Distribution cable line comprehensive state detection training system and training method

By designing a comprehensive status detection training system for distribution cable lines, simulating the complex structure and noise environment of distribution cable lines, injecting test signals and monitoring the status, the problem of theorization and imperfection of existing training is solved, and the training effect and effectiveness are improved. Adaptability.

CN118840908AActive Publication Date: 2024-10-25GUANGZHOU ZHIFENG ELECTRIC TECH CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411205408.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-10-25
Estimated Expiration
2044-08-30

AI Technical Summary

Technical Problem

The existing partial discharge detection and fault location training for distribution cable line ring main unit systems has a disconnect between theoretical content and practice, an imperfect training platform, difficulty in evaluating effects, and a lack of pertinence, resulting in poor training results.

Method used

A comprehensive status detection and training system for distribution cable lines is designed, including substation end, ring switch device, overhead line device and background operation cabinet. By simulating the three-phase cable terminal structure of distribution cable lines, multi-circuit cable lines and ring Network structure, inject test signals and monitor status, analyze frequency characteristics and attenuation characteristics, and conduct training combined with fault simulation triggering.

Benefits of technology

It effectively improves students' technical level of partial discharge testing and fault location, enhances the comprehensiveness and effectiveness of training, simulates complex noise environments, and adapts to the backgrounds and needs of different students.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118840908A_ABST
    Figure CN118840908A_ABST
Patent Text Reader

Abstract

The invention discloses a power distribution cable line comprehensive state detection training system and method, and the system comprises a power transformation end, a first annular switch device, a first overhead line device, a second annular switch device, a third annular switch device, a fourth annular switch device, a second overhead line device, and a background operation cabinet. Respectively injecting test signals to a plurality of preset signal injection positions of the distribution cable line through the background operation cabinet; state monitoring signals of a plurality of preset sensor installation positions of the distribution cable line are received through a background operation cabinet; and according to the test signal, the signal injection position, the state monitoring signal and the sensor installation position, analyzing the frequency characteristic, the propagation characteristic and the attenuation characteristic of the test signal and the detection sensitivity of different sensor installation positions. According to the invention, the comprehensiveness and training effect of partial discharge detection and fault positioning training of the distribution cable line ring main unit system are improved, and the method can be widely applied to the technical field of cable detection.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of cable detection, and in particular to a distribution cable line comprehensive status detection training system and training method. Background Art

[0002] With the continuous development of the power system, the reliability and safety of distribution cable lines are becoming increasingly important. As a reliable means to ensure the stable operation of cable lines, partial discharge detection and fault location technology has been widely used in distribution cable lines and ring network cabinet power equipment. However, due to the special structure, operation and laying environment of cable lines and ring network cabinets, the noise interference is relatively large, and partial discharge detection and fault location are difficult. It is urgent to improve and popularize partial discharge detection and fault location skills. However, the skill training at the live site is subject to a variety of safety and operating conditions. For example, the safety space is small and the environment is complex, and the operability is very low. In addition, the probability of partial discharge and failure in cable lines is extremely low, and the detection technology is difficult to popularize and master. It is difficult to effectively improve the level of partial discharge testing and fault location technology by relying solely on the experience accumulation of on-site live detection and fault location.

[0003] The existing technologies for partial discharge detection and fault location training of distribution cable line ring main unit systems have the following problems:

[0004] 1) The content is theoretical and out of touch with the actual conditions on site: The knowledge and experience of partial discharge detection and fault location are explained only through theory. The theoretical content is too abstract and lacks the complex operating environment and practical operation experience of the real site. The trainees have insufficient understanding of the complex situations and interference factors in actual work.

[0005] 2) The training platform system is not perfect: it is only a simple single-phase cable line, and does not simulate the actual situation of multi-circuit branches in the ring network cabinet of the 10kV distribution cable line, nor does it simulate the actual overhead line structure. Trainees cannot fully understand and master the operating characteristics and structure of the entire distribution power system.

[0006] 3) The effect is difficult to evaluate: there is a lack of cable line models close to the site, a lack of conditions that can simulate complex noise on site, a lack of a platform system for trainees to operate, and no means to effectively evaluate the trainees' actual operating ability and problem-solving ability. It is impossible to determine whether the trainees have truly mastered the partial discharge detection and fault location technology, which affects the training effect.

[0007] 4) Lack of specificity: Existing training methods are often fixed and stereotyped. Trainees with different backgrounds, experiences and needs have differences in the learning process, but the existing training model fails to fully consider these factors. Some trainees may not benefit fully because the training content is too basic or complicated, resulting in uneven training results and wasting valuable training resources.

[0008] The above problems need to be solved urgently. Summary of the invention

[0009] In order to solve the above technical problems, the purpose of the present invention is to provide a distribution cable line comprehensive status detection training system and training method, which improves the comprehensiveness and training effect of partial discharge detection and fault location training of distribution cable line ring network cabinet system.

[0010] The first technical solution adopted by the present invention is:

[0011] A distribution cable line comprehensive status detection training system includes a transformer terminal, a first ring switch device, a first overhead line device, a second ring switch device, a third ring switch device, a fourth ring switch device, a second overhead line device and a backstage operation cabinet, wherein:

[0012] The transformer terminal is electrically connected to the first ring switch device through a power line, the first ring switch device, the first overhead line device, the second ring switch device, the third ring switch device, the fourth ring switch device and the second overhead line device are connected in sequence through a coaxial cable, and the first ring switch device is connected to the fourth ring switch device through a coaxial cable to form a distribution cable line;

[0013] The first ring switch device, the second ring switch device, the third ring switch device and the fourth ring switch device are all used to simulate the switch cabinet in the distribution cable line, the first overhead line device and the second overhead line device are both used to simulate the overhead line in the distribution cable line, the substation is used to adjust and control the voltage input to the distribution cable line, and the background operation cabinet is used to inject test signals into the distribution cable line and perform status detection.

