Foam performance measuring device and method for engine dry type lubricating system
By designing a foam performance measurement device for simulating engine dry lubrication systems, the problem that existing technology cannot accurately measure foam performance is solved, the simulation of lubricating oil flow and the accurate measurement of foam characteristic parameters are realized, and the measurement efficiency and Accuracy.
Patent Information
- Application Number
- CN202411097709.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-10-15
AI Technical Summary
The existing foam performance measurement method cannot accurately simulate the generation of foam in the engine's dry lubrication system, and cannot effectively restore the flow of lubricating oil in the oil tank, resulting in inaccurate foam performance measurement.
A device including a lubricating oil circulation system, an electrical control system and a foam measurement system was designed. By simulating the lubricating oil flow process in the engine, the lubricating oil temperature, gas content and injection angle were controlled, and computer control was used to measure the foam characteristic parameters, including the maximum Bubble height, half-life and conductivity.
It realizes the simulation of the lubricating oil foam generation process under different engine working conditions in a laboratory environment, improves the accuracy and efficiency of foam performance measurement, reduces labor costs, and can effectively measure the foaming properties and stability of foam.
Smart Images

Figure CN118777534A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of measuring the foam performance of lubricating oil, and in particular relates to a foam performance measuring device and method for a dry lubrication system of an engine. Background Art
[0002] An efficiently functioning lubrication system is a core element to ensure stable and efficient engine operation. However, the unique working principle of the dry lubrication system will cause gas to be entrained in the oil and form foam in the external oil tank, which may cause problems such as changes in the properties of the lubricating oil, the production of colloid and acidic substances, reduced lubrication, and corrosion of metal surfaces. The continued presence of foam will also increase the dilution of the lubricating oil, affect its function, and may cause overflow.
[0003] The research on the performance of foam systems mainly focuses on the foaming ability of the solution (the ease of foaming) and the stability of the foam (the ease of foam breaking). These properties are affected by many factors, including the properties of the solution, the physical or chemical conditions of foaming, and the detection method. The commonly used foaming methods are pouring method, oscillation method, stirring method and airflow method. However, each method has limitations. For example, the pouring method is simple, efficient, and has good repeatability. It is closer to the real foam generation method of the dry lubrication system, but the existing device cannot control the various variables in the real system, such as simulating the injection liquid beam with a certain gas content. Due to the complex operating conditions of the engine and the unique flow mode of the lubricating oil in the dry lubrication system, the above method cannot accurately restore the flow of the lubricating oil in the oil tank. Therefore, simply using the above method to simulate the foam generation in the oil tank of the engine dry lubrication system may not be able to obtain the accurate foam performance of the lubricating oil in the oil tank under various conditions.
[0004] With the development of technology, modern measurement methods such as optical method, conductivity method and high-energy particle method are gradually applied to foam research, so that parameters such as foam morphology, size, distribution and liquid content can be accurately obtained, which promotes the automation and refinement of research. Thanks to the update and upgrade of measurement methods, in addition to traditional indicators such as foam height, volume and half-life, some characteristic parameters are gradually used to evaluate foam performance, such as foam liquid content measured by conductivity method and bubble size distribution measured by optical method. In response to the above challenges, the present invention proposes a foam performance measurement device and method for engine dry lubrication system. Summary of the invention
[0005] The object of the present invention is to provide a foam performance measuring device and method for an engine dry lubrication system, aiming to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above object, the present invention provides the following technical solutions:
[0007] A foam performance measuring device for an engine dry lubrication system, comprising:
[0008] Lubricating oil circulation system, used to simulate the flow process of lubricating oil in the engine;
[0009] Electrical control system, used to control the operation of electrical equipment;
[0010] Foam measurement system, used to observe and measure foam characteristic parameters;
