Self-adaptive task scheduling system for large hydropower station
By designing an adaptive task scheduling system in the hydropower station to collect and process real-time data, the problem of insufficient data in the operation of the hydropower station is solved, the water resource utilization efficiency and unit performance are improved, and the waste of water resources is reduced.
Patent Information
- Application Number
- CN202410807592.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-21
- Publication Date
- 2024-10-22
AI Technical Summary
The lack of reasonable data and system support in the operation of existing hydropower stations leads to inaccurate determination of reservoir water levels and inflows, and there is a waste of water resources.
An adaptive task scheduling system for large hydropower stations is designed, including a computer control center, data communication module, data acquisition unit and power plant peaking processing unit. It collects real-time data through units information collection, gate information collection, water regime telemetry and other modules, and The data analysis and processing unit collects and forecasts data every 10 minutes to provide decision support.
It realizes data collection, processing and information sharing of hydropower stations, improves water resource utilization efficiency and unit comprehensive performance, provides a reasonable basis for decision-making, and reduces water waste.
Smart Images

Figure CN118819086A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of hydropower stations, and in particular to an adaptive task scheduling system for a large hydropower station. Background Art
[0002] With the development of my country's economy and society, my country's annual power generation is constantly increasing. In my country's energy consumption structure, hydropower energy consumption ranks second. With the country's emphasis on the adjustment of energy structure, the annual power generation of hydropower is also increasing. Directly related to hydropower generation is hydropower station. Hydropower station is a comprehensive engineering facility that can convert water energy into electrical energy. Generally, it includes a reservoir formed by water retaining and water discharge structures (dams) and a hydropower station water diversion system, power plant, electromechanical equipment, etc.
[0003] Hydropower is the most mature and competitive clean renewable energy in my country's current development and operation technology. During the operation of a hydropower station, both the reservoir water level and the inflow volume must be considered, as well as the performance of the unit. Existing hydropower stations are mostly operated based on experience, and there are situations where the reservoir water level and inflow volume are not accurately determined. Some power stations do not have water level and flow collection devices, and empirical operation lacks reasonable data and system support, resulting in water resource waste.
[0004] Constructing an optimized dispatching system for existing hydropower stations to realize data collection, optimization integration and automatic control can ensure the rationality of hydropower station operation and improve the utilization efficiency of water resources and the comprehensive performance of units. Summary of the invention
[0005] The purpose of the present invention is to provide a large hydropower station adaptive task scheduling system, aiming to solve the technical problems in the above-mentioned background technology.
[0006] The technical solution of the present invention is achieved in this way:
[0007] The technical solution of the present application provides an adaptive task scheduling system for a large hydropower station, including a computer control center, a data communication module, a data acquisition unit, a data management unit and a power plant peak-shaving processing unit, wherein the data communication module is used to realize information interaction between the data acquisition unit, the power plant peak-shaving processing unit and the computer control center;
[0008] The data acquisition unit includes a unit information acquisition module, a gate information acquisition module and a water regime telemetry module. The unit information acquisition module is used to collect the working data of the generator unit, the gate information acquisition module is used to collect the working data of the gate, and the water regime telemetry module is used to jointly measure the water level, flow velocity, flow rate and evaporation.
[0009] The power plant peak load regulation processing unit includes a dam water level acquisition module, a dam water level acquisition module, a data analysis and processing module and a unit output acquisition module. The data analysis and processing unit collects a set of real-time data from the dam water level acquisition module, the dam water level acquisition module and the unit processing acquisition module every 10 minutes to calculate and forecast the inflow process of the dam body in the future visible period, and obtain the total output value of the optimal hydropower station in the future for the management personnel to make reference decisions;
[0010] The data management unit is responsible for the storage and management of water regulation data, and includes a real-time data storage module, a historical data storage module, a static data storage module and an achievement data storage module;
[0011] The computer control center receives various types of data collected by the power plant peak-shaving processing unit and the data acquisition module, and automatically processes the data according to the preset application requirements of the computer control center.
[0012] In some embodiments of the present invention, the unit information acquisition module includes a current monitoring module for acquiring unit current, a voltage monitoring module for acquiring unit voltage, and a unit temperature monitoring module for acquiring unit temperature.
[0013] In some embodiments of the present invention, the water regime telemetry module includes a water level sensor, a rainfall tester and a telemetry station.