[0014] Further as an optional embodiment, the first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device all include a shell, a load, a busbar, an incoming terminal, an outgoing terminal, an incoming cable line, an outgoing cable line, a signal injection port and a ground bus, the load, the busbar, the incoming terminal and the outgoing terminal are all arranged in the shell, the incoming cable line is connected to the busbar through the incoming terminal, the outgoing cable line is connected to the busbar through the outgoing terminal, the load is connected to the busbar, the signal injection port is arranged on the incoming cable line and / or the outgoing cable line, and the armor of the incoming terminal and the outgoing terminal is grounded through the ground bus.

[0015] Further as an optional implementation, the first overhead line device and the second overhead line device both include an overhead line, a wire drum, a support column and a chassis, the wire drum is fixedly connected to the chassis via the support column, and the overhead line is arranged and wound on the wire drum.

[0016] Further as an optional embodiment, the background operation cabinet includes a cabinet body, a display screen, an operating table, a signal generator, a line monitoring device and a test computer. The display screen, the operating table, the signal generator, the line monitoring device and the test computer are all arranged on the cabinet body. The display screen, the signal generator and the line monitoring device are all communicatively connected to the test computer. The test computer is used to control the signal generator to inject a test signal into at least one of the incoming terminal, the outgoing terminal and the signal injection port, and to monitor the status of the distribution cable line through the line monitoring device.

[0017] As a further optional implementation, one end of the signal generator is connected to the lead-out port of the coaxial cable, and the other end of the signal generator is grounded;

[0018] or,

[0019] One end of the signal generator is connected to the cable core conductor of the incoming terminal and / or the outgoing terminal, and the other end of the signal generator is grounded;

[0020] or,

[0021] The signal generator is connected to the signal injection port.

[0022] Further as an optional implementation, the distribution cable line comprehensive status detection training system also includes a status monitoring sensor, the status monitoring sensor includes a fault current sensor, a current sensor and a partial discharge sensor, the status monitoring sensor is communicatively connected to the line monitoring device, the status monitoring sensor is arranged on the cable body of the incoming terminal / the outgoing terminal, or, the status monitoring sensor is arranged on the main insulation of the branch cable of the incoming terminal / the outgoing terminal, or, the status monitoring sensor is arranged on the ground bus, or, the status monitoring sensor is arranged on the shell.

[0023] The second technical solution adopted by the present invention is:

[0024] A distribution cable line comprehensive state detection training method, which is implemented by the above-mentioned distribution cable line comprehensive state detection training system, comprises the following steps:

[0025] Injecting test signals into a plurality of preset signal injection positions of the distribution cable line respectively through the background operation cabinet;

[0026] Receiving status monitoring signals of a plurality of preset sensor installation positions of the power distribution cable line through the backstage operation cabinet;

[0027] The frequency characteristics, propagation characteristics, attenuation characteristics of the test signal and the detection sensitivity of different sensor installation positions are analyzed according to the test signal, the signal injection position, the state monitoring signal and the sensor installation position.

[0028] Further as an optional embodiment, the signal injection position includes the incoming terminal, outgoing terminal, incoming cable line and outgoing cable line of the first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device, the sensor installation position includes the incoming terminal, outgoing terminal, ground bus and shell of the first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device, and the test signal includes various types of partial discharge signals and noise signals.

[0029] As an optional implementation, the distribution cable line comprehensive status detection training method further includes the following steps:

[0030] Injecting a first partial discharge signal into the first annular switch device through a signal generator of the background operation cabinet;

[0031] Obtaining partial discharge monitoring signals at corresponding positions through partial discharge sensors arranged on the first annular switch device, the second annular switch device, the third annular switch device, and the fourth annular switch device, and sending the partial discharge monitoring signals to the line monitoring device of the background operation cabinet;

[0032] The partial discharge signal attenuation characteristic is analyzed according to the first partial discharge signal and each of the partial discharge monitoring signals.

[0033] As an optional implementation, the distribution cable line comprehensive status detection training method further includes the following steps:

[0034] By means of fault simulation triggering switch, a ground fault is generated by instant closing and short-circuiting a signal injection port of the first ring switch device, the second ring switch device, the third ring switch device or the fourth ring switch device;

[0035] Acquire current monitoring signals at corresponding positions through current sensors arranged on the first annular switch device, the second annular switch device, the third annular switch device, and the fourth annular switch device, and send the current monitoring signals to the line monitoring device of the background operation cabinet;

[0036] Fault location analysis is performed based on each of the current monitoring signals and the corresponding positions.

[0037] The beneficial effects of the present invention are as follows: the present invention provides a distribution cable line comprehensive state detection training system and method, including a transformer terminal, a first ring switch device, a first overhead line device, a second ring switch device, a third ring switch device, a fourth ring switch device, a second overhead line device and a background operation cabinet, wherein the background operation cabinet is used to respectively inject test signals into a plurality of preset signal injection positions of the distribution cable line, and the background operation cabinet is used to receive the state monitoring signals of a plurality of preset sensor installation positions of the distribution cable line, and the frequency characteristics, propagation characteristics, attenuation characteristics of the test signals and the detection sensitivity of different sensor installation positions are analyzed according to the test signals, the signal injection positions, the state monitoring signals and the sensor installation positions. The distribution cable line comprehensive state detection training system of the present invention can simulate the three-phase cable terminal structure, multi-circuit cable line and ring network structure of the actual distribution cable line, and can also simulate the complex noise environment of the overhead line and the actual site, and the teaching and training through the distribution cable line comprehensive state detection training system can effectively improve the trainees' partial discharge test and fault location technical level, and improve the comprehensiveness and training effect of the partial discharge detection and fault location training of the distribution cable line ring network cabinet system. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 A schematic diagram of the structure of a distribution cable line comprehensive status detection training system provided by an embodiment of the present invention;

