Concrete module system of integrated reinforcement cage shear wall and construction method

By integrating the concrete module system with reinforced cage shear walls, the space occupied by formwork and beam formwork and the time required for tying steel bars are solved, achieving a more efficient construction process.

CN118814979AActive Publication Date: 2024-10-22GUANGDONG HAILONG CONSTR TECH CO LTD +1

Patent Information

Application Number
CN202411128302.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-10-22
Estimated Expiration
2044-08-16

AI Technical Summary

Technical Problem

In the existing technology, the formwork and beam formwork occupy the usable area of ​​the room and the binding of steel bars takes a lot of time, which affects the construction efficiency.

Method used

A concrete module system with integrated steel cage shear walls is used. By pre-embedding the steel cage and the tensile structure, the modules can participate in the stress during pouring, reducing space occupation. The steel bars are prefabricated in the factory to reduce on-site lashing work.

Benefits of technology

It reduces the space occupied by modules in the building, increases the usable area, greatly shortens on-site construction time, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118814979A_ABST
    Figure CN118814979A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of modular construction, and particularly relates to a concrete module system of an integrated reinforcement cage shear wall and a construction method, in the system, protruding reinforcement cages are pre-buried in first wall shells in a first module and a second module, and protruding pull structure reinforcing bars are pre-buried in first beam shells. The method comprises the following steps: placing a first module; a second module is placed, and a second stirrup is placed; a lap joint rib is pre-buried between the first module and the second module; a third module is placed, and a second stirrup is placed; a lap joint rib is pre-buried between the second module and the third module; splicing an upper layer module; and the second vertical stress ribs are connected. Therefore, the module of the system adopts the structural form of the first wall shell and the first beam shell, so that the first wall shell and the first beam shell participate in stress, the occupied space of the second shear wall and the beam is reduced, and the usable area of a building is increased. By means of the method, application of the concrete module system in engineering is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of modular construction, and in particular relates to a concrete module system and a construction method of an integrated steel cage shear wall. Background Art

[0002] With the continuous acceleration of urbanization and the continuous increase of urban population, the existence of old communities has become one of the bottlenecks restricting urban renewal and development. Moreover, the houses in old communities have poor construction quality and pose a large number of safety hazards. Therefore, the renovation and renewal of old communities can not only improve the living conditions of residents, but is also one of the mainstream directions for the subsequent development of the construction industry.

[0003] For the original demolition and reconstruction of old communities, if traditional construction methods are used, the noise, dust and other pollution generated will have a great impact on the normal life of surrounding residents. Therefore, it is necessary to introduce modular construction technology that can achieve rapid construction. Among them, the box-type concrete module uses the concrete formwork as the on-site concrete pouring formwork to make shear walls, and uses the beam formwork as the on-site concrete pouring formwork to make beam formwork, which greatly reduces the on-site formwork and internal decoration time, and minimizes the impact on surrounding residents.

[0004] However, the formwork and beam formwork do not participate in the force bearing, so the thickness of the formwork and beam formwork will not be calculated into the specified concrete thickness when pouring concrete. Then the formwork and beam formwork will occupy a certain area of ​​the room. At the same time, the steel bars of the shear wall and beam formwork need to be tied on site, which consumes a lot of time. Summary of the invention

[0005] 1. Technical issues to be resolved

[0006] In view of the above-mentioned shortcomings and deficiencies of the prior art, the present invention provides a concrete module system and construction method of integrated steel cage shear wall, thereby solving the technical problems that the formwork and beam formwork occupy the usable area of ​​the room, and that on-site tying of the steel bars of the shear wall and beam formwork consumes a lot of time.

