Method for detecting uplift bearing capacity of prestressed pipe pile

Through the automatic adsorption connection and switch control of the electromagnet and the magnetic suction piece on the top of the pipe pile, combined with the motor drive device, the problem of manual debugging affecting efficiency in the existing technology is solved, and the automation and efficient connection of the pull-out detection of prestressed pipe piles are realized. .

CN118814871APending Publication Date: 2024-10-22CECEP GUOZHEN ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310429704.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-04-18
Publication Date
2024-10-22

AI Technical Summary

Technical Problem

When the existing prestressed pipe pile pullout detection device is connected, it is necessary to manually adjust the descending height of the detection device, which affects the detection efficiency.

Method used

An electromagnet is used to adsorb and connect the magnetic piece on the top of the pipe pile, and the contact between the trigger plate and the pipe pile is automatically controlled through a switch mechanism to avoid manual adjustment. It is combined with a motor drive device to achieve automated detection.

Benefits of technology

The automatic connection efficiency between the detection device and the pipe pile is improved, manual intervention is reduced, and detection efficiency and accuracy are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118814871A_ABST
    Figure CN118814871A_ABST
Patent Text Reader

Abstract

The invention relates to a method for detecting the uplift bearing capacity of a prestressed pipe pile, which belongs to the technical field of uplift pipe piles, and comprises the following steps: arranging sleepers with the same height on the two sides of the prestressed pipe pile respectively, arranging a cross beam at the top ends of the sleepers, and arranging a motor and a detection device on the cross beam; the motor is started to reach preset thrust until the motor automatically stops, and the displacement condition of the prestressed pipe pile in the vertical direction is measured; the detection device comprises a measuring frame and a driving mechanism for providing power for the vertical movement of the measuring frame; the driving mechanism is arranged at the top of the crossbeam; the bottom of the measuring frame is fixedly connected with a plurality of connecting shafts, and the measuring frame is slidably connected with a trigger plate in the vertical direction through the connecting shafts. A second electromagnet is arranged on the trigger plate, and a magnetic attraction piece capable of being magnetically attracted to the second electromagnet is arranged at the top of the prestressed pipe pile; a switching mechanism for communicating the electromagnet II with a power supply is arranged on the cross beam. The tubular pile pull-out test device has the effect of automatically carrying out the tubular pile pull-out test.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of pull-out resistant pipe piles, and in particular to a method for detecting the pull-out resistant bearing capacity of prestressed pipe piles. Background Art

[0002] At present, after the construction of prestressed pipe piles is completed, compression or pull-out tests must be carried out on the engineering piles to verify the design bearing capacity.

[0003] For related technologies, please refer to the Chinese utility model patent with authorization announcement number CN214574176U, which discloses a prestressed PHC pile pull-out detection device, including a flange plate and a jack with a digital display function; the flange plate is rectangular, and support rods are respectively provided near the front side and the rear side of the flange plate, and cross beams are provided at the upper ends of the support rods located on the front and rear sides of the flange plate; the jack is arranged above the flange plate, and a pad is provided above the jack, and the front and rear parts of the pad are against the lower side of the corresponding side beam. The detection method of the above device includes the following steps: installing the flange plate on the upper end face of the pile; setting sleepers on the left and right sides of the flange plate, and placing a horizontally arranged support beam on two sleepers; placing the jack on the support beam, placing the pad on the jack, starting the jack and making it reach a preset thrust, if the PHC pile is not pulled out, its pull-out resistance performance meets the standard.

[0004] With respect to the above-mentioned related technologies, the inventors believe that there are the following defects: at the initial stage of the detection process, the detection device needs to be connected to the top of the prestressed pipe pile, but during the connection, the lowering height of the bottom of the detection device needs to be manually adjusted repeatedly to match the height of the prestressed pipe pile, which affects the detection efficiency. Summary of the invention

[0005] In order to improve the problem that the detection device cannot stop automatically after contacting the pipe pile, the present application provides a method for detecting the pull-out bearing capacity of a prestressed pipe pile.

