Formwork assembly for overcrossing existing line bridge wet joint and construction method

By designing formwork components for bridge wet joints and using wing plates and connectors to pour concrete to form a wet joint structure, the problem of difficulty in dismantling the formwork was solved, shortening the construction period and reducing costs.

CN118835528APending Publication Date: 2024-10-25NO 1 ENG CO LTD OF FHEC OF CCCC +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411117832.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-10-25

AI Technical Summary

Technical Problem

In bridge construction, it is difficult to dismantle the formwork of wet joints, resulting in long construction period and high cost, and the traditional formwork process is complicated, which affects the construction efficiency.

Method used

Design a formwork assembly for wet joints of existing bridges over spans, including flanges, connectors, bottom formwork, top formwork and side walls. The wet joint structure is formed by pouring concrete without removing the formwork, reducing the process and strengthening Connection reliability.

Benefits of technology

It achieves construction without removing the formwork, shortens the construction period, reduces construction costs, and improves the overall stability and construction efficiency of the bridge connection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118835528A_ABST
    Figure CN118835528A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of bridge construction, and discloses a formwork assembly used for overcrossing existing line bridge wet joints and a construction method.The formwork assembly used for overcrossing existing line bridge wet joints comprises first connecting pieces, second connecting pieces, third connecting pieces and fourth connecting pieces, the two ends of the bottom template are fixedly connected with the bottoms of the two wing plates respectively; the two ends of the top formwork are fixedly connected with the tops of the two wing plates respectively; the bottom formwork, the top formwork and the two adjacent wing plates define a wet joint post-cast strip, the wet joint post-cast strip is filled with concrete, and the bottom formwork, the top formwork and the concrete jointly form a wet joint structure. According to the formwork assembly for the wet joint of the overpass existing line bridge, the concrete is poured into the wet joint post-cast strip, the bottom formwork, the top formwork and the concrete jointly form a wet joint structure, and therefore the formworks do not need to be dismantled, working procedures are reduced, the construction period is shortened, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a template assembly and a construction method for a wet joint of an existing bridge. Background Art

[0002] With the development of highways and railways in my country, the construction method of prefabricating assembled beam and slab segments and hoisting them on site is becoming more and more widely used in the construction of bridges across existing lines. The purpose of rapid construction is achieved by quantitatively producing prefabricated beams and slabs and directly transporting them to the construction site for hoisting and splicing. The construction process of the key joints of the assembled structure is crucial to the life of the overall beam. Most of the wet joints in this part are transverse wet joints. However, the current wet joint construction of bridges still mostly uses traditional steel molds, wooden molds or bamboo glue molds. The molds need to be removed after the concrete is poured. There are many processes, and the difficulty in removing the molds leads to a long construction period and high construction costs. Summary of the invention

[0003] In view of this, the present invention provides a formwork assembly and construction method for wet joints of bridges across existing lines, so as to solve the problem that the formwork needs to be removed after the wet joints are poured, there are many steps, and the formwork is difficult to remove, resulting in a long construction period and high construction costs.

[0004] In a first aspect, the present invention provides a formwork assembly for crossing a wet joint of an existing bridge, which is arranged between two adjacent beams that are parallel and spaced apart in a first direction, and the two ends of the beams in the first direction are respectively extended to form wing plates. The formwork assembly for crossing a wet joint of an existing bridge comprises:

[0005] A first connecting member, fixedly connected between two adjacent wing plates;

[0006] A bottom template, a first end of which is fixedly connected to the bottom of one of the two adjacent wing plates, and a second end of which is fixedly connected to the bottom of the other wing plate;

[0007] A top template, a first end of which is fixedly connected to the top of one of the two adjacent wing plates, and a second end of which is fixedly connected to the top of the other wing plate;

[0008] The bottom formwork, the top formwork and the side walls of the two adjacent wing plates are combined to form a wet joint post-casting strip. The first connecting piece is located in the wet joint post-casting strip and is fixedly connected to the bottom formwork and the top formwork. The wet joint post-casting strip is suitable for being filled with concrete. The bottom formwork, the top formwork and the concrete together form a wet joint structure.

[0009] Beneficial effect: The first connecting piece, the bottom formwork and the top formwork are fixedly connected between two adjacent wing plates, concrete is poured into the wet joint post-casting zone, and the bottom formwork and the top formwork are constructed together with the concrete to form a wet joint structure, so there is no need to remove the formwork, which is beneficial to reducing the process, shortening the construction period and reducing the construction cost.

[0010] In an optional embodiment, a wing plate reinforcement is provided on the side of the wing plate facing another adjacent wing plate, and the first connecting member is fixedly connected to the two wing plate reinforcements at the same time.