[0011] The lubricating oil circulation system comprises a liquid reservoir, a filter set 1, a gear pump 1, a gear pump 2, a waste liquid tank, a ball valve 1, a temporary storage tank, a filter set 2, a heating plate, a filter, a pressure gauge 1, a pressure relief valve 1, a gear pump 3, a gear pump 4, a flow meter, a pressure relief valve 2, a pressure gauge 2, a foam observation tank, an injection pipe, an angle adjustment mechanism, an air source, a ball valve 2, a ball valve 3, a ball valve 4 and a ball valve 5; the lower part of the temporary storage tank is connected to the outlet of the gear pump 1 through a ball valve 1, and a filter set 1 is installed at the end of the inlet pipeline of the gear pump 1, and the filter set 1 extends below the liquid level of the liquid reservoir, and the liquid reservoir is used to hold experimental oil and provide oil for the experiment; the temporary storage tank is installed outside A heating plate is used to control the temperature of the lubricating oil to simulate the temperature changes of the engine under different working conditions; the temporary storage box is connected to the air source through a ball valve 2, and the air source is used to introduce specific gas into the circulation; a pressure gauge 1 and a pressure relief valve 1 are installed on the temporary storage box to control the pressure in the temporary storage box to simulate the pressure changes in the crankcase; the bottom of the temporary storage box is connected to the inlet of the gear pump 2 through a ball valve 3, and the outlet of the gear pump 2 is connected to the waste liquid tank; the inlet pipeline of the gear pump 4 is connected to the filter and the filter 2 in sequence, the filter 2 extends below the liquid level of the temporary storage box, and the outlet pipeline of the gear pump 4 is connected to the injection pipe in the foam observation box; the rear part of the injection pipe is assembled with the angle adjustment mechanism;
[0012] A ruler is attached to one side of the foam observation box; the foam observation box is connected to the air source through a ball valve five; a pressure relief valve two and a pressure gauge two are installed on the foam observation box to regulate the pressure in the foam observation box so that it is at the experimental setting pressure; the bottom of the foam observation box is connected to the gear pump three inlet pipelines through a flow meter and a ball valve four, and the gear pump three outlet pipelines extend below the liquid level of the temporary storage box;
[0013] The foam measurement system includes an LED lamp, an electrode sheet, a camera and an electric lifting platform; a plurality of pairs of electrode sheets are installed at different heights above the liquid surface on the inner wall of the foam observation box; the camera is installed on the electric lifting platform and placed on the side of the foam observation box with a ruler attached;
[0014] The electrical control system includes an electric control box and a computer; the electric control box is provided with a controller or control module of related equipment, including: four frequency converters for controlling the normal operation of gear pump 1, gear pump 2, gear pump 3 and gear pump 4; a temperature controller 1 for controlling the heating plate to reach a set temperature and a temperature controller 2 for controlling the heating belt to reach a set temperature; a light source controller for setting the working conditions of the LED lamp; a control module for controlling the normal operation of the stepper motor; a current detection module and a power supply connected to the electrode sheet, each channel of the current detection module detecting the current between pairs of electrode sheets at different positions; the controller or control module in the electric control box is connected to the computer.
[0015] Furthermore, the angle adjustment mechanism includes a stepper motor, a turntable and a tube clamp; the turntable is a circular disk, and a tube clamp seat is provided at the edge of one side of the disk, and the tube clamp seat is used to install the tube clamp; a shaft is provided at the center position of the other side of the circular disk, and the shaft passes through the foam observation box and is connected to the stepper motor, and bearings and oil seals are installed at the contact between the shaft and the foam observation box for transmission and sealing; the bending center of the injection pipe is located on the axis of the turntable; the tube clamp is used to fix the injection pipe.
[0016] Furthermore, the temporary storage box is made of metal material and is a closed container, and the joints on the temporary storage box are all sealed.
[0017] Furthermore, the foam observation box is made of transparent glass or organic plastic and is a closed container, and the joints on the foam observation box are all sealed.
[0018] Furthermore, a heating belt is wound around the connecting pipeline between the temporary storage box and the second ball valve and the connecting pipeline between the foam observation box and the fifth ball valve.
[0019] Furthermore, the injection pipe is made of a deformable corrugated pipe or an oil-resistant hose.
[0020] A method for measuring using the measuring device as described above comprises the following steps:
[0021] Step 1: Add the experimental test oil into the liquid reservoir, connect the gas source containing the experimental gas to the pipeline; turn on the computer and each module or device in the electric control box, and turn on the camera;
[0022] Step 2: adjust the opening pressure of the pressure relief valve 1 and the pressure relief valve 2 to atmospheric pressure, and control the gear pump 1 through the computer to suck a certain amount of experimental oil into the temporary storage tank through the ball valve 1; adjust the filter 2 to extend to a set depth below the liquid level of the temporary storage tank; and control the angle adjustment mechanism through the computer to drive the injection pipe to bend to a set angle;
[0023] Step 3: After running gear pump 3 for a period of time through the computer, open ball valve 4, set the same flow rate to run gear pump 4, set the temperature of the heating plate and heating belt, turn on the gas source, set the pressure, and run for a period of time;
[0024] Step 4: After the working condition is stable, adjust the opening pressure of the pressure relief valve 1 and the pressure relief valve 2, observe whether the pressure measured by the pressure gauge 1 and the pressure gauge 2 is consistent with the setting, make the foam observation box under the experimental setting air pressure, set the flow rate of the gear pump 3 and the gear pump 4 through the computer, fill the outlet pipeline of the gear pump 4 with the experimental setting air content through the suction flow difference, and observe whether the flow rate measured by the flow meter is consistent with the setting;
