Construction method of device for solving installation problem of oil pipe in pile through self-balancing method

By designing the device of connecting rod slider mechanism and pulley structure, the problem of difficulty in installing oil pipes in the self-balancing pile is solved, and the stable drag and binding of oil pipes during the release of steel cages is realized, reducing manual operations and improving project progress and adaptability.

CN118880948APending Publication Date: 2024-11-01TIANJIN PORT ENG INST LTD OF CCCC FIRST HARBOR ENG +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410811783.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-21
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

In pile foundation projects, the oil pipes derived from the self-balancing load box cannot be connected to the main bar of the steel cage in advance, resulting in installation difficulties and a large amount of manpower, affecting the progress of the project.

Method used

A device including a connecting rod slide mechanism, a pulley structure and a rotating box is designed to wrap the oil pipe through the pulley structure, and the ratchet structure is adjusted to fit the main rib of the steel cage with the connecting rod slide mechanism to ensure that the oil pipe is stable during the process of lowering the steel cage. Drag and tie to reduce manual intervention.

Benefits of technology

The device simplifies the oil pipe installation process through double guarantee (crane hook and operator lifting) to prevent the device from moving downward, reducing manual operation, improving installation efficiency and adaptability, and is suitable for steel cages of different diameters and locations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880948A_ABST
    Figure CN118880948A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method of a device for solving the problem of installation of an oil pipe in a pile through a self-balancing method, and the device for solving the problem of installation of the oil pipe in the pile through the self-balancing method comprises a connecting rod sliding block mechanism, a pulley structure, a rotating box and a ratchet wheel structure; the rotating box comprises an upper rotating disc box and a lower rotating disc box, the upper rotating disc box is rotationally installed on the lower rotating disc box through a rotating shaft, a pulley structure used for winding an oil pipe led out of the load box in advance is fixedly installed on the top face of the rotating box, and a plurality of connecting rod sliding block mechanisms are installed on the bottom face of the rotating box. The other end of each connecting rod sliding block mechanism is provided with a ratchet wheel structure. The whole process is time-saving and labor-saving, oil pipes do not need to be inserted manually, the device is high in adaptability, and the device can be adjusted according to different diameters of reinforcement cages, the number and the position of the oil pipes and the position of main reinforcements.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of pile foundation bearing capacity detection, and in particular relates to a construction method of a device for solving the problem of oil pipe installation in a self-balancing pile. Background Art

[0002] The self-balancing method is a method for testing the vertical bearing capacity of pile foundations. The main principle is that before the test, the load box needs to be placed at the balance point of the pile body. Two upper displacement rods, two lower displacement rods and oil pipes are arranged on the load box. During the test, the load box is pressurized through the oil pipe, the upper displacement rod of the upper pile is displaced upward, and the lower displacement rod of the lower pile is displaced downward. The final test result QS curve can be converted into the QS curve of the traditional static load.

[0003] In current pile foundation projects, the steel cage is relatively long. Due to the limitations of transportation and hoisting equipment, the steel cage is divided into two or three sections, which are spliced ​​and installed during the lowering of the steel cage. At this time, the oil pipes drawn from the self-balancing load box cannot be connected to the main reinforcement of the steel cage in advance. It is also troublesome to install the oil pipes when the cage is lowered. The more oil pipes there are, the more people are needed to install them. The steel cage needs to be threaded with oil pipes about 2 meters below the ground, and if the personnel are negligent, the oil pipes will fall into the mud in the pile, which will greatly affect the progress of the project.

[0004] Since the installation of oil pipelines by completely manual methods not only requires a large number of people but also is extremely slow, it is crucial to solve this problem. Summary of the invention

[0005] The present invention is mainly to overcome the deficiencies of the prior art and to provide a construction method for a device that solves the problem of installing an oil pipe in a self-balancing pile.

