Off-board welding integrated rail changing construction method
Through the integrated rail replacement construction method of non-vehicle welding, the integrated operation of unrack, welding and rail collection is used to carry out integrated operations of rail unloading, welding and rail collection, solving the safety hazards of medium and long rails in the existing technology and the low utilization rate of equipment, and achieving efficient railways The construction of line overhaul and rail replacement reduces transportation interference and improves equipment utilization.
Patent Information
- Application Number
- CN202411231296.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2024-07-31
- Filing Date
- 2024-09-04
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-09-04
AI Technical Summary
The existing rail replacement construction methods have the safety hazard of long rails being placed on the outside of the rail or in the core for a long time. After the vehicle-mounted welding equipment is added, the pure operation time of rail replacement will be extended, the line blocking time will be longer, and the transportation will be more disturbed. Moreover, the utilization rate of equipment has decreased and the economy is poor.
Using the integrated rail replacement construction method of non-vehicle welding, the integrated operation of unrack, welding and rail collection is carried out through the marshalling train. Using existing mobile welding equipment, unloading of the 175mm superheight 25‰ ramp section within 335 minutes. Rail, welding rail, rail replacement and rail retraction operations avoid the use of aluminum thermal welding and reduce interference to transportation and capital investment.
The railway line major repair and rail replacement construction was completed within 335 minutes, eliminating the safety hazards of long rail placement, improving construction efficiency, reducing interference to transportation, and improving the utilization rate of existing equipment, achieving completion of work. The effect of clean materials and clean people.
Smart Images

Figure CN118880683A_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of track replacement construction, and specifically relates to a non-vehicle-mounted welding integrated track replacement construction method. Background Art
[0002] The existing track replacement construction organization model is to use the T11 long-rail transport vehicle to unload the long rails to be replaced to the outer ballast shoulder or track core of the rail in advance, and use anti-expansion rods to reinforce them for replacement. The day before the track replacement, the offline welding operation mode is used to weld the unit rails that have been unloaded from the vehicle in the early stage into long rails of more than 1 km, and then continue to use anti-expansion rods for reinforcement. On the day of the track replacement, after the old rails are unloaded from the track, they are cut into about 500 meters of rails and continue to be placed on the outer ballast shoulder or track core of the rail, and are reinforced with anti-expansion rods for collection. According to the construction arrangement, the T11 long-rail transport vehicle is used or it is cut into 25-meter short rails again, and the rail collection working device is used for recovery. However, the biggest problem with this construction organization is the safety hazard of long rails being placed on the outer ballast shoulder or track core of the rail for a long time.
[0003] Although the existing integrated track-changing construction method can realize all track-changing operations within a skylight by adding onboard welding equipment to the long-track train, and ensure that the work is completed, the materials are clean, and the site is clear. However, after adding onboard welding equipment, the pure operation time of track-changing is also extended accordingly, the line is blocked for a longer time, and the interference with transportation is greater. On the other hand, the existing integrated track-changing construction method not only requires the purchase of new equipment, but also causes a decrease in the utilization rate of existing mobile rail welding equipment, and its economic efficiency is poor. Therefore, how to realize all track-changing operations within a skylight on the basis of using existing mobile welding equipment requires exploration and innovation. Summary of the invention
[0004] The purpose of this application is to provide a non-vehicle-mounted welding integrated track replacement construction method, which realizes the use of existing mobile rail welding equipment to complete the integrated construction mode of rail unloading, rail welding, rail replacement and rail collection on the same day in a 175mm super-high and 25‰ slope section within a 335-minute blockade time. It can not only ensure that the work is completed and the materials are clean, and the site is cleared, but also meet the requirements of completing the replacement, welding and collection of two pairs of new rails within one skylight without using aluminum thermite welding, thereby reducing interference with transportation and capital investment.
