Construction method for combined control of ground surface settlement monitoring and muddy water bin

The GPS intelligent monitoring system and the mechanical pipe jacking equipment master console jointly control the mud and water tank pressure, which solves the problem of surface settlement or uplift during mechanical pipe jacking construction, improves construction quality and safety, and reduces the impact on surrounding buildings and secondary pollution. processing costs.

CN118774833APending Publication Date: 2024-10-15CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410806153.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-21
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

There are problems with surface settlement or uplift during mechanical pipe jacking construction, which affects the construction quality and the stability of surrounding buildings. The construction efficiency is low and the cost of secondary treatment is increased.

Method used

A GPS intelligent monitoring system is used to detect surface changes in real time, and the mud water pressure in the mud water bin is adjusted through the main console of the mechanical pipe jacking equipment to balance the groundwater pressure and prevent surface uplift or subsidence.

Benefits of technology

It can effectively reduce surface settlement, reduce disturbance to the surrounding environment, improve the safety of building structures, save costs, manpower and material resources, and improve construction efficiency and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774833A_ABST
    Figure CN118774833A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for ground surface settlement monitoring and muddy water bin combined control, which comprises the following steps: during jacking pipe jacking construction, performing dynamic real-time detection on the ground surface and the periphery on a jacking route by utilizing a GPS (Global Positioning System) intelligent monitoring system, setting a corresponding early-warning value, and when the ground surface bulges or the settlement exceeds the early-warning value, performing early-warning on the ground surface and the periphery of the jacking route; the pressure of muddy water in the mechanical pipe-jacking muddy water bin is adjusted through the mechanical pipe-jacking equipment master console so as to balance the pressure of underground water. In this way, when the shallow-buried mechanical jacking pipe is jacked, ground surface settlement is reduced, disturbance to the surrounding environment and building structures is reduced, larger damage to the surrounding building structures is avoided, the safety of the surrounding building structures is improved, meanwhile, disturbance and damage to the surrounding buildings possibly caused by conventional construction are avoided, and the construction efficiency is improved. Corresponding compensation cost is saved, manpower and material resources of external units are coordinated, and the satisfaction degree of construction units and surrounding citizens is increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the field of municipal shallow buried mechanical pipe jacking construction, and specifically relates to a construction method for joint control of surface settlement monitoring and mud and water bin. Background Art

[0002] Drainage and flood control projects are an important part of urban infrastructure and are of great significance to the normal operation of the city and the quality of life of residents. Mechanical pipe jacking construction is an important construction method in drainage and flood control projects, and its construction quality directly affects the function and life of the drainage system.

[0003] Mechanical pipe jacking construction is a complex underground engineering construction method involving multiple professional fields, such as civil engineering, mechanical engineering, electrical engineering, etc. Its construction process requires strict control of construction quality to ensure the installation accuracy and stability of the pipeline, while minimizing the impact of construction on surrounding buildings.

[0004] During the construction of the project, there are problems in controlling the stability of the working well during the jacking process, ground subsidence or uplift within a certain range on both sides of the pipeline axis during the jacking process or after construction, problems in precise steering and deviation control of the jacking pipe, and problems in low jacking efficiency. If the above problems are not solved, the quality of the jacking pipe construction will be reduced, the construction efficiency will be low, the secondary processing cost will be increased, and in serious cases, the safety and stability of the building structure may be affected. Summary of the invention

[0005] The purpose of the present application is to provide a construction method for joint control of surface subsidence monitoring and mud and water bin, which solves the problem of surface subsidence or uplift in mechanical pipe jacking construction.

[0006] The purpose of this application is achieved through the following technical solutions:

[0007] A construction method for joint control of surface settlement monitoring and mud and water bins, comprising: during pipe jacking construction, using a GPS intelligent monitoring system to perform dynamic real-time detection of the surface and surrounding areas on the jacking route, setting corresponding warning values, and when the surface uplift or settlement exceeds the warning value, adjusting the mud and water pressure in the mechanical pipe jacking mud and water bin through a mechanical pipe jacking equipment main control console to balance the groundwater pressure.

[0008] Furthermore, when the ground surface rises and exceeds the warning value, the pressure of the mud and water tank is reduced through the main control console of the mechanical pipe jacking equipment; when the ground surface sinks and exceeds the warning value, the pressure of the mud and water tank is increased through the main control console of the mechanical pipe jacking equipment.

[0009] Furthermore, the GPS intelligent monitoring system includes a GPS monitoring unit, a data communication unit and a data processing and control unit.

[0010] Furthermore, the GPS monitoring unit reflects the structural response through GPS and feeds back the digital signal to the data communication unit.

[0011] Furthermore, the GPS monitoring units are arranged in a dot matrix on the jacking line.

[0012] Furthermore, the data communication unit transmits the data collected by the GPS to the data processing and control unit in a wireless manner.