[0025] Step 5: Set the LED light and camera parameters through the computer, move the electric lifting platform to a suitable height so that the camera can capture the top of the foam, and record the maximum foaming height h max , by moving the electric lifting platform to a suitable height so that the camera can capture the bottom of the foam, and record the drop distance d of the liquid level at this time, which is calculated by h max The maximum foaming volume V is obtained by analyzing the foam max and the maximum discharge volume V of the foam lmax ;
[0026] Step 6, stop gear pump 3 and gear pump 4, let the foam evolve naturally, and then start timing to record the half-life T1 and the dissipation period T2 of the foam; after timing, move the camera through the electric lifting platform to shoot the bubble size distribution of the foam at different times and heights; after timing, set the computer to start recording the current value measured by the electrode sheet at each position, and calculate the conductivity value σ, and finally calculate the liquid fraction ε of the foam;
[0027] Step 7: If the experiment is completed, turn off gear pump 4, pump the oil back to the temporary storage tank through gear pump 3, open ball valve 3, set the flow rate of gear pump 2 through the computer, pump the experimental oil into the waste liquid tank, and turn off the equipment;
[0028] Step 8: if the foam performance under different lubricating oil temperature, gas temperature, injection angle, injection flow rate and gas content setting values is measured, the setting values of the corresponding variables are changed by computer, and after stabilization, steps 5 and 6 are repeated to measure the corresponding foam performance;
[0029] Step 9: If the foam performance under different gas types is measured, change the gas source, wait for it to stabilize, and repeat steps 5 and 6 to measure the corresponding foam performance;
[0030] Step 10: If the foam performance under different ambient pressures is to be measured, adjust the pressure relief valve 2, and after stabilization, repeat steps 5 and 6 to measure the corresponding foam performance;
[0031] Step 11: If the foam performance at different liquid level heights is to be measured, stop gear pump 3 and gear pump 4, adjust the distance of filter 2 extending below the liquid level, and repeat steps 5 and 6 after stabilization to measure the corresponding foam performance;
[0032] Step 12: If the foam performance under different spray diameters is measured, stop gear pump 3 and gear pump 4, replace spray pipes with different diameters, and repeat steps 5 and 6 after stabilization to measure the corresponding foam performance;
[0033] Step 13. If the foam performance under different oil products is measured, turn off gear pump 4, pump the oil back to the temporary storage tank through gear pump 3, set gear pump 2 through the computer, pump the experimental oil into the waste liquid tank, replace the oil in the liquid reservoir, repeat steps 2 and 3, clean the pipeline, repeat step 7 to remove the waste oil, and then repeat steps 2 to 6. After stabilization, measure the corresponding foam performance.
[0034] Compared with the prior art, the present invention has the following beneficial effects:
[0035] The present invention simulates the operating state of the dry lubrication system of the engine under different working conditions in a laboratory environment, restores the generation process of lubricating oil foam in the oil tank, and avoids the risk of poor lubrication and body damage caused by improper parameter selection when conducting experiments on the engine. The present invention can observe and measure the characteristic parameters of the foam, obtain the foam performance under different engine working conditions, and has practical significance for measuring the foaming and stability of the foam under different working conditions. In the present invention, the lubricating oil temperature, gas temperature, injection angle, injection flow rate and gas content can be set and adjusted by a computer, which improves the experimental efficiency and accuracy. In addition, the angle adjustment mechanism and the deformable injection tube are used, so that the adjustment of the injection angle can be controlled by a computer, reducing labor costs. The present invention can measure the foaming, stability and bubble size distribution of the foam, and the measurement of the foam performance is more comprehensive, and is uniformly controlled by a computer, which greatly improves the measurement accuracy and efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 It is a structural schematic diagram of the present invention.
[0037] Figure 2 It is a structural schematic diagram of the angle adjustment mechanism in the present invention.
[0038] In the figure: 1-liquid reservoir; 2-filter collection device 1; 3-gear pump 1; 4-gear pump 2; 5-waste liquid tank; 6-ball valve 1; 7-temporary storage box; 8-filter collection device 2; 9-heating plate; 10-filter; 11-pressure gauge 1; 12-pressure relief valve 1; 13-gear pump 3; 14-gear pump 4; 15-LED lamp; 16-flow meter; 17-pressure relief valve 2; 18-pressure gauge 2; 19-foam observation box; 20-injection pipe; 21-angle adjustment mechanism; 211-stepping motor; 212-turntable; 213-pipe clamp; 22-electrode sheet; 23-camera; 24-electric control box; 25-computer; 26-electric lifting platform; 27-gas source; 28-ball valve 2; 29-ball valve 3; 30-ball valve 4; 31-ball valve 5; 32-heating belt. DETAILED DESCRIPTION
[0039] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0040] The specific implementation of the present invention is described in detail below in conjunction with specific embodiments.