[0039] Figure 2 A schematic diagram of the structure of a ring switch device provided in an embodiment of the present invention;

[0040] Figure 3 A schematic structural diagram of an overhead line device provided in an embodiment of the present invention;

[0041] Figure 4 A schematic diagram of the structure of a backstage operation cabinet provided in an embodiment of the present invention;

[0042] Figure 5 A schematic diagram of a direct injection method and an indirect injection method of a test signal provided in an embodiment of the present invention;

[0043] Figure 6 A schematic diagram of direct injection of a test signal into a cable terminal and into a cable body provided by an embodiment of the present invention;

[0044] Figure 7 A schematic diagram of the installation position of the condition monitoring sensor provided in an embodiment of the present invention;

[0045] Figure 8A flow chart of the steps of a distribution cable line comprehensive status detection training method provided by an embodiment of the present invention;

[0046] Fig. 9 A schematic diagram of an implementation scenario of the comprehensive technical training for fault location and partial discharge detection provided by an embodiment of the present invention;

[0047] Fig.10 A schematic diagram of an implementation scenario of the attenuation characteristic detection training of partial discharge signals provided in an embodiment of the present invention;

[0048] Fig.11 A schematic diagram comparing the attenuation characteristics of a test coaxial cable and a high-voltage cable provided in an embodiment of the present invention;

[0049] Fig.12 A schematic diagram of an implementation scenario of partial discharge signal detection training under noise interference provided by an embodiment of the present invention;

[0050] Fig.13 A schematic diagram of an implementation scenario of the fault location training provided in an embodiment of the present invention.

[0051] Reference numerals:

[0052] 1. Substation terminal; 2. First ring switch device; 3. Second ring switch device; 4. Third ring switch device; 5. Fourth ring switch device; 6. First overhead line device; 7. Second overhead line device; 8. Backstage operation cabinet; 9. Power line; 10. Coaxial cable; 21. Shell; 22. Load; 23. Busbar; 24. Incoming line terminal; 25. Outgoing line terminal; 26. Incoming cable line; 27. Outgoing cable line; 28. Signal injection port; 29. ​​Ground bus; 61. Overhead line; 62. Cable tray; 63. Support column; 64. Chassis; 81. Cabinet; 82. Display screen; 83. Operation table; 84. Signal generator; 85. Line monitoring device; 86. Test computer; 111. High-frequency partial discharge sensor; 112. Current sensor; 113. Fault current sensor; 114. Wireless monitoring device; 115. Switch cabinet partial discharge sensor; 116. Space UHF partial discharge sensor; 117. Fault simulation trigger switch; 122. Tablet computer; 231. Status monitoring device installed on the main insulation of the branch cable at the incoming terminal; 232, a status monitoring sensor installed on the main insulation of the branch cable at the outgoing terminal; 233, a status monitoring sensor installed on the terminal grounding wire; 234, a status monitoring sensor installed on the cable body at the outgoing terminal; 235, a status monitoring sensor installed on the cable body at the incoming terminal; 236, a status monitoring sensor installed on the casing of the ring switch device; A1, a signal injection port on the incoming cable line of the first ring switch device; A2 to A4, a signal injection port on the outgoing cable line of the first ring switch device; B1, a signal injection port on the incoming cable line of the second ring switch device; B2 to B4, a signal injection port on the outgoing cable line of the second ring switch device; C1, a signal injection port on the incoming cable line of the third ring switch device; C2 to C4, a signal injection port on the outgoing cable line of the third ring switch device; D1, a signal injection port on the incoming cable line of the fourth ring switch device; D2 to D4, a signal injection port on the outgoing cable line of the fourth ring switch device. DETAILED DESCRIPTION

[0053] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. The step numbers in the following embodiments are only provided for the convenience of explanation and description, and the order between the steps is not limited in any way. The execution order of each step in the embodiment can be adaptively adjusted according to the understanding of those skilled in the art.

[0054] In the description of the present invention, the meaning of "a plurality" is more than two. If there is a description of "a first" or "a second", it is only used to distinguish the technical features, and it cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features. In addition, unless otherwise defined, all technical and scientific terms used in this article have the same meaning as those commonly understood by those skilled in the art. The terms used in this specification are only for describing specific embodiments, not for limiting the present invention.

[0055] Reference Figure 1 The embodiment of the present invention provides a distribution cable line comprehensive status detection training system, including a substation, a first ring switch device, a first overhead line device, a second ring switch device, a third ring switch device, a fourth ring switch device, a second overhead line device and a background operation cabinet, wherein:

[0056] The transformer end is electrically connected to the first ring switch device through a power line, the first ring switch device, the first overhead line device, the second ring switch device, the third ring switch device, the fourth ring switch device and the second overhead line device are sequentially connected through a coaxial cable, and the first ring switch device is connected to the fourth ring switch device through a coaxial cable to form a distribution cable line;

[0057] The first ring switch device, the second ring switch device, the third ring switch device and the fourth ring switch device are all used to simulate the switch cabinet in the distribution cable line, the first overhead line device and the second overhead line device are both used to simulate the overhead line in the distribution cable line, the substation is used to adjust and control the voltage of the input distribution cable line, and the background operation cabinet is used to inject test signals into the distribution cable line and perform status detection.