[0006] The present application provides a method for testing the pull-out bearing capacity of prestressed pipe piles using the following technical solution: A method for detecting the pull-out bearing capacity of a prestressed pipe pile comprises the following steps: Sleepers of equal height are arranged on both sides of the prestressed pipe piles, a crossbeam is arranged on the top of the sleepers, and a motor and a detection device are arranged on the crossbeam; Starting the motor and making it reach a preset thrust until the motor stops automatically, and measuring the vertical displacement of the prestressed pipe pile; The detection device includes a measuring frame and a driving mechanism that provides power for the vertical movement of the measuring frame; the driving mechanism is arranged on the top of the crossbeam; a plurality of connecting shafts are fixedly connected to the bottom of the measuring frame, and the measuring frame is connected to a trigger plate by the connecting shaft along the vertical sliding; a second electromagnet is arranged on the trigger plate, and a magnetic attraction sheet that can be magnetically adsorbed by the second electromagnet is arranged on the top of the prestressed pipe pile; a switch mechanism that connects the second electromagnet with a power supply is arranged on the crossbeam.

[0007] By adopting the above technical solution, the detection device achieves the purpose of connecting with the pipe pile by adsorbing the second electromagnet to the magnetic suction sheet on the top of the pipe pile. When the trigger plate contacts the top of the pipe pile, the second electromagnet is connected to the power supply through the switch mechanism, so that the trigger plate is automatically connected to the pipe pile. There is no need to manually adjust the descending position of the trigger plate, thereby improving the connection efficiency.

[0008] Optionally, a plurality of springs 2 are fixed to the bottom surface of the bottom plate, the springs 2 are sleeved on the circumferential side of the connecting shaft, and the bottom ends of the springs 2 are fixedly connected to the top surface of the trigger plate.

[0009] By adopting the above technical solution, the second spring provides the trigger plate with a downward elastic force, so that the trigger plate can be driven to reset downward by the second spring.

[0010] Optionally, a magnetic attraction sheet that can be magnetically attracted to the second electromagnet is provided on the bottom surface of the bottom plate.

[0011] By adopting the above technical solution, the second electromagnet can also be connected to the bottom plate through the magnetic sheet after being energized, so that the trigger plate and the bottom plate can move together when the trigger plate drags the pipe pile upward.

[0012] Optionally, the measuring frame includes a top plate and a bottom plate, the bottom end of the top plate is rotatably provided with a plurality of threaded tubes, and the top end of the bottom plate is rotatably provided with a plurality of screws; the threaded tube is threadedly connected to the screw; the driving mechanism includes a driving box and a connecting piece 1 and a connecting piece 2 that turn in opposite directions; a support rod is fixed to the top surface of the driving box, and a sliding tube is vertically slidably provided on the circumference of the support rod; a pipe sleeve is rotatably installed in the sliding tube, and the pipe sleeve is arranged on the circumference of the connecting piece 1 and the connecting piece 2; two ends of the pipe sleeve are respectively provided with a pipe groove 1 that can slidably cooperate with the connecting piece 1 and the connecting piece 2, and a pipe groove 2 is provided in the pipe sleeve between the two pipe grooves 1; the top of the pipe sleeve is vertically slidably connected with a top shaft; a gear 5 and a plurality of gears 4 are rotatably installed on the top surface of the top plate, and the bottom surface of the gear 5 is fixedly connected to the top end of the top shaft; the top end of the threaded tube is fixedly connected to the bottom surface of the gear 4.

[0013] By adopting the above technical solution, since the connecting piece 1 and the connecting piece 2 rotate in opposite directions, when the pipe groove 1 of the pipe sleeve cooperates with any one of the connecting piece 1 and the connecting piece 2, it will rotate along with the matching connecting piece. Therefore, by adjusting the vertical position of the pipe sleeve, the direction of gear 5, gear 6 and the threaded pipe can be controlled, and the vertical movement direction of the base plate can be further adjusted.