[0006] The present invention is achieved through the following technical solutions:

[0007] A construction method of a device for solving the problem of installing an oil pipe in a self-balancing pile, the device for solving the problem of installing an oil pipe in a self-balancing pile comprising: a connecting rod slider mechanism, a pulley structure, a rotating box and a ratchet structure;

[0008] The rotating box comprises an upper rotating disk box and a lower rotating disk box, wherein the upper rotating disk box is rotatably mounted on the lower rotating disk box via a rotating shaft, a pulley structure for pre-winding the oil pipe led out from the load box is fixedly mounted on the top surface of the rotating box, and a plurality of connecting rod slider mechanisms are mounted on the bottom surface of the rotating box, and a ratchet structure is mounted on the other end of each of the connecting rod slider mechanisms;

[0009] The construction method of the device for solving the problem of installing the oil pipe in the self-balancing pile comprises the following steps:

[0010] Step 1: Install a load box on the first section of the steel cage (the upper and lower ends of the load box are respectively connected to the steel cage to form the first section of the steel cage to be lowered);

[0011] Step 2: Determine the number of pulley structures according to the number of oil pipes led out of the load box, and install the pulley structures on the top surface of the turntable box; determine the number of connecting rod slider mechanisms according to the number of main reinforcements of the steel cage, and install the connecting rod slider mechanisms on the bottom surface of the turntable box, and connect the ratchet structure to the outer end of the connecting rod slider mechanism;

[0012] Step 3: adjust the position of the connecting rod slider mechanism so that the ratchet structure connected to it is close to the main reinforcement of the first section of the steel cage; adjust the upper turntable box of the turntable box so that the pulley structure installed on it corresponds to the position of the oil pipe, and wrap the oil pipe led out of the load box around the pulley;

[0013] Step 4: Use a crane to vertically lower the first section of the steel cage. During the process of lowering the steel cage, the height of the device for solving the problem of installing the oil pipe in the self-balancing pile is kept unchanged, always 1 to 2 meters above the hole. During the process of lowering the steel cage, the oil pipe will be gradually dragged out from the pulley, and the operator will gradually tie the oil pipe from bottom to top along the steel cage.

[0014] Step 5: When the first section of the steel cage is lowered to a position higher than 2m at its top, the next section of the steel cage is spliced ​​on its top. During the splicing process, the device for solving the problem of installing the oil pipe in the self-balancing pile can be temporarily lowered inside the top of the first section of the steel cage. After the splicing is completed, the device is pulled up to a suitable height and remains unchanged;

[0015] Step six, continue to lower the steel cage and splice the next section of steel cage according to the operations of steps four and five, until the load box is lowered into place. During the lowering of the steel cage, keep the height of the device for solving the oil pipe installation problem in the self-balancing pile unchanged, always 1 to 2 meters above the hole.

[0016] In the above technical solution, the rotating box is a disc-shaped structure, including a rotating bolt, an upper turntable box, a handle and a lower turntable box, and the upper turntable box is connected to the lower turntable box by a rotating bolt.

[0017] In the above technical solution, four handles are arranged in an annular array on the annular side wall of the rotating box, and a hook is arranged on the top surface of the rotating box.

[0018] In the above technical solution, the pulley structure includes a pulley base, a fixing bolt, a pulley, a pulley rotating shaft and a pulley protective shell; the pulley base includes two right-angle connecting pieces, each of which has two bolt holes on the bottom surface and a rotating shaft hole on the vertical surface, the two right-angle connecting pieces are symmetrically arranged, and the right-angle connecting pieces are fixedly installed on the top surface of the rotating box by inserting fixing bolts through the bolt holes on the bottom surfaces thereof to form a pulley base, the pulley rotating shaft is fixedly installed in the rotating shaft holes of the two right-angle connecting pieces symmetrically arranged front and back, the pulley is rotatably installed on the pulley rotating shaft, and the pulley protective shell is installed on the pulley.