[0013] Furthermore, the data processing and control unit receives and processes the data collected by the GPS monitoring unit in real time, and displays, evaluates online and issues early warnings for the original data and processed data.

[0014] Furthermore, the mechanical pipe jacking equipment control console is targeted at slurry balance tunnel boring machines.

[0015] Furthermore, the main control console of the mechanical pipe jacking equipment includes an in-machine mud and water valve control system, a deviation correction control system, a power control system, a main top control system and a mud and water pump system.

[0016] Furthermore, the mud and water valve control system in the machine is used to control the start and stop of the mud discharge valve, the start and stop of the bypass valve, the start and stop of the front water supply and the start and stop of the lower water supply; the correction control system is used to control the start and stop of the correction pump, the start and stop of the external water supply, and the extension and retraction of the upper left, upper right, lower left and lower right correction cylinders; the power control system is used to control the forward, reverse, stop, acceleration and deceleration of the cutter disc; the main top control system is used to control the start and stop of the pump station, and the extension, retraction and stop of the main top cylinder; the mud and water tank pressure is controlled by the mud and water pump system, and the mud and water pump system is used to control the start and stop of the booster pump, mud discharge pump, relay pump and water inlet pump.

[0017] Furthermore, the construction method is applied to shallow buried mechanical pipe jacking construction.

[0018] Functions implemented by this application:

[0019] This application combines the dynamic settlement monitoring of the surface during shallow buried pipe jacking construction with the pressure control of the mud and water bin of mechanical pipe jacking. During the process of pipe jacking, through the dynamic settlement monitoring of the surface at the pipe jacking site, when the surface bulge exceeds the warning value, the pressure of the mud and water bin is reduced through the main control console of the mechanical pipe jacking equipment. When the surface settlement exceeds the warning value, the pressure of the mud and water bin is increased through the main control console of the mechanical pipe jacking equipment. In this way, when shallow buried mechanical pipe jacking is carried out, the surface settlement is reduced, the disturbance to the surrounding environment and building structures is reduced, and greater damage to surrounding building structures is avoided. While improving the safety of surrounding building structures, it also avoids the disturbance and damage to surrounding buildings that may be caused by conventional construction, saving the corresponding compensation costs and coordinating the manpower and material resources of external units, and increasing the satisfaction of the construction unit and surrounding citizens.

[0020] Beneficial effects of this application:

[0021] 1. When jacking the pipe, avoid uplift or subsidence of the road surface or ground surface due to inadequate monitoring.

[0022] 2. Compared with conventional measurements, dynamic monitoring technology can monitor 24 hours a day and respond to surface deformation in a timely manner to avoid major safety and quality accidents.

[0023] 3. Compared with conventional measurements, the data processing system saves a lot of labor costs.

[0024] 4. Effectively control the disturbance of jacking construction to surrounding buildings.

[0025] 5. Reduce surrounding disturbances, and at the same time reduce the corresponding coordination matters of the construction unit, saving manpower and material resources.

[0026] 6. Reduce all negative impacts caused by construction.

[0027] The aforementioned main scheme of the present application and its further options can be freely combined to form multiple schemes, all of which are schemes that can be adopted and claimed for protection in the present application; and in the present application, (non-conflicting options) can also be freely combined with each other and with other options. After understanding the scheme of the present application, those skilled in the art can understand that there are multiple combinations based on the prior art and common knowledge, all of which are technical schemes to be protected by the present application, and they are not exhaustively listed here. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a monitoring diagram of this application.

[0029] In the figure: 1-pipe jacking working shaft, 2-jacking route, 3-monitoring point, 4-wireless transmission module, 5-data processing system. DETAILED DESCRIPTION

[0030] The following non-limiting examples are provided to illustrate the present application.

[0031] Example 1

[0032] refer to Figure 1 As shown, a construction method for joint control of surface settlement monitoring and mud and water bin is applied to shallow buried mechanical pipe jacking construction, including a pipe jacking working well 1 and a jacking line 2 between the pipe jacking working wells 1.

[0033] During the pipe jacking construction, the GPS intelligent monitoring system is used to conduct dynamic real-time detection of the surface and surrounding areas on the jacking route, and corresponding warning values ​​are set. When the surface uplift or settlement exceeds the warning value, the mud and water pressure in the mechanical pipe jacking mud and water tank is adjusted through the mechanical pipe jacking equipment main control console to balance the groundwater pressure.

[0034] When the ground surface rises and exceeds the warning value, the pressure in the mud and water bin is reduced through the main control console of the mechanical pipe jacking equipment; when the ground surface sinks and exceeds the warning value, the pressure in the mud and water bin is increased through the main control console of the mechanical pipe jacking equipment; this effectively prevents the excavation surface and the ground from continuing to rise or sink.