[0007] (II) Technical solution

[0008] In order to achieve the above object, the main technical solutions adopted by the present invention include:

[0009] On the one hand, an embodiment of the present invention provides a concrete module system with an integrated steel cage shear wall, comprising at least two vertically connected concrete module layers, each concrete module layer comprising at least three transversely spliced ​​modules, the module comprising a connected shear wall portion and a beam portion, the shear wall portion and the beam portion supporting each other to form a module frame; three types of modules are provided, including a first module located at an outer edge of one side of the concrete module layer, a second module located inside the concrete module layer, and a third module located at an outer edge of the other side of the concrete module layer;

[0010] The first module and the second module are constructed as follows:

[0011] The shear wall portion includes a first wall shell, which is located on a side of the inner wall of the module and is pre-embedded with a protruding steel cage. The steel cage includes a plurality of first truss bars, a plurality of transverse bars and a plurality of longitudinal bars fixed into a whole and arranged vertically; the beam portion includes a first beam shell, which is located on a side top edge of the inner wall of the module and is pre-embedded with protruding tension structural bars.

[0012] Furthermore, the shear wall portion of the first module also includes a first shear wall located at the outer wall, the first shear wall is arranged opposite to the first wall shell, a vertical through hole is opened in the first shear wall, a first vertical force-bearing reinforcement is embedded in the through hole, the top end of the first vertical force-bearing reinforcement is protruding from the first shear wall, and the bottom end of the first vertical force-bearing reinforcement is recessed in the first shear wall, a grouting sleeve is embedded in the through hole and at the lower end of the first vertical force-bearing reinforcement, when two concrete module layers are vertically spliced, the first vertical force-bearing reinforcement located at the bottom is inserted into the corresponding through hole located at the top, and is connected to the first vertical force-bearing reinforcement in the corresponding through hole located at the top through the grouting sleeve; the beam portion of the first module also includes a first beam shell located at the outer wall.

[0013] Furthermore, the shear wall portion of the second module also includes a second wall shell, which is arranged opposite to the first wall shell, and the surface of the second wall shell is provided with an opening for accommodating a steel cage. When the two modules are horizontally spliced, the first wall shell of the module that is placed first and the second wall shell of the module that is placed later cooperate to form a second shear wall; the beam portion of the second module also includes a second beam shell, which is arranged opposite to the first beam shell. When the two modules are horizontally spliced, the first beam shell of one module cooperates with the second beam shell of the other module to form a beam.

[0014] Furthermore, the shear wall portion of the third module includes a first shear wall located on the side of the outer wall and a second wall shell arranged opposite thereto, and the beam portion of the third module includes a first beam shell located on the side top edge of the outer wall and a second beam shell arranged opposite thereto.

[0015] Furthermore, the first wall shell and the first beam shell of the same second module are located on the same side, and the second wall shell and the second beam shell are located on the same side; the first shear wall and the first beam shell of the same third module are located on the same side, and the second wall shell and the second beam shell are located on the same side.

[0016] Furthermore, the second shear wall includes a long side and a short side, and the long side and the short side form a U-shape. First stirrups in three directions are pre-embedded at the intersection of the long side and the short side in the second shear wall. The three first stirrups on the same horizontal plane are arranged in a U-shape. A number of second vertical force bars are arranged in the range surrounded by the three first stirrups. Two third vertical force bars and one third vertical force bar are respectively arranged at the inner and outer ends of the long side. When the two concrete module layers are vertically spliced, all the second vertical force bars and all the third vertical force bars corresponding to the upper and lower parts are overlapped by mechanical sleeves; part of the second vertical force bars in the first stirrups in the three directions are tightened by a number of second stirrups to connect the first stirrups with the second stirrups, so that the first stirrups in the three directions of each horizontal plane form a whole.

[0017] Furthermore, when two concrete module layers are vertically spliced, a plurality of lap bars protruding from the second shear wall are buried in the middle of the long side of the second shear wall below. The plurality of lap bars are arranged in pairs along the length direction of the long side. When the upper module layer falls, the lap bars are inserted into the corresponding second shear wall above.

[0018] Furthermore, the module also includes a top plate arranged on the top surface of the module and a bottom plate arranged on the bottom surface of the module; the top plate is a prefabricated concrete composite plate, and a second truss reinforcement protruding upward is embedded in the top plate. Before the two concrete module layers are vertically spliced, concrete is poured on the top plate to form a floor slab connected to the shear wall part and the beam part on the side; the bottom plate is a concrete plate.