[0005] The purpose of this application is achieved through the following technical solutions:
[0006] A non-vehicle-mounted welding integrated track replacement construction method, characterized in that it comprises the following steps:
[0007] Step 1: The first train set enters the track-changing section. The first train set includes the first locomotive, the long rail car and the second locomotive connected in sequence from front to back. At the starting point Longkou, the long rail car is separated from the second locomotive, and the first locomotive pulls the long rail car to unload the first pair of new rails;
[0008] Step 2: After the first pair of new rails are completely on the ground, the second pair of new rails are unloaded;
[0009] Step 3: After the second pair of new rails are completely on the ground, the second locomotive moves forward and couples with the long rail car, and the first marshaling train drives out of the rail-changing section;
[0010] Step 4: While performing step 3, the second train set enters the track-changing section. The second train set includes the third locomotive, the welding machine, the rail welding car, the fourth locomotive, the rail collecting car set, the high-power rail car, the fifth locomotive, the auxiliary car set and the sixth locomotive, which are connected in sequence from front to back. Before the starting point of the track-changing section, the rail welding car is separated from the welding machine and the fourth locomotive respectively. The third locomotive pulls the welding machine to the overlap of the first and second pairs of new rails to prepare for welding operations, and the rail welding car goes to the starting point of the track-changing section by itself;
[0011] Step 5: While carrying out step 4, the operator performs pre-welding preparation work on the first and second pairs of new rails;
[0012] Step 6: The welding machine performs the offline long rail welding operation to weld the first pair and the second pair of new rails into a pair of rails. After the operation is completed, the third locomotive pulls the welding machine to the stop point and performs the stop point pre-welding preparation work simultaneously;
[0013] Step 7: While carrying out step 6, the track change starts at the starting point of the dragon mouth, and the track change stops at the operation position of the welding machine, and the operation of the welding machine is completed, and then the track change continues;
[0014] Step 8: While carrying out step 7, the rail welding vehicle enters the starting point of the dragon mouth, performs pre-welding preparation work, and simultaneously carries out the old rail cutting operation;
[0015] Step 9: The rail welding vehicle performs online welding of the new and old rails at the starting point Longkou;
[0016] Step 10: After the on-line welding and rail replacement operations at the starting point are completed, the rail welding vehicle exits the starting point, stretches and releases the rails, and after reserving the free end distance of the new rail at the end point, the line is locked;
[0017] Step 11: Carry out preparation work before stop-point dragon mouth welding;
[0018] Step 12: The welding machine performs online welding of the new and old rails at the stop point;
[0019] Step 13: while performing steps 11 and 12, the rail welding vehicle automatically goes to the stop point and waits, the high-power rail vehicle is separated from the fifth locomotive, and the fourth locomotive pulls the rail collecting vehicle group to perform the rail collecting operation;
[0020] Step 14: After the welding operation at the stop point is completed, the welding machine is connected to the rail welding vehicle, and the third locomotive pulls the welding machine and the rail welding vehicle forward;
[0021] Step 15: while performing steps 13 and 14, the fifth locomotive pulls the auxiliary vehicle group to perform the material receiving operation;
[0022] Step 16: After the old rails and old materials are recovered, the second train sets are coupled to each other and drive out of the track replacement area.
[0023] Furthermore, in step 5, the pre-welding preparation work includes cutting, grinding, rust removal, support and rail alignment of the first pair and the second pair of new rails.
[0024] Furthermore, in step 6, the pre-welding preparation work includes removing the rail fastener bolts in the old rail support area, installing the gauge rod, supporting the rail, and performing rust removal and grinding operations.
[0025] Furthermore, in step 9, the rail welding vehicle includes a bicycle body, a crane, a rail welding supply unit, a rail welding machine body, an extension pipeline and a machine body bracket. The machine body bracket is set up on the roadbed, and the crane on the bicycle body lifts the rail welding machine body on the vehicle onto the machine body bracket. Then the bicycle body drives out of the rail pad area, and the rail welding supply unit on the bicycle body supplies power, gas, liquid and oil to the rail welding machine body through the extension pipeline. The rail welding machine body performs online welding operations on the new and old rails at the starting point dragon mouth.
[0026] Furthermore, in step 9, the machine body support is stabilized on the roadbed by a support assembly.