[0014] In some embodiments of the present invention, the gate information collection module includes an information recording module and an information reading module. The information reading modules are installed on both sides of the gate. There are multiple information reading modules, which are equidistantly arranged in sequence along the vertical movement direction of the gate. The information recording module is installed in the reading direction of the information reading module.
[0015] In some embodiments of the present invention, a comprehensive processing unit is further included, and the comprehensive processing unit includes a power generation management module, an information query module, a report management module, a benchmarking management module and a data entry module.
[0016] In some embodiments of the present invention, the computer control center includes a real-time data processing module and a conventional data processing module. The real-time data processing module completes the conversion of real-time water level-flow relationship and the calculation of rainfall in time period, and organizes it into time period data for different application requirements of hours, days, ten days, months and years.
[0017] In some embodiments of the present invention, a fire emergency module is further included, the fire emergency module includes a fire alarm module and a gate control module, the fire alarm module includes a smoke detector, a flame detector, a smoke exhaust fan and a fire extinguishing system;
[0018] The gate control module includes a gate control circuit.
[0019] In some embodiments of the present invention, a real-time monitoring module is also included, which is used to monitor the main equipment information of the hydropower station in real time, including the current unit operation mode, active and reactive data of the unit line, and the status of the main equipment.
[0020] In some embodiments of the present invention, the computer control center is communicatively connected to a cloud platform, and the cloud platform is communicatively connected to a weather forecast center.
[0021] Compared with the prior art, the technical solution of the present invention has at least the following advantages or beneficial effects:
[0022] (1) In this application, through the cooperation of the computer control center, data communication module, data acquisition unit, data management unit and power plant peak load processing unit, full use is made of computer, communication, database and hydrological technologies to automatically collect the information required for the dispatch of the hydropower station, and timely process and analyze the information to provide decision support for flood control, power generation and other applications of the hydropower station. At the same time, the above decision-making plan can be shared with the superior department through the data communication module to provide a decision-making basis for the superior management personnel to make reasonable dispatch.
[0023] (2) In the present application, the data analysis and processing unit collects a set of real-time data from the above-mentioned dam water level collection module, dam water level collection module and unit processing collection module every 10 minutes to calculate and forecast the inflow process of the dam body in the future visible period, and obtains the total output value of the optimal hydropower station in the future for the management personnel to make reference decisions. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.
[0025] Figure 1 This is a structural diagram of a large hydropower station adaptive task scheduling system according to an embodiment of the present invention;
[0026] Figure 2 This is a structural diagram of a unit information acquisition module according to an embodiment of the present invention;
[0027] Figure 3 This is a structural diagram of a water regime telemetry module according to an embodiment of the present invention;
[0028] Figure 4 This is a structural diagram of a gate information acquisition module according to an embodiment of the present invention;
[0029] Figure 5 This is a structural diagram of the cooperation among the computer control center, cloud platform and weather forecast center in an embodiment of the present invention. DETAILED DESCRIPTION
[0030] Example
[0031] Please refer to Figure 1-Figure 5 A large-scale hydropower station adaptive task scheduling system includes a computer control center, a data communication module, a data acquisition unit, a data management unit and a power plant peak-shaving processing unit. The data communication module is used to realize the information interaction between the data acquisition unit, the power plant peak-shaving processing unit and the computer control center; the data acquisition unit includes a unit information acquisition module, a gate information acquisition module and a water regime telemetry module. The unit information acquisition module is used to collect the working data of the generator unit, the gate information acquisition module is used to collect the working data of the gate, and the water regime telemetry module is used to measure the water level, flow velocity, flow and evaporation; the power plant peak-shaving processing unit includes an upper dam water level acquisition module, a lower dam water level acquisition module, a data management unit and a data management unit. According to the analysis and processing module and the unit output acquisition module, the data analysis and processing unit collects a group of real-time data from the above-dam water level acquisition module, the below-dam water level acquisition module and the unit processing acquisition module every 10 minutes to calculate and forecast the inflow process of the dam body in the future visible period, and obtain the total output value of the optimal hydropower station in the future for the management personnel to make reference decisions; the data management unit is responsible for the access and management of water regulation data, which includes a real-time data storage module, a historical data storage module, a static data storage module and an achievement data storage module; the computer control center receives various types of data collected by the power plant peak regulation processing unit and the data acquisition module, and automatically processes them according to the preset application requirements of the computer control center.