[0058] Specifically, Figure 1 As shown, the distribution cable line comprehensive state detection training system of the embodiment of the present invention includes a transformer terminal 1, a ring switch device 2, a ring switch device 3, a ring switch device 4, a ring switch device 5, an overhead line device 6, an overhead line device 7, a backstage operation cabinet 8, a power line 9 and a cable line 10. The transformer terminal 1 is electrically connected to the ring switch device 2 through the power line 9, and the ring switch device 2 and the overhead line 6, the overhead line 6 and the ring switch device 3, the ring switch device 3 and the ring switch device 4, the ring switch device 4 and the ring switch device 5, the ring switch device 5 and the overhead line 7, and the ring switch device 5 and the ring switch device 2 are all connected through a test coaxial cable 10 to form a distribution cable line. The transformer terminal 1 adjusts and controls the voltage flowing through the cable line through the transformer equipment, simulates the changing state of the fault signal under different voltages, and can understand the influence of the voltage on the size of the detection signal.

[0059] Reference Figure 2 , further as an optional implementation, the first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device all include a shell, a load, a busbar, an incoming terminal, an outgoing terminal, an incoming cable line, an outgoing cable line, a signal injection port and a ground bus, the load, the busbar, the incoming terminal and the outgoing terminal are all arranged in the shell, the incoming cable line is connected to the busbar through the incoming terminal, the outgoing cable line is connected to the busbar through the outgoing terminal, the load is connected to the busbar, the signal injection port is arranged on the incoming cable line and / or the outgoing cable line, and the armor of the incoming terminal and the outgoing terminal is grounded through the ground bus.

[0060] Specifically, the ring switch devices 2, 3, 4, 5 are constructed as follows: Figure 2 As shown, the ring switch devices 2, 3, 4, and 5 are composed of a housing 21, a load 22, a busbar 23, an incoming terminal 24, an outgoing terminal 25, an incoming cable line 26, an outgoing cable line 27, a signal injection port BNC head 28 for simulating partial discharge, noise or grounding fault, and a grounding bus 29. The ring switch devices 2, 3, 4, and 5 are mainly used to simulate the switch cabinet structure in the distribution cable line.

[0061] The load 22 can be replaced with loads of different sizes to simulate the changing state of the fault signal under different currents and understand the influence of the current on the size of the detection signal.

[0062] The incoming terminal 24 and the outgoing terminal 25 are connected to the busbar 23 using a 10kV three-core cable, which is the same as the terminal structure of the actual distribution cable line.

[0063] The incoming cable line 26 and the outgoing cable line 27 are both test coaxial cables. The lengths of the incoming cable line 26 and the outgoing cable line 27 are adjustable from tens of meters to hundreds of meters and are hidden in the ring network cabinet. Several signal injection ports BNC heads 28 simulating partial discharge, noise or ground fault can be set on the incoming cable line 26 and the outgoing cable line 27. Through the signal injection ports 28 simulating partial discharge, noise or ground fault, simulated partial discharge or noise can be injected into the cable line, or a ground fault can be triggered.

[0064] Reference Figure 3 As an optional implementation, the first overhead line device and the second overhead line device both include an overhead line, a wire drum, a support column and a chassis. The wire drum is fixedly connected to the chassis through the support column, and the overhead line is arranged and wound on the wire drum.

[0065] Specifically, the overhead line in the actual cable line is a straight line, and the traveling wave speed of the overhead line is about 300m / us. However, for the training system, the straight line of the overhead line occupies a large space and is not suitable for installation and training. Therefore, it is necessary to shorten the distance of the overhead line in a limited space to ensure that the traveling wave speed of the overhead line model is similar to the traveling wave speed of the overhead line in the actual line, so as to simulate the real distribution cable line situation to the greatest extent. The overhead line device in the embodiment of the present invention adopts a unique and innovative design, such as Figure 3 As shown, the overall structure consists of an overhead line 61, a wire drum 62, a support column 63, and a chassis 64. The overhead line 61 is wound around the outer edge of the wire drum 62 in a 60° triangular convoluted winding manner. The height between the wire drums is 10 cm. The number of wire drums 62 is selected appropriately according to the length of the overhead line 61. This wiring method effectively reduces the wiring space and does not affect the transmission characteristics of the signal. The test results show that the overhead line wave speed is 294m / us~297m / us, which is close to the overhead line wave speed of the actual line.

[0066] Reference Figure 4 As an optional implementation, the background operation cabinet includes a cabinet body, a display screen, an operation table, a signal generator, a line monitoring device and a test computer. The display screen, the operation table, the signal generator, the line monitoring device and the test computer are all arranged on the cabinet body. The display screen, the signal generator and the line monitoring device are all communicatively connected with the test computer. The test computer is used to control the signal generator to inject a test signal into at least one of the incoming terminal, the outgoing terminal and the signal injection port, and to monitor the status of the distribution cable line through the line monitoring device.

[0067] Specifically, the backstage operation cabinet 8 is as follows Figure 4 As shown, it is composed of a cabinet 81, a display screen 82, an operation table 83, a partial discharge and noise comprehensive simulation signal generator 84, a distribution network partial discharge online monitoring device 85 (i.e., a line monitoring device), and a test computer 86. The backstage operation cabinet 8 is used to transmit test signals and observe monitoring signals.

[0068] As a further optional implementation, one end of the signal generator is connected to the lead-out port of the coaxial cable, and the other end of the signal generator is grounded;

[0069] or,

[0070] One end of the signal generator is connected to the cable core conductor of the incoming terminal and / or the outgoing terminal, and the other end of the signal generator is grounded;

[0071] or,

[0072] The signal generator is connected to the signal injection port.

