Large-span steel tube arch bridge arch rib segmental splicing structure and construction method thereof

By designing the segmented splicing structure and connection components of the arch ribs, the precise positioning and fixing of the arch ribs is achieved, the problem of amplification of errors caused by the sinking of the arch ribs is solved, and the lifting accuracy and construction efficiency are improved.

CN118880725APending Publication Date: 2024-11-01CHONGQING JIAOTONG UNIV +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411312509.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The arch ribs of the large-span steel pipe arch bridge will sink under the action of gravity, resulting in the gradual amplification of the error when the final closing is completed. The existing method relies on empirical calculations, and the calculation is large and inaccurate.

Method used

A segmented splicing structure of arch ribs is designed, using multiple arch ribs and connecting components. Through components such as card slots, card blocks, arc grooves, rectangular plates, insert rods and springs, the precise positioning and fixing of arch ribs is achieved. , reduce manual operation and improve lifting accuracy.

Benefits of technology

Through precise positioning and fixing, the workload of workers is reduced, the lifting accuracy is improved, error is reduced, and construction efficiency and safety are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880725A_ABST
    Figure CN118880725A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of arch bridges, particularly relates to a large-span steel tube arch bridge arch rib segmental splicing structure and a construction method thereof, and provides the following scheme that the large-span steel tube arch bridge arch rib segmental splicing structure comprises a plurality of arch ribs, each arch rib comprises two upper splicing arches and two lower splicing arches, the two upper splicing arches are located above the two lower splicing arches, the two upper splicing arches are arranged in parallel, and the two lower splicing arches are arranged in parallel; a first clamping block enters a second clamping groove, a second clamping block enters a first clamping groove, positioning between a second vertical supporting plate and a first vertical supporting plate is guaranteed, a pushing block is withdrawn, the braking state of an inserting rod is relieved, the inserting rod moves into a second circular groove, and the inserting rod is pushed to move into the second circular groove. And a sliding plate is pushed to move transversely through the two ends of an inserting rod, a second clamping round rod enters two first clamping round grooves, the inserting rod is braked again, the device is prevented from loosening, then pre-fixing can be achieved, the hoisting precision can be improved, and the workload of workers can be reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of arch bridges and relates to a segmented splicing structure of an arch rib of a large-span steel tube arch bridge and a construction method thereof. Background Art

[0002] An arch bridge refers to a bridge in a vertical plane that uses an arch as the main load-bearing component of the structure. If a surface is formed in the powder layer in the container that can withstand the pressure of the powder above without transmitting this pressure to the bottom, this surface is called an arch bridge. An arch bridge is an upward convex surface, and its maximum principal stress acts along the arch bridge surface, and the minimum principal stress along the vertical direction of the arch bridge is zero. The formation and collapse of the arch bridge may occur repeatedly during the powder outflow process under the action of gravity. This kind of arch bridge is called a dynamic arch bridge.

[0003] After searching, the invention with the announcement number CN111625893A discloses a method for dynamically correcting the deviation of the arch rib inclined buckle hanging splicing. Feedback control can be performed based on the displacement value measured by the current splicing segment. In the case of deviation between the measured value and the theoretical value, the proposed arch rib inclined buckle hanging splicing method can be re-optimized through the dynamic feedback system to obtain a new arch rib segment buckle displacement control value, thereby efficiently guiding the construction, avoiding the traditional method of frequently tensioning and adjusting the cable to correct the deviation value, overcoming the delay in construction period and fatigue loss of temporary buckle cables caused by repeated adjustment of the buckle cables in the traditional method, and reducing the probability of catastrophic consequences due to the breakage of temporary buckle cables; while ensuring that the displacement after the completion of the bridge meets the target requirements, it also greatly reduces the delay in construction period caused by adjusting the displacement of each segment, and its economic benefits are significant.

[0004] Although the arch ribs are pulled by cables, they will still sink under the action of gravity, causing the error to gradually increase when they are finally closed, and there will be a deviation at both ends. The current method is to calculate by experienced experts to increase the position of the cable in advance to offset the influence of gravity, but the calculation is large. Summary of the invention

[0005] In view of this, the present invention aims to solve the problem that although the arch ribs are pulled by cables, they will still sink under the action of gravity, resulting in a gradual increase in the error when they are finally closed, and there will be a deviation at both ends. The current method is to calculate by experienced experts to increase the position of the cable pulling in advance to offset the influence of gravity, but the calculation amount is large. A large-span steel tube arch bridge arch rib segmented splicing structure and a construction method thereof are provided.