[0011] Beneficial effect: By making the first connecting member fixedly connected to the two flange steel bars at the same time, it is beneficial to enhance the connection reliability of the two adjacent beams.

[0012] In an optional embodiment, the formwork assembly for the wet joint of an existing bridge also includes: a second connecting member, the second connecting member extends along a third direction, the second connecting member is connected between the bottom formwork and the top formwork, and the second connecting member at least partially crosses and overlaps with the first connecting member and is connected in the cross-overlap area.

[0013] Beneficial effect: The second connection not only fixes the bottom template and the top template together, but is also fixedly connected to the first connection piece, thereby improving the overall stability of the connection between the bottom template and the top template and the two wing panels.

[0014] In an optional embodiment, the first connecting member includes a waist-shaped steel bar; the second connecting member includes a U-shaped steel bar.

[0015] In an optional embodiment, the beam extends along the second direction, and multiple bottom templates are arranged along the second direction; the template assembly for crossing the wet joint of an existing bridge also includes a pad, which is arranged at the junction of two adjacent bottom templates, and the pad is suitable for covering the gap between the two adjacent bottom templates.

[0016] Beneficial effect: By setting a pad at the joint of two adjacent bottom templates to cover the gap between the two bottom templates, it is avoided that when pouring concrete into the wet joint post-casting zone, the concrete leaks to the bottom through the gap between the two bottom templates, affecting the normal operation of the existing line below.

[0017] In an optional embodiment, a fixing plate is fixedly connected to the bottom of the wing plate, and along the gravity direction, the projection of the fixing plate partially overlaps with the projection of the wet joint post-casting strip, so as to fix the fixing plate to the bottom formwork.

[0018] Beneficial effect: A fixing plate is fixedly connected to the bottom of the wing plate, and the bottom template is supported and fixed by the fixing plate, which is beneficial to improving the convenience of forming a fixed connection between the bottom template and the wing plate.

[0019] In an optional embodiment, the beam also includes a web extending along a third direction, the web is located below the wing plate, and there is a spacing between the webs of two adjacent beams. Along the second direction, the formwork assembly for crossing the wet joint of an existing bridge also includes at least one set of side formworks, each set of side formworks includes two spaced apart, the side formworks are located below the wing plate, and are simultaneously abutted against the lower end surface of the wing plate and the side surface of the web; the formwork assembly for crossing the wet joint of an existing bridge also includes a bottom formwork, the bottom formwork is simultaneously fixedly connected to the bottoms of two adjacent webs, the bottom formwork and the side formwork are enclosed between two adjacent beams to form a diaphragm post-cast strip, and the diaphragm post-cast strip is suitable for being filled with concrete.

[0020] Beneficial effect: By pouring concrete into the post-cast strip of the transverse beam, a transverse beam connecting two adjacent beams is formed, thereby improving the overall stability of the connection between the two adjacent beams.

[0021] In an optional embodiment, a first fixing member is provided on the lower end surface of the wing plate, and the first fixing member is fixedly connected to the side formwork to support and fix the side formwork.

[0022] In an optional embodiment, a second fixing member is arranged at an angle at the bottom of the first fixing member, and the second fixing member is fixedly connected to the bottom template to support and fix the bottom template.

[0023] In the second aspect, the present invention also provides a construction method, using the formwork assembly as mentioned above for wet joints of bridges across existing lines, the construction method comprising the following steps: pre-embedding a first fixing member when making a beam; fixing a fixing plate to the bottom of a wing plate; fixing a second fixing member to the bottom of the first fixing member; fixing a side formwork to the first fixing member, and fixing a bottom formwork to the second fixing member to enclose and form a transverse beam post-cast strip; pouring concrete into the transverse beam post-cast strip; laying a plurality of bottom formworks along the extension direction of the wing plate, and fixing them to the fixing plate; fixing a connecting pad at the joint between two adjacent bottom formworks; fixing the first connecting member to the wing plate steel bars of two adjacent beams; after fixing the second connecting member to the top formwork, laying a plurality of top formworks in sequence, and fixing the second connecting member to the first connecting member and the bottom formwork; pouring concrete into the wet joint post-cast strip.

[0024] Because the construction method using the formwork assembly for wet joints of bridges spanning existing lines as described above has the same effects as the formwork assembly for wet joints of bridges spanning existing lines, its beneficial effects are not repeated here. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0026] Figure 1 It is a schematic diagram of the matching state between the beam and the wet joint of the present invention;

[0027] Figure 2 for Figure 1 A partial enlarged view of the middle A;

[0028] Figure 3 for Figure 1 Schematic diagram of the middle BB section;

[0029] Figure 4 for Figure 3 A partial enlarged view of point C in the middle;

[0030] Figure 5 A top view of the fixed plate and the bottom template of the present invention in an exploded state;

[0031] Figure 6 It is a front view of the bottom formwork, side formwork and web plate in the matching state of the present invention;

[0032] Figure 7 It is a top view of the matching state of the bottom formwork, the side formwork and the web plate of the present invention;

[0033] Figure 8 It is a front view of the beam and the hanging basket in the matching state of the present invention;

[0034] Fig. 9 It is a top view of the matching state of the beam and the hanging basket of the present invention.