[0073] Specifically, when detecting faults or partial discharge signals on actual cable lines, the probability of failure is extremely small (about 1 / 1000), and the chance of detecting faults or partial discharge signals is very small, making it difficult to achieve the purpose of training. However, the comprehensive status detection training system for distribution cable lines is not restricted and can achieve the training purpose.

[0074] like Figure 5 The diagram shows a direct injection method and an indirect injection method of the test signal provided by an embodiment of the present invention. The embodiment of the present invention can simulate both direct injection of the signal and indirect injection method. The indirect injection method uses an aluminum foil with a length of 10 cm to wrap two layers on the surface of the cable body. The lead-out port is fastened by a metal ring in the middle of the aluminum foil. One end of the signal generator 84 is connected to the lead-out port, and the other end is connected to the ring device box for grounding, so as to couple the simulated signal into the cable line. In the direct injection method, the signal generator 84 is directly connected to the BNC head of the injection port for simulating partial discharge, noise or grounding fault preset on the test coaxial cable, and the core conductor and metal sleeve of the cable are connected to directly inject the simulated signal into the cable line. The output waveform ratio of the indirect injection method to the direct injection method is 2:1, and the actual discharge amount of the partial discharge point can be calculated and evaluated by the apparent amount of the partial discharge signal measured by the sensor.

[0075] like Figure 6 The schematic diagram of direct injection of the test signal at the cable terminal and the cable body provided in the embodiment of the present invention, wherein the direct injection of the analog signal is further divided into direct injection at the cable terminal and direct injection at the cable body. The direct injection at the cable terminal is that one end of the signal generator 84 is connected to the core conductor of the terminal cable, and the other end is connected to the grounding of the ring device box; the direct injection of the cable body is that the signal generator 84 is directly connected to the BNC head of the injection port simulating partial discharge, noise or grounding fault, and the core conductor and metal sheath of the cable are connected.

[0076] Reference Figure 7 As an optional implementation, the distribution cable line comprehensive status detection training system also includes a status monitoring sensor, the status monitoring sensor includes a fault current sensor, a current sensor and a partial discharge sensor, the status monitoring sensor is communicatively connected to the line monitoring device, the status monitoring sensor is arranged on the cable body of the incoming terminal / outgoing terminal, or, the status monitoring sensor is arranged on the main insulation of the branch cable of the incoming terminal / outgoing terminal, or, the status monitoring sensor is arranged on the ground bus, or, the status monitoring sensor is arranged on the shell.

[0077] Specifically, the installation methods of the fault current sensor and the partial discharge sensor are various. The embodiments of the present invention can simulate the installation form of the sensor on the cable line actually running on site, such as Figure 7As shown, the fault current sensor, current sensor or partial discharge sensor can be installed on the main insulation of the incoming terminal branch cable (231), the main insulation of the outgoing terminal branch cable (232), the terminal grounding wire (233), the outgoing terminal cable body (234), the incoming terminal cable body (235) and the ring switch device housing (236). By installing sensors at different positions, comparative training and experiments on detection sensitivity can be carried out.

[0078] Various forms of partial discharge sensors, current sensors, fault current sensors, etc. can be installed on the incoming and outgoing line terminals and on the grounding wire. This design is in line with the installation methods of various sensors on the actual distribution cable lines in field operation, allowing trainees to learn and master the detection methods of various sensors and the sensitivity of different positions, so that trainees can better understand and master the operating skills and precautions in actual work, and improve the training effect.

[0079] Reference Figure 8 The embodiment of the present invention provides a distribution cable line comprehensive state detection training method, which is implemented by the above-mentioned distribution cable line comprehensive state detection training system, and includes the following steps:

[0080] S101, injecting test signals into a plurality of preset signal injection positions of a distribution cable line through a backstage operation cabinet;

[0081] S102, receiving status monitoring signals of multiple preset sensor installation positions of the distribution cable line through a backstage operation cabinet;

[0082] S103, analyzing the frequency characteristics, propagation characteristics, attenuation characteristics of the test signal and the detection sensitivity of different sensor installation positions according to the test signal, the signal injection position, the status monitoring signal and the sensor installation position.

[0083] Specifically, Fig. 9 The diagram shows the implementation scenario of the comprehensive technical training for fault location and partial discharge detection provided by the embodiment of the present invention. Taking the composition of four ring switch devices and two overhead line devices as an example, it includes a transformer terminal 1, ring switch devices 2, 3, 4, 5, overhead line devices 6, 7. The left end of the ring switch device 2 is connected to the transformer terminal 1, and the right end is connected to the overhead line 6; the left end of the ring switch device 3 is connected to the overhead line 6, and the right end is connected to the ring switch device 4; the left end of the ring switch device 5 is connected to the ring switch device 4, and the right end is connected to the overhead line 7, and is connected to the ring switch device 2 to form a distribution cable line ring network system. 8 is a background operation cabinet, which is used to control the output of partial discharge and noise signals, as well as the processing, display and analysis of detection signals.

[0084] A high-frequency partial discharge sensor 111 (HFCT for short) is installed on the three-phase cable conductor of the incoming terminal in the ring switch devices 2, 3, 4, and 5, a current sensor 112 is installed on the three-phase cable conductor of the outgoing terminal, and a fault current sensor 113 (FPCT for short) is installed on the grounding wire. The sensor detection signal is transmitted to the distribution network line comprehensive online monitoring device 114 (i.e., wireless monitoring device) for signal processing. The processed signal is wirelessly transmitted to the background test computer 86 for analysis and judgment, and the display screen 82 displays the result.