[0006] To achieve the above object, the present invention provides the following technical solution: a segmented splicing structure of arch ribs of a long-span steel tube arch bridge, comprising:

[0007] A plurality of arch ribs, the arch ribs comprising two upper spliced ​​arches and two lower spliced ​​arches, the two upper spliced ​​arches are located above the two lower spliced ​​arches, the two upper spliced ​​arches are arranged in parallel, the two lower spliced ​​arches are arranged in parallel, a first vertical support plate and a second vertical support plate are fixedly connected between the upper spliced ​​arches and the lower spliced ​​arches, and the first vertical support plate and the second vertical support plate are used to connect the upper spliced ​​arches and the lower spliced ​​arches;

[0008] A first connecting assembly, the first connecting assembly is arranged between the first vertical support plate and the second vertical support plate for connecting two arch ribs;

[0009] A first cross brace plate and a second cross brace plate are fixedly connected between the two upper splicing arches, and the first cross brace plate and the second cross brace plate are used to connect the two upper splicing arches;

[0010] The second connecting assembly is arranged between the first cross brace plate and the second cross brace plate and is used to connect the two arch ribs.

[0011] Furthermore, the first connecting component includes a second card slot opened on one side of the first vertical support plate, a first card block is fixedly connected to one side of the second vertical support plate, the first card block is used in conjunction with the second card slot, two symmetrically arranged first card slots are opened on one side of the second vertical support plate, two symmetrically arranged second card blocks are fixedly connected to one side of the first vertical support plate, and the second card block is used in conjunction with the first card slot.

[0012] Furthermore, first arc-shaped grooves are formed on both sides of the top of the second slot, and second arc-shaped grooves are formed on both sides of the bottom of the first slot.

[0013] Furthermore, the second connecting component includes a connecting block fixedly connected to one side of the second cross brace plate, one end of the connecting block is fixedly connected to a rectangular plate, a second rectangular groove is provided on the top of the first cross brace plate for use with the rectangular plate, and a rectangular notch is provided on one side of the first cross brace plate for use with the connecting block.

[0014] Furthermore, a first circular groove is provided at both ends of the first cross brace plate, an insertion rod is slidably inserted into the interior of the first circular groove, a compression spring is fixedly connected between one end of the insertion rod and the first circular groove, a second clamping circular groove is provided at the top of the insertion rod, and a first clamping circular groove is provided on one side of the insertion rod.

[0015] Furthermore, a strip vertical groove is provided at the bottom of the first cross brace plate, a first rectangular groove is provided inside the first cross brace plate, the bottom of the first rectangular groove is connected with the top of the strip vertical groove, a same pressure plate is slidably connected between the inner walls on both sides of the first rectangular groove, two symmetrically arranged first springs are fixedly connected between the top of the pressure plate and the top inner wall of the first rectangular groove, a pushing block is fixedly connected to the middle position of the bottom of the pressure plate, the bottom of the pushing block passes through the strip vertical groove, and two symmetrically arranged first clamping round rods are fixedly connected to the bottom of the pressure plate, and the first clamping round rods are used in conjunction with the second clamping circular groove.

[0016] Furthermore, two symmetrically arranged second circular grooves are provided inside the first cross brace plate, and the two second circular grooves are respectively located on both sides of the second rectangular groove and are connected to the second rectangular groove. A third rectangular groove is provided inside the first cross brace plate, and a strip plate is slidably connected to the bottom inner wall of the third rectangular groove, and one side of the strip plate is fixedly connected to two symmetrically arranged second clamping round rods, and the second clamping round rods are used in conjunction with the first clamping circular groove, and two symmetrically arranged tension springs are fixedly connected between one side of the strip plate and the inner wall of one side of the third rectangular groove.