[0027] Furthermore, in step 9, the support assembly is located below the machine body support, and the low-position rail supports the machine body support through the support assembly.
[0028] Furthermore, in the step 9, the support assembly is located above the machine body support, and the high roadbed performs a reverse pulling action on the machine body support through the support assembly.
[0029] Furthermore, in the step 11, the pre-welding preparation work includes rail bending, cutting, grinding, rust removal and support operations.
[0030] Furthermore, in step 13, the track collecting vehicle group includes a first track collecting device, a boxcar and a second track collecting device which are sequentially connected from front to back.
[0031] Furthermore, in step 15, the auxiliary vehicle group includes a road flat car, a first passenger car, a second passenger car, a third passenger car and a fourth passenger car connected in sequence from front to back.
[0032] Beneficial effects of this application:
[0033] (1) It is possible to complete all the operations of rail unloading, rail welding, rail replacement, and rail collection at one time in a section with a super-high height of 175 mm and a slope of 25‰ within the 335-minute blockade time for rail replacement construction of railway lines.
[0034] (2) It eliminates the potential safety hazard of long rails being placed on the outer ballast shoulder or in the rail core for a long time.
[0035] (3) For the first time, during the overhaul and track replacement construction in the 175mm super-high and 25‰ ramp section, thermite welding was completely eliminated.
[0036] (4) The efficiency of overhaul track replacement construction has been further improved, and the construction that originally required multiple skylights to be completed can be implemented within one skylight, greatly reducing the interference with transportation.
[0037] (5) A small amount of capital investment has achieved the same effect as the existing vehicle-mounted integrated welding construction method. While eliminating the need to purchase vehicle-mounted welding equipment, it has also greatly improved the utilization rate of the existing YHGQ-1200 pneumatic rail welding vehicle and YHGR-1200 integrated welding machine.
[0038] The aforementioned main scheme of the present application and its further options can be freely combined to form multiple schemes, all of which are schemes that can be adopted and claimed for protection in the present application; and in the present application, (non-conflicting options) can also be freely combined with each other and with other options. After understanding the scheme of the present application, those skilled in the art can understand that there are many combinations based on the prior art and common knowledge, all of which are technical schemes to be protected by the present application, and they are not exhaustively listed here. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 This is a schematic diagram of the application process.
[0040] Figure 2 It is a schematic diagram of the first train formation of this application.
[0041] Figure 3 It is a schematic diagram of the second train set of this application.
[0042] Figure 4 It is a schematic diagram of the separate welding operation structure of the rail welding vehicle in this application.
[0043] Figure 5 This is a schematic diagram of the operation of the separate welding operation of the rail welding vehicle in this application.
[0044] Figure 6 This is a schematic diagram of the stop point dragon mouth welding operation of this application.
[0045] Figure 7 This is a schematic diagram of the support rail for the stop point longkou welding operation of this application.
[0046] In the figure: 10-first train set, 11-first locomotive, 12-long rail car, 13-second locomotive.
[0047] 20-the second train set, 21-the third locomotive, 22-the integrated welding machine, 23-the rail welding car, 24-the fourth locomotive, 25-the rail collecting car set, 26-the high-power rail car, 27-the fifth locomotive, 28-the auxiliary car set, 29-the sixth locomotive.
[0048] 231 - bicycle body, 232 - crane, 233 - rail welding supply unit, 234 - rail welding machine body, 235 - extension pipeline, 236 - machine body bracket, 237 - support assembly.
[0049] 251-the first track-collecting device, 252-the boxcar, 253-the second track-collecting device.
[0050] 281-road flat car, 282-first passenger car, 283-second passenger car, 284-third passenger car, 285-fourth passenger car. DETAILED DESCRIPTION
[0051] The following non-limiting examples are provided to illustrate the present application.
[0052] Embodiment 1:
[0053] refer to Figure 1 to Figure 7 As shown, a non-vehicle-mounted welding integrated track replacement construction method includes a first train set 10 and a second train set 20.