[0041] like Figure 1 As shown, a foam performance measuring device for an engine dry lubrication system provided by one embodiment of the present invention comprises:
[0042] Lubricating oil circulation system, used to simulate the flow process of lubricating oil in the engine;
[0043] Electrical control system, used to control the operation of electrical equipment;
[0044] Foam measurement system, used to observe and measure foam characteristic parameters;
[0045] like Figure 1 and Figure 2 As shown, as a preferred embodiment of the present invention, the lubricating oil circulation system includes a liquid reservoir 1, a filter 2, a gear pump 3, a gear pump 4, a waste liquid tank 5, a ball valve 6, a temporary storage tank 7, a filter 8, a heating plate 9, a filter 10, a pressure gauge 11, a pressure relief valve 12, a gear pump 3 13, a gear pump 4 14, a flow meter 16, a pressure relief valve 2 17, a pressure gauge 2 18, a foam observation box 19, an injection pipe 20, an angle adjustment mechanism 21, an air source 27, a ball valve 2 28, a ball valve 3 29, a ball valve 4 30, a ball valve 5 31 and a heating belt 32;
[0046] The temporary storage box 7 is made of metal material (preferably made of stainless steel, with a volume of 80L), and is a closed container. The joints on it are all sealed and can withstand high temperature and high pressure; a pressure gauge 11 and a pressure relief valve 12 are installed on the temporary storage box 7 to adjust the pressure in the temporary storage box 7 to simulate the pressure change in the crankcase; a heating plate 9 is installed outside the temporary storage box 7, and the heating plate 9 is used to adjust the temperature of the lubricating oil to simulate the temperature change under different working conditions of the engine (preferably the heating temperature range is 0-150°C), so as to realize the function of measuring the foam performance under different temperature conditions.
[0047] The lower part of the temporary storage box 7 is connected to the outlet of the gear pump 3 through a ball valve 6. A filter 2 is installed at the end of the inlet pipeline of the gear pump 3. The filter 2 extends into the liquid reservoir 1 below the liquid level near the bottom. The liquid reservoir 1 is used to hold experimental oil and provide oil for the experiment. The liquid reservoir 1 is set on the bottom side of the temporary storage box 7; through the operation of the computer 25, the experimental oil can be accurately provided to the temporary storage box 7 for multiple times in one experiment, thereby improving the experimental efficiency and accuracy.
[0048] The bottom of the temporary storage box 7 is connected to the inlet of the gear pump 2 4 through the ball valve 3 29, and the outlet of the gear pump 2 4 is connected to the waste liquid tank 5. After the experiment, the waste oil in the temporary storage box 7 is promptly pumped out through the gear pump 2 4 so as to start the next experiment and improve the experimental efficiency.
[0049] The temporary storage box 7 is connected to the gas source 27 through the ball valve 28. A heating belt 32 (preferably with a heating temperature range of 0-400°C) is wound around the connecting pipeline between the temporary storage box 7 and the ball valve 28. Since the gas composition in the engine is complex, the required specific non-toxic gas is introduced into the circulation by setting the gas source 27 to realize the function of measuring the foam performance under conditions of different gas types, and is heated to the required temperature for the experiment through the heating belt 32 to simulate the complex gas environment of the crankcase and restore the real gas state.
[0050] The inlet pipeline of the gear pump four 14 is connected to the filter 10 and the filter set 8 in sequence. The filter set 8 extends below the liquid level of the temporary storage tank 7, and the extension distance is adjustable. By changing the distance that the filter set 8 extends below the liquid level, the amount of oil sucked into the foam observation box 19 can be controlled, thereby changing the liquid level height in the foam observation box 19, thereby realizing the function of measuring the foam performance under different liquid level height conditions.
[0051] The injection pipe 20 is connected to the outlet pipe of the gear pump 414 through a pipe connector installed on the upper part of the foam observation box 19. The rear part of the injection pipe 20 is assembled with an angle adjustment mechanism 21. The material of the injection pipe 20 is a deformable bellows or an oil-resistant hose (preferably a bellows, with a bending angle range of 0-90° and a diameter of 2cm). The angle adjustment mechanism 21 includes a stepper motor 211, a turntable 212 and a pipe clamp 213; the turntable 212 is a circular disk, and a pipe clamp seat is provided at the edge of one side of the disk, and the pipe clamp seat is used to install the pipe clamp 213; a shaft is provided at the center position of the other side of the circular disk, and the shaft passes through the foam observation box 19 and is connected to the stepper motor 211. The contact between the shaft and the foam observation box 19 is equipped with a bearing and an oil seal for transmission and sealing; the bending center of the injection pipe 20 is located on the axis of the turntable 212; the pipe clamp 213 is used to fix the injection pipe 20. When the angle of the injection pipe 20 needs to be adjusted, the stepper motor 211 drives the turntable 212 to rotate to bend the injection pipe 20 at a certain angle, thereby realizing variable control of the injection angle and simulating different injection angles of the oil beam in the engine oil tank.