[0032] In this application, through the cooperation of the computer control center, data communication module, data acquisition unit, data management unit and power plant peak-shaving processing unit, full use is made of computers, traffic, databases, hydrology and other technologies to automatically collect the information required for hydropower station scheduling, and timely process and analyze the information to provide decision support for hydropower station flood control, power generation and other applications. At the same time, the above decision-making plans can be shared with superior departments through the data communication module to provide decision-making basis for superior managers to make reasonable scheduling.
[0033] In some embodiments of the present invention, the unit information acquisition module includes a current monitoring module for acquiring unit current, a voltage monitoring module for acquiring unit voltage, and a unit temperature monitoring module for acquiring unit temperature.
[0034] In the above embodiment, the computer control center sets the thresholds of the current, voltage and temperature of the generator set. When the corresponding monitoring values of the current monitoring module, the voltage monitoring module and the temperature monitoring module of the generator set exceed the thresholds, the computer control center promptly performs adaptive adjustment. Furthermore, the generator set is also equipped with a temperature monitoring module and a temperature adjustment module. The computer control center presets the temperature threshold of the generator set. When the operating temperature of the generator set exceeds the above temperature threshold, the temperature adjustment module is started to cool down the computer set to ensure that the generator set works under normal temperature conditions.
[0035] In some embodiments of the present invention, the water regime telemetry module includes a water level sensor, a rainfall tester and a telemetry station.
[0036] In the above embodiment, the real-time water and rainfall information upstream and downstream of the hydropower station is automatically collected based on the cooperation of the water level sensor, the rainfall tester and the telemetry station, and flood forecasting services are provided.
[0037] In some embodiments of the present invention, the gate information collection module includes an information recording module and an information reading module. The information reading modules are installed on both sides of the gate. There are multiple information reading modules, which are equidistantly arranged in sequence along the vertical movement direction of the gate. The information recording module is installed in the reading direction of the information reading module.
[0038] In the above embodiment, when there are multiple gates in the hydropower station, the multiple gates are equipped with information recording modules and information reading modules, and the multiple gates, information recording modules and information reading modules are numbered one by one. The cooperation of the information recording module and the information reading module can accurately record the position of the gate, and then obtain the size of the gate opening and closing, so that the staff can understand the working status of the position status of all gates in the hydropower station without any on-site observation and monitoring.
[0039] In some embodiments of the present invention, a comprehensive processing unit is further included, and the comprehensive processing unit includes a power generation management module, an information query module, a report management module, a benchmarking management module and a data entry module.
[0040] In the above embodiment, the comprehensive processing unit is used to perform integrated management of multiple hydropower stations. The power generation management module mainly calculates the power generation of each hydropower station according to the time dimensions of day, week, month and year, and performs statistics on the year-on-year and month-on-month data of the power generation completion value. The information query module queries various trend information of the data, including annual, monthly, daily, year-on-year and month-on-month data information; the trend information of any data can be listed together with the unit load information for easy analysis. The report management module provides statistical analysis reports with flexible data query, customization and export functions, and the reports can be exported to Excel and PDF formats for storage. The benchmarking management module establishes a production indicator benchmarking system, which is displayed in various forms such as tables, bar charts, curve charts and radar charts through vertical benchmarking and horizontal comparison. The data entry module provides entry of management information of each hydropower station and queries the entry status.
[0041] In some embodiments of the present invention, the computer control center includes a real-time data processing module and a conventional data processing module. The real-time data processing module completes the conversion of real-time water level-flow relationship and the calculation of rainfall in time period, and organizes it into time period data for different application requirements of hours, days, ten days, months and years.
[0042] In the above embodiment, the computer control center realizes automatic processing of various types of collected data according to application requirements. The real-time data processing module and the conventional data processing module cooperate to complete the conversion of real-time water level flow relationship, time period rainfall calculation and other operations: time period data processing organizes real-time data into time period data of different application requirements such as hours, days, ten days, months, and years, providing basic data for water regulation and other systems.
[0043] In some embodiments of the present invention, a fire emergency module is further included, the fire emergency module includes a fire alarm module and a gate control module, the fire alarm module includes a smoke detector, a flame detector, a smoke exhaust fan and a fire extinguishing system;
[0044] The gate control module includes a gate control circuit.