[0019] Furthermore, the module also includes a partition wall portion, which is connected with the shear wall portion and the beam portion to form the side of the module; the partition wall portion includes a partition wall and a ring beam and a structural column surrounding the partition wall, the ring beam is fixed to the upper and lower sides of the partition wall, and the structural column is fixed to both sides of the partition wall;

[0020] On the other hand, an embodiment of the present invention further provides a construction method of a concrete module system with an integrated steel cage shear wall, comprising the following steps:

[0021] S1: Place the first module;

[0022] S2: placing the second module next to the first module, and placing second stirrups at the short side of the second shear wall formed between the first module and the second module;

[0023] S3: The second vertical force reinforcement is pre-embedded in the short side of the second shear wall formed between the first module and the second module, and the third vertical force reinforcement and lap reinforcement are pre-embedded in the long side;

[0024] S4: placing the third module next to the second module, and placing second stirrups at the short side of the second shear wall formed between the second module and the third module;

[0025] S5: The second vertical force reinforcement is pre-embedded in the short side of the second shear wall formed between the second module and the third module, and the third vertical force reinforcement and lap reinforcement are pre-embedded in the long side;

[0026] S6: After all modules of the same concrete module layer are in place, the upper modules are spliced. When the upper modules are in place, the first vertical force reinforcement at the bottom is inserted into the corresponding grouting sleeve in the first shear wall at the top, and the lap reinforcement is inserted into the corresponding second shear wall;

[0027] S7: Connect all the second vertical force-bearing bars and all the third vertical force-bearing bars corresponding to the upper and lower layers through mechanical sleeves.

[0028] (III) Beneficial effects

[0029] The beneficial effects of the present invention are:

[0030] The present invention discloses a concrete module system with integrated steel cage shear wall. Since the module adopts the structural form of a first wall shell and a first beam shell, when the first wall shell and the first beam shell are used as concrete casting templates for on-site casting, the steel cage of the first wall shell and the tensile structural reinforcement of the first beam shell are buried in the concrete cast on-site so that the first wall shell and the first beam shell are anchored with the cast-in-place concrete to form a whole, so that the first wall shell and the first beam shell participate in the force bearing, thereby reducing the occupied space of the second shear wall and the beam and increasing the usable area of ​​the building.

[0031] At the same time, most of the steel bars inside the shear walls of the integrated steel cage and the tensile reinforced beams are prefabricated and integrated in the factory, which greatly reduces the work of steel bar binding on site, thereby reducing the workload on site and saving on-site construction time.

[0032] The present invention also provides a construction method for a concrete module system of an integrated steel cage shear wall, so that the concrete module system can be applied to actual projects, thus realizing the application of the concrete module system in projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 It is a schematic diagram of the structure after the first module, the second module and the third module are spliced ​​together;

[0034] Figure 2 is a structural schematic diagram of the first module;

[0035] Figure 3 is a schematic diagram of the structure of the second module;

[0036] Figure 4 This is a structural diagram of the second module from another perspective;

[0037] Figure 5 is a structural schematic diagram of the third module;

[0038] Figure 6 It is a schematic diagram of the cross-sectional structure of the shear wall;

[0039] Figure 7 for Figure 6 Schematic diagram of AA in the middle;

[0040] Figure 8 for Figure 6 Schematic diagram of the middle BB;

[0041] Fig. 9 is a schematic diagram of the cross-sectional structure of the beam;

[0042] Fig.10 is a schematic diagram of the cross-sectional structure of the first shear wall;

[0043] Fig.11 for Fig.10 Schematic diagram of CC;

[0044] Fig.12 It is a schematic diagram of the planar structure after the first module, the second module and the third module are spliced ​​together.