[0035] Description of reference numerals:

[0036] 1. Beam; 101. Flange; 102. Web; 2. Bottom formwork; 3. Top formwork; 4. Wet joint post-cast strip; 5. First connecting piece; 6. Second connecting piece; 7. Pad; 8. Side formwork; 9. Bottom formwork; 10. Flange reinforcement; 11. Fixing plate; 12. First fixing piece; 13. Second fixing piece; 14. Third connecting piece; 15. Hanging basket; 16. Steel pipe; 17. Fence. DETAILED DESCRIPTION

[0037] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0038] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0039] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0040] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0041] In the process of construction across existing lines, the purpose of rapid construction is achieved by quantitatively producing prefabricated beams and slabs, and directly transporting them to the construction site for hoisting and splicing. The construction process of the key joints of the prefabricated structure is crucial to the life of the overall beam. Most of the wet joints in this part are transverse wet joints. At present, most bridge wet joint construction still uses traditional steel molds, wooden molds or bamboo glue molds for construction. After pouring, the molds need to be removed. There are problems such as difficulty in removing the mold materials, more processes, longer construction periods, and high removal costs. Due to the short application window period, especially in areas with dense railway networks or busy lines, the difficulty of applying for the window period increases exponentially, and due to various external factors, the application window period and fees need to be increased, which greatly increases the construction cost.

[0042] Combine the following Figures 1 to 9 , describing an embodiment of the present invention.

[0043] According to an embodiment of the present invention, on the one hand, a template assembly for crossing a wet joint of an existing bridge is provided, which is arranged between two adjacent beams 1 arranged parallel and spaced apart in a first direction, and the two ends of the beam 1 in the first direction are respectively extended to form wing plates 101. The template assembly for crossing a wet joint of an existing bridge includes:

[0044] A first connecting member 5 is fixedly connected between two adjacent wing plates 101;

[0045] A bottom template 2, a first end of which is fixedly connected to the bottom of one of the two adjacent wing panels 101, and a second end of which is fixedly connected to the bottom of the other wing panel 101;

[0046] A top template 3, a first end of which is fixedly connected to the top of one of the two adjacent wing panels 101, and a second end of which is fixedly connected to the top of the other wing panel 101;

[0047] The bottom formwork 2, the top formwork 3 and the side walls of the two adjacent wing panels 101 are combined to form a wet joint post-cast strip 4. The first connecting member 5 is located in the wet joint post-cast strip 4 and is fixedly connected to the bottom formwork 2 and the top formwork 3. The wet joint post-cast strip 4 is suitable for being filled with concrete. The bottom formwork 2, the top formwork 3 and the concrete are together constructed into a wet joint structure.

[0048] The formwork assembly provided in this embodiment is used for the wet joint of the bridge across the existing line. The first connecting member 5, the bottom formwork 2 and the top formwork 3 are fixedly connected between two adjacent wing plates 101, concrete is poured into the wet joint post-cast strip 4, and the bottom formwork 2 and the top formwork 3 are constructed together with the concrete to form a wet joint structure, so there is no need to remove the formwork, which is beneficial to reducing the process, shortening the construction period and reducing the construction cost.

[0049] Specifically, the beam 1 includes a box beam and a T-beam. The first direction is the width direction of the existing line bridge. Multiple prefabricated beams 1 are arranged in parallel and at intervals along the first direction. The second direction is the length direction of the existing line bridge. The beam 1 extends along the second direction. The two ends of the first connecting member 5 are respectively fixedly connected to the two adjacent wing plates 101 to form a fixed connection between the two adjacent beams 1. The bottom template 2 is located below the first connecting member 5 and is directly or indirectly fixedly connected to the two adjacent wing plates 101 and the first connecting member 5 at the same time. The top template 3 is located above the first connecting member 5 and is directly or indirectly fixedly connected to the two adjacent wing plates 101 and the first connecting member 5 at the same time.