[0019] In the above technical solution, the connecting rod slider mechanism includes a long connecting rod base, a long connecting rod, a short connecting rod base, a short connecting rod, two connecting rod base rotating shafts, a slider, a slider fixing bolt, and a slider rotating shaft; the long connecting rod base is fixedly installed on the bottom surface away from the center of the rotating box, one end of the long connecting rod is rotatably installed on the long connecting rod base through the connecting rod base rotating shaft, and the other end is connected to the ratchet structure.

[0020] In the above technical solution, the slider is installed on the long connecting rod through a slider fixing bolt, and a slider rotating shaft for rotatably installing the short connecting rod is provided on it; the short connecting rod base is fixedly installed on the bottom surface close to the center of the rotating box, one end of the short connecting rod is rotatably installed on the short connecting rod base through the connecting rod base rotating shaft, and the other end is rotatably installed on the slider rotating shaft.

[0021] In the above technical solution, the ratchet structure includes a pawl rotating shaft, a pawl, a sliding wheel rotating shaft, a sliding wheel, a ratchet and a T-shaped connecting rod; the T-shaped connecting rod is connected to the other end of the long connecting rod of the connecting rod slider mechanism.

[0022] In the above technical solution, the T-shaped connecting rod is provided with a sliding wheel rotating shaft mounting hole, the sliding wheel rotating shaft is installed in the sliding wheel rotating shaft mounting hole, the sliding wheel is rotatably installed on the sliding wheel rotating shaft, and the outer edge of the sliding wheel is provided with a concave structure that is convenient for fitting the main reinforcement.

[0023] In the above technical solution, the ratchet is fixedly mounted on both ends of the sliding wheel; a pawl rotating shaft is provided on the T-shaped connecting rod, the upper end of the pawl is mounted on the T-shaped connecting rod through the pawl rotating shaft, and the lower end of the pawl abuts against the outer edge of the ratchet.

[0024] The beneficial effects of the present invention are:

[0025] (1) The present invention ensures that the device is difficult to move downward by providing a ratchet structure. At the same time, the device is difficult to move downward by using a crane arm to hang the hook of the device or the operator to lift the handle of the device, thereby further ensuring that the device is difficult to move downward, providing double protection.

[0026] (2) The present invention can flexibly adjust the position of the ratchet structure by providing a connecting rod slider mechanism, thereby enabling the ratchet structure to be closely attached to the steel cage, making it easier to tie the oil pipe.

[0027] (3) The whole process of the present invention saves time and effort, does not require manual insertion of oil pipes, and the device has strong adaptability. The device can be adjusted according to different diameters of the steel cage, the number and position of the oil pipes, and the position of the main bars. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a front view of the present invention.

[0029] Figure 2 It is a top view of the present invention.

[0030] Figure 3 It is a front view of the connecting rod slider mechanism of the present invention.

[0031] Figure 4 It is a rear view of the connecting rod slider mechanism of the present invention.

[0032] Figure 5 It is a front view of the pulley structure of the present invention.

[0033] Figure 6 It is a side view of the pulley structure of the present invention.

[0034] Figure 7 It is a front view of the rotating box of the present invention.

[0035] Figure 8 It is a top view of the rotating box of the present invention.

[0036] Fig. 9 It is a front view of the ratchet structure of the present invention.

[0037] Fig.10 It is a side view of the ratchet structure of the present invention.

[0038] In the figure:

[0039] 1. Main reinforcement of steel cage 2. Oil pipe 3. Connecting rod slider mechanism

[0040] 4. Steel cage stirrups 5. Hook 6. Pulley structure

[0041] 7. Rotating box 8. Ratchet structure 9. Long connecting rod base

[0042] 10. Long connecting rod 11. Slider fixing bolt 12. Slider

[0043] 13. Short connecting rod base 14. Connecting rod base rotating shaft 15. Short connecting rod

[0044] 16. Slider rotating shaft 17. Pulley protective shell 18. Pulley

[0045] 19. Pulley base 20. Pulley rotating shaft 21. Fixing bolt

[0046] 22. Turn the bolt 23. Upper turntable box 24. Handle

[0047] 25. Lower turntable box 26. Ratchet rotating shaft 27. Ratchet

[0048] 28. Ratchet 29. Sliding wheel rotating shaft 30. Sliding wheel

[0049] 31. T-type connecting rod

[0050] For ordinary technicians in this field, other relevant drawings can be obtained based on the above drawings without any creative work. DETAILED DESCRIPTION

[0051] In order to enable those skilled in the art to better understand the technical solution of the present invention, the technical solution of the present invention is further described below in conjunction with specific embodiments.