[0045] [Description of Reference Numerals]

[0046] 1: first wall shell; 11: first truss reinforcement; 12: transverse reinforcement; 13: longitudinal reinforcement;

[0047] 2: First beam shell; 21: Tensile reinforcement;

[0048] 3: first shear wall; 31: first vertical force reinforcement; 32: grouting sleeve;

[0049] 4: Second wall shell; 5: Second beam shell;

[0050] 6: top plate; 61: second truss reinforcement;

[0051] 7: Bottom plate;

[0052] 8: partition wall; 81: partition wall; 82: ring beam; 83: structural column;

[0053] 9: second shear wall; 91: long side; 92: short side; 93: first stirrup; 94: second vertical force reinforcement; 95: mechanical sleeve; 96: second stirrup; 97: lap reinforcement; 98: third vertical force reinforcement;

[0054] 10: beam;

[0055] a: first module; b: second module; c: third module. DETAILED DESCRIPTION

[0056] In order to better explain the present invention and facilitate understanding, the present invention is described in detail below through specific implementation modes in conjunction with the accompanying drawings.

[0057] like Figure 1-12 As shown, the present invention provides a concrete module system with integrated steel cage shear wall, including at least two vertically connected concrete module layers, each concrete module layer includes at least three transversely spliced ​​modules, and the module includes a shear wall part, a beam part, a top plate 6 arranged on the top surface of the module, a bottom plate 7 arranged on the bottom surface of the module, and a partition wall part 8.

[0058] The shear wall part and the beam part are connected and support each other to form the frame of the module.

[0059] The top plate 6 is a prefabricated concrete composite plate, in which the bottom plate steel bars and the second truss bars 61 protruding upward are pre-embedded, and the thickness is about 60 mm. Before the two concrete module layers are vertically spliced, the bottom plate steel bars are mortised into the shear wall and beam parts, and then concrete is poured to bury the protruding second truss bars 61 and the bottom plate steel bars, so as to connect the top plate 6 with the shear wall and beam parts, and form a floor plate connected with the side shear wall and beam parts, and the final thickness of the floor plate is about 130 mm.

[0060] The bottom plate 7 is a concrete plate with a thickness of about 60 mm.

[0061] The partition wall part 8 is connected with the shear wall part and the beam part to form the side of the module, including the partition wall 81 and the ring beam 82 and the structural column 83 surrounding the partition wall 81. The partition wall 81 is a conventional ALC wall, which is lighter than a concrete wall and can reduce the weight of the entire module. The ring beam 82 is a concrete beam fixed to the upper and lower sides of the partition wall 81, and the structural column 83 is a concrete column fixed to both sides of the partition wall 81, which can increase the strength of the partition wall 81 and can play a hoisting role when the partition wall part 8 is hoisted.

[0062] like Figure 1 As shown, three modules are provided, including a first module a located at the outer edge of one side of the concrete module layer, a second module b located inside the concrete module layer, and a third module c located at the outer edge of the other side of the concrete module layer.

[0063] When there are three modules in the concrete module layer, the concrete module layer includes a first module a located at an outer edge of one side, a second module b located inside, and a third module c located at an outer edge of the other side.

[0064] When the number of modules in the concrete module layer is greater than three, the concrete module layer includes a first module a located at an outer edge of one side, a plurality of second modules b located inside, and a third module c located at an outer edge of the other side.

[0065] like Figure 2 , Figure 6 As shown, the first module a is constructed as follows:

[0066] The shear wall part includes a first wall shell 1 and a first shear wall 3 located at the outer wall. The first wall shell 1 is made of high-strength concrete, and vertical and horizontal steel bars have been pre-buried and tied in the factory. The first wall shell 1 is located on one side of the inner wall of the module. The first wall shell 1 is pre-buried with a protruding steel cage. The steel cage includes a plurality of first truss bars 11, a plurality of transverse bars 12 and a plurality of longitudinal bars 13 fixed into a whole and arranged vertically. A plurality of nuts are welded on the first truss bars 11. The thickness of the first wall shell 1 is not more than 50 mm. It is anchored with the cast-in-place concrete to form a whole and bear force together.