[0085] Switch cabinet partial discharge sensors 115 are installed on the outer walls of the cabinets of the ring switch devices 2, 3, 4, and 5, and are connected to the distribution network partial discharge online monitoring device 85 (i.e., line monitoring device) via LoRa wireless; spatial ultra-high frequency partial discharge sensors 116 are installed next to the background operation cabinet, connected to the distribution network partial discharge online monitoring device 85, and the signal analysis and judgment results are viewed through the test computer 86.

[0086] 117 is a fault simulation trigger switch, which is connected to the port simulating partial discharge, noise or ground fault, and is closed instantaneously to cause a short circuit, thereby forming a ground fault. 84 is a partial discharge and noise comprehensive simulation signal generator, which is connected to the BNC head of the injection port simulating partial discharge, noise or ground fault, and is wirelessly remotely controlled by a tablet computer 122 to simulate partial discharge of the cable line or simulate complex noise conditions of the cable line.

[0087] The partial discharge and noise comprehensive simulation signal generator 84 can simulate and output various types of partial discharges such as internal air gap discharge, surface discharge, and preform defect discharge, and can simulate and output corona noise, power supply noise, rotating motor noise, etc. The partial discharge and noise comprehensive simulation signal generator combined with the distribution cable line comprehensive status detection training platform of the present invention can set more than 50 groups of combined simulation signals, such as generating a single partial discharge or a single noise signal, or a composite signal of partial discharge and interference noise superimposed.

[0088] By changing the signal injection position to simulate the occurrence of partial discharge or grounding fault at various locations on the distribution cable line, the partial discharge, current or fault current sensors collect signals, and then the frequency characteristics, propagation characteristics, attenuation characteristics and sensitivity of different detection methods of partial discharge and fault location are investigated and mastered based on the signals collected by the sensors set at different locations, so as to popularize and improve the testers' distribution network cable line partial discharge detection and fault location technology level.

[0089] Further as an optional embodiment, the signal injection position includes the incoming terminal, outgoing terminal, incoming cable line and outgoing cable line of the first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device, the sensor installation position includes the incoming terminal, outgoing terminal, ground bus and shell of the first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device, and the test signal includes various types of partial discharge signals and noise signals.

[0090] In some optional embodiments, the partial discharge signal includes an internal air gap discharge signal, a surface discharge signal, and a preform defect discharge, and the noise signal includes a corona noise signal, a power supply noise signal, and a rotating motor noise signal.

[0091] As an optional implementation, the distribution cable line comprehensive status detection training method further includes the following steps:

[0092] Injecting a first partial discharge signal into the first ring switch device through a signal generator in a backstage operation cabinet;

[0093] The partial discharge sensors arranged on the first ring switch device, the second ring switch device, the third ring switch device and the fourth ring switch device are used to obtain the partial discharge monitoring signals at the corresponding positions, and the partial discharge monitoring signals are sent to the line monitoring device of the backstage operation cabinet;

[0094] The partial discharge signal attenuation characteristics are analyzed according to the first partial discharge signal and each partial discharge monitoring signal.

[0095] Specifically, Fig.10 The figure shows a schematic diagram of an implementation scenario of the attenuation characteristic detection training of partial discharge signals provided by an embodiment of the present invention, in which a tablet computer in the background operates a partial discharge and noise comprehensive simulation signal generator. Fig.10 A single simulated partial discharge signal is injected into the ring switch device 2 (point A3). The partial discharge sensors on the ring switch devices 2, 3, 4, and 5 all detect the partial discharge signal and transmit it to the distribution network comprehensive online monitoring device for processing and then transmit it to the background. The signal is transmitted in the cable line and gradually attenuates from the ring switch device 2 to the ring switch device 5, and then the attenuation characteristics of the partial discharge signal are understood. The propagation characteristics and attenuation characteristics of the test coaxial cable are basically the same as those of the 10kV three-core cable through the following formula test and calculation, such as Fig.11 Therefore, the system can use a test coaxial cable instead of a 10kV three-core cable.

[0096]

[0097] Among them, α is the attenuation, f is the frequency, ε is the dielectric constant of the cable insulation medium, k1, k2, k b is a constant, k p1and k p2 is the resistivity of the inner and outer conductors, d is the diameter of the inner conductor, D is the diameter of the outer conductor, dw is the diameter of the braided wire, and tanδ is the tangent value of the insulating medium loss.

[0098] like Fig.12 The figure shows a schematic diagram of the implementation scenario of the partial discharge signal detection training under noise interference provided by an embodiment of the present invention, in which a background tablet computer operates a partial discharge and noise comprehensive simulation signal generator. Fig.12 The annular switch device 4 (point C2) injects an internal air gap discharge signal, and the annular switch device 4 (point C4) superimposes and injects a corona noise interference signal with a central phase difference of 120°, thereby simulating the interference signal of the actual operating cable line without adding high voltage, making the partial discharge detection environment closer to the actual partial discharge test site.

[0099] As an optional implementation, the distribution cable line comprehensive status detection training method further includes the following steps:

[0100] By means of fault simulation triggering switch, a ground fault is generated by instant closing and short-circuiting a signal injection port of the first ring switch device, the second ring switch device, the third ring switch device or the fourth ring switch device;

[0101] The current monitoring signals at the corresponding positions are obtained by current sensors arranged on the first ring switch device, the second ring switch device, the third ring switch device and the fourth ring switch device, and the current monitoring signals are sent to the line monitoring device of the background operation cabinet;

[0102] Fault location analysis is performed based on each current monitoring signal and the corresponding position.

