Robust scheduling optimization method for cascade hydropower system under condition of uncertain electricity price
By combining prediction and scenario analysis with the White Shark optimization algorithm and long-short-term memory network model, a robust online dispatching scheme is established to solve the impact of electricity price uncertainty on the cascade hydropower system, maximizing settlement income and improving operating efficiency.
Patent Information
- Application Number
- CN202410717772.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-04
- Publication Date
- 2024-10-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Under conditions of uncertain electricity prices, it is difficult for cascade hydropower systems to achieve optimal dispatch, and existing technology cannot effectively manage the impact of electricity price fluctuations on dispatch decisions, resulting in a decline in operating efficiency and economic performance.
Using forecasting, scenario-based stochastic optimization and real-time feedback mechanisms, combined with the White Shark optimization algorithm and long-short-term memory network model, a robust online dispatch plan is established. Through multiple electricity price scenario analysis and dynamic adjustment of dispatch plans, the day-ahead power generation plan is optimized and enhanced Scheduling robustness and adaptability.
It improves the robustness and adaptability of cascade hydropower station dispatching, maximizes settlement income, enhances the optimization effect in the face of complex environments, and improves operating efficiency and economic performance.
Smart Images

Figure CN118780828A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of optimized dispatching of cascade hydropower stations, and in particular to a robust dispatching optimization method for a cascade hydropower system under uncertain electricity price conditions. Background Art
[0002] With the intensification of competition in the power market, the high dynamics of operating conditions, and the increasingly stringent requirements of relevant regulatory agencies on power system operation, the research and application of efficient dispatching methods for power systems, especially cascade hydropower systems, have become particularly important. The core purpose of cascade hydropower system dispatch is to optimize the economic performance of the system and maximize profits while complying with various internal and external constraints of the system.
[0003] The operation of hydropower systems faces uncertainty in electricity prices, and fluctuations in electricity prices will affect scheduling decisions. Therefore, how to accurately predict these parameters and how to develop the best scheduling plan under uncertain conditions have become key issues in the management of cascade hydropower systems.
[0004] In order to meet these challenges, developing efficient scheduling strategies to manage and mitigate the impact of uncertainty has become an important topic in research and practice. These strategies need to be able to comprehensively consider various aspects of the system, including the characteristics of hydropower generation, fluctuations in market electricity prices, and uncertainties in other related parameters. Therefore, how to accurately and effectively solve the problem of uncertainty in the optimal scheduling of cascade hydropower stations is an urgent problem that technicians in this field need to solve. Summary of the invention
[0005] The technical problem to be solved by the present invention is to provide a robust scheduling optimization method for cascade hydropower systems under uncertain electricity prices, which effectively manages the uncertainty in the short-term operation of cascade hydropower systems by combining prediction, scenario-based stochastic optimization and real-time feedback mechanism.
[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is: a robust dispatch optimization method for cascade hydropower stations under the condition of uncertain electricity prices, comprising the following steps: S1. Given the initial data of cascade hydropower stations, including the overall reserved flood control storage capacity of the cascade hydropower stations, the water level-storage capacity curve of each power station, the downstream water level-flow curve and the expected output curve; S2. Optimize modeling with the goal of maximizing the settlement income of cascade hydropower stations during the dispatch period, and complete the day-ahead dispatch modeling of cascade hydropower stations with time period water level constraints, time period output constraints, time period flow constraints, water level fluctuation constraints, water volume balance constraints, power volume balance constraints, hydraulic connections between hydropower stations, and net head calculation formula as constraints; S3, perform uncertainty management and robust optimization, establish stochastic optimization models and robust online scheduling solutions; S4. Use the White Shark optimization algorithm to solve the established scheduling model and determine the initial daily power generation plan; S5. Build an optimization model based on two-stage stochastic programming, consider multiple uncertain scenarios to generate scheduling strategies, adjust the scheduling plan according to the prediction and actual system response feedback, and update the scheduling process of the cascade hydropower system in a rolling manner.