[0014] Optionally, gear one is rotatably installed on the inner top surface of the drive box, and gear two is rotatably installed on the inner bottom surface; gear three is rotatably installed on the inner side wall of the drive box; the motor output shaft is coaxially fixedly connected with gear three; gear three is respectively meshed with gear one and gear two; a drive tube is fixed on the top of gear one, and a drive shaft is fixed on the top of gear two; connecting piece one is fixedly connected to the top end of the drive shaft; connecting piece two is fixedly connected to the top end of the drive tube.

[0015] By adopting the above technical solution, since gear one and gear two are respectively meshed with gear three, connecting piece one and connecting piece two rotate in opposite directions, thereby achieving the purpose of changing the moving direction of the bottom plate.

[0016] Optionally, a support plate is fixed on the outer circumferential surface of the support rod, a spring is fixed on the top of the support plate, and the top of the spring is fixedly connected to the bottom surface of the sliding tube; an electromagnet is fixed on the top of the support rod, and a magnetic plate that can be magnetically attracted to the electromagnet is fixed on the top surface of the sliding tube.

[0017] By adopting the above technical solution, the electromagnet 1 drives the tube sleeve to move upward by adsorbing the magnetic attraction plate, and the spring 1 is used to drive the tube sleeve to reset downward after the electromagnet 1 loses its magnetism, thereby achieving the purpose of changing the moving direction of the bottom plate.

[0018] Optionally, a switch movable plate 1 is fixed to the top surface of the trigger plate, and a switch stator 1 is fixed to the bottom surface of the bottom plate; the switch movable plate 1 is connected in series with the electromagnet 1 and the electromagnet 2, and the switch stator 1 is connected in series with the power supply.

[0019] By adopting the above technical solution, when the trigger plate contacts the pipe pile, the electrical contact between the switch movable plate 1 and the switch fixed plate 1 can not only achieve the purpose of connecting the trigger plate to the pipe pile, but also control the bottom plate to move upward, thereby facilitating the automated propulsion test.

[0020] Optionally, a baffle is fixedly connected to the outer circumferential surface of the lead screw; a support plate is fixed to the bottom end of the threaded tube; a number of push rods are passed through the support plate; a switch movable plate 2 is fixed to the top of the push rod, and a switch stator 2 electrically connected to the switch movable plate 2 is fixed to the top surface of the support plate; the switch movable plate 2 is electrically connected to the motor, and the switch stator 2 is electrically connected to the power supply; a spring 3 is fixed to the bottom surface of the support plate, and the bottom end of the spring 3 is fixed to the bottom end of the push rod.

[0021] By adopting the above technical solution, when the lead screw drives the baffle to move upward to a predetermined height, the baffle moves upward by pushing the push rod, triggering the separation of the switch moving piece 2 and the switch fixed piece 2, thereby stopping the motor from working.

[0022] In summary, the present application includes at least one of the following beneficial technical effects: 1. The detection device is connected to the pipe pile by adsorbing the second electromagnet with the magnetic sheet on the top of the pipe pile. When the trigger plate contacts the top of the pipe pile, the second electromagnet is connected to the power supply through the switch mechanism, so that the trigger plate is automatically connected to the pipe pile. There is no need to manually adjust the descending position of the trigger plate, which improves the connection efficiency. 2. Since the connection piece 1 and the connection piece 2 rotate in opposite directions, when the pipe groove 1 of the pipe sleeve matches with any one of the connection piece 1 and the connection piece 2, it will rotate along with the matching connection piece. Therefore, by adjusting the vertical position of the pipe sleeve, the rotation direction of the gear 5, the gear 6 and the threaded pipe can be controlled, and the vertical movement direction of the bottom plate can be further adjusted; 3. When the trigger plate contacts the pipe pile, the electrical contact between the switch moving piece 1 and the switch fixed piece 1 can not only achieve the purpose of connecting the trigger plate to the pipe pile, but also control the bottom plate to move upward, which is convenient for the automated propulsion test. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a schematic diagram of the structure of the detection device of the embodiment of the present application.

