Foundation settlement treatment process

The double-layer support system for reinforcement and stabilization layers is formed through the drilling and grouting process, which solves the problem of poor foundation settlement management effect in the prior art, and significantly improves the bearing capacity and stability of the foundation.

CN118880853AInactive Publication Date: 2024-11-01山东隆达伟业地基加固技术有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411280397.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing foundation settlement treatment methods are mainly used to improve foundation stability through concrete pile foundations, but the effect is not significant enough to effectively solve the problems of building inclination and cracking caused by uneven settlement.

Method used

The drilling process is used to drill reinforcement and stabilization holes on the foundation, and slurry is injected into a reinforcement layer and a stabilization layer respectively. The bearing capacity and stability of the foundation are improved through a double-layer support system of the reinforcement layer and the stabilization layer.

Benefits of technology

The plate-like or root-like structure formed by grouting makes the soil compressed and tightly squeezed, increasing the stability of the foundation, and forming a lifting layer through the stabilizing holes, which significantly improves the reinforcement effect of the foundation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880853A_ABST
    Figure CN118880853A_ABST
Patent Text Reader

Abstract

According to the technical scheme, the foundation settlement treatment process is characterized by comprising the following steps that S01, drilling is conducted, drilled holes are divided into two types, namely reinforcing holes and stabilizing holes, the stabilizing holes penetrate into a bearing stratum of a foundation, and the depth of the reinforcing holes is smaller than that of the stabilizing holes; s02, preparing slurry; s03, grouting is conducted, specifically, grout is injected into the reinforcing holes and the stabilizing holes, and the grouting pressure of the stabilizing holes is controlled to be larger than that of the reinforcing holes; s04, hole sealing is conducted; the reinforcing holes are grouted, so that grout can enter an original foundation to form a reinforcing layer, the bearing capacity of the foundation is improved, through grouting of the reinforcing layer, a plate-shaped or root-shaped structure is formed due to grouting, soil in a filling area is pressed and compacted, the stability is improved, and due to the fact that the stabilizing holes penetrate into a bearing layer, the stability of the foundation is improved. And the stable layer formed by grouting can also be used as a bearing layer for reinforcing and lifting the foundation, so that a double-layer supporting system of the reinforcing layer and the stable layer is formed, and the reinforcing effect of the foundation is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of foundation treatment, and more specifically, to a foundation settlement treatment process. Background Art

[0002] The foundation refers to the soil or rock that supports the base of a building. The soil layers that serve as the foundation of a building are divided into rock, gravel, silt, clay and artificial fill.

[0003] A subsidence foundation refers to the subsidence of the foundation surface caused by the compaction of the foundation soil layer under the action of additional stress. Excessive subsidence, especially uneven subsidence, can cause the building to tilt, crack, and become unusable. For a subsidence foundation, the existing treatment method is often to drill pile holes on the foundation, and then pour concrete in the pile holes to form a pile foundation, and to improve the stability of the foundation through the concrete pile foundation. However, the existing treatment method for a subsidence foundation mainly transfers the force of the building to a more stable concrete pile foundation extending into the ground, which has little effect on improving the stability of the foundation itself. Summary of the invention

[0004] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a foundation settlement control process, which allows grouting of reinforcement holes to allow slurry to enter the original foundation to form a reinforcement layer, thereby improving the bearing capacity of the foundation. The grouting of the reinforcement layer will form a plate-like or root-like structure, which will cause the soil in the grouting area to be compressed and compacted to increase stability. Moreover, because the stabilization holes penetrate deep into the bearing layer, the stabilization layer formed by grouting can also serve as the bearing layer for foundation reinforcement and lifting, thereby forming a double-layer support system of reinforcement layer and stabilization layer, thereby improving the reinforcement effect of the foundation.

[0005] To achieve the above object, the present invention provides the following technical solution: a foundation settlement control process, comprising the following steps: S01, drilling, drilling holes on the foundation by means of a drilling rig, the drilled holes are divided into two types, namely reinforcement holes and stabilization holes, the reinforcement holes and stabilization holes have different drilling depths, the stabilization holes go deep into the foundation bearing layer, and the reinforcement holes are deeper than the stabilization holes; S02, preparing slurry; S03, grouting, injecting slurry into the reinforcement hole and the stabilization hole respectively, and controlling the grouting pressure of the stabilization hole to be greater than the grouting pressure of the reinforcement hole; S04. Seal the holes, and use slurry to seal and smooth the openings of the reinforcement holes and stabilization holes.

[0006] The present invention is further configured as follows: the drilling depth of the reinforcement hole is 10 m, and the drilling depth of the stabilization hole is 12 m.