[0050] As a preferred implementation form, the planes where the bottom formwork 2 and the top formwork 3 are located are parallel to the horizontal direction, wherein the bottom formwork 2 and the top formwork 3 are steel formworks. Concrete is poured into the wet joint post-casting strip 4 to directly cast the bottom formwork 2, the top formwork 3 and the first connecting member 5 with the concrete as a whole, thereby forming a wet joint structure together, which is conducive to improving the degree of integration of the formwork assembly used for the wet joint of the bridge across the existing line; the bottom formwork 2 and the top formwork 3 become components of the overall structure, and bear the load together with the concrete, which is conducive to improving the overall strength of the bridge across the existing line and ensuring the transportation safety of the existing line; after the concrete pouring is completed, there is no need to remove the formwork, which can avoid the cost of removing the formwork, and the construction is simple, which is conducive to reducing the construction process, improving the construction efficiency, shortening the construction period, thereby completing the construction within a shorter skylight window, avoiding increasing the time limit and cost of applying for the skylight window, and helping to reduce the construction cost.

[0051] In some embodiments, in combination Figures 1 to 9 As shown, a wing plate reinforcement 10 is provided on the side of the wing plate 101 facing the other wing plate 101 adjacent thereto, and the first connecting member 5 is fixedly connected to the two wing plate reinforcements 10 at the same time.

[0052] The formwork assembly for a wet joint of a bridge over an existing line provided in this embodiment is beneficial to enhancing the connection reliability of two adjacent beams 1 by fixing the first connecting member 5 to the two wing plate steel bars 10 at the same time.

[0053] Specifically, when manufacturing the beam 1, a part of the wing plate steel bar 10 is embedded in the beam 1, and the remaining area is exposed on the beam 1. After the multiple beams 1 are hoisted, the exposed part of the wing plate steel bar 10 is located inside the wet joint post-casting strip 4. Along the second direction, there are multiple wing plate steel bars 10 arranged at intervals, and the number of first connecting members 5 is adapted to the number of wing plate steel bars 10. The position of the wing plate steel bar 10 on one beam 1 corresponds to the position of the wing plate steel bar 10 on another adjacent beam 1. One end of the first connecting member 5 is fixedly connected to the wing plate steel bar 1 on one beam 1, and the other end is fixedly connected to the wing plate steel bar 1 on another beam 1. The fixed connection form includes binding and welding. Along the second direction, the projection shape of the exposed part of the wing plate steel bar 10 includes a half waist type, a square, and a triangle. As a feasible implementation form, the spacing between two adjacent wing plate steel bars 10 on the same beam 1 is 200 mm.

[0054] In some embodiments, in combination Figures 1 to 9 As shown, the formwork assembly for the wet joint of the bridge across the existing line also includes: a second connecting member 6, the second connecting member 6 extends along the third direction, the second connecting member 6 is connected between the bottom formwork 2 and the top formwork 3, and the second connecting member 6 and the first connecting member 5 are at least partially overlapped and connected in the overlapping area.

[0055] The formwork assembly provided in this embodiment for the wet joint of the bridge across the existing line is fixedly connected to the bottom formwork 2 and the top formwork 3 by the second connecting member 6, and is also fixedly connected to the first connecting member 5, thereby improving the overall stability of the connection between the bottom formwork 2 and the top formwork 3 and the two wing panels 101.

[0056] Specifically, the third direction is the height direction of the beam 1, the second connector 6 is extended along the third direction, the top of the second connector 6 is fixedly connected to the top formwork 3, the bottom of the second connector 6 is fixedly connected to the bottom formwork 2, and along the second direction, a portion of the structure of the area between the top and the bottom of the second connector 6 crosses and overlaps with the first connector 5 and is fixedly connected, so that the top formwork 3, the bottom formwork 2, the first connector 5, the second connector 6 and the flange steel bar 10 are connected to form a whole, which is beneficial to improve the connection reliability of the wet joint after pouring concrete into the wet joint post-casting strip 4. The number of the second connector 6 includes multiple, and each first connector 5 is fixedly connected to at least one second connector 6.

[0057] In some embodiments, in combination Figures 1 to 9 As shown, the first connecting member 5 includes waist-shaped steel bars; the second connecting member 6 includes U-shaped steel bars.

[0058] Specifically, the first connecting member 5 includes waist-shaped steel bars, steel plates, angle steels, I-shaped steels, etc.; the second connecting member 6 includes U-shaped steel bars, waist-shaped steel bars, steel plates, angle steels, I-shaped steels, etc.

[0059] As a feasible implementation form, the first connecting member 5 adopts waist-shaped steel bars. Along the second direction, multiple first connecting members 5 are fixedly connected to multiple wing plate steel bars 10 in sequence, in the order of one waist-shaped steel bar being tied to the wing plate steel bar 10, and one waist-shaped steel bar being single-sidedly welded to the wing plate steel bar 10.