[0054] The first train set 10 includes a first locomotive 11, a long rail car 12 (T11 long rail car) and a second locomotive 13 connected in sequence from front to back. The second train set includes a third locomotive 21, a welding machine 22 (YHGR-1200 welding machine), a rail welding car 23 (YHGQ-1200 pneumatic rail welding car), a fourth locomotive 24, a rail collecting car set 25, a high-power rail car 26, a fifth locomotive 27, an auxiliary car set 28 and a sixth locomotive 29 connected in sequence from front to back.
[0055] The construction method specifically comprises the following steps:
[0056] Step 1: After the construction section is blocked, the first train set enters the track-changing section. At the starting point Longkou, the long-rail car is separated from the second locomotive, and the second locomotive withdraws from the track-unloading operation area. The first locomotive pulls the long-rail car to unload the first pair of new rails, and the second locomotive stays on standby.
[0057] Step 2: After the first pair of new rails have completely landed on the ground, the first locomotive stops on the spot and waits for the ground workers to prepare for unloading the second pair of new rails before continuing to unload the second pair of new rails.
[0058] Step 3: After the second pair of new rails are completely put into place, the second locomotive moves forward through the rail unloading area and connects with the long rail car. The first trainset drives out of the rail-changing area and enters the station ahead in groups. It returns to the stop station from the adjacent line in a timely manner according to the construction manager and the operation plan.
[0059] Step 4: While carrying out step 3, the second marshaling train enters the track-changing section and stops about 500 meters before Longkou, the starting point of the track-changing section. The rail welding car is separated from the welding machine and the fourth locomotive.
[0060] The third locomotive pulled the welding machine (YHGR-1200 welding machine) to the joint of the first and second pairs of new rails to prepare for welding operations. The rail welding vehicle (YHGQ-1200 pneumatic rail welding vehicle) moved to the outside of the starting point Longkou and waited, while the remaining trains waited in place.
[0061] Step 5: While carrying out step 4, the operator performs pre-welding preparation work on the first and second pairs of new rails. The pre-welding preparation work includes cutting, grinding, rust removal, support and rail alignment of the first and second pairs of new rails.
[0062] Step 6: After the welding machine is in place, the long rail welding operation is carried out offline to weld the first and second pairs of new rails into a pair of rails. After the operation is completed, the third locomotive pulls the welding machine to the outside of the stop mouth and waits. The preparation work before the stop mouth welding is carried out simultaneously, including removing the rail fastener bolts in the old rail support area, installing the gauge rod, supporting the rail, rust removal and grinding.
[0063] Step 7: While carrying out step 6, start manual track changing at the starting point Longkou, and stop at the operating position of the welding machine. Stop about 200 meters away from the welding machine, wait for the welding machine to finish operating, and continue manual track changing.
[0064] Step 8: While carrying out step 7, when the manual rail replacement is about 100 meters away from the starting point, the rail welding vehicle enters the starting point to carry out pre-welding preparations. The old rail dismantling team enters the site to carry out the old rail cutting operation, cutting the replaced old rail into 24.5-meter short rails.
[0065] Step 9: The rail welding vehicle performs online welding operations on the new and old rails at the starting point Longkou.
[0066] The rail welding vehicle 23 includes a bicycle body 231 , a crane 232 , a rail welding supply unit 233 , a rail welding machine body 234 , an extension pipeline 235 , a machine body bracket 236 and a support assembly 237 .
[0067] A machine body bracket is set up on the roadbed, and the crane on the bicycle body lifts the rail welding machine on the vehicle onto the body bracket. Then the bicycle body drives out of the rail pad area, and the rail welding supply unit on the bicycle body supplies electricity, gas, liquid and oil to the rail welding machine through extended pipelines. The rail welding machine performs online welding operations on the new and old rails at the starting point Longkou.
[0068] The machine body support is stabilized on the roadbed through the support assembly. The support assembly is located below the machine body support, and the low-position rail supports the machine body support through the support assembly. Alternatively, the support assembly is located above the machine body support, and the high-position roadbed reverses the machine body support through the support assembly.
[0069] This solution is not restricted by the super-height and ramp of online rail welding operations and can be applied to various working environments.