[0017] Furthermore, two symmetrically arranged rectangular holes are opened inside the first cross brace plate, and the rectangular holes are used to connect the second circular groove and the third rectangular groove. A sliding plate is slidably connected to the bottom inner wall of the rectangular hole, and a second spring is fixedly connected between one side of the sliding plate and one side inner wall of the rectangular hole. One side of the sliding plate is fixedly connected to a limiting plate, which extends to the inside of the third rectangular groove and conflicts with one side of the strip plate.

[0018] A construction method for a segmented splicing structure of an arch rib of a long-span steel tube arch bridge specifically comprises the following steps:

[0019] S1. The arch ribs are formed into a steel frame in the factory and transported to the site for assembly;

[0020] S2. The arch ribs are symmetrically suspended on both sides. The arch ribs close to the shore are hoisted first, and connected and fixed with the embedded steel in the arch seat by flange bolts. The hoisting points are first released, the anchor cables are installed and tensioned, and the concrete part of the arch seat is poured;

[0021] S3. Then hoist the middle section arch ribs one by one, use the connection components to temporarily hang the buckles, use concrete pouring to complete the joints, and after the concrete curing is completed, release the anchor cables.

[0022] The beneficial effects of the present invention are:

[0023] 1. The present invention discloses a segmented splicing structure of the arch rib of a large-span steel tube arch bridge and a construction method thereof, wherein the first clamping block is arranged to enter the interior of the second clamping slot, and the second clamping block is arranged to enter the interior of the first clamping slot, thereby ensuring the positioning between the second vertical support plate and the first vertical support plate.

[0024] 2. The present invention discloses a segmented splicing structure of the arch ribs of a large-span steel tube arch bridge and a construction method thereof. By retracting the push block, the first clamping round rod is moved out from the inside of the second clamping round groove, the braking state of the insertion rod is released, and the insertion rod moves laterally under the elastic force of the compression spring to the inside of the second round groove, thereby realizing the connection between the rectangular plate and the first cross brace plate.

[0025] 3. The present invention discloses a segmented splicing structure of the arch rib of a large-span steel tube arch bridge and a construction method thereof. The two ends of the insertion rod push the sliding plate to move horizontally, and the second clamping round rod enters the interior of the two first clamping round grooves to brake the insertion rod again to prevent the device from loosening, thereby achieving pre-fixation, improving the lifting accuracy, and reducing the workload of workers.

[0026] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the following examination and study, or can be taught from the practice of the present invention. The objectives and other advantages of the present invention can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention will be described in detail below in conjunction with the accompanying drawings, wherein:

[0028] Figure 1 A three-dimensional structural schematic diagram of a segmented splicing structure of a long-span steel tube arch bridge arch rib and a construction method thereof proposed by the present invention;

[0029] Figure 2 This is a schematic diagram of the main structure of a long-span steel tube arch bridge arch rib segmented splicing structure and a construction method thereof proposed by the present invention;

[0030] Figure 3 A schematic diagram of a three-dimensional cross-sectional structure of an arch rib in a segmented splicing structure of an arch rib of a large-span steel tube arch bridge and a construction method thereof proposed by the present invention;

[0031] Figure 4 It is a schematic diagram of the exploded structure of the second vertical bracing plate and the first vertical bracing plate in a segmented splicing structure of the arch rib of a large-span steel tube arch bridge and a construction method thereof proposed by the present invention;

[0032] Figure 5 A schematic diagram of the three-dimensional structure of the second vertical bracing plate and the first vertical bracing plate in a segmented splicing structure of the arch rib of a large-span steel tube arch bridge and a construction method thereof proposed by the present invention;

[0033] Figure 6 A schematic diagram of the three-dimensional structure of a first cross brace plate and a second cross brace plate in a segmented splicing structure of an arch rib of a large-span steel tube arch bridge and a construction method thereof proposed by the present invention;

[0034] Figure 7 A schematic diagram of a three-dimensional cross-sectional structure of a rectangular plate and a plug-in rod in a segmented splicing structure of an arch rib of a large-span steel tube arch bridge and a construction method thereof proposed by the present invention;

[0035] Figure 8It is a schematic diagram of the exploded structure of rectangular plates and inserted rods in a segmented splicing structure of arch ribs of a large-span steel tube arch bridge and a construction method thereof proposed by the present invention;

[0036] Fig. 9 A three-dimensional cross-sectional structural schematic diagram of a first cross brace plate in a segmented splicing structure of an arch rib of a large-span steel tube arch bridge and a construction method thereof proposed by the present invention;

[0037] Fig.10 The present invention provides a schematic diagram of the exploded structure of the first cross brace plate and the sliding plate in a segmented splicing structure of the arch rib of a large-span steel tube arch bridge and a construction method thereof.

