Rigid frame arch bridge support-free dismantling construction method based on model
Through the model-based support-free demolition construction method, simulation modeling and real-time monitoring technology are used to demolish rigid-frame bridges section by section, solving the problems of environmental damage, high cost and safety risks in traditional methods, and achieving efficient and safe bridge demolition. process.
Patent Information
- Application Number
- CN202410786048.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-18
- Publication Date
- 2024-10-18
AI Technical Summary
Traditional rigid frame bridge demolition methods have problems such as damage to the surrounding environment and buildings, high equipment and labor costs, and safety risks, especially in old city reconstruction and road widening projects.
A model-based support-free demolition construction method is adopted to determine the optimal bridge demolition plan through simulation modeling, and the model is monitored and corrected in real time during the demolition process to ensure the safety and stability of the bridge structure. The main beams and abutments are demolished section by section, using finite element The analysis software provides real-time monitoring and early warning to avoid the erection of temporary supports.
It achieves full-process safety monitoring, improves demolition efficiency and reliability, reduces costs and safety risks, ensures construction safety and efficiency, and overcomes the problems of insufficient monitoring accuracy and low efficiency in traditional methods.
Smart Images

Figure CN118797767A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of rigid frame arch bridge dismantling, in particular to a model-based rigid frame arch bridge support-free dismantling construction method. Background Art
[0002] In recent years, with the rapid development of infrastructure construction in my country, rigid frame bridges have played an increasingly important role in urban transportation. Rigid frame bridges are widely used in bridge construction due to their fast construction speed, high strength, and strong durability. However, in projects such as old city reconstruction and road widening, some old rigid frame bridges need to be demolished to meet the needs of urban development. This brings challenges to the demolition of rigid frame bridges.
[0003] Traditional bridge demolition methods mainly include blasting, mechanical cutting and manual demolition. However, these methods have certain problems when demolishing rigid frame bridges. Blasting may cause damage to the surrounding environment and buildings, mechanical cutting requires a lot of equipment and manpower, and the cost is high, and manual demolition has safety risks. Summary of the invention
[0004] In view of the above-mentioned prior art, the present invention proposes a model-based support-free dismantling construction method for a rigid frame arch bridge.
[0005] The present invention provides a model-based rigid frame arch bridge support-free demolition construction method, which firstly carries out bridge demolition simulation modeling, determines the optimal bridge demolition plan and the monitoring theoretical values of bridge components at each stage during the bridge demolition process, continuously corrects the model during the demolition process, and simultaneously carries out real-time monitoring of the bridge to ensure that the main structure of the bridge is safe and stable during the demolition process; then, the bridge deck is asphalt-washed and planed, and then the flange plates on both sides are removed, and after the flange plates are removed, the main beams are removed from the middle to both sides in sequence, and the order of main beam removal is the top plate, the bottom plate, and the web plate, and after all the main beams are removed, the abutments on both sides are removed, and after the abutments are removed, the ground is cleaned and then the bridge piers on both sides are cut and hoisted; the whole process does not set up temporary supports, and the section-by-section demolition is completed in a self-balancing state.
[0006] Preferably, the steps of simulation modeling are: S101: Collect the structural and performance parameters of the target bridge as basic data for subsequent calculations; S102: Based on the collected parameters, a number of comparative construction plans are formulated by comprehensively considering the construction steps, structural bearing capacity, displacement dynamics and convenience of construction operations, and a corresponding simulation model is constructed for in-depth analysis; S103: Based on the specific construction environment and operation requirements, select the best demolition plan from the results of numerous simulation analyses.
[0007] Preferably, the steps of real-time monitoring of the bridge are: S201: Based on the engineering design drawings, implement multi-parameter fusion multivariate simulation modeling for the target bridge, identify and establish the optimal solution for bridge dismantling strategy based on the model calculation output, and calculate the monitoring theoretical benchmark of bridge components at each dismantling stage; S202: Real-time monitoring of each stage of the bridge components during the construction process and recording relevant measurement data; S203: evaluating whether to proceed to the next disassembly stage by comparing and analyzing the theoretical values calculated by the simulation model with the actual monitoring measurement values; S204: Perform detailed inspection on the existing bridge conditions, and adaptively modify the bridge analysis model based on the inspection results; S205: using the revised bridge analysis model, theoretically analyzing each stage of the dismantling construction, and setting monitoring index thresholds of the monitoring object at each dismantling stage; S206: collecting index data of the monitored object at each disassembly stage in real time; S207: Compare the real-time monitoring data with the preset monitoring index threshold, and generate and transmit an early warning signal in a timely manner; S208: Based on the comparative analysis results, if the dismantling construction meets the safety standards, the subsequent dismantling operations will be seamlessly connected; if there are safety hazards, a response strategy will be immediately formulated, and the bridge analysis model will be further revised before continuing the construction.
