People and goods elevator foundation supporting device for basement roof and construction method of people and goods elevator foundation supporting device
By designing the basement rooftop support device for cargo elevators, and using combined beams and hydraulic systems, the problem of transporting and installing steel support devices during construction is solved, the construction efficiency and safety are improved, and the support process of basement rooftops is simplified.
Patent Information
- Application Number
- CN202410535915.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-30
- Publication Date
- 2024-11-01
AI Technical Summary
During construction, due to the large weight and long height, the steel support device is difficult to transport and install, and the internal space of the basement is small, resulting in low construction efficiency and easy basement damage.
A basic support device for the basement roof panel of a cargo elevator is designed, including the basement floor, support mechanism, lifting mechanism and drive mechanism. Through the combination of beams and screws, the stability and installation efficiency of steel beams are improved by using hydraulic systems and jacks to simplify steel. The splicing and disassembly of beams.
The rapid and safe installation and disassembly of steel beams is achieved, the construction efficiency is improved, the risk of damage to the basement structure is reduced, and the support process of the basement roof is simplified.
Smart Images

Figure CN118880928A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of basement top plate support, and in particular to a passenger and cargo elevator foundation support device for a basement top plate and a construction method thereof. Background Art
[0002] During the construction process, a construction elevator needs to be installed on the basement roof. Due to the large installation height, long service life, and frequent use during construction and decoration, in order to ensure the safety of the basement structure, the basement roof needs to be supported and reinforced to prevent deformation and damage to the basement roof. Steel support has the advantages of fast construction efficiency and easy disassembly and recycling, so it is widely used in basement roof support.
[0003] However, due to the heavy weight and length of the steel sections themselves, it is difficult to transport the steel sections to the basement. In addition, the internal construction space of the basement is small, making it difficult to use a crane to erect the steel sections. During the erection process, the steel sections are prone to contact and collide with the surface structure of the basement, causing damage to the basement.
[0004] Therefore, it is necessary to provide a new basement top plate passenger and cargo elevator foundation support device and a construction method thereof to solve the above-mentioned technical problems. Summary of the invention
[0005] The technical problem solved by the present invention is to provide a basement top plate passenger and freight elevator foundation support device and a construction method thereof which can accelerate the construction efficiency and have high safety.
[0006] In order to solve the above technical problems, the basement ceiling passenger and cargo elevator foundation support device provided by the present invention comprises: a basement floor, a construction elevator is placed on the surface of the basement floor, and a plurality of support mechanisms are placed on the surface of the basement floor, and a composite beam for providing support for the basement floor and the construction elevator is installed on the surface of the support mechanism; the composite beam comprises a first steel beam, a second steel beam and a rubber pad, the rubber pad for contacting the basement floor is placed on the surface of the first steel beam, the first steel beam and the second steel beam, and the adjacent second steel beams are fixedly connected by bolts, and a reinforcement mechanism for improving the movement stability of the first steel beam and the second steel beam is installed on the surface of the basement floor; a lifting mechanism, the lifting mechanism comprises a first jack , steel pipe, screw, extrusion plate, rubber sleeve, connecting pipe and second jack; a plurality of the first jacks for driving the first steel beam and the second steel beam to move up and down are installed on the surface of the supporting mechanism, and the extrusion plate is installed on the surface of the first jack; the steel pipes are installed on the side walls of the first steel beam and the second steel beam, and the screw for connecting adjacent steel pipes is installed at one end of some of the steel pipes; the bottom end of the supporting mechanism is rotatably connected to the second jack for supporting the first steel beam and the second steel beam, the first jack and the second jack are connected by the connecting pipe, and the elastic rubber sleeve is installed on the top of the second jack; a driving mechanism, the driving mechanism connects the first jack, the second jack and the supporting mechanism.
[0007] Preferably, the supporting mechanism includes a base, a fixed seat, a fixed shaft, rollers, a top plate and a third jack; the base is placed on the surface of the basement floor, and the fixed seat is installed on the surface of the base; a plurality of fixed shafts are equidistantly installed inside the fixed seat, and the side walls of the fixed shafts are rotatably connected to a plurality of rollers that facilitate the movement of the first steel beam and the second steel beam; a plurality of the third jacks are installed on one side of the fixed seat, and the top plate for pushing the first steel beam and the second steel beam to move upward is installed on the top of the third jack.
[0008] Preferably, the supporting mechanism further includes steel wedges and notches, a plurality of the notches are provided on one side of the fixing seat, the side walls of the notches are slidably connected to the steel wedges, and the steel wedges with trapezoidal side walls abut against the bottom surface of the second steel beam.
[0009] Preferably, the first steel beam and the second steel beam are both composed of a support plate, an I-beam and a reinforcement plate, the support plates are welded to both ends of the I-beam, and a plurality of reinforcement plates with trapezoidal side walls are welded at the connection between the support plate and the I-beam.
[0010] Preferably, the side wall of the I-beam is slidably connected to the steel pipe, and the rubber sleeve is engaged at the connection between the I-beam and the support plate.