[0038] In the figure: 5, upper splicing arch; 9, first vertical support plate; 10, lower splicing arch; 11, second vertical support plate; 12, first horizontal support plate; 13, second horizontal support plate; 14, first arc groove; 15, first clamping block; 16, first clamping groove; 17, second clamping block; 18, second clamping groove; 20, second arc groove; 21, connecting block; 22, rectangular plate; 24, plug rod; 25, pressure plate; 26, first rectangular groove; 27, first spring ; 28. Push block; 29. ​​Compression spring; 30. First snap-fit ​​circular groove; 31. First circular groove; 32. Strip vertical groove; 33. Second snap-fit ​​circular groove; 34. First snap-fit ​​round rod; 35. Second snap-fit ​​round rod; 36. Strip plate; 37. Tension spring; 38. Rectangular notch; 39. Second rectangular groove; 40. Second circular groove; 41. Third rectangular groove; 42. Limiting plate; 43. Sliding plate; 44. Second spring; 45. Rectangular hole. DETAILED DESCRIPTION

[0039] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the illustrations provided in the following embodiments only illustrate the basic concept of the present invention in a schematic manner, and the following embodiments and features in the embodiments can be combined with each other without conflict.

[0040] Among them, the drawings are only used for illustrative explanations, and they only represent schematic diagrams rather than actual pictures, and should not be understood as limitations on the present invention. In order to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of actual products. For those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.

[0041] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "front", "rear", etc. indicate the orientation or position relationship, they are based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the terms describing the position relationship in the drawings are only used for illustrative purposes and cannot be understood as limiting the present invention. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0042] Reference Figure 1-10 , a long-span steel tube arch bridge arch rib segmented splicing structure, comprising:

[0043] A plurality of arch ribs, the arch ribs comprising two upper splicing arches 5 and two lower splicing arches 10, the two upper splicing arches 5 are located above the two lower splicing arches 10, the two upper splicing arches 5 are arranged in parallel, the two lower splicing arches 10 are arranged in parallel, the first vertical support plate 9 and the second vertical support plate 11 are fixedly connected between the upper splicing arches 5 and the lower splicing arches 10, and the first vertical support plate 9 and the second vertical support plate 11 are used to connect the upper splicing arches 5 and the lower splicing arches 10;

[0044] The first connecting component is arranged between the first vertical support plate 9 and the second vertical support plate 11 for connecting the two arch ribs. The first connecting component includes a second card slot 18 opened on one side of the first vertical support plate 9, a first card block 15 is fixedly connected to one side of the second vertical support plate 11, and the first card block 15 is used in conjunction with the second card slot 18. Two symmetrically arranged first card slots 16 are opened on one side of the second vertical support plate 11, and two symmetrically arranged second card blocks 17 are fixedly connected to one side of the first vertical support plate 9. The second card block 17 and the first card slot 16 are connected to the first card slot 16. In cooperation, both sides of the top of the second card slot 18 are provided with first arc grooves 14, and both sides of the bottom of the first card slot 16 are provided with second arc grooves 20. When hoisting between multiple arch ribs, the arch rib close to the center is hoisted from top to bottom. At this time, the first card block 15 enters the interior of the second card slot 18 to complete the positioning, and the second card block 17 enters the interior of the first card slot 16 to ensure the positioning between the second vertical support plate 11 and the first vertical support plate 9. The provision of the first arc groove 14 and the second arc groove 20 can help complete the positioning process;

[0045] A first cross brace plate 12 and a second cross brace plate 13 are fixedly connected between the two upper splicing arches 5, and the first cross brace plate 12 and the second cross brace plate 13 are used to connect the two upper splicing arches 5;