[0060] In some embodiments, in combination Figures 1 to 9 As shown, the beam 1 extends along the second direction, and multiple bottom formworks 2 are arranged along the second direction; the formwork assembly for crossing the wet joint of the existing bridge also includes a pad 7, which is arranged at the junction of two adjacent bottom formworks 2, and the pad 7 is suitable for covering the gap between the two adjacent bottom formworks 2.

[0061] The formwork assembly for the wet joint of a bridge over an existing line provided in this embodiment is provided with a pad 7 at the joint of two adjacent bottom formworks 2 so as to cover the gap between the two bottom formworks 2, thereby preventing the concrete from leaking to the bottom through the gap between the two bottom formworks 2 when pouring concrete into the wet joint post-cast zone 4, thereby preventing the normal operation of the existing line below from being affected.

[0062] Specifically, the pad 7 extends along the second direction and is attached to and fixedly connected to the upper end surface of the bottom formwork 2. The number of pads 7 includes multiple pads, and at least one pad 7 is arranged between each two adjacent bottom formworks 2, so that it covers the joint between the two adjacent bottom formworks 2, thereby preventing the leakage of mortar at the joint between the two adjacent bottom formworks 2 during the process of pouring concrete into the wet joint post-casting strip 4. Further, structural adhesive is applied to the joint between the pad 7 and the upper end surface of the bottom formwork 2 to seal the gap between the pad 7 and the bottom formwork 2. Preferably, the plane where the bottom formwork 2 is located is parallel to the horizontal plane, and the plane where the pad 7 is located is parallel to the horizontal plane.

[0063] In some embodiments, in combination Figures 1 to 9 As shown, a fixing plate 11 is fixedly connected to the bottom of the wing plate 101 , and along the gravity direction, the projection of the fixing plate 11 partially overlaps with the projection of the wet joint post-casting strip 4 , so as to be suitable for fixing the fixing plate 11 to the bottom formwork 2 .

[0064] The formwork assembly provided in this embodiment for the wet joint of the bridge across the existing line is fixedly connected to the fixing plate 11 through the bottom of the wing plate 101, and the bottom formwork 2 is supported and fixed by the fixing plate 11, which is conducive to improving the convenience of forming a fixed connection between the bottom formwork 2 and the wing plate 101.

[0065] Specifically, when manufacturing the beam 1, as a feasible implementation form, a third connecting member 14 is embedded in the wing plate 101, and a part of the third connecting member 14 is exposed on the lower end surface of the wing plate 101, so that the fixing plate 11 is fixedly connected to the exposed part of the third connecting member 14, thereby being fixedly arranged on the lower end surface of the wing plate 101; as an additional implementation form, the third connecting member 14 is fixedly connected to the fixing plate 11, and is embedded in the beam 1 at the same time, and a part of the fixing plate 11 is exposed on the bottom of the side wall of the wing plate 101 facing the wet joint post-casting strip 4, so that the fixing plate 11 is fixedly connected to the bottom of the wing plate 101. The third connecting member 14 includes U-shaped steel bars, steel plates, angle steels, I-shaped steels, etc. For example, the third connecting member 14 is a U-shaped steel bar and the fixing plate 11 is a steel plate, and the steel plate is welded to the bottom of the U-shaped steel bar.

[0066] Preferably, the plane where the fixed plate 11 is located is parallel to the horizontal plane, and a partial area is located below the wet joint post-casting strip 4, and the bottom formwork 2 is abutted against and fixedly connected to the upper end surface of the fixed plate 11 located below the wet joint post-casting strip 4, so that the fixed plate 11 supports and fixes the bottom formwork 2.

[0067] As a feasible implementation form, along the second direction, the wet joint length between two adjacent beams 1 is 35m, including 5 bottom templates 2, top templates 3 and bottom templates 2 are made of Q235 thin steel plates with a thickness of 5mm, and the size of the bottom template 2 is 7m*20cm*5mm, and the size of the top template 3 is 7m*46cm*5mm; the second connecting member 6 uses U-shaped steel bars, and the opening of the U-shaped steel bars is set upward, and the U-shaped steel bars are double-sidedly welded to the top template 3 and the bottom template 2, and the weld is full. The pad 7 uses a 46cm, 10cm wide, 5mm thick steel plate, and is welded and fixed to the bottom template 2.