[0070] Step 10: After the on-line welding and rail changing operations at the starting point Longkou are completed, the rail welding vehicle exits the starting point Longkou, stretches and releases the rails, reserves the distance for the free end of the new rail at the end point Longkou, and then locks the line.
[0071] Step 11: Carry out the preparatory work before welding the stop-point dragon mouth. The preparatory work before welding includes rail bending, cutting, grinding, rust removal and support operations, and prepares for flash welding on the stop-point dragon mouth line.
[0072] Step 12: The third locomotive pushes the welding machine at a speed not exceeding 2 km / h, and uses a climbing method to accurately align it to the welding operation point. The welding machine performs online welding operations on the new and old rails at the stop point dragon mouth, and implements online flash welding operations.
[0073] Step 13: While carrying out steps 11 and 12, the rail welding vehicle automatically moves to the outside of the online welding locking area at the stop mouth and waits.
[0074] The high-power railcar is separated from the fifth locomotive, and the fourth locomotive pulls the rail collecting vehicle group to perform rail collecting operations. The rail collecting vehicle group 25 includes a first rail collecting device 251, a boxcar 252, and a second rail collecting device 253 connected in sequence from front to back. The boxcar is placed in the middle to ensure that one stop can meet the simultaneous operation of two sets of rail collecting devices.
[0075] Step 14: After the welding operation at the stop point is completed, the welding machine is connected to the rail welding vehicle. The third locomotive pulls the welding machine and the rail welding vehicle forward for 2 kilometers to make room for the subsequent recycling of short rails and old materials.
[0076] Step 15: While performing steps 13 and 14, the fifth locomotive pulls the auxiliary vehicle group to perform the material collection operation. The auxiliary vehicle group 28 includes a road flat car 281, a first passenger car 282, a second passenger car 283, a third passenger car 284 and a fourth passenger car 285 connected in sequence from front to back. The fifth locomotive pulls the auxiliary vehicle group to run slowly, always keeping a safe enough distance from the short-track recovery vehicle in front.
[0077] Step 16: After the old rails and old materials are recovered, the second train set is coupled to each other, drives out of the track-changing area, restores the original set, and returns to the station.
[0078] This construction method mainly includes four functional parts: rail unloading, rail replacement, rail welding and rail collection. Each functional part is briefly described as follows:
[0079] 1. Unloading the tracks.
[0080] (1) Rail unloading operation process and control plan.
[0081] 1. According to the slope of the line on that day, calculate the number of hand brakes to be tightened for the T11 long rail transport vehicle during the rail unloading operation, prepare an operation plan, clearly specify the vehicle number, implementer, and inspector to be tightened, ensure that the speed of the T11 long rail transport vehicle is stable when unloading the rails on the slope, and prevent the impact of braking impact on the rail unloading operation. Through repeated verification, the unloading speed is appropriately controlled within the range of 3-5km / h.
[0082] 2. To prevent the risk of long rails sliding down the ballastless track drainage ditch during unloading, a 110×110×500mm supporting square wood and special U-shaped threaded steel bars are placed every 8 meters in the unloading area for protection. This solution can also effectively protect the concrete track bed and electrical auxiliary equipment from damage, and make it more convenient to pry the new and old track groups, thereby improving the efficiency of the prying operation.
[0083] 3. Double clamps are used to fix the new rails at the starting point of rail unloading to prevent the long rail vehicle from dragging the rails when it starts running, effectively improving the timeliness and safety of rail unloading.
[0084] 4. When transporting rails, wrap the ends of the new rails with rubber to avoid damaging the roadbed surface during the transport process.
[0085] 5. During the rail unloading process, two people on the ground use hooks to fix the rails as the vehicle moves, control the horizontal distance between the new and old rails, and ensure that the new rails are placed on the square timber after unloading.
[0086] (2) Introduction to the structure, location and function of the mechanical equipment used for rail unloading.