[0007] In the preferred solution, in step S2, the maximum settlement income of the cascade hydropower station during the scheduling period is taken as the optimal goal, and the objective function expression is established as follows: (1) Where, M is the total number of cascade hydropower stations; T is the total number of time periods in the dispatching period; is the time period granularity; m Number the hydroelectric power stations; for t Time m The contract price of electricity from the power station; Predict electricity prices for the day-ahead market clearing of the time period; for t Time m The contracted electricity of power station No. is apportioned to the hourly output; is the total output of power station m during period t.
[0008] In a preferred solution, in step S2, the expressions of the constraints are as follows: Time period water level constraints: (2) In the formula, , , Respectively represent m The minimum water level limit, average water level and maximum water level limit of the power station in the t period; Output constraints during time period: (3) In the formula, , , Respectively represent m Power station t Minimum output limit, average output and maximum output limit for each time period; and Respectively m Power station t The guaranteed output of the time period and the expected output corresponding to the generating head; Time period flow constraints: (4) In the formula, , , Respectively represent m Power station t The minimum downstream flow limit, average downstream flow limit and maximum downstream flow limit for each time period; Water level fluctuation constraints: (5) In the formula, Indicates m Power station t Water level fluctuation during the period; , Respectively represent m Power station t The lower limit and upper limit of water level fluctuation in the time period; Water balance constraints: (6) In the formula, and Respectively m Power station t The initial storage capacity and final storage capacity of the time period; and Respectively m Power station t The inflow and outflow of the time period, The scheduling period is long; Power balance constraints: (7) In the formula, Indicates t The power grid's demand for cascade power station output within a period; Indicates m Power station t Output during the time period; The hydraulic connection between hydropower stations is expressed as follows: (8) In the formula, is the inflow flow of the mth power station in the tth period; For the m-1 The power station is located in t Outbound flow in the time period; is the interval inflow between upstream and downstream adjacent power stations in period t; Net water head calculation formula: (9) In the formula, , 、, Respectively represent m Power station t Net water head of the period, t Water level during this period and downstream of the power station t Water level during the period; is the head loss of the power station at period t.
[0009] In the preferred solution, step S3 specifically includes the following steps: Robust online scheduling solution S3.1. Establish a stochastic optimization model. The first-stage decision is executed before the uncertainty is realized, and the implementation of the second-stage decision is postponed. The first-stage decision is all discrete and continuous decisions within the periodic scheduling interval; the second-stage decision is all discrete and continuous decisions within the remaining part of the scheduling period. The decision is hedged by considering multiple discrete scenarios of possible uncertain parameters of electricity prices; S3.2. Establish a robust online dispatch model, adopt a long short-term memory network model, use the prediction model and historical data to update the predicted values of the uncertain parameters of the electricity price, and then apply the updated predicted values to the stochastic optimization model. Subsequently, the stochastic optimization model is used to analyze various possible scenarios of the uncertain parameters to formulate a dispatch plan.
[0010] In a preferred solution, the specific operation of step S3.1 is as follows: For the uncertain parameters of electricity prices in step S3.1, it is necessary to determine the statistical characteristics of the disturbance, assuming that the disturbance follows a normal distribution ,in Estimated based on the standard deviation of historical forecast errors; Based on the model prediction, add random perturbations to generate multiple scenarios, which can be achieved through the following operations:
[0011] in, Indicates Time in each scenario The electricity price, is the electricity price predicted using the forecasting model, are independent and identically distributed random disturbances.