[0008] Preferably, in S205, the monitoring index thresholds include the normal section bending strength, oblique section shear strength and eccentric compressive strength allowed by the structure.
[0009] Preferably, in S205, the monitoring objects in the monitoring index threshold include the upper beam body, the inclined legs, the pier body and environmental influencing factors.
[0010] Preferably, the monitoring frequency and comparative analysis method during demolition construction include: using finite element analysis software MidasCivil 2021 for modeling and calculation, and all components are simulated by beam units; the middle span is demolished in three sections in the longitudinal direction of the bridge, and the middle section is demolished first. After the top plate of the first section of the middle span is demolished, the structure is checked. After the results meet the requirements, the second and third sections are demolished. When the top plate of the middle section is demolished, the crane is still on the bridge to lift and remove the beam pieces; after the three sections of the middle span are demolished, the positive section bending bearing capacity of the side span inclined legs is not surplus. During operation, the load on the bridge is limited to not exceed the calculation assumption. During the whole process, there is no need to set up a scaffold to complete the section-by-section demolition of the beam body, inclined legs and pier body.
[0011] Compared with the prior art, the beneficial effects of the present invention are: 1. The present invention proposes a complete set of full-process safety monitoring strategies, which effectively makes up for the shortcomings of current safety monitoring methods in the demolition of rigid frame arch bridges.
[0012] 2. Through in-depth analysis of engineering drawings, the present invention uses multi-scheme finite element simulation calculations to conduct a detailed simulation of the bridge to be demolished, thereby locking in the most ideal demolition and monitoring plan. These solutions based on calculation simulation have been improved in terms of rationality and reliability.
[0013] 3. The present invention adopts adaptive calculation technology, which effectively solves the problem that the monitoring control value is difficult to accurately determine in real time due to the complex stress conditions during the arch bridge demolition process. This innovative method can accurately and real-time evaluate the state of the bridge structure, allowing the operation to continue under suitable scaffold-free construction conditions, and when necessary, by reviewing the calculation model parameters and taking corresponding construction control measures to ensure the safety and reliability of the construction.
[0014] 4. The present invention implements real-time full-process monitoring of the bridge status during the demolition process, and uses high-precision long-distance monitoring technology to overcome the problems of insufficient monitoring accuracy and low efficiency caused by the large span in the traditional rigid frame arch bridge demolition measurement. The safety monitoring points and monitoring objects set are both comprehensive and reasonable, ensuring the accuracy and reliability of the monitoring results, while not hindering the smooth progress of the demolition operation. The high efficiency of the monitoring process and the timely feedback of the results further improve the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of dismantling the cross box in an embodiment of the present invention.
[0016] Figure 2 This is a schematic diagram of dismantling a side span box according to an embodiment of the present invention.
[0017] Figure 3 It is a schematic diagram of the removal of abutments on both sides of an embodiment of the present invention.
[0018] Figure 4 It is a schematic diagram of the removal of bridge piers on both sides according to an embodiment of the present invention.
[0019] Figure 5 This is a schematic diagram of the demolition elevation across the first section in an embodiment of the present invention.
[0020] Figure 6 It is a three-dimensional schematic diagram of a finite element model of an embodiment of the present invention.
[0021] Figure 7 This is an envelope diagram of the bending bearing capacity of an embodiment of the present invention.
[0022] Figure 8 This is the shear bearing capacity envelope diagram of an embodiment of the present invention.
[0023] Fig. 9 This is an envelope diagram of the eccentric compressive bearing capacity of an embodiment of the present invention. DETAILED DESCRIPTION
[0024] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific embodiments.
[0025] Example: Figure 1-9 The present invention shows a model-based construction method for dismantling a rigid-frame arch bridge without support. First, a bridge dismantling simulation model is built to determine the optimal bridge dismantling plan and the monitoring theoretical values of the bridge components at each stage during the dismantling process. The model is continuously corrected during the dismantling process, and the bridge is monitored in real time to ensure that the main structure of the bridge is safe and stable during the dismantling process. Then, the bridge deck is asphalt-washed and planed, and then the flange plates on both sides are removed. After the flange plates are removed, the main beams are removed from the middle to both sides in the order of top plate, bottom plate, and web plate. After all the main beams are removed, the abutments on both sides are removed. After the abutments are removed, the ground is cleaned and the piers on both sides are cut and hoisted. No temporary support is set up during the whole process, and the dismantling is completed section by section in a self-balancing state.