[0087] The long rail car unloading operation mainly uses the T11 long rail transport car, which is powered by a 500kw generator set for the rail conveyor, winch and other equipment, and is installed in the equipment power room. The rail conveyor is driven by a hydraulic motor, and its power wheel is in close contact with the bottom of the rail. It is responsible for conveying the long rails to the unloading trough and providing power for the initial landing of the long rails. It is installed in the middle of the tail work car, and the two are arranged symmetrically, and can transport two rails at the same time. The winch is driven by an electric motor, and the wire rope is used to pull the work car under or recover it to the T11 long rail transport car, and it is arranged at the tail of the work car.
[0088] 2. Welding rails.
[0089] (1) YHGQ-1200 pneumatic welding rail car with separated starting point and longkou line welding.
[0090] 1. Starting point Longkou online welding operation process and control plan.
[0091] (1) Remove the rail fastener bolts at both ends of the weld, support the rails and perform rust removal and grinding before welding. (2) The rail space bolts that have been removed on the driving path of the bicycle body of the rail welding vehicle are restored every three days to ensure driving safety. The free end rails are synchronously opened, and the rails are supported to prepare for welding. (3) The personnel get off the road, and the bicycle body of the rail welding vehicle is accurately aligned to the rail welding operation site. (4) Install the special body bracket of the rail welding machine, lower the rail welding machine body and place it on the special body bracket, remove the rail welding machine body and the crane chain to separate them. (5) Recover the crane, the personnel get off the road, and the bicycle body exits the static end support rail area. (6) Use the extension pipeline to connect the rail welding machine body and the rail supply unit on the bicycle body. (7) Normal rail welding operation. (8) Remove the extension pipeline, support the rail below, and restore the static end fastener bolts every three days. (9) The personnel get off the road, and the bicycle body is accurately aligned again. (10) Install the lifting chain, connect the rail welding machine, and recover the pipeline. (11) Recover the crane, remove the special machine support, and recover the operating tools. (12) The rail welding vehicle exits the rail welding operation surface.
[0092] 2. Introduction to the structure, location and function of the mechanical equipment used.
[0093] The YHGQ-1200 pneumatic rail welding vehicle is an integrated large-scale track maintenance machine that integrates railway line self-wheel operation and welding operations. It is equipped with a Deutz inline 12-cylinder air-cooled engine as the power source, and the running parts are two sets of speed-up bogies. The bogies are designed in an H-shaped structure. The front bogies are equipped with two power wheel pairs, and the rear bogies are equipped with two non-power wheel pairs. The power wheel pairs are driven by a hydraulic motor suspended on the bogie. The hydraulic motor is connected to the hydraulic pump through a pipeline. The hydraulic pump is plugged into the transfer case. The transfer case is connected to the engine through a coupling, and the static hydraulic drive running circuit is completed. Another core component of the YHGQ-1200 pneumatic rail welding vehicle is the GPW-1200 pneumatic welding machine it carries. This equipment also uses the engine operating power source and obtains power through the hydraulic pump plugged into the transfer case. A double-arm crane is installed at the front end of the YHGQ-1200 gas pressure welding rail vehicle. The welding machine is connected to the crane through a lifting chain. The welding machine can be accurately aligned by operating the crane. The actions of each actuator of the GPW-1200 gas pressure welding machine and the gas flow control are all controlled by the central control computer, and the execution signal is sent through the PLC to realize the full automation of the welding operation.
[0094] (2) YHGR-1200 type integrated flash welding machine uses the climbing method to weld the stop point on the dragon mouth line.
[0095] 1. Stop point dragon mouth online welding operation process and control plan.
[0096] (1) Remove the rail fastener bolts at both ends of the weld, support the rails and perform rust removal and grinding before welding. (2) Install the rail bottom pad at the upper stop point of the road flat car's travel path, tighten the safety bolts; install the gauge pull cylinder and check the track gauge. (3) Synchronously open the free end rails, support the rails, and prepare for welding. (4) Personnel go down the road, install iron shoes at the end of the weld, and accurately align the road flat car to the rail welding operation site. (5) The welding machine is below and the welding operation is normal. (6) After welding is completed, the welding machine is recovered and the road flat car withdraws from the rail welding operation surface.