[0007] The present invention is further configured as follows: in step S01, the holes drilled in the foundation include a plurality of rows of drill holes arranged in a transverse direction, a plurality of rows of drill holes arranged in a longitudinal direction, and the plurality of rows of drill holes are respectively configured as staggered rows and reinforced rows; The staggered rows include a number of reinforcement holes and stabilization holes staggered along the transverse direction, and the reinforcement rows include a number of reinforcement holes arranged along the transverse direction.

[0008] The present invention is further configured as follows: the distance between adjacent reinforcement holes and stabilization holes in the staggered rows is set to 4m, and the distance between two adjacent reinforcement holes in the reinforcement row is set to 4m.

[0009] The present invention is further configured as follows: the reinforcement rows and the staggered rows are arranged staggered along the longitudinal direction, and the distance between adjacent reinforcement rows and staggered rows is set to 4m.

[0010] The present invention is further configured such that any reinforcement hole of a reinforcement row is located between adjacent reinforcement holes and stabilization holes of a staggered row in the transverse direction.

[0011] The present invention is further configured as follows: the diameters of the reinforcement holes and the stabilization holes are set to 42 mm.

[0012] The present invention is further configured as follows: the slurry is configured as A and C non-shrinkage double slurries, and the ratio thereof is 1:0.5-1.3.

[0013] The present invention is further configured as follows: the grouting pressure of the reinforcement hole is 0.3-0.5 MPa, and the grouting pressure gradually increases with the increase of the grouting height.

[0014] The present invention is further configured as follows: the grouting pressure of the stabilizing hole is 0.5-0.8 MPa, and the grouting pressure gradually increases with the increase of the grouting height.

[0015] In summary, the present invention has the following beneficial effects compared with the prior art: the present invention performs grouting on the reinforcement holes so that the slurry can enter into the original foundation to form a reinforcement layer, thereby improving the bearing capacity of the foundation; and through the grouting of the reinforcement layer, a plate-like or root-like structure is formed due to the grouting, so that the soil in the grouting area is compressed and compacted to increase stability; and because the stabilization holes penetrate deep into the bearing layer, the stabilization layer formed by grouting can also serve as the bearing layer for foundation reinforcement and lifting, thereby forming a double-layer support system of the reinforcement layer and the stabilization layer, thereby improving the reinforcement effect of the foundation. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 Schematic diagram of reinforcement holes and stabilization holes according to an embodiment. DETAILED DESCRIPTION

[0017] In order to enable those skilled in the art to better understand the technical solution of the present invention, the technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings of the present invention. Based on the embodiments in this application, other similar embodiments obtained by ordinary technicians in this field without making creative work should all fall within the scope of protection of this application. In addition, the directional words mentioned in the following embodiments, such as "up", "down", "left", "right", etc., are only reference to the directions of the accompanying drawings. Therefore, the directional words used are used to illustrate rather than limit the invention.

[0018] The present invention will be further described below in conjunction with the accompanying drawings and preferred embodiments.

[0019] Embodiment: A foundation settlement treatment process comprises the following steps: S01, drilling, drilling holes on the foundation by a drilling rig, the drilled holes are divided into two types, namely reinforcement holes and stabilization holes, the reinforcement holes and stabilization holes have different drilling depths, the stabilization holes go deep into the foundation bearing layer, and the reinforcement holes are deeper than the stabilization holes; Figure 1 As shown, label a is a reinforcement hole and label b is a stabilization hole.

[0020] S02, preparing slurry; S03, grouting, injecting slurry into the reinforcement hole and the stabilization hole respectively, and controlling the grouting pressure of the stabilization hole to be greater than the grouting pressure of the reinforcement hole; S04. Seal the holes, and use slurry to seal and smooth the openings of the reinforcement holes and stabilization holes.

[0021] By grouting the reinforcement holes, the slurry can enter the original foundation to form a reinforcement layer, thereby improving the bearing capacity of the foundation. By grouting the reinforcement layer, a plate-like or root-like structure will be formed, which will compress and compact the soil in the injection area to increase stability. In addition, because the stabilization holes penetrate deep into the bearing layer, the stabilization layer formed by grouting can also serve as the bearing layer for foundation reinforcement and lifting, thereby forming a double-layer support system of reinforcement layer and stabilization layer, thereby improving the reinforcement effect of the foundation.

[0022] Specifically, the drilling depth of the reinforcement hole is 10 m, and the drilling depth of the stabilization hole is 12 m.