[0011] Preferably, the reinforcement mechanism includes a support rod, a splint, a first connecting rod, a second connecting rod, a slide groove, a fixed rod and a fixed sleeve, and a plurality of the support rods are installed between adjacent basement floors, the support rods are slidably connected to the elastic splints, and the splints are fixed to the side walls of the support rods by bolts; the side walls of the reinforcement plates are provided with the slide grooves, the fixed rods are fixed to the inside of the slide grooves by the fixed sleeves, and the fixed rods are threadedly connected to the second connecting rods, the second connecting rods are threadedly connected to the first connecting rods, and the first connecting rods are rotatably connected to the splints.
[0012] Preferably, the driving mechanism includes an oil tank, an oil pump, an oil outlet pipe, an oil return pipe and a solenoid valve. The oil tank is placed inside the fixed seat, and a plurality of the oil pumps are installed inside the oil tank. The plurality of oil outlet pipes connect the oil pump, the first jack, the second jack and the third jack. The plurality of oil return pipes connect the oil tank, the first jack, the second jack and the third jack, and the solenoid valves are installed on the side walls of the oil outlet pipe and the oil return pipe.
[0013] Preferably, the first jack, the second jack and the third jack are all composed of a piston, an oil cylinder and a lifting rod, the oil outlet pipe and the oil return pipe are installed at the bottom end of the oil cylinder, and the piston and the lifting rod are slidably connected inside the oil cylinder, and the lifting rod is fixedly connected to the piston.
[0014] Preferably, a construction method for a passenger and cargo elevator foundation support for a basement top plate specifically comprises the following steps: Step 1: During construction, first install the support device in the lowest layer of the basement, place the base on the surface of the basement floor according to the design position, so that the center of the construction elevator and the center of the combined beam are located on the same straight line; place the first steel beam on the surface of the fixed seat, and the surface of the fixed seat has a plurality of rollers, the rollers are in contact with the first steel beam, and the movement of the first steel beam drives the rollers to rotate on the side walls of the fixed seat, while reducing the resistance of the first steel beam to the movement of the first steel beam on the surface of the fixed seat, so as to facilitate the change of the position of the first steel beam, so that the center of the first steel beam and the center of the construction elevator are located on the same straight line; Step 2: Pass multiple steel pipes through the first steel beam, and rotate one of the steel pipes at the same time, so that the steel pipe drives the screw to rotate and enter the interior of the other steel pipe, and the two steel pipes are spliced; open the first jack, and the first jack drives the extrusion plate to move upward, and the upward movement of the extrusion plate pushes the steel pipe and the first steel beam upward, so that the upward movement distance of the first steel beam is greater than the height of the second steel beam; when the height of the first steel beam is appropriate, rotate the second jack and open the second jack at the same time, so that the second jack pushes the rubber sleeve to contact the side wall of the first steel beam; open the connecting pipe, and under the compression of the weight of the first steel beam, the rubber sleeve is gradually compressed and deformed, and the hydraulic oil inside the first jack is compressed into the interior of the second jack, the first jack shrinks slightly, and the second jack is compressed. The second jack drives the rubber sleeve to rise slightly, increasing the squeezing force between the rubber sleeve and the first steel beam, and at the same time reducing part of the pressure on the first jack to share it with the second jack, and the first jack and the second jack are connected to each other, so that the pressure of the first steel beam on the first jack and the pressure on the second jack offset each other, thereby increasing the stability of the first steel beam when suspended in the air; similarly, the second steel beam is placed on one side of the fixing seat, the second steel beam is moved so that the second steel beam moves to align with the first steel beam, the connecting pipe is closed, the first jack is opened to make the first steel beam move upward, the second jack is removed, and the first steel beam is moved downward to contact the surface of the second steel beam, and the second steel beam is fixed to the first steel beam with bolts, and the other second steel beams are installed in the same way according to the above method; Step 3: As the second steel beam is gradually installed, the resistance to the upward movement of the first jack becomes greater and greater. When it is necessary to push the second steel beam upward, the third jack is opened, and the movement of the third jack and the first jack pushes the second steel beam upward, thereby reducing the resistance when the first jack is started; when the last piece of the second steel beam is installed, the first jack and the third jack push the steel beam upward, so that the rubber pad on the surface of the first steel beam squeezes the basement floor, and at the same time, the second jack is used to reinforce the side wall of the steel beam, and the steel wedge is used to fix the steel beam on the surface of the fixing seat; similarly, the steel beam is installed on the surface of the basement floor of the upper layer according to the above method. When the steel beam is installed, the construction elevator can be installed on the surface of the basement roof; Step 4: After the construction elevator is disassembled, disassemble the steel beams from top to bottom in sequence, open the third jack and the first jack, move the steel beam upward to squeeze the rubber pad, separate the second steel beam from the steel wedge, and facilitate taking out the steel wedge. Then disassemble the second steel beam and the first steel beam layer by layer from bottom to top.