[0097] 2. Introduction to the structure, location and function of the mechanical equipment used.
[0098] The YHGQ-1200 type welding and flash welding machine is designed as a container type, which is loaded on a road flat car for operation and has no power. All devices of the equipment are arranged inside the container, which consists of two containers. The power room container is mainly equipped with a 450kw Volvo generator set and an air dryer, and the workshop container is equipped with a YHGR-1200 type welding and flash welding machine, a crane, a chiller, a hydraulic pump station, an autotransformer, etc. The generator set provides power for the equipment, and matches the current and voltage required for the welding operation through the autotransformer; the air dryer is mainly responsible for filtering the moisture in the compressed air to prevent rust inside the pipelines and components; the hydraulic pump station provides power source for each hydraulic actuator of the welding machine, which is uniformly controlled by the central control computer of the welding machine to realize the full automation of the welding operation.
[0099] 3. Change tracks.
[0100] (A) Operation process and control plan.
[0101] A manual track changing mode is adopted, with two rail prying groups set up, each with 10 people, under unified command, using crowbars to manually remove the old rails and install the new rails.
[0102] 4. Close the track.
[0103] (A) Operation process and control plan.
[0104] The old rails on the road were cut into 24.5-meter short rails by gas cutting and recycled using the LSD-I rail collection device. In order to improve the efficiency of the rail collection operation, an organizational mode of pulling two sets of rail collection devices to work synchronously was adopted.
[0105] (2) An introduction to the structure, location and function of the mechanical equipment used.
[0106] The main cross beam of the cantilever steel frame of the LSD-I rail collecting device is welded from a box beam, and is equipped with a Cummins 30kw generator set to provide power. The winch is driven by an electric motor, and the wire rope is arranged along the cantilever steel frame. The load of the winch is reduced through the pulley block to achieve the lifting function of heavy objects. A hydraulic cylinder is installed on the cantilever steel frame, which can provide lateral force to move the upper sliding part of the cantilever steel frame horizontally, so as to achieve the horizontal movement of heavy objects.
[0107] The aforementioned basic examples and their further selected examples can be freely combined to form multiple embodiments, all of which are embodiments that can be adopted and claimed for protection in this application. In the scheme of this application, each selected example can be arbitrarily combined with any other basic examples and selected examples.
[0108] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application should be included in the protection scope of the present application.
Claims
1. A non-vehicle-mounted welding integrated track replacement construction method, It is characterized in that The steps include: Step 1: The first train set enters the track-changing section. The first train set includes the first locomotive, the long rail car and the second locomotive connected in sequence from front to back. At the starting point Longkou, the long rail car is separated from the second locomotive, and the first locomotive pulls the long rail car to unload the first pair of new rails; Step 2: After the first pair of new rails are completely on the ground, the second pair of new rails are unloaded; Step 3: After the second pair of new rails are completely on the ground, the second locomotive moves forward and couples with the long rail car, and the first marshaling train drives out of the rail-changing section; Step 4: While performing step 3, the second train set enters the track-changing section. The second train set includes the third locomotive, the welding machine, the rail welding car, the fourth locomotive, the rail collecting car set, the high-power rail car, the fifth locomotive, the auxiliary car set and the sixth locomotive, which are connected in sequence from front to back. Before the starting point of the track-changing section, the rail welding car is separated from the welding machine and the fourth locomotive respectively. The third locomotive pulls the welding machine to the overlap of the first and second pairs of new rails to prepare for welding operations, and the rail welding car goes to the starting point of the track-changing section by itself; Step 5: While carrying out step 4, the operator performs pre-welding preparation work on the first and second pairs of new rails; Step 6: The welding machine performs the offline long rail welding operation to weld the first pair and the second pair of new rails into a pair of rails. After the operation is completed, the third locomotive pulls the welding machine to the stop point and performs the stop point pre-welding preparation work simultaneously; Step 7: While carrying out step 6, the track change starts at the starting point of the dragon mouth, and the track change stops at the