[0023] In step S01, the holes drilled on the foundation include several rows of drill holes arranged in the transverse direction, multiple rows of drill holes are arranged in the longitudinal direction, and the multiple rows of drill holes are respectively arranged as staggered rows and reinforcement rows; the staggered rows include several reinforcement holes and stabilization holes staggered in the transverse direction, and the reinforcement rows are several reinforcement holes arranged in the transverse direction.

[0024] Specifically, the distance between adjacent reinforcement holes and stabilization holes in the staggered rows is set to 4m, and the distance between two adjacent reinforcement holes in the reinforcement row is set to 4m; the reinforcement rows and the staggered rows are staggered in the longitudinal direction, and the distance between adjacent reinforcement rows and staggered rows is set to 4m.

[0025] Specifically, any reinforcement hole of the reinforcement row is located between adjacent reinforcement holes and stabilization holes of the staggered row in the transverse direction. The diameter of the reinforcement holes and stabilization holes is set to 42 mm.

[0026] Specifically, the slurry is set to be A and C non-shrinkage double slurry, and the ratio thereof is 1:0.5-1.3.

[0027] Specifically, when the slurry is being stirred and mixed, rope ends, paper pieces and other debris are prevented from entering the mixer. The stirring and mixing time is not less than three minutes. The stirred slurry is filtered through a sieve and then enters the grouting machine for grouting.

[0028] Specifically, the grouting pressure of the reinforcement hole is 0.3-0.5MPa, and the grouting pressure gradually increases with the increase of the grouting height; the grouting pressure of the stabilization hole is 0.5-0.8MPa, and the grouting pressure gradually increases with the increase of the grouting height. The grouting process needs to be continuous and cannot be terminated midway.

[0029] During the grouting process, if there is a sudden rise or drop in pressure or slurry overflow, stop the grouting action in time, find out the cause of the problem and solve it, and then grout again. When the problem is difficult to solve, shift the drilling position or drill an inclined hole for grouting.

[0030] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.

Claims

1. A foundation settlement control process, characterized in that: The following steps are involved: S01, drilling, drilling holes on the foundation by means of a drilling rig, the drilled holes are divided into two types, namely reinforcement holes and stabilization holes, the reinforcement holes and stabilization holes have different drilling depths, the stabilization holes go deep into the foundation bearing layer, and the reinforcement holes are deeper than the stabilization holes; S02, preparing slurry; S03, grouting, injecting slurry into the reinforcement hole and the stabilization hole respectively, and controlling the grouting pressure of the stabilization hole to be greater than the grouting pressure of the reinforcement hole; S04. Seal the holes, and use slurry to seal and smooth the openings of the reinforcement holes and stabilization holes.

2. A foundation settlement treatment process according to claim 1, characterized in that: The drilling depth of the reinforcement hole is 10m, and the drilling depth of the stabilization hole is 12m.

3. A foundation settlement treatment process according to claim 2, characterized in that: In step S01, the holes drilled in the foundation include a plurality of rows of drill holes arranged in a transverse direction, a plurality of rows of drill holes arranged in a longitudinal direction, and the plurality of rows of drill holes are respectively arranged as staggered rows and reinforced rows; The staggered rows include a number of reinforcement holes and stabilization holes staggered along the transverse direction, and the reinforcement rows include a number of reinforcement holes arranged along the transverse direction.

4. A foundation settlement treatment process according to claim 3, characterized in that: The distance between adjacent reinforcement holes and stabilization holes in the staggered rows is set to 4m, and the distance between two adjacent reinforcement holes in the reinforcement row is set to 4m.

5. A foundation settlement treatment process according to claim 4, characterized in that: The reinforcement rows and the staggered rows are arranged alternately along the longitudinal direction, and the distance between adjacent reinforcement rows and staggered rows is set to 4m.

6. A foundation settlement treatment process according to claim 5, characterized in that: Any reinforcement hole of a reinforcement row is located between adjacent reinforcement holes and stabilization holes of a staggered row in the transverse direction.

7. A foundation settlement treatment process according to claim 6, characterized in that: The diameter of the reinforcement holes and the stabilization holes is set to 42 mm.

8. A foundation settlement treatment process according to claim 7, characterized in that: The slurry is set to be A and C non-shrinkage double slurry, and the ratio thereof is 1:0.5-1.

3.

9. A foundation settlement treatment process according to claim 8, characterized in that: The grouting pressure of the reinforcement hole is 0.3-0.5MPa, and the grouting pressure gradually increases with the increase of the grouting height.

10. A foundation settlement treatment process according to claim 9, characterized in that: The grouting pressure of the stabilizing hole is 0.5-0.8 MPa, and the grouting pressure gradually increases with the increase of the grouting height.