[0052] The foam observation box 19 is made of transparent glass or organic plastic (preferably ultra-white glass), and is a closed container. The joints on it are sealed and can withstand high temperature and high pressure. A ruler is attached to one side of the foam observation box 19 for the camera 23 to take pictures and measure the foam height. The foam observation box 19 is connected to the gas source 27 through the ball valve five 31, and a heating belt 32 (preferably the heating temperature range is 0-400°C) is wrapped around the connecting pipeline between the foam observation box 19 and the ball valve five 31; a pressure relief valve two 17 and a pressure gauge two 18 are installed on the foam observation box 19 to regulate the pressure in the foam observation box 19 to keep it at the experimental setting pressure and restore the real gas state in the engine oil tank; the bottom of the foam observation box 19 is connected to the inlet pipeline of the gear pump three 13 through the flow meter 16 and the ball valve four 30, and the outlet pipeline of the gear pump three 13 extends below the liquid level of the temporary storage box 7. By setting the flow rate of the gear pump four 14 and the flow rate of the gear pump three 13 in the experiment, the gas content in the oil extracted from the temporary storage box 7 can be controlled, and the function of measuring the foam performance under different gas content conditions can be achieved.
[0053] In the embodiment of the present invention, the spray pipe 20 is independent of the pipeline and the angle adjustment mechanism 21, so it is easy to replace the spray pipe 20 to achieve the function of measuring the foam performance under different spray diameter conditions.
[0054] Two gear pumps, gear pump three 13 and gear pump four 14, are designed for oil circulation. By setting the flow rate of gear pump four 14 greater than that of gear pump three 13, gear pump four 14 can pump out part of the gas while sucking oil, so that the injection oil beam contains a certain amount of gas, thereby realizing variable control of the injection flow rate and the gas content in the injection liquid beam, and being able to restore the real injection state of the engine dry lubrication system.
[0055] like Figure 1 As shown in the figure, as a preferred embodiment of the present invention, the foam measurement system includes an LED lamp 15, an electrode sheet 22, a camera 23 and an electric lifting platform 26; a plurality of pairs of electrode sheets 22 (preferably 2 pairs of electrode sheets are installed, and the position and number of the electrode sheets 22 are not limited to) are installed at different heights above the liquid surface on the inner wall of the foam observation box 19. Figure 1 In the embodiment shown, the position and number of the electrode sheets 22 can be adjusted according to actual needs), and the electrode sheets 22 are connected in sequence to the power supply and current detection module in the electrical control system to form a closed loop, which can measure the conductivity of foams at different heights; the camera 23 is installed on the electric lifting platform 26 and placed on the side of the foam observation box 19 with a ruler attached. The height of the electric lifting platform 26 (preferably the lifting height is 0-50cm) can be controlled by the computer 25 of the electrical control system to capture and record the foam within a certain height range; the LED lamp 15 is placed on the opposite side of the camera 23 to illuminate the shooting area and improve the shooting quality. The power of the LED lamp is preferably 50W.
[0056] like Figure 1 As shown, as a preferred embodiment of the present invention, the electrical control system includes an electric control box 24 and a computer 25; the electric control box 24 is provided with a controller or control module of related equipment, including: four frequency converters for controlling the normal operation of gear pump 1 3, gear pump 2 4, gear pump 3 13 and gear pump 4 14; a temperature controller 1 for controlling the heating plate 9 to reach a set temperature and a temperature controller 2 for controlling the heating belt 32 to reach a set temperature; a light source controller for setting the working conditions of the LED lamp 15; a control module for controlling the normal operation of the stepper motor 211; a current detection module and a power supply connected to the electrode sheet 22, each channel of the current detection module detects the current between electrode pairs at different positions; the controller or control module in the electric control box 24 is connected to the computer 25, and can control the related equipment on the computer 25, simplifying the experimental operation, and improving the experimental efficiency and accuracy.
