Method for measuring heights of new and old anodes

The automated system of robotic arms and high-temperature laser rangefinders solves the problem of inaccurate manual measurement of old and new anode heights, enables safer and more efficient anode replacement operations, and improves the quality and production efficiency of aluminum water in aluminum electrolysis production.

CN118816732APending Publication Date: 2024-10-22SHANDONG REAL CONTROL AUTOMATION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411112919.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-10-22

AI Technical Summary

Technical Problem

In the aluminum electrolysis production process, manual measurement of the height of new and old anodes is dangerous and inaccurate, resulting in poor aluminum water quality and low production efficiency.

Method used

A robotic arm combined with a high-temperature laser rangefinder is used to automatically measure the height of the old and new anodes. Hydraulic cylinders and rope-type rotary encoders are used to achieve precise height coding and automated operations, replacing manual measurement and ensuring a high degree of consistency in anode replacement.

Benefits of technology

It improves the accuracy and safety of anode height measurement, reduces worker labor intensity, avoids potential accidents, improves aluminum water quality and production efficiency, and ensures stable and efficient production of electrolytic aluminum.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118816732A_ABST
    Figure CN118816732A_ABST
Patent Text Reader

Abstract

According to the method for measuring the heights of the new and old anodes, the production organization is optimized, a large amount of time is saved for electrode changing operation, fine electrode changing operation such as electrode changing block fishing, furnace bottom precipitation treatment and bus ash wiping can be better carried out, the electrode changing quality is guaranteed, and production linkage is greatly optimized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of electrolytic aluminum, and in particular relates to a method for measuring the heights of new and old anodes. Background Art

[0002] In the aluminum electrolysis production process, because the anode carbon blocks are consumed very quickly, they need to be replaced frequently, with new anodes replacing old anodes. During the replacement process, the new anode is required to be in the same position as the lower surface of the other old anodes. The greater the position deviation between the new anode and the other old anodes, the more likely it is to produce abnormal effects, thereby deteriorating the quality of the produced aluminum liquid. This will not only reduce production output, but also cause energy waste.

[0003] However, in the current process of replacing the old anode with the new one, the height of the old anode is generally measured manually with a handheld ruler, which is dangerous in use. Summary of the invention

[0004] In order to solve the above-mentioned deficiencies in the prior art, the present invention provides a method for measuring the height of new and old anodes.

[0005] This application proposes a method for measuring the height of new and old anodes, S1: measuring the installation height of the original and old anodes in the electrolytic cell, After the clamping part at the end of the mechanical arm is correctly clamped in the clamping hole of the anode, the hydraulic cylinder lifts the mechanical arm, and the pull-rope rotary encoder sends the current height code to the control instrument to obtain the currently measured height of the mechanical arm; S2: Measure the height of the old anode, After measuring the installation height of the old anode, the old anode is lifted to the top of one of the anodes and then stopped. The anodes start to be lifted at the same time, and the lifting speed is kept consistent. The movement is stopped at the same time. The high-temperature laser rangefinder is lowered. When the bottom of the anode is detected, the height measured by the stroke measuring device on the measuring rod is recorded instantly. The height of the anode can be obtained by calculation. After the measurement is completed, the laser rangefinder is retracted to the top. S3: Measure the height of the new anode, By using the above method, the height of the new anode can be measured respectively, and after the measurement is completed, the laser rangefinder (2) is retracted to the top; S4: Install new anode, After measuring the above three data, the installation height of the new anode is automatically calculated, the new anode is lifted above the electrolytic cell, and the new anode is lowered. When the control instrument detects that the lowering height reaches the installation height of the new anode, the control instrument automatically stops the descending movement of the robotic arm to keep the new anode at the installation height, thus completing the entire anode replacement operation.

[0006] Specifically, in S2, during the descent of the laser rangefinder, it is determined whether the bottom of the anode is measured by the change in the measured distance.

[0007] Compared with the prior art, the present invention has the following beneficial effects: 1. The aluminum plant anode height measurement and positioning system using laser ranging technology has the advantages of high accuracy, high degree of automation and greater safety; 2. Replacement of manual labor: It replaces manual measurement of residual (new) anodes, reduces the labor intensity of workers, reduces the high-temperature baking of operators when taking out hot residual anode wires, and avoids the occurrence of some potential safety accidents; 3. Improve quality and increase efficiency: The anode height measurement accuracy is improved, the current distribution of the electrolytic cell is more uniform, and the electrolytic cell needle swing and bias current caused by uneven anode current distribution are reduced, the electrolyte quality is improved, and the stability and efficiency of electrolytic aluminum are guaranteed; 4. Optimize production organization: Save a lot of time for pole changing operations, which can be used to better carry out refined pole changing operations such as pole changing blocks, furnace bottom sedimentation treatment, busbar wiping, etc., to ensure the quality of pole changing and greatly optimize production connection. BRIEF DESCRIPTION OF THE DRAWINGS