[0015] Compared with the related art, the basement ceiling passenger and cargo elevator foundation support device and the construction method thereof provided by the present invention have the following beneficial effects: The present invention provides a basic support device for a passenger and freight elevator for a basement top plate and a construction method thereof. The basement floor surface support device is composed of the support mechanism, the first steel beam and a plurality of the second steel beams, so that it is convenient to move the components into the basement; the first steel beam is placed at a designed position on the surface of the support mechanism, a plurality of the steel pipes are passed through the first steel beam, and one of the steel pipes is rotated at the same time, so that the steel pipe drives the screw to rotate and enter the interior of the other steel pipe, and the two steel pipes are spliced; the first jack is opened, the first jack drives the extrusion plate to move upward, and the upward movement of the extrusion plate pushes the steel pipe and the first steel beam upward, so that the upward movement distance of the first steel beam is greater than the height of the second steel beam; when the height of the first steel beam is appropriate, the second jack is rotated and the second jack is opened at the same time, so that the second jack pushes the rubber sleeve to contact the side wall of the first steel beam; the connecting pipe is opened, and under the compression of the weight of the first steel beam, the rubber sleeve is gradually compressed and deformed, and the hydraulic oil inside the first jack is compressed. The first jack is compressed into the interior of the second jack, the first jack contracts slightly, and the second jack drives the rubber sleeve to rise slightly, thereby increasing the extrusion pressure between the rubber sleeve and the first steel beam, and at the same time reducing part of the pressure on the first jack to share it with the second jack, and the first jack and the second jack are connected to each other, so that the pressure of the first steel beam on the first jack and the pressure on the second jack offset each other, thereby increasing the stability of the first steel beam when suspended in the air; similarly, the second steel beam is placed on one side of the fixing seat, the second steel beam is moved so that the second steel beam moves to align with the first steel beam, the connecting pipe is closed, the first jack is opened to make the first steel beam move upward, the second jack is removed, and the first steel beam is moved downward to contact the surface of the second steel beam, and the second steel beam is fixed to the first steel beam with bolts, and the other second steel beams are installed according to the above method, so that the steel beams can be quickly assembled to support the basement floor, speed up the construction efficiency, and facilitate the installation of steel beams inside the basement. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1A schematic structural diagram of a basement ceiling passenger and cargo elevator foundation support device and a construction method thereof provided by the present invention; Figure 2 for Figure 1 The schematic diagram of composite beam splicing is shown; Figure 3 for Figure 2 An enlarged schematic diagram of the structure at A shown; Figure 4 for Figure 3 An enlarged schematic diagram of the structure at D shown; Figure 5 for Figure 1 An enlarged schematic diagram of the structure at B shown; Figure 6 for Figure 1 An enlarged schematic diagram of the structure at position C is shown; Figure 7 for Figure 3 Schematic diagram of composite beam structure shown; Figure 8 for Figure 3 A top view of the reinforcement mechanism structure shown; Fig. 9 for Figure 3 A top view of the support structure is shown.
[0017] Numbers in the figure: 1, basement floor, 2, construction elevator, 3, composite beam, 31, first steel beam, 32, second steel beam, 33, rubber pad, 34, support plate, 35, I-beam, 36, reinforcement plate, 4, reinforcement mechanism, 41, support rod, 42, clamping plate, 43, first connecting rod, 44, second connecting rod, 45, slide, 46, fixing rod, 47, fixing sleeve, 5, lifting mechanism, 51, first jack, 52, steel pipe, 53 , screw, 54, extrusion plate, 55, rubber sleeve, 56, connecting pipe, 57, second jack, 58, piston, 59, oil cylinder, 510, lifting rod, 6, supporting mechanism, 61, base, 62, fixed seat, 63, fixed shaft, 64, roller, 65, top plate, 66, third jack, 67, steel wedge, 68, notch, 7, driving mechanism, 71, oil tank, 72, oil pump, 73, oil outlet pipe, 74, oil return pipe, 75, solenoid valve. DETAILED DESCRIPTION
[0018] The present invention will be further described below in conjunction with the accompanying drawings and implementation modes.
[0019] See also Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 , Figure 7 , Figure 8 and Fig. 9 ,in Figure 1 A schematic structural diagram of a basement ceiling passenger and cargo elevator foundation support device and a construction method thereof provided by the present invention; Figure 2 for Figure 1 The schematic diagram of composite beam splicing is shown; Figure 3 for Figure 2 An enlarged schematic diagram of the structure at A shown; Figure 4 for Figure 3 An enlarged schematic diagram of the structure at D shown; Figure 5 for Figure 1 An enlarged schematic diagram of the structure at B shown; Figure 6 for Figure 1 An enlarged schematic diagram of the structure at position C is shown; Figure 7 for Figure 3 Schematic diagram of composite beam structure shown; Figure 8 for Figure 3 A top view of the reinforcement mechanism structure shown; Fig. 9 for Figure 3 The supporting mechanism structure is shown in the top view. The basement ceiling passenger and cargo elevator foundation supporting device comprises: a basement floor 1, a construction elevator 2 is placed on the surface of the basement floor 1, and a plurality of supporting mechanisms 6 are placed on the surface of the basement floor 1, and a composite beam 3 for providing support for the basement floor 1 and the construction elevator 2 is installed on the surface of the supporting mechanism 6; the composite beam 3 comprises a first steel beam 31, a second steel beam 32 and a rubber pad 33, the rubber pad 33 for contacting the basement floor 1 is placed on the surface of the first steel beam 31, and the rubber pads 33 between the first steel beam 31 and the second steel beam 32 and the adjacent ones are placed on the surface of the first steel beam 31 and the second steel beam 32. The second steel beams 32 are fixedly connected by bolts, so that the first steel beam 31 and the second steel beam 32 can provide support for the basement floor 1 after being combined; the first steel beam 31 and the second steel beam 32 are composed of a support plate 34, an I-beam 35 and a reinforcement plate 36. The support plates 34 are welded at both ends of the I-beam 35 to facilitate the mutual splicing of the support plates 34, and a plurality of reinforcement plates 36 with trapezoidal side walls are welded at the connection between the support plate 34 and the I-beam 35 to increase the firmness between the support plate 34 and the I-beam 35.