[0026] Wherein, the steps of simulation modeling are: S101: Collect the structural and performance parameters of the target bridge as basic data for subsequent calculations; S102: Based on the collected parameters, a number of comparative construction plans are formulated by comprehensively considering the construction steps, structural bearing capacity, displacement dynamics and convenience of construction operations, and a corresponding simulation model is constructed for in-depth analysis; S103: Based on the specific construction environment and operation requirements, select the best demolition plan from the results of numerous simulation analyses.
[0027] The steps of real-time monitoring of the bridge are as follows: S201: Based on the engineering design drawings, implement multi-parameter fusion multivariate simulation modeling for the target bridge, identify and establish the optimal solution for bridge dismantling strategy based on the model calculation output, and calculate the monitoring theoretical benchmark of bridge components at each dismantling stage; S202: Real-time monitoring of each stage of the bridge components during the construction process and recording relevant measurement data; S203: evaluating whether to proceed to the next disassembly stage by comparing and analyzing the theoretical values calculated by the simulation model with the actual monitoring measurement values; S204: Perform detailed inspection on the existing bridge conditions, and adaptively modify the bridge analysis model based on the inspection results; S205: using the modified bridge analysis model, theoretically analyzing each stage of the dismantling construction, and setting the monitoring index threshold of the monitoring object at each dismantling stage; the monitoring index threshold includes the normal section bending strength and oblique section shear strength and eccentric compressive strength allowed by the structure; the monitoring objects in the monitoring index threshold include the upper beam body, oblique legs, pier body and environmental influencing factors; S206: collecting index data of the monitored object at each disassembly stage in real time; S207: Compare the real-time monitoring data with the preset monitoring index threshold, and generate and transmit an early warning signal in a timely manner; S208: Based on the comparative analysis results, if the dismantling construction meets the safety standards, the subsequent dismantling operations will be seamlessly connected; if there are safety hazards, a response strategy will be immediately formulated, and the bridge analysis model will be further revised before continuing the construction.
[0028] Among them, the monitoring frequency and comparative analysis methods during demolition construction include: using finite element analysis software MidasCivil 2021 (V2.1) for modeling and calculation, and all components are simulated by beam units; the middle span is demolished in three sections in the longitudinal direction of the bridge. The middle section is demolished first, and the structure is checked after the top plate of the first section of the middle span is demolished. After the results meet the requirements, the second and third sections are demolished. When the top plate of the middle section is demolished, the crane is still on the bridge to lift and remove the beams; after the three sections of the middle span are demolished, the positive section bending bearing capacity of the side span inclined legs is not surplus. During operation, the load on the bridge is limited to not exceed the calculation assumption. During the whole process, no scaffolding is required to complete the section-by-section demolition of the beam body, inclined legs and pier body.
[0029] refer to Figure 1-5 , the removal steps are as follows: Phase I: Dismantling of the middle span box: The middle span cast-in-place box girder is cut in sections and blocks by rope saw and removed by car crane. The dismantled beam sections are transported to the designated site for crushing by beam transport vehicles. The middle span is dismantled in three sections longitudinally, with the middle section being 6m and the beam sections on both sides being 4m each.
[0030] The second stage: dismantling of the side span box: the cast-in-place box girder of the side span is cut in sections and blocks by rope saw and removed by car crane. The dismantled beam sections are transported to the designated site for crushing by beam transport vehicles, and the side span is dismantled as a whole longitudinally.
[0031] The third stage: demolition of the abutments on both sides: the abutments on both sides are demolished by excavators and the construction access road is repaired. The broken concrete and gravel from the abutments on both sides are used to repair the construction access road. The abutments on both sides are broken on site with a pickaxe machine and the site is leveled for crane positioning and hoisting of the bridge piers on both sides.
[0032] The fourth stage: demolition of bridge piers on both sides: after the bridge abutments on both sides are crushed, a site for a car crane is leveled on the river bank, and the bridge piers on both sides are cut with a rope saw. The cut blocks are removed in sections using a shore crane, and the beam components are transported to the designated site for crushing using a transport vehicle.