[0024] Figure 2 It is a schematic diagram of the structure of the driving mechanism of the embodiment of the present application.

[0025] Figure 3 It is a cross-sectional view of the pipe sleeve according to the embodiment of the present application.

[0026] Figure 4 It is a structural schematic diagram of the base plate of an embodiment of the present application.

[0027] Figure numerals: 1, crossbeam; 11, top plate; 12, bottom plate; 13, threaded pipe; 14, lead screw; 15, connecting shaft; 16, sleeper; 17, measuring frame; 2, driving mechanism; 21, driving box; 22, motor; 23, gear 1; 24, gear 2; 25, gear 3; 26, driving pipe; 27, driving shaft; 28, connecting piece 1; 29, connecting piece 2; 3, sliding pipe; 31, support rod; 32, pipe sleeve; 33, Tube slot one; 34, tube slot two; 35, support plate; 36, spring one; 37, electromagnet one; 38, magnetic plate; 4, top shaft; 41, gear five; 42, gear four; 43, spring two; 44, electromagnet two; 45, spring three; 46, magnetic plate; 5, trigger plate; 51, switch moving plate one; 52, switch fixed plate one; 53, blocking plate; 54, support plate; 55, push rod; 56, switch moving plate two; 57, switch fixed plate two. DETAILED DESCRIPTION

[0028] The following is combined with Figure 1-4 This application is described in further detail.

[0029] The present application embodiment discloses a method for detecting the pull-out bearing capacity of a prestressed pipe pile. Figure 1 The method for testing the pull-out bearing capacity of prestressed pipe piles includes the following steps: Sleepers 16 of equal height are respectively arranged on both sides of the prestressed pipe piles, a crossbeam 1 is arranged on the top of the sleeper 16, and a motor 22 and a detection device are arranged on the crossbeam 1.

[0030] The motor 22 is started and made to reach a preset thrust until the motor 22 stops automatically, and the vertical displacement of the prestressed pipe pile is measured to determine whether the pull-out resistance of the prestressed pipe pile meets the standard.

[0031] Reference Figure 1 The detection device includes a measuring frame 17 and a driving mechanism 2 for providing power for the vertical movement of the measuring frame 17. The measuring frame 17 is arranged above the prestressed pipe pile to be measured, and the driving mechanism 2 is arranged on the top of the beam 1. The measuring frame 17 includes a top plate 11 and a bottom plate 12. A plurality of threaded tubes 13 are rotatably arranged at the bottom end of the top plate 11, and a plurality of lead screws 14 are rotatably arranged at the top end of the bottom plate 12. The threaded tubes 13 are threadedly connected to the lead screws 14.

[0032] Reference Figure 1 , Figure 2 and Figure 3The driving mechanism 2 includes a driving box 21 and a motor 22. A gear 1 23 is rotatably mounted on the top surface of the driving box 21, and a gear 2 24 is rotatably mounted on the bottom surface; a gear 3 25 is rotatably mounted on the inner side wall of the driving box 21. Gear 1 23, gear 2 24 and gear 3 25 are all bevel gears; gear 3 25 is meshed with gear 1 23 and gear 2 24 respectively; the output shaft of the motor 22 is coaxially fixed to gear 3 25. A driving tube 26 that passes through the top of the driving box 21 is fixed to the top of gear 1 23, and a driving shaft 27 that passes through the top surface of gear 1 23 and is arranged in the driving tube 26 is fixed to the top of gear 24. Gear 1 23, gear 2 24, driving shaft 27 and driving tube 26 are coaxially arranged. A connecting piece 1 28 is fixed to the top of the driving shaft 27, and a connecting piece 2 29 is fixed to the top of the driving tube 26.

[0033] Reference Figure 2 and Figure 3 A support rod 31 is fixed on the top surface of the driving box 21, and a slide tube 3 is vertically slidably arranged around the support rod 31. A pipe sleeve 32 is rotatably installed in the slide tube 3, and the pipe sleeve 32 is sleeved around the connecting piece 1 28 and the connecting piece 2 29. Square pipe grooves 1 33 are respectively opened at both ends of the pipe sleeve 32, and a circular pipe groove 2 34 is opened in the pipe sleeve 32 between the two pipe grooves 1 33.