[0103] Specifically, Fig.13 Schematic diagram of the implementation scenario of the fault location training provided by the embodiment of the present invention, operating the fault simulation trigger switch in Fig.13 The ring switch device 2 (point A3) is instantly closed and short-circuited, resulting in a ground fault. The fault current sensors on the ring switch devices 2, 3, 4, and 5 all detect the signal and transmit it to the distribution network comprehensive online monitoring device for processing and then transmitted to the background. The background fault location system software automatically calculates the location result through the waveform time difference detected at several measuring points and the line information, and compares and analyzes it with the actual fault location.

[0104] It should be noted that Fig.10 , Fig.12 as well as Fig.13In the figure, A1 represents the signal injection port on the incoming cable line of the first ring-shaped switch device, A2 to A4 represent the signal injection ports on the outgoing cable line of the first ring-shaped switch device, B1 represents the signal injection port on the incoming cable line of the second ring-shaped switch device, B2 to B4 represent the signal injection ports on the outgoing cable line of the second ring-shaped switch device, C1 represents the signal injection port on the incoming cable line of the third ring-shaped switch device, C2 to C4 represent the signal injection ports on the outgoing cable line of the third ring-shaped switch device, D1 represents the signal injection port on the incoming cable line of the fourth ring-shaped switch device, and D2 to D4 represent the signal injection ports on the outgoing cable line of the fourth ring-shaped switch device. It should be recognized that Fig.10 , Fig.12 as well as Fig.13 Although four signal injection ports are shown, this is only for illustration and does not limit the number of signal injection ports on the ring switch device in the present invention.

[0105] The above is an explanation of the system structure and working principle of the embodiments of the present invention. It can be appreciated that the embodiments of the present invention list embodiments in which partial discharge occurs in a cable line body, a partial discharge signal occurs in a cable line body and is covered by noise, and a grounding fault occurs in a cable line body. In the actual training process, partial discharge or grounding faults in other terminals or cable bodies can also be simulated, and more other detection technology training can be carried out on the distribution cable line comprehensive status detection training platform system, which can provide more comprehensive verification and skills training.

[0106] The distribution cable line comprehensive status detection training system of the present invention can simulate the three-phase cable terminal structure, multi-circuit cable line and ring network structure of the actual distribution cable line, and can also simulate the complex noise environment of the overhead line and the actual site. Teaching and training through the distribution cable line comprehensive status detection training system can effectively improve the trainees' partial discharge testing and fault location technical level, and improve the comprehensiveness and training effect of partial discharge detection and fault location training of the distribution cable line ring network cabinet system.

[0107] It should be appreciated that embodiments of the present invention may be implemented or enforced by computer hardware, a combination of hardware and software, or by computer instructions stored in a non-transitory computer-readable memory. The above methods may be implemented in a computer program using standard programming techniques, including a non-transitory computer-readable storage medium configured with a computer program, wherein the storage medium so configured causes the computer to operate in a specific and predefined manner, according to the methods and drawings described in the specific embodiments. Each program may be implemented in a high-level procedural or object-oriented programming language to communicate with a computer system. However, if desired, the program may be implemented in an assembly or machine language. In any case, the language may be a compiled or interpreted language. In addition, the program may be run on a programmed dedicated integrated circuit for this purpose.

[0108] Furthermore, the operations of the processes described herein may be performed in any suitable order unless otherwise indicated herein or otherwise clearly contradicted by context. The processes described herein (or variations and / or combinations thereof) may be performed under the control of one or more computer systems configured with executable instructions, and may be implemented as code (e.g., executable instructions, one or more computer programs, or one or more applications) that is executed collectively on one or more processors, by hardware, or a combination thereof. The computer programs described above include a plurality of instructions that may be executed by one or more processors.

[0109] Further, the above method can be implemented in any type of computing platform that is operably connected to a suitable computer, including but not limited to a personal computer, a minicomputer, a mainframe, a workstation, a network or distributed computing environment, a separate or integrated computer platform, or in communication with a charged particle tool or other imaging device, etc. Various aspects of the present invention can be implemented in machine-readable code stored on a non-transitory storage medium or device, whether removable or integrated into a computing platform, such as a hard disk, an optical read and / or write storage medium, a RAM, a ROM, etc., so that it can be read by a programmable computer, and when the storage medium or device is read by the computer, it can be used to configure and operate the computer to perform the process described herein. In addition, the machine-readable code, or a portion thereof, can be transmitted via a wired or wireless network. When such media includes instructions or programs that implement the steps described above in conjunction with a microprocessor or other data processor, the invention described herein includes these and other different types of non-transitory computer-readable storage media. When programmed according to the methods and techniques described in the present invention, the present invention also includes the computer itself.

[0110] The computer program can be applied to input data to perform the functions described herein, thereby converting the input data to generate output data stored in a non-volatile memory. The output information can also be applied to one or more output devices such as a display. In a preferred embodiment of the present invention, the converted data represents physical and tangible objects, including specific visual depictions of physical and tangible objects produced on the display.

[0111] The above is only a preferred embodiment of the present invention. The present invention is not limited to the above implementation. As long as the technical effect of the present invention is achieved by the same means, any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the scope of protection of the present invention. Within the scope of protection of the present invention, its technical scheme and / or implementation method may have various modifications and changes.

Claims

1. A distribution cable line comprehensive status detection training system, characterized in that: It includes a transformer terminal, a first ring switch device, a first overhead line device, a second ring switch device, a third ring switch device, a fourth ring switch device, a second overhead line device and a backstage operation cabinet, wherein: The transformer terminal is electrically connected to the first ring switch device through a power line, the first ring switch device, the first overhead line device, the second ring switch device, the third ring switch device, the fourth ring switch device and the second overhead line device are connected in sequence through a coaxial cable, and the first ring switch device is connected to the fourth ring switch device through a coaxial cable to form a distribution cable line; The first ring switch device, the second ring switch device, the third ring switch device and the fourth ring switch device are all used to simulate the switch cabinet in the distribution cable line, the first overhead line device and the second overhead line device are both used to simulate the overhead line in the distribution cable line, the substation is used to adjust and control the voltage input to the distribution cable line, and the background operation cabinet is used to inject test signals into the distribution cable line and perform status detection.