[0067] like Figure 2 As shown, the first shear wall 3 is arranged opposite to the first wall shell 1. Fig.10 , Fig.11 As shown, a vertical through hole is opened in the first shear wall 3, and a first vertical force reinforcement 31 is embedded in the through hole. The top end of the first vertical force reinforcement 31 is protruding from the first shear wall 3, and the bottom end of the first vertical force reinforcement 31 is recessed in the first shear wall 3. A grouting sleeve 32 is embedded in the through hole and at the lower end of the first vertical force reinforcement 31. When two concrete module layers are vertically spliced, the first vertical force reinforcement 31 located at the bottom is inserted into the corresponding through hole located at the top, and is connected to the first vertical force reinforcement 31 in the corresponding through hole located at the top through the grouting sleeve 32.

[0068] like Figure 2 , Fig. 9 As shown, the beam portion includes a first beam shell 2 located at the inner wall and a first beam shell 2 located at the outer wall, vertical and horizontal steel bars have been pre-embedded and tied in the factory, and at the same time, the first beam shell 2 is pre-embedded with protruding tension structural bars 21, and the thickness of the first beam shell 2 is not more than 30 mm, and it is anchored with the cast-in-place concrete to form a whole and bear the force together.

[0069] like Figure 3 , Figure 4 , Figure 6 As shown, the second module b is constructed as follows:

[0070] The shear wall portion includes a first wall shell 1 and a second wall shell 4. The first wall shell 1 is made of high-strength concrete and is located on one side of the module. The first wall shell 1 is pre-embedded with a protruding steel cage. The steel cage includes a plurality of first truss bars 11, a plurality of transverse bars 12 and a plurality of longitudinal bars 13 fixed into a whole and arranged vertically. A plurality of nuts are welded to the first truss bars 11. The thickness of the first wall shell 1 is not more than 50 mm. It is anchored with the cast-in-place concrete to form a whole and bear force together.

[0071] The second wall shell 4 is arranged opposite to the first wall shell 1. The surface of the second wall shell 4 is provided with a hole for accommodating a steel cage. The second wall shell 4 does not participate in the force and is only used as a template. The thickness of the second wall shell 4 is not more than 30 mm. When the two modules are horizontally spliced, a bolt is inserted into the hole of the second wall shell 4 of the module that is placed later, and one end of the bolt is fixed to the nut welded on the first truss reinforcement 11 of the module that is placed earlier, and then another nut is screwed into the other end of the bolt to fix the first wall shell 1 of the module that is placed earlier and the second wall shell 4 of the module that is placed later, and then concrete is poured between the first wall shell 1 of the module that is placed earlier and the second wall shell 4 of the module that is placed later to form a second shear wall 9.

[0072] The beam part includes a first beam shell 2 and a second beam shell 5. The first beam shell 2 is located at one side top edge of the module. The first beam shell 2 is pre-embedded with a protruding tensioning reinforcement 21. The thickness of the first beam shell 2 is not more than 30 mm. It is anchored with the cast-in-place concrete to form a whole and bear force together.

[0073] like Fig. 9 As shown, the second beam shell 5 is arranged opposite to the first beam shell 2, does not participate in the force, and is only used as a template. The thickness of the second beam shell 5 is not greater than 30 mm. When the two modules are horizontally spliced, the first beam shell 2 of one module cooperates with the second beam shell 5 of the other module to form a beam 10.

[0074] Preferably, the first wall shell 1 and the first beam shell 2 of the same second module b are located on the same side, and the second wall shell 4 and the second beam shell 5 are located on the same side.

[0075] like Figure 5 As shown, the third module c is constructed as follows:

[0076] The shear wall portion of the third module c includes a first shear wall 3 located on the side of the outer wall and a second wall shell 4 arranged opposite thereto, and the beam portion of the third module c includes a first beam shell 2 located on the top side of the outer wall and a second beam shell 5 arranged opposite thereto.

[0077] Preferably, the first shear wall 3 and the first beam shell 2 of the same third module c are located on the same side, and the second wall shell 4 and the second beam shell 5 are located on the same side.

[0078] It should be noted that the first wall shell 1 in the second module b is at the same position in the module as the first wall shell 1 in the first module a, and the second wall shell 4 in the second module b is at the same position in the module as the first shear wall 3 in the first module a. The first shear wall 3 in the third module c is at the same position in the module as the first wall shell 1 in the first module a, and the second wall shell 4 in the third module c is at the same position in the module as the first shear wall 3 in the first module a.