[0052] Embodiment 1

[0053] A device for solving the problem of installing oil pipes in self-balancing piles, see attached Figure 1-10 , including: a connecting rod slider mechanism 3, a pulley structure 6, a rotating box 7 and a ratchet structure 8.

[0054] The rotating box 7 includes an upper turntable box 23 and a lower turntable box 25. The upper turntable box 23 is rotatably mounted on the lower turntable box 25 via a rotating shaft. A pulley structure 6 for pre-winding the oil pipe 2 led out from the load box (not shown in the figure) is fixedly mounted on the top surface of the rotating box 7. A plurality of connecting rod slider mechanisms 3 are installed on the bottom surface of the rotating box 7. A ratchet structure 8 is installed at the other end of each of the connecting rod slider mechanisms 3. The ratchet structure 8 is used to fit with the main reinforcement 1 of the steel cage. The steel cage is formed by connecting a plurality of main reinforcement 1 of the steel cage through steel cage hoops 4. A load box is arranged on the steel cage, and a plurality of oil pipes 2 are led out of the load box.

[0055] See attached Figure 7-8 The rotating box 7 is a disc-shaped structure, including a rotating bolt 22, an upper turntable box 23, a handle 24 and a lower turntable box 25. The upper turntable box 23 is connected to the lower turntable box 25 by the rotating bolt 22. The upper turntable box 23 can rotate relatively around the lower turntable box 25. There are four handles 24 in an annular array on the annular side wall of the rotating box 7.

[0056] See attached Figure 5-6The pulley structure 6 includes a pulley base 19, a fixing bolt 21, a pulley 18, a pulley rotating shaft 20 and a pulley protective shell 17; the pulley base 19 includes two right-angle connecting pieces 13, each of which is provided with two bolt holes (not shown in the figure) on the bottom surface of the right-angle connecting piece 13, and a rotating shaft hole (not shown in the figure) is provided on the vertical surface, the two right-angle connecting pieces 13 are symmetrically arranged, and the right-angle connecting pieces 13 are fixedly installed on the top surface of the rotating box 7 by inserting fixing bolts 21 through the bolt holes (not shown in the figure) on the bottom surfaces thereof to form a pulley base 19, the pulley rotating shaft 20 is fixedly installed in the rotating shaft holes (not shown in the figure) of the two right-angle connecting pieces 13 symmetrically arranged front and back, the pulley 18 is rotatably installed on the pulley rotating shaft 20, and the pulley protective shell 17 is installed on the pulley 18.

[0057] See attached Figure 3-4 The connecting rod slider mechanism 3 includes a long connecting rod base 9, a long connecting rod 10, a short connecting rod base 13, a short connecting rod 15, two connecting rod base rotating shafts 14, a slider 12, a slider fixing bolt 11, and a slider rotating shaft 16; the long connecting rod base 9 is fixedly installed on the bottom surface away from the center of the rotating box 7, one end of the long connecting rod 10 is rotatably installed on the long connecting rod base 9 through the connecting rod base rotating shaft 14, and the other end is connected to the ratchet structure 8; the slider 12 is installed on the long connecting rod 10 through the slider fixing bolt 11, and a slider rotating shaft 16 for rotatably installing the short connecting rod 15 is provided thereon; the short connecting rod base 13 is fixedly installed on the bottom surface close to the center of the rotating box 7, and one end of the short connecting rod 15 is rotated through the connecting rod base rotating shaft 14 is rotatably mounted on the short connecting rod base 13, and the other end is rotatably mounted on the slider rotating shaft 16; when it is necessary to adjust the rotation angle of the long connecting rod 10 around the connecting rod base rotating shaft 14, loosen the slider fixing bolt 11 on the slider 12, and the short connecting rod 15 can rotate toward the center direction of the steel cage or away from the center direction of the steel cage. At this time, the slider 12 connected to the short connecting rod 15 can move toward the center direction of the steel cage or away from the center direction of the steel cage, thereby driving the long connecting rod 10 to rotate toward the center direction of the steel cage or away from the center direction of the steel cage. When the angle of the long connecting rod 10 is adjusted to a suitable angle, tighten the slider fixing bolt 11 again, so that the connecting rod slider mechanism 3 can be fixed at the required rotation angle.

