side wall structure 2, then erecting a prefabricated top plate 32 between the prefabricated main beam 31 and the side wall structure 2, and pouring concrete at the connection;
[0079] The above steps are specific to the embodiment, refer to Fig.10 , erect the precast main beam 31 on the side wall structure 2, connect the sixth connecting steel bar 215 on the top of the precast pool wall 21 with the fifth connecting steel bar 312 at both ends of the precast main beam 31; then erect the precast top plate 32 between the precast main beam 31 and the side wall structure 2, and erect one end of the precast top plate 32 on the third connecting portion 316 of the precast main beam 31, connect the third connecting steel bar 322 on the precast top plate 32 with the fourth connecting steel bar 311 on the precast main beam 31; and erect the other end on the precast pool wall 21, connect the third connecting steel bar 322 on the precast top plate 32 with the sixth connecting steel bar 215 on the top of the precast pool wall 21. Pour concrete at the connection points of the above connecting steel bars, refer to Fig.11 , realizing the connection between the prefabricated main beam 31, the prefabricated top plate 32 and the side wall structure 2.
[0080] S4: a casting cavity is enclosed between two precast top plates 32 spaced apart on one side of the precast main beam 31 , and concrete is poured into the casting cavity to form a cast-in-place secondary beam 33 .
[0081] The above steps are specific to this embodiment. Fig.11 As shown, two prefabricated top plates 32 (one prefabricated top plate 32 is omitted in the figure) are spaced apart on one side of the prefabricated main beam 31, and the bending modules 321 on the two prefabricated top plates 32 enclose a casting cavity, and concrete is poured into the casting cavity to form a cast-in-place secondary beam 33.
[0082] Specifically, in this embodiment, Figure 8 As shown, a plurality of pouring holes 323 are provided on the prefabricated top plate 32 at intervals. The provision of the pouring holes 323 can make it easier to pour concrete into the pouring cavity, thereby improving construction efficiency.
[0083] It should be noted that the above-mentioned connecting steel bars may be connected to each other by overlapping or by tying after overlapping, so as to further improve the strength of the node connection and ensure the integrity of the reaction tank structure.
[0084] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the protection scope of the present invention. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. A semi-assembled bioreactor structure, characterized in that: include: A cast-in-place base plate (1), wherein a first connecting steel bar (11) is protrudingly provided on the cast-in-place base plate (1); The side wall structure (2) comprises: A plurality of prefabricated pool walls (21) arranged at intervals, wherein the bottom end of each of the prefabricated pool walls (21) is clamped between two adjacent first connecting steel bars (11), and a first gap for pouring concrete is provided between two adjacent prefabricated pool walls (21); A cast-in-place pool wall (22) is arranged at a corner of the side wall structure (21) and connected between the two prefabricated pool walls (21); The top structure (3) comprises: A prefabricated main beam (31) is erected on the side wall structure (2), and concrete is poured at the connection with the side wall structure (2); A prefabricated top plate (32) is connected between the prefabricated main beam (31) and the side wall structure (2); a bending module (321) is arranged on the bottom side of the prefabricated top plate (32); two prefabricated top plates (32) are arranged at intervals on one side of the prefabricated main beam (31); the bending modules (321) on the two prefabricated top plates (32) and the prefabricated main beam (31) enclose a casting cavity; A cast-in-place secondary beam (33) is arranged in the casting cavity, and the cast-in-place secondary beam (33) is connected between the prefabricated main beam (31) and the side wall structure (2).
2. The semi-assembled bioreactor structure according to claim 1, characterized in that: A second connecting steel bar (211) is protrudingly provided on the side surface of the prefabricated pool wall (21) located at the corner of the side wall structure (2), and the second connecting steel bar (211) is used to connect the cast-in-place pool wall (22).
3. The semi-assembled bioreactor structure according to claim 2, characterized in that: First grooves (212) are provided on both sides of the prefabricated pool wall (21), and the first grooves (212) extend in a vertical direction.
4. The semi-assembled bioreactor structure according to claim 1, characterized in that: First connecting parts (213) are protrudingly provided on both sides of the top of the prefabricated pool wall (21), and the first connecting parts (213) are used to support the prefabricated main beam (31) and the prefabricated top plate (32); The bottom of the prefabricated pool wall (21) is provided with a second connecting portion (214), and the second connecting portion (214) is clamped between two adjacent first connecting steel bars (11) on the cast-in-place bottom plate (1).
5. The semi-assembled bioreactor structure according to claim 1, characterized in that: The prefabricated top plate (32) is provided with third connecting steel bars (322) protruding around the periphery, and the third connecting steel bars (322) are connected to the side wall structure (2) and the prefabricated main beam (31).
6. The semi-assembled bioreactor structure according to claim 5, characterized in that: A fourth connecting steel bar (311) is protrudingly provided at the upper end of the prefabricated main beam (31), and the fourth connecting steel bar (311) is used to be connected to the third connecting steel bar (322); The prefabricated main beam (31) is provided with fifth connecting steel bars (312) at both ends along the length direction, and the fifth connecting steel bars (312) are connected to the side wall structure (2).
7. The semi-assembled bioreactor structure according to claim 1, characterized in that: A roughened area (313) is provided on the side wall of the prefabricated main beam (31), and one end of the cast-in-place secondary beam (33) is connected to the roughened area (313).
8. The semi-assembled bioreactor structure according to claim 1, characterized in that: The prefabricated main beam (31) is provided with a second groove (314) at both ends along the length direction, and a plurality of the second grooves (314) are arranged at intervals along the vertical direction.
9. The semi-assembled bioreactor structure according to any one of claims 1 to 8, characterized in that: Hanging rods (315) are protrudingly provided on the upper end surfaces of the prefabricated pool wall (21), the prefabricated main beam (31) and the prefabricated top plate (32).
10. A construction method for a semi-assembled bioreactor structure, characterized in that: The semi-assembled bioreactor structure according to any one of claims 1 to 9 comprises the following steps: S1: tying the steel bars of the cast-in-place bottom plate (1) and clamping a plurality of the prefabricated pool walls (21) between two adjacent first connecting steel bars (11); S2: pouring concrete between the prefabricated pool wall (21) and the cast-in-place bottom plate (1), and between two adjacent prefabricated pool walls (21), and connecting the side wall structure (2) to the cast-in-place bottom plate (1); S3: erecting the prefabricated main beam (31) on the side wall structure (2), then erecting the prefabricated top plate (32) between the prefabricated main beam (31) and the side wall structure (2), and pouring concrete at the connection; S4: a casting cavity is enclosed between two prefabricated top plates (32) spaced apart on one side of the prefabricated main beam (31), and concrete is cast into the casting cavity to form the cast-in-place secondary beam (33).
Citation Information
Patent Citations
Prefabricated concrete pool wallboard structure and construction method thereof
CN113605770A
Invisible beam assembly type disassembly-free heat preservation floor slab structure
CN210459701U
Prefabricated concrete pool wallboard structure
CN215978692U
Bridge deck using precast concrete panel
KR101735077B1
Modular construction system and components and method
US20120167501A1