[0045] In the above embodiment, the smoke detector, flame detector, smoke exhaust fan and fire extinguishing system cooperate to realize the emergency fire protection of the hydropower station. The gate control circuit can realize the control of gate lifting and lowering to achieve water flow regulation.
[0046] In some embodiments of the present invention, a real-time monitoring module is also included, which is used to monitor the main equipment information of the hydropower station in real time, including the current unit operation mode, active and reactive data of the unit line, and the status of the main equipment.
[0047] In the above embodiment, the computer control center is equipped with a human-machine interface, which consists of a human-machine interface display, a human-machine interface editor, graphics, reports and a user interface, realizing the display of graphics, pictures and reports, and providing users with a visual water adjustment platform operation interface.
[0048] In some embodiments of the present invention, the computer control center is communicatively connected to a cloud platform, and the cloud platform is communicatively connected to a weather forecast center.
[0049] In the above embodiment, weather information is obtained based on the cloud platform and the weather forecast center to facilitate timely regulation of the system.
[0050] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A large hydropower station adaptive task scheduling system, characterized in that: It includes a computer control center, a data communication module, a data acquisition unit, a data management unit and a power plant peak-shaving processing unit, wherein the data communication module is used to realize information interaction between the data acquisition unit, the power plant peak-shaving processing unit and the computer control center; The data acquisition unit includes a unit information acquisition module, a gate information acquisition module and a water regime telemetry module. The unit information acquisition module is used to collect the working data of the generator unit, the gate information acquisition module is used to collect the working data of the gate, and the water regime telemetry module is used to jointly measure the water level, flow velocity, flow rate and evaporation; The power plant peak load processing unit includes a dam water level acquisition module, a dam water level acquisition module, a data analysis and processing module and a unit output acquisition module. The data analysis and processing unit collects a group of real-time data from the dam water level acquisition module, the dam water level acquisition module and the unit processing acquisition module every 10 minutes to calculate and predict the inflow process of the dam body within the future visible period, and obtain the total output value of the optimal hydropower station in the future for the management personnel to make reference decisions; The data management unit is responsible for the storage and management of water regulation data, and includes a real-time data storage module, a historical data storage module, a static data storage module and an achievement data storage module; The computer control center receives various types of data collected by the power plant peak-shaving processing unit and the data acquisition module, and automatically processes them according to the preset application requirements of the computer control center.
2. A large hydropower station adaptive task scheduling system according to claim 1, characterized in that: The unit information acquisition module includes a current monitoring module for acquiring unit current, a voltage monitoring module for acquiring unit voltage, and a unit temperature monitoring module for acquiring unit temperature.
3. A large hydropower station adaptive task scheduling system according to claim 2, characterized in that: The water regime telemetry module includes a water level sensor, a rainfall tester and a telemetry station.
4. A large hydropower station adaptive task scheduling system according to claim 3, characterized in that: The gate information acquisition module includes an information recording module and an information reading module. The information reading modules are installed on both sides of the gate. There are multiple information reading modules, which are equidistantly arranged in sequence along the vertical movement direction of the gate. The information recording module is installed in the reading direction of the information reading module.
5. A large hydropower station adaptive task scheduling system according to claim 1, characterized in that: It also includes a comprehensive processing unit, which includes a power generation management module, an information query module, a report management module, a benchmarking management module and a data entry module.
6. A large hydropower station adaptive task scheduling system according to claim 5, characterized in that: The computer control center includes a real-time data processing module and a conventional data processing module. The real-time data processing module completes the conversion of real-time water level flow relationship and the calculation of rainfall in time period, and organizes the time period data into different application requirements of hours, days, ten days, months and years.
7. A large hydropower station adaptive task scheduling system according to claim 1, characterized in that: It also includes a fire emergency module, which includes a fire alarm module and a gate control module. The fire alarm module includes a smoke detector, a flame detector, a smoke exhaust fan and a fire extinguishing system.
8. A large hydropower station adaptive task scheduling system according to claim 1, characterized in that: The gate control module includes a gate control circuit.
9. A large hydropower station adaptive task scheduling system according to claim 1, characterized in that: It also includes a real-time monitoring module, which is used to monitor the main equipment information of the hydropower station in real time, including the current unit operation mode, the active and reactive data of the unit line, and the status of the main equipment.
10. A large hydropower station adaptive task scheduling system according to claim 1, characterized in that: The computer control center is communicatively connected to a cloud platform, and the cloud platform is communicatively connected to a weather forecast center.