[0058] See attached Figure 9-10The ratchet structure 8 includes a ratchet pawl rotating shaft 26, a ratchet pawl 28, a sliding wheel rotating shaft 29, a sliding wheel 30, a ratchet tooth 27 and a T-shaped connecting rod 31; the T-shaped connecting rod 31 is connected to the other end of the long connecting rod 10 of the connecting rod slider mechanism 3; the T-shaped connecting rod 31 is provided with a sliding wheel rotating shaft mounting hole (not shown in the figure), the sliding wheel rotating shaft 29 is installed in the sliding wheel rotating shaft mounting hole (not shown in the figure), the sliding wheel 30 is rotatably installed on the sliding wheel rotating shaft 29, and the outer edge of the sliding wheel 30 is provided with a The concave structure of the main reinforcement 1 is formed, and the ratchet 27 is fixedly installed at both ends of the sliding wheel 30; a pawl rotating shaft 26 is provided on the T-shaped connecting rod 31, and the upper end of the pawl 28 is installed on the T-shaped connecting rod 31 through the pawl rotating shaft 26, and the lower end of the pawl 28 abuts against the outer edge of the ratchet 27; when the steel cage is lowered, the sliding wheel 30 drives the ratchet 27 to rotate clockwise, and when the steel cage moves to the desired position, the pawl 28 is stuck on the ratchet 27, limiting the ratchet 27 from rotating in the opposite direction, and the ratchet structure 8 cannot move downward under the action of gravity.

[0059] The rotating box 7 is fixedly connected with a hook 5 which is convenient for hoisting a device for solving the problem of installing the oil pipe in the self-balancing pile.

[0060] Embodiment 2

[0061] This embodiment provides a construction method for a device for solving the problem of installing an oil pipe in a self-balancing pile, comprising the following steps:

[0062] Step 1: Install a load box on the first section of the steel cage (the upper and lower ends of the load box are respectively connected to the steel cage to form the first section of the steel cage to be lowered);

[0063] Step 2: Determine the number of pulley structures 6 according to the number of oil pipes led out of the load box, and install the pulley structure 6 on the top surface of the turntable box 7; determine the number of connecting rod slider mechanisms 3 according to the number of main reinforcement bars 1 of the steel cage, and install the connecting rod slider mechanisms 3 on the bottom surface of the turntable box 7, and connect the ratchet structure 8 to the outer end of the connecting rod slider mechanism 3;

[0064] Step 3: adjust the position of the connecting rod slider mechanism 3 so that the ratchet structure 8 connected thereto is close to the main reinforcement of the first section of the reinforcement cage; adjust the upper turntable box 23 of the turntable box 7 so that the pulley structure 3 installed thereon corresponds to the position of the oil pipe, and wind the oil pipe 2 led out of the load box around the pulley 18;

[0065] Step 4: Use a crane to vertically lower the first section of the steel cage. During the process of lowering the steel cage, the height of the device for solving the problem of installing the oil pipe in the self-balancing pile is kept unchanged, always 1 to 2 meters above the hole. During the process of lowering the steel cage, the oil pipe 2 will be gradually dragged out from the pulley 18, and at the same time, the operator will gradually tie the oil pipe 2 along the steel cage from bottom to top (that is, tie the oil pipe 2 to the steel cage);