[0034] Since the gear 3 25 is meshed with the gear 1 23 and the gear 2 24 respectively, the gear 1 23 and the gear 2 24 rotate in opposite directions, thereby driving the connecting piece 1 28 and the connecting piece 2 29 to rotate in opposite directions. The slide tube 3 can choose to cooperate with the connecting piece 1 28 or the connecting piece 2 29 in the vertical process, so that the rotation direction of the slide tube 3 changes. When one of the connecting piece 1 28 or the connecting piece 2 29 is located in the tube groove 1 33, the other is located in the tube groove 2 34.

[0035] Reference Figure 3 A support plate 35 is fixed to the outer circumference of the support rod 31, a spring 36 is fixed to the top of the support plate 35, and the top of the spring 36 is fixed to the bottom surface of the slide tube 3. An electromagnet 37 is fixed to the top of the support rod 31, and a magnetic attraction plate 38 that can be magnetically attracted to the electromagnet 37 is fixed to the top surface of the slide tube 3.

[0036] Reference Figure 2 The top of the sleeve 32 is vertically slidably connected to the top shaft 4; the cross section of the top shaft 4 is square; the top surface of the top plate 11 is rotatably mounted with a gear 5 41 and a plurality of gears 42 that can mesh with the gear 5 41, and the bottom surface of the gear 5 41 is coaxially fixed to the top of the top shaft 4. The top of the threaded tube 13 penetrates the top plate 11 and is coaxially fixed to the bottom surface of the gear 4 42.

[0037] The driving mechanism 2 is powered by the motor 22, and the reverse direction is changed by the reverse rotation of the gear 1 23 and the gear 2 24, and then the threaded transmission of the threaded tube 13 and the lead screw 14 cooperates to drive the bottom plate 12 to move vertically upward or downward.

[0038] Reference Figure 1 and Figure 4 , a plurality of connecting shafts 15 are fixedly connected to the bottom of the bottom plate 12, and the bottom plate 12 is connected to the trigger plate 5 by sliding along the vertical direction through the connecting shafts 15. A plurality of springs 43 are fixed to the bottom surface of the bottom plate 12, and the springs 43 are sleeved around the connecting shafts 15, and the bottom ends of the springs 43 are fixedly connected to the top surface of the trigger plate 5. An electromagnet 44 is provided through the trigger plate 5, and a magnetic attraction sheet 46 that can be magnetically adsorbed by the electromagnet 44 is provided on the bottom surface of the bottom plate 12 and the top of the prestressed pipe pile to be tested. A switch moving piece 51 is fixed to the top surface of the trigger plate 5, and a switch stator 52 is fixed to the bottom surface of the bottom plate 12; the switch moving piece 51 is connected in series with the electromagnet 37 and the electromagnet 44, and the switch stator 52 is connected in series with the power supply.

[0039] During the downward movement of the bottom plate 12, due to the downward elastic force of the spring 2 43, the bottom plate 12 is not in contact with the trigger plate 5, and the switch moving piece 1 51 is disconnected from the switch fixed piece 1 52. When the trigger plate 5 contacts the top of the prestressed pipe pile and moves upward under pressure, the switch moving piece 1 51 contacts the switch fixed piece 1 52 and energizes the electromagnet 1 37 and the electromagnet 2 44. The energization of the electromagnet 1 37 will fix the trigger plate 5 with the bottom plate 12 and the prestressed pipe pile, so as to apply an upward force to the prestressed pipe pile for the pull-out test.

[0040] When the electromagnet 2 44 is energized, the sleeve 32 moves upward, so that the sleeve 32 is connected with the connecting piece 1 28. When the sleeve 32 rotates following the connecting piece 29, the bottom plate 12 moves downward, and when the sleeve 32 rotates following the connecting piece 1 28, the bottom plate 12 moves upward.