[0068] In some embodiments, in combination Figures 1 to 9 As shown, the beam 1 also includes a web 102 extending along the second direction, the web 102 is located below the wing 101, and there is a spacing between the webs 102 of two adjacent beams 1. Along the second direction, the formwork assembly for crossing the wet joint of the existing line bridge also includes at least one group of side formworks 8, each group of side formworks 8 includes two spaced apart, the side formworks 8 are located below the wing 101, and are simultaneously abutted against the lower end surface of the wing 101 and the side surface of the web 102; the formwork assembly for crossing the wet joint of the existing line bridge also includes a bottom formwork 9, the bottom formwork 9 is simultaneously fixedly connected to the bottom of two adjacent webs 102, the bottom formwork 9 and the side formworks 8 are enclosed between the two adjacent beams 1 to form a transverse beam post-cast strip, and the transverse beam post-cast strip is suitable for being filled with concrete.

[0069] The formwork assembly provided in this embodiment for the wet joint of the bridge over the existing line pours concrete into the post-cast strip of the diaphragm to form a diaphragm connecting two adjacent beams 1, thereby improving the overall stability of the connection between the two adjacent beams 1.

[0070] Preferably, the plane where the side formwork 8 is located is perpendicular to the second direction, and along the second direction, the projection shape of the side formwork 8 is adapted to the shape of the enclosed area of ​​the webs 102 and the wing plates 101 of the two adjacent beams 1, that is, the upper end surface of the side formwork 8 is in contact with the lower end surface of the wing plates 101, and the two end surfaces of the side formwork 8 along the first direction are respectively in contact with the side walls of the two webs 102. The bottom formwork 9 is arranged in the horizontal direction and is correspondingly arranged below the two side formworks 8 of the same group, and blocks the bottom opening between the two side formworks 8 of the same group, thereby forming a diaphragm beam post-casting strip for casting and constructing a diaphragm beam. A gap is reserved between the fixed plates 11 of the two adjacent beams 1, and concrete is cast into the diaphragm beam post-casting strip through the gap to form a diaphragm beam. The side formwork 8 and the bottom formwork 9 are constructed as a permanent formwork for the diaphragm beam. By setting up cross beams to enhance the connection stability of wet joints of existing bridges and ensure the lateral stiffness of bridges across existing lines, as a feasible implementation form, cross beams are set at the ends of beams 1 or at the support sections in continuous beams, thereby connecting each beam 1 to form a whole, which is beneficial to improving the integrity of bridges across existing lines and enabling each beam 1 to work better together under load.

[0071] In some embodiments, in combination Figures 1 to 9 As shown, a first fixing member 12 is disposed on the lower end surface of the wing plate 101 , and the first fixing member 12 is fixedly connected to the side formwork 8 to support and fix the side formwork 8 .

[0072] Preferably, the first fixing member 12 extends along the gravity direction, the side wall of the first fixing member 12 is fixedly connected to the main plane of the side template 8, and the first fixing member 12 includes angle steel, steel plate, I-beam, box steel and the like.

[0073] In some embodiments, in combination Figures 1 to 9 As shown, a second fixing member 13 is arranged at an angle at the bottom of the first fixing member 12 , and the second fixing member 13 is fixedly connected to the bottom template 9 to support and fix the bottom template 9 .

[0074] Preferably, the second fixing member 13 extends in the horizontal direction, and the bottom template 9 is fixedly connected to the upper end surface of the second fixing member 13, so that the second fixing member 13 supports and fixes the bottom template 9. The second fixing member 13 includes angle steel, steel plate, I-beam, box steel, etc. Further, at least one U-shaped steel bar is fixedly connected between the bottom of the first fixing member 12 and the second fixing member 13, and a part of the U-shaped steel bar is fixedly connected to the first fixing member 12, and another part of the U-shaped steel bar is fixedly connected to the second fixing member 13, thereby enhancing the connection reliability of the first fixing member 12 and the second fixing member 13. As a feasible implementation form, the first fixing member 12 adopts an angle steel with a specification of L110*70*8mm, and the second fixing member 13 adopts a steel plate, and the steel plate is welded and fixed to the bottom of the angle steel.

[0075] According to an embodiment of the present invention, on the other hand, a construction method is also provided, using the formwork assembly for wet joints of bridges across existing lines as described above, the construction method comprising the following steps: pre-embedding a first fixing member 12 when making a beam 1; fixing a fixing plate 11 to the bottom of a wing plate 101; fixing a second fixing member 13 to the bottom of the first fixing member 12; fixing a side formwork 8 to the first fixing member 12, and fixing a bottom formwork 9 to the second fixing member 13 to enclose and form a transverse beam post-casting strip; pouring concrete into the transverse beam post-casting strip; laying a plurality of bottom formworks 2 along the extension direction of the wing plate 101, and fixing them to the fixing plate 11; fixing a connecting pad 7 at the joint between two adjacent bottom formworks 2; fixing a first connecting member 5 to the wing plate steel bars 10 of two adjacent beams 1; after fixing a second connecting member 6 to the top formwork 3, laying a plurality of top formworks 3 in sequence, and fixing the second connecting member 6 to the first connecting member 5 and the bottom formwork 2; pouring concrete into the wet joint post-casting strip 4.