[0066] Step 5: When the first section of the steel cage is lowered to a position higher than 2m at its top, the next section of the steel cage is spliced ​​on its top. During the splicing process, the device for solving the problem of installing the oil pipe in the self-balancing pile can be temporarily lowered inside the top of the first section of the steel cage. After the splicing is completed, the device is pulled up to a suitable height and remains unchanged;

[0067] Step six, continue to lower the steel cage and splice the next section of steel cage according to the operations of steps four and five, until the load box is lowered into place. During the lowering of the steel cage, keep the height of the device for solving the oil pipe installation problem in the self-balancing pile unchanged, always 1 to 2 meters above the hole.

[0068] For ease of explanation, spatial relative terms such as "upper", "lower", "left", "right" and the like are used in the embodiments to illustrate the relationship of one element or feature shown in the figure relative to another element or feature. It should be understood that, in addition to the orientation shown in the figure, the spatial terms are intended to include different orientations of the device in use or operation. For example, if the device in the figure is inverted, the element described as being "under" other elements or features will be positioned "on" other elements or features. Therefore, the exemplary term "under" can include both upper and lower orientations. The device can be positioned in other ways (rotated 90 degrees or in other orientations), and the spatial relative descriptions used here can be interpreted accordingly.

[0069] Furthermore, relational terms such as “first” and “second” and the like are merely used to distinguish one component from another having the same name, but do not necessarily require or imply any such actual relationship or order between these components.

[0070] The present invention is described above by way of example. It should be noted that, without departing from the core of the present invention, any simple deformation, modification or other equivalent replacement that can be made by those skilled in the art without inventive effort falls within the protection scope of the present invention.

Claims

1. A construction method for a device for solving the problem of installing an oil pipe in a self-balancing pile, wherein the device for solving the problem of installing an oil pipe in a self-balancing pile is characterized by: include: Connecting rod and slider mechanism, pulley structure, rotating box and ratchet structure; The rotating box comprises an upper rotating disk box and a lower rotating disk box, wherein the upper rotating disk box is rotatably mounted on the lower rotating disk box via a rotating shaft, a pulley structure for pre-winding the oil pipe led out from the load box is fixedly mounted on the top surface of the rotating box, and a plurality of connecting rod slider mechanisms are mounted on the bottom surface of the rotating box, and a ratchet structure is mounted on the other end of each of the connecting rod slider mechanisms; The construction method of the device for solving the problem of installing the oil pipe in the self-balancing pile comprises the following steps: Step 1: Install the load box on the first section of the steel cage; Step 2: Determine the number of pulley structures according to the number of oil pipes led out of the load box, and install the pulley structures on the top surface of the turntable box; determine the number of connecting rod slider mechanisms according to the number of main reinforcements of the steel cage, and install the connecting rod slider mechanisms on the bottom surface of the turntable box, and connect the ratchet structure to the outer end of the connecting rod slider mechanism; Step 3: adjust the position of the connecting rod slider mechanism so that the ratchet structure connected to it is close to the main reinforcement of the first section of the steel cage; adjust the upper turntable box of the turntable box so that the pulley structure installed on it corresponds to the position of the oil pipe, and wrap the oil pipe led out of the load box around the pulley; Step 4: Use a crane to vertically lower the first section of the steel cage. During the process of lowering the steel cage, the height of the device for solving the problem of installing the oil pipe in the self-balancing pile is kept unchanged, always 1 to 2 meters above the hole. During the process of lowering the steel cage, the oil pipe will be gradually dragged out from the pulley, and the operator will gradually tie the oil pipe from bottom to top along the steel cage. Step 5: When the first section of the steel cage is lowered to a position higher than 2m at its top, the next section of the steel cage is spliced ​​on its top. During the splicing process, the device for solving the problem of installing the oil pipe in the self-balancing pile can be temporarily lowered inside the top of the first section of the steel cage. After the splicing is completed, the device is pulled up to a suitable height and remains unchanged; Step six, continue to lower the steel cage and splice the next section of steel cage according to the operations of steps four and five, until the load box is lowered into place. During the lowering of the steel cage, keep the height of the device for solving the oil pipe installation problem in the self-balancing pile unchanged, always 1 to 2 meters above the hole.