[0079] like Figure 6 , Figure 8As shown, the second shear wall 9 includes a long side 91 and a short side 92, and the long side 91 and the short side 92 form a T-shape. First stirrups 93 in three directions are pre-buried at the intersection of the long side 91 and the short side 92 in the second shear wall 9. The three first stirrups 93 on the same horizontal plane are arranged in a T-shape. A plurality of second vertical force bars 94 are arranged in the range surrounded by the three first stirrups 93. Two third vertical force bars 98 and one third vertical force bar 98 are respectively arranged at the inner and outer ends of the long side 91. When the two concrete module layers are vertically spliced, all the second vertical force bars 94 and all the third vertical force bars 98 corresponding to the upper and lower parts are connected through a mechanical sleeve 95.

[0080] Part of the second vertical force-bearing bars 94 in the first stirrups 93 in three directions are tightened by a plurality of second stirrups 96 to overlap the first stirrups 93 and the second stirrups 96 , so that the first stirrups 93 in three directions of each horizontal plane form a whole.

[0081] like Figure 7 As shown, when two concrete module layers are vertically spliced, a plurality of lap bars 97 protruding from the second shear wall 9 are buried in the middle of the long side 91 of the second shear wall 9 below. The plurality of lap bars 97 are arranged in pairs along the length direction of the long side 91. When the upper module layer falls, the lap bars 97 are inserted into the corresponding second shear wall 9 above.

[0082] like Fig.12 As shown, the present invention also provides a construction method of a concrete module system with an integrated steel cage shear wall, comprising the following steps:

[0083] S1: When installing the modules, since the first module a is integrated with a steel cage, it may collide with the lap ribs 97 below when it is in place, and after it is in place, it is necessary to check whether the steel cage is misaligned or fallen off, so the first module a needs to be installed first.

[0084] S2: Place the second module b next to the first module a, insert a bolt into the hole of the second wall shell 4 of the second module b, and fix one end of the bolt to the nut welded on the first truss reinforcement 11 of the first module a, and then screw another nut into the other end of the bolt to fix the first wall shell 1 of the first module a and the second wall shell 4 of the second module b, and then pour concrete between the first wall shell 1 of the first module a and the second wall shell 4 of the second module b to form a second shear wall 9, and place second stirrups 96 at the short side 92 of the second shear wall 9 formed between the first module a and the second module b.

[0085] S3: The second vertical force-bearing reinforcement is pre-embedded in the short side 92 of the second shear wall 9 formed between the first module a and the second module b, and the third vertical force-bearing reinforcement 98 and the lap reinforcement 97 are pre-embedded in the long side 91.

[0086] If the number of modules in the concrete module layer is greater than three, the remaining second modules b are continuously spliced ​​transversely in sequence after S3.

[0087] S4: The third module c is placed next to the second module b, and second stirrups 96 are placed at the short side 92 of the second shear wall 9 formed between the second module b and the third module c.

[0088] S5: The second vertical force-bearing reinforcement bars are pre-embedded in the short side 92 of the second shear wall 9 formed between the second module b and the third module c, and the third vertical force-bearing reinforcement bars 98 and the lap reinforcement bars 97 are pre-embedded in the long side 91 .

[0089] S6: After all modules of the same concrete module layer are in place, cast the concrete of the top plate 6, beam 10, beams at the outer wall and the second shear wall 9 as a whole, cast all the modules of the same concrete module layer that have been in place into a whole, then hoist the modules in the upper module layer, and splice the upper modules. When the upper modules are in place, the first vertical force reinforcement 31 below is inserted into the corresponding grouting sleeve 32 in the first shear wall 3 above, and the lap reinforcement 97 is inserted into the corresponding second shear wall 9.

[0090] S7: Connect all the second vertical force-bearing bars 94 and all the third vertical force-bearing bars 98 corresponding to the upper and lower layers through the mechanical sleeve 95.

[0091] It should be noted that the first module a, the second module b and the third module c in the construction method of the concrete module system of the integrated steel cage shear wall also include a top plate 6 arranged on the top surface of the module, a bottom plate 7 arranged on the bottom surface of the module and a partition wall portion 8.