[0057] One embodiment of the present invention provides a method for measuring using the measuring device as described above, comprising the following steps:
[0058] Step 1: Add the experimental test oil into the liquid reservoir 1 according to the experimental needs, connect the gas source 27 filled with experimental gas to the pipeline, turn on the computer 25 and each module or device in the electric control box 24, and turn on the camera 23;
[0059] Step 2: adjust the opening pressure of the pressure relief valve 12 and the pressure relief valve 2 17 to atmospheric pressure, open the ball valve 16, and control the gear pump 13 through the computer 25 to pump 60L of experimental oil into the temporary storage tank 7 at 15L / min; adjust the filter 28 to extend 5 / 6 below the liquid level of the temporary storage tank 7; control the angle adjustment mechanism 21 through the computer 25 to drive the injection pipe 20 to bend 45°;
[0060] Step 3: Set the flow rate of gear pump 3 13 and gear pump 4 14 to 30 L / min through computer 25, set the temperature of heating plate 9 to 80° C., the temperature of heating belt 32 to 200° C., open ball valve 4 30, open ball valve 2 28 and ball valve 5 31, open gas source 27, set the gas source pressure to 5 bar, and run for about 20 minutes;
[0061] Step 4: After the oil temperature reaches the set temperature and the temporary storage box 7 and the foam observation box 19 are filled with experimental gas, adjust the opening pressure of the pressure relief valve 12 to 1 bar and the opening pressure of the pressure relief valve 2 17 to 3 bar, observe whether the pressure measured by the pressure gauge 11 and the pressure gauge 2 18 is consistent with the setting, make the foam observation box 19 under the experimental set air pressure of 3 bar, set the flow rate of the gear pump 3 13 to 25L / min through the computer 25, and fill the outlet pipeline of the gear pump 4 14 with the experimental set gas content through the suction flow difference, and the oil mixed with gas is ejected through the injection pipe 20 to impact the liquid surface in the foam observation box 19 to generate foam, and observe whether the flow rate measured by the flow meter 16 is consistent with the setting;
[0062] Step 5: Set the parameters of the LED light 15 and the camera 23 through the computer 25 to optimize the image quality. Move the electric lifting platform 26 to a suitable height so that the camera 23 can capture the top of the foam and record the maximum foaming height h of the foam. max , using the formula V max = Sh to obtain the maximum foam volume V max , where S is the bottom area of the foam observation box 19; by moving the electric lift 26 to a suitable height so that the camera 23 can capture the bottom of the foam, record the drop distance d of the liquid level at this time, and use the formula V lmax = Sd to obtain the maximum foam discharge V lmax ;
[0063] Step 6: Stop gear pump 3 13 and gear pump 4 14, and let the foam evolve naturally. At this time, start timing until the foam reaches the maximum foaming volume V max When the foam is half of the original time, the recorded time T1 is the half-life of the foam, and when the foam is completely dissipated, the recorded time T2 is the dissipation period of the foam; after timing, the electric lifting platform 26 is used to move the camera 23 to shoot the bubble size distribution of the foam at different times and heights; after timing, the computer 25 is set to start recording the current value measured by the electrode sheet at each position, and then the conductivity value σ is calculated. According to the relationship between the conductivity value σ and the liquid fraction ε provided by researchers such as K Feitosa, the liquid fraction ε at different positions and at different times and the change of the liquid fraction ε with the evolution of the foam can be calculated;
[0064] Step 7. If the experiment is completed, turn off the gear pump 4 14, pump the oil back to the temporary storage box 7 through the gear pump 3 13, open the ball valve 3 29, set the flow rate of the gear pump 2 4 to 10L / min through the computer 25, pump the experimental oil into the waste liquid tank 5, and hand it over to professionals for subsequent processing, and turn off the equipment.
[0065] In the embodiment of the present invention, if the experiment has other special requirements, the injection process can be adjusted according to the actual situation to meet the experimental requirements. For example:
[0066] If the foam performance under different lubricating oil temperature, gas temperature, injection angle, injection flow rate and gas content setting values is measured, the corresponding variable setting values are changed by computer 25, and after stabilization, steps 5 and 6 are repeated to measure the corresponding foam performance;
[0067] If the foam performance under different gas types is measured, the gas source 27 is replaced, and after stabilization, steps 5 and 6 are repeated to measure the corresponding foam performance;
[0068] If the foam performance under different ambient pressures is measured, adjust the pressure relief valve 17, and after stabilization, repeat steps 5 and 6 to measure the corresponding foam performance;
[0069] If the foam performance at different liquid level heights is measured, the gear pump 3 13 and the gear pump 4 14 are stopped, and the distance of the filter 2 8 extending below the liquid level is adjusted. After stabilization, steps 5 and 6 are repeated to measure the corresponding foam performance;
[0070] If the foam performance under different spray diameters is measured, the gear pump three 13 and the gear pump four 14 are stopped, and spray pipes with different diameters are replaced. After stabilization, steps five and six are repeated to measure the corresponding foam performance;
[0071] If the foam performance under different oil products is measured, turn off gear pump four 14, pump the oil back to the temporary storage box 7 through gear pump three 13, set gear pump two 4 through computer 25, pump the experimental oil into the waste liquid tank 5, replace the oil in the liquid reservoir 1, repeat steps two and three, clean the pipeline, repeat step seven to remove the waste oil, and then repeat steps two to six. After stabilization, measure the corresponding foam performance.