[0012] In a preferred solution, in step S4, the established scheduling model is solved using the White Shark optimization algorithm, which specifically includes the following steps: S4.1, Initialization: Set the population size G of white sharks, set the maximum number of iterations to 10000, and randomly generate the positions of the white sharks in the initial state, that is, the initial optimization scheduling plan The decision variable of the model is the average power generation flow of each stage of the cascade hydropower station , the initial dispatching plan is generated according to the random number simulation through the power generation reference flow constraint condition; S4.2, Speed update: White sharks spend most of their time hunting and tracking prey. In the framework of the white shark optimization algorithm, white sharks sense the location of prey based on the movement of prey and update their speed accordingly; S4.3. Position update: Based on the position update of the best prey or based on the position update of the best white shark, the two methods complement each other: Based on the position update of the optimal prey, in the white shark optimization algorithm, the white shark updates its position by moving toward the optimal prey to find the optimal or suboptimal prey; Based on the position update of the best white shark, in the white shark optimization algorithm, the white shark moves towards the optimal white shark position to get closer to the optimal position of the prey; S4.4. Fish school behavior: The white shark optimization algorithm retains the first two optimal solutions by simulating the foraging behavior of white shark schools and updates the positions of other white shark individuals based on these optimal positions.
[0013] In a preferred solution, step S5 specifically includes the following steps: S5.1. In the cascade hydropower system, the day-ahead dispatch model of cascade hydropower stations is used to determine the initial dispatch plan with the help of the White Shark Optimization Algorithm, and the corresponding day-ahead power generation arrangement is formulated; S5.2. Based on the current day-ahead power generation arrangement and the initial dispatch period data of the actual inflow of cascade reservoirs, the day-ahead power generation arrangement is updated by introducing a stochastic optimization model and a robust dispatch scheme; S5.3. According to step S5.2, the dispatching plan of the cascade hydropower system is updated in a loop and iterative manner.
[0014] The present invention provides a robust dispatch optimization method for cascade hydropower systems under uncertain electricity prices, which has the following beneficial effects: 1. In step S3.1 of the present invention, a stochastic optimization model is used to generate multiple electricity price scenarios, thereby providing multiple possibilities for scheduling decisions and enhancing the robustness of the scheduling scheme.
[0015] 2. In step S3.2 of the present invention, a robust online scheduling model is adopted to dynamically adjust the scheduling plan, thereby improving the adaptability to electricity price uncertainty and the real-time performance of scheduling.
[0016] 3. In step S4 of the present invention, the White Shark optimization algorithm is used, and its dynamic speed and position update mechanism can quickly adapt to different electricity price scenarios and uncertain conditions. The group behavior simulation enhances the robustness of the algorithm, so that the scheduling scheme can still maintain a high optimization effect when facing a complex and changing environment.
[0017] 4. By clarifying the scheduling plan, the goal of maximizing settlement revenue within the scheduling cycle can be achieved.
[0018] 5. This method can adapt to the uncertainty of electricity prices, improve the robustness of cascade hydropower station scheduling, and improve the operating efficiency of cascade hydropower station scheduling management. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The present invention will be further described below in conjunction with the accompanying drawings and embodiments: Figure 1 It is a schematic diagram of the process of the present invention; Figure 2 This is a schematic diagram of the random optimization model; Figure 3 Flowchart of the robust scheduling scheme with feedback. DETAILED DESCRIPTION
[0020] The specific implementation manner of the present invention is further described in conjunction with the accompanying drawings and embodiments.
[0021] like Figure 1 As shown, a robust dispatch optimization method for cascade hydropower stations under uncertain electricity prices specifically includes the following steps: S1. Given the initial data of cascade hydropower stations, including the overall reserved flood control storage capacity of the cascade hydropower stations, the water level-storage capacity curve of each power station, the downstream water level-flow curve and the expected output curve.
[0022] S2. Optimize modeling with the goal of maximizing the settlement income of cascade hydropower stations during the dispatch period, and complete the day-ahead dispatch modeling of cascade hydropower stations with time period water level constraints, time period output constraints, time period flow constraints, water level fluctuation constraints, water volume balance constraints, power volume balance constraints, hydraulic connections between hydropower stations, and net head calculation formula as constraints; Specifically include: Taking the maximum settlement income of cascade hydropower stations during the dispatch period as the optimal goal, the objective function is established: (1) Where, M is the total number of cascade hydropower stations; T is the total number of time periods in the dispatching period; is the time period granularity, which is set to 1h in this paper; m is the hydropower station number; is the contract electricity price of power station m during period t; Predict electricity prices for the day-ahead market clearing of the time period; The contracted electricity of power station m during period t is allocated to the hourly output; is the total output of power station m during period t.