operation position of the welding machine, and the operation of the welding machine is completed, and then the track change continues; Step 8: While carrying out step 7, the rail welding vehicle enters the starting point of the dragon mouth, performs pre-welding preparation work, and simultaneously carries out the old rail cutting operation; Step 9: The rail welding vehicle performs online welding of the new and old rails at the starting point Longkou; Step 10: After the on-line welding and rail replacement operations at the starting point are completed, the rail welding vehicle exits the starting point, stretches and releases the rails, and after reserving the free end distance of the new rail at the end point, the line is locked; Step 11: Carry out preparation work before stop-point dragon mouth welding; Step 12: The welding machine performs online welding of the new and old rails at the stop point; Step 13: while performing steps 11 and 12, the rail welding vehicle automatically goes to the stop point and waits, the high-power rail vehicle is separated from the fifth locomotive, and the fourth locomotive pulls the rail collecting vehicle group to perform the rail collecting operation; Step 14: After the welding operation at the stop point is completed, the welding machine is connected to the rail welding vehicle, and the third locomotive pulls the welding machine and the rail welding vehicle forward; Step 15: while performing steps 13 and 14, the fifth locomotive pulls the auxiliary vehicle group to perform the material receiving operation; Step 16: After the old rails and old materials are recovered, the second train sets are coupled to each other and drive out of the track replacement area.
2. The non-vehicle-mounted welding integrated track replacement construction method according to claim 1, Features: In step 5, the pre-welding preparation work includes cutting, grinding, rust removal, support and rail alignment of the first and second pairs of new rails.
3. The non-vehicle-mounted welding integrated track replacement construction method according to claim 1, Features: In step 6, the pre-welding preparation work includes removing the rail fastener bolts in the old rail support area, installing the gauge tie rod, supporting the rail, and performing rust removal and grinding operations.
4. The non-vehicle-mounted welding integrated track replacement construction method according to claim 1, Features: In the step 9, the rail welding vehicle includes a bicycle body, a crane, a rail welding supply unit, a rail welding machine body, an extension pipeline and a machine body bracket. The machine body bracket is set up on the roadbed, and the crane on the bicycle body lifts the rail welding machine body on the vehicle onto the machine body bracket. Then the bicycle body drives out of the rail pad area, and the rail welding supply unit on the bicycle body supplies power, gas, liquid and oil to the rail welding machine body through the extension pipeline. The rail welding machine body performs online welding operations on the new and old rails at the starting point dragon mouth.
5. The non-vehicle-mounted welding integrated track replacement construction method according to claim 4, Features: In the step 9, the machine body support is stabilized on the roadbed by the support assembly.
6. The non-vehicle-mounted welding integrated track replacement construction method according to claim 5, Features: In the step 9, the support assembly is located below the machine body support, and the low-position rail supports the machine body support through the support assembly.
7. The non-vehicle-mounted welding integrated track replacement construction method according to claim 5, Features: In the step 9, the support assembly is located above the machine body support, and the high roadbed performs a reverse pulling action on the machine body support through the support assembly.
8. The non-vehicle-mounted welding integrated track replacement construction method according to claim 1, Features: In the step 11, the preparatory work before welding includes rail deflection, bending, cutting, grinding, rust removal and support operations.
9. The non-vehicle-mounted welding integrated track replacement construction method according to claim 1, Features: In step 13, the track collecting vehicle group includes a first track collecting device, a boxcar and a second track collecting device which are sequentially connected from front to back.
10. The non-vehicle-mounted welding integrated track replacement construction method according to claim 1, Features: In step 15, the auxiliary vehicle group includes a road flat car, a first passenger car, a second passenger car, a third passenger car and a fourth passenger car connected in sequence from front to back.
Citation Information
Patent Citations
Integrated rail changing operation method
CN112900168A
High-speed rail existing line steel rail replacement and laying construction method
CN115418897A
Steel rail cushion block suitable for optimizing steel rail gas pressure welding
CN217254038U
Off-board welding integrated rail changing construction system
CN222961830U
Track installation replacement method and train for carrying out the method
EP0108168A1