[0020] The support mechanism 6 includes a base 61, a fixed seat 62, a fixed shaft 63, a roller 64, a top plate 65 and a third jack 66. The base 61 is placed on the surface of the basement floor 1, and the fixed seat 62 is installed on the surface of the base 61; a plurality of fixed shafts 63 are installed equidistantly inside the fixed seat 62, and a plurality of rollers 64 are rotatably connected to the side walls of the fixed shafts 63 for facilitating the movement of the first steel beam 31 and the second steel beam 32; a plurality of third jacks 66 are installed on one side of the fixed seat 62, and a top plate 65 for pushing the third jack 66 is installed on the top of the third jack The first steel beam 31 and the second steel beam 32 move upwardly on the top plate 65; when the first steel beam 31 is placed on the surface of the fixing seat 62, a plurality of rollers 64 are provided on the surface of the fixing seat 62, and the rollers 64 are in contact with the first steel beam 31. The movement of the first steel beam 31 drives the rollers 64 to rotate on the side walls of the fixing seat 63, while reducing the resistance of the first steel beam 31 to the movement of the surface of the fixing seat 62, so as to facilitate changing the position of the first steel beam 31 so that the center of the first steel beam 31 and the center of the construction elevator 2 are located on the same straight line.
[0021] The surface of the basement floor 1 is installed with a reinforcement mechanism 4 for improving the movement stability of the first steel beam 31 and the second steel beam 32; the reinforcement mechanism 4 includes a support rod 41, a clamping plate 42, a first connecting rod 43, a second connecting rod 44, a slide 45, a fixing rod 46 and a fixing sleeve 47, and a plurality of the support rods 41 are installed between adjacent basement floors 1, the support rods 41 are slidably connected to the elastic clamping plates 42, and the clamping plates 42 are fixed to the side walls of the support rods 41 by bolts; the side walls of the reinforcement plates 36 are provided with the slide 45, the fixing rod 46 is fixed to the inside of the slide 45 by the fixing sleeve 47, and the fixing rod 46 is threadedly connected to the second connecting rod 44, the second connecting rod 44 is threadedly connected to the first connecting rod 43, and the first connecting rod 43 is rotatably connected to the clamping plate 42; after the first steel beam 31 and the second steel beam 32 are installed on the surface of the fixing seat 62, the fixing rods 46 are ... first connecting rod 43 is threadedly connected to the first connecting rod 43, and the first connecting rod 43 is rotatably connected to the clamping plate 42. The second connecting rod 44 is placed between the two reinforcing plates 36, the fixing rod 46 is passed through the sliding groove 45 and rotated into the interior of the second connecting rod 44, the fixing sleeve 47 is rotated on the side wall of the fixing rod 46, and the fixing sleeve 47 is threadedly connected to the fixing rod 46, and the reinforcing plate 36 is squeezed by rotating the fixing sleeve 47 to fix the second connecting rod 44 between the two reinforcing plates 36, and the first connecting rod 43 is rotated, the first connecting rod 43 is rotated out from the interior of the second connecting rod 44 and drives the clamping plate 42 to move, so that the support rod 41 enters the interior of the clamping plate 42, and the clamping plate 42 is fixed to the side wall of the support rod 41 with bolts, and when the first steel beam 31 and the second steel beam 32 move up and down, the first steel beam 31 and the second steel beam 32 drive the clamping plate 42 to slide up and down on the side wall of the support rod 41, thereby increasing the stability of the first steel beam 31 and the second steel beam 32 when moving.