[0033] This embodiment uses the scaffold-free demolition construction technology based on the preliminary model calculation and analysis to improve the demolition efficiency, reduce the cost and safety risks; introduces BIM technology to realize the automation and intelligence of the demolition construction of the rigid frame bridge. The application of these new technologies provides a new solution for the demolition construction of the rigid frame bridge, and strongly promotes the development of the demolition construction technology of the rigid frame bridge.
[0034] The above are only implementation modes of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent schemes made using the contents of the present invention specification, directly or indirectly applied in other related technical fields, are also within the patent protection scope of the present invention.
Claims
1. A model-based method for dismantling a rigid frame arch bridge without support. It is characterized in that First, we conduct bridge demolition simulation modeling to determine the optimal bridge demolition plan and the theoretical monitoring values of bridge components at each stage during the demolition process. During the demolition process, we continuously revise the model and monitor the bridge in real time to ensure that the main structure of the bridge is safe and stable during the demolition process. Then the bridge deck is asphalt washed and scraped, and then the flange plates on both sides are removed. After the flange plates are removed, the main beams are removed from the middle to both sides in the order of top plate, bottom plate, and web plate. After all the main beams are removed, the abutments on both sides are broken. After the abutments are broken, the ground is cleaned and then the piers on both sides are cut and hoisted. No temporary supports are set up during the whole process, and the dismantling is completed section by section in a self-balancing state.
2. The model-based rigid frame arch bridge support-free dismantling construction method according to claim 1, It is characterized in that The steps of the simulation modeling are: S101: Collect the structural and performance parameters of the target bridge as basic data for subsequent calculations; S102: Based on the collected parameters, a number of comparative construction plans are formulated by comprehensively considering the construction steps, structural bearing capacity, displacement dynamics and convenience of construction operations, and a corresponding simulation model is constructed for in-depth analysis; S103: Based on the specific construction environment and operation requirements, select the best demolition plan from the results of numerous simulation analyses.
3. The model-based rigid frame arch bridge support-free dismantling construction method according to claim 1 or 2, It is characterized in that The steps of real-time monitoring of the bridge are as follows: S201: Based on the engineering design drawings, implement multi-parameter fusion multivariate simulation modeling for the target bridge, identify and establish the optimal solution for bridge dismantling strategy based on the model calculation output, and calculate the monitoring theoretical benchmark of bridge components at each dismantling stage; S202: Real-time monitoring of each stage of the bridge components during the construction process and recording relevant measurement data; S203: evaluating whether to proceed to the next disassembly stage by comparing and analyzing the theoretical values calculated by the simulation model with the actual monitoring measurement values; S204: Perform detailed inspection on the existing bridge conditions, and adaptively modify the bridge analysis model based on the inspection results; S205: using the revised bridge analysis model, theoretically analyzing each stage of the dismantling construction, and setting monitoring index thresholds of the monitoring object at each dismantling stage; S206: collecting index data of the monitored object at each disassembly stage in real time; S207: Compare the real-time monitoring data with the preset monitoring index threshold, and generate and transmit an early warning signal in a timely manner; S208: Based on the comparative analysis results, if the dismantling construction meets the safety standards, the subsequent dismantling operations will be seamlessly connected; if there are safety hazards, a response strategy will be immediately formulated, and the bridge analysis model will be further revised before continuing the construction.
4. The model-based rigid frame arch bridge support-free dismantling construction method according to claim 3, It is characterized in that In S205, the monitoring index thresholds include the normal section bending strength, oblique section shear strength and eccentric compressive strength allowed by the structure.
5. The model-based rigid frame arch bridge support-free dismantling construction method according to claim 3, It is characterized in that In S205, the monitoring objects in the monitoring index threshold include the upper beam body, the inclined legs, the pier body and environmental influencing factors.
6. The model-based rigid frame arch bridge support-free dismantling construction method according to claim 1 or 2, It is characterized in that The monitoring frequency and comparative analysis methods during demolition construction include: using finite element analysis software Midas Civil 2021 for modeling and calculation, and all components are simulated using beam units; the middle span is demolished in three sections in the longitudinal direction of the bridge, and the middle section is demolished first. After the top plate of the first section of the middle span is demolished, the structure is checked. After the results meet the requirements, the second and third sections are demolished. When the top plate of the middle section is demolished, the crane is still on the bridge to lift and remove the beams; after the three sections of the middle span are demolished, the positive section bending bearing capacity of the side span inclined legs is not much surplus. During operation, the load on the bridge is limited to not exceed the calculated assumptions. During the whole process, no scaffolding is required to complete the section-by-section demolition of the beam body, inclined legs and pier body.