[0046] The second connecting component is arranged between the first cross brace plate 12 and the second cross brace plate 13 and is used to connect the two arch ribs. The second connecting component includes a connecting block 21 fixedly connected to one side of the second cross brace plate 13, one end of the connecting block 21 is fixedly connected to a rectangular plate 22, the top of the first cross brace plate 12 is provided with a second rectangular groove 39 used in conjunction with the rectangular plate 22, one side of the first cross brace plate 12 is provided with a rectangular notch 38 used in conjunction with the connecting block 21, both ends of the first cross brace plate 12 are provided with a first circular groove 31, the interior of the first circular groove 31 is slidably penetrated by a plug rod 24, one end of the plug rod 24 is fixedly connected to the first circular groove 31 with the same compression spring 29, the top of the plug rod 24 is provided with a second clamping circular groove 33, and one side of the plug rod 24 A first clamping circular groove 30 is provided, a strip vertical groove 32 is provided at the bottom of the first cross bracing plate 12, a first rectangular groove 26 is provided inside the first cross bracing plate 12, the bottom of the first rectangular groove 26 is communicated with the top of the strip vertical groove 32, a same pressing plate 25 is slidably connected between the inner walls on both sides of the first rectangular groove 26, two first springs 27 symmetrically arranged are fixedly connected between the top of the pressing plate 25 and the top inner wall of the first rectangular groove 26, a pushing block 28 is fixedly connected to the middle position of the bottom of the pressing plate 25, the bottom of the pushing block 28 passes through the strip vertical groove 32, two first clamping round rods 34 symmetrically arranged are fixedly connected to the bottom of the pressing plate 25, the first clamping round rod 34 is used in conjunction with the second clamping circular groove 33, and the second cross bracing plate 13 moves to the first cross On one side of the support plate 12, the connecting block 21 enters the interior of the rectangular notch 38, and the rectangular plate 22 enters the interior of the second rectangular groove 39. When the bottom of the rectangular plate 22 conflicts with the bottom inner wall of the second rectangular groove 39, the pushing block 28 is retracted, and the pushing block 28 pushes the pressure plate 25 to move upward. The pressure plate 25 squeezes the first spring 27 and drives the two first clamping round rods 34 to move upward. At this time, the first clamping round rod 34 moves out from the interior of the second clamping circular groove 33, releasing the braking state of the insertion rod 24. The insertion rod 24 moves laterally under the elastic force of the compression spring 29 and moves to the interior of the second circular groove 40. The interior of the first cross brace plate 12 is provided with two symmetrically arranged second circular grooves 40, and the two second circular grooves 40 are respectively located on both sides of the second rectangular groove 39 and are connected to the second rectangular groove 39. The grooves 39 are connected, a third rectangular groove 41 is provided inside the first cross brace 12, a strip plate 36 is slidably connected to the bottom inner wall of the third rectangular groove 41, one side of the strip plate 36 is fixedly connected with two symmetrically arranged second clamping round rods 35, the second clamping round rods 35 are used in conjunction with the first clamping round groove 30, two symmetrically arranged tension springs 37 are fixedly connected between one side of the strip plate 36 and the inner wall of one side of the third rectangular groove 41, two symmetrically arranged rectangular holes 45 are provided inside the first cross brace 12, the rectangular holes 45 are used to connect the second round groove 40 and the third rectangular groove 41, a sliding plate 43 is slidably connected to the bottom inner wall of the rectangular hole 45, and a second spring 44 is fixedly connected between one side of the sliding plate 43 and the inner wall of one side of the rectangular hole 45,One side of the sliding plate 43 is fixedly connected to the limit plate 42, which extends to the inside of the third rectangular groove 41 and conflicts with one side of the strip plate 36, and the two ends of the insertion rod 24 will push the sliding plate 43 to move horizontally, and the sliding plate 43 squeezes the second spring 44 and drives the limit plate 42 to move horizontally. The limit plate 42 no longer conflicts with the strip plate 36. At this time, the strip plate 36 moves horizontally under the tension of the tension spring 37, and the strip plate 36 drives the two second clamping round rods 35 to move horizontally. The second clamping round rods 35 enter the inside of the two first clamping round grooves 30, and brake the insertion rod 24 again to prevent the device from loosening, thereby achieving pre-fixation, improving the hoisting accuracy, and reducing the workload of workers.