[0023] The modeling is completed with the water level constraints of the cascade hydropower stations, output constraints of the time period, flow constraints of the time period, water level fluctuation constraints, water balance constraints, power balance constraints, hydraulic connections between hydropower stations, and net head calculation formula as constraints, specifically: Time period water level constraints: (2) In the formula, , , They represent the minimum water level limit, average water level and maximum water level limit of the mth power station in the tth period respectively; Output constraints during time period: (3) In the formula, , , They represent the minimum output limit, average output and maximum output limit of the mth power station in the tth period respectively; and It is usually set to the guaranteed output of the mth power station in the tth period and the expected output corresponding to the generating head; Time period flow constraints: (4) In the formula, , , They represent the minimum discharge flow limit, average discharge flow limit and maximum discharge flow limit of the mth power station in the tth period respectively; Water level fluctuation constraints: (5) In the formula, Indicates m Power station t Water level fluctuation during the period; , Respectively represent m Power station t The lower limit and upper limit of water level fluctuation in the time period; Water balance constraints: (6) In the formula, and are the initial storage capacity and final storage capacity of the mth power station in the tth period respectively; and are the inflow and outflow of the mth power station in the tth period, The scheduling period is long; Power balance constraints: (7) In the formula, It represents the power grid's demand for the output of cascade power stations in the tth period; represents the output of the mth power station in the tth period; Hydraulic connections between hydropower stations: (8) In the formula, is the inflow flow of the mth power station in the tth period, is the outflow flow of the m-1th power station in the tth period, is the interval inflow between upstream and downstream adjacent power stations in period t; Net water head calculation formula: (9) In the formula, , 、, They represent the net water head of the mth power station in the tth period, the water level in the tth period, and the water level in the tth period downstream of the power station, respectively. is the head loss of the power station at period t.
[0024] S3. Perform uncertainty management and robust optimization, and establish stochastic optimization models and robust online scheduling solutions.
[0025] Specifically include: S3.1. Establish a random optimization model. Its specific working method is as follows: Figure 2 As shown, the first-stage decision is executed before the uncertainty is realized, delaying the implementation of the second-stage decision. The first-stage decision is all discrete and continuous decisions within the period of the periodic dispatch interval; the second-stage decision is all discrete and continuous decisions within the remaining part of the dispatch period. By considering multiple discrete scenarios of uncertain parameters of electricity prices that may be realized, the decision is hedged. For uncertain parameters of electricity prices, it is necessary to determine the statistical characteristics of the disturbance, assuming that the disturbance follows a normal distribution ,in Estimated based on the standard deviation of historical forecast errors; Based on the model prediction, add random perturbations to generate multiple scenarios, which can be achieved through the following steps:
[0026] in, Indicates Time in each scenario The electricity price, is the electricity price predicted using the forecasting model, are independent and identically distributed random disturbances.
[0027] S3.2. Establish a robust online scheduling model. Its specific working method is as follows: Figure 3 As shown, a long short-term memory network model is adopted, and the prediction model and historical data are used to update the predicted values of the uncertain parameters of the electricity price. The updated predicted values are then applied to the stochastic optimization model. Subsequently, the stochastic optimization model is used to analyze various possible scenarios of the uncertain parameters to formulate a scheduling plan.
[0028] In the developed stochastic programming based optimization model, the predicted values of these uncertain parameters are used at each step to generate hedges against uncertainties by considering multiple uncertain parameter scenarios. The updated system information is fed back at the end of each rescheduling interval and then the schedule is rolled forward by the same duration as the rescheduling interval for future decisions.
[0029] The stochastic optimization model aims to optimize the economic objective and update the system state at each recalculation step. The proposed scheme involves implementing a set of input decisions on the system corresponding to the rescheduling interval, which is in sharp contrast to the traditional model predictive control strategy, which only involves executing the first control input on the system and rolling the time horizon forward by one time period at each step in forming the scheduling scheme.