[0022] The lifting mechanism 5 includes a first jack 51, a steel pipe 52, a screw 53, an extrusion plate 54, a rubber sleeve 55, a connecting pipe 56 and a second jack 57; a plurality of the first jacks 51 for driving the first steel beam 31 and the second steel beam 32 to move up and down are installed on the surface of the support mechanism 6, and the extrusion plate 54 is installed on the surface of the first jack 51; the steel pipes 52 are installed on the side walls of the first steel beam 31 and the second steel beam 32, and the screws 53 for connecting the adjacent steel pipes 52 are installed at one end of some of the steel pipes 52; the bottom end of the support mechanism 6 rotates The second jack 57 for supporting the first steel beam 31 and the second steel beam 32 is connected, the first jack 51 and the second jack 57 are connected through the connecting pipe 56, and the top of the second jack 57 is installed with the elastic rubber sleeve 55; when the first steel beam 31 is placed on the surface of the fixing seat 62; a plurality of the steel pipes 52 penetrate the first steel beam 31, and one of the steel pipes 52 is rotated at the same time, and the steel pipe 52 drives the screw 53 to rotate into the inside of the other steel pipe 52, and the two steel pipes 52 are spliced; open the first jack 5 1, the first jack 51 drives the extrusion plate 54 to move upward, and the upward movement of the extrusion plate 54 pushes the steel pipe 52 and the first steel beam 31 to move upward, so that the upward movement distance of the first steel beam 31 is greater than the height of the second steel beam 32; when the height of the first steel beam 31 is appropriate, the second jack 57 is rotated and the second jack 57 is opened at the same time, so that the second jack 57 pushes the rubber sleeve 55 to contact the side wall of the first steel beam 31; the connecting pipe 56 is opened, and under the weight compression of the first steel beam 31, the rubber sleeve 55 is gradually compressed and deformed, and the first jack The hydraulic oil inside the jack 51 is compressed and enters the inside of the second jack 57, the first jack 51 contracts slightly, and the second jack 57 drives the rubber sleeve 55 to rise slightly, thereby increasing the extrusion force between the rubber sleeve 55 and the first steel beam 31, and at the same time reducing part of the pressure on the first jack 51 to share it with the second jack 57, and the first jack 51 and the second jack 57 are connected to each other, so that the pressure of the first steel beam 31 on the first jack 51 and the pressure on the second jack 57 offset each other, thereby increasing the stability of the first steel beam 31 when suspended in the air;Similarly, the second steel beam 32 is placed on one side of the fixing seat 62, and the second steel beam 32 is moved so that the second steel beam 32 moves to align with the first steel beam 31, the connecting pipe 56 is closed, the first jack 51 is opened to make the first steel beam 31 move upward, and the second jack 57 is removed. After the first steel beam 31 moves downward to contact the surface of the second steel beam 32, the second steel beam 32 is fixed to the first steel beam 31 with bolts, and the other second steel beams 32 are installed in the same way. When the second steel beam 32 is installed, the support mechanism 6 also includes a steel wedge 61 and a notch 62. A plurality of notches 62 are provided on one side of the fixing seat 62. The side wall of the notch 62 is slidably connected to the steel wedge 61. The steel wedge 61 with a trapezoidal side wall contacts the bottom surface of the second steel beam 32. The steel wedge 61 is inserted between the fixing seat 62 and the second steel beam 32 through the notch 62 to provide support for the second steel beam 32 and fix the second steel beam 32 at the same time. ;
[0023] A driving mechanism 7 , wherein the driving mechanism 7 connects the first jack 51 , the second jack 57 and the supporting mechanism 6 . The driving mechanism 7 includes an oil tank 71, an oil pump 72, an oil outlet pipe 73, an oil return pipe 74 and an electromagnetic valve 75. The oil tank 71 is placed inside the fixing seat 62, and a plurality of the oil pumps 72 are installed inside the oil tank 71. A plurality of the oil outlet pipes 73 are connected to the oil pump 72, the first jack 51, the second jack 57 and the third jack 66. A plurality of the oil return pipes 74 are connected to the oil tank 71, the first jack 51, the second jack 57 and the third jack 66, and the electromagnetic valve 75 is installed on the side walls of the oil outlet pipe 73 and the oil return pipe 74. The first jack 51, the second jack 57 and the third jack 66 are all composed of a piston 58, an oil cylinder 59 and a lifting rod 510. The oil outlet pipe 73 and the oil return pipe 74 are installed at the bottom end of the oil cylinder 59, and the inner wall of the oil cylinder 59 is provided with a piston 58, an oil cylinder 59 and a lifting rod 510. The piston 58 and the lifting rod 510 are slidably connected, and the lifting rod 510 is fixedly connected to the piston 58. When the jack rises upward, the solenoid valve 75 on the side wall of the oil pump 72 and the oil outlet pipe 73 is opened, so that the oil pump 72 is operated to inject the hydraulic oil inside the oil tank 71 into the oil cylinder 59. The oil outlet pipe 73 has a small diameter, which slows down the speed at which the hydraulic oil enters the oil cylinder 59 and reduces the working intensity of the oil pump 72 when it is operating, so that the hydraulic oil pushes the piston 58 and the lifting rod 510 to move slowly upward; when the jack moves downward, the solenoid valve 75 on the side wall of the return oil pipe 74 is opened. The return oil pipe 74 has a small diameter, so that the hydraulic oil inside the oil cylinder 59 is relieved to enter the oil tank 71 through the return oil pipe 74, so that the piston 58 and the lifting rod 510 move slowly downward.