[0008] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0009] Figure 1 It is a schematic diagram of the structure of the present invention; Figure 2 This is a schematic diagram of the measurement process of the old anode; Figure 3 It is a schematic diagram of the measurement process of the new anode; Figure 4 It is a flow chart of the present invention. DETAILED DESCRIPTION

[0010] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0011] A method of measuring the height of the new and old anodes, such as Figure 1 As shown, S1: Measure the installation height of the old anode in the electrolytic cell. After the clamping part at the end of the mechanical arm 7 is correctly stuck in the clamping hole of the anode 6, the hydraulic cylinder 8 lifts the mechanical arm 7, and the pull-rope rotary encoder 3 sends the current height code to the control instrument to obtain the currently measured height of the mechanical arm 7; S2: Measure the height of the old anode, After measuring the installation height of the old anode, the old anode is simultaneously lifted to the top of one of the anodes 6 and then stopped. The anode 6 starts to be lifted at the same time, and the lifting speed is kept consistent, and the movement is stopped at the same time. The high-temperature laser rangefinder 2 is lowered. During the descent of the laser rangefinder 2, it is determined whether the bottom of the anode 6 is measured by the change in the measured distance. When the bottom of the anode 6 is detected, the height measured by the stroke measuring device on the measuring rod 1 is recorded instantly. The height of the anode 6 can be obtained by calculation. After the measurement is completed, the laser rangefinder 2 is retracted to the top. S3: Measure the height of the new anode, By using the above method, the height of the new anode can be measured respectively, and after the measurement is completed, the laser rangefinder 2 is retracted to the top; S4: Install new anode, After measuring the above three data, the installation height of the new anode is automatically calculated, the new anode is lifted above the electrolytic cell, and the new anode is lowered. When the control instrument detects that the lowering height reaches the installation height of the new anode, the control instrument automatically stops the descending movement of the robot arm 7 to keep the new anode at the installation height, thus completing the entire replacement operation of the anode 6.

[0012] Measurement process: 1. Take the old position When the crane lifts the old anode, the position needs to be recorded, which is called taking the old position.

[0013] 2. Measure the old height The old anode is lifted up by an overhead crane, and a laser rangefinder is used to find the bottom of the old anode and record the position data at that time. This is to measure the old height.

[0014] 3. Measuring new highs Subsequently, the old anode is placed in the old anode collection tank. After the crane operator cleans the electrolytic cell, the new anode is lifted by the crane and the bottom of the new anode is measured to obtain the new height.

[0015] 4. Calculate the potential difference Position difference = old position - (new high - old high) - horizontal reference value New high - old high = anode consumption The old position is a reference value for the depth of the new anode placed in the electrolytic cell. Combined with the anode consumption, it is possible to determine how much the new anode is higher than the old position.

[0016] The horizontal reference value (which can be regarded as the zero point) is the compensation amount in the calculation formula and is used to correct the error.

[0017] Specific implementation process: 1. Old position measurement: read the values ​​of the encoders of robot arms 1 and 2, which is the position of the old anode placed in the liquid surface of the electrolytic cell; At this time, the power of the laser rangefinder is closed and the laser rangefinder starts working; 2. Old height measurement: allow measurement position, drive the measuring rod to descend: position control, speed control, descend to the outer surface of the carbon block (i.e. the anode), at this time rely on the data measured by the laser rangefinder to make judgments, and record the value of the measuring rod rope encoder at the same time, The measuring rod slows down and continues to descend until the laser rangefinder data is separated from the carbon block, and the measuring rod encoder value is recorded as data 1. The measuring rod stops descending and starts to rise. The laser rangefinder measures the carbon block and records the measuring rod encoder value as data 2. The measuring rod stops rising and starts to descend. The laser rangefinder data is separated from the carbon block, and the measuring rod encoder value is recorded as data 3. The measuring rod stops descending and starts to rise. The laser rangefinder data measures the carbon block and records the measuring rod encoder value as data 4. The measuring rod stops rising and starts to descend. The laser rangefinder data is separated from the carbon block, and the measuring rod encoder value is recorded as data 5. The measuring rod stops descending and starts to rise. The laser rangefinder data measures the carbon block and the measuring rod encoder value is recorded as data 6. The measuring rod rises back to the top zero point, the height measurement is finished, and the average of the 6 data = the old height data; 3. New high measurement: Allows measuring position and driving the measuring rod to land: position control, speed control, The measuring rod with the laser rangefinder descends to the outer surface of carbon block 1. The laser rangefinder measures data to determine whether the carbon block is detected, and also records the value of the measuring rod rope encoder: The measuring rod slows down and continues to descend until the laser rangefinder data is separated from carbon block 1, and the measuring rod encoder value is recorded as data 1. The measuring rod stops descending and starts to rise. The laser rangefinder measures the carbon block 1 and records the measuring rod encoder value as data 2. The measuring rod stops rising and starts to descend. The laser rangefinder data is separated from carbon block 1, and the measuring rod encoder value is recorded as data 3. The measuring rod stops descending and starts to rise. The laser rangefinder data measures the carbon block 1, and the measuring rod encoder value is recorded as data 4. The measuring rod stops rising and starts to descend. The laser rangefinder data is separated from carbon block 1, and the measuring rod encoder value is recorded as data 5. The measuring rod stops descending and starts to rise. The laser rangefinder data measures the carbon block 1, and the measuring rod encoder value is recorded as data 6. After the new high is measured, the average of the 6 data is the new high 1 data. at this time, The measuring rod continues to descend until the laser rangefinder is separated from the carbon block 2, and the value of the measuring rod encoder is recorded as data 7. The measuring rod stops descending and starts to rise. The laser rangefinder data measures the carbon block 2, and the measuring rod encoder value is recorded as data 8. The measuring rod stops rising and starts to descend. The laser rangefinder data is separated from carbon block 2, and the measuring rod encoder value is recorded as data 9. The measuring rod stops descending and starts to rise. The laser rangefinder data measures the carbon block 2, and the measuring rod encoder value is recorded as data 10. The measuring rod stops rising and starts to descend. The laser rangefinder data is separated from carbon block 2, and the measuring rod encoder value is recorded as data 11. The measuring rod stops descending and starts to rise. The laser rangefinder data measures the carbon block 2, and the measuring rod encoder value is recorded as data 12. After the second measurement of the new high is completed, the average value of the 6 data = the new high 2 data; During the measurement of the old height and the new height, the lifting speed is controlled according to the position change; The data measured by the laser rangefinder determines whether it has left the bottom edge of the carbon block, and records the encoder value when the measuring rod is at the bottom of the carbon block.