[0092] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0093] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0094] In the present invention, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.

[0095] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.

[0096] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may alter, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A concrete module system with integrated steel cage shear wall, characterized in that: It comprises at least two layers of vertically connected concrete modules, each of which comprises at least three modules connected transversely, wherein the modules comprise connected shear wall parts and beam parts, and the shear wall parts and beam parts support each other to form a frame of the modules; Three modules are provided, including a first module (a) located at the outer edge of one side of the concrete module layer, a second module (b) located inside the concrete module layer, and a third module (c) located at the outer edge of the other side of the concrete module layer; The first module (a) and the second module (b) are constructed as follows: The shear wall portion comprises a first wall shell (1), the first wall shell (1) being located on a side surface of the inner wall of the module, the first wall shell (1) being pre-embedded with a protruding steel cage, the steel cage comprising a plurality of first truss bars (11), a plurality of transverse bars (12) and a plurality of longitudinal bars (13) fixed into a whole and arranged vertically; The beam portion comprises a first beam shell (2), the first beam shell (2) being located at a side top edge of the module inner wall, and the first beam shell (2) being pre-embedded with protruding tension structural ribs (21).

2. The concrete module system of integrated steel cage shear wall according to claim 1 is characterized in that: The shear wall portion of the first module (a) further comprises a first shear wall (3) located at the outer wall, the first shear wall (3) being arranged opposite to the first wall shell (1), a vertical through hole being provided in the first shear wall (3), a first vertical force-bearing bar (31) being pre-buried in the through hole, the top end of the first vertical force-bearing bar (31) being protruding from the first shear wall (3), the bottom end of the first vertical force-bearing bar (31) being recessed from the first shear wall (3), a grouting sleeve (32) being pre-buried in the through hole and at the lower end of the first vertical force-bearing bar (31), when two layers of the concrete module are vertically spliced, the first vertical force-bearing bar (31) located at the bottom is inserted into the corresponding through hole located at the top, and is connected to the first vertical force-bearing bar (31) in the corresponding through hole located at the top through the grouting sleeve (32); The beam portion of the first module (a) further comprises a first beam shell (2) located at the outer wall.

3. The concrete module system of integrated steel cage shear wall according to claim 2 is characterized in that: The shear wall portion of the second module (b) further comprises a second wall shell (4), the second wall shell (4) being arranged opposite to the first wall shell (1), the surface of the second wall shell (4) being provided with an opening for accommodating the steel cage, and when the two modules are horizontally spliced, the first wall shell (1) of the module that is placed first and the second wall shell (4) of the module that is placed later cooperate to form a second shear wall (9); The beam portion of the second module (b) further comprises a second beam shell (5), the second beam shell (5) being arranged opposite to the first beam shell (2), and when the two modules are transversely spliced, the first beam shell (2) of one module cooperates with the second beam shell (5) of the other module to form a beam (10).

4. The concrete module system of integrated steel cage shear wall according to claim 3 is characterized in that: The shear wall portion of the third module (c) comprises a first shear wall (3) located on the side of the external wall and a second wall shell (4) arranged opposite thereto, and the beam portion of the third module (c) comprises a first beam shell (2) located on the top side of the external wall and a second beam shell (5) arranged opposite thereto.

5. The concrete module system of integrated steel cage shear wall according to claim 4 is characterized in that: The first wall shell (1) and the first beam shell (2) of the same second module (b) are located on the same side, and the second wall shell (4) and the second beam shell (5) are located on the same side; The first shear wall (3) and the first beam shell (2) of the same third module (c) are located on the same side, and the second wall shell (4) and the second beam shell (5) are located on the same side.