[0041] Reference Figure 1 , a baffle 53 is fixedly connected to the outer circumference of the lead screw 14. A support piece 54 is fixed to the bottom end of the threaded tube 13. A plurality of push rods 55 are provided on the support piece 54. A switch moving piece 2 56 is fixed to the top of the push rod 55, and a switch stator 2 57 which can be electrically connected to the switch moving piece 2 56 is fixed to the top surface of the support piece 54; the switch moving piece 2 56 is electrically connected to the motor 22, and the switch stator 2 57 is electrically connected to the power supply. A spring 3 45 is fixed to the bottom surface of the support piece 54, and a support piece is fixed to the bottom end of the push rod 55, and the bottom end of the spring 3 45 is fixed to the top surface of the support piece.

[0042] During the pulling test, the threaded transmission cooperation between the threaded tube 13 and the lead screw 14 will drive the lead screw 14 to rise continuously. The lead screw 14 moves to the support plate 54 and abuts against the bottom end of the push rod 55, and pushes the support plate 54 to move upward. During the movement of the support plate 54, the switch movable plate 2 56 and the switch fixed plate 2 57 are separated, thereby disconnecting the motor 22 from the power supply.

[0043] The implementation principle of the detection device in the embodiment of the present application is: In the initial state, the pipe sleeve 32 rotates with the connecting piece 29, and after the motor 22 is started, the bottom plate 12 moves downward. When the trigger plate 5 contacts the top of the prestressed pipe pile and moves upward under pressure, the switch moving piece 1 51 contacts the switch fixed piece 1 52 and energizes the electromagnet 1 37 and the electromagnet 2 44. The energization of the electromagnet 1 37 will make the trigger plate 5 fixedly connected with the bottom plate 12 and the prestressed pipe pile.

[0044] When the electromagnet 2 44 is energized, the sleeve 32 moves upward, so that the sleeve 32 is connected with the connecting piece 1 28, and the bottom plate 12 moves upward. The lead screw 14 moves upward along with the bottom plate 12 until the support piece 54 abuts against the bottom end of the push rod 55, and pushes the support piece 54 to move upward. During the movement of the support piece 54, the switch moving piece 2 56 and the switch fixed piece 2 57 are separated, so that the motor 22 is disconnected from the power supply. The pull-out test ends when the motor 22 stops working.

[0045] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A method for testing the pull-out bearing capacity of prestressed pipe piles. It is characterized in that The steps include: Sleepers (16) of equal height are respectively arranged on both sides of the prestressed pipe pile, a crossbeam (1) is arranged at the top of the sleeper (16), and a motor (22) and a detection device are arranged on the crossbeam (1); Starting the motor (22) and causing it to reach a preset thrust until the motor (22) stops automatically, and measuring the vertical displacement of the prestressed pipe pile; The detection device comprises a measuring frame (17) and a driving mechanism (2) for providing power for the vertical movement of the measuring frame (17); the driving mechanism (2) is arranged on the top of the crossbeam (1); a plurality of connecting shafts (15) are fixedly connected to the bottom of the measuring frame (17); the measuring frame (17) is vertically slidably connected to a trigger plate (5) via the connecting shafts (15); a second electromagnet (44) is arranged on the trigger plate (5); a magnetic attraction sheet (46) capable of magnetically adsorbing the second electromagnet (44) is arranged on the top of the prestressed pipe pile; and a switch mechanism for connecting the second electromagnet (44) with a power source is arranged on the crossbeam (1).

2. A method for detecting the pull-out bearing capacity of a prestressed pipe pile according to claim 1, Features: The measuring frame (17) comprises a top plate (11) and a bottom plate (12); a plurality of threaded tubes (13) are rotatably arranged at the bottom end of the top plate (11); a plurality of lead screws (14) are rotatably arranged at the top end of the bottom plate (12); a plurality of second springs (43) are fixed to the bottom surface of the bottom plate (12); the second springs (43) are sleeved around the circumference of the connecting shaft (15); and the bottom end of the second springs (43) is fixedly connected to the top surface of the trigger plate (5).