[0035] The GPS intelligent monitoring system includes a GPS monitoring unit (also called a sensor system), a data communication unit (also called a wireless transmission module 4) and a data processing and control unit (GPSensor software part). The GPS monitoring unit is used for real-time on-site data monitoring, the data communication unit is used for wireless data transmission, and the data processing and control unit is used to receive data, process data and perform equipment control.

[0036] The GPS monitoring unit uses GPS to respond to structural responses and feeds back digital signals to the data communication unit. The GPS monitoring units are arranged in a dot matrix on the jacking line. Figure 1 The monitoring point 3 in the middle ensures the monitoring coverage of the entire jacking line 2 and the surrounding area, ensuring that there are no blind spots in the monitoring.

[0037] The data communication unit (also called wireless transmission module 4) transmits the data collected by GPS to the data processing and control unit (also called data processing system 5) by wireless means. The data processing and control unit receives and processes the data collected by the GPS monitoring unit in real time, and displays the original data and processed data, performs online evaluation and early warning.

[0038] The equipment for the mechanical pipe jacking equipment control console is the slurry balance tunnel boring machine, that is, the equipment for tunneling at the front end of the jacking pipe is the slurry balance tunnel boring machine. The mechanical pipe jacking equipment control console is equipped with a pressure gauge that displays the pressure of the slurry bin. The mechanical pipe jacking equipment control console includes the machine's internal slurry valve control system, deviation correction control system, power control system, main top control system and slurry pump system.

[0039] The internal mud valve control system is used to control the start and stop of the mud discharge valve, the start and stop of the bypass valve, the start and stop of the front water supply, and the start and stop of the lower water supply. The correction control system is used to control the start and stop of the correction pump, the start and stop of the external water supply, and the extension and retraction of the upper left, upper right, lower left and lower right correction cylinders. The power control system is used to control the forward, reverse, stop, acceleration and deceleration of the cutter head. The main top control system is used to control the start and stop of the pump station, and the extension, retraction and stop of the main top cylinder. The pressure of the mud tank is controlled by the mud pump system, which is used to control the start and stop of the booster pump, mud discharge pump, relay pump and water intake pump.

[0040] The aforementioned basic examples and their further selected examples can be freely combined to form multiple embodiments, all of which are embodiments that can be adopted and claimed for protection in this application. In the scheme of this application, each selected example can be arbitrarily combined with any other basic examples and selected examples.

[0041] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A construction method for joint control of surface settlement monitoring and mud and water bin, characterized in that: include: During the pipe jacking construction, the GPS intelligent monitoring system is used to conduct dynamic real-time detection of the surface and surrounding areas on the jacking route, and corresponding warning values ​​are set. When the surface uplift or settlement exceeds the warning value, the mud and water pressure in the mechanical pipe jacking mud and water tank is adjusted through the mechanical pipe jacking equipment main control console to balance the groundwater pressure.

2. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 1 is characterized by: When the ground surface rises and exceeds the warning value, the pressure in the mud and water tank is reduced through the main control console of the mechanical pipe jacking equipment; when the ground surface sinks and exceeds the warning value, the pressure in the mud and water tank is increased through the main control console of the mechanical pipe jacking equipment.

3. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 1 is characterized by: The GPS intelligent monitoring system includes a GPS monitoring unit, a data communication unit and a data processing and control unit.

4. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 3 is characterized by: The GPS monitoring unit reflects the structural response through GPS and feeds back the digital signal to the data communication unit.

5. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 3 or 4 is characterized in that: The GPS monitoring units are arranged in a dot matrix on the jacking line.

6. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 3 is characterized by: The data communication unit transmits the data collected by GPS to the data processing and control unit in a wireless manner.

7. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 3 is characterized by: The data processing and control unit receives and processes the data collected by the GPS monitoring unit in real time, and displays, evaluates and warns the original data and processed data online.

8. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 1 is characterized by: The mechanical pipe jacking equipment master control console is designed for slurry balance tunnel boring machines. The mechanical pipe jacking equipment master control console includes the machine's internal slurry valve control system, deviation correction control system, power control system, main top control system and slurry pump system.

9. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 8 is characterized by: The mud and water valve control system in the machine is used to control the start and stop of the mud discharge valve, the start and stop of the bypass valve, the start and stop of the front water supply and the start and stop of the lower water supply; the correction control system is used to control the start and stop of the correction pump, the start and stop of the external water supply, and the extension and retraction of the upper left, upper right, lower left and lower right correction cylinders; the power control system is used to control the forward, reverse, stop, acceleration and deceleration of the cutter disc; the main top control system is used to control the start and stop of the pump station, and the extension, retraction and stop of the main top cylinder; the pressure of the mud and water bin is controlled by the mud and water pump system, and the mud and water pump system is used to control the start and stop of the booster pump, mud discharge pump, relay pump and water inlet pump.

10. The construction method for ground subsidence monitoring and mud-water bin joint control according to claim 1 is characterized by: This construction method is applied to shallow buried mechanical pipe jacking construction.