[0030] S4. Use the White Shark optimization algorithm to solve the established scheduling model and determine the initial daily power generation plan.
[0031] Specifically include: The White Shark Optimization Algorithm, proposed by Braik et al. in 2022, is a new optimization algorithm inspired by the deep-sea predation strategy of white sharks. White sharks rely on their highly developed hearing and sense of smell to locate and capture prey in a vast search space. The White Shark Optimization Algorithm draws on this ability of white sharks and solves the optimization problem by simulating the dynamic update of the position of white sharks. The basic mathematical model of the algorithm can be briefly summarized as follows: S4.1. Initialization, set the population size G of white sharks, and the maximum number of iterations is set to = 10000, randomly generate the initial state of the population white shark position, that is, the initial optimization scheduling plan The decision variable of the model is the average power generation flow of each stage of the cascade hydropower station , the initial dispatching plan is generated by random number simulation based on the power generation reference flow constraints.
[0032] S4.2, Speed Update,White sharks spend most of their time hunting and tracking prey. In the framework of the white shark optimization algorithm, the white shark senses the location of the prey based on the movement of the prey and updates its speed accordingly.
[0033] S4.3. Position update: based on the position update of the best prey or the position update of the best white shark. The two methods complement each other: S4.3.1, based on the position update of the optimal prey, in the white shark optimization algorithm, the white shark updates its position by moving towards the optimal prey to find the optimal or suboptimal prey; S4.3.2, based on the position update of the best white shark, in the white shark optimization algorithm, the white shark moves towards the optimal white shark position to get closer to the optimal position of the prey; S4.4, Fish school behavior, the white shark optimization algorithm retains the first two optimal solutions by simulating the foraging behavior of white shark schools, and updates the positions of other white shark individuals based on these optimal positions.
[0034] S5. Build an optimization model based on two-stage stochastic programming, consider multiple uncertain scenarios to generate scheduling strategies, adjust the scheduling plan according to the prediction and actual system response feedback, and update the scheduling process of the cascade hydropower system in a rolling manner.
[0035] Specifically include: S5.1. In cascade hydropower systems, the short-term optimization dispatch model is used to determine the initial dispatch plan with the help of the White Shark optimization algorithm, and the corresponding day-ahead power generation arrangement is formulated. S5.2: Based on the current day-ahead power generation schedule and the initial dispatch period data of the actual inflow of cascade reservoirs, the day-ahead power generation schedule is updated by introducing a stochastic optimization model and a robust dispatch scheme.
[0036] S5.3: According to this process, the dispatch plan of the cascade hydropower system is updated iteratively.
[0037] Example: A cascade hydropower station was selected as the simulation object, and the optimal goal was to maximize the settlement income of the cascade hydropower station during the scheduling period. An optimal scheduling model for cascade reservoirs was established, and the above-mentioned robust scheduling optimization method was used for solution calculation, and the solution results were statistically compared and analyzed.
[0038] The cascade hydropower system on which this embodiment is based includes three hydraulically interconnected reservoirs and their associated power generation units. The considered operation time span is 24 hours, discretized into 1-hour time periods.
[0039] The dispatch is recalculated every 4 hours, with updated system information fed back at the end of each rescheduling interval. Afterwards, the dispatch is rolled forward for future decision making at the same time span of the rescheduling interval, with the initial water levels and volumes of the dispatch generated step by step measured directly from the cascade hydropower system.
[0040] For the case study of the robust online dispatch scheme with feedback, 20 uncertainty scenarios are generated for each predicted electricity price curve in each recalculation step. For each of the 20 instances of the case study, system economic comparison results of different electricity price forecast scenarios are generated at the recalculation step of each instance.