2. A distribution cable line comprehensive status detection training system according to claim 1, characterized in that: The first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device all include a shell, a load, a busbar, an incoming terminal, an outgoing terminal, an incoming cable line, an outgoing cable line, a signal injection port and a ground bus. The load, the busbar, the incoming terminal and the outgoing terminal are all arranged in the shell, the incoming cable line is connected to the busbar through the incoming terminal, the outgoing cable line is connected to the busbar through the outgoing terminal, the load is connected to the busbar, the signal injection port is arranged on the incoming cable line and / or the outgoing cable line, and the armor of the incoming terminal and the outgoing terminal is grounded through the ground bus.

3. A distribution cable line comprehensive status detection training system according to claim 1, characterized in that: The first overhead line device and the second overhead line device both include an overhead line, a wire drum, a support column and a chassis. The wire drum is fixedly connected to the chassis via the support column, and the overhead line is arranged and wound on the wire drum.

4. A distribution cable line comprehensive status detection training system according to claim 2, characterized in that: The background operation cabinet includes a cabinet body, a display screen, an operating table, a signal generator, a line monitoring device and a test computer. The display screen, the operating table, the signal generator, the line monitoring device and the test computer are all arranged on the cabinet body. The display screen, the signal generator and the line monitoring device are all communicatively connected with the test computer. The test computer is used to control the signal generator to inject a test signal into at least one of the incoming terminal, the outgoing terminal and the signal injection port, and to monitor the status of the distribution cable line through the line monitoring device.

5. A distribution cable line comprehensive status detection training system according to claim 4, characterized in that: One end of the signal generator is connected to the lead-out port of the coaxial cable, and the other end of the signal generator is grounded; or, One end of the signal generator is connected to the cable core conductor of the incoming terminal and / or the outgoing terminal, and the other end of the signal generator is grounded; or, The signal generator is connected to the signal injection port.

6. A distribution cable line comprehensive status detection training system according to claim 4, characterized in that: The distribution cable line comprehensive status detection training system also includes a status monitoring sensor, which includes a fault current sensor, a current sensor and a partial discharge sensor. The status monitoring sensor is communicatively connected to the line monitoring device. The status monitoring sensor is arranged on the cable body of the incoming terminal / the outgoing terminal, or the status monitoring sensor is arranged on the main insulation of the branch cable of the incoming terminal / the outgoing terminal, or the status monitoring sensor is arranged on the grounding bus, or the status monitoring sensor is arranged on the shell.

7. A distribution cable line comprehensive status detection training method, which is implemented by a distribution cable line comprehensive status detection training system as claimed in any one of claims 1 to 6, characterized in that: The following steps are involved: Injecting test signals into a plurality of preset signal injection positions of the distribution cable line respectively through the background operation cabinet; Receiving status monitoring signals of a plurality of preset sensor installation positions of the power distribution cable line through the backstage operation cabinet; The frequency characteristics, propagation characteristics, attenuation characteristics of the test signal and the detection sensitivity of different sensor installation positions are analyzed according to the test signal, the signal injection position, the state monitoring signal and the sensor installation position.

8. A distribution cable line comprehensive status detection training method according to claim 7, characterized in that: The signal injection position includes the incoming terminal, outgoing terminal, incoming cable line and outgoing cable line of the first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device; the sensor installation position includes the incoming terminal, outgoing terminal, ground bus and shell of the first annular switch device, the second annular switch device, the third annular switch device and the fourth annular switch device; the test signal includes various types of partial discharge signals and noise signals.

9. A distribution cable line comprehensive status detection training method according to claim 7, characterized in that: The distribution cable line comprehensive status detection training method also includes the following steps: Injecting a first partial discharge signal into the first annular switch device through a signal generator of the background operation cabinet; Obtaining partial discharge monitoring signals at corresponding positions through partial discharge sensors arranged on the first annular switch device, the second annular switch device, the third annular switch device, and the fourth annular switch device, and sending the partial discharge monitoring signals to the line monitoring device of the background operation cabinet; The partial discharge signal attenuation characteristic is analyzed according to the first partial discharge signal and each of the partial discharge monitoring signals.

10. A distribution cable line comprehensive status detection training method according to claim 7, characterized in that: The distribution cable line comprehensive status detection training method also includes the following steps: By means of fault simulation triggering switch, a ground fault is generated by instant closing and short-circuiting a signal injection port of the first ring switch device, the second ring switch device, the third ring switch device or the fourth ring switch device; Acquire current monitoring signals at corresponding positions through current sensors arranged on the first annular switch device, the second annular switch device, the third annular switch device, and the fourth annular switch device, and send the current monitoring signals to the line monitoring device of the background operation cabinet; Fault location analysis is performed based on each of the current monitoring signals and the corresponding positions.

Citation Information

Patent Citations

  • Simulation screen for monitoring switch cabinet circuit system

    CN106655505A

  • 10kV distribution network cable line fault location simulation device

    CN106707104A

  • System for positioning faults of power supply cable lines of power distribution network

    CN106771884A

  • True type power distribution network multi-state complex fault simulation test platform and test method thereof

    CN109669103A

  • Primary side fault injection FA detection system and method

    CN112924862A