6. The concrete module system of integrated steel cage shear wall according to claim 5, characterized in that: The second shear wall (9) comprises a long side (91) and a short side (92), wherein the long side (91) and the short side (92) form a T-shape, first stirrups (93) in three directions are pre-buried at the intersection of the long side (91) and the short side (92) in the second shear wall (9), the three first stirrups (93) on the same horizontal plane are arranged in a T-shape, a plurality of second vertical force-bearing bars (94) are arranged within the range surrounded by the three first stirrups (93), two third vertical force-bearing bars (98) and one third vertical force-bearing bar (98) are respectively arranged at the inner and outer ends of the long side (91), and when two concrete module layers are vertically spliced, all the second vertical force-bearing bars (94) and all the third vertical force-bearing bars (98) corresponding to each other above and below are connected via a mechanical sleeve (95); Part of the second vertical force-bearing bars (94) in the first stirrups (93) in three directions are tightened by a plurality of second stirrups (96) so that the first stirrups (93) and the second stirrups (96) are overlapped, so that the first stirrups (93) in three directions of each horizontal plane form a whole.

7. The concrete module system of integrated steel cage shear wall according to claim 6, characterized in that: When the two concrete module layers are vertically spliced, a plurality of lap ribs (97) protruding from the second shear wall (9) are embedded in the middle of the long side (91) of the second shear wall (9) below. The plurality of lap ribs (97) are arranged in pairs along the length direction of the long side (91). When the module layer above falls, the lap ribs (97) are inserted into the corresponding second shear wall (9) above.

8. The concrete module system of integrated steel cage shear wall according to claim 1, characterized in that: The module further comprises a top plate (6) arranged on the top surface of the module and a bottom plate (7) arranged on the bottom surface of the module; The top plate (6) is a prefabricated concrete composite plate, and a second truss rib (61) protruding upward is pre-embedded in the top plate (6). Before the two concrete module layers are vertically spliced, concrete is poured on the top plate (6) to form a floor plate connected to the shear wall part and the beam part on the side. The bottom plate (7) is a concrete plate.

9. The concrete module system of integrated steel cage shear wall according to claim 1, characterized in that: The module further comprises a partition wall portion (8), wherein the partition wall portion (8) is connected with the shear wall portion and the beam portion to form a side surface of the module; The partition wall portion (8) comprises a partition wall (81) and a ring beam (82) and a structural column (83) surrounding the partition wall (81); the ring beam (82) is fixed to the upper and lower sides of the partition wall (81); and the structural column (83) is fixed to both sides of the partition wall (81).

10. A construction method for a concrete module system of an integrated steel cage shear wall according to claim 7, characterized in that: The following steps are involved: S1: placing the first module (a); S2: placing the second module (b) next to the first module (a), and placing the second stirrups (96) at the short side (92) of the second shear wall (9) formed between the first module (a) and the second module (b); S3: The second vertical force-bearing reinforcement (94) is pre-embedded in the short side (92) of the second shear wall (9) formed between the first module (a) and the second module (b), and the third vertical force-bearing reinforcement (98) and the lap reinforcement (97) are pre-embedded in the long side (91); S4: placing the third module (c) next to the second module (b), and placing the second stirrups (96) at the short side (92) of the second shear wall (9) formed between the second module (b) and the third module (c); S5: The second vertical force-bearing reinforcement (94) is pre-embedded in the short side (92) of the second shear wall (9) formed between the second module (b) and the third module (c), and the third vertical force-bearing reinforcement (98) and the lap reinforcement (97) are pre-embedded in the long side (91); S6: After all the modules of the same concrete module layer are in place, the modules of the upper layer are spliced. When the modules of the upper layer are in place, the first vertical force-bearing reinforcement (31) below is inserted into the corresponding grouting sleeve (32) in the first shear wall (3) above, and the lap reinforcement (97) is inserted into the corresponding second shear wall (9); S7: Connecting all the second vertical force-bearing bars (94) and all the third vertical force-bearing bars (98) corresponding to the upper and lower layers via a mechanical sleeve (95).

Citation Information

Patent Citations

  • Modular shear wall structure and construction method thereof

    CN115807499A

  • Modularized frame shear wall structure

    CN219316095U

  • Prefabricated room module, steel-concrete building module composite structure and steel-concrete building

    WO2024160302A2

Cited By

  • Ribbed formwork shell plate composite wall, concrete module and assembling method of concrete module

    CN120990273A