[0076] Specifically, when casting and manufacturing the beam 1, the first fixing member 12 and the third connecting member 14 are embedded, and the fixing plate 11 is fixedly connected to the exposed part of the third connecting member 14, or the fixing plate 11 is pre-connected with the third connecting member 14 and then embedded at the same time, so as to form a fixed connection with the wing plate 101. A fence 17 is embedded on the beam 1 at the location corresponding to the diaphragm affected by the existing line. The fence 17 is constructed by welding steel pipes and steel bars to form a frame structure (it should be noted that the fence is a conventional technical means in this field, so it will not be described in detail); after the beam 1 is erected, within the skylight period, the hanging basket 15 is hung between two adjacent beams 1 through the steel pipe 16 corresponding to the position of the diaphragm. As a feasible implementation form, the hanging basket 15 is welded with Φ16 steel bars, and a hanging ring made of Φ20 steel bars is welded on the upper end of the hanging basket 15. The hanging ring is fixed at Φ70mm between the top surfaces of the two adjacent beams 1, and the wall On a transverse steel pipe with a thickness of 6.5 mm (it should be noted that the hanging basket is a conventional technical means in this field, so it will not be described in detail), a person manually enters the hanging basket 15 to fix the second fixing member 13 to the bottom of the first fixing member 12, and fixes the side formwork 8 and the bottom formwork 9 to the first fixing member 12 and the second fixing member 13 respectively, thereby forming a diaphragm formwork; the hanging basket 15 and the steel pipe 16 are removed, and concrete is poured into the diaphragm beam post-cast strip at the diaphragm beam formwork through the gap between the two fixing plates 11, so that the concrete in the diaphragm beam post-cast strip and the diaphragm beam formwork together constitute a diaphragm structure.

[0077] A plurality of bottom formworks 2 are sequentially spliced ​​and laid on a fixed plate 11, and fixedly connected to the fixed plate 11; a pad 7 is fixedly connected to the joint between two adjacent bottom formworks 2; a first connector 5 is fixedly connected to the wing plate reinforcement 10 of two adjacent beams 1; after the second connector 6 is fixedly connected to the top formwork 3, the top formwork 3 is laid. When laying the top formwork 3, the second connector 6 is located in the wet joint post-casting strip 4, and is fixedly connected to the first connector 5 and the bottom formwork 2. Since the length of a single top formwork 3 in the second direction is about 40 cm, the fixed connection between the second connector 6 in the wet joint post-casting strip 4 and the first connector 5 and the bottom formwork 2 is not affected. Concrete is poured into the wet joint post-casting strip 4, so that the bottom formwork 2 and the top formwork 3 and the concrete are jointly constructed into a wet joint structure. This construction method is convenient for construction, eliminates the complicated demoulding process, saves the time of template removal, and ensures the normal operation of the existing line; it can be applied to the construction of various bridges across the existing line, with high efficiency, and can quickly complete the construction of diaphragms and wet joints across the existing line, which is conducive to speeding up the progress of the project. During the construction process, the thickness of the diaphragm and wet joints must meet the design requirements, and the thickness of the concrete protective layer must meet the requirements. All exposed steel plates are treated with hot-dip galvanizing for corrosion protection.

[0078] Obviously, the above embodiments are only examples for clear explanation, and are not intended to limit the implementation methods. Although the embodiments of the present invention are described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations all fall within the scope defined by the present invention.

Claims

1. A formwork assembly for wet joints of bridges over existing lines, characterized in that: It is arranged between two adjacent beams (1) which are parallel and spaced apart in a first direction, and the two ends of the beams (1) in the first direction are respectively extended to form wing plates (101). The formwork assembly for crossing the wet joint of an existing bridge comprises: A first connecting member (5) is fixedly connected between two adjacent wing plates (101); A bottom template (2), a first end of which is fixedly connected to the bottom of one of the two adjacent wing panels (101), and a second end of which is fixedly connected to the bottom of the other wing panel (101); A top template (3), a first end of which is fixedly connected to the top of one of the two adjacent wing panels (101), and a second end of which is fixedly connected to the top of the other wing panel (101); The bottom formwork (2), the top formwork (3) and the side walls of the two adjacent wing plates (101) are combined to form a wet joint post-casting strip (4); the first connecting member (5) is located in the wet joint post-casting strip (4) and is fixedly connected to the bottom formwork (2) and the top formwork (3); the wet joint post-casting strip (4) is suitable for being filled with concrete; the bottom formwork (2), the top formwork (3) and the concrete are jointly constructed into a wet joint structure.