3. A method for detecting the pull-out bearing capacity of a prestressed pipe pile according to claim 2, Features: The bottom surface of the bottom plate (12) is provided with a magnetic attraction sheet (46) capable of magnetically adsorbing the second electromagnet (44).

4. A method for detecting the pull-out bearing capacity of a prestressed pipe pile according to claim 3, Features: The threaded tube (13) is threadedly connected to the lead screw (14); the driving mechanism (2) comprises a driving box (21) and a first connecting piece (28) and a second connecting piece (29) which rotate in opposite directions; a support rod (31) is fixed to the top surface of the driving box (21), and a sliding tube (3) is vertically slidably arranged around the support rod (31); a pipe sleeve (32) is rotatably installed in the sliding tube (3), and the pipe sleeve (32) is sleeved around the first connecting piece (28) and the second connecting piece (29); two ends of the pipe sleeve (32) are respectively provided with There is a pipe groove one (33) which can be slidably matched with the connecting piece one (28) and the connecting piece two (29); a pipe groove two (34) is provided in the pipe sleeve (32) between the two pipe grooves one (33); the top of the pipe sleeve (32) is vertically slidably connected to a top shaft (4); a gear five (41) and a plurality of gear fours (42) are rotatably mounted on the top surface of the top plate (11); the bottom surface of the gear five (41) is fixedly connected to the top end of the top shaft (4); and the top end of the threaded pipe (13) is fixedly connected to the bottom surface of the gear four (42).

5. A method for detecting the pull-out bearing capacity of a prestressed pipe pile according to claim 4, Features: A gear 1 (23) is rotatably mounted on the top surface of the drive box (21), and a gear 2 (24) is rotatably mounted on the bottom surface of the drive box (21); a gear 3 (25) is rotatably mounted on the inner side wall of the drive box (21); the output shaft of the motor (22) is coaxially fixedly connected to the gear 3 (25); the gear 3 (25) is meshed with the gear 1 (23) and the gear 2 (24) respectively; a drive tube (26) is fixedly mounted on the top of the gear 1 (23), and a drive shaft (27) is fixedly mounted on the top of the gear 2 (24); the connecting piece 1 (28) is fixedly mounted on the top end of the drive shaft (27); and the connecting piece 2 (29) is fixedly mounted on the top end of the drive tube (26).

6. A method for detecting the pull-out bearing capacity of a prestressed pipe pile according to claim 4, Features: A support plate (35) is fixed to the outer circumferential surface of the support rod (31), a spring (36) is fixed to the top end of the support plate (35), and the top end of the spring (36) is fixedly connected to the bottom surface of the slide tube (3); an electromagnet (37) is fixed to the top end of the support rod (31), and a magnetic attraction plate (38) that can be magnetically attracted to the electromagnet (37) is fixed to the top surface of the slide tube (3).

7. A method for detecting the pull-out bearing capacity of a prestressed pipe pile according to claim 6, Features: A switch moving plate 1 (51) is fixed on the top surface of the trigger plate (5), and a switch stator 1 (52) is fixed on the bottom surface of the bottom plate (12); the switch moving plate 1 (51) is connected in series with the electromagnet 1 (37) and the electromagnet 2 (44), and the switch stator 1 (52) is connected in series with a power source.

8. A method for detecting the pull-out bearing capacity of a prestressed pipe pile according to claim 4, Features: A blocking plate (53) is fixedly connected to the outer peripheral surface of the lead screw (14); a support plate (54) is fixed to the bottom end of the threaded tube (13); a plurality of push rods (55) are passed through the support plate (54); a second switch moving plate (56) is fixed to the top end of the push rod (55); a second switch stator plate (57) electrically connected to the second switch moving plate (56) is fixed to the top surface of the support plate (54); the second switch moving plate (56) is electrically connected to the motor (22), and the second switch stator plate (57) is electrically connected to a power source; a third spring (45) is fixed to the bottom surface of the support plate (54), and the bottom end of the third spring (45) is fixedly connected to the bottom end of the push rod (55).