[0041] For all case studies, the schedules generated by several forecast scenarios are contrasted by comparing the average values of the economic objectives of these 20 scenarios in Table 1. To analyze the economic performance of the system under the dispatch strategy based on the initial electricity price forecast without incorporating the robust control mechanism; To implement a dispatch scheme with robust control mechanism without applying stochastic optimization model to deal with uncertainty of electricity price, the economic performance indicators of the system are analyzed; The economic indicators of the system are analyzed for the scheduling strategy of comprehensive application of stochastic optimization model and robust control mechanism.
[0042] Table 1 Analysis of economic indicators of cascade hydropower stations
[0043] The results show that using the robust online scheduling scheme leads to greater improvements in system economics, which justifies the rationality of introducing the robustness of the present invention into the online scheduling scheme.
[0044] The above-mentioned embodiments are only preferred technical solutions of the present invention and should not be regarded as limitations of the present invention. The embodiments and features in the embodiments of the present application can be arbitrarily combined with each other without conflict. The protection scope of the present invention shall be the technical solutions recorded in the claims, including the equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. A robust dispatch optimization method for cascade hydropower stations under uncertain electricity prices, characterized in that: The following steps are involved: S1. Given the initial data of cascade hydropower stations, including the overall reserved flood control storage capacity of the cascade hydropower stations, the water level-storage capacity curve of each power station, the downstream water level-flow curve and the expected output curve; S2. Optimize modeling with the goal of maximizing the settlement income of cascade hydropower stations during the dispatch period, and complete the day-ahead dispatch modeling of cascade hydropower stations with time period water level constraints, time period output constraints, time period flow constraints, water level fluctuation constraints, water volume balance constraints, power volume balance constraints, hydraulic connections between hydropower stations, and net head calculation formula as constraints; S3, perform uncertainty management and robust optimization, establish stochastic optimization models and robust online scheduling solutions; S4. Use the White Shark optimization algorithm to solve the established scheduling model and determine the initial daily power generation plan; S5. Build an optimization model based on two-stage stochastic programming, consider multiple uncertain scenarios to generate scheduling strategies, adjust the scheduling plan according to the prediction and actual system response feedback, and update the scheduling process of the cascade hydropower system in a rolling manner.
2. The robust dispatch optimization method for cascade hydropower systems under uncertain electricity prices according to claim 1, characterized in that: In step S2, the maximum settlement income of the cascade hydropower stations during the dispatch period is taken as the optimal goal, and the objective function expression is established as follows: (1) Where, M is the total number of cascade hydropower stations; T is the total number of time periods in the dispatching period; is the time period granularity; m Number the hydroelectric power stations; for t Time m The contract price of electricity from the power station; Predict electricity prices for the day-ahead market clearing of the time period; for t Time m The contracted electricity of power station No. is apportioned to the hourly output; is the total output of power station m during period t.
3. The robust dispatch optimization method for cascade hydropower systems under uncertain electricity prices according to claim 1, characterized in that: In step S2, the expressions of the constraints are as follows: Time period water level constraints: (2) In the formula, , , Respectively represent m The minimum water level limit, average water level and maximum water level limit of the power station in the t period; Output constraints during time period: (3) In the formula, , , Respectively represent m Power station t Minimum output limit, average output and maximum output limit for each time period; and Respectively m Power station t The guaranteed output of the time period and the expected output corresponding to the generating head; Time period flow constraints: (4) In the formula, , , Respectively represent m Power station t The minimum downstream flow limit, average downstream flow limit and maximum downstream flow limit for each time period; Water level fluctuation constraints: (5) In the formula, Indicates m Power station t Water level fluctuation during the period; , Respectively represent m Power station t The lower limit and upper limit of water level fluctuation in the time period; Water balance constraints: (6) In the formula, and Respectively m Power station t The initial storage capacity and final storage capacity of the time period; and Respectively m Power station t The inflow and outflow of the period, The scheduling period is long; Power balance constraints: (7) In the formula, Indicates t The power grid's demand for cascade power station output within a period; Indicates m Power station t Output during the time period; The hydraulic connection between hydropower stations is expressed as follows: (8) In the formula, is the inflow flow of the mth power station in the tth period; For the m-1 The power station is located in t Outbound flow in the time period; is the interval inflow between upstream and downstream adjacent power stations in period t; Net water head calculation formula: (9) In the formula, , 、, Respectively represent m Power station t Net water head of the period, t Water level during this period and downstream of the power station t Water level during the period; is the head loss of the power station at period t.