[0072] The above are only preferred embodiments of the present invention. It should be pointed out that, for those skilled in the art, several modifications and improvements can be made without departing from the concept of the present invention. These should also be regarded as the protection scope of the present invention. These will not affect the effect of the implementation of the present invention and the practicality of the patent.
Claims
1. A foam performance measuring device for an engine dry lubrication system, characterized in that: include: Lubricating oil circulation system, used to simulate the flow process of lubricating oil in the engine; Electrical control system, used to control the operation of electrical equipment; Foam measurement system, used to observe and measure foam characteristic parameters; The lubricating oil circulation system comprises a liquid reservoir, a filter set 1, a gear pump 1, a gear pump 2, a waste liquid tank, a ball valve 1, a temporary storage tank, a filter set 2, a heating plate, a filter, a pressure gauge 1, a pressure relief valve 1, a gear pump 3, a gear pump 4, a flow meter, a pressure relief valve 2, a pressure gauge 2, a foam observation box, an injection pipe, an angle adjustment mechanism, an air source, a ball valve 2, a ball valve 3, a ball valve 4 and a ball valve 5; the lower part of the temporary storage tank is connected to the outlet of the gear pump 1 through the ball valve 1, and the end of the inlet pipeline of the gear pump 1 is equipped with a filter set 1, and the filter set 1 extends below the liquid level of the liquid reservoir, and the liquid reservoir is used to hold experimental oil and provide oil for the experiment; a heating plate is installed on the outside of the temporary storage tank, and the heating plate is used to adjust the temperature of the lubricating oil to simulate the temperature change under different working conditions of the engine; the temporary storage tank is connected to the air source through the ball valve 2, and the air source is used to introduce specific gas into the circulation; A pressure gauge 1 and a pressure relief valve 1 are installed on the temporary storage box to adjust the pressure in the temporary storage box to simulate the pressure change in the crankcase; the bottom of the temporary storage box is connected to the inlet of the gear pump 2 through the ball valve 3, and the outlet of the gear pump 2 is connected to the waste liquid tank; the inlet pipeline of the gear pump 4 is connected to the filter and the filter set 2 in sequence, the filter set 2 extends below the liquid level of the temporary storage box, and the outlet pipeline of the gear pump 4 is connected to the injection pipe in the foam observation box; the rear part of the injection pipe is assembled with the angle adjustment mechanism; A ruler is attached to one side of the foam observation box; the foam observation box is connected to the air source through a ball valve five; a pressure relief valve two and a pressure gauge two are installed on the foam observation box to regulate the pressure in the foam observation box so that it is at the experimental setting pressure; the bottom of the foam observation box is connected to the gear pump three inlet pipeline through a flow meter and a ball valve four, and the gear pump three outlet pipeline extends below the liquid level of the temporary storage box; The foam measurement system includes an LED lamp, an electrode sheet, a camera and an electric lifting platform; a plurality of pairs of electrode sheets are installed at different heights above the liquid surface on the inner wall of the foam observation box; the camera is installed on the electric lifting platform and placed on the side of the foam observation box with a ruler attached; The electrical control system includes an electric control box and a computer; the electric control box is provided with a controller or control module of related equipment, including: four frequency converters for controlling the normal operation of gear pump 1, gear pump 2, gear pump 3 and gear pump 4; a temperature controller 1 for controlling the heating plate to reach a set temperature and a temperature controller 2 for controlling the heating belt to reach a set temperature; a light source controller for setting the working conditions of the LED lamp; a control module for controlling the normal operation of the stepper motor; a current detection module and a power supply connected to the electrode sheet, each channel of the current detection module detecting the current between pairs of electrode sheets at different positions; the controller or control module in the electric control box is connected to the computer.
2. The foam performance measuring device for engine dry lubrication system according to claim 1, characterized in that: The angle adjustment mechanism includes a stepper motor, a turntable and a tube clamp; the turntable is a circular disk, and a tube clamp seat is provided at the edge of one side of the disk, and the tube clamp seat is used to install the tube clamp; a shaft is provided at the center position of the other side of the disk, and the shaft passes through the foam observation box and is connected to the stepper motor. Bearings and oil seals are installed at the contact between the shaft and the foam observation box for transmission and sealing; the bending center of the injection pipe is located on the axis of the turntable; the tube clamp is used to fix the injection pipe.
3. The foam performance measuring device for engine dry lubrication system according to claim 1, characterized in that: The temporary storage box is made of metal material and is a closed container, and the joints on the temporary storage box are all sealed.