[0024] A construction method for a passenger and cargo elevator foundation support for a basement top plate, specifically comprising the following steps: Step 1: During construction, first install the support device in the lowest level of the basement, place the base 61 on the surface of the basement floor 1 according to the design position, so that the center of the construction elevator 2 and the center of the composite beam 3 are located on the same straight line, and the support rod 41 is overlapped on the side wall of the basement floor 1; place the first steel beam 31 on the surface of the fixed seat 62, and the surface of the fixed seat 62 has a plurality of rollers 64, and the rollers 64 are in contact with the first steel beam 31. The movement of the first steel beam 31 drives the rollers 64 to rotate on the side wall of the fixed seat 63, and at the same time reduces the resistance of the first steel beam 31 to the movement of the surface of the fixed seat 62, so as to facilitate the change of the position of the first steel beam 31, so that the center of the first steel beam 31 and the center of the construction elevator 2 are located on the same straight line; Step 2: Connect the device to an external power source, pass the plurality of steel pipes 52 through the first steel beam 31, and rotate one of the steel pipes 52 at the same time. The steel pipe 52 drives the screw 53 to rotate into the inside of the other steel pipe 52, and the two steel pipes 52 are spliced; put the second connecting rod 44 between the two reinforcing plates 36, and pass the fixing rod 46 through the slide groove 45 and rotate it into the inside of the second connecting rod 44. Rotate the fixing sleeve 47 on the side wall of the fixing rod 46, and the fixing sleeve 47 is threadedly connected to the fixing rod 46. By rotating the fixing sleeve 47, the reinforcing plate is squeezed. 36, fix the second connecting rod 44 between the two reinforcing plates 36, and rotate the first connecting rod 43, the first connecting rod 43 is rotated out from the inside of the second connecting rod 44 and drives the clamping plate 42 to move, so that the support rod 41 enters the inside of the clamping plate 42, and the clamping plate 42 is fixed to the side wall of the support rod 41 with bolts; open the first jack 51, the first jack 51 drives the extrusion plate 54 to move upward, the extrusion plate 54 moves upward to push the steel pipe 52 and the first steel beam 31 to move upward, so that the first steel beam 31 moves upward a distance greater than the first jack 51. When the first steel beam 31 and the second steel beam 32 move up and down, the first steel beam 31 drives the clamping plate 42 to slide up and down on the side wall of the support rod 41, thereby increasing the stability of the first steel beam 31 when it moves; when the height of the first steel beam 31 is appropriate, the second jack 57 is rotated, and the second jack 57 is opened at the same time, so that the second jack 57 pushes the rubber sleeve 55 to contact the side wall of the first steel beam 31; the solenoid valve 75 on the side wall of the connecting pipe 56 is opened, and under the compression of the weight of the first steel beam 31, the rubber sleeve 55 is gradually compressed and deformed, and the The hydraulic oil inside the first jack 51 is compressed and enters the inside of the second jack 57, the first jack 51 contracts slightly, and the second jack 57 drives the rubber sleeve 55 to rise slightly, thereby increasing the extrusion force between the rubber sleeve 55 and the first steel beam 31, and at the same time reducing part of the pressure on the first jack 51 to share it with the second jack 57, and the first jack 51 and the second jack 57 are connected to each other, so that the pressure of the first steel beam 31 on the first jack 51 and the pressure on the second jack 57 offset each other, thereby increasing the stability of the first steel beam 31 when suspended in the air;Similarly, place the second steel beam 32 on one side of the fixing seat 62, move the second steel beam 32 so that the second steel beam 32 moves to align with the first steel beam 31, close the connecting pipe 56, open the first jack 51 to move the first steel beam 31 upward, remove the second jack 57, move the first steel beam 31 downward to contact the surface of the second steel beam 32, and use bolts to fix the second steel beam 32 to the first steel beam 31. Similarly, install other second steel beams 32 according to the above method; Step 3: As the second steel beam 32 is gradually installed, the resistance to the upward movement of the first jack 51 becomes greater and greater. When it is necessary to push the second steel beam 32 upward, the third jack 66 is opened, and the third jack 66 and the first jack 51 move to push the second steel beam 32 upward, thereby reducing the resistance when the first jack 51 is started; when the last piece of the second steel beam 32 is installed, the first jack 51 and the third jack 66 push the steel beam upward, so that the rubber pad 33 on the surface of the first steel beam 31 squeezes the basement floor 1, and at the same time, the second jack 57 is used to reinforce the side wall of the steel beam, and the steel wedge 67 is used to fix the steel beam on the surface of the fixing seat 62; similarly, the steel beam is installed on the surface of the upper basement floor 1 according to the above method, and when the steel beam is installed, the construction elevator 2 can be installed on the surface of the basement roof; Step 4: After the construction elevator 2 is disassembled, disassemble the steel beams from top to bottom in sequence, open the third jack 66 and the first jack 51, and move the steel beam upward to squeeze the rubber pad 33, so that the second steel beam 32 is separated from the steel wedge 67 to facilitate the removal of the steel wedge 67, and then disassemble the second steel beam 32 and the first steel beam 31 layer by layer from bottom to top.