2. The formwork assembly for wet joints of bridges over existing lines according to claim 1, characterized in that: A wing plate steel bar (10) is provided on the side of the wing plate (101) facing another wing plate (101) adjacent thereto, and the first connecting member (5) is fixedly connected to the two wing plate steel bars (10) at the same time.

3. The formwork assembly for wet joints of bridges over existing lines according to claim 2, characterized in that: The formwork assembly for crossing a wet joint of an existing bridge also includes: a second connecting member (6), the second connecting member (6) extending along a third direction, the second connecting member (6) connected between the bottom formwork (2) and the top formwork (3), and the second connecting member (6) at least partially cross-overlaps with the first connecting member (5) and is connected in the cross-overlapping area.

4. The formwork assembly for wet joints of bridges over existing lines according to claim 3, characterized in that: The first connecting member (5) comprises a waist-shaped steel bar; the second connecting member (6) comprises a U-shaped steel bar.

5. The formwork assembly for wet joints of bridges over existing lines according to claim 1, characterized in that: The beam (1) extends along a second direction, and a plurality of bottom templates (2) are arranged along the second direction; the template assembly for wet joints of bridges over existing lines also includes a pad (7), the pad (7) is arranged at the junction of two adjacent bottom templates (2), and the pad (7) is suitable for covering the gap between two adjacent bottom templates (2).

6. The formwork assembly for wet joints of bridges over existing lines according to claim 1, characterized in that: A fixing plate (11) is fixedly connected to the bottom of the wing plate (101), and along the gravity direction, the projection of the fixing plate (11) partially overlaps with the projection of the wet joint post-casting strip (4), so as to be suitable for fixing the fixing plate (11) to the bottom formwork (2).

7. The formwork assembly for wet joints of bridges over existing lines according to claim 1, characterized in that: The beam (1) further comprises a web (102) extending in a second direction, the web (102) being located below the wing (101), and a spacing being provided between the webs (102) of two adjacent beams (1). Along the second direction, the formwork assembly for crossing the wet joint of an existing bridge further comprises at least one set of side formworks (8), each set of the side formworks (8) comprising two spaced apart side formworks, the side formworks (8) being located below the wing (101) and simultaneously abutting against the lower end surface of the wing (101) and the side surface of the web (102); the formwork assembly for crossing the wet joint of an existing bridge further comprises a bottom formwork (9), the bottom formwork (9) being fixedly connected to the bottoms of two adjacent webs (102), the bottom formwork (9) and the side formworks (8) enclosing between the two adjacent beams (1) to form a diaphragm post-casting strip, the diaphragm post-casting strip being suitable for being filled with concrete.

8. The formwork assembly for wet joints of bridges over existing lines according to claim 7, characterized in that: A first fixing member (12) is provided on the lower end surface of the wing plate (101), and the first fixing member (12) is fixedly connected to the side formwork (8) to support and fix the side formwork (8).

9. The formwork assembly for wet joints of bridges over existing lines according to claim 8, characterized in that: A second fixing member (13) is arranged at an angle at the bottom of the first fixing member (12); the second fixing member (13) is fixedly connected to the bottom template (9) to support and fix the bottom template (9).

10. A construction method for a formwork assembly for a wet joint of an existing bridge, characterized in that: The formwork assembly for wet joints of bridges over existing lines as described in any one of claims 1 to 9 above is used, and the construction method includes the following steps: pre-embedding a first fixing member (12) when manufacturing a beam (1); fixing a fixing plate (11) to the bottom of a wing plate (101); fixing a second fixing member (13) to the bottom of the first fixing member (12); fixing a side formwork (8) to the first fixing member (12), and fixing a bottom formwork (9) to the second fixing member (13) to enclose and form a post-cast strip of a transverse beam; and extending the post-cast strip of the transverse beam to the transverse beam. Concrete is poured into the post-cast strip; a plurality of bottom formworks (2) are laid along the extension direction of the wing plate (101), and are fixedly connected to the fixing plate (11); a connecting pad (7) is fixedly connected at the joint between two adjacent bottom formworks (2); a first connecting piece (5) is fixedly connected to the wing plate steel bars (10) of two adjacent beams (1); after a second connecting piece (6) is fixedly connected to the top formwork (3), a plurality of top formworks (3) are laid in sequence, and the second connecting piece (6) is fixedly connected to the first connecting piece (5) and the bottom formwork (2); Concrete is poured into the wet joint post-casting strip (4).

Citation Information

Cited By

  • Beam piece formwork-free seamless construction method based on prefabricated bridge

    CN119913832A

  • Formwork-free seamless beam piece structure for post-pouring of top plate

    CN223837887U