4. The foam performance measuring device for an engine dry lubrication system according to claim 1, characterized in that: The foam observation box is made of transparent glass or organic plastic and is a closed container, and the joints on the foam observation box are all sealed.
5. The foam performance measuring device for engine dry lubrication system according to claim 1, characterized in that: A heating belt is wound around the connecting pipeline between the temporary storage box and the second ball valve, and the connecting pipeline between the foam observation box and the fifth ball valve.
6. The foam performance measuring device for engine dry lubrication system according to claim 1, characterized in that: The injection pipe is made of a deformable corrugated pipe or an oil-resistant hose.
7. A method for measuring using the measuring device according to any one of claims 1 to 6, comprising the following steps: Step 1: Add the experimental test oil into the liquid reservoir and connect the gas source containing the experimental gas to the pipeline; Turn on the computer and each module or device in the electric control box, and turn on the camera; Step 2: adjust the opening pressure of the pressure relief valve 1 and the pressure relief valve 2 to atmospheric pressure, and control the gear pump 1 through the computer to suck a certain amount of experimental oil into the temporary storage tank through the ball valve 1; adjust the filter 2 to extend to a set depth below the liquid level of the temporary storage tank; and control the angle adjustment mechanism through the computer to drive the injection pipe to bend to a set angle; Step 3: After running gear pump 3 for a period of time through the computer, open ball valve 4, set the same flow rate to run gear pump 4, set the temperature of the heating plate and heating belt, turn on the gas source, set the pressure, and run for a period of time; Step 4: After the working condition is stable, adjust the opening pressure of the pressure relief valve 1 and the pressure relief valve 2, observe whether the pressure measured by the pressure gauge 1 and the pressure gauge 2 is consistent with the setting, make the foam observation box under the experimental setting air pressure, set the flow rate of the gear pump 3 and the gear pump 4 through the computer, fill the outlet pipeline of the gear pump 4 with the experimental setting air content through the suction flow difference, and observe whether the flow rate measured by the flow meter is consistent with the setting; Step 5: Set the LED light and camera parameters through the computer, move the electric lifting platform to a suitable height so that the camera can capture the top of the foam, and record the maximum foaming height h max , by moving the electric lifting platform to a suitable height so that the camera can capture the bottom of the foam, and record the drop distance d of the liquid level at this time, which is calculated by h max The maximum foaming volume V is obtained by analyzing the foam max and the maximum discharge volume V of the foam lmax ; Step 6, stop gear pump 3 and gear pump 4, let the foam evolve naturally, and then start timing to record the half-life T1 and the dissipation period T2 of the foam; after timing, move the camera through the electric lifting platform to shoot the bubble size distribution of the foam at different times and heights; after timing, set the computer to start recording the current value measured by the electrode sheet at each position, and calculate the conductivity value σ, and finally calculate the liquid fraction ε of the foam; Step 7: If the experiment is completed, turn off gear pump 4, pump the oil back to the temporary storage tank through gear pump 3, open ball valve 3, set the flow rate of gear pump 2 through the computer, pump the experimental oil into the waste liquid tank, and turn off the equipment; Step 8: if the foam performance under different lubricating oil temperature, gas temperature, injection angle, injection flow rate and gas content setting values is measured, the setting values of the corresponding variables are changed by computer, and after stabilization, steps 5 and 6 are repeated to measure the corresponding foam performance; Step 9: If the foam performance under different gas types is measured, change the gas source, wait for it to stabilize, and repeat steps 5 and 6 to measure the corresponding foam performance; Step 10: If the foam performance under different ambient pressures is to be measured, adjust the pressure relief valve 2, and after stabilization, repeat steps 5 and 6 to measure the corresponding foam performance; Step 11: If the foam performance at different liquid level heights is to be measured, stop gear pump 3 and gear pump 4, adjust the distance of filter 2 extending below the liquid level, and repeat steps 5 and 6 after stabilization to measure the corresponding foam performance; Step 12: If the foam performance under different spray diameters is measured, stop gear pump 3 and gear pump 4, replace spray pipes with different diameters, and repeat steps 5 and 6 after stabilization to measure the corresponding foam performance; Step 13. If the foam performance under different oil products is measured, turn off gear pump 4, pump the oil back to the temporary storage tank through gear pump 3, set gear pump 2 through the computer, pump the experimental oil into the waste liquid tank, replace the oil in the liquid reservoir, repeat steps 2 and 3, clean the pipeline, repeat step 7 to remove the waste oil, and then repeat steps 2 to 6. After stabilization, measure the corresponding foam performance.
Citation Information
Cited By
Foam quantity detection device for foam drainage gas recovery
CN119936326A
A foam volume detection device for gas production by foam drainage
CN119936326B