[0025] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A basement ceiling passenger and cargo elevator foundation support device, characterized in that: include: A basement floor (1), a construction elevator (2) is placed on the surface of the basement floor (1), and a plurality of support mechanisms (6) are placed on the surface of the basement floor (1), and a composite beam (3) for supporting the basement floor (1) and the construction elevator (2) is installed on the surface of the support mechanism (6); The composite beam (3) comprises a first steel beam (31), a second steel beam (32) and a rubber pad (33); the rubber pad (33) for contacting the basement floor (1) is placed on the surface of the first steel beam (31); the first steel beam (31) and the second steel beam (32) and adjacent second steel beams (32) are fixedly connected by bolts; and a reinforcement mechanism (4) for improving the movement stability of the first steel beam (31) and the second steel beam (32) is installed on the surface of the basement floor (1); A lifting mechanism (5), the lifting mechanism (5) comprising a first jack (51), a steel pipe (52), a screw (53), an extrusion plate (54), a rubber sleeve (55), a connecting pipe (56) and a second jack (57); a plurality of the first jacks (51) for driving the first steel beam (31) and the second steel beam (32) to move up and down are installed on the surface of the supporting mechanism (6); the extrusion plate (54) is installed on the surface of the first jack (51); the first steel beam (31) and the second steel beam (32) are ) is installed on the side wall of the steel pipe (52), and one end of some of the steel pipes (52) is installed with the screw rod (53) used for connecting adjacent steel pipes (52); the bottom end of the support mechanism (6) is rotatably connected to the second jack (57) used for supporting the first steel beam (31) and the second steel beam (32), the first jack (51) and the second jack (57) are connected via the connecting pipe (56), and the top end of the second jack (57) is installed with the elastic rubber sleeve (55); A driving mechanism (7), wherein the driving mechanism (7) connects the first jack (51), the second jack (57) and the supporting mechanism (6).
2. The basement ceiling passenger and cargo elevator foundation support device according to claim 1 is characterized in that: The support mechanism (6) comprises a base (61), a fixed base (62), a fixed shaft (63), a roller (64), a top plate (65) and a third jack (66); the base (61) is placed on the surface of the basement floor (1), and the fixed base (62) is mounted on the surface of the base (61); a plurality of fixed shafts (63) are equidistantly mounted inside the fixed base (62), and a plurality of rollers (64) are rotatably connected to the side walls of the fixed shafts (63) for facilitating the movement of the first steel beam (31) and the second steel beam (32); a plurality of the third jacks (66) are mounted on one side of the fixed base (62), and the top plate (65) for pushing the first steel beam (31) and the second steel beam (32) to move upward is mounted on the top of the third jack (66).
3. The basement ceiling passenger and cargo elevator foundation support device according to claim 2 is characterized in that: The support mechanism (6) further comprises a steel wedge (61) and a notch (62); a plurality of the notches (62) are provided on one side of the fixing seat (62); the side walls of the notches (62) are slidably connected to the steel wedges (61); and the steel wedges (61) having trapezoidal side walls abut against the bottom surface of the second steel beam (32).
4. The basement ceiling passenger and cargo elevator foundation support device according to claim 3 is characterized in that: The first steel beam (31) and the second steel beam (32) are both composed of a support plate (34), an I-beam (35) and a reinforcement plate (36); the support plates (34) are welded to both ends of the I-beam (35), and a plurality of reinforcement plates (36) with trapezoidal side walls are welded to the connection between the support plate (34) and the I-beam (35).
5. The basement ceiling passenger and cargo elevator foundation support device according to claim 4 is characterized in that: The side wall of the I-beam (35) is slidably connected to the steel pipe (52), and the rubber sleeve (55) is engaged at the connection between the I-beam (35) and the support plate (34).
6. The basement ceiling passenger and cargo elevator foundation support device according to claim 4, characterized in that: The reinforcement mechanism (4) comprises a support rod (41), a clamping plate (42), a first connecting rod (43), a second connecting rod (44), a sliding groove (45), a fixing rod (46) and a fixing sleeve (47). A plurality of the support rods (41) are installed between adjacent basement floors (1). The support rods (41) are slidably connected to the elastic clamping plates (42), and the clamping plates (42) are fixed to the side walls of the support rods (41) by bolts. The side walls of the reinforcement plates (36) are provided with the sliding groove (45), the fixing rod (46) is fixed inside the sliding groove (45) by the fixing sleeve (47), the fixing rod (46) is threadedly connected to the second connecting rod (44), the second connecting rod (44) is threadedly connected to the first connecting rod (43), and the first connecting rod (43) is rotatably connected to the clamping plates (42).
7. The basement ceiling passenger and cargo elevator foundation support device according to claim 2 is characterized in that: The driving mechanism (7) comprises an oil tank (71), an oil pump (72), an oil outlet pipe (73), an oil return pipe (74) and an electromagnetic valve (75); the oil tank (71) is placed inside the fixing seat (62), and a plurality of oil pumps (72) are installed inside the oil tank (71); a plurality of oil outlet pipes (73) are connected to the oil pump (72), the first jack (51), the second jack (57) and the third jack (66); a plurality of oil return pipes (74) are connected to the oil tank (71), the first jack (51), the second jack (57) and the third jack (66); and the electromagnetic valve (75) is installed on the side walls of the oil outlet pipe (73) and the oil return pipe (74).