2. The construction method of a device for solving the problem of installing oil pipes in self-balancing piles according to claim 1 is characterized by: The rotating box is a disc-shaped structure, comprising a rotating bolt, an upper rotating disk box, a handle and a lower rotating disk box, and the upper rotating disk box is connected to the lower rotating disk box through the rotating bolt.

3. The construction method of a device for solving the problem of installing oil pipes in self-balancing piles according to claim 2 is characterized by: Four handles are arranged in an annular array on the annular side wall of the rotating box, and a hook is arranged on the top surface of the rotating box.

4. The construction method of a device for solving the problem of installing oil pipes in self-balancing piles according to claim 1 is characterized by: The pulley system includes a pulley base, a fixing bolt, a pulley, a pulley rotating shaft and a pulley protective shell; the pulley base includes two right-angle connecting pieces, each of which has two bolt holes on the bottom surface and a rotating shaft hole on the vertical surface, the two right-angle connecting pieces are symmetrically arranged, and the right-angle connecting pieces are fixedly installed on the top surface of the rotating box by inserting fixing bolts through the bolt holes on the bottom surfaces thereof to form a pulley base, the pulley rotating shaft is fixedly installed in the rotating shaft holes of the two right-angle connecting pieces symmetrically arranged front and back, the pulley is rotatably installed on the pulley rotating shaft, and the pulley protective shell is installed on the pulley.

5. The construction method of the device for solving the problem of installing the oil pipe in the self-balancing pile according to claim 1 is characterized by: The connecting rod slider system includes a long connecting rod base, a long connecting rod, a short connecting rod base, a short connecting rod, two connecting rod base rotating shafts, a slider, a slider fixing bolt, and a slider rotating shaft; the long connecting rod base is fixedly installed on the bottom surface away from the center of the rotating box, one end of the long connecting rod is rotatably installed on the long connecting rod base through the connecting rod base rotating shaft, and the other end is connected to the ratchet system.

6. The construction method of the device for solving the problem of installing the oil pipe in the self-balancing pile according to claim 5 is characterized by: The slider is installed on the long connecting rod through a slider fixing bolt, and a slider rotating shaft for rotatably installing the short connecting rod is provided on it; the short connecting rod base is fixedly installed on the bottom surface close to the center of the rotating box, one end of the short connecting rod is rotatably installed on the short connecting rod base through the connecting rod base rotating shaft, and the other end is rotatably installed on the slider rotating shaft.

7. The construction method of a device for solving the problem of installing oil pipes in self-balancing piles according to claim 1, characterized in that: The ratchet system comprises a pawl rotating shaft, a pawl, a sliding wheel rotating shaft, a sliding wheel, a ratchet and a T-shaped connecting rod; the T-shaped connecting rod is connected to the other end of the long connecting rod of the connecting rod slider system.

8. The construction method of the device for solving the problem of installing the oil pipe in the self-balancing pile according to claim 7 is characterized by: The T-shaped connecting rod is provided with a sliding wheel rotating shaft mounting hole, the sliding wheel rotating shaft is installed in the sliding wheel rotating shaft mounting hole, the sliding wheel is rotatably mounted on the sliding wheel rotating shaft, and the outer edge of the sliding wheel is provided with a concave structure that is convenient for fitting the main reinforcement.

9. The construction method of the device for solving the problem of installing the oil pipe in the self-balancing pile according to claim 7 is characterized by: The ratchet is fixedly mounted on both ends of the sliding wheel; a ratchet rotating shaft is arranged on the T-shaped connecting rod, the upper end of the ratchet is mounted on the T-shaped connecting rod through the ratchet rotating shaft, and the lower end of the ratchet abuts against the outer edge of the ratchet.