[0018] Measuring rod drawstring encoder: The measuring rod is moved by the inverter driving the motor (with a reducer driving the belt, the belt drives the measuring rod up and down). The drawstring encoder is fixedly installed at a fixed position next to the electrode reduction motor. The drawstring ring is located inside the measuring rod. When the measuring rod is raised or lowered, the drawstring ring follows the measuring rod to complete the travel measurement of the drawstring encoder, which is used as the measurement value of the measuring rod telescopic height. It is used for old height measurement and new height measurement.

[0019] Wire rope encoder: The fixed sides of the two wire rope encoders are installed on the fixed sides of the two hydraulic cylinders, and the wire rope pull ring is fixed on the hydraulic rod side. The hydraulic rod (the moving side of the hydraulic cylinder) is connected to the mechanical arm. When the hydraulic rod is extended or retracted, it drives the mechanical arm to rise and fall, thus completing the lifting of the anode. The wire rope encoder also completes the measurement during the lifting process. It is used for taking the old position for measurement.

[0020] Equipment location relationship: A hydraulic cylinder 8 is installed on one side of the bottom end of the overhead crane, and a mechanical arm 7 is installed on the bottom end of the moving end of the hydraulic cylinder 8. A box is installed on the other side of the bottom end of the overhead crane, and a motor 4 is installed in the box. A wire pulley 5 is fixedly installed on the end of the output shaft of the motor. An internal hollow measuring rod 1 is installed at the bottom end of the box. The upper end of the measuring rod is connected to the inside of the box, and the lower end of the measuring rod is connected to the outside world. A vertical rod is slidably installed in the measuring rod, and a laser rangefinder 2 is installed at the bottom end of the vertical rod.

[0021] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A method for measuring the height of new and old anodes, characterized in that: The following steps are involved: S1: Measure the installation height of the old anode in the electrolytic cell. After the clamping part at the end of the mechanical arm (7) is correctly clamped in the clamping hole of the anode (6), the hydraulic cylinder (8) lifts the mechanical arm (7), and the pull-rope type rotary encoder (3) sends the current height code to the control instrument to obtain the currently measured height of the mechanical arm (7); S2: Measure the height of the old anode, After measuring the installation height of the old anode, the old anode is simultaneously lifted to the top of one of the anodes (6) and then stopped. The anode (6) starts to be lifted at the same time, and the lifting speed is kept consistent. The movement is stopped at the same time. The high-temperature laser distance meter (2) is lowered. When the bottom of the anode (6) is detected, the height measured by the stroke measuring device on the measuring rod (1) is recorded instantly. The height of the anode (6) can be obtained by calculation. After the measurement is completed, the laser distance meter (2) is retracted to the top. S3: Measure the height of the new anode, By using the above method, the height of the new anode can be measured respectively, and after the measurement is completed, the laser rangefinder (2) is retracted to the top; S4: Install new anode, After the above three data are measured, the installation height of the new anode is automatically calculated, the new anode is lifted to the top of the electrolytic cell, and the new anode is lowered. When the control instrument detects that the lowering height reaches the installation height of the new anode, the control instrument automatically stops the descending movement of the mechanical arm (7) to keep the new anode at the installation height, thus completing the entire anode (6) replacement operation.

2. A method for measuring the height of new and old anodes according to claim 1, characterized in that: In S2, during the descent of the laser rangefinder (2), it is determined whether the bottom of the anode (6) has been measured by the change in the measured distance.