8. The basement ceiling passenger and cargo elevator foundation support device according to claim 7, characterized in that: The first jack (51), the second jack (57) and the third jack (66) are all composed of a piston (58), an oil cylinder (59) and a lifting rod (510); the oil outlet pipe (73) and the oil return pipe (74) are installed at the bottom end of the oil cylinder (59); the piston (58) and the lifting rod (510) are slidably connected inside the oil cylinder (59); and the lifting rod (510) and the piston (58) are fixedly connected.
9. The basement ceiling passenger and cargo elevator foundation support device according to any one of claims 1 to 8, characterized in that: A construction method for a passenger and cargo elevator foundation support for a basement top plate is provided, which specifically comprises the following steps: Step 1: During construction, first install the support device in the lowest layer of the basement, place the base (61) on the surface of the basement floor (1) according to the designed position, so that the center of the construction elevator (2) and the center of the composite beam (3) are located on the same straight line; place the first steel beam (31) on the surface of the fixing seat (62), and a plurality of rollers (64) are provided on the surface of the fixing seat (62). The rollers (64) are in contact with the first steel beam (31), and the movement of the first steel beam (31) drives the rollers (64) to rotate on the side wall of the fixing seat (63), while reducing the resistance of the first steel beam (31) to the movement on the surface of the fixing seat (62), so as to facilitate changing the position of the first steel beam (31) so that the center of the first steel beam (31) and the center of the construction elevator (2) are located on the same straight line; Step 2: inserting a plurality of the steel pipes (52) through the first steel beam (31), and rotating one of the steel pipes (52) at the same time, so that the steel pipe (52) drives the screw rod (53) to rotate and enter the interior of the other steel pipe (52), and the two steel pipes (52) are spliced; opening the first jack (51), so that the first jack (51) drives the extrusion plate (54) to move upward, and the extrusion plate (54) moves upward to push the steel pipe (52) and the first steel beam (31) to move upward, so that the first steel beam (31) moves upward a distance greater than the distance of the first steel beam (31) moving upward. the height of the second steel beam (32); when the height of the first steel beam (31) is appropriate, the second jack (57) is rotated and the second jack (57) is opened at the same time, so that the second jack (57) pushes the rubber sleeve (55) to contact the side wall of the first steel beam (31); the connecting pipe (56) is opened, and under the compression of the weight of the first steel beam (31), the rubber sleeve (55) is gradually compressed and deformed, and the hydraulic oil inside the first jack (51) is compressed and enters the inside of the second jack (57), and the first jack (51) is slightly contracted. The second jack (57) drives the rubber sleeve (55) to rise slightly, thereby increasing the squeezing force between the rubber sleeve (55) and the first steel beam (31), and at the same time reducing part of the pressure on the first jack (51) to share it with the second jack (57), and the first jack (51) and the second jack (57) are connected to each other, so that the pressure of the first steel beam (31) on the first jack (51) and the pressure on the second jack (57) offset each other, thereby increasing the stability of the first steel beam (31) when suspended in the air; similarly, the second steel beam (31) is lowered (32) is placed on one side of the fixing seat (62), the second steel beam (32) is moved so that the second steel beam (32) moves to align with the first steel beam (31), the connecting pipe (56) is closed, the first jack (51) is opened to move the first steel beam (31) upward, the second jack (57) is removed, and the first steel beam (31) is moved downward to contact the surface of the second steel beam (32), and the second steel beam (32) and the first steel beam (31) are fixed by bolts, and the other second steel beams (32) are installed in the same manner according to the above method; Step 3: As the second steel beam (32) is gradually installed, the resistance to the upward movement of the first jack (51) becomes greater and greater. When it is necessary to push the second steel beam (32) upward, the third jack (66) is opened, and the third jack (66) and the first jack (51) move to push the second steel beam (32) upward, thereby reducing the resistance when the first jack (51) is started. When the last piece of the second steel beam (32) is installed, the first jack (51) and the third jack (66) push the steel beam upward, so that the rubber pad (33) on the surface of the first steel beam (31) presses the basement floor (1), and at the same time, the second jack (57) is used to reinforce the side wall of the steel beam, and the steel wedge (67) is used to fix the steel beam on the surface of the fixing seat (62). Similarly, according to the above method, the steel beam is installed on the surface of the upper basement floor (1). When the steel beam is installed, the construction elevator (2) can be installed on the surface of the basement top plate. Step 4: After the construction elevator (2) is disassembled, the steel beams are disassembled from top to bottom in sequence, and the third jack (66) and the first jack (51) are opened to move the steel beams upward to squeeze the rubber pad (33), so that the second steel beam (32) is separated from the steel wedge (67) to facilitate the removal of the steel wedge (67), and then the second steel beam (32) and the first steel beam (31) are disassembled layer by layer from bottom to top.