[0047] A construction method for a long-span steel tube arch bridge arch rib segmented splicing structure specifically comprises the following steps:

[0048] S1. The arch ribs are formed into a steel frame in the factory and transported to the site for assembly;

[0049] S2. The arch ribs are symmetrically suspended on both sides. The arch ribs close to the shore are hoisted first, and connected and fixed with the embedded steel in the arch seat by flange bolts. The hoisting points are first released, the anchor cables are installed and tensioned, and the concrete part of the arch seat is poured;

[0050] S3. Then hoist the middle section arch ribs one by one, use the connection components to temporarily hang the buckles, use concrete pouring to complete the joints, and after the concrete curing is completed, release the anchor cables.

[0051] Working principle: When hoisting between multiple arch ribs, the arch rib close to the center is hoisted from top to bottom. At this time, the first clamping block 15 enters the inside of the second clamping groove 18 to complete the positioning, and the second clamping block 17 enters the inside of the first clamping groove 16 to ensure the positioning between the second vertical support plate 11 and the first vertical support plate 9. The first arc groove 14 and the second arc groove 20 can help complete the positioning process;

[0052] And the second cross brace 13 moves to one side of the first cross brace 12, at this time, the connecting block 21 enters the inside of the rectangular notch 38, and the rectangular plate 22 enters the inside of the second rectangular groove 39. When the bottom of the rectangular plate 22 contacts the bottom inner wall of the second rectangular groove 39, the pushing block 28 is retracted, and the pushing block 28 pushes the pressure plate 25 to move upward. The pressure plate 25 squeezes the first spring 27 and drives the two first clamping round rods 34 to move upward. At this time, the first clamping round rod 34 moves out from the inside of the second clamping round groove 33, releasing the braking state of the insertion rod 24. The insertion rod 24 moves laterally under the elastic force of the compression spring 29 and moves to the inside of the second round groove 40;

[0053] And the two ends of the insertion rod 24 will push the sliding plate 43 to move laterally, the sliding plate 43 squeezes the second spring 44 and drives the limit plate 42 to move laterally, the limit plate 42 no longer interferes with the strip plate 36, at this time the strip plate 36 moves laterally under the tension of the tension spring 37, the strip plate 36 drives the two second clamping round rods 35 to move laterally, the second clamping round rods 35 enter the interior of the two first clamping circular grooves 30, and brakes the insertion rod 24 again to prevent the device from loosening, thereby achieving pre-fixation, and can improve the lifting accuracy and reduce the workload of workers.

[0054] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution, which should be included in the scope of the claims of the present invention.

Claims

1. A long-span steel tube arch bridge arch rib segmented splicing structure, characterized in that: include: A plurality of arch ribs, the arch ribs comprising two upper spliced ​​arches (5) and two lower spliced ​​arches (10), the two upper spliced ​​arches (5) being located above the two lower spliced ​​arches (10), the two upper spliced ​​arches (5) being arranged in parallel, the two lower spliced ​​arches (10) being arranged in parallel, a first vertical support plate (9) and a second vertical support plate (11) being fixedly connected between the upper spliced ​​arches (5) and the lower spliced ​​arches (10), the first vertical support plate (9) and the second vertical support plate (11) being used to connect the upper spliced ​​arches (5) and the lower spliced ​​arches (10); A first connecting assembly, the first connecting assembly being arranged between the first vertical support plate (9) and the second vertical support plate (11) and being used for connecting two arch ribs; A first cross brace plate (12) and a second cross brace plate (13) are fixedly connected between the two upper splicing arches (5), and the first cross brace plate (12) and the second cross brace plate (13) are used to connect the two upper splicing arches (5); A second connecting component is arranged between the first cross brace plate (12) and the second cross brace plate (13) and is used to connect two arch ribs.

2. The long-span steel tube arch bridge arch rib segmented splicing structure according to claim 1 is characterized in that: The first connecting assembly comprises a second clamping groove (18) provided on one side of the first vertical support plate (9); a first clamping block (15) is fixedly connected to one side of the second vertical support plate (11); the first clamping block (15) is used in conjunction with the second clamping groove (18); two first clamping grooves (16) are symmetrically arranged on one side of the second vertical support plate (11); two second clamping blocks (17) are fixedly connected to one side of the first vertical support plate (9); the second clamping block (17) is used in conjunction with the first clamping groove (16).