4. The robust scheduling optimization method for cascade hydropower systems under uncertain electricity prices according to claim 1 is characterized in that: The step S3 specifically includes the following steps: robust online scheduling scheme S3.
1. Establish a stochastic optimization model. The first-stage decision is executed before the uncertainty is realized, and the implementation of the second-stage decision is postponed. The first-stage decision is all discrete and continuous decisions within the periodic scheduling interval; the second-stage decision is all discrete and continuous decisions within the remaining part of the scheduling period. The decision is hedged by considering multiple discrete scenarios of possible uncertain parameters of electricity prices; S3.
2. Establish a robust online dispatch model, adopt a long short-term memory network model, use the prediction model and historical data to update the predicted values of the uncertain parameters of the electricity price, and then apply the updated predicted values to the stochastic optimization model. Subsequently, the stochastic optimization model is used to analyze various possible scenarios of the uncertain parameters to formulate a dispatch plan.
5. The robust dispatch optimization method for cascade hydropower systems under uncertain electricity prices according to claim 4 is characterized in that: The specific operation of step S3.1 is as follows: For the uncertain parameters of electricity prices in step S3.1, it is necessary to determine the statistical characteristics of the disturbance, assuming that the disturbance follows a normal distribution ,in Estimated based on the standard deviation of historical forecast errors; Based on the model prediction, add random perturbations to generate multiple scenarios, which can be achieved through the following operations: in, Indicates Time in each scenario The electricity price, is the electricity price predicted using the forecasting model, are independent and identically distributed random disturbances.
6. According to claim 1, a robust dispatch optimization method for cascade hydropower systems under uncertain electricity prices, characterized in that: In step S4, the established scheduling model is solved using the White Shark optimization algorithm, which specifically includes the following steps: S4.1, Initialization: Set the population size G of white sharks, set the maximum number of iterations to 10000, and randomly generate the positions of the white sharks in the initial state, that is, the initial optimization scheduling plan The decision variable of the model is the average power generation flow of each stage of the cascade hydropower station , the initial dispatching plan is generated according to the random number simulation through the power generation reference flow constraint condition; S4.2, Speed update: White sharks spend most of their time hunting and tracking prey. In the framework of the white shark optimization algorithm, white sharks sense the location of prey based on the movement of prey and update their speed accordingly; S4.
3. Position update: Based on the position update of the best prey or based on the position update of the best white shark, the two methods complement each other: Based on the position update of the optimal prey, in the white shark optimization algorithm, the white shark updates its position by moving toward the optimal prey to find the optimal or suboptimal prey; Based on the position update of the best white shark, in the white shark optimization algorithm, the white shark moves towards the optimal white shark position to get closer to the optimal position of the prey; S4.
4. Fish school behavior: The white shark optimization algorithm retains the first two optimal solutions by simulating the foraging behavior of white shark schools and updates the positions of other white shark individuals based on these optimal positions.
7. According to claim 1, a robust dispatch optimization method for cascade hydropower systems under uncertain electricity prices, characterized in that: The step S5 specifically comprises the following steps: S5.
1. In the cascade hydropower system, the day-ahead dispatch model of cascade hydropower stations is used to determine the initial dispatch plan with the help of the White Shark Optimization Algorithm, and the corresponding day-ahead power generation arrangement is formulated; S5.
2. Based on the current day-ahead power generation arrangement and the initial dispatch period data of the actual inflow of cascade reservoirs, the day-ahead power generation arrangement is updated by introducing a stochastic optimization model and a robust dispatch scheme; S5.
3. According to step S5.2, the dispatching plan of the cascade hydropower system is updated in a loop and iterative manner.