3. The long-span steel tube arch bridge arch rib segmented splicing structure according to claim 2 is characterized in that: The second clamping slot (18) has first arc-shaped slots (14) on both sides of the top, and the first clamping slot (16) has second arc-shaped slots (20) on both sides of the bottom.

4. The long-span steel tube arch bridge arch rib segmented splicing structure according to claim 1 is characterized in that: The second connecting assembly comprises a connecting block (21) fixedly connected to one side of the second cross brace plate (13), one end of the connecting block (21) being fixedly connected to a rectangular plate (22), a second rectangular groove (39) for use with the rectangular plate (22) being provided at the top of the first cross brace plate (12), and a rectangular notch (38) for use with the connecting block (21) being provided at one side of the first cross brace plate (12).

5. The long-span steel tube arch bridge arch rib segmented splicing structure according to claim 1 is characterized in that: Both ends of the first cross brace (12) are provided with a first circular groove (31), an insertion rod (24) is slidably inserted into the interior of the first circular groove (31), a compression spring (29) is fixedly connected between one end of the insertion rod (24) and the first circular groove (31), a second clamping circular groove (33) is provided at the top of the insertion rod (24), and a first clamping circular groove (30) is provided on one side of the insertion rod (24).

6. The long-span steel tube arch bridge arch rib segmented splicing structure according to claim 1 is characterized in that: A strip-shaped vertical groove (32) is provided at the bottom of the first cross brace (12), a first rectangular groove (26) is provided inside the first cross brace (12), the bottom of the first rectangular groove (26) is connected to the top of the strip-shaped vertical groove (32), a same pressing plate (25) is slidably connected between the inner walls on both sides of the first rectangular groove (26), two symmetrically arranged first springs (27) are fixedly connected between the top of the pressing plate (25) and the inner wall of the top of the first rectangular groove (26), a pushing block (28) is fixedly connected to the middle position of the bottom of the pressing plate (25), the bottom of the pushing block (28) passes through the strip-shaped vertical groove (32), and two symmetrically arranged first clamping round rods (34) are fixedly connected to the bottom of the pressing plate (25), and the first clamping round rods (34) are used in conjunction with the second clamping round groove (33).

7. The long-span steel tube arch bridge arch rib segmented splicing structure according to claim 1 is characterized in that: Two symmetrically arranged second circular grooves (40) are provided inside the first cross bracing plate (12), and the two second circular grooves (40) are respectively located on both sides of the second rectangular groove (39) and are connected to the second rectangular groove (39). A third rectangular groove (41) is provided inside the first cross bracing plate (12), and a strip plate (36) is slidably connected to the bottom inner wall of the third rectangular groove (41), and two symmetrically arranged second clamping round rods (35) are fixedly connected to one side of the strip plate (36), and the second clamping round rods (35) are used in conjunction with the first clamping circular groove (30), and two symmetrically arranged tension springs (37) are fixedly connected between one side of the strip plate (36) and the inner wall of one side of the third rectangular groove (41).

8. The long-span steel tube arch bridge arch rib segmented splicing structure according to claim 1 is characterized in that: Two symmetrically arranged rectangular holes (45) are provided inside the first cross brace plate (12), the rectangular holes (45) being used to connect the second circular groove (40) and the third rectangular groove (41), a sliding plate (43) being slidably connected to the inner wall of the bottom of the rectangular hole (45), a second spring (44) being fixedly connected between one side of the sliding plate (43) and the inner wall of one side of the rectangular hole (45), a limiting plate (42) being fixedly connected to one side of the sliding plate (43), the limiting plate (42) extending into the interior of the third rectangular groove (41) and abutting against one side of the strip plate (36).

9. A construction method for a long-span steel tube arch bridge arch rib segmented splicing structure according to any one of claims 1 to 8, characterized in that: The specific steps include: S1. The arch ribs are formed into a steel frame in the factory and transported to the site for assembly; S2. The arch ribs are symmetrically suspended on both sides. The arch ribs close to the shore are hoisted first, and connected and fixed with the embedded steel in the arch seat by flange bolts. The hoisting points are first released, the anchor cables are installed and tensioned, and the concrete part of the arch seat is poured; S3. Then hoist the middle section arch ribs one by one, use the connection components to temporarily hang the buckles, use concrete pouring to complete the joints, and after the concrete curing is completed, release the anchor cables.